3205018D2-CON-FELIX CONSTRUCTION COMPANY-WELLHEAD TREATMENT WELL 10.PDF

City of Tempe — Regular City Council Meeting (2026-01-08)

View PDF Meeting page

Extracted text (via pymupdf) 132548 characters
1 
 
PUBLIC WORKS DEPARTMENT 
DIVISION OF ENGINEERING 
 
CONTRACT FOR CONSTRUCTION MANAGER AT RISK 
PRE-CONSTRUCTION PHASE SERVICES 
 
 
This Contract is made and entered into this       8th       day of         January           2026, by and 
between the City of Tempe, an Arizona municipal corporation (“City” or “Owner”), and Felix 
Construction Company, Inc., an Arizona corporation, hereinafter designated the (“Construction 
Manager at Risk” or “CMAR”). 
 
A. 
WHEREAS, City desires to construct improvements to be located at 2126 E. Southern 
Avenue in Tempe, Arizona, Maricopa County, Arizona, more particularly described 
herein; and 
 
B. 
WHEREAS, City and CMAR have reached an agreement, memorialized in this Contract, 
whereby CMAR will perform pre-construction services for said improvements for payment 
by City as set forth herein; and 
 
C. 
WHEREAS, City engages CMAR to perform professional construction management pre-
construction phase services for a project known and described as Wellhead Treatment – 
Well 10, Project No. 3205018D2 (“Project”). 
 
NOW, THEREFORE, City and CMAR, in consideration of the mutual representations and 
covenants set forth herein, and for other good and valuable consideration, do mutually agree as 
follows: 
 
1. 
TERMS AND DEFINITIONS 
 
For purposes of this Contract, the following definitions apply: 
 
1.1. 
“Addendum” means a document issued by City that modifies or supersedes 
portions of the Contract as to additional specifications, forms, or other information. 
 
1.2. 
Allowances” means costs for additional quantities and or additional Work that City 
may require. 
 
1.3. 
“Alternate Systems Evaluations” means alternatives for design, means and 
methods, or other scope considerations that are evaluated by City using value 
engineering principles for a potential reduction of construction costs of a quality 
and functional Project per City requirements. 
 
1.4. 
“Amendment” means a written modification of the terms and conditions of this 
Contract signed by the parties to the Contract.

2 
 
1.5. 
“Business Day” means any calendar day except Saturdays, Sundays, and holidays 
observed by City. 
 
1.6. 
“Calendar Day” means every day shown on the calendar including Saturdays, 
Sundays, and holidays. 
 
1.7. 
“Change Order” means a written agreement entered into after the execution of 
the Contract signed by the City, CMAR, and other parties as may be required or 
appropriate, which makes changes to the scope of services or Deliverables and sets 
forth adjustment to the Contract amount and or adjustment to the CMAR time of 
completion. 
 
1.8. 
“CMAR” (“Construction Manager at Risk” or “Contractor”) means the 
person, firm, corporation, or other approved legal entity with whom City has 
contracted with to provide pre-construction services or construction services. 
 
1.9. 
“Construction Fee” means CMAR’s total administrative costs, including home 
office overhead if any, and profit, whether at CMAR’s principal or branch offices. 
 
1.10. “Construction Management Plan (CMP)” means a plan as defined in Section 7 
of this Contract. 
 
1.11. “Construction Manager Professional” means the person, firm, or corporation 
having a separate contract with the City working as the Owner’s representative to 
provide construction program management services for the Project. 
 
1.12. “Contract” means this written document, including all Addenda, Amendments, 
exhibits, attachments, and schedules attached thereto, signed by City and CMAR 
covering the pre-construction phase of the Project.  The Contract collectively 
represents the entire agreement between City and CMAR, and which supersedes 
any prior negotiations, representations, or agreements, either written or oral. 
 
1.13. “Cost Model” means a breakdown of the scope of the Project that is initially 
developed by CMAR during the conceptual design phase and based on information 
from the Project Team and CMAR’s records of similar Projects.  The model will 
evolve as the design progresses and be maintained by CMAR throughout the pre-
construction phase and will include any assumptions and clarifications made by 
CMAR.  Cost Model will support any cost estimates, Alternate Systems 
Evaluations, and eventually any GMP, when required by the Project Team.  Cost 
Model is subject to approval by City in its sole discretion.

3 
 
1.14. “Cost of the Work” means the direct costs necessarily incurred by CMAR in the 
proper performance of the Work.  Cost of the Work may include direct labor costs, 
subcontract costs, costs of materials and equipment incorporated in the completed 
Work, costs of other materials and equipment, temporary facilities, building permit 
fees, materials testing, and related items.  Cost of the Work shall not include 
CMAR’s Construction Fee, General Conditions Cost, taxes, bonds, or insurance 
costs. 
 
1.15.  “Data” means all information, whether written, electronic, or verbal, including 
plans, photographs, studies, investigations, audits, analyses, samples, reports, 
calculations, internal memos, meeting minutes, field notes, work product, 
proposals, correspondence, and any other similar documents or information 
prepared by or obtained by CMAR in the performance of this Contract. 
 
1.16. “Day(s)” means Calendar Day(s) unless otherwise expressly stated herein. 
 
1.17. “Deliverables” means the work products prepared by CMAR in performing the 
scope of Work described in the Contract.  The major Deliverables to be prepared 
and provided by CMAR during the pre-construction phase include but are not 
limited to:  Construction Management Plan, Cost Model, Project schedule of 
values, Alternative System Evaluations, procurement strategies and plans, cost 
estimates, construction market surveys, cash flow projections, GMP Proposal, 
Subcontractor bid packages, other items as indicated in this Contract or required 
by the Project Team, and, if applicable, Subcontractor procurement plan, 
Subcontractor Contracts, and Supplier Contracts. 
 
1.18. “Design Professional” means the qualified and licensed design person, firm, or 
corporation having a contract with City to furnish design services for this Project. 
 
1.19. “Drawings” means documents which visually represent the scope, extent, and 
character of the Work and which have been prepared or approved by the Design 
Professional and City.  Drawings include such documents that have reached a 
sufficient stage of completion and are released by the Engineer solely for the 
purposes of review and or use in performing constructability or biddability reviews 
and in preparing cost estimates (e.g., conceptual design Drawings, preliminary 
design Drawings, detailed design Drawings at 30%, 60%, 90%, or 100%, but 
excluding Shop Drawings and those marked “NOT FOR CONSTRUCTION”). 
 
1.20. “Effective Date of this Contract” means the date specified in this Contract on 
which the Contract becomes effective, but if no such date is specified, the date on 
which the last of the parties signs this Contract. 
 
1.21. “Engineer” means City Engineer acting directly or through its duly authorized 
representative.

4 
 
1.22. “Final Acceptance” means a written Final Acceptance of the Work, prepared by 
the Engineer, after all Work has been completed in accordance with the Contract 
and after inspection is completed by City. 
 
1.23. “General Condition Costs” means, other than expressly limited or excluded 
herein, the costs of CMAR during the construction phase, including but not limited 
to:  payroll costs for the project manager or construction manager (but not both) 
for work conducted at the site; payroll costs for the superintendent and full-time 
general foremen; payroll costs for management personnel resident and working on 
or off the site; workers not included as direct labor costs engaged in support 
functions (e.g., loading, unloading, clean-up); costs of offices and temporary 
facilities including office materials, office supplies, office equipment, minor 
expenses, utilities, fuel, sanitary facilities, and telephone services at the site; costs 
of consultants not in the direct employ of CMAR or Subcontractors; and fees for 
licenses. 
 
1.24. “Guaranteed Maximum Price (GMP)” means the sum of the maximum Cost of 
the Work, the Construction Fee, General Conditions Costs, any Allowances, taxes, 
bonds, and insurance. 
 
1.25. “Guaranteed Maximum Price (GMP) Proposal” means the offer of a proposal 
detailing the qualifications, assumptions, exclusions, value engineering, and any 
and all other requirements set forth in the scope of work for the design phase. 
 
1.26. “Laws and Regulations; Laws or Regulations” means any and all applicable 
laws, rules, regulations, ordinances, codes, and orders of any and all federal, state, 
and local governmental bodies, agencies, authorities, and courts having 
jurisdiction over the subject Project, site, and or any Work for this Contract. 
 
1.27. “MAG Specifications” means the Maricopa Association of Governments 
Uniform Standard Specifications for Public Works Construction – latest edition, 
Maricopa Association of Governments Uniform Standard Details for Public 
Works Construction – latest edition, and City of Tempe Supplement to the MAG 
Uniform Standard Details and Specifications for Public Works Construction – 
2014 thereto.  The definitions set forth in MAG Specifications shall govern unless 
expressly defined herein. 
 
1.28. “Notice to Proceed” means written notification from City to CMAR supplied 
after this fully executed Contract, establishing the date on which performance of 
CMAR’s obligations under this Contract shall begin. 
 
1.29. “Progress Payment” means the form accepted by City and used by CMAR in 
requesting Progress Payments or final payment for Work performed under this 
Contract, which includes supporting documentation as required by the Contract or 
City.

5 
 
1.30. “Project” means the total design and construction of improvements or services 
and or Work to be performed by CMAR. 
 
1.31. “Project Contingency” means a fund to cover non-general condition and other 
cost growth during the Project used by the City, or approved by the City for CMAR 
use, at City’s sole discretion.  The City will permit use of the Project Contingency, 
as the need may arise, and such Project Contingency monies may be utilized and 
are generally available for increased charges due to material costs and availability, 
production capacity, unforeseen Project circumstances or site conditions, City 
directed changes to the Work to be performed under the Contract including design 
revisions or additional scope requests made by the City or the Design Professional, 
or may be utilized to cover costs that have not been completely identified as trade 
specific scope on the GMP setting documents such as scope gap, coordination 
issues between trades, and missed scope during the bidding process, and may 
require further clarification or coordination.  The amount of Project Contingency 
will be set solely by City and will not be included in the GMP or GMP Proposal. 
 
1.32. “Project Manager” means Engineer or Construction Manager Professional. 
 
1.33. “Project Team” means a construction services unit consisting of a Design 
Professional, CMAR, Engineer, Construction Manager Professional and other 
persons who are responsible for making decisions regarding the Project, as 
approved by Engineer.  Any other persons to be included in the Project Team shall 
be identified in the preconstruction conference and are subject to approval by the 
Engineer. 
 
1.34. “Samples” means physical examples of materials, equipment, or workmanship 
representative of a part of the construction phase establishing the standards by 
which that portion of the construction phase work will be evaluated. 
 
1.35. “Shop Drawings” means all Drawings, diagrams, illustrations, schedules, and 
other Data or information specifically prepared or assembled by or for CMAR and 
submitted by CMAR to illustrate some portion of the Work. 
 
1.36. “Specifications” means the technical specifications for the construction phase of 
this Project consisting of written technical descriptions of materials, equipment, 
construction systems, standards, and workmanship as applied to the Work and 
administrative details applicable thereto. 
 
1.37. “Subcontractor” means an individual, firm, entity, or corporation other than 
CMAR’s employees, having a contract with CMAR to undertake to perform a part 
or portion of the pre-construction phase services or construction phase work at the 
site for which CMAR is responsible.  Subcontractors shall be selected through the 
Subcontractor bid process described in Section 13 of this Contract.

6 
 
1.38. “Substantial Completion” means when the construction services for the Work 
(or a specified part thereof) has progressed to the point where, within the sole 
discretion of the City and as evidenced by a letter of Substantial Completion, such 
construction services are sufficiently complete in accordance with the Contract 
Documents so that City can occupy and use the Project or a portion thereof for its 
intended purposes. 
 
1.39. “Supplier” means a manufacturer, fabricator, supplier, distributor, materialman, 
or vendor having a direct contract with CMAR or with any Subcontractor to 
furnish materials or equipment. 
 
1.40. “Total Float” means number of Calendar Days by which the design phase 
services or construction phase work or any part of the same may be delayed 
without necessarily extending a pertinent schedule milestone in the Project 
schedule, as mutually agreed to by City and CMAR. 
 
1.41. “Work” means any or all of the improvements as required by the Contract, and 
the construction, demolition, reconstruction, design, and or repair of all or any 
portion of such improvements, and all labor, services, incidental expenses, and 
material necessary or incidental thereto. 
 
2. 
SERVICES OF CMAR 
 
2.1. CMAR shall perform in accordance with the degree of care, skill, and judgment 
that a licensed contractor in Arizona would exercise under similar conditions.  
CMAR will, at all times, perform the required services consistent with sound and 
generally accepted construction and construction management. 
 
2.2. CMAR has assigned Zac Teal, or designee as its representative for this Contract.  
Prior written approval by City is required in the event CMAR requests a personnel 
substitution.  CMAR shall submit the qualifications of any proposed substituted 
personnel to City for approval. 
 
2.3. CMAR shall provide services for this Project as described in Exhibit “A”.  The 
pre-construction phase services being provided under this Contract will not alter 
any real property owned by City. 
 
3. 
TERM 
 
CMAR shall complete all pre-construction phase services per the terms of the Contract, 
free and clear from any and all claims, liens, and changes whatsoever, within 330 calendar 
days of the Notice to Proceed date issued by City.  In the event delays are experienced 
beyond the control of CMAR, the schedule may be revised as determined by City in its 
sole discretion.

7 
 
4. 
CMAR’S COMPENSATION 
 
4.1. 
The method of payment for this Contract is payment by installments.  Total 
compensation for the services performed shall not exceed $146,873.72, unless 
otherwise authorized by City.  This fee does not include an Allowance for 
reimbursable expenses. 
 
4.2. 
Payment for this Contract shall be based on the following Budget Schedule: 
 
Task Description 
Method 
Amount 
Professional Services 
Hourly not to Exceed 
$86,873.72 
 
 
 
 
Subtotal Task Amount: 
$86,873.72 
 
 
 
Allowances 
Method 
Amount 
Site Investigation and Potholing 
Allowance 
Not to Exceed 
$50,000.00 
Owner’s Allowance 
Not to Exceed 
$10,000.00 
 
 
 
 
Subtotal Allowances Amount: 
$60,000.00 
 
 
 
 
Total Compensation 
Not to Exceed: 
$146,873.72 
 
4.3. 
Payment requests shall be submitted by CMAR through the City’s PMWeb 
Software System.  Requests shall be uploaded to the PMWeb Software System at 
https://tempe-az.pmweb.com/pmweb/ using a login provided to CMAR by City 
and shall include all supporting documentation. 
 
4.4. 
If detailed invoice(s) and progress report(s) are approved by City, installment 
payments will be made within 30 Calendar Days after City’s approval. 
 
4.5. 
CMAR acknowledges and agrees that invoices shall be submitted to City for 
review and approval no more than 60 Calendar Days after Work or services have 
been performed.  City reserves the right to deny in whole or in part, payment to 
CMAR, including but not limited to, fees and expenses contained in any invoice 
not received by the City within 60 Calendar Days of the date such Work or services 
were performed.  This in no way shall be construed to waive or diminish City’s 
rights and remedies for otherwise withholding funds under Arizona law. 
 
