CIP Page

City of El Mirage — Regular Meeting (2025-09-03)

View PDF Item 5 Meeting page

Extracted text (via pymupdf) 2483 characters
Project Number:
EM25-ST03
Department:
Development Services
Total Capital Cost:
$2,372,000.00
Type:
Capital Improvement
Request Groups:
New
Timeline:
09/01/2025
to
06/30/2027
Request description:
Capital Costs
FY2026
FY2027
FY2028
Total
Planning
$0.00
Design
$185,000.00
$54,000.00
$239,000.00
Engineering
$0.00
Land/Right-of-way
$0.00
Construction/Maintenance
$1,133,000.00
$1,000,000.00
$2,133,000.00
Other
$0.00
Total
$185,000.00
$1,187,000.00
$1,000,000.00
$2,372,000.00
Funding Source
FY2026
FY2027
FY2028
Total
111 - General
$0.00
114 - Court
$0.00
121 - Court Enhancement
$0.00
128 - Towing
$0.00
131 - HURF
$185,000.00
$1,187,000.00
$1,000,000.00
$2,372,000.00
141 - LTAF
$0.00
148 - CDBG
$0.00
149 - Special Projects
$0.00
156 - Capital Streets
$0.00
511 - Water
$0.00
516 - Ranchettes
$0.00
541 - Sewer
$0.00
591 - Sanitation
$0.00
Total
$185,000.00
$1,187,000.00
$1,000,000.00
$2,372,000.00
Account Codes (Capital Costs):
131-5-3581-658
$2,372,000.00
$2,372,000.00
Benefit to Community
Type of Project
Strategic Priority
Division
Grant Funding
Bond Eligible
Project Status
Cactus Road Half Street Improvements
The City owns both APNs 501-45-934 and 501-45-936 and is required to complete the ultimate roadway improvements along Cactus Road. This would require half street 
improvements along the frontage of these parcels including an additional 31 feet of asphalt, curb/gutter, 8 foot wide sidewalks, streetlights, landscaping and a HAWK signal 
located near 123rd Lane. Signing and striping would also be required between 127th Avenue and El Mirage Road.  Currently, the existing roadway reduces from 2 through 
lanes with a two-way left turn lane to a single lane, which causes potential conflicts while merging and for eastbound vehicles trying to turn left onto one of three side 
streets along this corridor. Widening the road would remove the need to merge and provide an additional lane for drivers to turn left in a safer manner.If this project is 
accepted, the Cactus Road Pedestrian Crossing Project (EM25-TS01, submitted for review) would not be required.
Additional Information
The widening of the south half of Cactus Road would complete the ultimate configuration of 2 lanes in each direction with a center two-
way left turn lane. It would also provide additional pedestrian-friendly amenities such as sidewalks and a HAWK signal which would 
allow for safer travel along and across this corridor. 
New Road
Superior Infrastructure
Engineering
No
No
New
54