CONSULTANT CHANGE ORDER - BOS APPROVAL
Maricopa County Department of Transportation
Change Order Number: 7
Date: 10/15/2013 Amount: $ 218,763.89 Agenda Item Nor C9112097500
Contract No: 2011-039 1 Work Order No:I TI-195
Consultant Name: Tristar Eingmeering and Management, Inc.
Project Name:I Northern Parkway: Sarival to Dysart, Phase 1
Initial Amount: $3,338,481.43 Contract Award Date: 1/17/2012 Total Prior Change Orders: $1,100,294.76
By mutual agreement of the parties, the following contract change(s) are incorporated into the above-identified contract. All other contract terms and conditions
remain unchanged.
Change Order No. 7 shall modify Contract No. 2011-039 as follows: 1) Extend the Base Contract Period of Service; and 2) Increase the Base Contract Not-to-
Exceed Fee for factors beyond the contract scope.
Extend the Base Contract Period of Service 61-days and increase the not-to-exceed contract base fee $218,763,89 due to the Construction Contractor being
over six-months behind schedule. With this Change Order No. 7 and prior Change Order No's. 3 thru 6, the Base Contract Period of Service will have been
extended a total 01231-days due to the Construction Contractor schedule slippage. The Optional Task Allowance time extension of 120-days per previous
Change Order No. 3 is unaffected by Change Order No. 7. The Optional Task Allowance completion date shall be 120-days after the revised Base Contract
completion date of 11130113.
With this Change Order, the total amount of this contract has increased 39%.
By reason of this change 61 days extension of time will be allowed.
The contract completion date is: November 30, 2013 (Base Contract) March 30, 2014 (Optional Task Allowance)
The following financial information is submitted:
Initial Contract Amount $ 3,338,481.43
Amended Contract Amount w/ previous change orders $ 4,438,776.19
Current Change Order Request $ 218,763.89
Amended Contract Amount w/ current change order $ 4.657,540.08
We, the undersigned Consultant, do hereby agree that upon execution of this Change Order that we will perform all work as identified above, and as may be described in
attachment(s) and will accept the above specified amount(s) as full payment thereof
IN WITNESS WHEREOF, the parties herein have executed this Contract Change Order:
Principal (Signature) Federal Tax ID Number:
Printed Name
Title:
Date:
CITY of )000000000( APPROVAL
I certify that this change is required for this contract.
Project Manager: Date:
MARICOPA COUNTY DEPARTMENT OF TRANSPORTATION
I certify that this change is required for this contract
Project Manager Date Branch Manager Date
I certify that funds are available Lio accomplish this Change Order I certify that this change is within the limits authorized by the Maricopa County
Procurement Code
CIP Cash Flow Manager Date Contract Specialists Date
COUNTY APPROVAL
RECOMMENDED BY: ACCEPTED AND APPROVED:
John B. Hauskins, P.E. Date Chairman, Board of Supervisors Date
Transportation Director
ATTEST:
LEGAL REVIEW
Approved as to form and within the powers and authority granted under the
laws of the State of Arizona to the Maricopa County Department of Transportation. Clerk of the Board Dale
Deputy County Counsel Dale
Distribution: Originals - Consultant, Contracts Branch, Clerk of the Board Copies - Finance, Project Manager, City Partner (if applicable)
Revised 10/15/2013

