CIP Page

City of El Mirage — Regular Meeting (2025-06-17)

View PDF Item 13 Meeting page

Extracted text (via pymupdf) 1598 characters
Project Number:
EM24-SS02
Department:
Development Services
Total Capital Cost:
$82,000.00
Type:
Capital Improvement
Request Groups:
New
Timeline:
07/01/2024
to
12/31/2024
Request description:
Capital Costs
FY2025
Total
Planning
$0.00
Design
$0.00
Engineering
$0.00
Land/Right-of-way
$0.00
Construction/Maintenance
$82,000.00
$82,000.00
Other
$0.00
Total
$82,000.00
$82,000.00
Funding Source
FY2025
Total
111 - General
$0.00
114 - Court
$0.00
121 - Court Enhancement
$0.00
128 - Towing
$0.00
131 - HURF
$82,000.00
$82,000.00
141 - LTAF
$0.00
148 - CDBG
$0.00
149 - Special Projects
$0.00
156 - Capital Streets
$0.00
511 - Water
$0.00
516 - Ranchettes
$0.00
541 - Sewer
$0.00
591 - Sanitation
$0.00
Total
$82,000.00
$82,000.00
Benefit to Community
Type of Project
Strategic Priority
Division
Grant Funding
Bond Eligible
Project Status
A Street, Myer Lane & 119th Avenue Signing and Striping Improvements
This project would install a variety of signage and striping along A Street, Myer Lane and 119th Avenue in an attempt to mitigate accidents involving vehicles running into residential 
property walls at T intersections.  A Traffic Safety Study was completed by Greenlight Traffic Engineering in June 2023 in response to several recent accidents. This study provided 
recommendations to improve the safety in this area of the City. The request does not include curb, gutter and sidewalk on the northern shoulder of Myer Lane.
Additional Information
The improvements would be installed in an attempt to decrease accidents in a residential neighborhood.
Other
Safe Community
Engineering
No
No
New
49