Item 3
enrcniiai mm
♦
REPORf mm
Meeting Date: November 24, 2026
General Plan Element: Connectivity
General Plan Goal: Circulation Element, Goal Cl-Design Safe and Efficient
Transportation Corridors
ACTION
ADOT Intergovernmental Agreement- Thomas Road: 56*'’ Street to TA**" Street Project. Adopt
Resolution No. 13811 authorizing the Intergovernmental Agreement Contract No. IGA 26-00011906-
I (2026-172-COS) with the Arizona Department of Transportation for the Thomas Road project from
56*'’ Street to 74*'’ Street.
BACKGROUND
This project includes pavement reconstruction on Thomas Road from Scottsdale Road to 56*'’ Street
and a micro seal on Thomas Road from 74*'’ Street to Scottsdale Road. The project will also include:
ADA and traffic signal upgrades at 60th Street, 61st Place, 64th Street, 68th Street, and 70th
Street intersections
Widening 64th Street along the north curb line
Construction of a right-turn lane at the southwest corner of 68th Street
Construction of a bus pull out at the northwest corner of Scottsdale Road
Construction of left turn lane near 73rd Street
Corridor-wide restriping of pavement markings; the existing roadway striping will remain the
same
Related roadway and storm drain improvements
Street lighting improvements (vicinity of 68th Street intersection)
Electric pole relocations southeast corner 64th Street
This project is an ADOT administered project. Arizona Department of Transportation will lead the
design and construcbon for the city. This requires an Intergovernmental Agreement with ADOT to
administer the federal funds on this project.
Page 1 of 3

City Council Report | ADOT Intergovernmental Agreement - Thomas Road: 56*'^ Street to 74*^
Street Project
ANALYSIS & ASSESSMENT
Recent Staff Action
The project design for the roadway improvements is complete. Sewerline improvements took place
from August to October 2026. Phase I waterline improvements began in late October 2026 and is
planned for completion by Thanksgiving. The second phase of waterline improvements is scheduled
to start in April 2027 and will be complete in June 2027.
Community Involvement
The community has been and will be involved in the implementation of this project via community
meetings (public open houses, Paths & Trails Subcommittee, and Transportation Commission) and
other appropriate methods. These include postcards, email, the newspaper, project updates on the
city's web page, and may include social media such as Facebook, X, and NextDoor online forums.
RESOURCE IMPACTS
Available funding
Funding is currently available in the adopted FY 2026/27 Capital Improvement Plan (CIP) budget for
the Thomas Road Project, 56*'^ Street to TA*'’ Street (New Capital Project 11). Funds include the City
of Scottsdale's Transportation 0.2% Sales Tax and federal grants. Federal funding is programmed
for this project.
CURRENT FUNDING SOURCES FOR CONSTRUCTION
Project Transportation 0.2% Sales
Type of Grant Grants
Tax Local Match Total
Thomas Federal Funds
Road: 56*" STBGP-MAG $ 17,379,099 $ 0 $ 17,379,099
Street to 74'" Local Funds $0 S 7,468,185 $ 7,468,185
Street
$ 17,379,099 $ 7,468,185 $ 24,847,284
Maintenance Requirements and Future Budget Implications
The completed project will be maintained by city staff and incorporated into the Street Operations
maintenance budget and schedule.
OPTIONS & STAFF RECOMMENDATION
Recommended Approach
Staff recommend City Council adopt Resolution No. 13811 authorizing the Intergovernmental
Agreement Contract No. IGA 26-00011906-1 (2026-172-COS) with the Arizona Department of
Transportation for the Thomas Road project from 56'" Street to 74'" Street.
Page 2 of 3

City Council Report | ADOT Intergovernmental Agreement - Thomas Road: 56*'^ Street to 74**’
Street Project
Proposed Next Steps
Upon Council approval. City staff will work with Arizona Department of Transportation who will lead
the project.
RESPONSIBLE DEPARTMENT(S)
Transportation and Infrastructure
STAFF CONTACTS (S)
Nathan Domme, Senior Manager Transportation Planning, (480) 312-2732,
ndomme(5>scottsdaleaz.gov
Derek Rogers, Senior Project Manager, (480) 312-7637, DerRogers(5)scottsdaleaz.eov
APPROVED BY
Alison Tymkiw, SeniorCirector - City Engineer
Transportation and Infrastructure Date
(480) 312-7760, Atvmkiw(a)scottsdaleaz.gov
ATTACHMENTS
1. Resolution No. 13811
2. Location Map
3. IGA 26-00011906-1 (2026-172-COS)
Page 3 of 3