TRISTAR
ENGINEERING AND
MANAGEMENT. INC.
October 3, 2013
Alfred Erives, P.E.
Chief Construction Engineer
Maricopa County Department of Transportation
2901 West Durango Street
Phoenix, AZ 85009
Re: MCDOT Contract No, 2011-039 Modification #7
Northern Parkway: Sarival to Dysart. Phase 1 - Construction Administration
Dear Mr. Erives:
Tristar Engineering and Management, Inc. (Tristar) is pleased to submit our request for
Contract Modification #7 for MCDOT Contract 2011-039, Northern Parkway: Sarival to Dysart
Phase 1. We appreciate the continued opportunity to provide construction administration
services to MCDOT.
As part of Modification #3,#4,#5 and #6, the contract was extended until September 30, 2013.
This date was based on the contractor's revised CPM schedule, which at that time identified a
completion date of September 18, 2013. Based on the contractor's actual schedule, their new
completion date has delayed to October 31, 2013. Tristar respectfully requests a time extension
for an additional 61 calendar days, taking the contract end date from September 30, 2013 to
November 30, 2013. Also, this request for contract modification includes the additional cost of
extending the contract two months to November 30, 2013. The following staff will be part of the
two month extension along with myself;
• Bob Webb (Tristar) 89 Structures - Part Time
• Robert Clifford (QT) -59 Roadway/Materials
• Steve Tischler (Tristar) -87 working on fence, striping, MVVD and punch list
• Dennis Torres (CEI) - 86 working on channel, structures, and. barrier
• Corey Clifford (QT) -54 materials runner and testing
In addition, Omayra Jose (PB) 87 will continue to be our office manager reviewing contractor's
payrolls and submittals. PB's budget was previously increased as part of Modification #3, and
no additional cost is needed as part of this modification.
I would like to point out that this request is based on the data compiled by the contractor and
the dates that result from the CPM schedule they have provided. Tristar concurs with the
activity relationships and logic presented as part of our review, but I have expressed my
concern to the contractor that their resource loading within the planned schedule regularly does
not match their day-to-day anticipated productivity. For this reason, there is still uncertainty if
the contractor will be substantially complete by October 31, 2013 as they have indicated.
Physical Address: Mailing Address:
10625 N. 25th Avenue, Suite 103 PO Box 35278
Phoenix, AZ 85029-4789 Tel: (602) 288-5594 Fax: (602) 288-5592 Phoenix, AZ 85069-5278

Furthermore, Modification #3 added four months as part of an optional task allowance to be
used in the event the two outstanding claims and time extension request were not resolved by
the end of the contract time. Since then, one claim is still pending, one additional claim has
been brought up and any contractor time extension has not necessarily been resolved with
contractor concurrence. Tristar would like to request that the contract maintain those additional
four months of the optional time as it was originally provided within Modification #3. In this
case, the contract end date would become March 30, 2014.
Please do not hesitate to contact me at (602) 768-4178 or clara@tristar-az.com to meet and
discuss any questions, or if you require additional information.
We appreciate the opportunity to continue working with you and other MCDOT staff on this
contract.
Sincerel
CarlOiLara, P.E.
Vice President
cc: Alissa Connelly
File T110401
*TRISTAR
ENGINEERING AND
AIANAGENIFNT. INC.

FEE PROPOSAL - TABLE A
CONSULTANT
COST PROPOSAL SUMMARY
CONSULTANT: Tristar Engineering and Management, Inc. Contract No.: 2011-039
PROJECT NAME: Northern Parkway: Sarival to Dysart, Phase 1
Date: 10/3/2013
DIRECT LABOR
Classifications Man-Hours Hourly Rates Labor Costs
SAE 352 $65.85 $23,179.20
59 176 $42.50 $7,480.00
56 Office $33.00
S7 E1T $36.00
$7 352 $34.00 $11,968.00
Si $34.00
57 $34.00
S7 $34.00
S6 Materials Coordinator $30.00
S5 $24.00
Consultant's Subtotal Direct Labor $42,627.20
Consultant's OH Rate (% of Direct Labor) 119.51% $50,943,77
Consultant's Profit (% x (Direct Labor + OH)) 10% $9,357.10
Consultant's Total Direct Labor $102,928.06
DIRECT AND OUTSIDE EXPENSES
Description Unit Price Quantiy Expense Amount
Mileage (1500 miles per mo a 6 vehicle months) $11.51 9,000.00 $4,590.00
Lease ($600 per mo a 6 vehicle months) $600.00 6.00 $3,600.00
Phone ($75 per mo x 6 phone months) $75.00 6.00 $450.00
Office Month $6,122.00 2.00 $12,244.00
Consultant's Total Direct & Outside Expenses $20,884.00
Page I of 2
Cost Proposal Summary - Table A

