Exhibit A — Project Scope

Public Works Department

A PW21-WRFO1 10000 N. El Mirage Rd.
- Ta reac SCOPE OF WORK AND El Mirage, Arizona 85335
——<=-== | PROJECT SPECIFICATIONS Telephone: (623) 936.6405

Fax: (623) 933-8418

CITY OF EL MIRAGE

PUBLIC WORKS DEPARTMENT

i. City of
EL MIRAGE

eae Arizona
GRAND HERITAGE, BRIGHT FUTURE

WATER RECLAMATION FACILITY — EFFLUENT
FILTER PROJECT

Design/Build
Scope of Project Document

PW21 - WRFO1

Page 14 of 29
PW2I - WRFOL

Public Works Department

PW21-WRF01 10000 N. El Mirage Rd.
SCOPE OF WORK AND El Mirage, Arizona 85335
PROJECT SPECIFICATIONS vey ono eae

CONTENTS

ABBREVIATIONS
INTRODUCTION ___
BACKGROUND |
CURRENT STATUS.
BUSINESS CASE

A XW Rw DP

ll Project Meetings

Task 2 — Verification of Existing Conditions

2.1 Filter Placement, Structural Support and Chemical Tank Placement

Task 3 — Basis of Design Report 19

Task 4 — Detailed Design 19

18, DUST PREVENTION ________
19. MISCELLANEOUS REMOVAL AND RELOCATIONS,
20. SUBSIDIARY WORK,
21. MISCELLANEOUS WORK AND ALLOWANCES.
22. PROJECT COMPLETION oo ocee eee
23. FINAL ACCEPTANCE

24, PROPOSAL SUBMITTAL SHEET.

Page 15 of 29
PW21 - WRFOI

Public Works Department

EY PW21-WRF01 10000 N. El Mirage Rd.
Ma MaRAGE SCOPE OF WORK AND El Mirage, Arizona 85335
-—«ae== | PROJECT SPECIFICATIONS Telephone: (628) 936-6405

Fax: (623) 933-8418

25. APPENDIX A —- REFERENCES. 25

26. APPENDIX B - STATEMENT OF CONTRACTORS QUALIFICATIONS
27. AGREEMENT. 27

Page 16 of 29
PW21- WRFOI

Public Works Department

2S) PW21-WRF01 10000 N. El Mirage Ra.
Po it Mmage SCOPE OF WORK AND El Mirage, Arizona 85335
=——----= | PROJECT SPECIFICATIONS Telephone: (623) 935-6405
Fax: (623) 933-8418

1. ABBREVIATIONS

pg/L micrograms per liter

AACE Association for Advancement of Cost Engineering

AAD annual average day

AADF annual average daily flow

APP Aquifer Protection Permit

AZPDES Arizona Pollutant Discharge Elimination System

BOD biological oxygen demand

CCR Consumer Confidence Report

Ci2 chlorine

CITY City of El Mirage

CWwD clearwater discharge

ft feet gal gallons

gpm gallons per minute

gpm/sq ft gallons per minute per square foot

Ib/d pounds per day

MCESD Maricopa County Environmental Services Department

MG million gallons

mg/L milligrams per liter

mgd million gallons per day

min minimum

MMADF maximum month average day flow

MMADL maximum month average day load

MMEFPF maximum month flow peak factor

MML maximum month load

MMLPF maximum month load peaking factor

PDF peak day flow

PHF peak hour flow

SBR sequencing batch reactor

scfm standard cubic feet per minute

sq ft square feet

™ technical memorandum

TSS total suspended solids

PW21 - WRFOi

Page 17 of 29

Public Works Department

B PW21-WRF01 10000 N. El Mirage Rd.
PP a Mima SCOPE OF WORK AND EI Mirage, Arizona 85335

