Closeout Funding Notice

City of El Mirage — Regular Meeting (2025-11-04)

View PDF Item 5 Meeting page

Extracted text (via pymupdf) 8705 characters
October 6, 2025 
 
TO:  
Members of the MAG Management Committee  
 
FROM:  
Patrick Stone, Deputy Transportation Director - Programming 
 
SUBJECT: 
FEDERAL FISCAL YEAR 2026 CLOSEOUT – REDISTRIBUTION OF AVAILABLE  
 
FEDERAL HIGHWAY ADMINISTRATION FUNDING 
 
Federal Highway Administration (FHWA) funding allocated to the MAG region is primarily made up of Congestion 
Mitigation and Air Quality Improvement Program, Surface Transportation Block Grant Program, and 
Transportation Alternatives funds. Consistent with policy set forth in the Regional Strategic Transportation 
Infrastructure Investment Plan, these dollars are programmed through the three life cycle programs and the 
Regional Competitive Programs - Call for Projects process. 
Annually, MAG reviews projected FHWA funding and compares this amount against programmed projects for 
the current federal fiscal year to determine how much, if any, funding is unprogrammed. Federal funding is 
allocated to the MAG region on a use or lose basis and unused amounts need to be reprogrammed on other 
projects prior to the end of the federal fiscal year. This occurs through the annual closeout process. MAG is now 
accepting applications for Federal Fiscal Year (FFY) 2026 closeout funding. 
For FFY 2026, the MAG region is currently estimated to have $25.0 million available for closeout based on 
programmed amounts, project deferrals, potential cost savings, and projects that will be closed out. Only projects 
selected through the Regional Competitive Programs-Call for Projects process are eligible for closeout. Requests 
are now being accepted to: 
• 
Advance projects currently programmed in FFY 2027 to FFY 2026 
• 
Provide additional federal funding for current year (FFY 2026) projects 
• 
Fund design work phase requests for FFY 2026 
• 
Fund right of way work phase requests for FFY 2026 
• 
Fund PM-10 Certified Street Sweeper applications that were not selected as part of the FFY 2026 call 
for projects 
Projects requiring the execution of, or an amendment to, an Intergovernmental Agreement (IGA) between the 
member agency and the Arizona Department of Transportation must be initiated with ADOT by February 13, 
2026, and the IGA must be fully executed by May 15, 2026, to allow sufficient time for ADOT processing. 
Closeout requests to advance FFY 2027 projects to FFY 2026 are to be submitted on member agency letterhead 
and signed by the Manager/Designated Representative stating that project and agency resources are available 
to advance the project.

Closeout requests for additional funding or to fund design or right of way work phases for projects programmed 
in FFY 2026 should be submitted to MAG on the TIP Project Change form that is available on the MAG website. 
Increases to existing FFY 2026 construction projects should also be accompanied by an updated cost estimate 
prepared by the agency engineer or ADOT project manager (the original application contains a cost estimate 
form that may be used).  
Closeout requests to fund FFY 2026 Street Sweepers that were not awarded during the call for projects are to be 
submitted on member agency letterhead and signed by the Manager/Designated Representative stating that 
project and agency resources are available. 
A fact sheet is attached to this notification outlining specific MAG guidelines and procedures related to closeout 
and a schedule of key dates. 
Please submit closeout requests via email to Patrick Stone, pstone@azmag.gov and cc Wendy Miller, 
wmiller@azmag.gov on or before Thursday, November 13, 2025, at 12:00 p.m., via email. Late requests will 
not be accepted. 
MAG staff is available to help with information and questions regarding requirements.  Please contact Patrick 
Stone at pstone@azmag.gov or Wendy Miller, wmiller@azmag.gov via email, or by phone at (602) 254-6300. 
 
cc:  
ADOT, Local Public Agency Section          
ADOT Project Management Group 
 
FHWA Arizona Division Planners 
MAG Intergovernmental Representatives 
 
MAG Active Transportation Committee 
MAG Intelligent Transportation Systems Committee 
 
MAG Street Committee 
MAG Transportation Review Committee 
MAG Transportation Safety Committee