4.6. 
If any service(s) executed by the CMAR is abandoned or suspended in whole or 
in part, for a period of more than 180 Calendar Days through no fault of the 
CMAR, the CMAR is to be paid for the services performed prior to the 
abandonment or suspension.

8 
 
5. 
CITY’S RESPONSIBILITIES 
 
5.1. 
City may designate a Construction Manager Professional for the term of this 
Contract.  When designated, the Construction Manager Professional has authority 
to administer this Contract and will monitor compliance with all terms and 
conditions stated herein.  All requests for information from or a decision by City 
on any aspect of the Work will be directed to the Construction Manager 
Professional. 
 
5.2. 
City will review Deliverables by CMAR, provide prompt responses to questions, 
and render decisions to minimize delay in the progress of CMAR’s Work.  City 
will keep CMAR advised concerning the progress of City’s review of the Work.  
CMAR agrees that City’s inspection, review, acceptance, and or approval of 
CMAR’s Work shall not relieve CMAR’s responsibility for errors or omissions of 
CMAR or any of its Subcontractors. 
 
5.3. 
Unless included in CMAR’s services as identified herein, City may furnish the 
following to the extent it is within the City’s possession or control: 
 
5.3.1. 
One copy of its maps, records, laboratory tests, survey ties and 
benchmarks, or other Data in its possession pertinent to the services.  
However, CMAR shall be solely responsible for researching the records, 
requesting specific Drawings or information, and independently 
verifying all Data. 
 
5.3.2. 
Available City Data on policies, regulations, standards, criteria, and 
studies relevant to the Project. 
 
5.3.3. 
Supply all necessary copies of programs and reports reasonably required 
by CMAR. 
 
5.3.4. 
Provide 
CMAR 
with 
adequate 
information 
regarding 
City’s 
requirements for the Project. 
 
5.3.5. 
Give prompt written notice to CMAR in the event City becomes aware 
of any default or defect in the Project or nonconformance with the 
Drawings and or Specifications. 
 
5.3.6. 
Notify CMAR of changes concerning or affecting budget allocations. 
 
5.3.7. 
Contract separately with one or more Design Professionals to provide 
architectural and or engineering design services for the Project.  The 
scope of the services for the Design Professional will be provided to 
CMAR.  CMAR shall have no right to limit or restrict any changes of 
such services that are otherwise mutually acceptable to City.

9 
 
5.3.8. 
Authorize the Project Manager to approve the Project budget and Project 
schedule, render decisions, and furnish information to CMAR. 
 
5.4. 
GIS Data Disclaimer.  CMAR UNDERSTANDS THE CITY OF TEMPE DOES 
NOT WARRANT THE ACCURACY, COMPLETENESS, CONDITION, 
SUITABILITY, PERFORMANCE, OR CURRENCY OF THE GIS DATA 
PROVIDED UNDER THIS CONTRACT.  AREAS DEPICTED BY GIS DATA 
ARE APPROXIMATE, AND NOT GUARANTEED TO BE ACCURATE TO 
STANDARDS FOR MAPPING, SURVEYING, OR ENGINEERING.  THIS 
DATA IS FOR ILLUSTRATIVE PURPOSES ONLY AND SHOULD NOT BE 
RELIED UPON FOR SITE-SPECIFIC PURPOSES.  THE DATA HEREIN IS 
SUBJECT TO CONSTANT CHANGE AND MAY NOT BE COMPLETE, 
ACCURATE, OR UP-TO-DATE.  THE CITY OF TEMPE IN NO WAY 
ASSUMES LIABILITY OR RESPONSIBILITY FOR ANY INCORRECT 
DATA OR ANY INFORMATION PROVIDED HEREIN.  THE CMAR 
ACKNOWLEDGES AND AGREES THAT THE CITY OF TEMPE ASSUMES 
NO LIABILITY FOR DAMAGES INCURRED DIRECTLY OR INDIRECTLY 
RESULTING 
FROM 
INCOMPLETE, 
INCORRECT, 
OR 
MISSING 
INFORMATION INCLUDING ANY DIRECT, INDIRECT, SPECIAL, OR 
CONSEQUENTIAL DAMAGES, HOWEVER CAUSED OR UNDER ANY 
THEORY OF LIABILITY, WHETHER IN TORT, CONTRACT, STRICT 
LIABILITY, OR OTHERWISE.  BY WAY OF THE SIGNATURE ON THIS 
CONTRACT, THE CMAR ASSUMES ALL LIABILITY FOR ANY AND 
ALL DEPENDENCE AND OR RELIANCE UPON THIS INFORMATION 
AND ASSUMES ALL RESPONSIBILITY RELATING THERETO.  ANY 
AND ALL EXPRESSED OR IMPLIED WARRANTIES, INCLUDING BUT 
NOT LIMITED TO IMPLIED WARRANTIES OF MERCHANTABILITY 
AND FITNESS FOR A PURPOSE, ARE SPECIFICALLY AND 
EXPRESSLY DISCLAIMED.  CMAR SHOULD NOT RELY UPON THE GIS 
DATA WITHOUT PROPER FIELD VERIFICATION FOR ANY PURPOSE. 
 
6. 
GENERAL SCOPE OF SERVICES 
 
6.1. 
Project Meetings.  CMAR shall attend Project Team meetings and all other 
meetings as directed by City. 
 
6.2. 
CMAR shall provide any and all services described herein in a proactive manner 
and consistent with the intent of the most current Drawings and Specifications.  
CMAR will promptly notify City in writing in the event that CMAR determines 
that any Drawings or Specifications are inappropriate for the Project and or cause 
changes in the scope of work. 
 
6.3. 
CMAR when requested by City or at its own initiative, if previously approved by 
City, will attend, make presentations, and participate as may be appropriate in 
public agency and or community meetings relevant to the Project.  CMAR will 
provide Drawings, schedule diagrams, budget charts, and other materials

10 
 
describing the Project when their use is required or appropriate in any public 
agency meetings, as determined by City. 
 
6.4. 
Description of Work.  CMAR shall provide services for this Project as described 
in Section 7 through Section 13 herein. 
 
7. 
CONSTRUCTION MANAGEMENT PLAN 
 
7.1. 
Prior to the start of construction the CMAR shall prepare a Construction 
Management Plan (CMP) which will detail, but not necessarily be limited to, 
CMAR’s determination concerning:  (a) Project milestone dates and the Project 
schedule including the broad sequencing of the pre-construction and construction 
of the Project; (b) alternate strategies for fast-tracking and or phasing the 
construction; (c) the number of separate sub-agreements to be awarded to 
Subcontractors and Suppliers for the Project construction; (d) permitting strategy; 
(e) safety and training programs; (f) construction quality control; (g) a 
commissioning program, plant start up and training, where applicable; (h) the 
Cost Model and basis of the model; and (i) a matrix summarizing each Project 
Team member’s responsibilities and roles. 
 
7.2. 
CMAR will add detail to its previous version of the CMP to keep it current 
throughout the pre-construction phase so that the CMP is ready for 
implementation at the start of the construction phase.  The update and revisions 
will take into account:  (a) revisions in Drawings and Specifications; (b) CMAR’s 
examination of the results of any additional investigatory reports of subsurface 
conditions, Drawings of physical conditions of existing surface and subsurface 
facilities, and documents depicting underground utilities placement and physical 
conditions whether obtained by City, Design Professional, or CMAR; (c) 
unresolved permitting issues, and significant issues, if any, pertaining to the 
acquisition of land and right-of-way; (d) the fast-tracking of any of the 
construction or other chosen construction delivery methods; (e) the requisite 
number of separate bidding documents to be advertised; (f) the status of the 
procurement of long-lead time equipment, if any, and or materials; and (g) 
funding issues identified by City. 
 
8. 
PROJECT SCHEDULE 
 
8.1. 
The fundamental purpose of the Project schedule is to identify, coordinate, and 
record the tasks and activities to be performed by all of the Project Team members 
and then for the Project Team to utilize the schedule as a basis for managing and 
monitoring compliance by all Project Team members with the requirements of 
the Project.  Each Project Team member is responsible for compliance with the 
schedule requirements of the Project.  CMAR will develop and maintain the 
Project schedule for the Project Team based on input received, consistent with 
the most recent revised and updated CMP.  The Project schedule will use the 
critical path method (CPM) technique unless City by written notice requires a

11 
 
different method.  CMAR will use scheduling software to develop a Project 
schedule acceptable to City presented in graphical and tabular reports as agreed 
upon by the Project Team.  If Project phasing as described below is required, the 
Project schedule will indicate milestone dates for the phases once determined.  
The Project schedule’s activities shall correlate with the schedule of values 
specified herein. 
 
8.2. 
CMAR shall include and integrate in the Project schedule the services and 
activities required of City, Design Professional, and CMAR, including all 
construction phase activities.  The Project schedule will detail all activities to the 
extent required to show:  (a) the coordination between conceptual design, 
preliminary design, and development of the construction documents (detailed 
design); (b) any separate long-lead procurements; (c) permitting issues; (d) any 
land and right-of-way acquisition; (e) bid packaging strategy and awards to 
Subcontractors and Suppliers; (f) major stages of construction; (g) start-up and 
commissioning; and (h) occupancy of the completed Work by City.  The Project 
schedule will include, but not be limited to, proposed activity sequences and 
durations for pre-construction, procurement, construction, and testing activities, 
milestone dates for actions and decisions by the Project Team, preparation and 
processing of Shop Drawings and Samples, delivery of materials or equipment 
requiring long-lead time procurement, if any, milestone dates for various 
construction phases, Total Float for all activities, relationships between the 
activities, City’s occupancy requirements showing portions of the Project having 
occupancy priority, and proposed dates for Substantial Completion and when the 
Work shall be ready for Final Acceptance. 
 
8.3. 
The Project schedule shall be updated and maintained by CMAR throughout the 
pre-construction phase such that it will not require major revisions at the start of 
the construction phase to incorporate CMAR’s plan for the performance of the 
construction phase work.  CMAR will provide updates and or revisions to the 
Project schedule for use by the Project Team, whenever required, but no less often 
than at the monthly Project Team meetings.  CMAR will include comparison of 
the progress achieved to that planned, any concerns regarding delays or potential 
delays, and any recommendations regarding mitigating actions. 
 
8.4. 
Project Phasing.  If phased construction is deemed appropriate and City approves, 
CMAR shall review the design and make recommendations regarding the phased 
issuance of construction documents to facilitate phased construction of the Work 
with the objective of reducing the Project schedule and or Cost of the Work.  
CMAR will take into consideration factors such as natural and practical lines of 
work severability, sequencing effectiveness, access and availability constraints, 
total time for completion, construction market conditions, labor and materials 
availability, and other factors pertinent to saving time and decreasing costs.

12 
 
9. 
DESIGN DOCUMENT REVIEWS 
 
9.1. 
CMAR shall periodically evaluate the availability of labor, materials, equipment, 
building systems, cost-sensitive aspects of the design, and other factors that may 
impact the Cost Model, GMP Proposal, and or the Project schedule and update 
each accordingly. 
 
9.2. 
CMAR will identify, in conjunction with the Project Team, any additional surface 
and subsurface investigations that are required to provide the necessary 
information for the construction of the Project.  After completion of pre-
construction phase services, CMAR may provide additional investigations to 
improve the adequacy and completeness of the site condition information and the 
Data made available with the construction documents.  CMAR will be responsible 
for the time and cost required to obtain such additional investigations, except if 
otherwise provided by specific additional services. 
 
9.3. 
CMAR will meet with the Project Team as required, to review designs during 
development.  CMAR will thoroughly familiarize itself with the evolving 
documents through conceptual design, preliminary design, and development of 
detailed design documents.  CMAR will proactively advise the Project Team and 
make recommendations on factors related to construction costs and concerns 
pertaining to the feasibility and practicality of any proposed means and methods, 
selected materials, equipment and building systems, and labor and material 
availability.  CMAR will advise the Project Team on proposed site improvements, 
excavation, and foundation considerations, as well as any concerns with respect 
to coordination of the Drawings and Specifications.  CMAR will recommend 
cost-effective alternatives. 
 
9.4. 
The CMAR will conduct constructability and biddability reviews of the Drawings 
and Specifications at the 30%, 60%, and 90% document submittals.  The reviews 
will attempt to identify all discrepancies and inconsistencies in the construction 
documents, especially those related to clarity, consistency, and coordination of 
Subcontractors and Suppliers. 
 
9.5. 
Constructability Reviews.  CMAR shall evaluate whether: (a) Drawings and 
Specifications are configured to enable efficient construction; (b) design elements 
are standardized; (c) construction efficiency is properly considered in the 
Drawings and Specifications; (d) module or pre-assembly design are prepared to 
facilitate fabrication, transport, and installation; (e) design promotes accessibility 
of personnel, material, and equipment, and facilitates construction under adverse 
weather conditions; (f) sequences of Work required by or inferable from the 
Drawings and Specifications are practicable; and (g) design has taken into 
consideration efficiency issues concerning access and entrance to the site, 
laydown and storage of materials, staging of site facilities, construction parking, 
and other similar pertinent issues.

13 
 
9.6. 
Biddability Reviews.  CMAR will check and cross-reference complementary 
Drawings and Specifications, and evaluate, among other things, whether: (a) 
Drawings and Specifications are sufficiently clear and detailed to minimize 
ambiguity and to reduce scope of interpretation discrepancies; (b) named 
materials and equipment are commercially available and are performing well in 
similar installations; (c) design provides as-built Data; (d) Specifications include 
alternatives in the event a requirement cannot be met in the field; and (e) Project 
is likely to be subject to differing site conditions considering the Data on 
subsurface conditions, physical conditions of existing surface and subsurface 
facilities, and physical conditions of underground utilities made available by the 
design or resulting from conditions inherent to work similar to the Work. 
 
9.7. 
The results of these reviews as set forth in Section 9 will be provided to City in 
formal written reports clearly identifying all discovered discrepancies and 
inconsistencies in the Drawings and Specifications, with notations and 
recommendations made on the documents.  If requested by City, CMAR will meet 
with Design Professional to discuss its findings and review the reports.  
Responsibility for updating the Drawings and Specifications will remain with 
Design Professional and not CMAR. 
 
9.8. 
Notification of Variance or Deficiency.  It is CMAR’s responsibility to assist the 
Design Professional in determining whether the construction documents are in 
accordance with applicable laws, statutes, ordinances, building codes, rules, and 
regulations as they relate to the performance of the Work.  If CMAR recognizes 
that portions of the construction documents as they relate to the performance of 
the Work are at variance with applicable laws, statutes, ordinances, building 
codes, rules or regulations, it will promptly notify the Design Professional and 
Project Manager in writing describing the apparent variance or deficiency. 
 
9.9. 
Alternate Systems Evaluations.  The Project Team will routinely identify and 
evaluate, using value engineering principles, any alternate systems, approaches 
and or design changes that have the potential to reduce Project costs while still 
delivering a quality and functional product.  If the Project Team agrees, CMAR 
in cooperation with Design Professional will perform a cost/benefit analysis of 
the alternatives and submit the analysis in writing to the Project Team.  The 
Project Team will decide which alternatives will be incorporated into the Project.  
CMAR will include the cost of the alternatives in the Cost Model and any GMP 
Proposal. 
 
