G:\Infrastructure\W-WW\02-Proposals & SOQs\2021\PW21-08-02_El Mirage Expansion\6.0 Proposal or SOQ Submittal\El Mirage Expansion Design 
Scope Prop R1 v2-0.docx  
Wood Environment & Infrastructure Solutions, Inc.
4600 East Washington Street, Suite 600
Phoenix, Arizona 85034
T: (602) 733-6000
F: (602) 733-6100
www.woodplc.com
 
 
 
October 6, 2021 
Wood Proposal No.: PW21-08-02 R1 
 
 
City of El Mirage 
10355 N. 121st Avenue 
El Mirage, AZ 85335 
 
RE: 
El Mirage WRF Expansion Project 
 
Lump Sum Fee Proposal for Design R1 
 
Dear Mr. Ketchmark: 
Attached is our revised scope of services and fee proposal for providing engineering design services for 
the City of El Mirage expansion project to expand the capacity of the El Mirage Water Reclamation Facility 
to 3.15 million gallons per day (mgd). The project includes a new equalization basin, Sequencing Batch 
Reactor (SBR) System, and surge tank, dewatering centrifuge along with other process equipment and 
systems to meet the new flow requirements, and piping, valves, odor control, a new Blower Building with 
blower equipment, and a building to enclose the influent channels and coarse screen with added odor 
control. 
The scope of services in this proposal includes civil, mechanical, electrical, HVAC, architectural, and 
structural design work; geotechnical evaluation, survey, potholing, and preparation and submission of the 
County ATC and City permits. The APP and AZPDES permits have 3.6 mgd ratings and do not need to be 
modified. The fee for construction engineering services, including inspections, record drawings and 
County AOC permit preparation will be provided within a subsequent services contract.  
Please contact Ms. Kagie-Hay at (602) 733-6149, (480) 241-6622, or at andrea.kagie@woodplc.com with 
any comments or questions.  
We look forward to the opportunity to working with the City of El Mirage on this project. 
Respectfully submitted, 
Wood Environment & Infrastructure Solutions, Inc. 
Reviewed by: 
 
 
 
 
Andrea L Kagie-Hay, PE 
Tim LeClair, PE 
Project Manager 
Sr. Project Manager

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page i 
TABLE OF CONTENTS 
Page 
1.0 
Introduction ........................................................................................................................................................................... 1 
1.1 
Background ............................................................................................................................................................................ 1 
1.2 
Scope of Design Services / Project Understanding ................................................................................................ 1 
2.0 
Project Task Descriptions .................................................................................................................................................. 4 
2.1 
Task 1 – Project Management ........................................................................................................................................ 4 
Task 1100 – Project Management and Coordination ................................................................................... 4 
Task 1200 – Project Meetings ................................................................................................................................. 4 
2.2 
Task 2 – Conceptual Design / Design Concept Report......................................................................................... 4 
Task 2100 – Background Investigations ............................................................................................................. 5 
Task 2200 – Conceptual Design ............................................................................................................................ 5 
Task 2300 –Design Concept Report ..................................................................................................................... 6 
Task 2400 – Preliminary Opinion of Probable Construction Costs .......................................................... 6 
2.3 
Task 3 – 60% Design Services ......................................................................................................................................... 6 
Task 3100 – 60% Drawings ...................................................................................................................................... 6 
Task 3200 – Technical Specifications Update ................................................................................................... 6 
Task 3300 – Opinion of Probable Construction Costs Update .................................................................. 7 
2.4 
Task 4 – 90% Design Services ......................................................................................................................................... 7 
Task 4100 – Technical Specifications Update ................................................................................................... 7 
Task 4200 – Design Report Update ...................................................................................................................... 7 
Task 4300 – 90% Drawings ...................................................................................................................................... 7 
Task 4400 – Opinion of Probable Construction Costs Update .................................................................. 7 
2.5 
Task 5 – 100% Design Services ....................................................................................................................................... 7 
Task 5100 – 100% Design Set ................................................................................................................................. 7 
2.6 
Task 6 – Permit Assistance ............................................................................................................................................... 8 
Task 6100 – MCESD ATC .......................................................................................................................................... 8 
Task 6200 – City FBLSD ............................................................................................................................................. 8 
3.0 
Schedule .................................................................................................................................................................................. 8 
4.0 
Fee Proposal .......................................................................................................................................................................... 8

