City Council Report
Date: November 2, 2026
To: City Council
Through: Marc Heirshberg, Assistant City Manager
From: Lance Webb, City Engineer
Marc Ahlstrom, Assistant City Engineer
Subject: Rehabilitate West Vehicle Service Road
City Project No. CP1225GPH1
Council District 5
Purpose and Recommendation
The purpose of this report is to provide information to Council concerning the results of
the bids received for the Rehabilitate West Vehicle Service Road project (See Exhibit “A”
for the project location).
Staff recommends that Council award a contract for this project to the lowest responsible
bidder, Granite Construction, in the amount of $792,291.00, and authorize a change order
allowance in the amount of $79,229.10 (10%).
Background
The West Vehicle Service Road allows maintenance vehicles and airport staff to travel
from the offices and hangers on the east side of Falcon Field Airport to the those on the
west side. The pavement on the service road has deteriorated and its condition is rated
as poor. This project will utilize various repair methods to address the failing asphalt and
subgrade extending its service life.
Discussion
The design plans analyzed the west perimeter road and delineated which repair method
is needed in each area allowing for the condition of the road to be improved while still
fitting within the project budget. The repair methods include subgrade replacement and
repair, crack sealing, asphalt milling, full depth asphalt paving and improved roadway
shoulders.
Community Impact – There is no impact to the community, because all work will occur
within the perimeter fence of Falcon Field Airport.

Once underway, construction of this project is anticipated to last no more than 3 months.
Alternatives
An alternative to this project would be to not construct these improvements. This is not
recommended because the roadway condition would continue to worsen and become
unusable. Future repair costs would be significantly higher for the City of Mesa. If the
city chooses not to move forward with the project, over $700,000 in grant funding will be
forfeited.
Fiscal Impact
The total authorized amount recommended for this project is $871,520.10, based upon
the lowest responsible bid of $792,291.00, plus an additional $79,229.10 (10%) as a
change order allowance. This change order allowance will only be utilized for approved
change orders.
This project is funded by the Falcon Field Capital funds. This project is eligible for FAA
grant reimbursement. The FAA will reimburse the city for 95.0% of the eligible project
costs. Falcon Field has applied to the Arizona Department of Transportation, Aeronautics
Group (ADOT) for a matching grant to fund 2.5% and the Airport Enterprise Fund will fund
the remaining 2.5%. If an ADOT grant is not received, Falcon Field will fund the entire
local match of 5.0% with funding available from the adopted Falcon Field FY26-27.
Coordinated With
Falcon Field Airport concurs with this recommendation.
2

CITY OF MESA
MESA, ARIZONA
Rehabilitate West Vehicle Service Road
PROJECT NO. CP1225GPH1
Tabulation of Bids Received, Thursday, May 28, 2026, at 1:30P.M.
ENGINEER’S ESTIMATE $806,270.00
1. Granite Construction $792,291.00
3