Council Report

City of Mesa — City Council (2026-11-16)

View PDF Meeting page

Extracted text (via pymupdf_layout) 3255 characters
City Council Report
Date: November 16, 2026
To: City Council
Through: Marc Heirshberg, Assistant City Manager
From: Lance Webb, City Engineer
Marc Ahlstrom, Assistant City Engineer
Subject: Construct Taxiway I (Future Taxiway H)
City Project No. CP1222GPH1
Council District 5
Purpose and Recommendation
The purpose of this report is to provide information to Council concerning the results of
the bids received for the project, Construct Taxiway I (Future Taxiway H) (See Exhibit “A”
for the project location).
Staff recommends that Council award a contract for this project to the lowest responsible
bidder, Sunland Asphalt Construction Company, in the amount of $629,234.95, and
authorize a change order allowance in the amount of $62,923.50 (10%).
Background
The Construct Taxiway I (Future Taxiway H) will create a new taxiway at the end of the
existing Taxiway D at Falcon Field Airport. This project will provide a direct connection
from Taxiway D to Anzio Ramp. This will free up space for a future project to create a
holding bay allowing for safer and increased capacity queueing space for departing
aircraft.
Discussion
This project is needed to open up areas for aircraft to safely wait for takeoff while allowing
the more efficient use of Taxiway D. By creating a direct connection from Taxiway D to
the Anzio Ramp arrivals can quickly clear space while creating space for a future holding
bay between Taxiway D and Anzio Taxilane.
Community Impact – There is no impact to the community, because all work will occur
within the perimeter fence of Falcon Field Airport.

Once underway, construction of this project is anticipated to last no more than 3 months.
Alternatives
An alternative to this project would be to not construct these improvements. This is not
recommended because it would prevent the construction of a future project to build a
holding bay. These improvements are needed for the growing air traffic at Falcon Field
Airport. In addition, if the city chooses not to move forward with the project, over $600,000
in grant funding will be forfeited.
Fiscal Impact
The total authorized amount recommended for this project is $692,158.45, based upon
the lowest responsible bid of $629,234.95, plus an additional $62,923.50 (10%) as a
change order allowance. This change order allowance will only be utilized for approved
change orders.
This project is funded by the Falcon Field Capital funds. This project is eligible for FAA
grant reimbursement. The FAA will reimburse the city for 95.0% of the eligible project
costs. Falcon Field has applied to the Arizona Department of Transportation, Aeronautics
Group (ADOT) for a matching grant to fund 2.375% of the project and the Airport
Enterprise Fund will fund the remaining 2.625%. If an ADOT grant is not received, Falcon
Field will fund the entire local match of 5.0% with funding available from the adopted
Falcon Field FY26-27.
Coordinated With
Falcon Field Airport concurs with this recommendation.
2

CITY OF MESA
MESA, ARIZONA
Construct Taxiway I (Future Taxiway H)
PROJECT NO. CP1222GPH1
Tabulation of Bids Received, Thursday, May 28, 2026, at 1:00 P.M.
ENGINEER’S ESTIMATE $663,412.60
1. Sunland Asphalt Construction Company $629,234.95
2. Granite Construction $675,652.00
3