10. 
COST MODEL, COST ESTIMATES, AND SCHEDULE OF VALUES 
 
10.1. 
As soon as practical during the conceptual design phase, CMAR shall review all 
available information regarding the design and scope of the Project and other 
pertinent factors.  CMAR will develop a Cost Model for review and approval by 
City.  Once approved by City, Cost Model will be continually updated and kept 
current to the design phase by CMAR until a final GMP for the entire Project is

14 
 
established.  Cost Model shall constitute the best representation of what the 
complete functional Project’s estimated construction costs.  CMAR will 
communicate in writing to the Project Team any assumptions made in preparing 
Cost Model.  Cost Model will support CMAR’s construction cost estimates and 
shall be broken down by Construction Standard Institute (CSI) Specification 
Divisions 1-16 and or otherwise, as required by City.  Cost Model shall also 
include Allowances set by the Project Team, including but not limited to:  (a) 
construction cost Project Contingency based on an agreed upon percentage of a 
total estimated construction cost; (b) Allowances for potential additional 
quantities and or additional work that City may require; and (c) any costs as 
required by City. 
 
10.2. 
After receipt of Design Professional’s most current documents from certain 
specified pre-construction phase milestones, CMAR will provide a detailed 
written report to the Project Team regarding the impact of and changes to Cost 
Model based on CMAR’s review of the design documents.  Design Professional 
and CMAR will reconcile any disagreements on Cost Model to arrive at an 
agreed upon estimate for the construction costs based on the scope of the Project 
through that specified pre-construction phase milestone.  The pre-construction 
phase milestones applicable to this paragraph are: detailed design completion at 
60%, 90%, and 100%.  If no consensus is reached, City will make the final 
determination.  If the Project Team requires additional updates of Cost Model 
beyond what is specified herein, CMAR will timely provide the requested 
information. 
 
10.3. 
If at any point Cost Model submitted to City exceeds previously accepted 
estimates agreed to by the Project Team or other key aspects of Cost Model or 
City’s Project budget, CMAR will make appropriate recommendations to City 
and Design Professional on means and methods, materials, and or other design 
elements to reduce the estimated construction costs, without altering City’s 
parameters such that it is equal to or less than the established Project Team’s 
target and or the Project budget. 
 
10.4. 
Upon completion of the 90% detailed design review, included with the 
associated report, CMAR will submit to City for approval, a schedule of values 
which complies with the following requirements.  The schedule of values shall 
be based on the 16 CSI Divisions and highlight significant variances from any 
previously submitted schedule of values.  The schedule of values will be directly 
related to the breakdowns reflected in the Project schedule and CMAR’s Cost 
Model.  In addition, the schedule of values will:  (a) detail unit prices and 
quantity take-off’s; (b) segregate Work covered by any changes to construction 
phase work already in progress, if any; (c) reconcile used and remaining 
Allowance; (d) detail all other Allowances and unit price work shown and 
specified in the detailed design documents; and (e) segregate unit costs, material 
and equipment costs, labor costs, General Conditions Costs, hourly labor rates, 
payment for pre-construction services, and total cost.  Labor costs therein will

15 
 
include employee benefits, payroll taxes, and other payroll burdens.  The total 
cost for any portion of the Work to be performed by Subcontractors will include 
Subcontractor overhead and profit. 
 
10.5. 
As required herein, CMAR shall submit a final schedule of values to City, based 
on the 100% detailed design set of Drawings and Specifications for the entire 
Project or any portion thereof, which final schedule of values will also be 
included in any proposed GMP(s). 
 
10.6. 
Upon request by City, CMAR shall submit, not more than once per month, a 
cash flow projection for the Project based on the current updated and revised 
Project schedule and the anticipated level of payments for CMAR during the 
pre-construction and construction phases.  In addition, if requested by City and 
based on information provided by City, CMAR will prepare a cash flow 
projection, not more than once per month, for the entire Project based on 
historical records for similar types of projects to assist City in the financing 
process. 
 
11. 
GUARANTEED MAXIMUM PRICE (GMP) PROPOSALS 
 
11.1. 
The proposed GMP for the entire Work (or portions thereof) will be presented 
in a format acceptable to City and consistent with City’s request for a GMP.  City 
may request a GMP for all or any portion of the Project at such time as the City 
and CMAR agree the Drawings and Specifications are sufficiently complete.  
Any GMP submitted by CMAR will be based on, and consistent with, the current 
updated and revised Cost Model at the time of the request, the associated 
estimates for construction costs, and include any clarifications or assumptions 
upon which the GMPs are based, which shall include, but not be limited to: 
 
(a) 
a list of the Drawings and Specifications, including all Addenda, which 
were used in preparation of the GMP Proposal; 
 
(b) 
a list of Allowances and a statement of their basis; 
 
(c) 
a list of the assumptions and clarifications made by CMAR in the 
preparation of the GMP Proposal to supplement the information contained 
in the Drawings and Specifications; 
 
(d) 
the Date of Substantial Completion or the Date of Final Acceptance upon 
which the proposed GMP is based, and the schedule of Work upon which 
the Date of Substantial Completion or the Date of Final Acceptance is 
based; 
 
(e) 
a schedule of applicable alternate prices.

16 
 
11.2. 
GMPs for the entire Project shall be the sum of the maximum Cost of the Work 
and include the Construction Fee, General Conditions Cost, taxes, insurance, and 
bonds.  CMAR guarantees to complete the Project at or less than the final 
approved GMP, and agrees that it will be solely responsible for the costs of 
completing the Work that exceed the GMP, as adjusted in accordance with this 
Contract. 
 
11.3. 
CMAR, in preparing any GMP, shall obtain from Design Professional three sets 
of signed, sealed, and dated construction documents, including all Addenda.  
CMAR will prepare its GMP requirements based on the most current completed 
construction documents at that time.  CMAR will provide one set of those 
documents to the Engineer, retain one set, and return the third set to Design 
Professional. 
 
11.4. 
An updated and revised Project schedule shall be included with any GMP that 
reflects the scope of work shown in the current set of design documents upon 
which the GMP is based.  Any such Project schedule updates and revisions will 
continue to comply with the requirements of Section 3 of this Contract. 
 
11.5. 
In the event CMAR elects to maintain Allowances within the GMP, the criteria 
for development of those Allowances must be approved by City.  In addition, 
the terms and conditions regarding use of Allowances during the construction 
phase will be established by City and reflected in the Contract for that phase of 
the Project. 
 
12. 
REVIEW AND APPROVAL OF GMP PROPOSAL(S) 
 
12.1. 
CMAR shall meet with the Project Manager or Design Professional to review 
any GMP Proposal and the written statement of its basis.  In the event the Project 
Manager or Design Professional discovers inconsistencies or inaccuracies in the 
information presented, CMAR shall make adjustments as necessary to the GMP 
Proposal. 
 
12.2. 
Upon receipt of any GMP Proposal from CMAR, City may submit the same 
documents that were used by CMAR in developing the GMP Proposal to an 
independent third party or to the Design Professional for review and verification.  
The third party or Design Professional shall develop an independent estimate of 
the Cost of the Work and review the Project schedule for the associated scope of 
the GMP Proposal. 
 
12.3. 
If CMAR GMP Proposal is greater than the independent third party or Design 
Professional’s estimate, City may require CMAR to reconfirm the GMP 
Proposal.  CMAR will review the independent third party’s or Design 
Professional’s estimate for the Cost of Work and present a report to City within 
seven Calendar Days of a written request by City identifying, explaining, and 
substantiating the differences.  CMAR may be requested to submit a revised

17 
 
GMP Proposal for consideration by City.  At that time City may do one of the 
following: 
 
12.3.1. Accept CMAR GMP Proposal in City’s sole discretion. 
 
12.3.2. Reject CMAR’s GMP Proposal.  City may terminate this Contract or 
elect not to enter into a Contract with CMAR for the construction phase 
of this Project; or, 
 
12.3.3. Take other actions deemed appropriate by City. 
 
12.4. 
If during the review and negotiation of the GMP Proposal, design changes are 
required and agreed upon, City will authorize and cause the Design Professional 
to revise the construction documents to the extent necessary to reflect the agreed 
upon assumptions and clarifications contained in the final approved GMP.  Such 
revised construction documents will be furnished to CMAR.  CMAR will 
promptly notify the Design Professional and City if any such revised 
construction documents are inconsistent with the agreed upon assumptions and 
clarifications. 
 
13. 
SUBCONTRACTOR AND SUPPLIER SELECTIONS 
 
13.1. CMAR shall select Subcontractors as set forth in A.R.S. § 34-603.  CMAR 
hereby warrants that it has complied with the applicable provisions of A.R.S. § 
34-603 in its selection of any Subcontractor and agrees to hold harmless and 
indemnify City for any statutory noncompliance provided the City has not 
required the use of and or selected a specific Subcontractor for CMAR to use. 
 
13.2. All Subcontractors doing Work in excess of $100,000 shall maintain, during the 
course of the Contract, health insurance for all employees working on this 
Project and will offer health insurance coverage to eligible dependents of such 
employees as required by City of Tempe Guidelines for Implementation of 
Health Insurance, and Resolution No. 2000.73. 
 
13.3. City reserves the right to request a completed bid tabulation from CMAR within 
a reasonable time after the closing of the bid opening proceedings. 
 
13.4. Prior to the submittal of the GMP Proposal, CMAR will deliver to City a written 
notice of intent to award, itemizing the Subcontractors and Suppliers selected by 
CMAR.  The notice of intent to award will detail: (a) for each Subcontractor 
agreement, the amount of the bid and the corresponding Subcontractor or 
Supplier; (b) the sum of bids received for all intended Subcontractor agreements; 
and (c) trade work that CMAR intends to self-perform, if any. 
 
13.5. CMAR will distribute Drawings and Specifications, and when appropriate, 
conduct a pre-bid conference with prospective Subcontractors.

18 
 
13.6. City will conduct a conference with CMAR and other Project Team members.  
At the conference, CMAR will:  (a) discuss City concerns relating to any 
proposed self-performed Work; (b) review CMAR’s proposed Contract price for 
the Work during the construction phase; (c) discuss the conditions, if any, under 
which City will agree to leave any portion of the remaining Project Contingency 
within the Contract price for the construction phase work; (d) resolve possible 
scheduling issues with the commencement date of the Contract for the 
construction phase work; (e) schedule the pre-construction conference; and, (f) 
discuss other matters as needed. 
 
14. 
INSURANCE 
 
Without limiting any of their obligations or liabilities, CMAR, at its own expense, shall 
purchase and maintain the minimum insurance specified below with companies duly 
licensed or otherwise approved by the State of Arizona, Department of Insurance, and with 
forms reasonably satisfactory to City.  Each insurer shall have a current A.M. Best 
Company, Inc., rating of not less than A-VII.  Use of alternative insurers requires prior 
approval from City. 
 
14.1. 
General Clauses. 
 
14.1.1. Negligent Acts or Omissions. All insurance policies shall apply to the 
negligent acts or omissions of CMAR, its officers, agents, employees, 
and for CMAR’s legal responsibility for the negligent acts or omissions 
of its consultants and anyone directly or indirectly under its control, 
supervision, or employ, or that of CMAR’s Subcontractors or 
subconsultants. 
 
14.1.2. Additional Insured.  The insurance coverage, except workers’ 
compensation and professional liability, required by this Contract, shall 
name City, its agents, representatives, directors, officials, and 
employees, as additional insured, and shall specify that insurance 
afforded CMAR shall be primary insurance, and that any self-insured 
retention and or insurance coverage carried by City or its employees 
shall be excess coverage, and not contributory coverage to that 
provided by CMAR.  This provision and the naming of the City as an 
additional insured shall in no way be construed as giving rise to the 
responsibility or liability of the City for applicable deductible amounts 
under such policy(s). 
 
14.1.3. Coverage Term.  All insurance required herein shall be maintained in 
full force and effect until the services required to be performed under 
the terms of this Contract are satisfactorily completed and formally 
accepted; failure to do so may constitute a material breach of this 
Contract, at the sole discretion of City.

19 
 
14.1.4. Primary Coverage.  CMAR’s insurance shall be primary insurance as 
respects City and any insurance or self-insurance maintained by City 
shall be in excess of CMAR’s insurance and shall not contribute to it. 
 
14.1.5. Claim Reporting.  CMAR shall not fail to comply with the claim 
reporting provisions of the policies or cause any breach of a policy 
warranty that would affect coverage afforded under the policy to 
protect City. 
 
14.1.6. Waiver.  The policies for workers’ compensation and general liability 
shall contain a waiver of transfer rights of recovery (subrogation) 
against City, its agents, representatives, directors, officers, and 
employees for any claims arising out of the work of CMAR. 
 
14.1.7. Deductible/Retention.  The policies may provide coverage which 
contains deductibles or self-insured retentions.  Such deductible or self-
insured retentions shall not be applicable with respect to the coverage 
provided to City under such policies.  CMAR shall be solely 
responsible for deductible or self-insured retentions and City may 
require CMAR to secure the payment of such deductible or self-insured 
retentions by a surety bond or an irrevocable and unconditional letter 
of credit. 
 
14.1.8. Policies and Endorsements.  City reserves the right to request and to 
receive, within ten Calendar Days, information on any or all of the 
above policies or endorsements. 
 
14.1.9. Certificates of Insurance.  Prior to commencing services under this 
Contract, CMAR shall furnish City with Certificates of Insurance or 
formal endorsements as required by the Contract issued by CMAR’s 
insurer(s), as evidence that policies providing the required coverages, 
conditions and limits required by this Contract are in full force and 
effect.  Such certificates shall identify this Contract number and shall 
provide for not less than 30 Calendar Days advance written notice by 
certified mail of cancellation or termination. 
 
14.1.10. Subconsultants and Subcontractors.  CMAR shall include all 
subconsultants and Subcontractors as insured under its policies. 
 
14.2. 
Workers’ Compensation. 
 
14.2.1. 
CMAR shall carry workers’ compensation insurance to cover 
obligations imposed by federal and state statutes having jurisdiction 
of CMAR employees engaged in the performance of the services and 
employer’s liability insurance of not less than $100,000 for each 
accident, $100,000 disease coverage for each employee, and $500,000 
disease policy limits.

20 
 
 
14.2.2. 
In case services are subcontracted, CMAR will require the 
Subcontractor to provide workers’ compensation and employer’s 
liability to at least the same extent as provided by CMAR. 
 
14.3. 
Automobile Liability.  CMAR shall carry commercial/business automobile 
liability insurance with a combined single limit for bodily injury and property 
damages of not less than $1,000,000 each occurrence, regarding any owned, 
hired, and non-owned vehicles assigned to or used in performance of CMAR’s 
services.  Coverage will be at least as broad as coverage Code 1 “any auto” 
(Insurance Service Office policy form CA 00 01 or any replacements thereof).  
Such coverage shall include coverage for loading and unloading hazards. 
 
