City Council Report
Date: November 16, 2026
To: City Council
Through: Marc Heirshberg, Assistant City Manager
From: Lance Webb, City Engineer
Marc Ahlstrom, Assistant City Engineer
Subject: Brown Road and 40th Street Traffic Signal
City Project No. CP1067
Council District 2
Purpose and Recommendation
The purpose of this report is to provide information to Council concerning the results of
the bids received for the Brown Road and 40th Street Traffic Signal project (See Exhibit
“A” for the project location).
Staff recommends that Council award a contract for this project to the lowest responsible
bidder, Lincoln Constructors, in the amount of $968,106.00, and authorize a change order
allowance in the amount of $96,810.60 (10%).
Background
The Transportation Department routinely evaluates the City’s roadway network to support
safe and efficient travel for all users. Over the years, the City has received requests from
area residents to evaluate the need for a traffic signal at Brown Road and 40th Street,
with renewed public concern following a fatal crash in 2023. Although the intersection has
not experienced a high overall number of crashes, traffic counts and an engineering
evaluation determined that it meets established traffic signal warrants based on vehicle
volumes. The intersection is also located at a quarter-mile point along Brown Road,
consistent with typical traffic signal spacing. Based on the results of the traffic study,
Transportation Department initiated this project to construct a new signal and associated
improvements, as outlined below.

Discussion
At the northwest corner, the curb will be modified to establish a right-turn lane serving the
adjacent property in accordance with City standards. Supporting improvements include
pavement rehabilitation on 40th Street, sidewalks, ADA-compliant curb ramps, curb and
gutter, signing, pavement markings, street lighting, and other infrastructure necessary to
complete and operate the signalized intersection.
Community Impact – Temporary impacts during construction will include traffic control
restrictions at the intersection of Brown Road and 40th Street. Construction tasks will be
phased to limit traffic impacts, maintain public access to businesses and local streets
when feasibly possible.
Once underway, construction of this project is anticipated to last no more than 5 months.
Alternatives
An alternative to this project would be to not construct these improvements. This is not
recommended because without this project, the existing condition would stay in place and
not provide any safety measures for the public drivers.
Fiscal Impact
The total authorized amount recommended for this project is $1,064,916.60, based upon
the lowest responsible bid of $968,106.00, plus an additional $96,810.60 (10%) as a
change order allowance. This change order allowance will only be utilized for approved
change orders.
This project is funded by the Transportation Department Local Sales Street Tax.
Coordinated With
The Transportation Department concurs with this recommendation.
2

CITY OF MESA
MESA, ARIZONA
Brown Road and 40th Street Traffic Signals
PROJECT NO. CP1067BR
Tabulation of Bids Received, Thursday, October 22, 2026, at 1:30pm.
ENGINEER’S ESTIMATE $942,117.00
1. Lincoln Constructors $968,106.00
3