—

=<-—=eee= | PROJECT SPECIFICATIONS Telephone: (623) 936-6405

Fax: (623) 933-8418

2. INTRODUCTION

The WRF is designed to meet Class A+ effluent requirements. Wastewater enters the WRF by way of a 24-inch gravity sewer
pipeline through a coarse bar screen to remove large solids prior to entering the influent lift station. The lift station then pumps
the influent flow to fine screens and a vortex grit basin to remove smaller solids and grit. Next, wastewater flows by gravity to
the equalization tank before being pumped to the SBRs where it undergoes treatment in sequential phases of fill, anoxic reaction,
aerobic reaction, settling, and idle. Secondary effluent decanted from the SBRs is sent to the surge basin. The surge basin serves
as storage for the secondary effluent and also provides surge capacity for the SBR system during decant.

3. BACKGROUND

After several years of operation, the plant was de-rated to 2.5 mgd by the local regulatory agency. The facility originally
operated as a Hybrid SBR treatment system that incorporated a mixed liquor recycle flow to the anoxic basins located upstream
of the SBRs. However, due to difficulties achieving treatment objectives, the facility has been converted to operate as a
traditional SBR system, removing the recycle flows, and utilizing the anoxic basin as an equalization basin.

4, CURRENT STATUS

The El Mirage WRF is currently operating near the total tertiary filtration capacity of 2.1 mgd MMADF. The filtration capacity
will be exceeded in the near future due to pending industrial development. The filter limitation is an existing problem and any
additional flows will require the additional filtration capacity through installation of new filters and diverting filter overflows to
the headworks. The current overflow design overloads the filters, increasing run times, causing premature filter break through
and decreasing effluent quality.

5. BUSINESS CASE

The CITY has evaluated the upgrades required to successfully treat the increased flows from the planned industrial development.
The planned industrial development in El Mirage will include a large data center that will initially consist of one data center
building. This building requires significant water flows for cooling operations. The cooling operations will generate an industrial
wastewater that has constituents approximately twice the constituent level of the potable water that will supply the facility.
Therefore, this water will require treatment prior to disposal or reuse. These two waste streams will be combined and conveyed
to the Water Reclamation Facility located at 10355 N. 121 Ave., El Mirage, AZ, 85335

6. PROJECT OBJECTIVES

The objectives for the project include the following:

* Project design to integrate one (1) Tertiary disc treatment filter capable of meeting industry-standard hydraulic
loading. (3 — 6 gpm/sq ft for average day and PDF's.) The existing three (3) tertiary disc treatment filters are
functioning at 50% design limiting the amount of influent flow capacity to 2.0 mgd. After review, the filter
manufacturer “Aqua-Aerobic” representative IES Southwest, Inc. has verified the current operational and maintenance
practices meet the manufacturer O & M specifications. IES Southwest also recommends the current SER line be routed
to the headworks reducing the loading on the existing and proposed additional filter.

e — Site and Structural evaluation and modifications (Deck Support)

¢ One (1) filter control cabinet designed to operate the new filter in Local/Remote mode

* Each filter to include new like level indicators, pressure differential indicators, like flow metering including
influent, effluent controi valving and associated new air/electrical piping

Page 18 of 29
PW21 - WRFOI

Public Works Department

a PW21-WRF01 10000 N. El Mirage Rd.
AE Mima SCOPE OF WORK AND El Mirage, Arizona 85335
— PROJECT SPECIFICATIONS Telephone: (623) 935-6405

Fax: (623) 933-8418

¢ Each filter to include like process controls, alarms, real time process indicators integrated into the existing
Wonderware SCADA software
« Associated electrical improvements

¢ Filter effluent disinfection methods of application upgrade. The existing disinfection application point needs to be
relocated. Short circuiting along with slow reaction times are being experienced. Forty-five (45) minute to sixty (60)
minute reaction times are common, causing over and under feeding of disinfectant. The recommendation is to improve
the mixing by injecting the chlorine into a common pipe upstream of the clear well. This can be accomplished by
combining the four (4) filter discharge piping into a single header. The existing piping can be combined with some
straightforward modifications. This modification would ensure that all filter discharge would become completely mixed
with chlorine prior to entering the Clear Well, This would improve the disinfection capabilities of the facility, and better
utilize the existing contact basin and piping to ensure sufficient disinfection at the rated plant capacity.