FEE PROPOSAL - TABLE A
CONSULTANT
COST PROPOSAL SUMMARY
SUBCONSULTANT(s)
Name of Subconsultant Task Total Cost
Consultant Engineering the. $29,216.96
Quality Testing $65,734.87
Total Subconsultant(s) $94,951.83
Consultant's Total Direct Labor S1024928.06
Consultant's Total Direct and Outside Expenses S115,835.83
Total: $218,763.89
Consultant's Totals of Direct Labor and
Direct and Outside Expenses $218,763.89
OPTIONAL TASK ALLO ANCES
TASK ESTIMATED COST
TOTAL PROPOSED FEE S2I8,763.89
anclosive of( 'onsullant and Subconsultont(s) fool propmed fee.)
Tristar Engineering and Management, Inc.
Firm Contractor's Bid: $42,266,996.67
Original Contract Amount: $3,338,481.43
Orginal CE Cost: 7.90%
Modification #3 Amount: $713,263.71
Modification 45 Amount: $225,029.78
Modification #6 Amount: $162,001.27
Modification #7 Amount: $218,763.89
Vice President d Revised New Contract Amount: $4,657,540.08
Title New CE Cost 11.02%
10/3/2013
Dale
R. 11.021/11. fajc
Page 2 of 2
Cost Proposal Summary - Table A

FEE PROPOSAL - TABLE B
CONSULTANT/SUBCONSULTANT
SCHEDULED PROJECT MAN-HOURS
CONSULTANT NAME: Tristar Engineering and Management, Inc, Contract No.: 2011-039
PROJECT NAME: Northern Parkway: Sarival to Dysart, Phase 1
Date: 10/3/2013
MAN-HOURS ESTIMATED MAN-BOLAS
-1
Year . JAN FEB MAR APR MAY JUN JUL AEC SEP (l ET Nov ilrA"10T %1 S
SRE Year 1 352
Year 2 176 176
S9 Year 1 176
Year 2 88 88
S6 Office Year 1
Year 2
S7 EIT Y ear 1
Year 2
S7 Year I 352
Year 2 176 176
S7 Year 1
Year 2
S7 Year I
Year 2
57 Year I
Year 2
S6 Matenals Coordinator Year 1
Year 2
S5 Year I
Year 2
TOTAL 440 440 880
Manhours - Table B (3i Pag c Lofl

2011-039 TOTAL LABOR $42,627.20 $42,627.20 1 of 1
Page
CONTRACT: TOTAL MAN-HOURS 880 880
I
S5 $24.00 HR
Materials $30.00 HR
LABOR S7
I
S7 $34.00 HR
I
DIRECT S7 $34.00 HR
1 S7 $34.00 HR
C AND Inc. Phase . 1
Dysart, S7 $34.00 HR 352 352
TABLE CONSULTANT/SUBCONSULTANT Management, EIT I
MAN-HOURS to CLASSIFICATIONS S7 $36.00 HR
and Sarival Office I
533.00 HR
Engineering Parkway: LABOR S6
S9 $42.50 HR 176 176
ESTIMATED Tristar Northern 10/3/2013 DIRECT SRE $65.85 HR 352 352
, I
INSPECTION
TASK/PHASE CONFERENCE & (2) C
Table
-
NAME: CONTRACT ADMINISTRATION TASK/PHASE Clas.
NAME: REVIEW PRECONSTRUCTION Labor
CONSULTANT PROJECT PREBTD VISIT PLANS PROJECT CLOSE-OUT ANOTHER TOTAL Dir,
DATE: SITE

