City Council Report
Date: November 16, 2026
To: City Council
Through: Scott Butler, City Manager
Marc Heirshberg, Assistant City Manager
From: Nana Appiah, Development Services Director
Ashley Scott, Management Assistant II
Subject: DA26-00007 Waffle Flower Development Agreement
Council District 5
Purpose and Recommendation
The purpose of this report is to discuss and consider approving a Resolution to
authorize the City Manager to enter into a Development Agreement (“DA”) with ZEE
Properties LLC, a Delaware limited liability company (“Owner”). The Owner’s
property consists of 2.39 acres located north of Thomas Road and east of Higley
Road with the address of 5318 E Thomas Road. The agreement would temporarily
defer specified wastewater and streetlight improvements along 54th Street,
permanently waive the 54th Street sidewalk requirement, and permit temporary use of
an approved on-site commercial septic system until City wastewater service
becomes available.
Staff recommends that the City Council approve the Development Agreement.
Background
Through zoning case ZON25-00943, the Owner has applied to rezone the property
from Single Residential-90 (RS-90) to Light Industrial (LI) to allow for the
development of a building for manufacturing and warehouse uses. Mesa City Code
Title 9, Chapter 8 requires the Owner to provide public off-site infrastructure,
including wastewater facilities and roadway frontage improvements, unless
requirements are modified under applicable City Code provisions.
It has been identified that special conditions affecting the property include that
connection to City wastewater service is not currently available because certain
regional infrastructure has not been completed; a sidewalk system is not intended for
this primarily industrial area, and a comprehensive streetlight system is not
anticipated until a later date. Under Mesa City Code Sections 9-8-4(A) and 9-8-
4(D)(2), the Development Agreement provides for limited deferrals, a permanent
sidewalk waiver, and an alternative wastewater treatment arrangement in response
to these conditions.

Discussion
The Development Agreement sets out the Owner’s responsibilities for developing the
property while providing the following limited modifications and conditions:
 Deferred Improvements: The Owner’s obligation to extend the City wastewater
line, connect to the City wastewater system, and install streetlights along 54th
Street will be deferred for up to 10 years, unless the City Manager ends the
deferral earlier. The Owner must complete the deferred improvements within one
year after the deferral period ends, unless the City Manager requires an in-lieu
payment.
 Sidewalk waiver: The requirement to construct a sidewalk along 54th Street
adjacent to the property will be permanently waived, provided the Owner
complies with the Development Agreement.
 Lieu Payment and Financial Assurances: At the end of the deferral period, the
City Manager may require an in-lieu payment instead of construction of the
deferred improvements. The payment must be made within 60 days of notice and
will be based on an estimate approved by the City Engineer, including a 20%
contingency. The Owner must also provide financial assurances every two years
demonstrating that its tangible net worth is at least five times the estimated cost
of completing the deferred improvements.
 Temporary wastewater service: The Owner may install and operate an
approved onsite commercial septic system at its own expense until City
wastewater service becomes available. The Owner must also install a dry
wastewater line to allow for future connection. Once the City issues a Connection
Notice, the Owner must connect to the City wastewater system and properly
discontinue use of the septic system within 120 days.
These provisions allow the Project to proceed while preserving the Owner’s
obligations to complete all other required public infrastructure improvements and
connect to the City’s wastewater system when service becomes available.
Alternatives
The following alternatives are presented for consideration:
Not to Approve the Resolution:
If Council does not approve the Resolution, the City Manager would not be
authorized to enter into this Development Agreement. The Owner would remain
subject to applicable City Code infrastructure requirements without the proposed
wastewater and streetlight deferrals, sidewalk waiver, or temporary septic-system

alternative under this agreement. This could affect the timing or feasibility of the
proposed development.
Staff recommends approval of the Resolution to address the identified special
conditions while retaining the Owner’s obligations as provided in the Development
Agreement.
Fiscal Impact
The Development Agreement does not require any additional City investment or result in
any additional fiscal impact to the City. The Owner is responsible for the costs
associated with the required public infrastructure improvements and the onsite septic
system.
Coordinated With
The Development Agreement was coordinated with the Development Services
Department, Water Resources Department, and the City Attorney’s Office.