¢ Installation of a Secondary Effluent Recycle (SER) line. This SER line would return to the influent pumping station
(Headworks) stopping recycle through the filters, reducing filter loading and overflow while reducing sediment build up
within the surge tank. Aqua-Aerobics Director of Product Management also recommends that the existing filter
overflow piping (SER) be reconfigured to send these solids back to the head of the plant where they can be removed in
the secondary process.
© 16” recycle line to influent station, 160 LF
© Associated valve and valve controls

¢ Provide future influent/effluent pipe connections for EQ basin. The future EQ basin will allow for high flow
periods, improved process treatment and effluent water quality
o Spooled valved blind flange for future process influent piping

7, SCOPE OF SERVICES
The Scope of Services is organized in five main tasks:

Task 1 — Project Management

Task 2 - Verification of Existing Conditions
Task 3 — Basis of Design Report

Task 4 — Detailed Design

Task 5 — Permitting Services

Task 1 — Project Management

The project design build team will provide coordination of project work with disciplines to ensure project deliverables are
met. The design team will complete project setup, closeout, and invoicing during the project.

1.1 Project Meetings

The design build team will schedule a project kick-off meeting and up to four (4) project meetings during the design phase.
An updated project schedule and a written agenda for each meeting shall be prepared and submitted five working days prior
to the meeting. Meeting summary notes will be prepared and submitted to the City Project Manager within five working
days after the meeting. The meetings during the design phase wiil be as follows:

Kick-off Meeting

Draft Basis of Design Review Meeting
60% Design Review Meeting

90% Design Review Meeting

100% Design Review Meeting

Page 19 of 29
PW2I - WRFOL

Public Works Department

PW21-WRF01 10000 N. El Mirage Rd.
SCOPE OF WORK AND El Mirage, Arizona 85335
PROJECT SPECIFICATIONS Telephone: (623) 935-6405

Fax: (623) 933-8418

Task 2 — Verification of Existing Conditions

Investigations required to verify existing Record Drawings and utility “record” conditions will be provided by the design
build team. The design build team will verify record drawings and site conditions including current conditions.

2.1 Filter Placement, Structural Support and Chemical Tank Placement

A Structural Engineer will perform a structural evaluation including loading calculations for the cement deck area within the
available proposed filter (2) placement space within the chemical tank/filter area or immediately adjacent to the West.

Verify existing record drawings

Overall site conditions

Loading calculations

Structural support evaluation

Secondary site evaluation if appropriate
Influent, effluent piping location assessment

Task 3 — Basis of Design Report

A Basis of Design Report (BODR) will be prepared by the design build team that summarizes and documents the design
criteria and equipment selections. All data obtained from Task 2 should be included as an appendix to the BODR.

A draft BODR will be prepared and submitted to the City for review. Comments will be reviewed with the City and
incorporated into the final BODR.

Deliverables:

¢ One electronic version of the draft BODR shall be provided to the City of El Mirage
¢ Two (2) hardcopies and one electronic version of the final BODR shall be provided to the City of El Mirage.

Task 4 ~ Detailed Design

The design build team will prepare and submit a detailed design based on the City’s project objectives, filter manufacture
recommendation and site evaluation. The detailed design shall include detailed construction drawings, condition assessment
results, MCC, chemical feed line, tertiary filters, associated piping, valves, electrical, SER line, future EQ basin connections,
meter placements, and controls,

The design build team will prepare documents for City review at each of the design review milestones indicated in Task 1.
City review comments shall be incorporated at each milestone. The final contract documents shall be submitted in
reproducible form and submitted to the City project manager. Distribution of contract documents will be made by the City.
All supporting documentation related to the design calculations and computations will be sealed by a professional Engineer
licensed in the State of Arizona. The design build team shall prepare an engineer’s estimate of probable construction cost for
the 60%, 90%, and 100% design submittals. The final estimate will include a detailed breakdown to show the estimated
costs for the major components of the design. Estimates shall be prepared based on the price level projected for the
anticipated midpoint of construction.