RESOLUTION NO. 13811
A RESOLUTION OF THE COUNCIL OF THE CITY OF SCOTTSDALE.
MARICOPA COUNTY, ARIZONA. AUTHORIZING CONTRACT NO. 2026-
172-COS (IGA 26-00011906-1), AN INTERGOVERNMENTAL
AGREEMENT WITH THE ARIZONA DEPARTMENT OF
TRANSPORTATION (ADOT) FOR THE THOMAS ROAD PROJECT
FROM 56™ STREET TO 74™ STREET.
WHEREAS, Arizona Revised Statutes Sections 11-951, et seq. authorizes public
agencies to enter into agreements for services or to jointly exercise any powers common to
them, and to enter into agreements with one another for joint or cooperative action; and
WHEREAS, Article 1, Section 3-1 of the City's Charter authorizes the City to enter into
intergovernmental agreements with state agencies; and
WHEREAS, the City desires to enter into Contract No. 2026-172-COS (IGA 26-
00011906-1), an intergovernmental agreement with the Arizona Department of Transportation
(ADOT), for improvements to Thomas Road from Street to 74*^ Street (the “Project”); and
WHEREAS, the Scottsdale Transportation and Infrastructure Department is eligible for
a $17,379,099 federal grant with a $7,468,185 local match to fund the Project.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of Scottsdale,
Maricopa County, Arizona, as follows:
Section 1: The City Council hereby authorizes, approves and directs the Mayor
to execute, on behalf of the city. Contract No. 2026-172-COS (IGA 26-00011906-1), with the
Arizona Department of Transportation for the Thomas Road Project from 56^^ Street to 74*^
Street.
Section 2: The City Council hereby authorizes the City Manager or designee to
execute any other documents and take such other actions as a necessary to carry out the
intent of this Resolution.
PASSED AND ADOPTED by the City Council of the City of Scottsdale this dav
of _________ 2026.
CITY OF SCOTTSDALE, an
Arizona municipal corporation
ATTEST:
Ben Lane Lisa Borowsky
City Clerk Mayor
APPROVED AS TO FORM:
Luis E. Santaella, City Attorney
By: Lindsay Hampshire, Assistant City Attorney
19570182 Page 1 of 1
Resolution 13811 ATTACHMENT 1

•■Dl
X
CL
cs
in
cs
(D
CNJ •>,
cs
CM\
M-
•'“s»Jij
UJ
<Ia -
o
_i
CL
M
ccr
■D
■Q
0
0
cc
tf) r&2JMil^ gSPlUl -j,p©
0
E
0
CMw X
M-s
if
O)
c
0
(ft
CO ffi ' mil ’s;;L-'. SKt^-iSs?Si;r^ 'l JW ai
Ll PROJECT TITLE
LOCATION
CITY OF
Zo life'- *A, ^ MAP
•» SCOnSDALE
CO mm DEPT. S.C. I DRAWN IDATE I SCALE I SHT.
LU Q CPM RAH I 11/26 1 NTS I 1 OF 1

