Operating Manual for Vertical Job Order Contracting 
 
April 2017 
ARIZONA DEPARTMENT OF 
ADMINISTRATION 
 
OPERATING MANUAL FOR 
VERTICAL JOB ORDER 
CONTRACTING 
 
 
 April 19, 2017 
 
 
 
 
STATEWIDE VERTICAL 
 JOB ORDER CONTRACTING  
 
 
 
OWNER 
 
DEPARTMENT OF ADMINISTRATION 
for and on behalf of 
STATE OF ARIZONA

State of Arizona 
2 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
OPERATING MANUAL 
FOR VERTICAL JOB 
ORDER 
CONTRACTING 
 
 
• 
This Operating Manual is a legally binding contract document and is one of the Contract 
Documents. 
 
• 
All Detailed Scopes of Work under each Job Order and the other activities of Contractor under 
the JOC Program and all activities of Owner and the Design Professional, relating to the JOC 
Program must be in accordance with the requirements in all of the Contract Documents, 
regardless of whether the requirements are included in this Operating Manual or in another JOC 
Contract Document. 
 
• 
Statements of Qualifications (SOQs) submitted in responses to the solicitation do not modify or 
change any of the other Contract Documents. Nothing in the SOQs shall be construed to replace 
or supersede any provision of any of the other Contract Documents or Job Orders. If there is a 
conflict between anything in the SOQs and any provision of any other Contract Document or 
Job Order, the provision of the other Contract Documents and Job Orders shall be given effect 
and the conflicting material in the SOQs will not be given effect. 
 
Contractor agrees to perform Job Orders and the Contractor’s obligations and to comply with the terms and 
conditions applicable to Contractor under this Operating Manual and the other Contract Documents. Owner 
agrees to perform its obligations and to comply with the terms and conditions applicable to Owner under 
this Operating Manual and the other Contract Documents.

State of Arizona 
3 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
TABLE OF CONTENTS 
Section 1. 
DEFINITIONS ........................................................................................................................................ 4 
Section 2. 
REFERENCES ...................................................................................................................................... 8 
Section 3. 
JOC PROGRAM OVERVIEW .............................................................................................................. 17 
Section 4. 
COMMON GOAL, TEAM CONCEPT ................................................................................................... 19 
Section 5. 
ADMINISTRATION OF JOC PROGRAM ............................................................................................. 20 
Section 6. 
JOB ORDER DEVELOPMENT SERVICES AND ISSUANCE OF JOB ORDERS… ............................ 35 
Section 7. 
JOB ORDER PRICE ............................................................................................................................ 36 
Section 8. 
PROCEDURES TO DEVELOPS ALL JOB ORDERS ...........................................................................37 
Section 9. 
SUBCONTRACTORS AND SUPPLIERS ............................................................................................ 48 
Section 10. 
INSPECTIONS..................................................................................................................................... 49 
Section 11. 
PROJECT CLOSEOUT ....................................................................................................................... 52 
Section 12. 
MEASUREMENT AND PAYMENT ...................................................................................................... 62 
Section 13. 
CHANGES IN WORK .......................................................................................................................... 65 
Section 14. 
SITE CONDITIONS.............................................................................................................................. 66 
Section 15. 
ADJUSTMENT OF THE ADJUSTMENT FACTORS… ........................................................................ 68 
Section 16. 
TIME PERIOD TO ISSUE JOB ORDERS… ......................................................................................... 69 
Section 17. 
ADMISTRATIVE AND COOPERATIVE … .......................................................................................... 70 
Section 18. 
MARKETING THE CONTRACT.......................................................................................................... 71 
Section 19. 
SOFTWARE LICENSING… ................................................................................................................. 72 
APPENDIX 1.  FORM OF JOB ORDER… ....................................................................................................................... 73 
FORM OF JOB ORDER ATTACHMENT 4 ASBESTOS STATEMENT… ........................................................................ 75

State of Arizona 
4 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
SECTION 1 
DEFINITIONS 
1.1 
The following terms will have the following meanings when used in the Operating Manual. 
However, to the extent that a term is defined differently in a separate Contract Document, the 
definition used in that document will be controlling. Terms defined below or in the Contract 
Documents are sometimes used without initial capitals. In each such case they will have their 
respective defined meanings. 
 
1.2 
If not specifically defined, terms, words and phrases in the Contract Documents will have their 
ordinary and common meanings, with undefined words, phrases and abbreviations interpreted 
consistent with construction and design industry standards and technical and trade meanings. 
 
1.3 
Each reference in a Contract Document to a section, appendix, attachment or exhibit is a 
reference to the respective section in appendix, attachment or exhibit attached to that Contract 
Document. 
 
A. 
“Adjustment Factor” – means the adjustment factor supplied by Contractors in the 
Negotiations phase of the Request for Qualifications, and as modified by amendment to be 
applied to the Unit Prices listed in the Construction Task Catalog®. 
 
B. 
“All Working Hours” means all day Monday through Friday, Saturday, Sunday, and 
Owner Holidays. 
 
C. 
“Construction Schedule” means a graphic construction schedule showing the completion 
of the Detailed Scope of Work within the Job Order Completion Time. 
 
D. 
“Construction Start Date” means the date specified in a Job Order for the Contractor to begin 
the Detailed Scope of Work. 
 
E. 
“Contract” means the Agreement between the State and Contractor as a result of the 
Request for Qualifications, as modified from time to time by Amendments. 
 
F. 
“Contract Date” means the effective start date of the Contract. 
 
G. 
“Contractor” means the contractor named on the Offer and Acceptance page of the 
Contract. 
 
H. 
“Contractor’s Project Manager” means the person designated as Contractor’s Project 
Manager for the JOC program. Contractor’s Project Manager is responsible for the daily 
oversight of the Site Manager. 
 
I. 
"Day" means a calendar day unless specifically otherwise provided herein or by law. 
 
J. 
“Detailed Scope of Work” means a document setting forth the work the Contractor is 
obligated to complete for a particular Job Order. 
 
K. 
“Design Professional” means the person employed by the firm engaged by the customer 
under separate contract to perform Design Services relating to the Detailed Scope of Work 
for a Job Order and who is designated as the Design Professional in the Job Order. For 
some Job Orders there will be no Design Professional (see Owner Representative 
definition below). 
 
L. 
“Design Services” means professional architect services and/or professional engineer 
services that are within the scope of architectural practice or engineering practice, 
respectively, as provided in Arizona Revised Statutes Title 32, Chapter 1. Design Services 
includes preparation of the Drawings and Specifications for the Detailed Scope of Work. 
Contractor will not provide Design Services in the JOC Program. Owner will arrange for 
such Design Services as Owner determines are needed for each Job Order.

State of Arizona 
5 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
 
M. 
“Drawings” means the drawings, if any, referenced in the Detailed Scope of Work and 
attached thereto. 
1. 
he drawings referenced in the Detailed Scope of Work may be detailed drawings 
prepared by a Design Professional on behalf of Owner, approved by Owner and 
Owner Representative and, when required by law, stamped and sealed as required 
by law, including a hard copy and a set in electronic format. 
 
2. 
Alternatively, for some Job Orders there will be no drawings prepared by a Design 
Professional, in which case Owner will deliver to Contractor a Detailed Scope of 
Work that may reference line drawings and/or include a written description of the 
work. 
 
N. 
“Estimated Annual Value” means an estimate of the value of Job Orders that could be 
issued to the Contractor each year. 
 
O. 
“JOC Program” means Owner’s job order contracting construction services program under 
the Contract Documents. 
 
P. 
“Job Order” means a written order, signed by the Owner, requiring the Contractor to 
complete the Detailed Scope of Work for the Job Order Price within the Job Order 
Completion Time. Each Job Order will consist of a written Detailed Scope of Work, the Job 
Order Price and a purchase order from the owner to the contractor, Drawings and any other 
documents indicated on the Job Order Form. 
 
Q. 
“Job Order Completion Time” means the time frame specified in the Job Order by which the 
Contractor shall have started and completed the Detailed Scope of Work, including, without 
limitation, all deficiency, correction and incomplete items (Punch List). 
 
R. 
“Job Order Development Services” means all activities of Contractor prior to the Owner 
issuing a Job Order for a particular project as set forth in Section 8 the Procedures to 
Develop all Job Orders. This will include, without limitation: (i) assisting the Owner in 
determining whether to complete a Project in Job Order Contracting, (ii) preparing or 
assisting in the preparation of a Detailed Scope of Work, (iii) and preparing or revising a 
Job Order Proposal.  Job Order Development Services does not include performance of 
the Detailed Scope of Work. 
 
S. 
“Job Order Price” means the fixed price appearing in the Job Order that the Contractor will 
be paid by the Owner for the successful completion of the Detailed Scope of Work within the 
Job Order Completion Time. 
 
T. 
“Job Order Price Proposal” means a price proposal prepared by the Contractor that includes 
the Pre-priced Tasks, Non Pre-priced Tasks, quantities and appropriate Adjustment Factors 
required to complete the Detailed Scope of Work.  
 
U. 
“Job Order Proposal” means a set of documents including at least: (a) Job Order Price 
Proposal; (b) required drawings, sketches, or layouts; (c) list of anticipated Subcontractors; (d) 
Construction schedule; (e) technical data or information on proposed materials or equipment, 
and (f) other requested documents. 
 
V. 
“Job Order Proposal Request” means a written request to the Contractor to prepare a 
Job Order Proposal for the Detailed Scope of Work referenced therein. 
 
W. 
“Joint Scope Meeting” means a site meeting to discuss the Work before the Detailed 
Scope of Work is finalized. 
 
X. 
“Legal Requirements” means all regulations, policies and practices of Owner and all 
applicable rules, laws, codes, ordinances and regulations of any governmental or quasi- 
governmental entity, federal, state and local, having jurisdiction over Contractor, any

State of Arizona 
6 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
Subcontractor, any Job Order or the Detailed Scope of Work, the practices involved 
thereunder, or any other action performed by Contractor or any Subcontractor. Legal 
Requirements does not include sales, use, consumer, income and other taxes. 
 
Y. 
“Management Plan” means the management plan submitted in the Contractor’s SOQ, with 
such modifications as are negotiated and agreed to by the Owner at time of contract award, 
unless otherwise modified in writing by mutual agreement. 
 
Z. 
“Minimum Contract Value” means the minimum value of Job Orders that the Contractor 
is guaranteed the opportunity to perform under this Contract. 
AA. 
“Minor Change” means a change in the Detailed Scope of Work having no impact on the 
Job Order Price or Job Order Completion Time or Owner’s approved design intent, as 
determined by Owner. 
 
BB. 
“Non Prepriced Task” means an item of Work required by the Detailed Scope of Work 
but not included in the Construction Task Catalog®. 
 
CC. 
“Normal Working Hours” means the hours from 7:00 a.m. to 5:00 p.m. Monday through 
Friday, except for Owner holidays. 
 
DD. 
“Operating Manual” means this Operating Manual (Operating Manual for Vertical Job 
Order Contracting) (including, without limitation, the appendices), as modified from time to 
time by Amendments. 
 
EE. 
“Option Period” means an additional period of time beyond the Contract Term which 
extends the termination date of the Contract. 
 
FF. 
“Other than Normal Working Hours” means the hours of 5:01 p.m. to 6:59 a.m. Monday 
through Friday and all day Saturday, Sunday, and Owner Holidays.  
 
GG. 
 “Owner” means the organization as defined in the Job Order. 
 
HH. 
 “Owner Representative” means the person who is designated as the Owner 
Representative in the Job Order. The Owner Representative performs the roles and duties 
of the Design Professional proscribed in this Operating Manual when no Design 
Professional is listed in the Job Order. Communication given and roles performed by the 
Owner Representative are deemed to come from and be performed by the Owner. 
 
II. 
 “Prepriced Task” means an item of Work included in the Construction Task Catalog® for 
which a unit price is given. 
 
JJ. 
 “Price Proposal” means a price proposal prepared by the Contractor that includes the 
Prepriced Tasks, Non Prepriced Tasks, quantities and appropriate Adjustment Factors 
required to complete the Detailed Scope of Work prepared in accordance with the 
Procedures to Develop all Job Orders. 
 
KK. 
 “Procurement Officer of Record” means the Procurement Officer who is responsible     
for the administration of the statewide Job Order Contracting program. 
 
LL. 
“Project” means the collective improvements to be constructed by the Contractor pursuant 
to a Job Order, or a series of related Job Orders. 
 
MM. 
 “Punch List” means the list of deficiency, correction and incomplete items developed as 
provided in Section 10 “Inspections”. 
 
NN. 
“Secure Locations” means those buildings and grounds (sites) that require specific 
security-related criteria where access to the work site or the site’s daily operations 
negatively affects the Contractor’s productivity on a daily basis. These include but are not 
limited to public access and operations security.  These locations require the Contractor to

State of Arizona 
7 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
follow stipulated requirements to perform work at the site, without exception.  Examples of 
such sites include but are not limited to those for the State Facilities at Sky Harbor Airport 
(Department of Emergency and Military Affairs), Arizona Department of Corrections and 
Arizona Department of Juvenile Corrections. At the Joint Scope Meeting, any areas of work 
that are considered secure locations will be identified. 
 
OO. 
 “Statement of Qualifications” means all information and documents submitted by 
Contractor relating to Request for Qualifications #ADSPO17-00007249 including, without 
limitation, Contractor’s formal sealed qualifications package and all other qualifications 
documents, that is, all documents and materials delivered by Owner to Contractor or by 
Contractor to Owner in connection with Owner’s RFQ selection process. 
 
PP. 
 “Site” means the location, or locations, where the Detailed Scope of Work or a portion 
thereof will be performed. 
 
QQ. 
 “Site Manager” means the individual designated as Contractor’s site manager for the     
JOC Program, who shall be the person proposed in Contractor’s SOQ in response to the 
RFQ. The Site Manager will report to the Contractor’s Project Manager and supervise all 
Work conducted at each site. Contractor is permitted to replace the Site Manager only 
under the conditions provided in Section 5 “Administration of JOC Program” of this 
Operating Manual. 
 
RR. 
 “Subcontractor” means a person or company providing labor and materials  in  
connection with a Detailed Scope of Work, to the Contractor or to a Subcontractor of any 
tier. The term Subcontractor includes all Suppliers. 
 
SS. 
“Substantial Completion” means a point in time during construction, when the Detailed 
Scope of Work, or a specified portion thereof that the Owner agrees to accept separately, 
is, in accordance with the Contract Documents and Job Order, certified by the Design 
Professional as complete sufficiently enough to allow the Owner to occupy or utilize the 
Detailed Scope of Work, or such portion thereof, for its intended use. 
 
TT. 
 “Supplemental Job Order” means a secondary Job Order developed after the initial Job 
Order has been issued for the purpose of changing, deleting, or adding work to the initial 
Detailed Scope of Work, or changing the Job Order Completion Time. 
 
UU. 
 “Supplier” means a person providing materials, supplies or equipment to be included in   
the Work to Contractor or any Subcontractor. 
 
VV. 
 “Technical Specifications” means the written requirements for materials, equipment, 
systems, standards and workmanship for the Work, and performance of related services. 
The Technical Specifications apply for all Job Orders and are hereby included by reference 
into all Job Orders, whether or not specifically mentioned therein. The Technical 
Specifications may be amended unilaterally by the Owner from time to time in writing. 
 
WW. 
“Unit Price” means the price published in the Construction Task Catalog® for a specific 
construction or construction related work task. Unit Prices for new Prepriced Tasks can be 
established during the course of the Contract and added to the Construction Task 
Catalogs®. Each Unit Price is comprised of labor, equipment, and material costs to 
accomplish that specific Prepriced Task. 
 
XX. 
 “Work” means generally the construction, alteration, rehabilitation, remodeling, renewal, 
renovation, repair, maintenance and demolition and all labor, materials, supplies, tools, 
equipment, transportation, site cleanup, storage and disposal of construction or demolition 
debris, supervision, management, overhead and profit, bonds, insurance, licenses and 
permits, taxes, intellectual property royalty and license fees, all other activities and items 
required to perform the Job Orders and the requirements of the Contract Documents.

State of Arizona 
8 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
SECTION 2 
REFERENCES 
 
2.1 
QUALITY ASSURANCE 
 
A. 
For products or workmanship specified by association, trades, or Federal Standards: 
Comply with requirements of the standard, except when more rigid requirements are 
specified or are required by applicable codes. 
 
B. 
Publication Dates: Comply with standards in effect as of date of the Job Orders unless 
otherwise indicated. 
 
C. 
Abbreviations and Acronyms: Where abbreviations and acronyms are used in 
Specifications or other Contract Documents, they shall mean the recognized name of the 
entities in the following list. Names, telephone numbers, and Web site addresses are 
subject to change and are believed to be accurate and up-to-date as of the date of the 
Contract Documents. 
 
D. 
Should specified reference standards conflict with Contract Documents, request 
clarification from Owner Representative before proceeding with Detailed Scope of Work. 
 
E. 
The contractual relationship of the parties to the Contract shall not be altered from the 
Contract Documents by mention or inference otherwise in any reference document. 
 
2.2 
SCHEDULE OF REFERENCES 
 
AA 
Aluminum Association, Inc. (The) 
www.aluminum.org 
(703) 358-2960 
AABC 
Associated Air Balance Council 
www.aabchq.com 
(202) 737-0202 
AAMA 
American Architectural Manufacturers Association 
www.aamanet.org 
(847) 303-5664 
AASHTO 
American Association of State Highway and 
Transportation Officials 
www.aashto.org 
(202) 624-5800 
ACI 
American Concrete Institute/ACI International 
www.aci-int.org 
(248) 848-3700 
ADC 
Air Diffusion Council 
www.flexibleduct.org 
(847) 706-6750 
AFPA 
American Forest & Paper Association 
(See AF&PA) 
AF&PA 
American Forest & Paper Association 
(800) 878-8878 
www.afandpa.org 
(202) 463-2700 
AGA 
American Gas Association 
www.aga.org 
(202) 824-7000 
AHA 
American Hardboard Association 
http://domensino.com/AHA/ 
(847) 934-8800 
AI 
Asphalt Institute 
(859) 288-4960

State of Arizona 
9 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
www.asphaltinstitute.org 
AISC 
American Institute of Steel Construction, Inc. 
(800) 644-2400 
www.aisc.org 
(312) 670-2400 
AISI 
American Iron and Steel Institute 
www.steel.org 
(202) 452-7100 
AITC 
American Institute of Timber Construction 
www.aitc-glulam.org 
(303) 792-9559 
ALSC 
American Lumber Standard Committee 
www.alsc.org 
(301) 972-1700 
AMCA 
Air Movement and Control Association International, Inc. 
www.amca.org 
(847) 394-0150 
AMG 
Arizona Masonry Guild 
www.masonaryforlife.com 
(602) 265-5999 
ANSI 
American National Standards Institute 
www.ansi.org 
(202) 293-8020 
APA 
APA-The Engineered Wood Association 
www.apawood.org 
(253) 565-6600 
APA 
Architectural Precast Association 
www.archprecast.org 
(239) 454-6989 
API 
American Petroleum Institute 
www.api.org 
(202) 682-8000 
ARI 
Air-Conditioning, Heating & Refrigeration Institute 
www.ari.org 
(703) 524-8800 
ARMA 
Asphalt Roofing Manufacturers Association 
www.asphaltroofing.org 
(202) 207-0917 
ASCE 
American Society of Civil Engineers 
(800) 548-2723 
www.asce.org 
(703) 295-6300 
ASHRAE 
American Society of Heating, Refrigerating and 
(800) 527-4723 
Air-Conditioning Engineers 
www.ashrae.org 
(404) 636-8400

State of Arizona 
10 
Operating Manual for Vertical Job Order Contracting 
 
April 19, 2017 
April 2017 
ASME 
ASME International 
(800) 843-2763 
(The American Society of Mechanical Engineers 
International) 
www.asme.org 
(212) 591-7722 
ASSE 
American Society of Sanitary Engineering 
www.asse-plumbing.org 
(440) 835-3040 
ASTM 
ASTM International 
www.astm.org 
(610) 832-9585 
AWCI 
AWCI International 
(Association of the Wall and Ceiling Industries 
International) 
www.awci.org 
(703) 538-1600 
AWI 
Architectural Woodwork Institute 
www.awinet.org 
(571) 323-3636 
AWPA 
American Wood-Preservers' Association 
www.awpa.com 
(205) 733-4077 
AWS 
American Welding Society 
(800) 443-9353 
www.aws.org 
(305) 443-9353 
AWWA 
American Water Works Association 
(800) 926-7337 
www.awwa.org 
(303) 794-7711 
BHMA 
Builders Hardware Manufacturers Association 
www.buildershardware.com 
(212) 297-2122 
BIA 
Brick Industry Association 
www.gobrick.com 
(703) 620-0010 
BICSI 
BICSI 
www.bicsi.org 
(813) 979-1991 
BOCA 
BOCA International, Inc. 
www.bocai.org 
(708) 799-2300 
CABO 
Council of American Building Officials 
(See ICC) 
CCC 
Carpet Cushion Council 
www.carpetcushion.org 
(610) 527-3880 
CDA 
Copper Development Association Inc. 
(800) 232-3282 
www.copper.org 
(212) 251-7200 
CFFA 
Chemical Fabrics & Film Association, Inc. 
www.chemicalfabricsandfilm.com 
(216) 241-7333

