CIP Page - Core Switch

City of El Mirage — Regular Meeting (2025-08-18)

View PDF Item 4 Meeting page

Extracted text (via pymupdf) 1403 characters
Total Capital Cost:
$50,000.00
Department:
Information Technology
Type:
Capital Equipment
Request Groups:
New
Request description:
Capital Costs
FY2026
Total
Equipment
$45,000.00
$45,000.00
Installation
$0.00
Other
$5,000.00
$5,000.00
Total
$50,000.00
$50,000.00
Funding Source
FY2026
Future
Total
111 - General
$50,000.00
$5,000.00
$55,000.00
114 - Court
$0.00
121 - Court Enhancement
$0.00
128 - Towing
$0.00
131 - HURF
$0.00
141 - LTAF
$0.00
148 - CDBG
$0.00
149 - Special Projects
$0.00
156 - Capital Streets
$0.00
511 - Water
$0.00
516 - Ranchettes
$0.00
541 - Sewer
$0.00
591 - Sanitation
$0.00
Total
$50,000.00
$5,000.00
$55,000.00
Account Codes (Capital Costs):
111-5-1511-237
$45,000.00
111-5-1511-261
$5,000.00
$50,000.00
New Purchase or Replacement
Strategic Priority
Grant Funding
Project Status
No
New
Core Network Switch Replacement - Police Department 
The original network core switch (group) at the Police Department was installed in 2013.  The switches (2) will lose security updates in October 2025.   The core switch 
handles all the network traffic at the Police Department and part of the phone system.  The new device will have more processing power than the existing unit and will 
provide fast switching for servers, applications, and high-speed connectivity to other sites that are connected via fiber optic cable. 
Additional Information
Replacement
Superior Infrastructure
66