IGA 26-00011906-1
ADOT CAR No.: IGA 26- 0011906-1
AG Contract No.: P0012026000689
City Contract No.:
Project Location/Name: Thomas Road;
56th Street- 74th Street
Type of Work; System Preservation
Federal-aid No.: SCT-0(248) T
ADOT Project No.: T0776 OID OIR OIC
TIP/STIP No.: SCT26-520D
ALN: 20.205-Highway Planning and
Construction
Budget Source Item No.: 105783
City Contract No.: 2026-172-COS
INTERGOVERNMENTAL AGREEMENT
BETWEEN
THE STATE OF ARIZONA
AND
CITY OF SCOTTSDALE
THIS AGREEMENT ("Agreement") is entered into this date. ,pursuant
to the Arizona Revised Statutes {"A.R.S.") §§ 11-951 through 11-954, as amended, between the
STATE OF ARIZONA, acting by and through its DEPARTMENT OF TRANSPORTATION (the "State" or
"ADOT") and the CITY OF SCOTTSDALE, acting by and through its MAYOR and CITY COUNCIL (the
"CITY" or "Local Agenc/’). The State and the Local Agency are each individually referred to as a
"Party" and are collectively referred to as the "Parties."
1. RECITALS
1. The State is empowered by A.R.S. § 28-401 to enter into this Agreement and has delegated
to the undersigned the authority to execute this Agreement on behalf of the State.
2. The Local Agency is empowered by A.R.S. § 48-572 to enter into this Agreement and has by
resolution, if required, a copy of which is attached and made a part of, resolved to enter Into
this Agreement and has authorized the undersigned to execute this Agreement on behalf of
the Local Agency.
3. The work/improvements proposed under this Agreement consists of pavement
reconstruction at Thomas Road to Scottsdale Road to 56**' Street and a micro seal from 74"’
Street to Scottsdale Road, (the "Project"). The Project cost, shown in Exhibit A, is estimated
at $24,447,284, which includes federal aid and the Local Agency's match. The Local Agency
will administer the design at their own cost and the State will review all plans managed by
the Local Agency to ensure State and federal compliance. The State advertise, bid and
award, and administer the construction phase of the Project. The Local Agency will perform
the necessary right of way activities for the Project, under the stewardship and oversight of
ADOT, and submit eligible expended right of way costs to the State for reimbursement;
eligible right of way reimbursement will not exceed $245,000.
Page 1 of 12
ATTACHMENT 3

IGA 26-00011906-1
4. The interest of the State in this Project is the acquisition of federal funds for the use and
benefit of the Local Agency and authorization of such federal funds for the Project pursuant
to federal law and regulations. The State shall be the designated agent for the Local Agency
for the Project, if the Project is approved by Federal Highway Administration (FHWA) and
funds for the Project are available.
5. The foregoing Recitals and all Exhibits referred to herein and attached shall be incorporated
into this Agreement.
In consideration of the mutual terms expressed herein, the Parties agree as foliows:
II. SCOPE OF WORK
1. The Parties agree:
a. The Project will be completed, accepted, and paid for in accordance with the
requirements of the Project plans and specifications.
b. The final cost estimate may exceed the initial estimate identified in Exhibit A, and in
such case, the Local Agency is responsible for and agrees to pay, the difference prior to
bid advertisement.
c. The final Project amount may exceed the initial estimate(s) identified in Exhibit A, and
in such case, the Local Agency is responsible for, and agrees to pay, any and all actual
costs exceeding the initial estimate. If the final Project amount is less than the initial
estimate, the difference between the final bid amount and the initial estimate will be de-
obligated or otherwise released from the Project. De-obligated federal aid will be
returned to the Maricopa County Association of Governments. The Local Agency
acknowledges It remains responsible for actual costs and agrees to pay according to the
terms of this Agreement.
2. The State will:
a. Execute this Agreement, and if the Project is approved by FHWA and funds for the
Project are available, be the Local Agency’s designated agent for the Project.
b. After this Agreement is executed, and prior to performing or authorizing any work,
invoice the Local Agency for the Local Agency's share of the initial Project Development
Administration (PDA) costs, estimated at $9,000. If PDA costs exceed the estimate
during the review of design, notify the Local Agency, obtain concurrence prior to
continuing with the review of design, and invoice as determined by ADOT and the Local
Agency for additional costs to complete PDA for the Project. After the Project costs are
finalized, invoice or reimburse the Local Agency for the difference between actual costs
and the amount the Local Agency has paid for PDA.
Page 2 of 12