State of Arizona 
11 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
CFR 
Code of Federal Regulations 
(888) 293-6498 
www.access.gpo.gov/nara/index.html 
(202) 512-1530 
CIMA 
Cellulose Insulation Manufacturers Association 
(888) 881-2462 
www.cellulose.org 
(937) 222-2462 
CISCA 
Ceilings & Interior Systems Construction Association 
www.cisca.org 
(630) 584-1919 
CISPI 
Cast Iron Soil Pipe Institute 
www.cispi.org 
(404) 622-0073 
CLFMI 
Chain Link Fence Manufacturers Institute 
Email: clfmigh@aol.com  and www.chainlinkinfo.org 
(301) 596-2583 
CRD 
Army Corps of Engineers 
Handbook for Concrete and Cement 
www.wes.army.mil 
(601) 634-2355 
CRI 
Carpet and Rug Institute (The) 
(800) 882-8846 
www.carpet-rug.com 
(706) 278-3176 
CRSI 
Concrete Reinforcing Steel Institute 
www.crsi.org 
(847) 517-1200 
CSA 
CSA International 
(800) 463-6727 
(Formerly: IAS - International Approval Services) 
www.csa-international.org 
(416) 747-4000 
CSSB 
Cedar Shake & Shingle Bureau 
www.cedarbureau.org 
(604) 820-7700 
DHI 
Door and Hardware Institute 
www.dhi.org 
(703) 222-2010 
DOC 
Department of Commerce 
www.doc.gov 
(202) 482-2000 
DOD 
Department of Defense 
Military Specifications and Standards 
www.dodssp.daps.dla.mil 
(215) 697-6257 
EIA 
Electronic Industries Alliance 
www.eia.org 
(703) 907-7500 
EIMA 
EIFS Industry Members Association 
(800) 294-3462 
www.eima.com 
(770) 968-7945 
EPA 
Environmental Protection Agency 
www.epa.gov 
(202) 260-2090 
FDA 
Food and Drug Administration 
www.fda.gov 
(888) 463-6332 
FMG 
FM Global 
(Formerly: FM - Factory Mutual System) 
www.fmglobal.com 
(401) 275-3000

State of Arizona 
12 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
FS 
Federal Specification 
Available from Department of Defense Single Stock Point 
www.dodssp.daps.dla.mil 
(215) 697-6257 
Available from General Services Administration 
www.gsa.gov 
(202) 619-8925 
Available from National Institute of Building Sciences 
www.nibs.org 
(202) 289-7800 
FSC 
Forest Stewardship Council 
www.fscoax.org 
GA 
Gypsum Association 
www.gypsum.org 
(301) 277-8686 
GANA 
Glass Association of North America 
(Formerly: FGMA - Flat Glass Marketing Association) 
www.glasswebsite.com 
(785) 271-0208 
HI 
Hydraulic Institute 
(888) 786-7744 
www.pumps.org 
(973) 267-9700 
HI 
Hydronics Institute 
www.gamanet.org 
(908) 464-8200 
HPVA 
Hardwood Plywood & Veneer Association 
www.hpva.org 
(703) 435-2900 
HUD 
Department of Housing and Urban Development 
www.hud.gov 
(202) 708-1112 
IAS 
International Approval Services 
(See CSA International) 
ICC 
International Code Council 
(Formerly: CABO - Council of American Building Officials) 
www.intlcode.org 
(888) 422-7233 
ICBO 
International Code Council 
(888) 422-7233 
www.iccasafe.org 
(202) 783-2348 
ICEA 
Insulated Cable Engineers Association, Inc. 
www.icea.net 
(770) 830-0369 
IEEE 
Institute of Electrical and Electronics Engineers, Inc. (The) 
www.ieee.org 
(800) 678-4333

State of Arizona 
13 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
IESNA 
Illuminating Engineering Society of North America (The) 
www.iesna.org 
(212) 248-5000 
IGCC 
Insulating Glass Certification Council 
www.igcc.org 
(315) 646-2234 
IGMA 
Insulating Glass Manufacturers Alliance (The) 
(Formerly: SIGMA - Sealed Insulating Manufacturers 
Association) 
www.igmaonline.org 
(613) 233-1510 
ILI 
Indiana Limestone Institute of America, Inc. 
www.iliai.com 
(812) 275-4426 
ISSFA 
International Solid Surface Fabricators Association 
www.issfa.net 
(888) 464-7732 
ITS 
Intertek Testing Services 
(800) 345-3851 
www.itsglobal.com 
(607) 753-6711 
KCMA 
Kitchen Cabinet Manufacturers Association 
www.kcma.org 
(703) 264-1690 
LMA 
Laminating Materials Association 
(Formerly: ALA - American Laminators Association) 
www.lma.org 
(201) 664-2700 
LPI 
Lightning Protection Institute 
(800) 488-6864 
www.lightning.org 
(847) 577-7200 
MAG 
Maricopa Association of Governments 
www.azmag.gov 
(602) 254-6300 
MBMA 
Metal Building Manufacturers Association 
www.mbma.com 
(216) 241-7333 
MFMA 
Maple Flooring Manufacturers Association 
www.maplefloor.org 
(888) 480-9138 
MFMA 
Metal Framing Manufacturers Association 
www.metalframingmfg.org 
(312) 644-6610 
MIA 
Marble Institute of America 
www.marble-institute.com 
(440) 250-9222 
MIL 
Military Specification Promulgated by Military 
www.everyspec.com 
MPI 
Master Painters Institute 
www.paintinfo.com 
(888) 674-8937

State of Arizona 
14 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
MSS 
Manufacturers Standardization Society 
(703) 281-6613 
www.mss-hq.com 
NAAMM 
National Association of Architect Metal 
Manufacturers 
www.naamm.org 
(630) 942-6591 
NCMA 
National Concrete Masonry Association 
www.ncma.org 
(703) 713-1900 
NEBB 
National Environmental Balancing Bureau 
www.nebb.org 
(301) 977-3698 
NEC 
National Electrical Code 
P.O. Box 9101, Quincy, MA 02269-9101 
NECA 
National Electrical Contractors Association 
www.necanet.org 
(301) 657-3110 
NeLMA 
Northeastern Lumber Manufacturers' Association 
www.nelma.org 
(207) 829-6901 
NEMA 
National Electrical Manufacturers Association 
www.nema.org 
(703) 841-3200 
NETA 
InterNational Electrical Testing Association 
www.netaworld.org 
(269) 488-6382 
NFPA 
NFPA International 
(800) 344-3555 
www.nfpa.org 
(617) 770-3000 
NFRC 
National Fenestration Rating Council 
www.nfrc.org 
(301) 589-1776 
NLGA 
National Lumber Grades Authority 
www.nlga.org 
(604) 524-2393 
NOFMA 
National Wood Flooring Manufacturers Association 
www.nwfa.org 
(901) 526-5016 
NRCA 
National Roofing Contractors Association 
(800) 323-9545 
www.nrca.net 
(847) 299-9070 
NSF 
NSF International 
(800) 673-6275 
(National Sanitation Foundation International) 
www.nsf.org 
(734) 769-8010 
NTMA 
National Terrazzo and Mosaic Association 
www.ntma.com 
(800) 323-9736 
NWWDA 
National Wood Window and Door Association 
(See WDMA) 
PCA 
Portland Cement Association 
www.cement.org 
(847)966-6200 
PCI 
Precast/Prestressed Concrete Institute 
(312) 786-0300

State of Arizona 
15 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
PDCA 
www.pci.org 
Painting and Decorating Contractors of America 
(800) 332-7322 
www.pdca.com 
RCSC 
Research Council on Structural Connections 
c/o AISC 
www.boltcouncil.org 
RFCI 
Resilient Floor Covering Institute 
www.rfci.com 
(706) 882-3833 
RIS 
Redwood Inspection Service 
www.redwoodinspection.com 
(925) 935-1499 
SAE 
SAE International 
www.sae.org 
(724) 776-4841 
SDI 
Steel Deck Institute 
www.sdi.org 
(847) 458-4647 
SDI 
Steel Door Institute 
www.steeldoor.org 
(440) 899-0010 
SIGMA 
Sealed Insulating Glass Manufacturers Association 
(See IGMA) 
SJI 
Steel Joist Institute 
www.steeljoist.org 
(843) 626-1995 
SMACNA 
Sheet Metal and Air Conditioning Contractors' National 
Association 
www.smacna.org 
(703) 803-2980 
SPIB 
Southern Pine Inspection Bureau (The) 
www.spib.org 
(850) 434-2611 
SPRI 
SPRI 
(Single Ply Roofing Industry) 
www.spri.org 
(781) 647-7026 
SSPC 
SSPC:  The Society for Protective Coatings 
(412) 281-2331 
www.sspc.org 
(877) 281-7772 
STI 
Steel Tank Institute 
www.steeltank.com 
(847) 438-8265 
TCA 
Tile Council of America, Inc. 
www.tileusa.com 
(864) 646-8453 
TFS 
Texas Forest Service 
www.txforestservice.tamu.edu 
(936) 639-8180 
TIA/EIA 
Telecommunications Industry Association/ Electronic Industries 
Alliance 
www.tiaonline.org 
(703) 907-7700 
TMS 
The Masonry Society 
www.masonrysociety.org 
(303) 939-9700

State of Arizona 
16 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
TPI 
Truss Plate Institute, Inc. 
www.tpinst.org 
(703) 683-1010 
UL 
Underwriters Laboratories Inc. 
(800) 704-4050 
www.ul.com 
(877) 854-3577 
WCLIB 
West Coast Lumber Inspection Bureau 
(800) 283-1486 
www.wclib.org 
(503) 639-0651 
WCMA 
Window Covering Manufacturers Association 
(See WCSC) 
(212) 661-4261 
WCSC 
Window Covering Safety Council 
(800) 506-4636 
www.windowcoverings.org 
(212) 297-2100 
WDMA 
Window & Door Manufacturers Association 
(Formerly: NWWDA - National Wood Window and Door 
Association) 
www.wdma.com 
(800) 223-2301 
WI 
Woodwork Institute 
(Formerly: WIC - Woodwork Institute of California) 
www.wicnet.org 
(916) 372-9943 
WIC 
Woodwork Institute of California 
(See WI) 
WMMPA 
Wood Moulding & Millwork Producers Association 
(800) 550-7889 
www.wmmpa.com 
(530) 661-9591 
WWPA 
Western Wood Products Association 
www.wwpa.org 
(503) 224-3930

State of Arizona 
17 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
SECTION 3 
JOC Program Overview 
 
3.1 
The Contract Documents establish a Job Order Contracting program including regional Job Order 
Contracts. 
 
3.2 
This Contract is an indefinite quantity contract pursuant to which the Contractor may perform an 
ongoing series of individual projects at different locations throughout the State as identified by 
seven (7) separate regions. See Request for Qualifications, PART 11, EXHIBIT 1, “Regions Map.” 
The Contract documents include a Construction Task Catalog® (CTC) containing construction tasks 
with preset unit prices. All unit prices are based on local labor, material and equipment costs and 
are for the direct cost of construction only. The Contract Documents also include the Technical 
Specifications. 
 
3.3 
Prior to contract award, the State and the highest-ranking Contractor’s on the short list will negotiate 
Adjustment Factors to be applied to the unit prices in any resultant contract. When preparing a Job 
Order Price Proposal, the Contractor shall select the appropriate Adjustment Factor for each task. 
Those Adjustment Factors are as follows: 
 
A. 
Adjustment Factor for performing Work during Normal Working Hours for Owner funded 
projects; 
B. 
Adjustment Factor for performing Work during Other Than Normal Working Hours or All 
Working Hours at Secure Locations for Owner funded projects; 
C. 
Adjustment Factor for performing Work during Normal Working Hours for Federally funded 
projects; 
D. 
Adjustment Factor for performing work during Other Than Normal Working Hours or All 
Working Hours at Secure Locations for Federally funded projects. 
3.4 
Secure Locations means those buildings and grounds (sites) that require specific security-related 
criteria where access to the work site or the site’s daily operations negatively affects the 
Contractor’s productivity on a daily basis. These include but are not limited to public access and 
operations security.  These locations require the Contractor to follow stipulated requirements to 
perform work at the site, without exception.  Examples of such sites include but are not limited to 
those for the State Facilities at Sky Harbor Airport (Department of Emergency and Military Affairs), 
Arizona Department of Corrections and Arizona Department of Juvenile Corrections. At the Joint 
Scope Meeting, any areas of work that are considered secure locations will be identified. 
 
3.5 
As projects are identified the Contractor will attend a Joint Scope Meeting with the Owner, Design 
Professional, and others. The Owner will prepare a Detailed Scope of Work and issue a Job Order 
Proposal Request to the Contractor. The Contractor will then prepare a Job Order Proposal for the 
project including a Price Proposal, proposed Construction Schedule, Sketches and/or Drawings, a 
list of Subcontractors, and other requested documentation. If the Proposal is found to be 
acceptable, a Job Order may be issued. 
 
3.6 
A Job Order will reference the Detailed Scope of Work and set forth the Job Order Completion 
Time, and the Job Order Price. The Job Order Price is determined by multiplying the preset unit 
prices by the appropriate quantities and by the appropriate Adjustment Factor as set forth in more 
detail in Section 8, Procedures to Develop all Job Orders. The Job Order Price shall be a lump 
sum, fixed price for the completion of the Detailed Scope of Work. Changes, deletions and additions 
to the Detailed Scope of Work will be contained in Supplemental Job Orders. 
 
3.7 
The Work to be performed under this Contract will be building, alteration, system replacement, 
remodeling, renovation, maintenance and repair of real property in the State of Arizona, in 
accordance with SECTION 5, “Scope of Work/Requirements Document”. 
 
3.8 
The Work to be performed under this Contract will include tasks in a combination of trades, for 
example, carpentry, excavation, electrical, sheet metal, painting, demolition, concrete, masonry

State of Arizona 
18 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
and welding. 
 
3.9 
It is anticipated that the Contractor will perform multiple Job Orders. 
 
3.10 
The Owner will pay the Contractor the Job Order Price for completing the Detailed Scope of Work 
within the Job Order Completion Time. 
 
A. 
Each Job Order issued under this Contract for a project shall not be a minimum dollar 
value. Since Supplemental Job Orders are for changes, deletions, and additions to an 
existing Project, Supplemental Job Orders may be for less than $5,000 and some may 
have a negative value. The total value of all Job Orders and Supplemental Job Orders 
issued in connection with a single project shall not exceed $1,000,000 for State agencies 
and up to their authorized Job Order Contracting dollar thresholds for Cooperative Program 
Members. 
B. 
For each Job Order issued between $1.00 to $1000.00 the Contract may charge a one-
time trip charge of not to exceed $100.00. 
 
3.11 
The Minimum Contract Value of Job Orders to be issued under each term of the Contract shall be 
$0.00. 
3.12 
Owner will have the right to elect to perform work of the types included in the Contract Documents 
itself or to have other contractors perform such work. Such action by Owner will not be a breach of, 
or otherwise violate, the Contract Documents.

State of Arizona 
19 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
SECTION 4 
COMMON GOAL, TEAM CONCEPT 
 
4.1 
The common goal for the JOC Program is the completion of quality construction projects meeting 
Owner’s needs, budget, and time schedule, at a reasonable and appropriate cost to Owner, and 
with a reasonable and appropriate fee for the Contractor, Subcontractors and any Design 
Professionals. 
 
4.2 
Owner, Contractor, Subcontractors and any Design Professionals commit, at all times, to 
cooperate, coordinate, collaborate and communicate fully with each other and with others involved 
in each Job Order and in the Job Order Contracting Program. 
 
4.3 
Owner, Contractor, Subcontractors and any Design Professionals will try to anticipate potential 
problems before they arise. They will communicate promptly with each other, and they will act 
quickly and cooperatively and in coordination to find ways to avoid potential problems. For problems 
that actually arise, they will attempt to solve actual problems early by identifying them as early as 
possible and acting on them quickly. Regardless of its nature, each potential or actual problem is 
a “team” or “project” problem that Owner, Contractor, Subcontractors and any Design Professionals 
will try to solve together cooperatively and collaboratively. 
 
4.4 
The JOC Program is not to be used as a comparison pricing mechanism for departments to 
find out how much a project will cost when compared to other procurement methods.  In 
advance of using the JOC Program, user should have already researched options for procurements 
and concluded that JOC is the best method for the project.

State of Arizona 
20 
Operating Manual for Vertical Job Order Contracting 
 
April 2017 
SECTION 5 
ADMINISTRATION OF JOC PROGRAM 
5.1 
Planning, Progress and Scheduling; Communications; Meetings; and Reports (if required per Job 
Order Form). 
 
A. 
Planning, scheduling and progress monitoring are essential functions of Contractor. 
 
B. 
Contractor shall employ and supply a sufficient force of workers, material and equipment, 
and shall complete each Detailed Scope of Work with such diligence as to maintain a 
steady rate of progress, to prevent Work stoppage and to ensure completion of each Job 
Order within the Job Order Completion Time. 
 
C. 
All project notices, requests, instructions, modifications, approvals, and claims must be in 
writing, unless expressly specified otherwise in the Contract Documents. 
 
D. 
Copies of all communications from Contractor to Design Professional, or Owner 
Representative shall be delivered to Owner. 
 
E. 
Computer Requirements. The Contractor shall maintain at its office for its use a computer 
with, at a minimum, a 1 GHz processor and an internet connection. The Contractor shall 
maintain individual email accounts for each of its project managers. 
 
 
5.2 
JOC Program Meetings (if required per Job Order Form). 
 
A. 
There will be regular oversight meetings attended by the Site Manager and the Owner 
Representative concerning the JOC Program, as determined by the Contract Procurement 
Officer of Record. Each meeting will be held at a time and day designated by Owner 
Representative. 
 
B. 
There will be separate ad hoc meetings attended by the Site Manager when requested by 
the Owner Representative or the Site Manager. 
 
5.3 
Individual Project Meetings (if required per Job Order Form). 
 
A. 
If Owner determines that a meeting on a particular Job Order is necessary and appropriate, 
then at a time designated by Owner, a progress meeting will be held at the Site. Contractor, 
together with representatives of its major Subcontractors, shall attend, as will the Owner 
and its representatives. Contractor shall be responsible for notifying Subcontractors of their 
required attendance. The purpose of this meeting will be to discuss the progress of the 
Detailed Scope of Work and to resolve any problems that may have developed or that are 
anticipated. Unless followed up in writing, verbal authorizations or acknowledgments by 
anyone present shall not be binding. 
 
5.4 
Meeting Minutes (if required per Job Order Form). 
 
A. 
Owner Representative, or Contractor if designated by Owner Representative, will take and 
issue minutes for all meetings. 
 
5.5 
Reports (if required per Job Order Form). 
 
A. 
One day before any scheduled Owner Representative and Site Manager meeting, 
Contractor will deliver to Owner Representative an update report (“Update Report”) for the 
JOC Program showing the following: 
 
1. 
A list of all prospective, but not yet issued, Job Orders, the status of each actual or 
anticipated issue related to each prospective Job Order and recommended action 
to resolve each issue.

State of Arizona 
21 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
2. 
A list of all issued and in process Job Orders, the status of each, actual or 
anticipated, issues relating to each Job Order, and recommended action to resolve 
each issue. 
 
3. 
Any other actual or anticipated issue relating to the JOC Program and 
recommended action to resolve each issue. 
 
5.6 
Administrative. 
 
A. 
Contractor agrees that it will have, or will establish, and will maintain during the JOC 
Program an administrative office at which Contractor will administer the JOC Program. 
 
5.7 
Hazardous Materials or Substances. (Also, see Special Terms and Conditions, Paragraph 3.20, 
Asbestos Containing Material and Hazardous Materials and Substances.) 
 
A. 
Definitions 
 
1. 
“Hazardous Substance” means a substance, material or hazardous waste which, 
by reason of being explosive, flammable, poisonous, corrosive, oxidizing, irritating 
or otherwise harmful, is likely to cause death or injury. 
 
2. 
“Hazardous Waste” means “hazardous waste”, as defined in the Resource 
Conversation and Recovery Act of 1976 and the Solid Waste Disposal Act (42 
U.S.C. 6901 et seq.) and any successor statutes and any regulations, rules or 
guidelines promulgated pursuant thereto as in effect from time to time (including, 
without limitation, any such waste resulting from removal of, demolition of, 
modifications of or additions to part or all of any existing structure, facility or 
equipment). 
 
3. 
“Contractor Hazardous Waste” means any Hazardous Waste arising during or 
from Work that is generated by the acts or omissions of Contractor or a 
Subcontractor. 
 
4. 
“Release” means any discharging, disposing, dumping, emitting, emptying, 
escaping, injecting, leaching, leaking, pouring, pumping, releasing, spilling, or 
similar action or event. 
 
5. 
“Contractor Release” means any Release of a Hazardous Substance on Owner’s 
property during the Work arising from acts or omissions of Contractor or any 
Subcontractor. This includes a Release of a Hazardous Substance pre- existing 
on Owner’s property under the following circumstances: 
 
a. 
If Owner has made Contractor aware of the existence of the Hazardous 
Substance pre-existing on Owner’s property and if Owner has provided an 
area free from the Hazardous Substance sufficient for Contractor to 
perform the Work; or 
 
b. 
If Owner has not made Contractor aware of the pre-existing Hazardous 
Substance on Owner’s property, but Contractor or any Subcontractor 
failed to act reasonably when it encountered the Hazardous Substance. 
 
6. 
“Owner Hazardous Waste” means Hazardous Waste (i) in any existing structure, 
facility or equipment on Owner’s property or otherwise present on Owner’s 
property at commencement of the Work, and (ii) that is not Contractor Hazardous 
Waste. 
 
7. 
“Project Hazardous Waste” means any Hazardous Waste arising on Owner’s 
property as the result of Work identified in the Detailed Scope of Work.

State of Arizona 
22 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
8. 
“OSHA” means the Federal Occupational Safety and Health Act (29 U.S.C. 
Section 651 et seq.) and any successor statutes and any regulations, rules or 
guidelines promulgated pursuant thereto as in effect from time to time. 
 
B. 
Compliance with Environmental Law and OSHA. Contractor shall, and shall cause each 
Subcontractor, to comply with all Environmental Law and provisions of OSHA applicable 
to: (1) Contractor; (2) Subcontractors; (3) the Detailed Scope of Work under each Job Order 
and; (4) all of their activities in respect to any Work. 
 
C. 
General Provisions on Contractor Hazardous Waste. 
 
1. 
Contractor is liable for the cleanup of, and any injury resulting from, Hazardous 
Waste generated by Contractor. 
 
2. 
Contractor is liable for the cleanup of, and any injury resulting from, any 
unreasonable acts by Contractor or Subcontractor involving Hazardous Waste. 
 
3. 
Owner is not liable for any injury to Contractor or Subcontractors caused by 
hazardous waste existing on Owner’s property at the commencement of the 
Detailed Scope of Work if Owner has provided notice to Contractor of pre- existing 
hazardous waste. 
 
D. 
General Provisions on Hazardous Substances. 
 
1. 
Hazardous Substances, excluding Hazardous Waste, may be transported to and 
from, and stored, and used on Owner’s property in such quantities as are generally 
recognized to be usual and customary for performance of the Detailed Scope of 
Work. 
 