14.4. Commercial General Liability. 
 
14.4.1. 
CMAR shall carry commercial general liability insurance with 
unimpaired limit of not less than $1,000,000 for each claim with a 
$2,000,000 general aggregate limit.  The general aggregate limit shall 
apply separately to the services under this Contract, or the general 
aggregate shall be twice the required per claim limit.  The policy shall 
be primary and include coverage for bodily injury including death, 
property damage, personal injury, products, completed operations 
and blanket contractual covering, but not limited to, the liability 
assumed under the indemnification provisions of this Contract, which 
coverage shall be at least as broad as Insurance Service Office policy 
form CG 00 01 or any replacement thereof. 
 
14.4.2. 
In the event the general liability insurance policy is written on a 
claims made basis, coverage shall extend for two years past 
completion and acceptance of the services as evidenced by annual 
certificates of insurance. 
 
14.4.3. 
Such policy shall contain a severability of interest provision (also 
known as cross-liability and separation of insured). 
 
14.5. Property Coverage.  CMAR shall purchase and maintain, in a company or 
companies lawfully authorized to do business in the jurisdiction in which the 
Project is located, property insurance written on a builders risk “all-risk” or 
equivalent policy form in the amount of the initial Contract sum, plus value of 
subsequent Contract modifications and cost of materials supplied or installed 
by others, comprising total value for the entire Project at the site on a 
replacement cost basis.  This insurance shall include interests of the City, the 
CMAR, Subcontractors and its subcontractors in the Project, and shall include 
insurance against the perils of fire and physical loss or damage including, 
without duplication of coverage, theft, vandalism, malicious mischief, 
collapse, earthquake, flood, windstorm, falsework, testing and startup, 
temporary buildings and debris removal, including demolition occasioned by

21 
 
enforcement of any applicable legal requirements and coverage for valuable 
papers. 
 
City and CMAR waive all rights against each other and against all 
Subcontractors, sub-Subcontractors, material Suppliers, and the Design 
Professional, for damages caused by fire or other perils covered by Builder’s 
Risk or any other property insurance, except such rights as they may have to 
the proceeds of such insurance.  Such insurance may be subject to an amount 
deductible from the sums otherwise payable thereunder and the burden of such 
deduction shall be borne by the CMAR.  The Owner or CMAR, as appropriate, 
shall require of the Design Professional, Design Professional’s consultants, 
separate contractors, if any, and the Subcontractors, sub-Subcontractors, 
agents, and employees of any of them, by appropriate agreements, written 
where legally required for validity, similar waivers each in favor of other 
parties enumerated herein. 
 
14.6. Health Insurance Requirements. 
 
All consultants and general contractors, who bid on projects or enter into 
public works contracts, in excess of $100,000 or the current Council approval 
contract limit in place at the time the contract is executed, with the City of 
Tempe, after January 1, 2001, are required to sign an affidavit in the form 
attached hereto. The general contractor shall be responsible for ensuring that 
the subcontractors comply with the health insurance requirements. 
 
Health insurance is required for all employees, except for those employees who 
work less than one hundred and twenty (120) days in any calendar year. A 
“workday” consists of any time within a twenty-four-hour period, regardless 
of number of hours, that the individual is paid. 
 
The level of health insurance provided shall be determined by each employer 
but should be no less than that provided by the Arizona Cost Containment 
Health System. 
 
All complaints concerning violations of the health insurance requirements shall 
be filed, in writing, with the Public Work's Department, within five (5) days 
from discovery of the violation. An administrative hearing will be held before 
the Public Works Director, and a written decision of findings will be provided 
to the parties to the hearing within ten (10) days thereafter. Appeal from the 
decision of the Public Works Director may be made within ten (10) days of the 
date of the decision by filing a notice of appeal in writing with the Public Works 
Department. If an appeal is timely filed, an administrative hearing will be held 
before an administrative hearing officer appointed by the City Manager. The 
decision of the administrative hearing officer shall be final.

22 
 
In the event of a finding of violation of the insurance provisions, the company 
in violation of the provision shall be barred from bidding on, or entering into, 
any public works contract with the City for a period of three (3) years. 
 
All consultants and contractors subject to the health insurance requirements 
shall post, in English and Spanish, notice of the health insurance requirements 
at the job site. Signs for posting will be provided by the City. 
 
15. 
PROJECT DOCUMENTS AND COPYRIGHTS 
 
15.1. City Ownership of Project Documents. All work products (electronically or 
manually generated) prepared in the performance of this Contract including but not 
limited to, plans, Drawings, Specifications, cost estimates, tracings, studies, design, 
analysis, CADD files, and related products, are the property of City and are to be 
delivered to City before the final payment is made to CMAR. Only if previously 
approved in writing by City, CMAR may retain originals and supply City with 
reproducible copies of the Work. 
 
15.2. Documents to Bear Seal.  When applicable and as required by law, CMAR and its 
Subcontractors will endorse by professional seal all plans, Works, and Deliverables 
prepared by them for this Contract. 
 
16. 
CONFLICT OF INTEREST 
 
16.1. CMAR agrees to disclose any financial or economic interest in the Project property, 
or any property affected by the Project, existing prior to the execution of this 
Contract.  Further, CMAR agrees to disclose any financial or economic interest 
with the Project property, or any property affected by the Project, if CMAR gains 
such interest during the course of this Contract.  Only if previously approved in 
writing by City, CMAR may retain originals and supply City with reproducible 
mylar copies of the Work. 
 
16.2. If CMAR gains financial or economic interest in the Project during the course of 
this Contract, this may be grounds for terminating this Contract at the sole 
discretion of City. 
 
16.3. CMAR shall not engage the services on this Contract of any present or former City 
employee who was involved as a decision maker in the selection or approval 
processes, or who negotiated or approved billings or Contract modifications for this 
Contract. 
 
16.4. To evaluate and avoid potential conflicts of interest, CMAR will provide written 
notice to City, as set forth in this section, of any Work or services performed by 
CMAR for third parties that may involve or be associated with any real property or 
personal property owned or leased by City.

23 
 
16.5. Actions considered to be adverse to City under this Contract include but are not 
limited to: 
 
16.5.1. Using Data as defined in the Contract, acquired in connection with this 
Contract, to assist a third-party pursuing administrative or judicial action 
against City. 
 
16.5.2. Testifying or providing evidence on behalf of any person in connection with 
an administrative or judicial action against City. 
 
16.5.3. Using Data to produce income for CMAR or its employees independently 
of performing the services under this Contract, without the prior written 
consent of City. 
 
16.6. CMAR represents that except for those persons, entities, and Projects previously 
identified in writing to City, the services to be performed by CMAR under this 
Contract are not expected to create an interest with any person, entity, or third-party 
Project that is or may be adverse to the interests of City. 
 
16.7. CMAR’s failure to provide a written notice and disclosure of the information as set 
forth in this section will constitute a material breach of this Contract. 
 
17. 
COVENANT AGAINST CONTINGENT FEES 
 
CMAR affirms that it has not employed or retained any company or person, other than a 
bona fide employee working for CMAR, to solicit or secure this Contract, and that it has 
not paid or agreed to pay any company or person, other than a bona fide employee, any 
fee, commission, percentage, brokerage fee, gift, or any other consideration contingent 
upon or resulting from the award or making of the Contract.  For breach or violation of this 
clause, City shall terminate this Contract or in its discretion may deduct from the Contract 
price or otherwise recover, the full amount of such fee, commission, percentage brokerage 
fee, gift, or contingent fee from CMAR. 
 
18. 
INDEMNIFICATION 
 
To the fullest extent permitted by law, CMAR shall indemnify and hold harmless City, its 
officers, and its employees, from liabilities, damages, losses, and costs, including 
reasonable attorney fees and court costs, to the extent caused by the negligence, 
recklessness, or intentional wrongful conduct of CMAR, its Subcontractors, design 
professionals, or other persons employed or used by CMAR in the performance of the 
Contract or subcontract.  Nothing in this section shall prohibit the requirement of insurance 
coverage that complies with this section, including the designation of any person as an 
additional insured on a general liability insurance policy or as a designated insured on an 
automobile liability policy.  The amount and type of insurance coverage requirement set 
forth herein will in no way be construed as limiting the scope of the indemnity in this 
paragraph.

24 
 
19. 
DISPUTE RESOLUTION 
 
In the event of a dispute between the parties regarding any provision of this Contract, a 
party’s performance of its obligations as stated in this Contract or any other matter 
governed by the terms of this Contract, the parties will meet in good faith to attempt to 
resolve the dispute.  If the parties fail to resolve the dispute, then City may pursue any and 
all remedies provided by law or in equity.  The exercise of any one of City’s remedies shall 
not preclude subsequent or concurrent exercise of further or additional remedies. 
 
20. 
ADDITIONAL SERVICES 
 
Additional services which are outside the scope of basic services contained in this Contract 
shall not be performed by CMAR without prior written authorization from City.  Additional 
services, when authorized by an agreement or an Amendment to this Contract shall be 
compensated for by a fee mutually agreed upon between City and CMAR. 
 
21. 
ALTERATION IN CHARACTER OF WORK 
 
In the event an alteration or modification in the character of Work or Deliverable results in 
a substantial change in this Contract, thereby materially increasing or decreasing the scope 
of services, costs of performance or Project schedule, the Work or Deliverable will 
nonetheless be performed as directed by City.  However, before any altered or modified 
Work begins, a Change Order or Amendment must be approved and executed by City, and 
executed by CMAR.  Such Change Order or Amendment will not be effective unless 
approved by City.  Additions to, modifications, or deletions from the Project provided 
herein may be made, and the compensation to be paid to CMAR may be adjusted by mutual 
agreement of the contracting parties.  No claim for extra Work done or materials furnished 
by CMAR will be allowed by City except as provided herein, nor will CMAR do any Work 
or furnish any material(s) not covered by this Contract unless such Work or material is 
previously authorized in writing by City.  Work or material(s) furnished by CMAR without 
such prior written authorization shall be at CMAR’s sole jeopardy, cost and expense, and 
CMAR hereby agrees that without prior written authorization no claim for compensation 
for such Work or materials furnished will be made. 
 
22. 
SUCCESSORS AND ASSIGNS 
 
City and the CMAR will each bind itself, and their partners, successors, assigns, and legal 
representatives to the other party to this Contract and to the partners, successors, assigns, 
and legal representatives of such other party in respect to all covenants of this Contract.  
Neither City nor the CMAR will assign, sublet, or transfer its interest in this Contract 
without the prior written consent of the other.  In no event will any contractual relation be 
created or be construed to be created as between any third party and City.

25 
 
23. 
COMPLETENESS AND ACCURACY OF CMAR’S WORK 
 
CMAR is solely responsible for the completeness and accuracy of all its reviews, reports, 
supporting Data, and other pre-construction phase Deliverables prepared or compiled 
pursuant to its obligations under this Contract, and will at its sole expense correct its Work 
or Deliverables.  Acceptance or approval of CMAR’s Work or Deliverables by City does 
not relieve or diminish CMAR’s responsibilities under the Contract nor does this 
requirement to correct the Work or Deliverable constitute a waiver of any claims or 
damages otherwise available in law or in equity to City. 
 
24. 
DISSEMINATION OF DATA 
 
24.1. The parties agree that all Data, including originals, images, and reproductions 
prepared by, obtained by, or transmitted to CMAR in connection with CMAR’s 
performance of this Contract is the sole property of City. 
 
24.2. CMAR shall not divulge Data to any third party without prior written consent of 
City.  CMAR will not use the Data for any purposes except to perform the services 
required under this Contract.  However, these prohibitions do not apply to the 
following Data, provided CMAR first provides the required notice to City: 
 
24.2.1. Data which were known to CMAR prior to its performance under this 
Contract unless such Data was acquired in connection with work 
performed for City; 
 
24.2.2. Data which was acquired by CMAR in its performance under this Contract 
and which was disclosed to CMAR by a third party, who to the best of 
CMAR’s knowledge and belief had the legal right to make such disclosure 
and CMAR is not otherwise required to hold such Data in confidence; or 
 
24.2.3. Data which is required to be disclosed by CMAR by law, regulation, or 
court order. 
 
24.3. In the event a third party requires or requests CMAR to disclose Data or any other 
information to which CMAR became privy as a result of any other contract with 
City, CMAR will first notify City as set forth in this section of the request or 
demand for such Data.  CMAR will timely give City sufficient facts such that City 
has a meaningful opportunity to either first give its consent or take such action that 
City may deem appropriate to protect such Data or other information from 
disclosure. 
 
24.4. CMAR, unless prohibited by law, within ten Calendar Days after completion of 
services for a third party on real or personal property owned or leased by City, will 
promptly deliver, as set forth in this section, a copy of all Work products and Data 
to City.  All Data will continue to be subject to the provisions of this section.

26 
 
24.5. CMAR assumes all liability for maintaining the Data in its possession and agrees 
to compensate and indemnify City if any of the provisions of this section are 
violated by CMAR, its employees, agents, authorized assigns, subconsultants, or 
Subcontractors.  A breach of this section shall be deemed to cause irreparable harm 
to City that justifies injunctive relief. 
 
25. 
PROJECT STAFFING 
 
25.1. Prior to the start of any Work or Deliverable under this Contract, and in response 
to City’s request for qualifications or subsequent fee proposals and revisions 
thereto, CMAR will submit to City an organizational chart for CMAR staff and 
Subcontractors and detailed resumes of key personnel involved in performing the 
services prescribed in the Contract.  Unless otherwise informed, City hereby 
acknowledges its acceptance of such personnel to perform such services under this 
Contract.  In the event CMAR desires to change such key personnel from 
performing such services under this Contract, CMAR will submit the qualifications 
of the proposed substituted personnel to City for prior approval.  Key personnel 
include, but are not limited to, principal-in-charge, Project manager, 
superintendent, Project director or those persons specifically identified to perform 
services of cost estimating, scheduling, value engineering, and procurement 
planning. 
 
25.2. CMAR will maintain an adequate number of competent and qualified persons to 
ensure acceptable and timely completion of the scope of services described in this 
Contract throughout the period of those services.  If City objects, with reasonable 
cause, to any of CMAR’s staff, CMAR will take prompt corrective action and, if 
required, remove such personnel from the Project and replace with other personnel. 
 
26. 
INDEPENDENT CONTRACTOR 
 
CMAR is and shall be an independent contractor and whatever measure of control City 
exercises over the Work or Deliverables pursuant to the Contract will be as to the results 
of the Work only.  No provision in this Contract will give or be construed as establishing 
an employer/employee relationship, partnership, or joint venture, between City and 
CMAR, or cause City to be responsible in any way for the debts or obligations of CMAR.  
CMAR must comply with all applicable laws and ordinances pertaining thereto. 
 
27. 
SUBCONTRACTORS 
 
Prior to beginning any Work or Deliverables, CMAR will furnish to City the names of all 
Subcontractors to be used on this Project.  This provision shall in no way be deemed to 
diminish CMAR’s responsibility for Subcontractor or impose liability upon City for the 
contracting with any Subcontractor.