IGA 26-00011906-1
c. After receipt of the PDA costs, review design plans, specifications, cost estimates and
other such documents required for the construction bidding and construction of the
Project, including scoping/design plans and documents required by FHWA to qualify
projects for and to receive federal funds; provide design review comments to the Local
Agency as appropriate.
d. Within 30 days of receipt, review, and approval of invoice(s) and documentation of
payment for right of way acquisition, reimburse the Local Agency for eligible costs
incurred, less the Local Agency's applicable pro-rata match in an amount not to exceed
$245,000, the federal-aid approved and programmed for the Project.
e. After completion of design review and prior to bid advertisement, invoice the Local
Agency for the actual PDA costs, as applicable, and the Local Agency’s share of the
Project construction costs, estimated at $7,334,185. After the Project costs for
construction are finalized, the State will either invoice or reimburse the Local Agency
for the difference between estimated and actual costs. De-obligate or otherwise release
any remaining federal funds from the scoping/design phase of the Project.
f. After receipt of the actual PDA costs, if applicable, and the Local Agency’s estimated
share of the Project construction costs, including the difference between the final and
the initial construction cost estimates, if applicable, submit all required documentation
to FHWA with the recommendation that the maximum federal funds programnied for
construction of this Project be approved. Should costs exceed the maximum federal
funds available, it is understood and agreed that the Local Agency will be responsible
for any overage.
g. After receipt of FHWA authorization, proceed to advertise for, receive and open bids,
award and enter into a contract with the firm for the construction of the Project. If the
bid amounts exceed the construction cost estimate, obtain the Local Agency’s
concurrence and invoice the Local Agency for the difference between the construction
cost estimate and thie bid amount prior to awarding the contract.
h. Notify the Local Agency of completion and final acceptance of the Project; coordinate
with the Local Agency and turn over full responsibility of the Project improvements,
i. Not be obligated to maintain the Project, should the Local Agency fail to budget or
provide for proper and perpetual maintenance as set forth in this Agreement.
3. The Local Agency will:
a. Designate the State as the Local Agency’s authorized agent for the Project.
b. Within 30 days of receipt of an invoice from the State, pay the initial PDA costs,
estimated at $9,000. Agree to be responsible for actual PDA costs, if during the review of
design, PDA costs exceed the initial estimate. Be responsible for the difference between
the estimated and actual PDA arid design costs of the Project.
c. Prepare and provide design plans, specifications, cost estimates and other such
documents required for the construction bidding and construction of the Project,
Page 3 of 112

IGA 26-00011906-1
including scoping/design plans and documents required by FHWA to qualify projects
for and to receive federal funds; incorporate design review comments from the State, as
appropriate.
d. Enter into an agreement with the design consultant which states that the design
consultant will provide professional post-design services as required and requested
throughout and at completion of the construction phase of the Project. After final
acceptance of the Project, provide an electronic version of the record drawings to the
ADOT Project Manager.
e. Coordinate with the State as required for right of way acquisition activities. Perform all
activities required for acquisition of right of way and submit an invoice(s) on ADOT’s
Progress Payment Report Form, Exhibit B, attached and made part of this Agreement,
providing all back-up documentation, to the State for review and approval, of eligible
costs incurred by the Local Agency for acquisition of right of way for the Project, less the
Local Agency's applicable pro-rata match, not to exceed the total federal-aid
programmed amount of $245,000. Any costs incurred prior to the date of federal funds
authorization are not eligible for reimbursement.
f. After completion of design, within 30 days of receipt of an invoice from the State and
prior to bid advertisement, pay to the State any outstanding PDA costs, the Local
Agency's share of the Project construction costs, estimated at $7,334,185, and if
applicable, the difference between the final and initial construction cost estimates. Be
responsible for and pay the difference between the estimated construction costand
Project bid amount prior to award. After Project completion, be responsible for and pay
any outstanding Project costs, within 30 days of receipt of an Invoice.
g. Be responsible for all costs incurred in performing and accomplishing the work as set
forth under this Agreement, that are not covered by federal funding. Should costs be
deemed ineligible or exceed the maximum federal funds available, it is understood and
agreed that the Local Agency is responsible for these costs; payment for these costs
shall be made within 30 days of receipt of an invoice from the State.
h. Certify that all necessary rights of way have been or will be acquired prior to
advertisement for bid and also certify that all obstructions or unauthorized
encroachments of whatever nature, either above or below the surface of the Project
area, shall be removed from the proposed right of way, or will be removed prior to the
start of construction, in accordance with The Uniform Relocation Assistance and Real
Property Acquisition Policies Act of 1970 as amended; 49 CFR 24.102 Basic Acquisition
Policies; 49 CFR 24.4 Assurances, Monitoring and Corrective Action, parts (a) & (b) and
ADOT Right of Way Procedures Manual: 8.02 Responsibilities, 8.03 Prime Functions,
9.06 Monitoring Process and 9.07 Certification of Compliance. Coordinate with the
appropriate State’s Right of Way personnel during any right of way process performed
by the Local Agency, if applicable.
i. As applicable, the Local Agency shall certify that it has adequate resources to discharge
the Local Agency’s real property related responsibilities and ensures that Its Title 23-
funded projects are carried out using the FHWA approved and certified ADOT Right of
Way Procedures Manual and that it will comply with current FHWA requirements
whether or not the requirements are included in the FHWA approved ADOT Right of
Page 4 of 12