2. 
Hazardous Waste may be generated on Owner’s property of such kinds and in 
such quantities as are generally recognized to be usual and customary in 
connection with performance of the Detailed Scope of Work. Hazardous Waste so 
generated may not be stored on Owner’s property without prior approval of Owner. 
 
3. 
Prior to final completion of the Detailed Scope of Work, Contractor shall remove 
from Owner’s property, and dispose of in accordance with Environmental Law and 
OSHA, any Hazardous Substances brought onto Owner’s property  during the 
Detailed Scope of Work or used in connection with the Detailed Scope of Work. 
 
4. 
Other than as provided in the three preceding paragraphs immediately above, 
Contractor shall not, and Contractor shall cause all Subcontractors to not,  dispose 
of, generate, manufacture, process, produce, Release, treat or otherwise store, 
use or have in or on, or transport to or from Owner’s property any Hazardous 
Substance, regardless of whether the Hazardous Substance is preexisting on 
Owner’s property of otherwise. 
 
E. 
Releases of Hazardous Substances 
 
1. 
Upon any Release of any Hazardous Substance in connection with the Detailed 
Scope of Work, whether relating to a pre-existing condition on Owner’s property 
(for example, arising from any demolition of, removal of, modification of, or addition 
to any structure, facility or equipment) or relating to acts or omissions of Contractor 
or a Subcontractor, Contractor shall take any immediate action reasonably 
necessary to contain the Release.

State of Arizona 
23 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
2. 
If the Release is not a Contractor Release, Owner will pay Contractor the 
reasonable costs incurred by Contractor in taking such reasonably necessary 
immediate action necessary to contain the Release. 
 
3. 
Owner may elect to have Contractor control and carry out any containment, clean-
up, removal and remediation activity as to a Release. If the Release is not a 
Contractor Release, Owner will pay Contractor reasonable costs and expenses of 
performing such activity. If the Release is a Contractor Release, Contractor shall 
pay all such costs and expenses. Contractor will not be obligated to begin 
performing the activities, and shall not begin the activities, until Contractor and 
Owner have agreed in writing on the tasks to be performed by Contractor and the 
amount to be paid to Contractor, if any, for performing the activities. 
 
4. 
Alternatively, Owner shall have the right to elect to control and carry out any 
containment, clean-up, removal and remediation activities. 
 
5. 
Regardless of who carries out the activities in the preceding two paragraphs, 
Contractor shall absorb, without reimbursement from Owner, all costs and expense 
incurred by Contractor in connection with any Contractor Release. In addition, 
Contractor shall pay or reimburse Owner for all costs and expenses incurred by 
Owner relating to any Contractor Release, including without  limitation, costs and 
expenses of third parties engaged by Owner. If the amount  is not paid promptly, 
Owner may offset the amount against any amount payable by Owner to Contractor 
under the Job Order or otherwise. 
 
6. 
Remediation, removal, and other cleanup action arising from any Release shall be 
in full compliance with Environmental Law and OSHA and shall be subject to 
approval by Owner. In addition, Owner may require remedial, removal or other 
cleanup action in excess of applicable minimum requirements of Environmental 
Law and OSHA (A) as reasonably necessary or appropriate in the judgment of 
Owner to permit human use and habitation of Owner’s property and to permit use 
of Owner’s property for its intended use, and (B) as reasonably consistent in the 
judgment of Owner with such habitation and uses. 
 
F. 
Hazardous Waste 
 
1. 
Owner will arrange for handling, storage and disposal of any Owner Hazardous 
Waste. 
 
2. 
Contractor shall assure proper handling (including, without limitation, segregation 
from waste that is not Hazardous Waste) and storage of Contractor and Project 
Hazardous Waste in full compliance with Environmental Law and OSHA. 
 
3. 
If Owner discovers that Contractor has not properly handled Contractor and Project 
Hazardous Waste, Owner may make arrangements for proper disposal of said 
Contractor or Project Hazardous Waste. Contractor shall pay all of Owner’s 
expenses of storing, handling and disposing of Project and Contractor Hazardous 
Waste. Owner will deliver a statement to Contractor showing Owner’s expenses, 
and Contractor will promptly pay such amount to Owner. If the amount is  not paid 
promptly, Owner may offset the amount against any amount payable by Owner to 
Contractor under the Job Order or otherwise. 
 
G. 
Environmental Notifications to Owner 
 
1. 
Contractor shall notify Owner immediately upon occurrence of any of the following:

State of Arizona 
24 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
a. 
any discovery by Contractor or a Subcontractor of any Hazardous 
Substance in any existing structure, facility or equipment on Owner’s 
property. 
 
b. 
any Release of any Hazardous Substance on Owner’s property in 
connection with the Detailed Scope of Work; 
 
c. 
the creation or generation of any Hazardous Waste resulting from the 
Detailed Scope of Work (including, without limitation, Hazardous Waste 
arising from the removal of, demolition of, modification of, or addition to 
any existing structure, facility or equipment); 
 
d. 
the need for any remediation or removal of any Hazardous Substance 
relating to the Detailed Scope of Work whether relating to a pre-existing 
condition on Owner’s property or to acts or omissions of Contractor or a 
Subcontractor; or 
 
e. 
any claim, demand, inquiry, investigation, litigation or other action or 
proceeding by any governmental authority or other person relating to any 
Hazardous Substance, Hazardous Waste, Environmental Law or OSHA 
relating to Work. 
 
2. 
Except for immediate action to contain any Release of any Hazardous Substance 
and except for interim handling and storage of Project Hazardous Waste, 
Contractor shall not take any action on any of the above matters without the prior 
written approval of Owner, and Owner shall have the right to elect to control and 
carry out any such action or matter. 
 
5.8 
Material Safety Data Sheet Submittals. 
 
A. 
Contractor shall include a copy of the MSDSs with the packing list or other suitable shipping 
document that accompanies each shipment to the job site. 
 
B. 
Prior to shipping hazardous materials (solids, liquids, cryogenic liquids, gases) hereunder, 
Contractor shall provide the Owner with two (2) copies of the Material Safety Data Sheet 
(MSDS) [U.S. Department of Labor "OSHA Voluntary form (Non-Mandatory Form)" or 
equivalent thereof] for each material, inclusive of all required information. 
 
C. 
The Contractor shall notify the Owner’s Representative of any hazardous or toxic materials 
or any combination thereof that may produce a hazardous environment or any potentially 
dangerous process intended for use at the project site. The submittal will include the safety 
or control measures the Contractor proposes to implement. The Contractor shall not deliver 
any such material to the project site until so authorized by the Owner’s Representative. 
This clause will be included in any subcontract issued for Work on this contract. 
 
D. 
Where two (2) or more hazardous materials are supplied separately or in kit form for the 
purpose of combining such materials to form an end compound that is the result, in whole 
or in part, of a chemical reaction, Contractor will provide an MSDS for the end compound 
as well as for each component part. 
 
E. 
The Contractor shall provide an MSDS for any propellant or explosive. In the case of 
explosive devices, the MSDS may be specific for the explosive device or may be the MSDS 
for the explosive material contained in the device. 
 
F. 
Contractor shall send one (1) copy of the MSDS to the Owner's Representative prior to 
shipment and include one copy with the shipment.

State of Arizona 
25 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
G. 
Proprietary or trade secret information about products containing a hazardous material, as 
defined above, will be disclosed as required by applicable statutes and government rules, 
regulations, and orders. 
 
H. 
Mandatory resubmission of an MSDS is required with each change in formulation of the 
material that affects its hazardous characteristics, with each change in information 
regarding the material's hazardous characteristics, and with each change in information 
regarding handling procedures for the material. 
 
I. 
The Contractor shall include, or cause to be included, the following additional information 
in an attachment to the MSDS: 
 
1. 
NFPA (National Fire Protection Association) hazard identification signal numbers 
and symbols; 
 
2. 
Proper DOT shipping name, UN number, hazard-class number, packing group 
number, labeling requirements, and any specialized container requirements; and 
 
3. 
DOT Exemptions and Department of Defense Certificate of Equivalency (COE) - 
Any solid or liquid chemical material, gases, and all cryogenic liquids that require 
specification containers or cylinders must be so supplied, unless Seller obtains and 
submits applicable DOT Exemptions or Department of Defense COEs to Buyer as 
provided above. 
 
J. 
All primary containers of hazardous materials shall bear labels that comply with  all aspects 
of the labeling requirements in all applicable statutes and government rules, regulations, 
and orders. 
 
K. 
All inside and outside shipping containers shall comply in all respects with all applicable 
statutes and government rules, regulations, and orders, utilizing specification containers 
when required. 
 
L. 
The MSDS shall be furnished at the time of delivery of the material. Failure to provide the 
MSDS with the material at time of delivery will result in rejection of the material pursuant to 
the provisions of this contract addressing acceptance, rejection, and/or inspection of 
goods. 
 
M. 
The Contractor shall submit one (1) copy of the MSDS, unless a previous copy of the MSDS 
has been submitted and is still valid. The MSDS shall be sent to the following appropriate 
address depending on where the Job Order originated: 
 
Owner Representative as shown in Section IV of the Job Order 
 
5.9 
Indoor Air Quality Control Requirements 
 
A. 
General. The Contractor shall follow design approaches of the Sheet Metal and Air 
Conditioning National Contractors Association (SMACNA) IAQ Guidelines for Occupied 
Buildings under Construction, 2nd Edition, ANSI / SMACNA 008 - 2008, and ASHRAE std 
62.1-2010. 
 
The Contractor shall follow project specific strategies and requirements to ensure the best 
possible building environment is maintained during the construction project. The existence 
of construction dirt, dust, toxins and objectionable odors in the occupant’s workspace is 
unacceptable. To avoid occupant exposure to diminished air quality during construction or 
renovation projects, Contractors and Subcontractors shall follow the following guidelines: 
 
1. 
Indoor Air Quality (IAQ) Management Plan (applicable to all Job Orders over 
$100,000).       The Contractor shall implement an indoor air quality management

State of Arizona 
26 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
plan to be approved by the Owner’s Representative. The purpose of the plan is  to 
prevent residual problems with indoor air quality in the completed building and to 
protect workers on the site and building occupants from undue health risks during 
construction. The plan shall identify specific measures to address: 
 
a. 
Control of problem substances, including: construction dust, chemical 
fumes, off-gassing materials, and moisture. The plan will ensure that these 
substances are not introduced into the building environment during, or 
upon completion of construction. 
 
b. 
Pre-project planning, including: 
 
1) 
Hazardous product identification and substitution, 
 
2) 
Materials storage, 
 
3) 
Safe installation, 
 
4) 
Project sequencing, 
 
5) 
Monitoring, and 
 
6) 
Cleanup. 
 
2. 
Scheduling. Whenever possible, the Contractor shall schedule all activities that 
can be reasonably anticipated to compromise indoor air quality for times in which 
the building is not occupied. Scheduling of activities such as the installation of 
sealants, caulks, paints, etc. will be sequenced such that proper venting of 
objectionable odors can be accomplished to keep odor emissions as low as 
reasonably achievable. 
 
3. 
HVAC Protection – During Construction. Contractor shall protect and enclose 
ductwork on site to keep all supply, return and exhaust ductwork free of dust, dirt, 
mold and air-borne contaminants. All open ends of installed supply, return, exhaust 
ductwork or return air shaft openings are to be sealed by the Contractor with plastic 
materials to prevent contamination, until startup or testing/operation of system. 
When the air distribution systems will be operating during construction, Contractor 
shall include temporary filtration media on all return air openings and check/replace 
during construction as necessary to ensure that building air quality and system 
operation are not impacted. The central filtration system shall be monitored and 
clean filters will be installed by the Contractor during heavy construction. 
 
a. 
Return Air Systems. Contractor shall shut down all return air systems and 
openings during the heaviest periods of construction to prevent dust and 
odors from entering the system and settling in the ductwork, or being 
released throughout the building. 
 
b. 
Supply. Contractor shall keep the supply side of the  HVAC  system clean. 
When the HVAC system is off, Contractor shall cover all ducts and 
diffusers, and inspect and clean them as necessary. During start up, it will 
be common for some dirt to be discharged, however if it is a considerable 
amount of debris Contractor shall change the filters until the proper indoor 
air quality is restored. 
 
c. 
Filtration. Contractor shall replace installed filtration media with new 
materials at the end of construction, prior to occupancy. MERV ratings of 
filters used during construction will meet LEED IAQ Credit requirements.

State of Arizona 
27 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
Daily monitoring of temporary filters during heavy construction activity 
shall be performed by Contractor. 
 
If any HVAC equipment will be operated during construction, Contractor 
shall use temporary air filters with a minimum MERV-8 rating on all return 
air openings and within the air handing equipment and 100% outdoor 
makeup air will be utilized in lieu of return air from construction spaces. 
 
d. 
Duct Work.  Contractor shall comply with the following: 
 
1) 
All ductwork sections, fan terminal unit (FTUs) and variable air 
volume (VAV) boxes and equipment in storage or staged on site, 
shall be physically protected by wrapping in plastic and covering 
completely, and stored in a clear area, free from construction 
activities on wood blocking supports with a minimum of four (4) 
inches off the floor surface until installed. Absorptive insulating 
materials shall be weather protected from moisture damage. 
 
2) 
All openings to include piping, ductwork, and conduit system 
openings shall be closed at the end of each work day for systems 
under construction, or when HVAC equipment is shutoff at end of 
day for operational systems. Ductwork and/or insulation, which 
contain moisture or is wet, shall not be installed. Installed 
ductwork and/or insulation, which is wet, shall be removed and 
replaced with new. All newly installed fresh air intake louvers, 
openings, ductwork, etc. for indoor air handling units, perimeter 
louvers, exhaust openings, etc. shall be covered with plywood and 
plastic until ready to be operational. Ductwork, after installation, 
shall be kept clean. 
 
3) 
All open ends of installed supply, return, exhaust ductwork or 
return air shaft openings shall be sealed by the Contractor with 
plastic materials to prevent contamination, until startup or 
testing/operation of system. 
 
4) 
All condensate drain flows from mechanical equipment shall be 
constantly monitored for leaks, proper flow and blockage 
prevention. 
 
5) 
For projects with special minimum or maximum indoor humidity 
levels as required for proper preparation or installation 
environment for millwork, casework, wood finishes and 
furnishings, etc. Contractor’s project construction team shall 
collectively plan means and methods to achieve minimum or 
maximum humidity levels, and provide these plans to the Owner’s 
Representative. 
 
6) 
Central filtration media in equipment shall be changed on a regular 
basis by the Contractor in conformance with Sheet Metal & Air 
Conditioning 
Contractors’ 
National 
Association 
(SMACNA 
Standards and to meet LEED Requirements. 
 
7) 
At completion of construction and prior to occupancy, temporary 
filtration media in all equipment shall be removed and replaced 
with permanent filters with a minimum MERV-13 rating unless 
specified permanent filtration media is as good or a better rating, 
in accordance with LEED Requirements.

State of Arizona 
28 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
8) 
Specific IAQ requirements and procedures regarding prevention 
of airborne infection isolation, air pressure and exchange ranges, 
filtration and control requirements for specific healthcare and 
laboratory spaces shall be handled on a job-specific basis and 
issued by addendum to the project requirements. 
 
4. 
Source Control – During Construction 
 
a. 
A concurrent approach for maintaining construction indoor air quality is 
source/pollution control. Whenever possible, electric powered equipment 
shall be utilized in lieu of fuel powered equipment to limit combustion 
discharge into the project site. 
 
b. 
The Contractor shall implement measures for exhausting all contaminants 
out of the building and away from air intakes. Construction processes 
which may create a hazardous environment, or create objectionable odors 
such as installation of epoxy flooring, etc. shall be properly identified during 
construction and signage will be posted to advise workers of potential 
hazards or personal protective equipment requirements. Whenever 
practicable, the Contractor shall utilize methods such as local recirculation 
of air by filtering out all odors and dust; all filters shall be properly selected 
for the materials they will be controlling. Determination of odor control and 
ventilation means shall be made by and at the expense of the installing 
Subcontractor. 
 
c. 
Construction areas that create a large amount of contaminants as defined 
by the (SMACNA) IAQ Guideline for Occupied Buildings under 
Construction and OSHA Guidelines, whether air borne dust, or drywall 
dust shall be properly ventilated away from other construction activities  to 
reduce the transfer of the contaminants from one work area to another 
work area. 
 
d. 
Temporary exhaust fans directed to the building exterior shall be provided 
by at the expense of the installing Subcontractor. 
 
e. 
All finish materials (i.e. carpet, ceramic tile, paints, stains, etc.) shall be 
covered or contained prior to installation and after installation as much as 
possible, along with all waste material by the installing Subcontractor. 
 
f. 
Construction activities shall be inspected for visible moisture when 
installing drywall by the installing Subcontractor. Upon identification of 
moisture in drywall by the installing Subcontractor and with the assistance 
of the Owner’s Representative, the source of the moisture is to be verified 
and eliminated and specific measures to remediate will be followed. 
 
g. 
No materials shall be covered up which are wet or can absorb moisture. 
Wall vapor barriers shall be checked constantly by the installing 
Subcontractor for proper installation. 
 
5. 
Reduce Construction Dust. Construction generated dusts shall be contained to the 
greatest possible extent though the use of vacuum assisted drywall sanding 
equipment, and use of vacuums instead of brooms to clean construction dust from 
floors. 
 
6. 
Ventilation. The Contractor shall use volatile organic compound (VOC) free or  low 
VOC products whenever possible. All products that cannot be used as above due 
to architect requirements must have the product reviewed and approved   by

State of Arizona 
29 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
the Owner’s Representative. In addition, activities that release VOCs into a facility 
may require, at the discretion of the Owner’s Representative, temporary ventilation 
systems until the building returns to its pre-construction condition. These include 
but are not limited to: painting (even with no- or low-VOC paints), spreading of floor 
adhesives, and use of large amounts of caulk, sealants, and cleaning agents. 
Additionally, the installation of large amounts of building materials, such as carpet 
or vinyl-based flooring products and composite wood cabinets and shelves, may 
require extra ventilation. 
 
7. 
VOC–Emitting Products (Carpet, Paints, Furnishings) – Supplemental Ventilation. 
An exhaust fan shall be used to pull the air out of the building, not to push outdoor 
air into the building. The fan shall be placed in a window or exterior door as close 
to the Work area as possible, and any openings in the window or door around the 
fan shall be temporarily sealed with plastic or cardboard. A window or exterior 
door at the opposite end of the room or building is to be opened, so that outdoor 
air will flow across the work area and sweep polluted air out through the exhaust 
fan. Exhaust Fans shall provide at minimum 5 air changes per hour (5 ACH). 
Ventilation shall continue for a minimum of 24 hours after completion, or until there 
are no longer any noticeable odors. 
 
8. 
Wet Sanding Methods for Gypsum Board Assemblies. Exception: Dry sanding is 
acceptable if the following measures are taken: 
 
a. 
Full isolation of space under finishing. 
 
b. 
Plastic protection sheeting is installed to provide air sealing during the 
sanding. 
 
c. 
Closure of all air system devices and ductwork. 
 
d. 
Sequencing of construction precludes the possibility of contamination of 
other spaces with gypsum dust. 
 
e. 
Worker protection is provided. Use safety meetings, signage, and 
Subcontractor agreements to communicate the goals of the construction 
indoor air quality plan. 
 
9. 
Clean Spills Immediately. If solvents, cleaners, gasoline, or other odorous or 
potentially toxic liquids are spilled onto the floor, Contractor shall clean up 
immediately. If a spill occurs on an easily replaced building material, Contractor 
shall replace with new material. 
 
10. 
Pathway Interruption – During Construction. All project equipment and material 
staging areas shall be located away from critical air flow pathways. Mechanical 
rooms and air handling equipment areas shall not be used as storage space for 
construction materials and waste. 
 
11. 
Housekeeping – During Construction. Contractor shall clean up construction 
waste, debris and rubbish during all phases of construction. All lunch papers, cups 
and other litter shall be placed into trash receptacles. Food and drinks, other than 
drinking water, shall not be allowed in the building interior. Cigarette smoking, cigar 
smoking or chewing tobacco shall not be allowed in the building interior. 
 
Before sealing up a vertical shaft or chase, the bottom area and all surfaces shall 
be cleaned of trash, dust, dirt and debris by shaft construction and installing 
Subcontractor. Loose insulation media material installation shall be controlled and 
monitored by the installing Subcontractor and shall prevent fiber discharge or 
particle release. Contractor shall provide pedi-mats or clean gravel

State of Arizona 
30 
April 2017 
Operating Manual for Vertical Contractor Job Order Contracting 
 
to limit foot traffic dirt from migrating into the building for each construction entry 
location. 
 
12. 
Use of Combustion Equipment Indoors Prohibited. Engines and heaters that run 
on gasoline, diesel, kerosene, or other fossil fuels shall not be operated indoors 
unless approved by Owner’s Representative, and only when large quantities of 
exhaust ventilation are provided to remove combustion pollutants such as carbon 
monoxide and moisture. 
 
13. 
Liquid Storage Outdoors. To reduce the possibility of spills during storage, transfer, 
or mixing, all odorous or toxic liquids are to be stored in a previously approved 
location outside the building and protected against heat or freezing. 
 
14. 
Indoor Air Quality – Post Construction, Prior to Occupancy. 
 
a. 
Upon completion of the project and prior to occupancy, the Owner may 
contract with an independent agency to perform a complete hygienic test 
of indoor air quality by an industrial hygienist certified in comprehensive 
practice by the American Board of Industrial Hygiene. 
 
b. 
IH testing may be used to verify accordance with the US Green Building 
Council Criteria and referenced EPA Standards and may include testing 
for formaldehyde, particulates (PM10) total volatile organic compounds, 
and 4-phenylcyclohexane. One sample may be taken for each 25,000 
square foot area, as a maximum. 
 
c. 
The US Green Building Council Criteria also includes guidelines for carbon 
dioxide which may either be measured when the building is fully occupied, 
or may be calculated based on ventilation measurements. Testing of 
carbon dioxide levels may be included in hygienic testing. 
 
d. 
Multiple sets of samples of each suspect compound may be taken in the 
newly completed areas and sent to certified laboratory facilities. For each 
material sample sent, a blank may be included as a quality control check. 
To insure appropriate detection limits, samples may be taken for 
approximately seven (7) hours. 
 
e. 
If sampling is done in accordance with the above paragraphs, laboratory 
facilities accredited by the American Industrial Hygiene Association shall 
be used to complete analyses. Independently documented results, which 
compare the sample results to the US Green Building Council Guidelines, 
shall be provided. The Action Plan for corrective measures when any 
unfavorable readings are encountered in any testing zone for any level 
above the pre-determined thresholds, shall be to verify the source of the 
unfavorable readings with the industrial hygienist; remediate or eliminate 
the source; perform ventilation flush-out; perform additional testing at the 
expense of the contractor responsible for the installation or introduction of 
the source of the unfavorable readings. 
 