OVERTIME RATE DESIGNATION - TABLE D
CONSULTANT
COST PROPOSAL SUMMARY
CONSULTANT: Tristar Engineering and Management, Inc. CONTRACT NO.: 2011-039
PROJECT NAME: Northern Parkway: Sarival to Dysart, Phase 1
DIRECT LABOR
Classifications Hourly Rates OT Factor , OT Rate
SAE $65.85 1.0 $65.85
59 $42.50 1.0 $42.50
56 Office $33.00 - 1.5 $49.50
Si EIT $36.00 1.0 $36.00
S7 $34.00 .. 1.5 $51.00
Si $34.00 1.5 , $51.00 ..
Si $34.00 1.5 $51.00
Si $34.00 1.5 $51.00
S6 Materials Coordinator $30.00 1.5 $45.00
S5 $24.00 1.5 $36.00
Overtime will require approval by the MCDOT Project Manager prior to use.
Overhead and profit will be applied to the base OT rate for actual hours worked over 40 in a single week.
Tristar Engineering and Management, Inc.
Vice President
Title
1013/2013
Date

CONSULTANT: Tristar Engineering and Management, Inc. Contract No.: 2011-039
PROJECT NAME: Northern Parkway: Sarival to Dysart, Phase 1 Date: 10/3/2013
OFFICE COST
Office Rent $2,800.00 month
Office Alarm $100.00 month
APS Power $300.00 month
Drinking Water $100.00 month
Janitor Service $350.00 month
Office Supplies $100.00 month
Pest Control $50.00 month
Copier/Scanner $500.00 month
Internet $150.00 month
Computers $1,400.00 month
IT Support $272.00 month
$6,122.00

FEE PROPOSAL - TABLE A
SUBCONSULTANT
COST PROPOSAL SUMMARY
SUBCONSULTANT: Consultant Engineering, Inc. (DBE) Contract No.: 2011-039
Survey / Construction Inspection
Subconsultant to Tristar Engineering and Management, Inc.
PROJECT NAME: Northern Parkway: Sarival to Dysart, Phase 1
Contract Modification
Date: 9/25/2013
INSPECTION DIRECT LABOR
Man-Hours Hourly Rates Labor Costs
Inspector 352 $30.00 $10,560.00
Subconsultant's Subtotal Direct Labor for CM $10,560.00
Subconsultant's OH Rate (% of Direct Labor) for CM 126.73% $13,382.69
SubconsuItant's Profit (% x (Direct Labor + OH) for CM 10% $2,394.27
Subconsultant's Total Direct Labor for CM $26,336.96
SURVEY DIRECT LABOR
,
Re!'stered Land Surve or $38.00
Surve or $32.00
Subconsultant's Subtotal Direct Labor for Survey
Subconsultant's OH Rate (% of Direct Labor) for Survey 185.95%
Subconsultant's Profit (% x (Direct Labor + OH) for Survey 10%
Subconsultant's Total Direct Labor for Survey
DIRECT AND OUTSIDE EXPENSES
011.1111. Description Unit Price Quantity EApeose Amnia
Inspection Mileage -2 Months x 1500 miles = 3,000 $0.510 3,000.00 $1,530.00
Inspection Vehicle Lease - 2 Months x $600.00! Month .= $1,200.00 $600.00 2.00 $1,200.00
Inspection Phone -2 Months at $75.00! Month = $150.00 $75.00 2.00 $150.00
Survey Mileage - 14 months x 500 miles --- 7,000 $0.510
Survey Vehicle Lease - $600.00! Month $600.00
Survey GPS Unit at $100.00! Day $100.00
Survey Phone - 7 Months at $75.00 / Month $75.000
Subconsultant's Total Direct Labor $26,336.96
Cost Proposal Summary - Table A Page 1 of 5

