MR Tanner Greenway Proposal
Extracted text (via pymupdf)
2982 characters
Item Description
Unit
Quantity
Unit Price
Total
1
Mill Asphalt 1.5” (1-165,000)
SY
2,826.00
1.90
5,369.40
2
Pave (12.5mm EVAC A/C Mix) (1-165,000)
SY
2,826.00
9.50
26,847.00
3
Pre-lower manhole frame and covers
EA
-
275.00
-
4
Adjust Manhole
EA
-
485.00
-
5
Adjust Valves
EA
-
275.00
-
6
Adjust Monuments
EA
-
225.00
-
7
4” Yellow Paint
LF
-
0.40
-
8
4” Yellow Paint - Thermo
LF
-
0.60
-
9
4" White Paint
LF
-
0.40
-
10
4" White Paint - Thermo
LF
-
0.60
-
11
8” White Paint (Turn Lane) - Temporary
LF
675.00
0.60
405.00
12
8” White Thermo (Turn Lane)
LF
675.00
0.75
506.25
13
12” White Paint (Crosswalks) - Temporary
LF
-
1.50
-
14
12” White Thermo (Crosswalks)
LF
-
3.00
-
15
18” White Paint (Stop Bars) - Temporary
LF
-
2.00
-
16
18” White Thermo (Stop Bars)
LF
-
4.00
-
17
School Crosswalks: 24”X10' Yellow High VisibilityRectangles
SETS
-
100.00
-
18
Turn Arrows, Paint – Temporary
EA
5.00
70.00
350.00
19
Turn Arrows, Thermo
EA
5.00
125.00
625.00
20
Bike Lane Symbols
EA
75.00
-
21
Bike Lane Symbols - Thermo
EA
125.00
-
22
White Raised Pavement Markers (RPMs)
EA
5.00
-
23
Yellow Raised Pavement Markers (RPMs)
EA
5.00
-
24
Traffic Control Arterial Roadway Sections
LS
1.00
1,250.00
1,250.00
25
City of Surprise Uniformed Police Officer
LS
-
12,500.00
-
35,352.65
ALL PRICING BASED ON BUCKEYE MILL AND PAVE JOC
2019005-03
Greenway: Grand Ave to Dysart
Asphalt Patch Removals and Replace
Utility / Monument Adjustments
Striping