IGA 26-00011906-1
Way Procedures Manual (23 CFR 710.201). Additionally, the Local Agency shall certify
that all real estate related activities requiring licensure are performed by licensed
individuals as defined by the Arizona Department of Real Estate (A.R.S. §§ 32-2121 &
32-2122).
j. Not permit or allow any encroachments on or private use of the right of way, except
those authorized by permit. In the event of any unauthorized encroachment or
improper use, the Local Agency shall take all necessary steps to remove or prevent any
such encroachment or use. Provide a copy of encroachment permits Issued within the
Project limits to the State.
k. Automatically grant to the State, by execution of this Agreement, its agents and/or
contractors, without cost, the temporary right to enter the Local Agency’s rights of way,
as required, to conduct any and all construction and preconstruction related activities
for the Project, on, to and over said Local Agency’s rights of way. This temporary right
will expire with completion of the Project.
l. Investigate and document utilities within the Project limits; submit findings to ADOT
determining prior rights or no prior rights; approve a location within the final right of
way to re-establish the prior rights location for those utilities with prior rights.
m. Be obligated to incur any expenditure should unforeseen conditions or circumstances
increase Project costs. Be responsible for the cost of any Local Agency requested
changes to the scope of work of the Project, such changes will require State and FHWA
approval. Be responsible for any contractor claims for additional compensation caused
by Project delay attributable to the Local Agency. Payment for these costs will be made
to the State within 30 days of receipt of an invoice from the State.
n. After completion and final acceptance of the Project, agree to maintain and assume full
responsibility of the Project and all Project components.
111. MISCEI.LANEOIIS PROVISIONS
1. Effective Date. This Agreement shall become effective upon signing and dating of all
Parties.
2. Amendments. Any change or modification to the Project will only occur with the mutual
written consent of both Parties.
3. Duration. The terms, conditions and provisions of this Agreement shall remain in full
force and effect until completion of the Project and all related deposits and/or
reimbursements are made. Any and all obligations of maintenance hereunder shall
remain perpetual and shall survive any termination hereof and the assignment or
assumption of this Agreement or the Project by another competent jurisdiction or
entity.
4. Cancellation. This Agreement may be canceled at any time up to 30 days before the
award of the Project contract, so long as the canceling Party provides at least 30 days'
prior written notice to the other Party. It is understood and agreed that, in the event the
Page 5 of 12

IGA 26-00011906-1
Local Agency terminates this Agreement, the Local Agency shall be responsible for all
costs incurred by the State up to the time of termination. It is further understood and
agreed that in the event the Local Agency terminates this Agreement, the State shall in
no way be obligated to complete or maintain the Project.
5. Indemnification. The Local Agency shall indemnify, defend, and hold harmless the State,
any of its departments, agencies, boards, commissions, officers or employees
[collectively referred to in this paragraph as the "State") from any and all claims,
demands, suits, actions, proceedings, loss, cost and damages of every kind and
description, including reasonable attorneys' fees and/or litigation expenses (collectively
referred to in this paragraph as the "Claims"), which may be brought or made against or
incurred by the State on account of loss of or damage to any property or for injuries to
or death of any person, to the extent caused by, arising out of, or contributed to, by
reasons of any alleged act, omission, professional error, fault, mistake, or negligence of
the Local Agency, its employees, officers, directors, agents, representatives, or
contractors, their employees, agents, or representatives in connection with or incident
to the performance of this Agreement. The Local Agency's obligations under this
paragraph shall not extend to any Claims to the extent caused by the negligence of the
State, except the obligation does apply to any negligence of the Local Agency which may
be legally imputed to the State by virtue of the State's ownership or possession of land.
The Local Agency's obligations under this paragraph shall survive the termination of
this Agreement.
6. Third-Party Indemnification. The State shall include Section 107.13 of the 2021 version
of the Arizona Department of Transportation Standard Specifications for Road and
Bridge Construction, incorporated into this Agreement by reference, in the State's
contract with any and all contractors, of which the Local Agency shall be specifically
named as a third-party beneficiary. This provision may not be amended without the
approval of the Local Agency.
7. Programmed Federal Funds. The cost of scoping, construction, and construction
engineering work under this Agreement is to be covered by the federal funds
programmed for this Project, up to the maximum available. The Local Agency
acknowledges that actual Project costs may exceed the maximum available amount of
federal funds, or that certain costs may not be accepted by FHWA as eligible for federal
funds. Therefore, the Local Agency agrees to pay the difference between actual costs of
the Project and the federal funds received,
8. Termination of Federal Funding. Should the federal funding related to this Project be
terminated or reduced by the federal government, or Congress rescinds, fails to renew,
or otherwise reduces apportionments or obligation authority, the State shall in no way
be obligated for funding or liable for any past, current or future expenses under this
Agreement.
9. Indirect Costs. The cost of the Project under this Agreement includes indirect costs
approved by FHWA, as applicable.
10. Federal Funding Accountability and Transparency Act. The Parties warrant compliance
with the Federal Funding Accountability and Transparency Act of 2006 and associated
2008 Amendments (the "Act"). Additionally, in a timely manner, the Local Agency will
Page 6 of 12