FEE PROPOSAL - TABLE A
SUBCONSULTANT
COST PROPOSAL SUMMARY
Subconsultant's Total Direct and Outside Expenses $2,880.00
Total: $29,216.96
Subconsultant's Totals of Direct Labor and
Direct and Outside Expenses $29,216.96
OPTIONAL TASK ALLOWANCES
TASK ESTIMATED COST
Overtime
TOTAL PROPOSED FEE 529,216.96
(Inclusive of Consultant and Subconsuhani(s) total proposed fee)
Consultant Engineering, Inc. (DBE) - (Subconsultant to Tristar)
Firm
Signature
President
Title
9/25/2013
Date
Rev 11.2911 iajc
Cost Proposal Summary - Table A Page 2 of 5

of 5
3
9/25/2013 Page
352 352
2011-039
No.: Date: DEC
Contract
N 176 176
OCT 176 176
-
SE?
B MAN-HOURS 'IL '
_All ....
TABLE MAN-HOURS
ESTIMATED
-
1
SUBCONSULTANT PROJECT Phase ni
PROPOSAL (DBE) Dysart,
Inc. to MIME
Sarival
SCHEDULED
Engineering,
FEE Parkway: _di
2012 2013 2012 2013 2012 2013
Consultant Northern
_
NAME: MAN-HOURS Inspector RLS Surveyor TOTAL
(3)
B
NAME: Table
SUBCONSULTANT -
PROJECT Manhours
-

of 4 5
Page
2011-039 TOTAL LABOR S10.560.00 510,560.00
NO: I
CONTRACT TOTAL MAN-HOURS 352 352
LABOR
DIRECT 1
C AND Phase Surveyor $32.00 HR
(DBE) Dysart,
TABLE SUBCONSULTANT Inc, to Sarival RLS $38.00 HR
MAN-HOURS Engineering, CLASSIFICATIONS
Parkway:
Consultant Northern 9/25/2013 LABOR Inspector $30.00 HR 352 352
ESTIMATED DIRECT
TASK/PHASE
NAME: (2)
NAME: CONTRACT Inspection Survey Survey C Table
SUBCONSULTANT PROJECT DATE: Construction Construction Construction TOTAL Clas.
Labor
Dir.

OVERTIME RATE DESIGNATION - TABLE D
SUBCONSULTANT
COST PROPOSAL SUMMARY
SUBCONSULTANT: Consultant Engineerina. Inc. (DBE) CONTRACT NO.: 2011-039
PROJECT NAME: Northern Parkway: Sarival to Dysart, Phase 1
DIRECT LABOR
Classifications Hourly Rates OT Factor OT Rate
Inspector $30.00 1.5 $45.00
Registered Land Surveyor $38.00 1.0 $38.00
Surveyor $32.00 1.5 $48.00
Overtime allowance will be provided separately by MCDOT and will require approval by the MCDOT Project
Manager prior to use.
Overhead and profit will be applied to the base OT rate for actual hours worked over 40 in a single week.
Consultant Engineering, Inc. (DBE)
Firm
Signature
President
Title
9/25/2013
Date
Page 5 of 5