27 
 
28. 
SECURE FACILITY ACCESS 
 
Contracts that call for work to be done in any of the City’s secure facilities are subject to 
the City’s Secure Facility Access Requirements, which are incorporated herein. 
 
29. 
LABOR 
 
CMAR agrees and covenants to use only licensed Subcontractors in the making and or 
installation of any and all repairs, alterations, improvements, or other work of CMAR on 
the Project.  CMAR shall be liable to City for any losses and liabilities associated with any 
violation of this provision, and the Contract shall immediately be terminated upon any 
violation hereof by CMAR. 
 
30. 
WITHHOLDING PAYMENT 
 
City, pursuant to and in accordance with A.R.S. § 34-221 et seq., as they may be amended 
from time to time, reserves the right to withhold funds from Progress Payments up to the 
amount equal to resolve claims City may have against CMAR, until such time as the 
settlement on those claims is reached. 
 
31. 
TERMINATION 
 
31.1. City and the CMAR hereby agree to the full performance of the covenants 
contained herein, except that in addition to MAG Specifications 108.11 and A.R.S. 
§ 38-511, City, at its sole discretion, may terminate this Contract for convenience 
or abandon any portion of the Project for which services have not been performed 
by the Contractor. 
 
31.2. In the event of such termination or abandonment, City will so notify the CMAR in 
writing, and the CMAR will immediately after receiving such notice discontinue 
advancing the Work specified under this Contract and mitigate the expenditure, if 
any, of costs resulting from such abandonment or termination. The CMAR shall 
deliver to City all Drawings, special provisions, field survey notes, reports, 
estimates, and any and all other documents or Work product generated by the 
CMAR under the Contract, entirely or partially completed, together with all unused 
materials supplied by City. 
 
31.3. If City terminates or abandons the Contract due to no fault of the Contractor, the 
CMAR will receive compensation in full for services satisfactorily performed to 
the date of such termination.  The fee will be paid in accordance with Section 4 of 
this Contract.  However, in no event will the fee exceed that set forth in Section 4 
or as amended in accordance with Paragraph 21, “Alteration in Character of Work”.  
City shall make final payment within 60 Calendar Days after the CMAR has 
delivered the last of the completed items and City has approved and determined the 
final fee.

28 
 
32. 
RECORDS/AUDIT 
 
32.1. Records of CMAR’s direct personnel payroll and reimbursable expenses pertaining 
to this Project and records of accounts between City and CMAR will be kept 
following generally accepted accounting principles, for a period of five years after 
completion of the Contract.  City, its authorized representative and or the 
appropriate federal agency, reserve the right to audit CMAR’s records to verify the 
accuracy and appropriateness of all pricing Data, including Data used to negotiate 
this Contract and any attendant Change Orders, for a period of five years after 
completion of this Contract.  City reserves the right to decrease Contract amount 
and or payments made on this Contract if, inter alia, upon audit of CMAR’s 
records, the audit discloses that CMAR has provided false, misleading, or 
inaccurate cost and or pricing Data. 
 
32.2. CMAR will include a provision in all of its agreements with subconsultants, 
Subcontractors, and Suppliers providing services under this Contract to ensure City, 
its authorized representative, and or the appropriate governmental agency, has 
access to the subconsultants’, Subcontractors’, and Suppliers’ records.  City 
reserves the right to decrease Contract amount and or payments made on this 
Contract if the above provision is not included in subconsultant, Subcontractor, and 
Supplier Contracts and one or more of those parties do not allow City to audit their 
records to verify the accuracy and appropriateness of pricing Data. 
 
33. 
NOTICES 
 
Unless otherwise provided herein, notices and or demands under this Contract shall be in 
writing and will be deemed to have been duly given and received either (a) on the date of 
service if personally served on the party to whom notice is to be given, or (b) on the third 
Business Day after the date of the postmark of deposit by first class United States mail, 
registered or certified, postage prepaid, and properly addressed as follows: 
 
To City: 
 
Mark A. Weber, P.E. 
Deputy Public Works Director/ 
City Engineer 
Public Works Department 
Engineering Division 
Mail Stop 0108 
31 E. 5th Street 
Tempe, Arizona 85281 
To CMAR: 
 
 
____________________________ 
(Printed Name of Signatory) 
Felix Construction Company, Inc. 
2530 S. 52nd Avenue 
Phoenix, Arizona 85043

29 
 
34. 
COMPLIANCE WITH STATE AND FEDERAL LAWS 
 
34.1. Lawful Presence in the United States.  Pursuant to A.R.S. § 1-502, any 
individual/sole proprietor who applies for local public benefits by signing this 
Contract shall also sign a sworn affidavit (Exhibit “B”) and present one of the 
documents listed on the affidavit to verify lawful presence in the United States.  
This Contract shall not be fully executed by the City if the individual/sole proprietor 
fails to sign the affidavit and present one of the listed documents. 
 
34.2. Specially Designated Nationals and Blocked Persons List.  CMAR represents and 
warrants to City that neither CMAR nor any affiliate or representative of CMAR:  
(a) is listed on the Specially Designated Nationals and Blocked Persons List 
maintained by the Office of Foreign Asset Control, Department of the Treasury 
(OFAC) pursuant to Executive Order No. 13224, 66 Fed. Reg. 49079 (“Order”); 
(b) is listed on any other list of terrorists or terrorist organizations maintained 
pursuant to the Order, the rules and regulations of OFAC or any other applicable 
requirements contained in any enabling legislation or other related Order(s); (c) is 
engaged in activities prohibited in the Order; or (d) has been convicted, pleaded 
nolo contendre, indicted, arraigned, or custodially detained on charges involving 
money laundering or predicate crimes to money laundering.  In addition, CMAR 
certifies that it does not have a scrutinized business operation in either Iran or 
Sudan. 
 
34.3. Legal Compliance.  CMAR agrees and covenants that it will comply with any and 
all applicable governmental restrictions, regulations, and rules of duly constituted 
authorities having jurisdiction insofar as the performance of the Work and services 
pursuant to the Contract, and all applicable safety and employment laws, rules and 
regulations, including but not limited to, the Fair Labor Standards Act, the Walsh-
Healey Act, and the Legal Arizona Workers Act (LAWA), and all amendments 
thereto, along with all attendant laws, rules, and regulations.  CMAR acknowledges 
that a breach of this warranty is a material breach of this Contract and Contractor 
is subject to penalties for violation(s) of this provision, including termination of this 
Contract.   City retains the right to inspect the documents of any and all Contractors, 
Subcontractors and sub-Subcontractors performing Work and or services relating 
to the Contract to ensure compliance with this warranty.  Any and all costs 
associated with City inspection are the sole responsibility of CMAR.  CMAR 
hereby agrees to indemnify, defend, and hold City harmless for, from, and against 
all losses and liabilities arising from any and all violations thereof. 
 
34.4. Equal Opportunity.  City is an equal opportunity, affirmative action employer.  
CMAR hereby covenants that it shall not discriminate unlawfully against any 
employee or applicant for employment, nor shall it deny the benefits of this 
Contract, to any person on the basis of race, color, creed, religion, ancestry, national 
origin, physical or mental disability, age, sex, gender, sexual orientation, gender 
identity, marital status, or veteran status with regard to discharging obligations 
under this Contract.  CMAR covenants and agrees that it will comply in all respects

30 
 
with the applicable provisions of the Executive Order 11246, Title VII of the Civil 
Rights Act of 1964, the Americans with Disabilities Act, the Age Discrimination 
in Employment Act, the Vietnam Era Veterans’ Readjustment Assistance Act, the 
Rehabilitation Act, and any other applicable state and federal statutes governing 
equal opportunity.  CMAR agrees to post hereinafter in conspicuous places, 
available for employees and applicants for employment, notices to be provided by 
the contracting officer setting for the provisions of this clause. 
 
34.5. Boycott.  CMAR certifies that it is not currently engaged in, and agrees for the 
duration of this Contract that it will not engage in, a boycott of Israel, as that term 
is defined in A.R.S. § 35-393. 
 
34.6. Compliance with Ariz. Rev. Stat. § 35-394.  Contractor hereby certifies that it does 
not currently, and agrees for the duration of this Agreement, that Contractor will 
not, use: 1. The forced labor of ethnic Uyghurs in the People’s Republic of China; 
2. Any goods or services produced by the forced labor of ethnic Uyghurs in the 
People’s Republic of China; or 3. Any contractors, subcontractors or suppliers that 
use the forced labor or any goods or services produced by the forced labor of ethnic 
Uyghurs in the People’s Republic of China.  Contractor hereby agrees to indemnify 
and hold harmless the City, its officials, employees, and agents from any claims or 
causes of action relating to the City’s action based upon reliance upon this 
representation, including the payment of all costs and attorney fees incurred by the 
City in defending such as action. 
 
34.7. CMAR further agrees to include the provisions of this Section 34 in any and all 
subcontracts hereunder.  Any violation of such provisions shall constitute a material 
breach of this Contract. 
 
34.8. Burial and Cultural Discoveries.  Personnel working on projects involving ground-
disturbing activity are required to comply with the Salt River Pima-Maricopa Indian 
Community (SRPMIC) Statement on Burials and Cultural Resource Discoveries 
(the “Statement”), a copy of which can be obtained from the City of Tempe 
Historical Preservation Office upon request at 480-350-8870.  To comply with the 
Statement, Contractor and its’ agents are prohibited from publicly releasing 
information about archeological findings or recording (through photos, video, or 
other imaging) archaeological resources, including human remains, funerary 
objects, or other discoveries. 
 
34.9. Heat Safety Standards for Outdoor Workers.  If Contractor's employees or contract 
workers will perform work under this Contract in an outdoor environment for a 
substantial period of time, the Contractor must have and implement a written plan 
listing the preventative and proactive measures that Contractor will take to protect 
those employees and contract workers from heat hazards (the "heat safety plan") 
while performing that work.  The City may request a copy of this heat safety plan 
and documentation of all heat safety and mitigation efforts currently implemented 
by the Contractor to prevent heat-related illnesses and injuries for work done under

31 
 
this Contract.  The heat safety plan must also be posted where it is accessible to 
employees. 
At a minimum, the heat safety plan must include each of the following elements as 
it relates to heat safety: 
 
(1) 
The heat safety plan shall address the requirements of Section 13A-102. 
 
(2) 
Effective acclimatization practices to promote the physiological adaptation 
of employees or contract workers newly assigned or reassigned to work in 
an outside environment.  An employee who has been newly assigned to a 
high heat area shall be closely observed by a supervisor or designee for the 
first ten (10) days of the employee's employment. Employers may follow the 
Arizona Division of Occupational Safety and Health (ADOSH) 
acclimatization recommendations, which prescribe starting with twenty 
percent (20%) of a normal workload and progressively increasing it by 
twenty percent (20%) each subsequent day. 
 
(3) 
Close monitoring and observation of employees working in heat, potentially 
including a 'buddy system' where employees are partnered together. 
 
(4) 
Communication and emergency response protocols: specifically, a means of 
communication between supervisors and employees in the event of a heat-
related emergency. 
 
(5) 
Training of employees and contract workers, no later than one (1) week prior 
to being deployed to work in an outdoor environment, on heat illness and 
injury that focuses on environmental and personal risk factors, prevention, 
how to recognize and report signs and symptoms of heat illness and injury 
and how to report heat illness and injury to emergency medical personnel. 
Employees shall receive at least one (1) additional training session annually 
thereafter. 
 
(6) 
The posting of signage at the job site that contains information, in both 
English and Spanish, explaining how to (a) recognize and report signs and 
symptoms of heat illness and injury; (b) administer appropriate first aid 
measures, and (c) report heat-related illness and injury to emergency medical 
personnel.  The signage must also include a phone number for reporting heat 
violations to OSHA/ADOSH.  The signage must also include a phone 
number for reporting heat violations to Occupational Safety and Health 
Administration (OSHA), Arizona Division of Occupational Safety and 
Health (ADOSH).  The signage must indicate that reports may be made 
anonymously. 
 
(7) 
Providing written notification to all employees and contract workers 
regarding their new worker protections under this provision.  This 
notification shall be provided to existing employees and during the 
onboarding process for new employees.  The notification shall be provided

32 
 
to each worker in the language preferred by that worker and must be posted 
in the workplace.  Contractors will incorporate this section in all subcontracts 
with subcontractors or other entities or individuals who may perform work 
under this Contract, including the requirement that those subcontractors 
impose the same obligations under any sub- subcontractors.  It is the 
obligation of the Contractor to ensure compliance with this provision by its 
subcontractors. City may terminate this Contract for failure to comply with 
this provision. 
 
35. 
ANTIDISCRIMINATION 
 
CMAR shall not refuse to hire or employ or bar or discharge from employment any person, 
or discriminate against such person in compensation, conditions, or privileges of 
employment because of race, color, gender, gender identity, sexual orientation, religion, 
national origin, familial status, age, disability, or United States military veteran status.  
CMAR shall provide a copy of its antidiscrimination policy to City to confirm compliance 
with this requirement or attest in writing to compliance based upon the criteria outlined in 
(Exhibit “C”). 
 
36. 
CONTRACTOR’S LICENSE AND PRIVILEGE TAX LICENSE 
 
Prior to award of the Contract, CMAR must provide to City’s Public Works Department, 
its contractor’s license classification and number, its City of Tempe privilege tax license 
number and its federal tax I.D. number. 
 
37. 
FORCE MAJEURE 
 
If either party is delayed or prevented from the performance of any service, in whole or 
part, required under this Contract by reason of acts of God or other cause beyond the control 
and without fault of that party, financial inability excepted, performance of that act may be 
excused at City’s discretion, but only for the period of the delay.  The time for performance 
of the act will be extended for a period equivalent to the period of delay. 
 
38. 
NON-WAIVER PROVISION 
 
The failure of either party to enforce any of the provisions of this Contract or to require 
performance by the other party of any of the provisions of this Contract shall not be 
construed as a waiver of such provisions nor will it affect the validity of this Contract or 
any part thereof or the right of either party to thereafter enforce each and every provision.

33 
 
39. 
JURISDICTION 
 
This Contract is made under and will be construed in accordance with and governed by the 
laws of the State of Arizona, without regard to the conflicts or choice of law provisions 
thereof.  An action to enforce any provision of this Contract or to obtain any remedy with 
respect hereto will be brought in the Superior Court, Maricopa County, Arizona, and for 
this purpose, each party hereby expressly and irrevocably consents to the jurisdiction and 
venue of such court. 
 
40. 
ATTORNEYS’ FEES AND COSTS 
 
In the event of any legal action or proceeding arising out of this Contract, the prevailing 
party shall be entitled to recover its reasonable attorney’s fees and costs incurred in such 
legal action or proceeding, and such fees and costs shall be included in any judgment 
rendered as determined by the Court to the extent such claim or action arises out of or is 
related to an act, omission, negligence, misconduct, or other fault of the CMAR, its 
employees, authorized volunteers, or agents. 
 