5.10 
Contractor’s Management of the Detailed Scope of Work 
 
A. 
Contractor shall competently and thoroughly direct and superintend the Detailed Scope of 
Work and shall be solely responsible for all construction safety, means, methods, 
techniques, sequences and procedures. 
 
B. 
Contractor shall coordinate and schedule the Detailed Scope of Work, the performance of 
all its employees, agents, independent contractors, Subcontractors and Suppliers, and the 
timely procurement of all necessary labor, materials, equipment, supplies, and all else 
needed to complete the Detailed Scope of Work.

State of Arizona 
31 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
C. 
Contractor shall at all times enforce strict discipline and good order among the workers on 
each Job Order and shall not employ or continue to employ on any Job Order any unfit 
person or any person not skilled in the Work assigned to him. Contractor shall be 
responsible to Owner for all acts and omissions of its employees, agents, independent 
contractors, Subcontractors, Suppliers, anyone whom Contractor may allow to perform, 
inspect or supervise any Work, and their employees, agents and independent contractors 
together with anyone whom Contractor may allow to come on the Site. In addition, if 
Contractor receives written notice from Owner to dismiss any unskilled or unfit 
Subcontractors, Suppliers, employees, agents or independent contractors or one who is a 
hindrance to proper or timely execution of the Work, Contractor shall dismiss the same and 
agrees to replace those dismissed without delay to the Work and at no additional cost to 
Owner. At Arizona Department of Corrections locations, background checks and 
clearances are required for all Contractor and Subcontractor employees. 
 
5.11 
Contractor’s Site Manager 
 
A. 
Contractor shall employ as Site Manager a proposed Site Manager in Contractor’s 
Statement of Qualifications submitted in response to Owner’s Request for Qualifications 
and necessary assistants. 
 
B. 
Among other activities, the Site Manager shall (i) perform the Job Order Development 
Services for prospective Job Orders when requested by Owner, (ii) oversee the Detailed 
Scope of Work under each Job Order, (iii) oversee all of the Contractor’s activities with 
respect to the Job Orders and (iv) visit the Sites as necessary and appropriate to assure 
the completion of the Detailed Scope of Work within the Job Order Completion Time and 
in accordance with the Contract Documents. 
 
C. 
Site Manager shall have such assistants with such individual competencies (including, 
without limitation, scheduling, etc.) as may be necessary to administer and manage all Job 
Order Development Services, all aspects of the Detailed Scope of Work, and all of the 
Contractor’s activities with respect to the Job Orders. 
 
D. 
A communication to the Site Manager or his designated assistants by the Owner, the 
Design Professional, or the Owner Representative is binding upon Contractor. 
 
E. 
The Site Manager shall be responsible to review work details with their subcontractors and 
suppliers in advance of the subcontractor or supplier being on site to include but not be 
limited to work locations and site rules.  In no circumstances should the subcontractor or 
supplier ask to review these same work details with the Owner.  If a subcontractor or 
supplier has a question, they are to first communicate with the Site Manager.    
 
F. 
Site Manager shall be responsible for the prevention of accidents at each Site. The 
Commercial Construction Safety Code of the Arizona Industrial Commission shall apply to 
all Work and a copy of the Code shall be available at the Contractor’s office. 
 
G. 
If on the Contract Date or any time thereafter, Contractor desires to use a person as Site 
Manager other than the Site Manager proposed in the Contractor’s Formal Sealed 
Qualifications, the substitute Site Manager must be as qualified, in the reasonable 
judgment of Owner, as the person being replaced and must be approved by Owner, such 
approval shall not to be unreasonably withheld or delayed. In determining whether to 
approve a substitute Site Manager, Owner may elect to use part or all of the criteria and 
process used to evaluate the proposed Site Manager under the Request for Qualifications 
(including, without limitation, questionnaires and a candidate interview). 
 
H. 
Upon reasonable request of Owner, Contractor will replace any Site Manager.

State of Arizona 
32 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
5.12 
Owner Representative and Design Professional 
 
A. 
Owner Representative will be as stated on the Job Order. In addition to the normal 
responsibilities of a project manager, the Owner Representative will have the 
administrative responsibilities of the outside design professional in a normal design-bid- 
build or construction-manager-at-risk project, even when Owner engages a Design 
Professional for Design Services for a Job Order. The role of the Design Professional will 
be as set forth in the Contract Documents. 
B. 
Owner Representative will oversee the Detailed Scope of Work on behalf of Owner. Owner 
Representative may be an employee of Owner or an independent person engaged by 
Owner. 
 
C. 
If the nature of the Detailed Scope of Work requires sealed construction drawings, the 
drawings will be sealed by the Design Professional. Installation drawings by the Contractor 
are the responsibility of the Contractor. 
 
D. 
If Owner provides a Design Professional for a Job Order, Design Professional shall have 
the right, responsibility and authority to carry out the specific obligations and activities of 
Design Professional in the Contract Documents and in the contract between the Design 
Professional and the Owner, which incorporates this Operating Manual, including any 
amendments thereto (collectively known as “Design Professional Contract Documents”). A 
copy of the Design Professional Contract Documents and any amendments will be 
furnished to Contractor, upon request of Contractor. 
 
E. 
Any Design Professional shall have such access to the Site as Design Professional 
determines to be appropriate in order to perform the Design Services and the other services 
of Design Professional. Owner Representative shall have access to the Site as the Owner 
Representative determines to be appropriate in order to perform oversight services for 
Owner. Owner Representative will visit the Site as determined by Owner Representative 
or Owner to be appropriate in order to advise Owner as to the quality and progress of 
construction. Contractor, Subcontractors and Owner shall cooperate with Design 
Professional and Owner Representative in all respects with regard to performing their 
functions. 
 
F. 
Owner Representative will be the initial interpreter of the requirements of the Contract 
Documents as they relate to a Job Order, provided that when the interpretation involves 
documents prepared by a Design Professional, Owner Representative will consult with 
Design Professional and obtain Design Professional’s view before rendering the 
interpretation and may elect to have Design Professional render or join in the interpretation. 
Design Professional shall consult with the Owner Representative whenever requested by 
Owner Representative. 
 
G. 
Design Professional and Owner Representative shall render written interpretations of the 
documents prepared by Design Professional with reasonable promptness following a 
written request from Owner or Contractor. These interpretations shall be consistent with 
the intent of the Contract Documents. Before issuing the interpretation, Owner 
Representative and Design Professional must discuss the matter with Site Manager. 
 
H. 
Following consultation as necessary with Owner, Owner Representative will take 
appropriate action on Supplemental Job Orders and may authorize Minor Changes in the 
Detailed Scope of Work, provided that when the Supplemental Job Order or Minor Change 
involves documents prepared by a Design Professional, Owner Representative shall 
consult with Design Professional and obtain Design Professional’s view before taking 
action on the Supplemental Job Order or Minor Change. Design Professional shall consult 
with the Owner Representative. 
 
I. 
Owner Representative and Owner, acting jointly or independently, will have authority to 
reject all or any portion of the Detailed Scope of Work that does not conform to the Contract 
Documents and Job Order and to require special inspection or testing, but Owner

State of Arizona 
33 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
Representative will take such action only after consultation with Site Manager, Owner and, 
if determined by Owner Representative to be appropriate, Design Professional. 
 
If Owner observes or otherwise becomes aware of any fault or defect in the Detailed 
Scope of Work or non-conformity with the Contract Documents or Job Order, Owner will 
give   prompt   written   notice   thereof   to   Contractor.     Failure   of   Owner   or 
Owner Representative to notify Contractor shall not reduce, change, lessen or alleviate 
in any way, Contractor’s duties and obligations under the Contract Documents or Job 
Order. 
 
J. 
Owner shall, throughout the performance of Detailed Scope of Work, cooperate with 
Contractor and perform Owner’s responsibilities, obligations and services in a timely 
manner so as not to delay or interfere with Contractor’s performance of the Detailed Scope 
of Work and Contractor’s other obligations under the Contract Documents and Job Order. 
 
K. 
Owner Representative shall be responsible for processing Owner-supplied information and 
approvals or rejections in a timely manner to permit Contractor to fulfill its obligations under 
the Contract Documents and Job Order. 
 
L. 
Owner and Owner Representative shall review documents submitted by Contractor and 
shall render decisions pertaining thereto without unreasonable delay. 
 
M. 
Owner will direct other parties engaged by Owner to perform work at any Site to cooperate 
and coordinate their activities with Contractor so as not to interfere unreasonably with 
Contractor’s ability to complete the Detailed Scope of Work in a timely manner and 
consistent with the Contract Documents. 
 
N. 
Final interpretations involving the Contract Statement of Work and terms and conditions 
shall be made by the Contract Procurement Officer of Record, whose interpretations shall 
be final. 
 
5.13 
Other Contractors and Cooperation 
 
A. 
Owner reserves the right to award other contracts related to any project, or to perform 
certain work itself. Owner also reserves the right to award other contracts unrelated to a 
Job Order but involving work in the vicinity of a Job Order Project or to perform unrelated 
work itself. Such other work may or may not be known to the Owner or disclosed to the 
Contractor prior to issuance of the Job Order. 
 
B. 
Contractor shall afford Owner and other contractors reasonable opportunity for the 
introduction and storage of their materials and equipment and the execution of their Work 
and shall properly coordinate its Detailed Scope of Work with theirs in such manner as the 
Owner Representative may direct. Contractor shall also assure at its own cost reasonable 
access of other contractors to the site and their Work. 
 
C. 
Upon request of Contractor, Owner will provide Contractor with a copy of all plans, 
specifications, schedules and other data relating to other contracts or Work. Contractor 
shall thoroughly examine these documents and shall within three (3) days of date on the 
Job Order Proposal Request Document complete such examination and notify the Owner 
Representative in writing of any conflicts with the Detailed Scope of Work to be performed 
by Contractor. In no event shall such notice be given so late as to interfere with or delay 
the Detailed Scope of Work to be performed by Contractor. Failure of Contractor to request, 
review, or provide written notice as provided above shall constitute a waiver of any 
objections or claims Contractor may have as a result of the necessity to coordinate 
Contractor's Detailed Scope of Work with other activities. 
 
D. 
Should Contractor sustain any damage through any act or omission of any other contractor, 
Contractor shall have no claim or cause of action against Owner for such damage and 
hereby waives any such claim. Contractor does not waive any claim or cause of action

State of Arizona 
34 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
against any other contractor or subcontractor to recover any and all damages sustained by 
reason of the acts or omissions of such other contractor or subcontractor. The phrase "acts 
or omissions" as used in this section shall include, but not be limited to, any reasonable 
delay by any such other contractors, whether due to negligence, gross negligence, 
inadvertence or any other cause. 
E. 
Should Contractor cause damage to the Work or property of any other contractor or of 
Owner, Contractor shall upon receiving due notice promptly attempt to settle with such 
other contractor or Owner by agreement, repair or otherwise to resolve the dispute. If such 
separate contractor sues or initiates a proceeding against Owner on account of any 
damage alleged to have been caused by Contractor, Owner shall notify Contractor who, at 
Owner’s option, shall defend such proceedings or pay the costs of Owner defending such 
proceedings, and if any judgment or award against Owner arises therefrom Contractor shall 
pay or satisfy it or reimburse Owner for any amount paid by Owner and shall reimburse 
Owner for all attorney's fees and court or other costs which Owner has incurred. 
 
5.14 
In the event that Local Government policy requires a building permit for each Job Order 
Development Services and Job Order issuance process, Owner Representative shall indicate the 
anticipated required permits on the Job Order and the Contractor shall prepare a building permit in 
the Local Government prescribed form in effect from time to time and submit to Local Government 
for approval. This must be done prior to the Job Order being issued and prior to commencing the 
Detailed Scope of Work.

State of Arizona 
35 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 6 
JOB ORDER DEVELOPMENT SERVICES AND ISSUANCE OF JOB ORDERS 
6.1 
Contractor shall provide Job Order Development Services whenever requested by Owner during 
all hours of the day seven (7) days a week. 
6.2 
Contractor shall perform Job Order Development Services in connection with each Job Order at its 
own cost and expense. The Owner will not be obligated to pay Contractor for Job Order 
Development Services. 
 
A. 
Owner will arrange for any Design Services required to prepare a final Detailed Scope of 
Work. If there will be no Design Services, Owner will develop the Detailed Scope of Work 
and any line drawings required. Once finalized, the Owner shall issue a Job Order Proposal 
Request and the Detailed Scope of Work to the Contractor. 
 
B. 
By submitting the Job Order Proposal, the Contractor agrees to perform the Detailed Scope 
of Work for the fixed Job Order set forth in the Price Proposal according to the proposed 
Construction Schedule that is within the Job Order Completion Time. 
 
C. 
The Owner will review the Contractor’s Job Order Proposal. 
 
Contractor and Owner will work together to develop the final Job Order in accordance with the 
Procedures to Develop all Job Orders, with Owner having the right to make a final determination 
on any matters as to which Contractor and Owner do not agree. 
All terms and provisions of the Contract Documents shall apply to, and are incorporated into, each 
Job Order issued, whether or not referenced therein. 
6.3 
Owner may issue Job Orders at any time during any term of this Contract. Except for Supplemental 
Job Orders required to complete a Project, no Job Orders shall be issued after the Contract has 
expired. 
 
6.4 
A Job Order is considered “issued” when: 
 
A. 
the Job Order and corresponding Purchase Order are sent through the State’s 
Procurement system, ProcureAZ (https://procure.az.gov); 
 
B. 
the Job Order and corresponding Purchase Order are emailed to Contractor’s email 
address listed in Contractor’s ProcureAZ profile and Owner does not receive a non- receipt 
message; 
 
C. 
the Job Order and corresponding Purchase Order are sent by facsimile copy to the fax 
number listed in the Contractor’s ProcureAZ profile and Owner’s fax machine prints and 
acknowledgement of receipt; or 
 
D. 
the Job Order and corresponding Purchase Order are sent separately to the Contractor 
and the Contractor receives the Job Order and Purchase Order sent separately by any of 
the methods listed above. 
 
6.5 
Contractor’s approval of or consent to the Job Order is not required. If the Contractor desires to 
decline performance of a Job Order on the basis that Contractor believes that the Job Order is not 
in compliance with the Contract Documents, Contractor must deliver a written notice to Owner 
Representative within seven (7) days after issuance of the Job Order stating the reasons for 
Contractor’s belief. If Contractor does not file such a written request with Owner Representative 
within that time frame, Contractor will be deemed to have waived any and all rights to not perform 
the Job Order.

State of Arizona 
36 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 7 
JOB ORDER PRICE 
7.1 
The Job Order Price shall be calculated in accordance with Section 8 Procedures to Develop all 
Job Orders. The Job Order Price shall be a fixed price for which the Contractor shall complete the 
Detailed Scope of Work within the Job Order Completion Time. 
 
7.2 
The Job Order Price may only be modified by a Supplemental Job Order. All Supplemental Job 
Orders shall be developed in accordance with the Procedures to Develop all Job Orders.

State of Arizona 
37 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION  8 
PROCEDURES TO DEVELOP ALL JOB ORDERS 
 
8.1 
Job Order Contract Overview 
 
A. 
The Owner will provide construction administration and inspection for the Job Order 
projects. 
 
B. 
Final commissioning of systems will be performed by the Owner Representative and the 
local authority having jurisdiction. 
 
8.2 
Ordering Process 
A. 
As the need exists, the Owner will notify the Contractor of a Project, schedule a Joint Scope 
Meeting and issue a Notice of Joint Scope Meeting. 
 
B. 
The Contractor shall attend the Joint Scope Meeting and discuss, at a minimum:  
1. 
the general scope of the Work; 
2. 
alternatives for performing the Work and value engineering; access to the site 
and protocol for admission; 
3. 
hours of operation; staging area; 
4. 
requirements for catalog cuts, technical data, samples and shop drawings; 
requirements for professional services, sketches, drawings, and specifications; 
construction duration; 
5. 
the presence of hazardous materials;  
6. 
whether or not any of the areas of work are considered to be secure locations; 
7. 
date on which Job Order Proposal is due.; 
C. 
Upon completion of the joint scoping process, the Owner will prepare a draft Detailed 
Scope of Work referencing any sketches, drawings, photographs, and specifications 
required to document accurately the Work to be accomplished. The Contractor shall review 
the Detailed Scope of Work and request any required changes or modifications. When an 
acceptable Detailed Scope of Work has been prepared, the Owner will issue a Job Order 
Proposal Request that will require the Contractor to prepare a Job Order Proposal. The 
Detailed Scope of Work, unless modified by both the Contractor and the Owner, will be the 
basis on which the Contractor will develop its Job Order Proposal and the Owner and/or 
Owner’s Representative will evaluate the same. The Contractor does not have the right to 
refuse to perform any task or any Work in connection with a particular Project. In other 
words, if the Contractor refuses a required task, the Contractor refuses the entire Job 
Order. 
 
D. 
If the Contractor requires clarifications or additional information regarding the Detailed 
Scope of work in order to prepare the Job Order Proposal, the request must be submitted 
so that the submittal of the Job Order Proposal is not delayed.  
 
E. 
The Owner may, at its option, include quantities in the Detailed Scope of Work if it helps to 
define the Detailed Scope of Work, if the actual quantities required are not known or cannot 
be determined at the time the Detailed Scope of Work is prepared, if the Contractor and 
the Owner cannot agree on the quantities required, or for any other reason as determined 
by the Owner. In all such cases, the Owner shall issue a Supplemental Job Order adjusting 
the quantities appearing in the Detailed Scope of Work to the actual quantities. 
 
8.3 
Preparation of the Price Proposal. 
A. 
The Contractor will prepare Price Proposals in accordance with the following:  
 
B. 
Prepriced Tasks: 
1. 
A Prepriced Task is a task described in, and for which a Unit Price is set forth in

State of Arizona 
38 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
the Construction Task Catalog®. The Contractor will select the appropriate 
Prepriced Tasks, and enter the accurate quantity, and the appropriate Adjustment 
Factor. 
2. 
Contractor shall be entitled to apply appropriate Adjustment Factor for the current 
contract term; however, if the Contractor’s Adjustment Factors in previous contract 
terms were lower, Contractor may choose to apply those Adjustment Factors at 
the Contractor’s sole discretion. 
C. 
Non Prepriced Tasks: 
1. 
A Non Prepriced Task is a task that is not set forth in the Construction Task 
Catalog®. Non Prepriced tasks shall be separately identified and submitted in the 
Price Proposal. Information submitted in support of Non Prepriced Tasks shall 
include, but not be limited to, the following: 
2. 
Catalog cuts, specifications, technical data, drawings, or other information as 
required to evaluate the task. 
3. 
If the Contractor will perform the Work with its own forces, it shall submit three 
independent quotes for all material to be installed and shall, to the extent possible, 
use Prepriced Tasks for labor and equipment from the Construction Task Catalog®.  
4. 
If the Work is to be subcontracted, the Contractor must submit three independent 
bids from Subcontractors. The Contractor shall not submit a quote or bid from any 
Supplier or Subcontractor that the Contractor is not prepared to use. The Owner 
may require additional quotes and bids if the Suppliers or Subcontractors are not 
acceptable or if the prices are not reasonable. If three quotes or bids cannot be 
obtained, the Contractor will provide the reason in writing for the Owner’s approval. 
If approved, less than three quotes or bids will be allowed. 
5. 
The final price submitted for Non Prepriced Tasks shall be according to one of the 
following two formulas. Which formula to use depends on whether or not the 
Projects is the State of Arizona project or an ezIQC® Project:  
Formula 1: Non Prepriced Formula for State of Arizona Projects: 
 
For Non Prepriced Tasks Performed with Contractor's Own Forces: 
A = The burdened rate for each trade classification including fringes (if 
applicable) not in the Construction Task Catalog® multiplied by the 
quantity; 
B = The rate for each piece of Equipment not in the Construction Task 
Catalog® multiplied by the quantity; 
C = Lowest of three independent quotes for all materials. 
D = Overhead and Profit = (A+B+C) x Not To Exceed 10% 
Total for a Non Prepriced Tasks performed with Contractor’s 
Own Forces = A+B+C+D 
 
For Non Prepriced Tasks Performed by Subcontractors:   
If the Non Prepriced Task is to be subcontracted, the Contractor must submit 
three independent quotes for the work. 
E = Lowest of three Subcontractor Quotes 
F = Overhead and Profit = F x Not To Exceed 10% 
Total Cost for Non Prepriced Tasks performed by Subcontractors = E + F

State of Arizona 
39 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
Formula 2: Non Prepriced Formula for ezIQC® Projects: 
 
For Non Prepriced Tasks Performed with Contractor's Own Forces: 
A = The burdened rate for each trade classification including fringes (if 
applicable) not in the Construction Task Catalog® multiplied by the 
quantity; 
B = The rate for each piece of Equipment not in the Construction Task 
Catalog® multiplied by the quantity; 
C = Lowest of three independent quotes for all materials. 
D = Overhead and Profit = (A+B+C) x Not To Exceed 15.79% 
Total for a Non Prepriced Tasks performed with Contractor’s 
Own Forces = A+B+C+D 
 
For Non Pre-priced Tasks Performed by Subcontractors:   
If the Non Prepriced Task is to be subcontracted, the Contractor must submit 
three independent quotes for the work. 
E = Lowest of three Subcontractor Quotes 
F = Overhead and Profit = F x Not To Exceed 15.79% 
Total Cost for Non Prepriced Tasks performed by Subcontractors = E + F 
 
6. 
For Non Prepriced Tasks, the Contractor shall use an Adjustment Factor of 1.0000. 
7. 
After a Non Pre-priced Task has been approved by the State of Arizona, the Unit 
Price for such task will be established, and fixed as a permanent Non Pre-priced 
Task which will no longer require price justification. 
8. 
After a Non Pre-priced Task has been approved by the Owner, the Unit Price for 
such task will be established, and fixed as a permanent Non Pre-priced Task which 
will no longer require price justification. 
9. 
The Owner’s determination as to whether an item is a Prepriced Task or a Non 
Prepriced Task shall be final, binding and conclusive as to the Contractor. 
D. 
Contractor shall make the necessary arrangements for and obtain all filings and permits 
required for the Work, including the preparation of all drawings, sketches, calculations and 
other documents and information that may be required therefore. If the Contractor is 
required to pay an application fee for filing a project, a fee to obtain a building permit, or 
any other permit fee to the City, State or some other governmental or regulatory agency, 
then the amount of such fee paid by the Contractor for which a receipt is obtained shall be 
treated as a Reimbursable Task. For State of Arizona Projects, the Reimbursable Task is 
to be paid without mark-up with an Adjustment Factor of 1.0000. For ezIQC® Projects, the 
Reimbursable Task is to be paid with an Adjustment Factor of 1.0526. The cost of 
expediting services or equipment use fees are not reimbursable. 
E. 
The Contractor shall provide incidental engineering and architectural services required in 
connection with a particular Job Order including drawings and information required for 
filing. 
F. 
The Contractor's Job Order Proposal shall include, at a minimum:  
1. 
Price Proposal; 
2. 
Required drawings or sketches;   
3. 
Catalog cuts, technical data or samples; 
4. 
List of anticipated Subcontractors and Suppliers and anticipated price;  
5. 
Construction Schedule;

State of Arizona 
40 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
6. 
Sample warranties or guarantees for materials, equipment or systems proposed; 
7. 
Other requested documentation. 
 