IGA 26-00011906-1
provide information that is requested by the State to enable the State to comply with the
requirements of the Act, as may be applicable.
11. Single Audit. The Local Agency acknowledges compliance with federal laws and
. regulations and may be subject to the CODE OF FEDERAL REGULATIONS/TITLE 2. PART
200 (also known as The Uniform Grant Guidance). Entities that expend $1,000,000 or
more (on or after 10/01/24) of federal assistance (federal funds, federal grants, or
federal awards) must comply by having an independent audit in accordance with 2 CFR
Part200 Subpart F (§§200.500 through 200.521).
12. Governing Law. This Agreement shall be governed by and construed in accordance with
Arizona laws.
13. Conflicts of Interest. This Agreement may be canceled in accordance with A.R.S. § 38-
511.
14. Inspection and Audit. The Local Agency shall retain all books, accounts, reports, files and
other records relating to this Agreement which shall be subject at all reasonable times
to inspection and audit by the State for five years after completion of the Project. Such
records shall be produced by the Local Agency, electronically or at the State office as set
forth in this Agreement, at the request of ADOT.
15. Title VI. The Local Agency acknowledges and will comply with Title VI of the Civil Rights
Act of 1964.
16. Non-Di.scrimination. This Agreement is subject to all applicable provisions of the
Americans with Disabilities Act (Public Law 101-336,42 U.S.C. 12101-12213) and all
applicable federal regulations under the Act, including 28 CFR Parts 35 and 36. The
Parties to this Agreement shall comply with Executive Order Number 2009-09, as
amended by Executive Order 2023-01, issued by the Governor of the State of Arizona
and incorporated In this Agreement by reference regarding "Non-Discrimination."
17. Non-Availability of Funds. Every obligation of the State under this Agreement is
conditioned upon the availability of funds appropriated or allocated for the fulfillment
of such obligations. If funds are not allocated and available for the continuance of this
Agreement, this Agreement may be terminated by the State at the end of the period for
which the funds are available. No liability shall accrue to the State in the event this
provision is exercised, and the State shall not be obligated or liable for any future
payments as a result of termination under this paragraph.
18. Arbitration. I n the event of any controversy, which may arise out of this Agreement, the
Parties agree to abide by arbitration as is set forth for public works contracts if required
by A.R.S.§ 12-1518.
19. E-Verify. The Parties shall comply with the applicable requirements of A.R.S. § 41-4401.
20. Contractor Certification.s. The Parties shall certify that all contractors comply with the
applicable requirements of A,R.S. §§ 35-393.01 and 35-394.
21. Other Applicable Laws. The Parties shall comply with all applicable laws, rules,
regulations and Ordinances, as may be pended.
PEage'7/dFjl2