Maricopa County Department of Transportation (MCDOT)
OT
SUBCONSULTANT COST PROPOSAL SUMMARY
SUBCONSULTANT Quality Testing. LLC - Inspection/Testing/Materials Management
( Subconsultant to Trislar)
PROJECT NAME Northern Parkway (Serval to Dysart, Phase 1), QT Add 0713-NOV13
QT DIRECT LABOR:
REG REG ASSID OF OF LABOR QT
CLASSIFICATION * HOURS RATES % 0/T HOURS RATES ** COSTS DiV
Materials Engineer (ADOT 72) 0 $ 46,00 0% 0 5 46.00 $ - FLDICM
Chief Inspector (ADOT S9) 352 $ 42,00 0% 0 $ 42.00 $ 14,784.00 FLD/CM
Inspector (ADOT S7) 0 $ 34.00 0% 0 $ 51.00 $ - FLDICM
Inspector (ADOT 56) 0 $ 28.00 0% 0 $ 42.00 $ • FLD/CM
lnspector/TechnicIan (FOOT 65) 0 $ 2200 . 0% 0 $ 33 00 $ - FLD/CM
Technicianniunner (ADOT S4) 352 $ 17.00 0% 0 $ 25_50 $ 5,984.00 FLD/CM
Project Lab Manager (ADOT S9) 0 $ 4200 0% 0 $ 4200 . $ LAB
Lab Supervisor (ADM' S7) 0 $ 34_00 0% 0 $ 51.00 $ LAB
Lab Technician 3 (ADOT 86) 0 $ 28,00 0% 0 $ 42.00 $ LAB
Lab Technician 2 (ADOT 55) 110 $ 22,00 0% 0 $ 33.00 $ 2,420.00 LAB
Lab Technician I (ADOT 84) 24 $ 17.00 0% 0 $ 25.50 $ 408.00 LAB
Rates reflects a typical rate within the classdication.
Regular Rate x Overtime Factor of 1 5 (1.0 for 59 and above)(SEE OPTIONAL TASKS)
Field/CM OW (II Labor Cost Applicable to Fiebiele ON $ 20,768.00
BASE 122 64% 2009 Audited Field/CM OH 'at
cn IELD
OH AEU 000% VehictelODC Recovered as Direct Costs ,—
OH ADJ 000% Overtime Recovered by OT Premium co
EFFECTNE (L7SE) 121.64% (Field I CH) Overhead x (1) Labor Cost $ 26,677.66
Let, ow (2) Labor Cost Applicable to Lab OH $ 2,828.00
BASE 165 61% 2009 Audited Lab OH ZR
OH ADJ 000% Vehicle/ODC Recovered as Direct Costs T? LAB
mr
CH A.0.1 Om% Overtime Recovered by OT Premtum
EFFECTIVE (USE} 185.61% (LAB/ Overhead r (1) Labor Cost $ 5,249.05
(3) Subtotal $ 54,522,61
FEE 10.00% FEE x (3) Subtotal $ 5,462.26
TOTAL EXTENDED OT LABOR 5 59,974.87
!OTHER DIRECT COSTS (Not included AbOre):
CLASSIFICATION UNITS U. PR. I OTY I FIELD I LAB A TOTAL COST
Outage Specalty Testalt (AC Binder. Reber. etc) $LS $ 000 a s • 5-
vehicle Project %leap NOT INC IN OH) MI $ 0 510 6000 3,060 1,20000
Vehicle Lease (NOT INC. IN OH) MO 0 600 000 4 2.403 0 2.40000
Cell PnOne NOT INC IN OH) MO $ 15 000 4 300 s 30005
TOTAL EXTENDED OTHER DIRECT COSTS $ 5,760.00
OPTIONAL TASK ALLOWANCES (Not included above):
TASK ESTIMATED COST
Contingency Overtime SO 00
TOTAL EXTENDED OTHER DIRECT COSTS $0.00
GRAND Ta TM.
OTAL ESTIMATED ADDITION TO PROJECT COST $ 65,734.87 This is only the amount that will be
added to the current contract
amount, The current contract
1.71, amount includes the Original
Contract plus Co No 3, CO Nob, and
CO No fi.
Signature -*-
Quality Testing, LLC
President - Doug Lot
061.00er 2, 2013
Date
Revised
COST SUMMARY, 1012/2013