Deliverables:

« Two (2) hardeopies and one electronic version of Construction drawings at 60%, 90%, and 100% project levels of
completions

« Two (2) hardcopies and one electronic version of specifications at 60%, 90%, and 100% project levels of completion

« Engineer’s estimate of probable construction cost at 60%, 90%, and 100% levels of completion

Page 20 of 29
PW21 - WRFO1

Public Works Department

EY PW21-WRF01 10000 N. El Mirage Rd.
i Mina SCOPE OF WORK AND El Mirage, Arizona 85335
or—namm= | PROJECT SPECIFICATIONS Telephone: (623) 835-6405

Fax: (623) 933-8418

Task 5 — Permitting Services

The design build team will identify, coordinate, and prepare the required permit approval documents for Maricopa County
Environmental Services Department (MCESD) and City of El Mirage Fire, Building, & Line Safety Department (FBLSD)
required for permitting in advance of construction, The permitting and inspection process is shall be completed through the
(MCESD) Approval to Construct (ATC) and Approval of Construction (AOC) process.

Once construction drawings are completed, the design build team shall prepare an ATC application package for review by
the MCESD and FBLSD. The review coordination will require the following:

© Prepare the required application package and submit to MCESD for review Respond to MCESD review comments after
consulting with City staff.
¢ Assist in obtaining any permits from FBLSD required in advance of construction,

Deliverables:

« Completed ATC application
¢ Completed AOC application
¢ Completed City of El Mirage permit application

8. LOCATION OF THE WORK:
All work is located within the City of El Mirage, Maricopa County, Arizona.

9. CONTRACTORS LICENSE

Successful proposers shall be licensed contractors through the Arizona Registrar of Contractors and have the proper
classification to perform the work specified in this contract.

10, GUARANTEE:

The Contractor shal! guarantee all work and operation of materials provided for one year after completion of the work.

11. INSPECTION

A. City Inspectors will monitor the work site(s) to report as to the progress of the work, the manner in which it is being
performed, and report whenever it appears that material furnished or work performed by the Contractor fails to fulfill
the requirements of the specifications and contract. The Inspectors may direct the attention of the Contractor to such
failures or infringement.

B. In a case of a dispute arising between the Inspector and the Contractor as to material furnished or the manner of
performing the work, the Inspector shall have the authority to reject materials or suspend the work until the question and
issue can be referred to and decided by the Public Works Director or designee. Inspectors are not authorized to revoke,
alter, enlarge, relax, or release any requirements of the specifications. Inspectors shall in no case act as foremen or
perform other duties for the Contractor or interfere with the management of the work by the Contractor.

C. Inspection or supervision by the Public Works Director or designee shall not be considered as direct control of the
individual worker and/or his/her work. The direct control shall be solely the responsibility of the Contractor.

Page 21 of 29
PW21 - WRFO1

Public Works Department

Be PW21-WRF01 10000 N. El Mirage Ra.
| 9 i Mimace SCOPE OF WORK AND EI Mirage, Arizona 85335
——< sara PROJECT SPECIFICATIONS Telephone: (623) 935-6405

Fax: (623) 933-8418

12. PROTECTION OF FINISHED OR PARTIALLY FINISHED WORK

The Contractor shall properly guard and protect all finished or partially finished work and shall be responsible for the same
until the entire contract is completed and accepted by the City. Partial payment on work so completed shall not release the
Contractor from such responsibility, but he/she shall turn over the entire work in full accordance with these specifications
before final settlement shall be made.