IGA 26-00011906-1
22. Notice.s. All notices or demands upon any Party to this Agreement shall be in writing
and shall be delivered electronically, in person, or sent by mail, addressed as follows:
For Agreement Administration: City of Scottsdale
Arizona Department of Transportation Attn: Derek Rogers
Joint Project Agreement Group 7447 E. Indian School Road, Ste 205
205 S. 17>h Avenue, Mail Drop 637E Scottsdale, AZ 85251
Phoenix, AZ 85007 480.312.2308
|PABranch@azdot.gov derrogers@scottsdaleaz.gov
City of Scottsdale
Attn: Susan Conklu
7447 E. Indian School Road, Ste 205
Scottsdale, AZ 85251
480.312.2308
sconklu@scottsdaleaz.gov
For Project Administration;
Arizona Department of Transportation City of Scottsdale
Project Management Group Attn: Derek Rogers
205 S. IZ'h Avenue, Mail Drop 614E 7447 E. Indian School Road, Ste 205
Phoenix, AZ 85007 Scottsdale, AZ 85251
PMG@azdot.eov 480.312.2308
derrogers@scottsdaleaz.gov
For Financial Administration:
Arizona Department of Transportation City of Scottsdale
Project Management Group Attn: Susan Conklu
205 S. 17'*' Avenue, Mail Drop 614E 7447 E. Indian School Road, Ste 205
Phoenix, AZ 85007 Scottsdale, AZ 85251
PMG@azdot.eov 480.312.2308
scnnklu@.scottsdaleaz.gov
23. Revisions to Contacts. Any revisions to the names and addresses above may be updated
administratively by either Party with written notice to the other Party.
24. Legal Counsel Approval. In accordance with A.R.S. § 11-952 (D), the written
determination of each Party's legal counsel providing that the Parties are authorized
under the laws of this State to enter into this Agreement and that the Agreement is in
proper form as set forth below.
25. Electronic Signatures. This Agreement may be signed in an electronic format including
DocuSign.
(Signatures begin on the next page)
Page 8 of 12

IGA 26-00011906-1
IN WITNESS WHEREOF, the Parties have executed this Agreement to be effective upon the full
completion of signing and dating by all Parties to this Agreement.
CITY OF SCOTTSDALE
By. Date.
LISA BOROWSKY
Mayor
ATTEST:
By. .Date.
BEN LANE
City Clerk
1 have reviewed the above referenced Intergovernmental Agreement between the State of
Arizona, acting by and through its Department of Transportation, and the City of Scottsdale, an
agreement among public agencies which, has been reviewed pursuant to A.R.S. §§ 11-951
through 11-954 and A.R.S. § 48-572 and declare this Agreement to be in proper form and
within the powers and authority granted to the City under the laws of the State of Arizona.
No opinion is expressed as to the authority of the State to enter into this Agreement.
Approved as to Form:
By nate H/^j^QZjQ
Luis E. Santaella, City Attorney
By: Lindsay Hampshire, Assistant City Attorney
Page 9 of 12

IGA 26-00011906-1
By. Date
MATTMOUL,PE
Project Delivery and Operations
Division Director
This Agreement between public agencies, the State of Arizona and City of Scottsdale has been
reviewed pursuant to A.R.S. §§ 11-951 through 11-954 and A.R.S. § 28-401, by the
undersigned Assistant Attorney General who has determined that it is in the proper form and
is within the powers and authority granted to the State of Arizona. No opinion is expressed as
to the authority of the remaining Parties, other than the State or its agencies, to enter into said
Agreement.
By. -Date.
Assistant Attorney General
Page 10 of 12

IGA 26-00011906-1
EXHIBIT A
Cost Estimate
T0776 01D/ OIR/OIC
The Project costs are estimated as follows: *
ADQT Project Development Administration (PDAl Cost, non-federal-aid:
Federal-aid funds @ 94.3% $ 21,000
Local Agency's match @ 5.7% 1,269
Local Agency's costs @ 100% 7,731
Subtotal - PDA $30,000
ROW Acquisition: **
Federal-aid funds @ 94.3% $ 245,000
Local Agency's match @ 5.7% 14,809
Local Agency's costs @ 100% 110,191
Subtotal - ROW Acquisition $370,000
Construction***;
Federal-aid funds @ 94.3% $17,113,099
Local Agency's match @ 5.7% 1,034,408
Local Agency's costs @ 100% 6,299,777
Subtotal - Construction $ 24,447,284
Estimated TOTAL Project Cost $ 24,847,284
Total Estimated Local Agency Funds $ 7,468,185
Total Federal Funds $ 17,379,099
* The federal funds listed In the agreement represent a standard 94.3 percent pro rata. MAG
policies require a maximum federal contribution of 70 percent. The 100 percent local funds
listed satisfy the additional match requirements
** The Local Agency will complete the ROW Acquisition at its own cost, as a result ADOT will not
invoice the Local Agency for the match or for their 100% local cost pertaining to the ROW
Acquisition
Page 11 of 12

IGA 26-00011906-1
***(Includes a minimum 15% construction engineering [CE) and administration cost (this
percentage is subject to change, any change will require concurrence from the Local Agency)
and 5% Project contingencies)
Page 12 of 12