41. 
SURVIVAL 
 
All warranties, representations and indemnifications by CMAR will survive the completion 
or termination of this Contract. 
 
42. 
MODIFICATION 
 
No supplement, modification, or Amendment of any term of this Contract will be deemed 
binding or effective unless in writing and signed by the parties hereto and in conformation 
with provisions of this Contract except as expressly provided herein to the contrary. 
 
43. 
SEVERABILITY 
 
If any provision of this Contract or the application thereof to any person or circumstance 
is held invalid, illegal, or unenforceable to any extent, the remainder of this Contract and 
the application thereof will not be affected and will be enforceable to the fullest extent 
permitted by law. 
 
44. 
INTEGRATION 
 
This Contract contains the full agreement of the parties hereto.  Any prior or 
contemporaneous written or oral agreement between the parties regarding the subject 
matter hereof is merged and superseded hereby. 
 
45. 
TIME IS OF THE ESSENCE 
 
Time of each of the terms, covenants, and conditions of this Contract is hereby expressly 
made of the essence.

34 
 
46. 
THIRD PARTY BENEFICIARY 
 
This Contract will not be construed to give any rights or benefits in the Contract to anyone 
other than City and CMAR.  All duties and responsibilities undertaken pursuant to this 
Contract will be for the sole and exclusive benefit of City and CMAR and not for the benefit 
of any other party. 
 
47. 
COOPERATION AND FURTHER DOCUMENTATION 
 
CMAR agrees to provide City such other duly executed documents as may be reasonably 
requested by City to implement the intent of this Contract. 
 
48. 
EXHIBITS 
 
The parties agree that all references to this Contract include all Exhibits designated in and 
attached to this Contract, such Exhibits being incorporated into and made an integral part 
of this Contract for all purposes. 
 
49. 
CONFLICT IN LANGUAGE 
 
All Work and Deliverables will conform to all applicable City codes, ordinances, and 
requirements.  If there is a conflict in interpretation between provisions in this Contract and 
any Exhibits thereto, the provisions in this Contract will prevail. 
 
50. 
HEADINGS 
 
The headings used in the Contract are for ease of reference only and shall not in any way 
be construed to limit or alter the meaning of any provision. 
 
51. 
NON-APPROPRIATION 
 
City is a government agency that relies upon appropriation of funds by its governing body 
to satisfy its obligations. In the event that (1) funds are not appropriated by the City Council 
to perform the Work; or (2) funds appropriated or otherwise allocated to perform the Work 
become unavailable for payment by City under this Contract, City may either (a) cancel 
this Contract without further obligation of City; or (b) delay the Work for a period of six 
(6) months, In case of any such delay by City, Consultant/Contractor may suspend 
performance of work or services as applicable. The parties retain all rights available under 
this Contract to the extent permitted under Arizona law, in the event of termination or 
cancellation of this Contract due to lack of funding on the part of the City.

35 
 
52. 
ASSIGNMENT OF CLAIMS 
 
City and CMAR recognize that in actual economic practice overcharges resulting from 
antitrust violations are in fact borne by City.  Therefore, CMAR hereby assigns City any 
and all claims for such overcharges.  CMAR in all subcontracts shall require all 
Subcontractors to likewise assign all claims for overcharges to City. 
 
53. 
DISPUTES 
 
Any failure of City to make a decision within a time limit agreed to by both parties and or 
Project Team in the normal course of Project Work, shall not be construed as acquiescence 
in all or any part of any CMAR claim for relief. 
 
54. 
SEXUAL HARASSMENT 
 
Provided the City has supplied this information to CMAR, CMAR shall comply with City’s 
current policy regarding sexual harassment.  City prohibits sexual harassment by any 
person on City’s premises or at any City affiliated functions. 
 
55. 
AMENDMENTS 
 
The Contract may not be changed, altered, or amended in any way except in writing signed 
by duly authorized representatives of CMAR and City. 
 
56. 
CMAR RECORDS 
 
CMAR agrees to retain all records relating to the Contract pursuant to A.R.S. § 35-214, as 
Amended from time to time.  CMAR agrees to make those records available at all 
reasonable times for inspection and audit by City during the term of the Contract and for a 
period of five years after the completion of the Contract.  The records shall be provided at 
the City’s Public Works Department, Engineering Division, Tempe, Arizona, or another 
location designated by City upon reasonable notice to CMAR. 
 
57. 
NO CONSTRUCTION AGAINST DRAFTING PARTY 
 
Each party acknowledges that it has had an opportunity to review the Contract with 
counsel, and such documents shall not be construed against any party that is determined to 
have been the drafter of the documents. 
 
58. 
INTERPRETATION OF CONTRACT DOCUMENTS 
 
58.1. In the event of omissions in the Contract documents, the following shall apply. 
 
58.1.1. If the Contract is not complete as to any minor detail of a required 
construction system or with regard to the manner of combining or 
installing of parts, materials, or equipment, but there exists an accepted

36 
 
trade standard for good and skillful construction, pursuant to MAG 
Specifications or otherwise, such detail shall be deemed to be an implied 
requirement of the Contract in accordance with such accepted trade 
standard. 
 
58.1.2. The quality and quantity of parts or materials supplied shall conform to 
trade standards and be compatible with the type, composition, strength, 
size, and profile of the parts of materials otherwise specified in the 
Contract documents. 
 
 
[SIGNATURE PAGE TO FOLLOW]

37 
 
SIGNATURE PAGE 
 
Wellhead Treatment – Well 10 
Project No. 3205018D2 
 
DATED this        8th       day of            January                 2026. 
 
 
  
 
 
 
 
 
 
 
CITY OF TEMPE, ARIZONA  
 
 
  
 
 
 
 
 
 
 
By:  
 
 
 
 
 
 
Corey D. Woods, Mayor 
 
 
By:  
 
 
 
 
 
 
 
Public Works Director 
 
 
ATTEST:  
 
 
 
 
 
Recommended By: 
 
 
  
 
 
 
 
 
 
 
 
 
 
 
 
Kara A. DeArrastia, City Clerk  
 
 
Deputy Public Works Director/ 
 
  
 
 
 
 
 
 
 
City Engineer 
 
APPROVED AS TO FORM: 
 
 
  
 
 
 
 
 
Eric C. Anderson, City Attorney 
 
CMAR warrants that the person who is signing this Contract on behalf of the CMAR is authorized 
to do so and to execute all other documents necessary to carry out the terms of this Contract. 
 
CMAR CONTRACTOR: 
Felix Construction Company, Inc. 
 
 
 
 
 
 
 
 
Signature 
 
 
 
 
 
 
 
Printed Name 
 
 
 
 
 
 
 
Title 
 
 
 
 
 
 
 
Email Address 
 
 
 
 
 
 
 
 
 
 
 
 
 
Federal I.D. No./Tax Payer I.D. No.

EXHIBIT A 
 
Pre-Construction Services Fee Proposal 
Wellhead Treatment – Well 10

AZ   -   TX 
MAILING ADDRESS: 2530 S. 52nd Ave, Phoenix, AZ 85043   
PHONE: 480.464.0011    EMAIL: info@felixconstruction.com
DALLAS OFFICE: 2000 Westridge Drive, Suite 104, Irving,  TX 75038 
PHONE: 469.458.0011 
WEB: felixconstruction.com 
                                 
Thursday, December 4, 2025 
City of Tempe - Engineering 
31 E. Fifth St., Garden Level 
Tempe, AZ 85281 
  
Attn: Jenny Lopez 
  
RE: 3205018D2 - Wellhead Treatment - Well 10 
  
Subject: Preconstruction Services Proposal 
  
Ms. Lopez, 
  
Attached you will find our Preconstruction Services Proposal for the Wellhead Treatment - Well 10 CMAR 
Project. This project will replace the existing Well 10 and expand the site including additional treatment 
upgrades. Felix has aligned our preconstruction efforts with expected participation and deliverables for this 
project.  It is anticipated the total amount for these services is $146,873.72.  
  
Felix agrees to a CMAR Markup Fee of 10% for the Construction Phase of the project.  
  
The anticipated duration of services for this phase is 11 months. 
 
 
 
A summary of the work in this proposal includes: 
• 
Meetings and Site Visits associated with the project 
• 
Constructability, Bidability & Value Engineering 
• 
Project Scheduling 
• 
Cost Modeling & Schedule of Values Development 
• 
GMP Development 
• 
Allowances  
o Site Investigation & Potholing Allowance 
o Owner's Allowance 
o Additional Services Allowance 
 
EXHIBIT A

AZ   -   TX 
MAILING ADDRESS: 2530 S. 52nd Ave, Phoenix, AZ 85043   
PHONE: 480.464.0011    EMAIL: info@felixconstruction.com
DALLAS OFFICE: 2000 Westridge Drive, Suite 104, Irving,  TX 75038 
PHONE: 469.458.0011 
WEB: felixconstruction.com 
                                 
 
 
Attached to this letter you will find our proposal documents which include: 
• 
Preconstruction Services Scope 
• 
Preconstruction Pricing Proposal 
• 
Preconstruction Services Schedule 
 
Preconstruction Services Schedule 
• Preconstruction Services Proposal (Felix) – 12/1/2025 
• Preconstruction Services Proposal Council Approval & NTP (COT) – 1/8/2026 
• 60% Design Submittal (Wilson) – 3/24/2026 
• 60% Cost Model (Felix) – 4/23/2026 
• Long Lead GMP 1 (Felix) – 5/5/2026 
• 90% Design Submittal (Wilson) – 7/9/2026 
• 90% Cost Model (Felix) – 8/6/2026 
• GMP 1 Council Approval & NTP (COT) – 6/25/2026 
• 95% Design Submittal (Wilson) – 9/3/2026 
• Construction GMP 3 (Felix) – 10/28/2026 
• Construction GMP 3 Council Approval & NTP (COT) – 12/3/2027 
 
Legal Name: Felix Construction Company 
Corporate & "Remit To" Address: 2530 S. 52nd Ave, Phoenix, AZ 85043 
Phone Number: 480-464-0011 
Contract Signatory: Jason Robinson 
Project Manager: Zac Teal 
  
Please submit contract to contracts@felixconstruction.com for processing. 
  
If you have any questions or wish to discuss this matter further, please contact me at (480) 464-0011. 
  
Sincerely,  
  
  
  
Jason Robinson 
Preconstruction Services Manager 
Felix Construction Company

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 1
PRECONSTRUCTION SERVICES NARRATIVE
1.0  GENERAL MEETINGS & SERVICES DEFINITIONS
This section details costs related to the contractor’s general project management efforts and involvement with the typical
meetings listed below held with the client, engineer and project team. Felix internal meetings for Constructability Reviews,
Value Engineering, Scheduling, Cost Modeling, and GMP Preparation, including those necessary for subcontractor and
vendor input, are not included in this section and are detailed in other categories below.
1.1  Preconstruction General Management
Felix will direct and monitor the progress of the design phase to ensure that deadlines are met, that the project budget is not
exceeded and that the client receives a Project that meets their expectations and requirements. Felix will coordinate with the
project team to monitor and address items associated with the project schedule, project budget, and other issues of concern.
1.2  Kickoff Meeting
The purpose of this meeting is to introduce the project team and stakeholders, review the project scope of work, schedule,
and client milestones. At this meeting the contact personnel for all stakeholders will be identified, project scope will be
detailed, design and preconstruction schedule will be defined, permitting will be discussed, communication protocols will be
established, and the project meeting schedule will be developed.
1.3  Design and Preconstruction Progress Meetings
This section includes hours directly related to the project team’s discussions and review of design documents in preparation
for cost modeling and JOC developments. Felix will attend and participate in the design review meetings for the anticipated
frequency and duration of the design process. At these meetings, Felix will present their constructability comments associated
with the current design package. Felix will gather information during the design review meeting necessary to develop the
project schedule and cost model associated with the current design package.
- Felix assumes that Progress Meetings will be monthly for approximately 8 months.
 1.4  Cost Model / GMP Review Meetings
This section includes hours for cost model and deliverable reviews with the project team. These meetings will be held
following the 60% and 90% cost models are complete.  Felix will gather feedback from the design review meetings, and our
constructability review comments, and these will be incorporated into the Cost Model for the given level of design (60% and
90%).
Deliverables:
- Felix will present their constructability comments associated with the current design package during the Progress Meetings

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 2
and Design Review Meetings. 
- Prepare a Comments Resolution Meeting using COT Excel file and incorporate in the GMP submittal. 
 
1.5  Design Review Meetings
This section includes hours directly related to the project team’s discussions and review of design documents in preparation
for cost modeling and JOC developments. Felix will attend and participate in the design review meetings at the 60% and 90%
design iterations. At these meetings, Felix will present their constructability comments associated with the current design
package. Felix will gather information during the design review meeting necessary to develop the project schedule and cost
model associated with the current design package.
 
 
 
 
 
 2.0  CONSTRUCTABILITY & BIDDABILITY REVIEW
Upon receipt of each design package (60% and 90%) Felix will perform an evaluation of the design as it relates to
constructability, biddability, construction means, methods, sequences, and techniques, as well as any safety considerations. 
Our focus during this review process will be to enhance project value, construction efficiency, and propose alternate
approaches based on our experience with the client and other similar projects. We will compile this evaluation into a list of
recommendations and clarification questions to present and discuss at the design review meetings referenced above.
2.1  30% Constructability & Biddability Review - Not utilized
2.2  60% Constructability & Biddability Review
2.3  90% Constructability & Biddability Review
Deliverables: Draft and Final Design Review Comments & Log

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 3
 
3.0 VALUE ENGINEERING
This section includes hours related to Value Engineering on the project. Felix will review plans and specifications for potential
cost saving and added value ideas. When this effort is complete, Felix will submit a Value Engineering Report detailing the
options. Selected options will be incorporated into the design.
 
4.0  PROJECT SCHEDULING 
Following the kick-off meeting, Felix will work with the design engineer to develop a preliminary project schedule reflecting our
understanding of the key project milestones and deliverable dates.  At each design stage, this project schedule will be
updated, and additional detail added to track the design progress, as well as identify key activities associated with material
procurement and construction that will drive the project’s overall critical path. This schedule will be presented for review at
each Cost Model review meeting. 
4.1  30% Schedule Update - Not utilized
4.2  60% Schedule Update
This section includes hours for initial schedule brainstorming and development including sequencing of the work with
assumed durations and lead times including utility coordination milestones and major transitional phases of the project.
4.3  90% Schedule Update 
This section includes hours for updating and detailing a 90% project schedule.
4.4  Final GMP Schedule
This section includes hours for updating and detailing a GPM schedule to accompany the final GMP.
 
5.0  COST  MODELS & GMP PROPOSALS
Felix will begin the development of the Cost Model. Questions and comments for the design engineer will be compiled and
addressed in the design review meetings and taken into account for the Cost Model. The Cost Model will be comprehensive
of the entire project and will be accompanied by an update project schedule.

