CHANGE ORDER
PROJECT; East Court Building 6th Floor Courtroon CHANGE ORDER NO.: 001
Build-Out
INITIATION DATE: February 19,2014
Project (Owner's) 3303-14-1101f
ForeSite Design & Construction, Inc. CONTRACT NO 13132-CMR Ph I
1425 N. Monde' Drive
Gilbert, Arizona 85233 CONTRACT DATE: December 11, 2013
Ph 1- CORM I Ibis Change Order hereby changes the Contract, by deleting any text referring to "6th Floor" and replacing such text with '7th
Floor". This shall apply to any and all articles, references and other places throughout the Agreement. This Change moves the
Project Work Area to the floor above the 6th floor for the purpose of avoiding conflicts with other necessary, but unforeseen
abatement Work being perfurmcd on the 6th Floor by others. ilic conflicting Work by others is the result of unforeseen, concealed
conditions that were unknown nt the time this Contract 1113132 was executed. All of the Work Products already produced shall be
as valid on the 7th Floor as they \Nem an the 6th by virtue of' the floors being identical as to urea, scope of work, and the design
drawings and specifications prepared by the Architect identified in Article I .1 of the Contract, the refinence to "6th Floor
notwithstanding.
TOTAL TIIIS CHANGE ORDER $0.00
This Change Order shall constitute a final settlement of all matters relating to the change in the Work which is the subject of the Change Order,
including but not limited to all direct or indirect costs associated with such change, ally impact such change may have on unchanged Work, and any and
all adjustments to the Contract Sum or the Contract Time. This Change Order supersedes all prior reservations stated or
Not Valid Until Signed By Maricopa County, Architect and Contractor,
The original Contract Sum was $32357.00
Net Change by previously authorized Change Orders S0.00
The Contract Sum prior to this Change Order was $32,357.00
The Contract Sum will be (increased-) (decreased) (unchanged) by this Change Order s0.00
The new Contract Sum including this Change Order is $32,357.00
The Contract lime will be finefeased) (-dreareased) (unchanged) by 0 Days
The dale of Substantial Completion as oldie dale of this Change Order therefore June 30,2014
Bale Architect j Ilatc
C°:1 FORE, "1H ITE lw D 'ION & CONSTRUCIION, INC. DICK & FaITSCI DESIGN GROUP
24-14
Capital ProjecAs Sy Project Nlitunger Dale ) Direct& Date
MARICOPA hIUNTY MARICOPA COUNTY
Chief Procurement Officer Date CLERK 01: Tut BoAnn OF SUPERVISORS Da;
MARICOPA COlINTY MARICOPA COUNTY
CIIAIRMAN Dale
MARICOPA COUNTY BOAR I) OF SUPERVISORS

Facilities Management Department
Project Information
Project Manager: Edward Wimmer Date: September 17, 2013
Building Supervisor Tim Rosenow Location: 6' Floor
Building No. 3303 Building Name: East Court
Project No. 3303-14-1108 Maximo No. 1 14219170 FM141108
Procurement EJ Article 5 ZA/E Firm - • Consultant
Budget $6,568,802.00 Method: El JOC - El CMR - 0 DBB
Article 3 • Simplified. Const - El Vendor
Fund Agency Low Org Activity F Class F Code Obj Sub Obj R Cal
Funding String 445 47B 4713 FACM ECIM 0915 3303
User Funds: LI YES 1 NO
User Group Superior Courts
Contact Person Hugh Gallagher Phone Number 602-506-3912
A/E Firm Dick & Fritsche Design Group
Contact Person John Dick, AIA (Principal) Phone Number 602-954-9060
Contractor To Be Determined
Contact Person Phone Number
Building Permit YES • NO - Why:
Project Scheduled Start Date 9/15/13 Estimated Completion Date 9/8114
Project Name: 6th Floor New Four (4) Courtrooms
Project Scope Of Work: Build-out the approximately 18,680 SF of the 6 th Floor for four (4) new courtrooms
with associated judicial chambers, jury deliberation rooms, conference rooms, and ancillary spaces. Scope
also includes upgrading existing restrooms and providing for new restrooms, and the installation of new FP
and MP&E systems. The Work is to be based on construction drawings already prepared by DFDG, Architects
and similar to the existing ECM 5th Floor recently completed.
Project Closeout Information:
Substantial Completion Date Warranty - Begins & Ends
Certificate Of Occupancy Issued: 1=I YES CI NO Final Payment Date
Job File S: \Capital Facilities..Active Projects FY14\3303-14-1108 EC'B CourtArns'10 AL Solicitationl I -Pro-Encuinberance \ Project Information ECB 6th
Fir Courinns {3303-14-1108.doc
Form Dale. Cif 1 7 OS

Mancopa County
Facilities Management Department
Article 5 Change Order Routing MEM:1W
Change Order # 01
Date: February 19, 2014 Project Manager & Edward J Wimmer / —6-0602
Phone # :
Vendor Name: ForeSite Design & Construction Work Order #: 14219170
Contract #: 13132-CMR Ph 1 Project #: 3303-14-1108
Purchase Order #: SC 147000801187 Project Name: East Court Building New
Courtrooms 2014
Amount
Funding Source D MM CIP 0 Annual Funds D User Funds Requested: $0.00
FUND AGENCY LOW ORG ACTIVITY F CODE OBJ SUB 0EiJ REP. CAT JOB # AMOUNT 1
445 47B 4713 FACM ECIM 0915 3303 141108 $0.00
$
$
$
APPROVAL OR REVIEW REQUIRED INITIAL
1. All information has been reviewed by Project Manager
2. All information has been reviewed by Building Region Supervisor
3. Budget Analyst Review
4. Article 5 Procurement Review
5. Additional Special or Requested Review (Specify)
6. 0 & M Division Manager Approval (if applicable)
7. CFD Manager or Planning Manager Approval
8. FMD Deputy Director Approval
9. FMD Director Approval
10. CFD Administration Processing
11. Article 5 Change Order Processing
12. Purchase Order Processing
Purchase Order Total to Date: $32,357.00
Project Start Date: 01/09/2014 Project End Date: 8/1212014
DESCRIPTION OF PROJECT SCOPE OR CHANGE ORDER: Change the floor where construction is to take place from
the 6th floor to the 7th Floor to avoid conflicts between the new Construction of this Contract and additional Selective
Demolition Abatement and Fireproofing of another contract which needs to work on the 6th floor. That other work is under
contract 12140-CMR (2) and made necessary due to concealed, unforeseen conditions within the building Return Air
Shafts..
Required Attachments 1. Change Order Package 2. Project Information Sheet w/ Complete Scope 3. Vendor Proposal with Supporting
Documentation 4. Schedule 5. Budget Summary Sheet