Cost Breakdown

City of El Mirage — Work Session (2025-10-21)

View PDF Item 1 Meeting page

Extracted text (via ocr_local) 5642 characters
RedTree

September 8, 2025 CONSULTING

Mr. Bryce Christo, P.E. Michael Crow, RRO
Assistant City Engineer President

City of El Mirage

10000 North El Mirage Road 2942 North 24" Street
El Mirage, Arizona 85335 Suite 114

Phoenix, Arizona 85016
RE: Cost Estimate
El Mirage City Hall Ph 602.424.3468
10000 North El Mirage Road mcrow@redtreeco.com
El Mirage, Arizona 85335

Mr. Christo,

Enclosed is Red Tree Consulting’s preliminary cost estimate for the proposed Tenant Improvement
project at El Mirage City Hall. This estimate has been developed directly from the approved concept
boards (Alternative 4) and incorporates the scope of work required to deliver the additional office and
workspace capacity identified by City leadership.

Our approach accounts for selective demolition, new partition construction, structural extension at
Rooms 201A-D, MEP modifications, and finishes to match the existing facility, with adjustments for
phasing and the added complexity of working within an occupied building.

The intent is to provide City Council with a transparent and defensible cost baseline for comparison
alongside the contractor’s estimate and to support informed decision-making.

Executive Summary
The project consists of interior renovations to the first and second floors of City Hall to add 10 new
private offices and reconfigure existing spaces as outlined in Alternative 4. Key elements include:

e Selective demolition

e New wall construction

e Relocation of security doors

e Finishes to match existing

e MEP adjustments (HVAC, power, lighting, data)

e Structural cantilever extension

The total estimated construction cost is projected at approximately $798,900, inclusive of allowances for
working in an occupied facility.

Scope of Work

e Demolition of select partitions, HR lobby reconfiguration, relocation of security doors.

e Construction of 10 new private offices and reconfiguration of storage and work areas.

e Structural 2’ cantilever extension at Rooms 201A-201D.

e Finish work including flooring, ceilings, and painting to match existing.
MEP adjustments including HVAC diffuser relocation, lighting, power, and data extensions.
e Relocation of workstations and provision of 1 new workstation.

Page 1 of 4

City of El Mirage — City Hall TI
ROM Cost Estimate — By Area

Area 1

Division Description Subtotal
02 — Demo HR lobby & entry wall demo $12,000
06 — Partitions New Walls $42,000
08 — Doors/Frames New Doors $9,000

09 — Finishes Paint/ceilings/flooring patch $36,000
21/22/23 — MPE HVAC, lighting, power/data $36,600
Construction Subtotal $135,600
Design (8%) Allowance $10,848
FFE Allowance $15,000
Total Area 1 $161,448
Area 2

Division Description Subtotal
02 — Demo Wall removal, emblem relocation $9,000
06 — Partitions New Partitions $28,000
08 — Doors/Frames New Doors $6,000
09 — Finishes Paint/ceilings/floor patch $24,000
21/22/23 — MPE HVAC/power $23,400
Construction Subtotal $90,400
Design (8%) Allowance $7,232
FFE Allowance $10,000
Total Area 2 $107,632
Area 3

Division Description Subtotal
02 —- Demo Storage & corridor adjustments $6,000
06 — Partitions New Partitions $16,000
08 — Doors/Frames New Doors $3,000
09 — Finishes Paint/floor patch $18,000
21/22/23 — MPE HVAC/power $17,600
Construction Subtotal $60,600
Design (8%) Allowance $4,848
FFE Allowance $5,000
Total Area 3 $70,448

Page 2 of 4

Area 4

Division Description Subtotal
02 —Demo Wall removals in Finance $11,000
03 — Structural Minor tie-ins $7,000
06 — Partitions New Partitions $31,000
08 — Doors/Frames New Doors $6,000
09 — Finishes Paint/floor patch $30,000
21/22/23 — MPE HVAC/lighting/data $31,100
Construction Subtotal $116,100
Design (8%) Allowance $9,288
FFE Allowance $10,000
Total Area 4 $135,388
Area 5

Division Description Subtotal
02 —Demo IT lobby demo $10,000
03 — Structural 2’ cantilever (201A—D) $60,000
06 — Partitions New Partitions $34,000
08 — Doors/Frames New Doors $6,000
09 — Finishes Paint/ceilings/floor $30,000
21/22/23 — MPE HVAC/power/data $38,700
Construction Subtotal $178,700
Design (8%) Allowance $14,296
FFE Allowance $10,000
Total Area 5 $202,996

Note: Ceilings are exposed structure; estimate assumes lighting/data drops and limited patch work only.

Area 6

Division

02 — Demo

06 — Partitions

08 — Doors/Frames
09 — Finishes
21/22/23 —- MPE
Construction Subtotal
Design (8%)

FFE

Total Area 6

Description

Storage & corridor reconfig

New Partitions
New Doors
Paint/floor patch
HVAC/power

Allowance
Allowance

Subtotal
$8,000
$29,000
$6,000
$26,000
$29,600
$98,600
$7,888
$10,000
$116,488

Page 3 of 4

Summary

¢ Construction (all areas): $680,000
© Design (8% allowance, per 1GPA): $54,400
© FFE (all areas): $60,000
© Environmental Allowance (asbestos survey): $4,500
© Total ROM (all areas): $798,900
Notes

e Room 114 and Area 5: exposed ceilings; scope assumes device relocations and touch-ups only.
e Room 107: ceiling may require modification; included in MEP allowance.
e Asbestos survey included as allowance only; 2016 construction = low risk.

ROM Disclaimer

This estimate is provided as a Rough Order of Magnitude (ROM) for planning purposes only. It is not a
contractor's detailed estimate and does not include bid-level quantities, subcontractor quotes, or unit
pricing. Final pricing shall be developed by the GC during preconstruction.

Prior to commencement of any work a comprehensive asbestos survey, including a written report, should
be available and located on the property. Please do not hesitate to contact us at your convenience with
any questions or concerns you may have.

Thank you,

— Heh

Michael L. Crow, RRO
President

Page 4 of 4