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 4
5.1  30% Cost Modeling - Not utilized
5.2  60% Cost Modeling
Upon receipt of the 60% design package, Felix will begin the development of the Cost Model. Questions and comments for
the design engineer will be compiled and addressed in the design review meetings and taken into account for the Cost Model.
5.3  90% Cost Modeling, Bid Solicitation & GMP Development 
Upon receipt of the 90% design package, we will perform a final biddability review of the design documents and we will begin
to solicit quotes from subcontractors and vendors.  During this phase, Felix will coordinate a site visit for all potential
subcontractors to view the project site and current conditions prior to the bid date. Answers to questions and clarification
issued from the 90% design review meeting will be issued to the bidders as addendum by Felix. We typically set the bids to
be due from subcontractors and vendors approximately four weeks after the 90% design review meeting. Following receipt of
the bids, we require an additional week during this phase to compile the final Cost Model, which becomes the first draft of the
GMP.
5.4 Final GMP Adjustments
After the Draft GMP is reviewed by the City, the final GMP will be presented taking into account the City, the Engineer, and
stakeholder's comments and any other adjustments will be made. 
 
PROJECT ALLOWANCES
$50,000 is set aside for Site Investigation & Potholing.
$10,000 is set aside for Owner's Allowance.
Due to the nature of this project, additional services may be required during Felix's pre-construction services for unforeseen
circumstances or conditions. The Owner's Allowance is intended for additional services that are found by the City to be
required for completion of the project. All tasks completed under this allowance shall be authorized in advance, in writing, by
the City's Engineering Project Manager.  
 
EXCLUSIONS
- Any and all construction activities 
- Permits

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 5
- Material Costs
- Taxes
- Bonds
  
PROJECT TEAM
Preconstruction Manager: Jason Robinson
Preconstruction Engineer: Victoria Morin
Estimator: Robert Salazar
Project Manager: Zac Teal
Project Engineer: Sam Shumaker 
Superintendent: Travis Barrick
Subcontractors: No subcontractors are anticipated for the Preconstruction phase.

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 6
Preconstruction Service Cost Summary
Description
Man Hours
Total Project Fee
Division 00 - Preconstruction Services
1.1 - Preconstruction General Management 
60.00
8,036.00
1.2 - Kickoff Meeting
6.50
862.03
1.3 - Design and Preconstruction Progress Meetings (Assumes 1 Meeting per Month for 8 Months)
44.00
6,093.16
1.4 - Cost Model / GMP Review Meetings  (60%, 90%, LLP, & Final)
26.00
3,446.40
1.5 - Design Review Meetings (QTY 3)
24.00
3,228.36
2.2 - 60% Constructability & Biddability Review
28.00
3,782.90
2.3 - 90% Constructability & Biddability Review
28.00
3,782.90
3.1 - Value Engineering Review
59.00
8,119.00
4.2 - 60% Schedule Development
10.00
1,378.42
4.3 - 90% Schedule Update
18.00
2,422.03
 4.4 - Final GMP Schedule 
12.00
1,582.36
5.1 - Long Lead Procurement, Bid Solicitation & GMP Development
37.00
5,211.42
5.2 - 60% Cost Modeling
91.00
13,045.76
5.3 - 90% Cost Modeling, Bid Solicitation & GMP Development
141.00
20,115.12
5.4 - Final GMP Adjustments 
35.00
4,907.72
Division 00 - Preconstruction Services Totals
619.5
$86,013.58
Bonds and Insurance
Description
Percentage
Totals
Sub-Total (Bonds and Insurance)
Insurance
1.00%
$860.14
Sub-Total (Bonds and Insurance) Total
$86,873.72
AZ Gross Receipt Tax
Description
Percentage
Totals
Sub-Total (Bonds and Insurance)
$86,873.72
Sub-Total (Taxes) Total
$86,873.72

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 7
Contingencies
Description
Percentage
Amount
Totals
Sub-Total (Taxes)
$86,873.72
Sub-Total (Project Contingencies) Total
$86,873.72
Allowances
Description
Percentage
Amount
Totals
Sub-Total (Project Contingencies)
$86,873.72
Site Investigation & Potholing Allowance
0.00%
50,000.00
$50,000.00
Owner's Allowance
0.00%
10,000.00
$10,000.00
Sub-Total (Project Allowances) Total
$146,873.72
Preconstruction Grand Total
Description
Totals
Sub-Total (Project Allowances)
$146,873.72
Total Estimate Total
$146,873.72

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 8
Preconstruction Services Cost Detail
Description
Man Hours
Unit Cost
Total Direct Cost
Division 00 - Preconstruction Services
1.1 - Preconstruction General Management
TE - Preconstruction Manager
40.00
143.68
5,747.20
TE - Preconstruction Project Engineer
20.00
114.44
2,288.80
1.1 - Preconstruction General Management  Totals
60.0
$8,036.00
1.2 - Kickoff Meeting
TE - Preconstruction Manager
1.00
143.68
143.68
TE - Preconstruction GC Estimator
1.00
145.17
145.17
TE - Preconstruction Coordinator
0.50
52.20
26.10
TE - Preconstruction Manager Electrical
1.00
143.68
143.68
TE - Preconstruction Project Engineer
1.00
114.44
114.44
TE - Preconstruction Estimator Electrical
1.00
145.23
145.23
TE - Preconstruction GC Project Manager
1.00
143.73
143.73
1.2 - Kickoff Meeting Totals
6.5
$862.03
1.3 - Design and Preconstruction Progress Meetings (Assumes 1 Meeting per Month for 8 Months)
TE - Preconstruction GC Project Manager
8.00
143.73
1,149.84
TE - Preconstruction GC Superintendent
4.00
140.34
561.36
TE - Preconstruction Manager Electrical
4.00
143.68
574.72
TE - Preconstruction Project Engineer
8.00
114.44
915.52
TE - Preconstruction Manager
8.00
143.68
1,149.44
TE - Preconstruction GC Estimator
8.00
145.17
1,161.36
TE - Preconstruction Estimator Electrical
4.00
145.23
580.92
1.3 - Design and Preconstruction Progress Meetings (Assumes 1 Meeting per Month
for 8 Months) Totals
44.0
$6,093.16
1.4 - Cost Model / GMP Review Meetings  (60%, 90%, LLP, & Final)
TE - Preconstruction GC Estimator
4.00
145.17
580.68
TE - Preconstruction Estimator Electrical
4.00
145.23
580.92
TE - Preconstruction Coordinator
2.00
52.20
104.40
TE - Preconstruction Manager
4.00
143.68
574.72
TE - Preconstruction Project Engineer
4.00
114.44
457.76
TE - Preconstruction Project Manager Electrical
4.00
143.25
573.00
TE - Preconstruction GC Project Manager
4.00
143.73
574.92
1.4 - Cost Model / GMP Review Meetings  (60%, 90%, LLP, & Final) Totals
26.0
$3,446.40
1.5 - Design Review Meetings (QTY 3)
TE - Preconstruction Manager
3.00
143.68
431.04

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 9
Description
Man Hours
Unit Cost
Total Direct Cost
TE - Preconstruction GC Estimator
3.00
145.17
435.51
TE - Preconstruction GC Sr. Project Manager
0.00
0.00
TE - Preconstruction GC Project Manager
3.00
143.73
431.19
TE - Preconstruction GC Superintendent
0.00
0.00
TE - Preconstruction GC Project Engineer
3.00
114.44
343.32
TE - Preconstruction Estimator Electrical
0.00
0.00
TE - Preconstruction Sr. Project Manager Electrical
0.00
0.00
TE - Preconstruction Project Manager Electrical
3.00
143.25
429.75
TE - Preconstruction Superintendent Electrical
0.00
0.00
TE  - Preconstruction Project Engineer Electrical
3.00
127.73
383.19
TE - Preconstruction Coordinator
0.00
0.00
TE - Preconstruction Manager Electrical
3.00
143.68
431.04
TE - Preconstruction Project Engineer
3.00
114.44
343.32
1.5 - Design Review Meetings (QTY 3) Totals
24.0
$3,228.36
2.2 - 60% Constructability & Biddability Review
TE - Preconstruction Manager
6.00
143.68
862.08
TE - Preconstruction GC Estimator
2.00
145.17
290.34
TE - Preconstruction GC Sr. Project Manager
2.00
154.18
308.36
TE - Preconstruction GC Project Manager
2.00
143.73
287.46
TE - Preconstruction GC Superintendent
2.00
140.34
280.68
TE - Preconstruction Project Engineer
2.00
114.44
228.88
TE - Preconstruction Superintendent Electrical
2.00
134.51
269.02
TE - Preconstruction Project Manager Electrical
2.00
143.25
286.50
TE - Preconstruction Manager Electrical
4.00
143.68
574.72
TE - Preconstruction Estimator Electrical
2.00
145.23
290.46
TE - Preconstruction Coordinator
2.00
52.20
104.40
2.2 - 60% Constructability & Biddability Review Totals
28.0
$3,782.90
2.3 - 90% Constructability & Biddability Review
TE - Preconstruction Manager
6.00
143.68
862.08
TE - Preconstruction GC Estimator
2.00
145.17
290.34
TE - Preconstruction GC Sr. Project Manager
2.00
154.18
308.36
TE - Preconstruction GC Project Manager
2.00
143.73
287.46
TE - Preconstruction GC Superintendent
2.00
140.34
280.68
TE - Preconstruction Estimator Electrical
2.00
145.23
290.46
TE - Preconstruction Project Manager Electrical
2.00
143.25
286.50
TE - Preconstruction Project Engineer
2.00
114.44
228.88
TE - Preconstruction Superintendent Electrical
2.00
134.51
269.02

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 10
Description
Man Hours
Unit Cost
Total Direct Cost
TE - Preconstruction Manager Electrical
4.00
143.68
574.72
TE - Preconstruction Coordinator
2.00
52.20
104.40
2.3 - 90% Constructability & Biddability Review Totals
28.0
$3,782.90
3.1 - Value Engineering Review
TE - Preconstruction Manager
6.00
143.68
862.08
TE - Preconstruction GC Sr. Project Manager
1.00
154.18
154.18
TE - Preconstruction Manager Electrical
8.00
143.68
1,149.44
TE - Preconstruction Project Engineer
8.00
114.44
915.52
TE - Preconstruction Project Manager Electrical
1.00
143.25
143.25
TE - Preconstruction GC Project Manager
1.00
143.73
143.73
TE - Preconstruction GC Estimator
16.00
145.17
2,322.72
TE - Preconstruction Estimator Electrical
16.00
145.23
2,323.68
TE - Preconstruction Coordinator
2.00
52.20
104.40
3.1 - Value Engineering Review Totals
59.0
$8,119.00
4.2 - 60% Schedule Development
TE - Preconstruction Manager Electrical
2.00
143.68
287.36
TE - Preconstruction GC Project Manager
2.00
143.73
287.46
TE - Preconstruction Project Engineer
2.00
114.44
228.88
TE - Preconstruction Manager
4.00
143.68
574.72
4.2 - 60% Schedule Development Totals
10.0
$1,378.42
4.3 - 90% Schedule Update
TE - Preconstruction Coordinator
1.00
52.20
52.20
TE - Preconstruction Project Engineer
2.00
114.44
228.88
TE - Preconstruction GC Project Engineer
1.00
114.44
114.44
TE - Preconstruction GC Sr. Project Manager
2.00
154.18
308.36
TE - Preconstruction GC Superintendent
2.00
140.34
280.68
TE - Preconstruction Manager
2.00
143.68
287.36
TE - Preconstruction GC Project Manager
4.00
143.73
574.92
TE - Preconstruction Sr. Project Manager Electrical
1.00
154.18
154.18
TE - Preconstruction Superintendent Electrical
1.00
134.51
134.51
TE - Preconstruction Project Manager Electrical
2.00
143.25
286.50
4.3 - 90% Schedule Update Totals
18.0
$2,422.03
4.4 - Final GMP Schedule
TE - Preconstruction GC Project Engineer
1.00
114.44
114.44
TE - Preconstruction Sr. Project Manager Electrical
1.00
154.18
154.18
TE - Preconstruction Manager
2.00
143.68
287.36
TE - Preconstruction GC Sr. Project Manager
1.00
154.18
154.18

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 11
Description
Man Hours
Unit Cost
Total Direct Cost
TE - Preconstruction GC Superintendent
1.00
140.34
140.34
TE - Preconstruction Project Manager Electrical
1.00
143.25
143.25
TE - Preconstruction Project Engineer
1.00
114.44
114.44
TE - Preconstruction Superintendent Electrical
1.00
134.51
134.51
TE - Preconstruction GC Project Manager
2.00
143.73
287.46
TE - Preconstruction Coordinator
1.00
52.20
52.20
 4.4 - Final GMP Schedule  Totals
12.0
$1,582.36
5.1 - Long Lead Procurement, Bid Solicitation & GMP Development
TE - Preconstruction Manager
2.00
143.68
287.36
TE - Preconstruction GC Estimator
15.00
145.17
2,177.55
TE - Preconstruction GC Project Manager
1.00
143.73
143.73
TE - Preconstruction Estimator Electrical
15.00
145.23
2,178.45
TE - Preconstruction Project Manager Electrical
1.00
143.25
143.25
TE - Preconstruction Coordinator
1.00
52.20
52.20
TE - Preconstruction Project Engineer
2.00
114.44
228.88
5.1 - Long Lead Procurement, Bid Solicitation & GMP Development Totals
37.0
$5,211.42
5.2 - 60% Cost Modeling
TE - Preconstruction Coordinator
1.00
52.20
52.20
TE - Preconstruction Project Engineer
2.00
114.44
228.88
TE - Preconstruction Manager
4.00
143.68
574.72
TE - Preconstruction GC Estimator
40.00
145.17
5,806.80
TE - Preconstruction Estimator Electrical
40.00
145.23
5,809.20
TE - Preconstruction GC Project Manager
2.00
143.73
287.46
TE - Preconstruction Project Manager Electrical
2.00
143.25
286.50
5.2 - 60% Cost Modeling Totals
91.0
$13,045.76
5.3 - 90% Cost Modeling, Bid Solicitation & GMP Development
TE - Preconstruction Coordinator
1.00
52.20
52.20
TE - Preconstruction Estimator Electrical
60.00
145.23
8,713.80
TE - Preconstruction GC Estimator
60.00
145.17
8,710.20
TE - Preconstruction GC Project Manager
2.00
143.73
287.46
TE - Preconstruction Manager
8.00
143.68
1,149.44
TE - Preconstruction Project Engineer
8.00
114.44
915.52
TE - Preconstruction Project Manager Electrical
2.00
143.25
286.50
5.3 - 90% Cost Modeling, Bid Solicitation & GMP Development Totals
141.0
$20,115.12
5.4 - Final GMP Adjustments
TE - Preconstruction Manager
4.00
143.68
574.72
TE - Preconstruction GC Estimator
10.00
145.17
1,451.70

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 12
Description
Man Hours
Unit Cost
Total Direct Cost
TE - Preconstruction Coordinator
1.00
52.20
52.20
TE - Preconstruction Project Manager Electrical
4.00
143.25
573.00
TE - Preconstruction Project Engineer
2.00
114.44
228.88
TE - Preconstruction GC Project Manager
4.00
143.73
574.92
TE - Preconstruction Estimator Electrical
10.00
145.23
1,452.30
5.4 - Final GMP Adjustments  Totals
35.0
$4,907.72
Division 00 - Preconstruction Services Totals
619.5
$86,013.58
Bonds and Insurance
Description
Percentage
Totals
Sub-Total (Bonds and Insurance)
Insurance
1.00%
$860.14
Sub-Total (Bonds and Insurance) Total
$86,873.72
AZ Gross Receipt Tax
Description
Percentage
Totals
Sub-Total (Bonds and Insurance)
$86,873.72
Sub-Total (Taxes) Total
$86,873.72
Contingencies
Description
Percentage
Amount
Totals
Sub-Total (Taxes)
$86,873.72
Sub-Total (Project Contingencies) Total
$86,873.72
Allowances
Description
Percentage
Amount
Totals
Sub-Total (Project Contingencies)
$86,873.72
Site Investigation & Potholing Allowance
0.00%
50,000.00
$50,000.00
Owner's Allowance
0.00%
10,000.00
$10,000.00
Sub-Total (Project Allowances) Total
$146,873.72

Wellhead Treatment Well 10
 
Contact: Jenny Lopez
Felix Project No.: TBD
Date: 12/04/2025
PRECONSTRUCTION SERVICES
PROPOSAL
Page Number: 13
Preconstruction Grand Total
Description
Totals
Sub-Total (Project Allowances)
$146,873.72
Total Estimate Total
$146,873.72

EXHIBIT B 
 
AFFIDAVIT DEMONSTRATING LAWFUL 
PRESENCE IN THE UNITED STATES 
 
ARS §§ 1-501 and 502 require any individual person or sole proprietor who applies to the City for a local public benefit (defined 
as a grant, contract or loan) to demonstrate his or her lawful presence in the United States.  An individual person or sole 
proprietor must complete this Affidavit and submit it with the all contract documents, along with a copy of one of the documents 
listed below. 
ALL VIOLATIONS OF FEDERAL IMMIGRATION LAW SHALL BE REPORTED TO 1-866-347-2423. 
 
