Extracted text (via pymupdf_layout)
743 characters
ROW –Wireless & Small Cell License Application Workflow Master License Agreement Approved & Signed by BOS Initial site location Initial desired site reviewed internally by Site Visit with Meets All Design location submitted via Utilities & Traffic Carrier & the Criteria, safety & No e-mail to the County Engineering for County Utility Clearances DOT Utility Branch preliminary approval Staff works with applicant/carrier To meet all criteria Final Drawing submittal for Public notice sent Permit/Plans Approval out by Yes carrier/applicant Applicant Annual Payments made to meets all criteria MCDOT finance for each approved location No Detailed Location (sub) Agreement then prepared by Communication Company for signature by MCDOT Director.