G. 
The Job Order Price shall be the value of the approved Price Proposal.  
H. 
The value of the Price Proposal shall be calculated by summing the total of the calculations 
for each Prepriced Tasks (Unit Price x Quantity x Adjustment Factor) plus the value of all 
Non Prepriced Tasks.  
 
8.4 
The Contractor's Proposal shall be submitted by the date indicated on the Job Order Proposal 
Request. All incomplete Job Order Proposals shall be rejected. The time allowed for preparation 
of the Contractor's Proposal will depend on the complexity and urgency of the Job Order but should 
average between seven and fourteen days. On complex Job Orders, such as Job Orders requiring 
incidental engineering/architectural drawings and approvals and permits, allowance will be made 
to provide adequate time for preparation and submittal of the necessary documents. 
 
8.5 
In emergency situations and minor maintenance and repair Job Orders requiring immediate 
completion, the Job Order Proposal may be required quickly and the due date will be so indicated 
on the Job Order Proposal Request or, as described below, the Contractor may be directed to 
begin Work immediately with the Job Order Proposal to follow.  In these cases, the Job Order 
Proposal will be required within three (3) working days after completion of the emergency 
situations. 
 
8.6 
Review of the Proposal and Issuance of Job Order.  
 
A. 
The Owner will evaluate the entire Proposal. The Owner will compare the Price Proposal 
with the Owner's cost estimate of the Detailed Scope of Work and determine the 
reasonableness of approach, including the appropriateness of the tasks and quantities 
proposed. 
B. 
The Contractor may choose the means and methods of construction; subject however, to 
the Owner's right to reject any means and methods proposed by the Contractor that: 
1. Will constitute or create a hazard to the work, or to persons or property; 
2. Will not produce finished Work in accordance with the terms of the Contract; or 
3. Unnecessarily increases the price of the Job Order when alternative means and 
methods are available. 
C. 
The Owner reserves the right to reject a Proposal or cancel a project for any reason. The 
Owner also reserves the right not to issue a Job Order if it is determined to be in the best 
interests of the Owner. The Owner may perform such work by other means. The Contractor 
shall not recover any costs arising out of or related to Job Order Development Services. 
D. 
By submitting a Job Order Proposal to the Owner, the Contractor offers to accomplish the 
Detailed Scope of Work in accordance with the Job Order Proposal Request within the 
proposed Construction Schedule for the lump sum Job Order Price. It is the Contractor's 
responsibility to include the necessary tasks and quantities in the Price Proposal prior to 
delivering it to the Owner. 
E. 
Each Job Order issued shall be on the approved Job Order Form attached as Appendix 1. 
The Job Order shall reference the Detailed Scope of Work and set forth the Job Order 
Price and the Job Order Completion Time. All provisions of the Contract Documents shall 
be applicable to each Job Order. The Job Order, issued by the Owner constitutes the 
Owner's acceptance of the Contractor's Proposal. A signed copy of the Job Order will be 
provided to the Contractor. 
F. 
In the event that immediate emergency response is necessary, the Contractor shall be 
required to follow alternative procedures as established by the Owner. The Contractor shall 
begin Work as directed notwithstanding the absence of a fully developed Job Order

State of Arizona 
41 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
Proposal Request, Detailed Scope of Work, or Job Order. The Contractor shall be 
compensated in accordance with Section 8, Procedures to Develop all Job Orders as if the 
Work had been ordered under the standard procedures. 
8.7 
BidSafe® 
A. 
When the estimated Job Order Price is between $650,000.00 and $1,000,000.00, the 
Owner may issue a Job Order Proposal Request to two or more Contractors for a Job 
Order. Selection of the Contractor and award of the Job Order will be in compliance with 
established Owner procedures.   
B. 
The Owner reserves the right to utilize BidSafe® on a Job Order by Job Order basis. 
C. 
The Owner will consider several factors when determining the applicability of BidSafe® to 
a Job Order including, but not limited to, the following: 
1. 
Estimated Job Order Price; 
2. 
Scope Documentation, including but not limited to A/E design; 
3. 
Nature and complexity of the Work; 
4. 
Contractors’ abilities to self-perform the Work; 
5. 
Contractors’ proven capabilities on similar Work; 
6. 
Schedule; and 
7. 
Other appropriate criteria as deemed in the best interest of the Owner. 
D. 
The Detailed Scope of Work will be developed by Owner personnel and included with the 
Job Order Proposal Request.  
E. 
The Owner may conduct one or more site visits with all contractors designated to receive 
the Job Order Proposal Request. 
F. 
All contractors that receive the Job Order Proposal Request will have the opportunity to 
submit requests for information. Should the Owner choose to respond to any or all of the 
requests for information, the responses, and any changes to the Job Order Proposal 
Request, will be provided in an addendum to all contractors designated to receive the Job 
Order Proposal Request. 
G. 
The Contractor will utilize the Bid Safe application in the eGordian® software to provide an 
Not-to-Exceed (NTE) Offer, along with any additional requested documentation, in 
response to the Job Order Proposal Request. 
H. 
The Owner will issue an Intent to Award to the Contractor submitting the NTE Offer that 
provides the best value to the Owner based on, but not limited to, price and any technical 
factors considered. 
I. 
The NTE Offer is valid for 90 Days from the date of opening unless stated otherwise in the 
Job Order. 
J. 
The Contractor that receives an Intent to Award will submit a Job Order Price Proposal to 
the Owner. Provided that any necessary Job Order Price Proposal modifications are 
completed in a timely and thorough manner, the Job Order may be issued to the Contractor. 
K. 
The Job Order Price shall be equal to the lessor of the NTE Offer and the Job Order Price 
Proposal amount.  
L. 
Where the NTE Offer is less than the Job Order Price Proposal, the difference between the 
NTE Offer and Job Order Price Proposal shall be deemed a discount offered by the 
Contractor. The discount amount shall be a percent-based discount that will be calculated 
by the following equation: 
M. 
Percent Discount = (Job Order Price Proposal Amount – NTE Offer) ÷ Job Order Price 
Proposal Amount 
N. 
The discount shall be applied to subsequent Job Orders (additions or deletions) required 
to complete the Work, provided the Job Order contains materials, equipment and tasks that

State of Arizona 
42 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
are similar in nature to the original Detailed Scope of Work. 
O. 
If the Owner exercises its right to award a Job Order utilizing BidSafe®, collaboration 
between Contractors is specifically prohibited. Contractor collaboration undermines 
competition, and evidence of such will be considered a material breach of this Contract and 
grounds for termination for cause. 
 
8.8 
General 
 
A. 
Before any Work is initiated, Contractor shall confer with Owner and agree on a sequence 
of procedure; means of access to premises and buildings; approaches; use of corridors, 
stairways elevators, and similar means of movement; and the location of partitions, eating 
spaces, and restrooms for Contractor’s employees and the like. 
 
B. 
Contractor shall commence the Work on the Construction Start Date. Final Completion 
shall be achieved not later than the Final Completion Date set forth in the Job Order. 
C. 
Contractor shall be prepared to perform Work during all hours of the day seven (7) days a 
week. Contractor shall perform Work during such hours and days as are necessary to 
complete the Detailed Scope of Work within the Job Order Completion Time. 
 
8.9 
Existing Furniture and Portable Office Equipment 
 
A. 
Furniture and portable office equipment in the immediate area of the Work shall be moved 
by Contractor, unless other arrangements have been made, and replaced to original 
position upon completion of the Detailed Scope of Work. If the location or nature of the 
Work will not allow furniture and portable office equipment to be replaced to its original 
position, new locations will be designated by Owner for placement by Contractor. 
 
8.10 
Materials, Equipment and Personnel 
 
A. 
Contractor shall furnish all materials, equipment and personnel necessary to manage and 
accomplish the Detailed Scope of Work. 
B. 
Delivery of materials and equipment shall be made with a minimum of interference to 
Owner operations and personnel. 
C. 
At no time during the Work shall Contractor place, or suffer to be placed, any material or 
equipment, etc., at any location that would impede or impair access to or from existing 
facilities. 
D. 
In order for Contractor to be paid for stored materials, the materials must be stored on site. 
An invoice for the stored materials must accompany the pay application.  Contractor must 
store material and equipment in areas indicated by the Owner. Contractor must store 
materials and equipment at Contractor’s own risk. The Owner is not responsible for lost, 
stolen or damaged goods. 
E. 
All materials and equipment shall be shipped and stored and handled in a manner that will 
afford protection and ensure that it remains in factory-new condition at the time it is 
incorporated in the Work. After installation, materials and equipment shall be properly 
protected by Contractor against damage or deterioration until Final Completion. 
F. 
Any part of the Work damaged during installation or prior to Final Completion shall be 
repaired by Contractor so as to be unnoticeable and to be equal in quality, appearance, 
serviceability and other respects to an undamaged item or part of the Work. Where this 
cannot be fully accomplished, the damaged item or part shall be replaced. After installation, 
all exposed surfaces and parts of an item or of the Work shall be cleaned in a manner that 
will not damage the finish or any of the parts of the item, so that the completed Work is free 
of all defects. All damaged or defaced Work shall be repaired or replaced to Owner's 
satisfaction at the expense of Contractor. 
 
8.11 
Method of Performing Work, Non-Interference with Owner Activities, Traffic Control and Job Site 
Management

State of Arizona 
43 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
A. 
Contractor shall perform the Work efficiently, safely, and so as not to interfere with the use 
of any adjacent land or building areas, including the reasonable aesthetic appearance of 
the Site and all storage/staging areas 
B. 
Contractor shall cooperate with Owner to the fullest extent in providing traffic control during 
course of construction so as to provide a minimum of inconvenience to Owner. 
C. 
Contractor shall limit its operations to the assigned Site, except as necessary to connect 
to existing utilities and shall not, without the prior written permission of Owner or the 
affected property owner, encroach on property outside the Site. 
D. 
Contractor shall not permit unauthorized persons or activities on the Site and shall maintain 
the Site in a safe and secure manner. 
 
8.12 
Utility and Other Services 
 
A. 
It is of paramount importance that the Work not interfere in any way with the normal 
operation of the existing utility services. No interruption of the utility services can be 
allowed. 
Contractor will coordinate all Work  affecting  utility  services  in the existing 
building with Owner Representative. 
B. 
Contractor shall prearrange time with Owner Representative whenever it becomes 
necessary to interrupt any service to make connections, alterations or relocations and shall 
fully cooperate with Owner in doing Work so as to cause the least annoyance and 
interference with the continuity of Owner's operations. Any existing plumbing, heating, 
ventilating, air conditioning or electrical disconnections which may affect portions of this 
construction or building or any other building must be coordinated with Owner 
Representative to avoid any disruption of operation within the building or construction or 
other building or utilities. In no case, unless previously approved in writing by Owner 
Representative, shall utilities or other services be left disconnected at the end of a workday 
or over a weekend. Any interruption of utilities or other services, whether negligently, 
intentionally, or accidentally, shall not relieve Contractor's responsibility for the interruption 
or from liability for loss or damage caused by such interruption even though such loss or 
damage was not foreseeable by Contractor or Subcontractor, or from responsibility for 
repairing and restoring the utility or other service to normal service. Repairs and restoration 
shall be made before the workmen responsible for the repair and restoration leave the job. 
 
8.13 
Site Neatness and Cleanup 
 
A. 
Contractor shall maintain the Site in a neat and orderly manner acceptable to the Owner. 
Contractor at all times shall keep the Site free from accumulation of waste materials or 
rubbish caused by its operations. If Contractor fails to properly clean up during construction, 
or if a dispute arises between Contractor and/or separate contractors as to their 
responsibility for cleaning up, Owner may clean up and charge the costs thereof to 
contractors responsible as determined by Owner or Owner Representative. 
B. 
Contractor shall complete final cleanup of the premises before Final Completion. 
Contractor shall remove all its waste materials and rubbish from the Site, as well as all 
tools, construction equipment, machinery and surplus materials. If Contractor fails to clean 
up at Site prior to Final Completion, Owner may do so and the cost thereof shall be charged 
to Contractor or offset against amounts due to the Contractor. 
 
8.14 
Matters Relating to Subcontractors 
 
A. 
Contractor shall caution each Subcontractor to become familiar with the Detailed Scope of 
Work and the Technical Specifications. Contractor shall also caution each Subcontractor 
that no consideration will be given to any claim of ignorance of the contents of the Detailed 
Scope of Work and any specification or standard referenced therein especially since each 
Subcontractor is expected to be familiar with his own trade’s generally accepted and 
published specifications and standards of quality. 
B. 
No allowance shall be made on behalf of any Subcontractor for errors due to its negligence 
in not being familiar with the existing site conditions for the Work. 
C. 
Each Subcontractor shall make the field measurements necessary for its Work and shall

State of Arizona 
44 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
be responsible for the accuracy of those measurements and its work. 
D. 
Each Subcontractor shall acquaint itself with the Work of other Subcontractors whose 
activities are mutually affected so that their efforts are coordinated to avoid mistakes, 
omissions, disputes, delays and damage to each other's work. 
E. 
If any structural difficulties prevent a Subcontractor from installing its materials or 
equipment properly, Contractor shall promptly notify Owner Representative so that Owner 
and Design Professional, may be consulted on how best to resolve the difficulty.   If it is 
necessary for the Subcontractor to cut into walls and/or floors, the Work shall be done 
carefully and neatly and only with the full knowledge of Owner Representative and Design 
Professional. This is especially true when structural elements or utilities are involved. 
F. 
All patching and repairing of damaged items of the Work shall be done by the Subcontractor 
originally performing that item of the Work. 
G. 
Each Subcontractor shall remove tools, equipment, materials and debris from the Site 
promptly upon completion of its Work and shall leave its work area clean and free from 
rubbish and debris. 
 
8.15 
Miscellaneous 
 
A. 
Contractor, Subcontractors and Suppliers shall be responsible for taking all appropriate 
field measurements prior to fabrication and installation of any item. Such measurements 
shall be taken sufficiently in advance so as to avoid any delay or potential delay. Failure to 
adhere to this provision shall render such delays the responsibility of Contractor. 
 
B. 
Contractor shall be responsible for laying out its own Work and for any damage which may 
occur to work of any other contractor because of Contractor's own errors or inaccuracies. 
Contractor shall also be responsible for unloading, uncrating, storing and handling all 
materials and equipment to be erected or placed by it, whether furnished by Contractor or 
others. 
 
C. 
Contractor shall repair any part of the finished Work damaged during installation or prior to 
substantial completion of the Work so as to be equal in quality, appearance, serviceability, 
and other respects to an undamaged item or part of the Work. Where this cannot be fully 
accomplished, Contractor shall replace the damaged item or part. 
 
D. 
Unless otherwise specifically mentioned, Contractor shall furnish and install all anchors, 
bolts, screws, fittings, fillers, hardware, accessories, wiring, conduit, ductwork, trim and 
other parts required for or in connection with any item or material to make a complete, 
serviceable, finished installation satisfactory to the Owner whether or not expressly called 
for by the Detailed Scope of Work or the Technical Specifications. 
 
E. 
Contractor shall procure and furnish to Owner all guarantees, warranties, manuals and 
spares that are called for by the Detailed Scope of Work or the Technical Specifications or 
that are mentioned in the manufacturer's product literature. Guaranties and warranties shall 
commence as of the date of Final Completion. 
 
F. 
Contractor shall pay all royalties and license fees to which third parties are entitled as 
holders of any proprietary rights, United States patent or copyright, now or hereafter issued 
relating to the Work. 
 
8.16 
Drawings and Specifications 
 
A. 
A Detailed Scope of Work may reference Drawings and Specifications. In such case, they 
will be attached to the Detailed Scope of Work and issued with the Job Order. 
 
B. 
Contractor will study and compare the Drawings and Specifications in advance of 
beginning each phase or portion of the Detailed Scope of Work to be performed and 
immediately report any material error, inconsistency, conflict, ambiguity or omission that is

State of Arizona 
45 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
discovered. 
 
C. 
All Work will be performed in a workmanlike manner and all materials used will be new and 
of the highest quality and of the type best adapted to their purpose, unless otherwise 
specified. 
 
D. 
If the Drawings and Technical Specifications do not cover a particular phase or aspect of 
the Work, the installation and maintenance directions of the manufacturer shall be followed. 
 
The Drawings are intended to show general arrangements, design and extent of Work and 
are not intended to serve as shop drawings. When the Job Order specifies shop drawings, 
Product Data or Samples are required, Contractor shall not perform the relevant portion of 
the Work without approved shop drawings, Product Data or   Samples as provided in this 
Section. Any Work performed in violation of this provision will be solely at the Contractor's 
risk regardless of the Design Professional’s, Owner Representative’s and/or Owner's 
knowledge of such work. 
 
E. 
The Contract Documents are applicable to each Job Order and are complementary, 
requiring a complete project. Any requirement occurring in any one of the Contract 
Documents is binding as though occurring in all documents. Generally, the Specifications 
and the Technical Specifications address criteria and quality of materials and standards for 
workmanship, types of materials and contract conditions and the Drawings show 
placement, sizes, fabrication details of materials, dimensions, positions and details of 
construction. In the event of conflict in the Contract Documents, the priorities stated in the 
definition of Contract Documents and the priorities stated below shall govern: 
 
1. 
Contract amendments shall govern over all other Contract Documents and 
subsequent Amendments shall govern over prior Modifications only to the extent 
modified. Supplemental Job Orders shall govern over its associated original Job 
Order and subsequent Supplemental Job Orders shall govern over prior 
Supplemental Job Orders. 
 
2. 
In case of conflict between Drawings and Specifications, the Specifications shall 
govern. 
 
3. 
Conflicts within the Drawings: 
 
a. 
Schedules, when identified as such, shall govern over all other portions of 
the Drawings. 
 
b. 
Specific notes shall govern over all other notes and all other portions of 
the Drawings, except schedules identified as such. 
 
c. 
Larger scale Drawings shall govern over smaller scale Drawings. 
 
d. 
Figured or numerical dimensions shall govern over dimensions obtained 
by scaling. 
 
4. 
This Operating Manual shall govern over all sections of the Drawings, Detailed 
Scope of Work and the Technical Specifications. 
 
5. 
In the event provisions of codes, safety orders, Contract Documents, referenced 
manufacturer's specifications or industry standards are in conflict, the more 
restrictive or higher quality shall govern. 
 
6. 
In the event of any conflict in the Job Order, Contractor shall request an 
interpretation by Owner Representative before performing the Work, provided that 
when the conflict involves documents prepared by Design Professional, Owner 
Representative may elect to consult with Design Professional and obtain Design

State of Arizona 
46 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
Professional’s view before resolving the conflict. 
 
F. 
If the Detailed Scope of Work, or the documents referenced therein, are not complete as 
to any Minor Detail of a required construction system or with regard to the manner of 
combining or installing of parts, materials, or equipment, but there exists an accepted trade 
standard for good and skillful construction, such detail shall be deemed to be an implied 
requirement in accordance with such standard. 
 
G. 
“Minor Detail” shall include the concept of substantially identical components, where the 
price of each such component is small even through the aggregate cost or importance is 
substantial, and shall include a single component which is incidental, even though its cost 
or importance may be substantial. 
H. 
The quality and quantity of the parts or material so supplied shall conform to trade 
standards and be compatible with the type, composition, strength, size, and profile of the 
parts of materials otherwise set forth in the Detailed Scope of Work. 
 
I. 
Each Job Order shall be presumed to include all items of Work reasonably necessary to 
complete the Detailed Scope of Work, expressly or by inference. Words and abbreviations 
which have well-known technical or trade meanings are used in the Contract Documents 
in accordance with such recognized meanings. 
 
J. 
The organization of the specifications, if any, for a Job Order into divisions, sections and 
articles, and the arrangement of drawings, if any, shall not control the Contractor in dividing 
the Work among Subcontractors or in establishing the extent of work to be performed by 
any trade. 
 
K. 
Prior to Final Completion, if the Contractor was provided Drawings, the Contractor shall 
complete and turn over to Owner Representative the as-built drawings for review by Owner 
Representative. The as-built drawings shall consist of a set of drawings, which clearly 
indicate all field changes that were made to adapt to field conditions, field changes resulting 
from Supplemental Job Orders or directives and all buried and concealed installation of 
piping, conduit and utility services. All buried and concealed items both inside and outside 
the facility shall be accurately located on the as-built drawings as to depth and in 
relationship to not less than two (2) permanent features such as interior or exterior wall 
faces. The as-built drawings shall be clean and all changes, corrections, and dimensions 
shall be given in a neat and legible manner in a contrasting color. 
 