LAWFUL PRESENCE IN THE UNITED STATES CAN BE DEMONSTRATED BY 
PRESENTATION OF ONE (1) OF THE DOCUMENTS LISTED BELOW. 
Please present the document indicated below to the City.  If mailing the document, attach a copy of the document to this 
Affidavit. 
(If the document may not be copied, present the document in person to the City for review and signing of the affidavit.) 
 
 
 
1. 
An Arizona driver license issued after 1996. 
 
 
 
Print first 4 numbers/letters from license: 
 
___ ___ ___ ___ 
 
 
2. 
An Arizona non-operating identification License. 
 
 
 
Print first 4 numbers/letters:  
 
 
___ ___ ___ ___ 
 
 
3. 
A birth certificate or delayed birth certificate issued in any state, territory, or possession of the United 
States. 
 
 
 
Year of birth:  
 
 
:   Place of birth:  
 
 
 
 
 
 
 
 
4. 
A United States Certificate of Birth abroad. 
 
 
 
Year of birth:  
 
 
:   Place of birth: 
 
 
 
 
 
 
 
 
5. 
A United States passport. 
 
 
 
Print first 4 numbers/letters on Passport: 
 
 
___ ___ ___ ___ 
 
 
6. 
A foreign passport with a United States Visa. 
 
 
 
Print first 4 numbers/letters on Passport  
 
___ ___ ___ ___ 
 
 
 
Print first 4 numbers/letters on Visa 
 
 
 
___ ___ ___ ___ 
 
 
7. 
An I-94 form with a photograph. 
 
 
 
Print first 4 numbers on I-94:  
 
 
___ ___ ___ ___ 
 
 
8. 
A United States Citizenship and Immigration Services Employment Authorization Document (EAD). 
 
 
 
Print first 4 numbers/letters on EAD: 
 
 
___ ___ ___ ___ 
 
 
9. 
Refugee travel document. 
 
 
 
Date of Issuance:   
 
   Refugee Country:   
 
 
 
 
 
 
 
10. 
A United States Certificate of Naturalization. 
 
 
 
Print first 4 digits of CIS Reg. No.:   
 
 
___ ___ ___ ___ 
 
 
11. 
A United States Certificate of Citizenship. 
 
 
 
Date of Issuance:   
 
   Place of Issuance:   
 
 
 
 
 
 
 
12. 
A tribal Certificate of Indian Blood. 
 
 
 
Date of Issuance:   
 
  Name of Tribe:    
 
 
 
 
 
 
 
13. 
A tribal or Bureau of Indian Affairs Affidavit of Birth. 
 
 
 
Year of Birth:   
 
 
  Place of Birth:  
 
 
 
 
 
 
I DO SWEAR OR AFFIRM UNDER PENALTY OF LAW THAT I AM LAWFULLY PRESENT IN THE UNITED 
STATES AND THAT THE DOCUMENT I PRESENTED ABOVE AS VERIFICATION IS TRUE. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Signature  
 
 
 
 
 
Business/Company (if applicable)  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Print Name  
 
 
 
 
 
Address 
Date:  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
City, State, Zip Code 
 
STATE OF ARIZONA 
 
COUNTY OF MARICOPA  
 
SUBSCRIBED AND SWORN to before me this ___________ day of _____________________ 2025. 
[Notary Seal] 
 
 
  
 
 
 
Notary Public ______________________________________

EXHIBIT C 
 
COMPLIANCE WITH TEMPE CITY CODE 
CHAPTER 2 ARTICLE VIII SECTION 2-603(5) 
_________________________________________________ 
 
Per Tempe City Code Chapter 2 Article VIII Section 2-603(5), it is unlawful for a City vendor or 
City contractor, because of race, color, gender, gender identity, sexual orientation, religion, 
national origin, familial status, age, disability, or United States military veteran status to refuse to 
hire or employ or bar or discharge from employment any person, or to discriminate against such 
person in compensation, conditions, or privileges of employment. 
 
City vendors and contractors of 15 or more employees shall provide a copy of its antidiscrimination 
policy to the City’s procurement officer to confirm compliance with this article.  Employers having 
14 or less employees may attest in writing to compliance with this article. 
 
 CONTRACTOR means any person who has a contract with the City. 
 
 VENDOR means a person or firm in the business of selling or otherwise providing products, 
materials, or services. 
 
 
CONTRACTOR/VENDOR, select one: 
 
           Current copy of antidiscrimination policy attached 
 
OR 
_____ I hereby certify _________________________________ (contractor/vendor) to be 
in compliance with Tempe City Code Chapter 2 Article VIII Section 2-603(5). 
 
 
____________________________________ 
 
Date: _____________________ 
Signature 
 
____________________________________ 
 
__________________________ 
Print Name 
 
 
 
 
 
 
Title 
 
____________________________________ 
Company

EXHIBIT D 
 
CITY OF TEMPE 
TEMPE, ARIZONA 
PUBLIC WORKS DEPARTMENT 
DIVISION OF ENGINEERING 
 
AFFIDAVIT OF GENERAL CONTRACTOR / PRIME CONSULTANT 
REGARDING HEALTH INSURANCE 
 
 
 
 
, Arizona 
 
Date 
 
 
 
 
Wellhead Treatment – Well 10 
Project No. 3205018D2 
 
I hereby certify that ______________________________________________ (name of company) currently has, and 
all of its major subcontractors/sub-consultants, defined as doing work in excess of $100,000 will have, during the 
course of this Contract, health insurance for all employees working on this project and will offer health insurance 
coverage to eligible dependents of such employees, as defined in the accompanying Guidelines.  The company’s health 
insurance is as follows: 
 
Name of Insurance Company: _____________________________________________________ 
 
Type of Insurance (PPO, HMO, POS, INDEMNITY): __________________________________ 
 
Policy No.: ___________________________________________ 
 
Policy Effective Date (MM/DD/YY): ______________________________________ 
 
Policy Expiration Date (MM/DD/YY): _____________________________________ 
 
Signed and dated at           
 
        , this        
      day of                                            2025. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
General Contractor/Prime Consultant 
 
 
 
 
 
 
 
 
 
By:  
 
 
 
 
STATE OF ARIZONA 
 
 
) 
 
 
 
 
 
 
)  ss 
COUNTY OF MARICOPA 
 
) 
 
 
SUBCRIBED AND SWORN to before me this ___________ day of _____________________ 2025. 
 
 
 
 
 
 
 
 
 
Notary Public 
 
[Notary Seal] 
 
 
My commission expires: 
 
 
 
 
 
 
 
____________________________

CITY OF TEMPE 
GUIDELINES FOR IMPLEMENTATION OF RESOLUTION NO. 2000.73 
 
These Guidelines are provided for purposes of implementing Resolution No. 2000.73 which 
requires that health insurance be provided by all consultants, general contractors and major 
subcontractors, as determined at the start of each project, for employees and dependents of 
employees. Questions regarding this procedure should be addressed to Tara Ford, Public Works 
Director for the City of Tempe. 
 
1. All consultants and general contractors, who bid on projects or enter into public works 
contracts, in excess of $100,000 or the current Council approval contract limit in place at the 
time the contract is executed, with the City of Tempe, after January 1, 2001, are required 
to sign an affidavit in the form attached hereto. The general contractor shall be responsible 
for ensuring that the subcontractors comply with the health insurance requirements. 
 
2. Health insurance is required for all employees, except for those employees who work less 
than one hundred and twenty (120) days in any calendar year. A “workday” consists of 
any time within a twenty-four-hour period, regardless of number of hours, that the 
individual is paid. 
 
3. The level of health insurance provided shall be determined by each employer but should 
be no less than that provided by the Arizona Cost Containment Health System. 
  
4. All complaints concerning violations of the health insurance requirements shall be filed, 
in writing, with the Public Work's Department, within five (5) days from discovery of the 
violation. An administrative hearing will be held before the Public Works Director, and 
a written decision of findings will be provided to the parties to the hearing within ten 
(10) days thereafter. Appeal from the decision of the Public Works Director may be 
made within ten (10) days of the date of the decision by filing a notice of appeal in writing 
with the Public Works Department. If an appeal is timely filed, an administrative hearing 
will be held before an administrative hearing officer appointed by the City Manager. 
The decision of the administrative hearing officer shall be final. 
 
5. In the event of a finding of violation of the insurance provisions, the company in violation 
of the provision shall be barred from bidding on, or entering into, any public works contract 
with the City for a period of three (3) years. 
 
6. All consultants and contractors subject to the health insurance requirements shall post, in 
English and Spanish, notice of the health insurance requirements at the job site. Signs for 
posting will be provided by the City. 
March 24, 2025  
 
Tara Ford, Public Works Director

EXHIBIT E 
 
CITY ENGINEERING SECURE FACILITIES ACCESS GUIDELINES 
 
These guidelines are applicable to all contracts that call for work to be done in any of the City’s secure 
facilities and are incorporated by reference into said contracts.  Contractors should be advised that there 
are separate requirements for General Secure Facilities and Water Utilities Department Secure Facilities. 
 
I. 
GENERAL SECURE FACILITIES ACCESS REQUIREMENTS 
 
The Contractor and Third-Party Construction Manager shall provide the City with a 10-year background 
check for all employees, including subcontractors, working in any of the City’s secure facilities which 
include, but are not limited to, the Tempe Transportation Center, East Valley Bus Operations and 
Maintenance Facility, Police Department/Courts Headquarters, and Police Department substations. 
Background checks shall be performed by an authorized company capable of conducting a nationwide 
search. Background checks shall include, at a minimum, information regarding state and national criminal 
and sexual offender information, and a 5-year driving record search. The Contractor and Third-Party 
Construction Manager shall be responsible for the cost of all their employee background checks. Below 
is a list of automatic and discretionary disqualifiers which may disqualify or make an individual ineligible 
to work at any of the City’s secure facilities. The Contractor and Third-Party Construction Manager shall 
submit all employee background checks to the City of Tempe for review and authorization before the 
contractor employees or subcontractors are issued a Contractor Identification Badge and before being 
allowed to work at any of the City’s secure facilities.  All authorized contractor, subcontractor and third-
party construction manager employees shall coordinate with the respective facility supervisor to obtain a 
contractor identification badge. Contractor and Third-Party Construction Manager employees must wear 
their contractor identification badge at-all-times while working at the City’s secure facility. 
 
AUTOMATIC DISQUALIFIERS 
The following will disqualify any individual who has, at any time: 
 
• 
Has known affiliations with gangs, gang members, terrorist groups and/or individuals,  
• 
Outstanding felony warrants, 
• 
Conviction for selling, producing, cultivating, or transporting marijuana for sale,  
• 
Conviction for producing, cultivating, or transporting any dangerous drugs or narcotics for sale. 
DISCRETIONARY DISQUALIFIERS 
The following may, upon review by the Tempe Police Department, make an individual ineligible to work 
in or around secure areas of City Facilities: 
 
• 
Unlawful sexual misconduct;  
• 
DUI conviction or suspension of your Arizona driver’s license due to a DUI; 
• 
Commission of a felony;  
• 
Conviction of a felony or any offense that would be a felony if committed in Arizona; 
• 
Outstanding misdemeanor warrants;  
• 
Any other conduct or offense that could jeopardize the safety of City employees or the public; or,  
• 
Insufficient information.

II. 
WATER UTILITIES DEPARTMENT SECURE FACILITIES ACCESS 
REQUIREMENTS 
 
The Contractor and Third-Party Construction Manager shall verify that a 10-year background check has 
been completed within the last 5 years for all employees, including subcontractors, working in any of the 
City’s Water Utilities Department secure facilities which include, but are not limited to, the Johnny G. 
Martinez Water Treatment Plant, South Tempe Water Treatment Plant, and Kyrene Water Reclamation 
Facility. The background check shall include state and national criminal and sexual offender information 
as well as driving record information outlined in Secure Facility Access Requirements. Background 
checks shall be performed by an authorized company capable of conducting a nationwide search. 
Background checks shall include, at a minimum, information regarding state and national criminal and 
sexual offender information, and a 5-year driving record search. The Contractor and Third-Party 
Construction Manager shall be responsible for the cost of all their employee background checks.  
 
Contractor and Third-Party Construction Manager shall disclose any knowledge of employee criminal 
history status involving the following: 
 
• 
Any felony offense 
• 
Any offense involving assault or threats of violence 
• 
Any theft, fraud or financial crimes offense   
• 
Any arson offense 
• 
Any sexual misconduct offense 
• 
Any offense of misconduct involving a deadly weapon 
SECURE FACILITY VERIFICATION REQUIREMENTS 
 
The Contractor and Third-Party Construction Manager shall verify that all employee background checks 
have been completed before the contractor employees or subcontractors are issued a Contractor 
Identification Badge and before being allowed to work at any of the City’s Water Utilities Department 
secure facilities. All authorized contractor, subcontractor and third-party construction manager 
employees shall coordinate with the respective facility supervisor to obtain a contractor identification 
badge. Contractor and Third-Party Construction Manager employees must wear their contractor 
identification badge at-all-times while working at the City’s secure facility.