Total Capital Cost:
$180,000.00
Department:
Parks and Recreation
Type:
Capital Improvement
Request Groups:
New
Timeline:
07/14/2025
to
08/29/2025
Request description:
Capital Costs
FY2026
Total
Planning
$0.00
Design
$0.00
Engineering
$0.00
Repairs/Improvements
$180,000.00
$180,000.00
Construction/Maintenance
$0.00
Furniture and Fixtures
$0.00
Other
$0.00
Total
$180,000.00
$180,000.00
Funding Source
FY2026
Total
111 - General
$180,000.00
$180,000.00
114 - Court
$0.00
121 - Court Enhancement
$0.00
128 - Towing
$0.00
131 - HURF
$0.00
141 - LTAF
$0.00
148 - CDBG
$0.00
156 - Capital Streets
$0.00
511 - Water
$0.00
516 - Ranchettes
$0.00
541 - Sewer
$0.00
591 - Sanitation
$0.00
149 - Special Projects
$0.00
Total
$180,000.00
$180,000.00
Account Codes (Capital Costs):
111-5-4561-617
$180,000.00
$180,000.00
Type of Project
Strategic Priority
Project Status
New
Parks and Recreation Department Admin Building Refurbishments
With the transition of the Public Works leadership staff into the newly completed Administration Building taking place in early 2025, this project includes refurbishments to 
the existing Public Works Administrative Building (originally constructed in 1987) necessary to create a viable Parks and Recreation Department with a functional and 
publicly accessible office. This includes the creation of an accessible entryway partition block wall, signage, flooring, paint and other updates to create a viable workspace 
for the Parks and Recreation Department. Staff offices at this location will include the existing Parks and Recreation Director, Recreation Coordinator-Special Events, and 
Parks Division Supervisor; as well as corresponding support staff workspace. 
Additional Information
Refurbishment
Superior Infrastructure