8.17 
Submittals and Shop Drawings 
 
A. 
Contractor shall submit to Design Professional, with such promptness as to cause no delay 
in the Work, all submittals and shop drawings as required by the Job Order. 
 
B. 
Each submittal or shop drawing must be accompanied by a transmittal letter containing a 
list of the titles and numbers of the submittal or shop drawings. Each series shall be 
numbered consecutively for ready reference and each submittal and shop drawing shall be 
marked with the following information: 
 
1. 
Date of submission 
 
2. 
Name of Project 
 
3. 
Location of Project 
 
4. 
Branch of Work (specification section) 
 
5. 
Contract Number 
 
6. 
Job Order number

State of Arizona 
47 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
7. 
Name of Contractor 
 
8. 
Name of Subcontractors 
 
9. 
Revision number 
 
C. 
Contractor shall include with submittals and shop drawings, a written statement indicating 
all deviations from the Detailed Scope of Work and the Technical Specifications. Failure to 
so notify the Design Professional of such deviations will be grounds for subsequent 
rejection of the related Work. If, in the opinion of Owner Representative, after consultation 
with Design Professional, the deviations are not acceptable, Contractor must furnish the 
item as specified or as indicated in the Detailed Scope of Work and the Technical 
Specifications. 
 
D. 
All Subcontractor submittals and shop drawings shall be reviewed by Contractor prior to 
being submitted to Design Professional and shall bear a written statement by Contractor 
that the submittals or shop drawings are consistent with the Detailed Scope of Work and 
the Technical Specifications or if not totally consistent shall bear a written statement 
indicating all deviations. Any submittals or shop drawings submitted without the statements 
will be returned for resubmission; the submittal or shop drawings will be considered as not 
having been submitted, and any delay caused thereby shall be Contractor's sole 
responsibility. This review by Contractor of Subcontractor shop drawings shall not be 
construed as Contractor approval of the design therein except that it shall be a 
representation that the letter accompanying the shop drawings does indicate all deviations 
from the Detailed Scope of Work and the Technical Specifications. 
 
E. 
It is Contractor's obligation and responsibility to check all of its shop drawings and to be 
fully responsible for them and for coordination with connecting construction Work. Shop 
drawings shall indicate in detail all parts of an item of Work, including, without limitation, 
erection and setting instructions and engagements with work of other trades or other 
separate contractors. 
 
F. 
By reviewing or submitting submittals and shop drawings, Contractor represents that it has 
determined and verified availability, field measurements, field construction criteria, 
materials, catalog numbers and similar data, and that it has checked and coordinated each 
submittal and shop drawing with the requirements of the Job Order and the Technical 
Specifications. If any specified material item or part is not available, Contractor shall so 
indicate to the Design Professional. 
 
G. 
Owner Representative with assistance of the Design Professional, shall review and 
approve submittals and shop drawings and return them to Contractor within ten (10) days 
of receipt unless otherwise previously agreed in writing. For scheduling purposes, 
Contractor must assume a ten (10) day review period for each set of submittals and shop 
drawings. For complex submittals and shop drawings, Contractor must assume two (2) ten 
(10) day review cycles. If review and approval are delayed beyond ten (10) days, Design 
Professional shall notify Contractor and Owner in writing stating the reason for the delay. 
Approval shall not relieve Contractor from the responsibility for deviations from the Detailed 
Scope of Work and the Technical Specifications, unless it has been called to Owner 
Representative’s attention, in writing, at the time of submission. Any modification will be 
approved only if it is in the interest of Owner to effect an improvement in the Work and does 
not increase the Job Order Price or the Job Order Completion Time. Any such modification 
is subject to all other provisions of the Detailed Scope of Work and the Technical 
Specifications and is without prejudice to any and all rights under any surety bond. 
 
H. 
If the Design Professional returns a submittal or shop drawing to Contractor with the 
notation “rejected”, “revise and resubmit”, or “approved as noted”, Contractor, so as not  to 
delay the Work, shall promptly submit a submittal or shop drawing conforming to the 
requirements of the Detailed Scope of Work and the Technical Specifications and 
indicating in writing on the submittal or shop drawings and on the  transmittal  what portions

State of Arizona 
48 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
of the resubmittal have been altered in order to meet with the approval of the Owner 
Representative and the Design Professional. Any other differences between the 
resubmittal and the prior submittal shall also be indicated on the submittal or shop drawing 
as a special note. 
 
I. 
No extension of time will be granted to Contractor because of its failure to submit submittals 
or shop drawings in ample time to allow for review, possible resubmittals and approval. 
Fabrication of Work shall not commence until Contractor has received written approval.   
Contractor   shall   furnish   prints   of   its   approved   shop   drawings   to all Subcontractors 
whose work is in any way related to the Work covered by the shop drawings. Only prints 
bearing this approval will be allowed on the Site. 
 
8.18 
Product Data and Product Samples 
 
A. 
When the Job Order requires product samples, Contractor shall furnish product samples 
of all items requested or required by the specifications. Product samples shall be properly 
identified and submitted with such promptness as to cause no delay in the Contractor’s 
Work or in the work of any other contractor and to allow time for consideration by Design 
Professional. Contractor shall submit product samples to Owner Representative and 
Design Professional, for review and approval in accordance with the requirements for shop 
drawings and submittals in the heading above, and the requirements in this heading on 
product data and product samples. 
 
B. 
Each product sample must be accompanied by a letter of transmittal containing the 
following information: 
 
1. 
Date of submission 
 
2. 
Name of Job Order 
 
3. 
Site 
 
4. 
Branch of Work (specification section number) 
 
5. 
Job Order number 
 
6. 
Name of submitting Contractor 
 
7. 
Name of Subcontractor 
 
B. 
Contractor shall furnish to Owner Representative and Design Professional, a certificate 
stating that material or equipment submitted complies with the Detailed Scope of Work and 
the Technical Specifications. If a certificate originates with the manufacturer, Contractor 
shall endorse it and submit it to Owner Representative and Design Professional, together 
with a statement of compliance in its own name. 
 
C. 
Unless Design Professional is requested at the time of submittal to return samples at 
Contractor's expense, rejected samples will be destroyed. 
 
D. 
After delivery of materials, the Owner Representative and Design Professional, may make 
such tests, as they deem necessary, with samples required for such tests being furnished 
by and at the cost of Contractor. Any test is for the benefit of Owner and shall not relieve 
Contractor of the responsibility for providing quality control measures to assure that the 
Work strictly complies with the Detailed Scope of Work and the Technical Specifications. 
No test shall be construed as implying acceptance of materials, work, workmanship, 
equipment, accessories or any other item or thing. 
 
E. 
On the basis of the test results, materials, workmanship, equipment or accessories may be 
rejected even though general approval has been given. If items have been incorporated in

State of Arizona 
49 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
the Work, Owner Representative after consultation with the Design Professional, and 
Owner shall each have the right to cause their removal and replacement by items meeting 
the Detailed Scope of Work and Technical Specifications requirements or to demand and 
secure appropriate reparation to Owner from the Contractor. 
 
8.19 
Tests, Inspections, Observations and Approvals Do Not Relieve Contractor of Responsibility 
A. 
No tests, inspections, observations or approvals performed or given by Owner 
Representative, Owner or Design Professional, or others acting for Owner or any agency 
of Federal, State or local government nor any acts or omissions by Owner Representative, 
Owner or Design Professional, in administering the JOC Program shall relieve Contractor 
from its duty to perform the Work in accordance with the Detailed Scope of Work and the 
Technical Specifications, the other Contract Documents and applicable law. 
 
Legal Requirements, Permits, Taxes and Fees 
 
B. 
Contractor shall be responsible for complying with all applicable Legal Requirements. 
Contractor shall be 100% responsible for and pay any costs associated with or arising from 
any non-compliance with Legal Requirements. 
 
C. 
Contractor shall pay all taxes for and related to the Work (including, without limitation, 
franchise taxes, sales taxes and use taxes) or its portion thereof, which are legally enacted 
when the Job Order is issued, whether or not yet effective. Contractor will not be 
reimbursed for any tax payments. 
 
8.20 
Contractor Provides Manufacturer’s Warranties and Manuals 
 
A. 
Contractor will provide Owner with all manufacturers’ warranties and operation and 
maintenance manuals upon Final Completion of the Job Order.

State of Arizona 
50 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 9 
SUBCONTRACTORS AND SUPPLIERS 
 
9.1 
Subcontractor Generally 
 
A. 
In addition to this Section 9 “Subcontractors and Suppliers”, there are many provisions 
relating to Subcontractors throughout the Contract Documents. The Owner has the right to 
reject any Subcontractor. 
 
9.2 
Contractor Self-Performance of Work 
 
A. 
Contractor may self-perform Work. 
 
9.3 
Contractor Subcontractor Selection Plan 
 
A. 
Contractor shall select Subcontractors for each Job Order on a qualifications only basis or 
on a qualifications and price basis. Subcontractors shall not be selected on a price only 
basis. The Contractor shall select Subcontractors in accordance with the subcontractor 
selection plan proposed by the Contractor in submitting its qualifications with those 
modifications as the Owner and the Contractor agreed to in writing. 
 
B. 
Although there is no contractual commitment, Owner encourages Contractor to have Work 
performed by small businesses. 
 
9.4 
Contractor Responsibilities Relating to Subcontractors 
 
A. 
Contractor agrees to pay each Subcontractor and Supplier the full amount due to the 
Subcontractor or Supplier within seven (7) business days after Contractor receives 
payment from Owner. 
 
B. 
Contractor is fully responsible for its Subcontractors’ Work and acts and omissions in 
connection with the performance of its Subcontractors’ Work. 
 
C. 
Contractor is responsible for coordinating the activities of all Subcontractors. 
 
9.5 
Subcontractor Relationship with Owner; Assignment of Subcontracts 
 
A. 
Nothing in the Contract Documents is intended or shall be construed or deemed to create 
any legal or contractual relationship between Owner and a Subcontractor. In addition, 
nothing in the Contract Documents is intended or shall be construed or deemed to create 
any third-party beneficiary rights.

State of Arizona 
51 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 10 
INSPECTIONS 
 
10.1 
General 
 
A. 
Design Professional and Owner shall at all times have access to the Detailed Scope of 
Work, including, without limitation, materials being fabricated or stored off site.  Contractor 
shall furnish at Contractor's cost any facilities necessary for sufficient and safe access to 
the Site. 
 
B. 
All Work and all materials are subject to inspection by Owner and Owner Representative 
to determine if they conform to the Contract Documents and Job Order. 
 
C. 
Contractor shall notify Owner and Design Professional by email or fax at least twenty-four 
(24) hours prior to the time at which Owner, Design Professional, or Owner Representative 
must be present to perform an inspection. Failure to provide such notice will place 
Contractor at risk for all consequences of non-inspection and having to uncover Work. 
 
D. 
Nonconforming Work or materials may be rejected and Contractor shall correct such 
rejected Work without additional compensation, even if the Work or materials have been 
previously inspected or accepted by Owner and Owner Representative or even if Owner 
or Owner Representative failed to observe the unsuitable Work or materials. 
 
E. 
Regardless of any notification by Contractor to Owner and Owner Representative that 
Work is ready for inspection, any Work which is covered prior to inspection by Owner 
Representative and Owner without prior consent of Owner Representative or Owner must 
be uncovered and recovered by Contractor, if requested by Owner Representative or 
Owner, at Contractor’s sole cost and expense and at no cost to Owner. 
 
F. 
If any portion of the Detailed Scope of Work has been covered after inspection by Owner 
Representative and Owner or with the consent of Owner Representative and Owner 
without inspection, Owner may request that it be uncovered for observation. If such portion 
is found to be in accordance with the requirements of the Contract Documents and the Job 
Order, the cost of uncovering and recovering it shall be charged to Owner. If such portion 
is found not to be in accordance with the requirements of the Contract Documents and the 
Job Order, Contractor shall pay such costs as well as the costs of correcting the non-
conforming Work. 
 
G. 
Inspections, tests, measurements, or other acts of Owner, Design Professional, and/or 
Owner Representative are for the sole purpose of assisting Owner, Design Professional, 
and Owner Representative in determining that the Work, materials, rate of progress, and 
quantities comply with the Contract Documents, Job Order and/or Contractor's requests 
for payment. These acts or functions and issuance of the Final Inspection Certificate as 
provided below shall not relieve Contractor from performing the Work in full compliance 
with the requirements of the Contract Documents nor relieve Contractor from any of the 
quality, compliance and responsibility for the Work assigned to it by the Contract 
Documents. No inspection or issuance of a Final Inspection Certificate or other action by 
Owner, Design Professional, or Owner Representative shall constitute or imply acceptance 
or waiver of rights.

State of Arizona 
50 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
10.2 
Design Professional Role in Inspections 
 
A. 
Design Professional, may inspect any Work on behalf of Owner and have the right to accept 
any Work on behalf of the Owner. Contractor shall rely on any inspection by Design 
Professional. Owner Representative may request Design Professional, engaged by Owner, 
to assist Owner Representative in inspection of Work. 
 
10.3 
Final Inspection 
 
A. 
The Punch List will be developed if it is determined at the inspection for Final Completion 
that there are deficiencies, corrections or incomplete items. 
 
B. 
When Contractor submits in writing to Owner a final Application for Payment for a Job 
Order and a request for a final inspection of the Detailed Scope of Work, Owner 
Representative and Owner shall determine the validity of the request. Owner 
Representative and Owner may request Design Professional, to participate in the 
determination. 
 
C. 
In making the determination whether to issue a Final Inspection Certificate and of the 
amount thereof, Owner Representative: 
 
1. 
May consult with Owner and Design Professional; 
 
2. 
May request Design Professional, to participate in the inspection or take other 
appropriate actions relating to the inspection; and 
 
3. 
Will visit and observe the site and evaluate whether the Detailed Scope of Work 
has been completed in conformance with the Contract Documents. 
 
D. 
Following the final inspection, 
 
1. 
If the Detailed Scope of Work is complete in accordance with the requirements of 
the Contract Documents and the Job Order, Owner Representative will issue a 
Final Inspection Certificate stating that to the best of the Owner Representative’s 
knowledge, information and belief, and on the basis of the Owner Representative’s 
observations and inspections, the Detailed Scope of Work(including, without 
limitation, all deficiency, incomplete and correction items (Punch List)) has been 
completed in accordance with the terms and conditions of the Contract Documents 
and the Job Order. 
 
2. 
If as a result of the inspection it is determined by Owner or Owner Representative 
that there are any deficiencies, corrections or incomplete items, Owner 
Representative will not issue the Final Inspection Certificate but instead will give 
Contractor a Punch List of such items. 
 
3. 
Contractor shall promptly complete or correct each of the items on the Punch List 
and may then request another final inspection. 
 
4. 
A Final Inspection Certificate will not be issued and final payment will not be made 
until all items on the Punch List and the Detailed Scope of Work are complete in 
accordance with the Contract Documents.

State of Arizona 
51 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
E. 
In the event Contractor does not complete the Detailed Scope of Work (including, without 
limitation, all Punch List items) within the Job Order Completion Time, Owner shall have 
the right to have these items corrected or completed by Owner or others, in which event 
Contractor shall pay or reimburse Owner for all costs and expenses incurred by Owner, 
including, without limitation, all architectural, engineering and inspection costs and 
expenses incurred by Design Professional, Owner Representative and Owner. 
Alternatively, Owner may deduct the amount owing by Contractor from any amount due 
Contractor under the Job Order or otherwise.

State of Arizona 
52 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 11 
PROJECT CLOSEOUT 
11.1 DEFINITIONS 
 
A. 
“Standard product warranties” means preprinted written warranties published by individual 
manufacturers for particular products and are specifically endorsed by the manufacturer to 
the Owner. 
 
B. 
“Special warranties” means written warranties required by or incorporated in the Contract 
Documents or the Job Order, either to extend time limits provided by the standard 
warranties or to provide greater rights for the Owner’s Representative. 
 
11.2 FINAL CLEANING 
 
A. 
Contractor shall employ experienced workers or professional cleaners for the final 
cleaning. Contractor shall perform the following special cleaning at completion of Work: 
 
1. 
Remove marks, stains, fingerprints, soil and dirt from finished surfaces. 
 
2. 
Remove spots, soil, paint, grout and mastic from tile work and wash same. 
 
3. 
Clean fixtures, equipment and piping; remove stains, paint, dirt and dust. 
 
4. 
Remove temporary floor protections; clean and polish floors. 
 
5. 
Clean exterior and interior metal surfaces, including doors and windows and their 
frames. 
 
6. 
Remove oil, stains, dust, dirt, paint and the like from items required to have a 
polished finish; polish and leave without finger marks or other blemishes. 
 
B. 
Existing improvements, inside or outside the property which are disturbed, damaged or 
destroyed by the Work shall be restored to the condition in which they originally were, or 
to the satisfaction of the Owner. 
 
11.3 
PROJECT RECORD DOCUMENTS 
 
A. 
As the Work progresses, the Contractor shall maintain a complete and accurate record of 
changes or deviations from the Detailed Scope of Work and Shop Drawings, indicating the 
Work as actually installed. Record information in the appropriate locations on a record set 
of blue line prints of the Drawings and Shop Drawings and a copy of the Specifications that 
are maintained solely for the purpose of this documentation.  Keep this set of record 
documents at the project site for review by the Owner and Owner Representative. 
Information contained in the record documents shall include, but not be limited to: 
 
1. 
Modifications made by Section 13, Change In Work, that shall be transferred to the 
record documents. 
 
2. 
Location of site underground pipes, conduits, ducts, cables and similar Work, 
dimensioned horizontally to permanent points of reference and located vertically 
by indicating depth of burial. Dimensions shall be accurate within +6 inches. 
 
3. 
Location of major conduit runs, power, control and alarm wiring, etc., dimensioned 
horizontally to permanent points of reference. Dimensions shall be accurate within 
6 inches. By notation, describe the vertical location of the item such as "below 
slab," "above ceiling," etc.

State of Arizona 
53 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
4. 
Modifications made to accommodate field conditions. 
 
5. 
Revise Drawings and panel schedules to show final circuiting of all equipment. 
 
B. 
The Owner Representative will provide the Contractor with a set of reproducible drawings 
at Contractor's expense. Seals and signatures of Registrants shall be completely removed 
and/or permanently obscured. Contractor shall provide the following on the Drawings: 
 
1. 
Changes in the Job Order, secured with prior approval of the Owner 
Representative, recorded in a neat readable manner, in black ink or pencil, by a 
competent drafter. Deletions shall be made by erasure or sepia eradicator only. 
 
2. 
Prior to application for final payment, transfer all changes, information and 
notations made to the record blue-line prints to a set of sepia Mylar transparencies. 
 
C. 
Upon Final Completion, deliver the complete set of Record Documents including blue-line 
prints, sepia Mylar transparencies, Shop Drawings and annotated Specifications to the 
Owner Representative for approval. 
 
D. 
Owner's Manual: Prior to final payment, submit two (2) hard copies in binders and two (2) 
electronic copies containing the following required submittals and any others required in 
other Sections, suitably typed, indexed and labeled for ready reference: 
 
1. 
Subcontractors, major Suppliers list with company’s names, addresses and 
telephone numbers. 
 
2. 
Warranties and certifications. 
 
3. 
Affidavit from general and Subcontractors on use of asbestos free materials (See 
Attachment 4 to Form of Job Order). 
 
4. 
Maintenance/operation instructions and parts list (other than Division 28). 
 
5. 
List of Extra Materials supplied to Owner, signed by Owner's Representative. 
 
6. 
Other items required by the Specifications. 
 
E. 
The following list is intended as a guide to the Contractor to aid in the determining record 
documents required for the project, however, the requirements specified in the technical 
sections shall take precedence over this list and this list is not to be interpreted as being 
complete. 
 
1. 
Division 00 through Division 48 
 
11.4 
OPERATION AND MAINTENANCE DATA 
 
A. 
Upon Final Completion specified under Division 28, Contractor shall furnish two (2) hard 
copies in binders and two (2) electronic copies of operating and maintenance instructions 
and parts lists for materials, equipment and systems, including electrical and control items, 
being supplied. 
 
B. 
Operating instructions shall include complete operating sequence, control diagrams, 
description of method of operating machinery, machine serial numbers, factory order 
numbers, parts, tests, instruction books, Suppliers’ phone numbers and addresses and 
individual equipment guarantees. Parts lists shall be complete in every respect, showing 
parts and part numbers for ready reference.

State of Arizona 
54 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
C. 
Maintenance instructions shall include a written list of required and suggested maintenance 
for HVAC, electrical, fire alarm or other equipment or features in the project. Each item 
shall contain a brief description of the maintenance required as well as the recommended 
time frame or period for the maintenance. 
 
D. 
Contractor shall assemble maintenance manual and operating instructions in hard back 
loose leaf binders and suitably label and index material for ready reference. 
 
E. 
Upon Final Completion, Contractor shall submit one copy of the Maintenance Manual and 
Operating Instructions to the Design Professional for approval and upon receipt of Notice 
of Approval, deliver the additional corrected copies to the Owner. 
 
11.5 
OPERATION AND MAINTENANCE MANUAL 
 
A. 
Owner’s Manual: Prior to final payment, contractor shall submit one (1) hard copy for review 
to the Design Professional. Upon approval, Contractor shall determine how many manuals 
are required containing the following required submittals and any others required in other 
Sections, suitably typed, indexed and labeled for ready reference. 
 
B. 
Upon Substantial Completion, Contractor shall furnish two (2) hard copies in binders and 
two (2 ) electronic of operating and maintenance instructions and parts lists for 
materials, equipment and systems, including electrical and control items, being 
supplied. Contractor shall furnish separate copies for each Division. 
 
C. 
Operating instructions shall include complete operating sequence, control diagrams, 
description of method of operating machinery, machine serial numbers, factory order 
numbers, parts, tests, instruction books, Suppliers’ phone numbers and addresses and 
individual equipment guarantees. Parts lists shall be complete in every respect, showing 
parts and part numbers for ready reference. 
 
