October 8, 2026
TO: Members of the MAG Management Committee
FROM: Patrick Stone, Deputy Transportation Director - Programming
SUBJECT: FEDERAL FISCAL YEAR 2027 CLOSEOUT – REDISTRIBUTION OF AVAILABLE
FEDERAL HIGHWAY ADMINISTRATION FUNDING
Federal Highway Administration (FHWA) funding allocated to the MAG region is primarily made
up of Congestion Mitigation and Air Quality Improvement Program, Surface Transportation Block
Grant Program, and Transportation Alternatives funds. Consistent with policy set forth in the
Regional Strategic Transportation Infrastructure Investment Plan, these dollars are programmed
through the three life cycle programs and the Regional Competitive Programs - Call for Projects
process.
Annually, MAG reviews projected FHWA funding and compares this amount against programmed
projects for the current federal fiscal year to determine how much, if any, funding is
unprogrammed. Federal funding is allocated to the MAG region on a use or lose basis and unused
amounts need to be reprogrammed on other projects prior to the end of the federal fiscal year.
This occurs through the annual closeout process. MAG is now accepting applications for Federal
Fiscal Year (FFY) 2027 closeout funding.
For FFY 2027, the MAG region is currently estimated to have $25.0 million available for closeout
based on programmed amounts, project deferrals, potential cost savings, and projects that will be
closed out. Only projects selected through the Regional Competitive Programs-Call for Projects
process are eligible for closeout. Requests are now being accepted to:
• Advance projects currently programmed in FFY 2028 to FFY 2027
• Provide additional federal funding for current year (FFY 2027) projects
• Fund design work phase requests for FFY 2027
• Fund right of way work phase requests for FFY 2027
• Fund PM-10 Certified Street Sweeper applications that were not selected as part of
the FFY 2027 call for projects
Projects requiring the execution of, or an amendment to, an Intergovernmental Agreement (IGA)
between the member agency and the Arizona Department of Transportation (ADOT) must be
initiated by February 12, 2027, and the IGA must be fully executed by May 14, 2027, to allow
sufficient time for ADOT processing.

Closeout requests to advance FFY 2028 projects to FFY 2027 are to be submitted on member
agency letterhead and signed by the Manager/Designated Representative stating that project and
agency resources are available to advance the project.
Closeout requests for additional funding or to fund design or right of way work phases for projects
programmed in FFY 2027 should be submitted to MAG on the TIP Project Change form that is
available on the MAG website. Increases to existing FFY 2027 construction projects should also be
accompanied by an updated cost estimate prepared by the agency engineer or ADOT project
manager (the original application contains a cost estimate form that may be used).
Closeout requests to fund FFY 2027 Street Sweepers that were not awarded during the call for
projects are to be submitted on member agency letterhead and signed by the
Manager/Designated Representative stating that project and agency resources are available.
A fact sheet is attached to this notification outlining specific MAG guidelines and procedures
related to closeout and a schedule of key dates.
Please submit closeout requests via email to Patrick Stone, pstone@azmag.gov and cc Wendy
Miller, wmiller@azmag.gov on or before Thursday, November 12, 2026, at 12:00 p.m., via
email. Late requests will not be accepted.
MAG staff is available to help with information and questions regarding requirements. Please
contact Patrick Stone at pstone@azmag.gov or Wendy Miller, wmiller@azmag.gov via email, or
by phone at (602) 254-6300.
cc: ADOT, Local Public Agency Section MAG Intelligent Transportation Systems
ADOT Project Management Group Committee
FHWA Arizona Division Planners MAG Street Committee
MAG Intergovernmental Representatives MAG Transportation Review Committee
MAG Active Transportation Committee MAG Transportation Safety Committee

October 8, 2026
Federal Fiscal Year 2027 Closeout Request – Fact Sheet
The Regional Council approved the Regional Programming Guidelines on June 25, 2025. Requirements for
Closeout as noted are found in Section 480 Redistribution of Unused Funding (i.e., Closeout) are as follows:
1. Funding estimate. In August of each year, MAG staff will release an estimate of funding available
for redistribution for the current federal fiscal year. Typically, this estimate is calculated as the
difference between the anticipated sum of regional competitive funding from appropriations,
closed out projects and project deferrals, and the sum of projects anticipated to authorize. This
estimate will be updated if warranted by new information.
2. Cost estimates for redistribution. Cost estimates to be used in the redistribution of regional
competitive funding to the current year and advancing projects must meet the following criteria:
a. TIP cost estimates. Only costs as reported in the TIP or in pending TIP
amendments will be used for the redistribution of regional funds. MAG
members may update cost estimates for projects whenever MAG
processes changes to the TIP. Member agencies are strongly encouraged
to update the TIP for changes in project costs as they occur in the
development process and when MAG distributes project workbooks.
b. Engineering cost estimates required. Up to date engineering cost
estimates are required for all projects that are to receive redistributed
regional competitive funds. These estimates must be provided by either
the sponsoring agency or ADOT project manager. The costs listed must
be sufficient to use the redistributed regional competitive funding.
3. Advancing projects. MAG member agencies may at any time request to advance projects to take
advantage of the anticipated redistribution of funding. At a minimum, projects that are requested
to be advanced must meet all requirements for inclusion in the current year as identified in Section
610. Actions to approve project advancements will occur at the same time as the decision to
redistribute regional competitive funding.
4. Redistribution meeting. Early in the calendar year, TRC will consider priorities for the
redistribution of regional competitive funding. As a default, advancing projects will be given first
priority, increased funding for currently programmed projects will have second priority and loans
to projects or programs will have third priority.
5. Review and approvals. Following the redistribution meeting, the action of the TRC will be
reviewed, revised and, as appropriate, approved by the MAG Management Committee and
Regional Council.

6. Notice of redistribution. Following Regional Council approval MAG staff will provide notice
to MAG member agencies that will receive redistributed funding. This notice will be distributed
to project sponsor representatives as identified in Section 440.
Schedule
Category Date Committee / Group Action
Management Send out memo to Management Committee
Thu, Oct 8, 2026 Committee members outlining the FFY 2027 Closeout
process.
Transportation Review, Send out memo to committee members
Thu, Oct 8, 2026 Safety, ITS, Street, outlining the FFY 2027 Closeout process.
Active Committees
Closeout Request Send out memo to all member agencies
Notice Thu, Oct 8, 2026 All Member Agencies outlining the FFY 2027 Closeout process.
Send out memo to ADOT LPA and PMG
Thu, Oct 8, 2026 ADOT groups outlining the FFY 2027 Closeout
process.
Thu, Oct 8, 2026 FHWA Send out memo to FHWA staff outlining the
FFY 2027 Closeout process.
Thu, Oct 8, 2026 - All Member Agencies MAG Staff will be available to provide answers
Thu, Nov 12, 2026 to questions regarding the closeout process.
Application Period
Thu, Nov 12, 2026 All Member Agencies Requests Due at 12:00 pm (late requests
are not accepted)
Request Review Mon, Nov 16, 2026 MAG Staff Review requests to confirm project eligibility
and completeness of request.
Thu, Dec 10, 2026 Transportation Review Review and recommendation for closeout
Committee requests.
Wed, Jan 13, 2027* Management Review and recommendation for closeout
Committee Review Committee requests.
Wed, Jan 20, 2027* Transportation Policy Review and recommendation for closeout
Committee requests.
Wed, Jan 27, 2027* Regional Council Review and approve closeout requests.
* Estimated meeting date, subject to change