October 6, 2025 
 
Federal Fiscal Year 2026 Closeout Request – Fact Sheet 
The Regional Council approved the Regional Programming Guidelines on June 25, 2025.  Requirements for 
Closeout as noted are found in Section 480 Redistribution of Unused Funding (i.e., Closeout) are as follows:  
1. Funding estimate. In August of each year, MAG staff will release an estimate of funding 
available for redistribution for the current federal fiscal year. Typically, this estimate is calculated 
as the difference between the anticipated sum of regional competitive funding from 
appropriations, closed out projects and project deferrals, and the sum of projects anticipated to 
authorize. This estimate will be updated if warranted by new information. 
2. Cost estimates for redistribution. Cost estimates to be used in the redistribution of regional 
competitive funding to the current year and advancing projects must meet the following criteria: 
3. Advancing projects. MAG member agencies may at any time request to advance projects to 
take advantage of the anticipated redistribution of funding. At a minimum, projects that are 
requested to be advanced must meet all requirements for inclusion in the current year as 
identified in Section 610. Actions to approve project advancements will occur at the same time 
as the decision to redistribute regional competitive funding. 
4. Redistribution meeting. Early in the calendar year, TRC will consider priorities for the 
redistribution of regional competitive funding. As a default, advancing projects will be given 
first priority, increased funding for currently programmed projects will have second priority and 
loans to projects or programs will have third priority. 
5. Review and approvals. Following the redistribution meeting, the action of the TRC will be 
reviewed, revised and, as appropriate, approved by the MAG Management Committee and 
Regional Council. 
a. TIP cost estimates. Only costs as reported in the TIP or in pending TIP 
amendments will be used for the redistribution of regional funds. MAG 
members may update cost estimates for projects whenever MAG 
processes changes to the TIP. Member agencies are strongly encouraged 
to update the TIP for changes in project costs as they occur in the 
development process and when MAG distributes project workbooks. 
b. Engineering cost estimates required. Up to date engineering cost 
estimates are required for all projects that are to receive redistributed 
regional competitive funds. These estimates must be provided by either 
the sponsoring agency or ADOT project manager. The costs listed must 
be sufficient to use the redistributed regional competitive funding.

6. Notice of redistribution. Following Regional Council approval MAG staff will provide notice 
to MAG member agencies that will receive redistributed funding. This notice will be 
distributed to project sponsor representatives as identified in Section 440. 
 
Schedule 
 
 
 
Category 
Date 
Committee / Group 
Action 
Closeout Request 
Notice 
Mon, Oct 6, 2025 
Management 
Committee 
Send out memo to members of Management 
Committee outlining the FFY 2026 Closeout 
process. 
Mon, Oct 6, 2025 
Transportation Review, 
Safety, ITS, Street, 
Active Committees 
Send out memo to members of the 
committees outlining the FFY 2026 Closeout 
process. 
Mon, Oct 6, 2025 
All Member Agencies 
Send out memo to all member agencies 
outlining the FFY 2026 Closeout process. 
Mon, Oct 6, 2025 
ADOT 
Send out memo to ADOT LPA and PMG 
groups outlining the FFY 2026 Closeout 
process. 
Mon, Oct 6, 2025 
FHWA 
Send out memo to FHWA staff outlining the 
FFY 2026 Closeout process. 
Application Period 
Mon, Oct 6, 2025 - 
Thu, Nov 13, 2025 
All Member Agencies 
MAG Staff will be available to provide answers 
to questions regarding the closeout process. 
Thu, Nov 13, 2025 
All Member Agencies 
Requests Due at 12:00 pm (late requests 
are not accepted) 
 
Request Review 
Mon, Nov 17, 2025 
MAG Staff 
Review requests to confirm project eligibility 
and completeness of request. 
 
Committee Review 
Thu, Dec 11, 2025 
Transportation Review 
Committee 
Review and recommendation for closeout 
requests. 
 
Wed, Jan 14, 2026* 
Management 
Committee 
Review and recommendation for closeout 
requests. 
 
Wed, Jan 21, 2026* 
Transportation Policy 
Committee 
Review and recommendation for closeout 
requests. 
 
Wed, Jan 28, 2026* 
Regional Council 
Review and approve closeout requests. 
 
* Estimated meeting date, subject to change