D. 
Maintenance instructions shall include a written list of required and suggested maintenance 
for HVAC, fire alarm, electrical or other equipment or features in the project. Each item 
shall contain a brief description of the maintenance required as well as the recommended 
time frame or period for the maintenance. 
 
E. 
Contractor shall assemble maintenance manual and operating instructions in hard back 
loose leaf binders, suitably labeled and indexed for ready reference. 
 
11.6 
SPARE PARTS AND MAINTENANCE MATERIALS 
 
A. 
Contractor shall provide products, spare parts, and maintenance materials in quantities 
specified in each section, in addition to that used for construction of Work. Contractor shall 
coordinate with Owner, deliver to person and location as directed and obtain receipt. 
Contractor shall copy receipt to the Design Professional and Owner. This documentation 
is required prior to final payment. 
 
B. 
Contractor shall deliver spare parts, tools, and extra stocks of material and similar physical 
items required by individual specification sections to the Owner with a copy of the 
transmittal to the Design Professional. Contractor shall obtain signed receipts from the 
Owner for all items. 
 
C. 
Contractor shall change over construction locks to permanent keying system and deliver 
the required number of keys to the Owner. Contractor shall prepare a transmittal document 
and obtain signed receipts from the Owner for all items. 
 
11.7 
SUMMARY

State of Arizona 
55 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
A. 
This Section includes administrative and procedural requirements for warranties required 
by the Contract Documents, including manufacturer’s standard warranties on products and 
special warranties. 
 
B. 
Refer to the Contract Documents of the contract for terms of the period for correction of the 
Work. 
 
C. 
Disclaimers and Limitations: Manufacturer’s disclaimers and limitations on product 
warranties do not relieve the Contractor of the warranty on the Work that incorporates the 
products. Manufacturer’s disclaimers and limitations on product warranties do not relieve 
Suppliers, manufacturers, and Subcontractors required to countersign special warranties 
with the Contractor 
 
D. 
Separate Prime Contracts: Each Prime Contractor is responsible for warranties related to 
its own contract. 
 
11.8 
WARRANTY REQUIREMENTS 
 
A. 
Warranties required by the Contract Documents shall commence on the date Substantial 
Completion is certified by the Design Professional. 
 
B. 
Related Damages and Losses: When Contractor corrects failed or damaged warranted 
construction, Contractor shall remove and replace construction that has been damaged as 
a result of such failure or must be removed and replaced to provide access of correction of 
warranted construction. 
 
C. 
Reinstatement of Warranty: When Work covered by a warranty has failed and been 
corrected by replacement or rebuilding; Contractor shall reinstate the warranty by written 
endorsement.  The reinstated warranty shall be equal to the original warranty including an 
equitable adjustment for depreciation. 
 
D. 
Replacement Cost: Upon determination that Work covered by a warranty has failed, 
Contractor shall replace or rebuild the Work to an acceptable condition complying with 
requirements of the Contract Documents and the Job Order. The Contractor is responsible 
for the cost of replacing or rebuilding defective Work regardless of whether the Owner had 
benefited from use of the Work through a portion of its anticipated useful service life. 
 
E. 
Owner Recourse: Express warranties made by Contractor to the Owner are in addition to 
implied warranties and shall not limit the duties, obligations, rights, and remedies otherwise 
available under the law. Express warranty periods shall not be interpreted as limitations on 
the time in which the Owner can enforce such other duties, obligations, rights, or remedies. 
 
F. 
Rejection of Warranties: The Owner reserves the right to reject warranties that conflict with 
requirements of the Contract Documents. 
 
11.9 
SUBMITTALS 
 
A. 
Contractor shall submit written warranties to the Design Professional prior to the date 
certified for Substantial Completion. If the Certificate of Substantial Completion designates 
a commencement date for warranties other than the date of Substantial Completion for the 
Work, or a designated portion of the Work, the Contractor shall submit written warranties 
upon request of the Owner. 
 
B. 
When a designated portion of the Work is completed and occupied or used by the Owner, 
by separate agreement with the Contractor, during the construction period, Contractor shall 
submit properly executed warranties to the Owner within fifteen (15) days of the completion 
of that designated portion of the Work.

State of Arizona 
56 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
C. 
Form of Submittal: At Final Completion, Contractor shall compile two (2) hard copies in 
binders and two (2 ) electronic copies of each required warranty properly executed by the 
Contractor, Subcontractor, Supplier, or manufacturer. The warranty documents must be 
organized into an orderly sequence based on the table of contents of the Project Manual. 
 
D. 
Contractor shall bind warranties and bonds in heavy-duty, commercial-quality, durable 3- 
ring, vinyl-covered loose-leaf binders, thickness as necessary to accommodate contents, 
and: 
 
1. 
Provide heavy paper dividers with celluloid covered tabs for each separate 
warranty. Mark the tab to identify the product or installation. Provide a typed 
description of the product or installation, including the name of the product, and 
name, address, and telephone number on the Installer. 
 
2. 
Identify each binder on the front spine with the typed or printed title 
“WARRANTIES”, Project title of name, and name of the Contractor. 
 
3. 
When warranted construction required operation and maintenance manuals, 
provide additional copies of each required warranty, as necessary, for inclusion in 
each required manual. 
 
11.10 
EXAMINATION AND PREPARATION 
 
A. 
Contractor shall examine substrates and conditions for compliance with manufacturer's 
written requirements including, but not limited to, surfaces that are sound, level, plumb, 
smooth, clean, and free of deleterious substances; substrates within installation tolerances; 
and application conditions within environmental limits. Contractor shall proceed with 
installation only after unsatisfactory conditions have been corrected. 
 
B. 
Before proceeding to lay out the Work, Contractor shall verify layout information shown in 
the Detailed Scope of Work, in relation to property survey and existing benchmarks. 
 
C. 
Contractor shall take field measurements as required to fit the Work properly. Where 
fabricated products are to be fitted to other construction, verify dimensions by field 
measurement before fabrication and, when possible, allow for fitting and trimming during 
installation. 
 
11.11 
CORRECTION OF WARRANTY WORK 
 
A. 
The Contractor is required to perform warranty repair work. When the Contractor fails to 
perform the warranty repair Work in accordance with these Contract Documents and the 
Job Order, the Owner may complete the repair work and seek reimbursement, for the 
expenses incurred, from the Contractor or may offset incurred expenses against amounts 
due to the Contractor. 
 
B. 
The Owner’s Representative and/or Owner shall serve as the Warranty Coordinator and 
may designate an Alternate Warranty Coordinator who shall have the authority and 
responsibility to perform the Coordinator’s functions when the Coordinator is absent. The 
Warranty Coordinator shall maintain: 
 
1. 
An updated list of all building/systems that are covered by a warranty. 
 
2. 
An updated schedule of all equipment under warranty and their warranty period. 
 
C. 
Before authorizing repairs to or replacement of parts on any building/system, the Warranty 
Coordinator shall determine if a valid warranty, covering the specific failure, exists. The 
Warranty Coordinator shall avoid, whenever possible, any action that may void a warranty.

State of Arizona 
57 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
D. 
When a valid warranty exists, the Warranty Coordinator shall contact the Contractor 
regarding the terms of the warranty. The Warranty Coordinator shall provide copies of the 
Warranty Notification to Owner Representative, Owner, the Contractor and the responsible 
Subcontractors, manufacturers and Suppliers. 
 
E. 
If there is no warranty covering the specific failure, or if the warranty has expired, the 
Warranty Coordinator shall ensure that the necessary repairs/replacements are completed 
in accordance with the appropriate written instructions. 
 
F. 
Warranty Coordinator shall evaluate all failures covered by a warranty and determine the 
required timeframe for correction based on the urgency of the failure. Failures will be 
categorized as Emergency, Urgent or General. Upon notification of warranty Work 
required, the Subcontractor shall complete the warranty repair Work in the following 
timeframe: 
 
1. 
Emergency repair Work with in four (4) hours 
 
2. 
Urgent repair Work within sixteen (16) hours 
 
3. 
General service or repairs within five (5) days 
 
G. 
Emergency failures require immediate action to resolve imminent threats to health, life, 
safety or a security system failure. When the Warranty Coordinator determines that an 
emergency situation exists, he/she shall authorize immediate action to control the 
emergency and prevent greater loss. 
 
1. 
Upon determination that the failure is covered by a warranty, the Coordinator shall 
complete a Warranty Notification Form, immediately notify the Contractor and 
coordinate with the Contractor for immediate repair. 
 
2. 
The Warranty Coordinator may extend the allowable timeframe, provided the 
Contractor has submitted a written request and has documented that the problems 
requiring the time extension are beyond their control. The Contractor shall reach 
an agreement with the Warranty Coordinator on the specific repairs to be 
performed, when the repairs will be completed, and document the agreement in a 
letter to the recipients of the Warranty Notification. 
 
H. 
In the event that the Contractor fails to respond and/or restore the building/systems to 
operating condition within the specified time period, the Warranty Coordinator will arrange 
for the Work to be performed by qualified personnel/contractors. The Contractor shall be 
responsible for reimbursing the Owner for the expenses incurred. 
 
I. 
Warranty Coordinator shall monitor all on-site repairs done by any Contractor in response 
to a warranty claim request to ensure compliance with the repair agreement. The Warranty 
Coordinator shall ensure that each warranty claim is fully documented. 
 
1. 
Contractor shall assign a representative to walk with the Owner Warranty 
Coordinator to review the completed project six (6) months and eleven (11) months 
after final completion date. Contractor shall document any found deficiencies. 
Items found requiring correction, modification, or warranty attention shall be 
documented and resolved as noted in this specification section. 
 
 
11.12 
PROJECT CLOUSEOUT CHECKLIST 
 
A. 
SPARE PARTS AND MAINTENANCE MATERIALS

State of Arizona 
58 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
1. 
Contractor shall deliver spare parts, tools, extra stocks of material and similar 
physical items required by individual Specification sections to the Owner with a 
copy of the transmittal to the Owner Representative and obtain signed receipts 
from the Owner for all items. 
 
B. 
OWNER TRAINING 
 
1. 
The Contractor shall include all costs associated with providing educational 
services necessary for (1) State of Arizona employee to become a factory 
authorized, fully certified technician for the fire alarm equipment, HVAC equipment 
and electrical systems being supplied and installed by the JOC Contractor. 
 
2. 
The educational services shall be provided locally (offered in the City of Phoenix 
metropolitan area) and shall be inclusive of all necessary educational / training 
classes, seminars, instructor fees and their associated travel expenses, learning 
materials, demonstration systems, tools, testing equipment, etc. as required for full 
factory certification. 
 
 
3. 
Schedule: Contractor shall provide warranties on products and installations for the 
following: 
 
a. 
Door Hardware 
b. 
Fire Alarm Systems 
c. 
HVAC Equipment 
d. 
Electrical Systems

State of Arizona 
60 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
WARRANTY NOTIFICATION 
Warranty File Claim Number   
 
 
To:  
Facility  
Date  
 
 
Warranty repair service is requested for the following problem: 
 
Problem Description 
 
 
Equipment involved 
Equipment ID Number 
 
Location of Problem-Building/Room Number or Area 
Warranty Coordinator Familiar with 
Problem 
 
Severity of Problem: 
Emergency 
Urgent 
General 
 
FOLLOW-UP TELEPHONE CALLS: 
 
Called 
on 
at 
Called 
on 
at 
Called 
on 
at 
 
 
This request for service will remain an outstanding item until a disposition response including 
the Contractor’s representative signature, is received. 
 
CONTRACTOR DISPOSITION: 
 
Date Request Received 
Time Received 
 
 
Who Resolved 
When 
 
 
Description of Action Taken 
 
 
Contractor’s Representative Signature 
Your assistance in obtaining prompt correction of this problem is appreciated. 
Sincerely, 
Warranty Coordinator 
 
 
END OF SECTION

State of Arizona 
61 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
CLOSEOUT CHECK LIST 
 
 
 
PROJECT: 
 
FACILITY: 
 
CONTRACTOR:    
 
 
Owner PROJECT NO.   
 
 
Submit the items required for your contract and project specifications as well as special items 
called for in the specifications not covered by this list. 
 
A. 
General Requirements: (Two (2) binders with hard copies and two (2) electronic 
copies) 
 
1. 
Certificate of Final Completion - AIA Form G704 or similar form 
acceptable to the Owner 
2. 
Final Pay Request 
 
3. 
Affidavit of Payment of Debts & Claims - AIA Form G706 or similar form 
acceptable to the Owner 
4. 
Affidavit of Release of Lien - AIA Form G706A or similar form acceptable 
to the Owner (Conditional or Unconditional as required by Owner) 
5. 
Consent of Surety - AIA Form G707 or similar form acceptable to the 
Owner (if bonded) 
6. 
Prime Consultant (A/E) Letter Certifying that Project completed according 
to Plans and Specifications 
 
B. 
Lien Waivers: (Two (2) binders with hard copies and two (2) electronic copies) 
 
1. 
All Subcontractors and Material Suppliers (see list submitted with bid and 
all approved substitutions) 
2. 
All Vendors with Preliminary Notices Filed 
 
 
C. 
Guarantees: (These are minimum warranty periods unless specifications state 
otherwise. (Two (2) binders with hard copies and two (2) electronic copies) 
   
 
1. 
Total project guarantee 2 years by Contractor 
  
 
2. 
Electrical (2 year by Subcontractor) 
  
 
3. 
Fire Alarm System (2 year Subcontractor) 
  
 
4. 
HVAC System (2 year Subcontractor) 
  
 
 
D. 
"As-Built" Drawings:   
1. 
Complete set of Construction Documents and (Two (2) hard copies and two 
(2) electronic copies) 
2. 
CAD backgrounds from Architect and Engineer to be submitted in electronic 
form 
 
E. 
Record Construction Documentation: Copies of the following items to be inserted in 
overall General Requirements Binders and in electronic form. 
1. 
Addenda 
2. 
Architect/Engineer's Supplemental Instructions (ASI/ESI) 
  
 
3. 
Change Orders 
4. 
Requests for Information 
  
 
 
F. 
Maintenance & Operations Manuals:  Provide in two (2) bound binders and two (2)

State of Arizona 
62 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
electronic forms.: 
 
1. 
Electrical 
2. 
Fire Alarm System 
  
 
3. 
HVAC System 
 
 
 
 
 
4. 
To be included in O&M: 
 
a) 
Subcontractors, major suppliers list with company’s names, 
addresses and telephone numbers. 
 
b) 
Warranties and certifications. 
 
c) 
Affidavit from general and subcontractors on use of asbestos free 
materials  
 
d) 
Maintenance/operation instructions and parts list. 
 
e) 
List of Extra Materials supplied to Owner (keys, video training tapes, 
etc. if applicable), signed by Owner’s Representative. 
 
f) 
Manufacturers’ Data Sheets 
 
g) 
Other items required by the Specifications 
 
END OF SECTION

State of Arizona 
63 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 12 
MEASUREMENT AND PAYMENT 
This Section 12 is applicable in the event progress payments will be utilized or as otherwise indicated on 
the Job Order. 
 
 
12.1 
SCHEDULE OF VALUES 
 
A. 
Applications for Payment shall be made on AIA Document G702 or similar forms 
acceptable to the Owner. 
 
B. 
The first Application for Payment package shall include the Application for Payment 
document as well as the Schedule of Values indicating the scheduled value of major 
categories and subcontracts for the Work. Contractor shall submit six (6) copies of the 
package for approval by the Owner Representative. 
 
C. 
For each item, Contractor shall provide a column for listing: Item number; Description of 
Work; Scheduled Value, Previous Applications: Work in Place and Stored Materials under 
this Application; Authorized Supplemental Job Orders; Total Completed and Stored to Date 
of Application; Percentage of Completion; and Balance to Finish. 
 
12.2 
PAY REQUEST 
 
A. 
The form of Application for Payment shall be a notarized AIA Document G702, or 
similar notarized form acceptable to the Owner, supported by approved AIA 
Document G703, or similar notarized form acceptable to the Owner. Unless 
otherwise directed by the Customer, a minimum of two (2) original copies of these 
forms shall be submitted for each application. Contractor shall: 
 
1. 
Present required information in typewritten form or electronic media printout to 
the Design Professional. 
 
2. 
Execute certification by signature of authorized officer. (NOTARIZED) 
 
3. 
Use data from approved Schedule of Values. Provide dollar value in each column 
for each line item for portion of Work performed and for stored products. 
Schedule of Values shall include line items for As-Builts, Bond, Supervision, 
General Conditions and Overhead and Profit. 
 
4. 
List each authorized Supplemental Job Order as an extension on continuation 
sheet, listing Supplemental Job Order number and dollar amount as for an 
original item of Work. 
 
B. 
With each Application for Payment Contractor shall submit lien releases for the 
previous payment, substantiation for stored materials, monthly progress reports and 
updates, and any other pertinent items required by the Owner or Owner Representative 
and identified during the Pre-Construction Conference. 
 
C. 
Contractor shall use AIA Documents G706, Contractor's Affidavit of Payment of Debts 
and Claims, G706-A, Contractor's Affidavit of Release of Liens, Documents G707, 
Consent of Surety Company to Final Payment, or similar forms acceptable to the 
Owner. 
 
D. 
When acceptable to the Owner, the Contractor may submit for payment on properly 
stored materials not yet incorporated into the Work. Materials stored on the site must 
be in a secured area and be protected from damage, weather, theft or vandalism. 
The Contractor shall be responsible for replacing any damaged or missing 
materials.

State of Arizona 
64 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
E. 
Offsite storage shall not be permitted. Stored materials must be located onsite. 
 
F. 
See Project Closeout Section 11 for Final Billing Procedure. 
 
12.3 
PAY FREQUENCY 
 
A. Job Orders With a Job Order Completion Time Less Than Thirty (30) Days. Contractor 
shall submit a single Application for Payment, as per Section 12 of this document, after Final 
Completion (including, without limitation, all deficiency, correction or incomplete items (Punch 
List). 
 
B. Job Orders With a Job Order Completion Time Greater Than Thirty (30) Days. Contractor 
shall initiate Progress Payments by monthly Applications for Payment submitted as per 
Section 12 of this document. Such payments shall be made in accordance with A.R.S. 
§ 41-2577. 
 
12.4 
CERTIFICATES OF PAYMENT. Within seven (7) days after the receipt of Contractor’s Application 
for Payment, the Design Professional will either issue a Certificate for Payment to Contractor for 
such amount as the Design Professional determines is properly due or notify the Contractor in 
writing of the reasons for withholding a Certificate for Payment. If the Design Professional or 
Owner Representative fails to take action within the seven (7) days, the Application for Payment 
will be deemed to have been approved and a Certificate for Payment for the full amount in the 
Application for Payment will be deemed to have been issued by Design Professional. 
 
12.5 
PAYMENTS 
 
A. Owner shall make payments on or before fourteen (14) days after the issuance of a Certificate 
for Payment against an Application for Payment. If a portion of an Application for Payment is 
disputed, the undisputed portion will be paid within fourteen (14) days after the Design 
Professional provides notification to the Contractor of the items in dispute. 
 
B. Before the Owner determines to pay nothing or to pay less than the amount requested by 
Contractor, the Design Professional and Owner must discuss the matter with the Site 
Manager and they must attempt to come to a mutually satisfactory resolution of the matter. 
If they do not concur, Design Professional will make a final determination. If the Contractor 
disagrees with Design Professional's final determination, Contractor may pursue the matter 
under Special Terms and Conditions, Paragraph 10, Claims. 
 
C. All material and Work covered by a paid partial payment shall thereupon become the sole 
property of the Owner. Nothing in this Subparagraph shall be construed as relieving the 
Contractor from sole responsibility of care and protection of materials and Work upon which 
payments have been made or restoration of any damaged Work or as a waiver of the right of 
the Owner to require fulfillment of all terms of the Contract Documents. 
 
 
12.4 
FINAL PAYMENT 
 
A. The Contractor shall submit to the Design Professional a final Certificate for Payment with the 
Final Inspection Certificate. 
 
B. The final payment shall not become due until the Contractor also submits all items required in 
12.02 (C) above. 
 
C. After the Design Professional has issued the Final Inspection Certificate and the final 
Certificate for Payment for a Job Order; after the Owner has received all other documents 
required by the Contract Documents; and after the Contractor has complied with the other 
requirements of the Contract Documents and the Job Order, Owner shall make final payment 
(“Final Payment”) under the Job Order in the manner provided in the Contract Documents.

State of Arizona 
65 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
D. The acceptance of final payment for a Job Order shall constitute a waiver of all claims by the 
Contractor except those previously submitted to Owner and Design Professional in writing 
and identified by the Contractor as unsettled at the time of the final Application for Payment. 
 
E. If any Subcontractor or Supplier refuses to furnish a release or waiver required by Owner, 
Contractor may furnish a bond satisfactory to Owner to indemnify Owner against any such 
lien. 
 
F. If any claim or lien remains unsatisfied after all payments are made under a Job Order, 
Contractor shall immediately upon demand refund to Owner all moneys that the latter may be 
compelled to pay in discharging such claim or lien, including all costs and reasonable 
attorneys’ fees. 
 
12.5 
SUBCONTRACTORS 
 
A. The Contractor shall pay to the Contractor's Subcontractors or material Suppliers and each 
Subcontractor shall pay to the Subcontractor's subcontractor or material supplier, within seven 
(7) days of receipt of each progress payment, unless otherwise agreed in writing by the parties, 
the respective amounts allowed the Contractor or subcontractor on account of the Work 
performed by the Contractor's or Subcontractor's subcontractors, to the extent of each such 
subcontractor's interest therein, except that no contract for construction may materially alter 
the rights of any Contractor, Subcontractor or material Supplier to receive prompt and timely 
payment as provided under this section. These payments to subcontractors or material 
suppliers shall be based on progress payments received. 
 
B. Neither Owner nor Owner Representative shall have any obligation to pay or to see to the 
payment of any moneys to any Subcontractor, except as may otherwise be required by law.

State of Arizona 
66 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 13 
CHANGES IN WORK 
13.1 
SUMMARY 
A. 
Section Includes: Procedures and documents for changes, deletions, or additions to the 
Detailed Scope of Work for a Job Order that has been issued. 
 