13. STOCKPILE OF MATERIALS

D. The contractor may, if approved by the Project Manager, place materials in the public right-of-way provided they do not
prevent access to adjacent properties or prevent compliance with traffic regulations.

E. Traffic shall not be required to travel over stockpiled materials, and proper dust contro! shall be maintained.

14, SUPERVISION BY CONTRACTOR

The Contractor shall supervise and direct the work and shall be solely responsible for the means, methods, techniques,
sequences, and procedures of construction. The Contractor shall employ and maintain at the work site a qualified supervisor
or superintendent who shall have been designated in writing by the Contractor as the Contractor's representative at the site.
The representative shall have full authority to act on behalf of the Contractor and all communications given to the
representative shall be as binding as if given to the Contractor. The representative shall be present on the site at all times as
required to perform adequate supervision and coordination of the work.

15. STANDARD SPECIFICATIONS AND DETAILS

Except as otherwise noted, construction of this project and all work done under this Contract shall be in accordance with
these specifications and all applicable Uniform Standard Specifications For Public Works Construction sponsored and
distributed by MAG, MAG Standard Details, the City of El Mirage supplements to MAG Standard Details, and City of
Peoria supplements to MAG Standard Details, including the latest approved revisions thereto in force at the time of bid
advertisement, which shall be referred to hereinafter as the "Standard Specifications". In all cases where accepted standards
(American Water Works Association (AWWA), American National Standards Institute (ANSI), MAG, etc.) are referred to
in the "Standard Specifications", the latest revisions as of bid advertisement shall prevail.

16. DUMPING AND DISPOSAL OF WASTE

The Contractor is responsible for the cost to dispose of all waste products including excess earth material which will not be
incorporated into the work under this contract. The waste product referred to herein shall become the property of the
Contractor, unless otherwise directed by the Public Works Director

17. CLEAN UP

Clean up shall include the removal of all excess materials in conjunction with the project accumulated on any driveways,
curbs, landscaping, or any other surface. No special payment will be made for this item,

The Contractor shall, upon completion of the work, remove all temporary construction facilities, debris, and unused
materials provided for in the work, and put the work site of the work and public right-of-way in a neat and clean condition.
No special payment will be made for this item.

Page 22 of 29
PW2!1 - WRFOL

Public Works Department

PW21-WRF01 10000 N. El Mirage Rd.
SCOPE OF WORK AND El Mirage, Arizona 85335
PROJECT SPECIFICATIONS Telephone: (623) 935-6405

Fax: (623) 933-8418

18.

19,

20.

21.

DUST PREVENTION

The Contractor shall take whatever steps, procedures or means required to prevent abnormal dust conditions due to
construction operations in connection with this contract. The dust control measures shall be maintained at all times during
construction of the project to the satisfaction of the Public Works Director and in accordance with the requirements of the
Maricopa County Health Department Air Pollution Control and Environmental Protection Agency (EPA) regulations. The
project will be small enough where a separate Dust Control Permit will not be required. Contractor will work under the
City’s Dust Control permit

MISCELLANEOUS REMOVAL AND RELOCATIONS

Miscellaneous removals and relocations shall be construed to mean the removal of all unsuitable materials whether
designated or implied by the plans and specifications and shall include but not be limited to the removal of such items as
Pipes, concrete, asphalt, block, brick, rock, metal, etc. of every nature and description, unless such items are specifically
designated in a separate bid item.

PROJECT COMPLETION

“Project Completion” is full completion of all construction associated with a contract, including, but not limited to punch list
items, close out documentation, O & M manuals, warranties, and record drawings as certified by the Architect or Engineer
of record.

FINAL ACCEPTANCE

"Final Acceptance" shall mean a written final acceptance of the work by the Public Works Director and shall make the final
acceptance promptly after all work under the contract has been completed in accordance with the contract documents and
after final inspection.