m-h m-h rn-h rn-h 10/2/2013
TOTAL m-h rn-h m-h rn-h m-h m-h rn-h m-h rn-h 4.76 4.00 0.76
352 352 110 24
HRs/Mo HRs/Mo HRs/Mo HRs/Mo HRs/Mo
176.0 88.0 44.0 17.6 8.8 041 U 0 0 MAN-HOURS,
= = = = =
Time Time Time Time Time Add N•13 176 176 55 12 2.30 2 0.38
Full 50% 25% 10% 5% Add 0.13 176 176 55 12 ?3U 2 038
PROJECT
S43 0 0 0
A43 0 0
No3/No5/No
SCHEDULED
3-13 0 0 0
COt
Pntrious .143 0 0 0
M43 0 0 0
15 A•13 0 0 0
(Regular)
(MCDOT) 14 1143 0 0 0
13 F•13 0 0 0
MAN-HOURS MONTH
NO.)
12 3-13 0 0 0
THE
Transportation (MONTH 11 I342 a 0 0
PROJECT IN .
10 842 0 0 0
BUDGET
of MAN-HOURS 9 OM 0 0 0
SCHEDULED CONSTRUCTION 8 SA? 0 0
OCT13-NOV13
Department Management
7 A42 0 0
ORIGINAL
Add 6 347 o 000 0
.
County SUBCONSULTANT QT 5 1.12 o 0
1), Tristar) ....
4 M-11 Month) a 0 0
Phase Inspectionffesting/Materials to
Maricopa 3 A-22 per 0 0 0
Dysart,
Subconsultant 2 I1-12 (FTEs 0 0
to
- 1 F.-12 ooa 5
(Sarival LLC ( .- 00
..I-12 EQUIVALENTS 6
Parkway Testing,
I TIME CLASSES)
Quality MAN-HOURS 13 T2) 55) S4) 59) 56) 55) 54)
Northern 59) 57)
2013 DEC (ADOT 57) 56) (ADOT (ADOT (ADOT FULL
2, PLKSONNEL (ADOT (ADOT (FOOT {ADOT {ADOT ONLY)
(ADOT (ADOT 3 2 1 LABOR ONLY)
through Engineer Manager
October Inspector Supervisor Technician Technician Technician -MONTHLY (ALL (FIELD (LAB
Inspector Inspector InspectorrTechnician Technician/Runner Lab
NAME SUBCONSULTANT 12
PROJkCi JAN Materials Chief Project Lab Lab Lab Lab FTEs FTEs FTEs
SUBCONSULTANT
CIT
PROJECT SUMMARY
DATE: TOTAL TOTAL TOTAL

CHANGE ORDER REQUEST FORM
Date of Request:
Change Order No. 7 Phone No. 6-2882
10/9/13
Project Manager: Dave Hopper
Dept. PMC
Consultant/Contractor Name: Contract No.
Tristar Engineering and Management, Inc. 2011-039
Project Name: Project No TT195
Northern Parkway: Sarival Ave to Dysart Rd, Phase 1
Type: ElDepartmental ZBoard of Supervisors Contract Award Date:
1/17/12
The following financial information is submitted:
Initial Contract Amount $ 3,338,481.43
Total Prior Change Order Amounts: $ 1,100,294.76
Amended Contract Amount w/ previous Change Orders $ 4,438,776.19
Current Change Order Request $ 218,763.89
Amended Contract Amount w/ current Change Order $ 4,657,540.08
With this Change Order, the total amount of this contract has increased 39 %
By reason of this change 61 days extension of time to Base Contract will be allowed.
The new Base Contract completion date is: 11/30/13
Brief Description of Change Order Justification: (Attachments: Fee Proposal and Scope of Work)
Change Order requested to modify the Construction Administration Services contract as follows: 1) Extend the Base
Contract Period of Service; and 2) Increase the Base Contract Not-to-Exceed Fee for factors beyond the contract scope.
See below for details.
Extend the Base Contract Period of Service 61-days and increase the not-to-exceed contract base fee $218,763.89 due
to the Construction Contractor being over six-months behind schedule. With this Change Order No. 7 and prior Change
Order No's. 3 thru 6, the Base Contract Period of Service will have been extended a total of 231-days due to the
Construction Contractor schedule slippage. The Optional Task Allowance time extension of 120-days per previous
Change Order No. 3 is unaffected by Change Order No. 7. The Optional Task Allowance completion date shall be 120-
days after the revised Base Contract completion date of 11/30/13.
Tristar's Contract Modification Request letter dated 10/3/13 is attached.
Project Manager has compared Change Order Fees with Contract Fee Proposal? @Yes
Effective Date: 10/9/2013 Page
1 of 2

Project Manager has received fundin
TIP/OPS Manager Signature:
Branch Manager Approval:
Division Manager Approval:
Transportation Director Approval:
Effective Date: 101912013 Page
2 of 2