P1 Paving quote and pricing contract

City of El Mirage — Regular Meeting (2021-07-08)

View PDF Item 9 Meeting page

Extracted text (via pymupdf) 2408 characters
P1 Paving and Construction LLC 
 
8550 N 91ST AVE STE. 65 PEORIA, ARIZONA 85345 
OFFICE:  (623) 594-7174  FAX: (623) 594-7159 
 
P R O P O S A L 
 
 
 
 
CITY OF ELMIRAGE 
 
ATTN: Marcus Johnson 
 
SUBJECT: Fire Station Pad 
 
P1 Paving and Construction submits the following proposal for your consideration and acceptance. 
 
Saw cut and remove curb, estimated 65 LF 
Remove existing concrete hose pad 
Grade, prep and pour 10” depth concrete steel reinforced pad 65’x55’x10” 
Haul off all removals and construction debris 
                                                                                                                                               $50,000.00 
 
Install 1-1/2” copper water line with 2 water spigots                                                          $8,000.00 
 
Install 1-1/2” electrical conduit from new sub panel to new structure 
1- 20 Amps lighting circuit 
2- 20 Amps outlet circuits to supply 6 power points                                                  $12,000.00 
 
                                                                                                                           Total $70,000.00 
 
                                                                                                                                                                             
Proposal includes/excludes the following: 
Saw Cutting 
yes 
x no 
 
Utility adjustments 
yes 
 
no 
x 
Prevailing Wage 
yes 
 
no 
x 
Survey & Engineering 
yes 
 
no 
x Slurry / Micro Seal 
yes 
 
no 
x 
Sales Tax 
yes 
 
no 
x 
Sub-Grade Prep 
yes 
 
no 
x Rubberized Asphalt 
yes 
 
no 
x 
Permits & Testing 
yes 
 
no 
x 
Concrete haul off 
yes 
x no 
 
Barricades 
yes 
 
no 
x 
Nights/Weekends 
yes 
 
no 
x 
Haul off Asphalt 
Removals 
yes 
 
no 
x Hot Rubber Asphalt Joint 
Sealer 
yes 
 
no 
x 
Plant opening fees 
yes 
 
no 
x 
 
PROVISIONS: 
 
1. 
All work is to be measured upon completion and will be billed at the unit cost for the measured quantities with minimum invoice for 
the quantity of work stated in the description of work above. 
2. 
Work will not be scheduled until an acceptable contract containing these unit prices, inclusions,  
exclusions and provisions have been signed by both parties. 
 
 
 
 
 
 
  
Bob Slawson 
P1 Paving and Construction LLC 
 
 
 
     
DATE: 6/22/2021 
  
 PRICE GOOD THRU: 10-31-2021 
 
ACCEPTED BY:  ____________