13.2 
DEFINITIONS 
A. 
“Construction Change Directive” (CCD) means a document signed by Owner and the 
Design Professional only, directing the Contractor to proceed with the changes, deletions, 
or additions to the Detailed Scope of Work and stating a proposed basis for adjusting the 
Job Order Price and Job Order Completion Time. This form is used in the absence of 
agreement on the terms of the Supplemental Job Order. 
 
13.3 
PROCEDURES 
A. 
Initiation of Proposals for Changes, Deletions, or Additions: 
 
1. 
From time to time, the Owner or the Design Professional may issue to the 
Contractor, a Job Order Proposal Request for a change, deletion, or addition in the 
Detailed Scope of Work. The request will contain a Detailed Scope of Work 
containing a description of the change, deletion or addition, and Drawings and 
Specifications, as applicable. 
 
2. 
The Contractor may also propose a change, deletion, or addition in the Detailed 
Scope of Work due to unforeseen conditions or from supplemental instructions 
received from the Design Professional, by submitting a request therefore in writing. 
This request is submitted to the Design Professional and describes the proposed 
change, deletion, or addition stating the reason therefore, and the impact on the 
Job Order Price and Job Order Completion Time, with supporting documentation. 
 
B. 
Execution of Documents: 
 
1. 
When a Job Order Proposal Request in connection with a Supplemental Job Order 
is received by the Contractor, the Contractor shall respond within seven (7) days 
by submitting a Job Order Proposal for such Supplemental Job Order in 
accordance with the Procedures to Develop all Job Orders. Likewise, the Design 
Professional shall respond to the Contractor's written request for a change, 
deletion, or addition within seven (7) days of receipt. 
 
2. 
In the absence of total agreement on the Supplemental Job Order, the Owner may 
issue a CCD to be followed by a Supplemental Job Order when an agreement is 
finally made. 
 
3. 
The Contractor shall promptly proceed with all changes, deletions, and additions 
upon receipt of an executed Supplemental Job Order or Construction Change 
Directive. 
 
C. 
Computation of Costs: 
 
1. 
The Contractor shall compute the cost of changes, deletions, or additions in 
accordance with Section 8, Procedures to Develop all Job Orders. 
 
2. 
Credits for Prepriced and Non Prepriced Tasks shall be calculated at the pre-set 
Unit Prices and multiplied by the appropriate Adjustment Factors. The result is that 
a credit for Tasks that have been deleted from the Detailed Scope of Work will be 
given at 100% of the value at which they were included in the original Price 
Proposal.

State of Arizona 
67 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 14 
SITE CONDITIONS 
 
14.1 
Contractor shall be thoroughly acquainted with all information provided by Owner or Design 
Professional, concerning the conditions of the Work. In addition, Contractor shall be responsible 
for obtaining information concerning conditions of the Work typically obtained within the 
construction industry to assess conditions for similar projects. Contractor is responsible for correctly 
and fully estimating the difficulty and cost of successfully performing the Detailed Scope of Work. 
 
14.2 
Contractor agrees that before submitting the Proposal, Contractor will thoroughly examine 
(collectively, the “Site Information”): 
 
A. 
the Site, 
 
B. 
the Detailed Scope of Work, 
 
C. 
all as-built data provided to Contractor by Owner or the Design Professional, and if 
applicable, any boring data or other soils information, 
 
D. 
all other information provided by Owner or any Design Professional concerning the 
conditions of the Site, and 
 
E. 
all information which Contractor is responsible to obtain under the paragraph immediately 
above. 
 
14.3 
Contractor acknowledges that as-built data and, if applicable, any boring data and other soils 
information made available to it is only a general indication of materials and/or conditions likely to 
be found in existing structures or facilities or other areas and, if applicable, adjacent to borings. If 
Contractor determines that the information is erroneous, inadequate or ambiguous, it shall 
immediately report its conclusions to Owner Representative, Owner and the Design Professional 
in writing. If, after determining that the information is erroneous, inadequate, or ambiguous, and 
after reporting its conclusions, Contractor remains dissatisfied or uninformed, Contractor shall 
refrain from submitting a Proposal until the matter is resolved. If Contractor submits a Proposal, 
Contractor shall be deemed to have waived any claim it may have as the result of the alleged 
erroneous, inadequate or ambiguous information. By submission of a Proposal, Contractor 
represents and warrants to Owner that Contractor has examined and evaluated the Site Information 
and has taken the Site Information into account in preparing its Proposal. 
 
14.4 
Contractor shall immediately, and before such conditions are disturbed, notify Owner 
Representative, Owner and the Design Professional in writing of concealed or latent physical 
conditions or subsurface conditions encountered at a Site that were not known by Contractor that 
could adversely affect the Job Order Price or the Job Order Completion Time, and that both: 
 
A. 
differ materially from those indicated by the Site Information and could not have been 
discovered by careful examination and investigation of the Site Information provided or 
obtained at the time of submission of the Proposal or by the date on which the Job Order 
was issued by Owner; and 
 
B. 
are of an unusual nature, differing materially from those ordinarily encountered in the locale 
or generally recognized as inherent in construction Work of the character provided for in 
the Job Order. 
14.5 
Owner shall within ten (10) days after receipt of notice from Contractor, or such other longer 
reasonable time as necessary, investigate the conditions reported by Contractor under the 
paragraph immediately above. If Owner finds that conditions are so materially different as to support 
an equitable adjustment in the Job Order Price or Job Order Completion Time, an equitable 
adjustment will be accomplished by a Supplemental Job Order. The Supplemental Job Order Price 
will be for the actual, demonstrated direct cost impact to address the unforeseen

State of Arizona 
68 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
condition. Extensions of Job Order Completion Time will be considered only when based upon 
submission of an updated Construction Schedule showing an actual unavoidable delay to the 
critical path resulting from the unforeseen condition. If Owner determines that no Supplemental Job 
Order will be issued, there will be no change in the Job Order Price or the Job Order Completion 
Time for the respective Job Order. Regardless of the outcome, Contractor shall continue with the 
original Detailed Scope of Work. 
 
14.6 
No claim by Contractor for an increase in the Job Order Price or the Job Order Time shall be 
allowed without proper advance notice and an adequate opportunity for Owner to investigate. 
 
14.7 
The Owner may, at its option, include quantities in the Detailed Scope of Work if it helps to define 
the Detailed Scope of Work, if the actual quantities required are not known or cannot be 
determined at the time the Detailed Scope of Work is prepared, if the Contractor and the Owner 
cannot agree on the quantities required, or for any other reason as determined by the Owner. In 
all such cases, the Owner shall issue a Supplemental Job Order adjusting the quantities 
appearing in the Detailed Scope of Work to the actual quantities.

State of Arizona 
69 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 15 
ADJUSTMENT OF THE ADJUSTMENT FACTORS 
A. 
The State may consider a request for increase in the Adjustment Factors on each 
anniversary of the award date to account for changes in construction costs, provided, the 
Contractor requests in writing, no less than thirty days prior to the anniversary of the 
award date, that the Adjustment Factors be updated. Such request shall be delivered to 
the State and to Gordian. In the event the Contractor fails to deliver the request timely, 
then the State shall determine the date on which the Adjustment Factors will be updated, 
if approved, but in no event will such date be later than thirty days after the written request 
to update the Adjustment Factors is received by the State.  
B. 
Thereafter, Contractor’s Normal Working Hours and Other than Normal Working Hours 
Adjustment Factors will be adjusted according to the following: 
1. 
A Base Year Index shall be calculated by averaging the 12-month Construction 
Cost Indices (CCI) the average of the twenty cities published in the Engineering 
News Record (ENR) for the 12 months immediately prior to the month of the bid 
due date (e.g. April bid date, Base Year Index is April of the prior year to March 
of the bid date year). 
2. 
A Current Year Index shall be calculated by averaging the 12-month Construction 
Cost Indices (CCI) for the average of the twenty cities published in the 
Engineering News Record (ENR) for the 12 months beginning with the month of 
anniversary of the bid due date (e.g. April bid date, Current Year Index is April of 
the prior year to March of the current year). 
3. 
The Economic Price Adjustment shall be calculated by dividing the Current Year 
Index by the Base Year Index. 
4. 
The Contractor’s original Adjustment Factors shall be multiplied by the Economic 
Price Adjustment to obtain the Contractor’s new Adjustment Factors effective for 
the next 12 months. 
5. 
Averages shall be obtained by summing the 12 month indices and dividing by 12. 
6. 
All calculations in this article shall be carried to the fifth decimal place and 
rounded to the fourth decimal place. The following rules shall be used for 
rounding: 
7. 
The fourth decimal place shall be rounded up when the fifth decimal place is five 
(5) or greater. 
8. 
The fourth decimal place shall remain unchanged when the fifth decimal place is 
less than five (5). 
C. 
ENR occasionally revises indices. ENR CCIs used in the calculations described above 
shall be those currently published at the time the Economic Price Adjustment calculation 
is performed. No retroactive adjustments will be made as a result of an ENR revision. 
Revised CCI indices, if any, shall be used in subsequent calculations. 
D. 
Under all circumstances, should the Contractor submit a Job Order Proposal with 
inaccurate Adjustment Factors, the act of submission by the Contractor is a waiver of all 
rights to any further compensation above the Job Order Price submitted in the Job Order 
Proposal. 
E. 
The Contractor cannot delay submission of the Job Order Proposal past the due date to 
take advantage of a scheduled update of the Adjustment Factors. In that event, the

State of Arizona 
70 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
Contractor shall use the Adjustment Factors that would have been in effect without the 
delay. 
F. 
The Adjustment Factors for Reimbursable Tasks will remain constant for the duration of 
the Contract and a not to exceed amount for Non Prepriced Tasks.

State of Arizona 
71 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 16 
TIME PERIOD TO ISSUE JOB ORDERS 
All Job Orders issued during the term of this Contract shall be valid and in effect notwithstanding that the 
Detailed Scope of Work may be performed, payments may be made, and the guarantee period may 
continue, after such period has expired. All terms and conditions of the Contract apply to each Job Order.

State of Arizona 
70 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 17 
ADMINISTRATIVE AND COOPERATIVE FEES 
 
Other state agencies and purchasing cooperative members within the State of Arizona may 
purchase construction services from the Contractor utilizing this Contract through a cooperative 
purchasing arrangement as provided in Special Terms and Conditions, Paragraph 2.5, Eligible 
Agencies. The Contractor acknowledges that The Gordian Group, Inc. will administer this Contract 
for other state agencies and cooperative program members through its ezIQC® system and its 
subsidiary EZIQC, LLC and that the State of Arizona has no obligation to administer Work 
performed for other entities. 
 
The Contractor shall inform the Gordian Group, Inc. of requests for Work by other state agencies 
and cooperative program members by entering new project information in the ezIQC® website at 
http://www.eziqc.com. The Contractor shall not collect information from other entities on forms or 
web sites other than at http://www.eziqc.com. The Contractor may input new project information 
on the ezIQC® web site on behalf of an Owner. 
 
Other agencies or members of cooperative purchasing entities (“Entities”) may purchase 
construction services from the Contractor utilizing this Contract. If the Contract is utilized by 
Entities, the Contractor agrees to pay Gordian a 5.00% license fee (ezIQC® License Fee) due and 
payable within five (5) days from the date the Contractor receives payment from an Entity. License 
Fees not paid by the specified deadline shall bear an interest rate of 1½% per month until paid. 
The Adjustment Factors for ezIQC® Projects, as calculated on the bid form prior to Contract 
award, include the ezIQC® License Fee. The application of the ezIQC® Adjustment Factors is the 
Contractor’s sole compensation for the ezIQC® License Fee that is to be paid on all ezIQC® 
Projects. 
 
If the Contract is accessed and utilized by other state agencies or cooperative program members, 
the Contractor agrees to promptly pay the 1% State of Arizona Department of 
Administration Administrative Fee (Administrative Fee) consistent with the Special Terms 
and Conditions, Paragraph 4.1, Administrative Fee. The Gordian Group, Inc. will collect the 
Administrative Fee through its subsidiary EZIQC, LLC, and will remit it to the State of Arizona on 
behalf of the contractor. The Adjustment Factors for ezIQC® Projects, as calculated on the bid 
form prior to Contract award, include the Administrative Fee. The application of the ezIQC® 
Adjustment Factors is the Contractor’s sole compensation for the Administrative Fee that is to be 
paid on all ezIQC® Projects. 
 
The Fee shall be due and payable within fifteen (15) Days from the date that the Contractor 
receives payment from a state agency or cooperative program member ordering Work by 
accessing the Contract. The Contractor shall have no claim or right to any portion of the Fees. 
Failure to pay Fees in a timely manner shall be considered a material breach of this Contract and, 
at the State of Arizona’s sole discretion, may be deemed grounds for termination of this Contract. 
 
The Contractor acknowledges that The Gordian Group, Inc. will administer cooperative purchases 
through this Contract and that the Owner has no obligation to administer purchases by Entities. 
 
Gordian authorize the Contractor the use of Gordian’s names, logos, trademarks, and Gordian 
provided materials solely for the presentation and promotion of the availability and use of this 
Contract by Entities and potential Entities. The Contractor authorizes the Owner and Gordian the 
use of the Contractor's name, logos, trademarks, and Contractor provided materials in the 
presentation and promotion of the availability and use of this Contract by Entities and potential 
Entities. 
 
The Owner and Gordian shall not be liable or responsible for any obligation, including, but not

State of Arizona 
70 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
limited to, payments due under a Job Order, Purchase Order or similar purchasing document 
issued to the Contractor by the Entity (“Purchase Order”). 
 
The Contractor shall remit License Fees as follows: 
 
          Payments Made Payable to:    ezIQC, LLC 
 
          Mail Checks to:                        Attention: A/R Department 
 30 Patewood Drive, Suite 350 
 Greenville, SC 29615 
 
The Contractor shall, within two (2) business days of receipt of a Purchase Order from an Entity, 
provide notification to the Owner and Gordian of each Purchase Order by forwarding a copy of the 
Purchase Order via email to PO@ezIQC.com or via facsimile to (864) 233-9100. 
 
The Contractor shall, within two (2) business days of sending an invoice to an Entity, provide 
notification to the Owner and Gordian of each invoice by forwarding a copy of the invoice via email 
to Invoice@ezIQC.com or via facsimile to (864) 233-9100. 
 
The State of Arizona and The Gordian Group, Inc. may request records from the Contractor for all 
purchasing conducted with Owners through use of this Contract and payment of all Fees. If 
discrepancies exist between Owner activity and Fees paid, the State of Arizona or The Gordian 
Group, Inc. will provide written notification to the Contractor of discrepancies and allow the 
Contractor thirty (30) days from the date of notification to resolve the discrepancy. In the event the 
Contractor does not resolve the discrepancy to the satisfaction of the State of Arizona and The 
Gordian Group, Inc., notwithstanding any other remedies available to the State of Arizona by law 
or contract, the State of Arizona and The Gordian Group, Inc. reserve the right to engage a third 
party to conduct an independent audit of the Contractor's records, and Contractor shall reimburse 
the appropriate party for the cost and expense related to such audits.

State of Arizona 
71 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION  18 
MARKETING THE CONTRACT 
The Contractor authorizes the State of Arizona and The Gordian Group, Inc. the use of the Contractor’s 
name, trademarks, and Contractor provided materials in the presentation and promotion of the availability 
and use of the Contract by other entities. 
 
Prior to the use, advertisement or promotion of information for commercial benefit concerning this 
Contract or anything having to do with this Contract, Contractor shall comply with Uniform Terms and 
Conditions, Paragraph 3.6. Additionally, the Contractor must adhere to the following when preparing 
marketing materials, and in the use of proprietary materials, such as trademarks, service marks, etc.: 
 
1. All uses of the trademarks and service marks belonging to The Gordian Group, Inc. and EZIQC, 
LLC shall include the registered trademark symbol (®) at all times. 
 
2. Under no circumstances may copy or branding images of the State of Arizona, The Gordian Group, 
Inc. or EZIQC, LLC be altered in any way without the express written approval of the State of 
Arizona or The Gordian Group, Inc. as applicable. 
 
3. The state may request the Contractor attend in-state tradeshows or speaking engagements in 
conjunction with the State of Arizona Procurement Officer administering the contract to provide 
information for the State Job Order Contracting Program. Contractor shall be responsible for 
payment of all necessary Contractor expenses for any event attendance.

State of Arizona 
72 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
SECTION 19 
SOFTWARE LICENSING 
The Contractor will be provided access to a Job Order Contracting information management system 
licensed to the State of Arizona Department of Administration by The Gordian Group, Inc. (“Gordian”). 
The system includes PROGEN®, a Job Order Contracting management tool that expedites the ordering 
and execution of Work. The Contractor shall use PROGEN® to prepare and submit Price Proposals, 
subcontractor lists, and other requirements as determined by the State of Arizona Department of 
Administration. The system also contains an electronic version of the Construction Task Catalog® for the 
Contractor’s use in preparation of Price Proposals. Use, in whole or in part, of PROGEN®, the 
Construction Task Catalog®, or any other Proprietary Information provided under the JOC System 
License specified below for any purpose other than to order and execute Work under this Contract for the 
State of Arizona Department of Administration, other State of Arizona agencies, or Cooperative Program 
Members is strictly prohibited unless otherwise stated in writing by Gordian. The Contractor hereby 
agrees to abide by the terms of the following JOC System License: 
 
a. Gordian, through its agreement with the State of Arizona, grants to Contractor, and Contractor 
hereby accepts from Gordian for the term of this Contract, a non-exclusive right, privilege, and 
license to utilize Gordian’s Job Order Contracting System and other related proprietary 
materials (collectively referred to as “Proprietary Information”) to be used for the sole purpose 
of executing its responsibilities to the State of Arizona under this Contract. The Contractor 
hereby agrees that Gordian’s Proprietary Information shall include, but is not 
limited to, the PROGEN® software and support documentation, Construction Task Catalog®, 
Training Manuals and additional training materials, and other proprietary materials provided 
to the Contractor by the State of Arizona or Gordian. In the event that this Contract expires or 
terminates as provided herein, this Job Order Contracting System License shall terminate 
and the Contractor shall return all Proprietary Information in its possession to Gordian. 
 
b. The Contractor acknowledges that disclosure of Proprietary Information will result in 
irreparable harm to Gordian for which monetary damages would be an inadequate remedy and 
agrees that no such disclosure shall be made to anyone without first receiving the written 
consent of Gordian. The Contractor further acknowledges and agrees to respect the 
copyrights, registrations, trade secrets, and other proprietary rights of Gordian in the 
Proprietary Information during and after the term of this Contract and shall at all times maintain 
complete confidentiality with regard to the Proprietary Information provided to the Contractor, 
subject to federal, state, and local laws related to public records disclosure.

State of Arizona 
73 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
Appendix 1 
FORM OF JOB ORDER 
 
JOB ORDER 
Job Order Number: 
Date: 
To: 
 Contractor (“Contractor”) 
 
From: 
State of Arizona (“Owner”) 
 
Re: 
Job Order Project Number: 
Job Order Project Name: 
 
This Job Order is issued pursuant to the Contract# 
(Contract) Between the State 
and Contractor and hereby incorporates the terms of the Contract into this Job Order. This Job Order is the 
Notice to Proceed with the subject Job Order Project on the below Job Order Beginning Date. The terms of this 
Job Order are as follows: 
 
Part I - Work 
Full street or physical address of each location at which Work will be done under this Job Order: 
1. 
The Detailed Scope of Work, including a listing of all Drawings and Specifications and related 
documents shall be generated in PROGEN® and affixed hereto as Attachment 1. 
In accordance with Operating Manual, Section 5, the following Subsections apply: 
5.01, Planning, Progress and Scheduling; Communications; 
Meetings; and Reports 
Applicable Wage Determinations 
5.02, JOC Program Meetings 
5.03, Individual Project Meetings 
5.04, Meeting Minutes 
5.05, Reports 
Accepting Work: 
Owner Representative 
Design Professional 
Applicable Wage Determinations are 
affixed hereto as Attachment 5. 
 
Part II – Job Order Price 
1.  Job Order Price 
$ 
2. The Job Order Price shall be equal to the value of the approved Price Proposal. The Price Proposal, which 
includes a list of each Prepriced task from the Construction Task Catalog®, required quantities, the Adjustment 
Factor used, and all Non Prepriced tasks shall be generated in PROGEN® and affixed hereto as Attachment 2. 
Part III – Job Order Completion Time 
2. Schedule 
Construction Start Date: 
Substantial Completion Date: 
Final Completion Date: 
□ Progress Payments will be utilized (See Section 12) 
□ A single payment will be made 
A Construction Schedule shall be affixed hereto as Attachment 3, or, if not attached, 
Contractor shall submit a Construction Schedule on or before the date to the right. The 
Asbestos Statement is affixed hereto as Attachment 4.

State of Arizona 
74 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
JOB ORDER 
Job Order Number: 
Date: 
Part IV - Points of Contact 
Owner Representative 
Address 
Phone Number 
Name & Title 
Fax Number 
Owner 
Address 
Phone Number 
Name & Title 
Fax Number 
Contractor  Project Manager 
Address 
Phone Number 
Name & Title 
Fax Number 
Site Manager 
Address 
Phone Number 
Name & Title 
Fax Number 
Design Professional 
Company Name 
Name 
Address 
Phone Number 
Title 
Fax Number 
 
Part V - Other Requirements 
The following checked items are required. The 
requirements for each are in the Operating Manual 
   Submittals 
  Shop Drawings 
  Samples 
  Product Data 
Received by Customer from Contractor? 
 Insurance Certificate 
   Performance Bond 
  Payment Bond 
The following checked items are required.  The requirements for each are in the RFQ: 
   Arizona Department of Corrections Provisions 
  Federal Requirements for Construction Job Orders 
  Federal Clauses for AIP Construction Job Orders 
  Federal Clauses for AIP Equipment 
Part VI – Approvals 
Owner Representative 
Signature 
Date 
Owner 
Signature 
Date

State of Arizona 
75 
April 2017 
Operating Manual for Vertical Job Order Contracting 
 
Form of Job Order, Attachment 4 
ASBESTOS STATEMENT 
 
 
State of Arizona 
) 
) ss. 
County of 
) 
Project Name: 
 
Contract No.: 
Subcontractor: 
All materials used in the above referenced project are free of 
asbestos. 
 
 
 
 
 