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page 1 
1.0 
Introduction 
The City of El Mirage (City) owns and operates the El Mirage Wastewater Reclamation Facility (WRF); a 
tertiary wastewater treatment facility designed with a capacity of 2.5 million gallons per day (mgd).  The 
facility operates using the Sequencing Batch Reactor (SBR) technology that currently has four (4) SBR 
basins to meet capacity. The WRF influent flow is nearing 80% of its design capacity and the service area, 
though limited in size, has the potential to increase flows to the plant at build out by approximately 
500,000 gallons per day. The City has requested Wood to provide design services for an expansion of the 
treatment capacity to 3.15 mgd. 
Expansion of the facility will generally consist of additional equalization basin capacity, a new SBR basin, 
expanded surge basin capacity, and additional process equipment and systems required to meet the 
increased wastewater treatment capacity. The additional items include fine screen, pumps, blowers, 
tertiary filter, odor control equipment, electrical systems, and controls. A new sludge dewatering 
centrifuge and a back-up chlorination system are included in the scope of services 
The project will require site investigations including survey, geotechnical investigations, and potholing. 
Support disciplines include electrical and structural engineering. Heating, ventilation and air conditioning 
(HVAC) and architectural services are included for the new Blower Building, and the new Influent Channel 
building over the influent channels and screen. Both the Aquifer Protection Permit (APP) and the AZPDES 
permit have ratings of 3.6 mgd and do not need to be modified. Typical approval-to-construct (ATC) and 
City permits will be required. The preparation of pre-construction permits is included with our services. 
Details of the design services to expand the facility to meet the future needs of the City are provided 
below. 
1.1 
Background 
Facility staff operates the 2.5-mgd SBR system, which produces Class B+ effluent. The facility is nearing 
80% of its design capacity, which triggers the regulatory requirement to begin planning and design for 
additional capacity. To meet future build-out requirements, the City is requesting a design to expand the 
plant to keep up with the increasing demands expected from new residential developments that are 
planned within the service area. This project will expand the treatment capacity of the plant and process 
equipment essential to operation of the new processes and systems. 
1.2 
Scope of Design Services / Project Understanding 
The El Mirage WRF expansion project includes not only the installation of new treatment basins, but 
additional process upgrades to ensure unit processes meet the needs of the expanded capacity of the 
plant, and to provide operational flexibility. The following is a summary of the main components that will 
be included in the design documents to construct the new facilities: 
Plant Expansion Features 
• 
Additional Fine Screen Capacity 
o 
Location of screening equipment will be considered with regard to space and operational 
aspects of the expanded Equalization (EQ) Basin

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page 2 
• 
New Flow Equalization (EQ) Basin 
o 
Proposed location for the second EQ Basin is to be south/southeast of the belt filter press 
operations. 
o 
EQ Basin is be designed to allow either basin to be taken out of service for maintenance 
and both basins are to be hydraulically and operationally connected 
o 
Provision for two SBR Feed pumps with VFDs to be designed into new basin; design 
approach is to allow for relocating existing feed pumps as necessary to either basin, as 
there is sufficient existing pumping capacity 
• 
New SBR Basin 
o 
Proposed location is to be directly west of SBR 4 
o 
For consistency and operational flexibility, SBR Basin will match size of the existing SBRs 
• 
SBR Blowers 
o 
Blowers to provide air supply and redundancy for new SBR 
o 
Will match existing Aerzen Hybrid blower units 
• 
Blower Building 
o 
New building to house new SBR blower systems and electrical equipment 
o 
Access to new blower will be through passage and overhead doors  
o 
HVAC will be provided to cool both the blower space and electrical equipment room. 
• 
Additional Surge Basin Volume 
o 
Proposed location is directly south of new SBR Basin; must not interfere with existing 
influent sewer 
o 
Surge basins are to be hydraulically and operationally connected 
• 
Tertiary Filtration 
o 
One new filter to provide sufficient redundancy located to the west of existing units 
• 
Disinfection 
o 
Back-up tablet chlorinator to be upgraded for improved periodic operation with 
expanded plant capacity  
• 
Odor Control 
o 
New EQ and SBR Basins will require odor control for air released to the atmosphere 
o 
Design to include consideration of revising existing odor control ducts to reduce number 
of additional odor control system(s) 
• 
Centrifuge 
o 
Larger sludge dewatering centrifuge will replace the existing unit to match the higher 
plant capacity  
o 
Existing centrifuge to be relocated within the Solids Handling Building to provide back-up 
service 
o 
New overhead door to be located to allow forklift access to the solids collection bin 
• 
Influent Channel Building and Odor Control 
o 
A new pre-engineered metal building will be constructed over the influent channels and 
screening system next to the existing pump station and building 
o 
Ionization-type odor control will be installed to treat the air within the building and the 
influent pump station wet well 
o 
See notes* below regarding the building’s deferred submittal design work 
• 
Support disciplines include: 
o 
Electrical – provide power for new equipment in new Motor Control Center (MCC) room 
o 
Structural – for watertight treatment basins and design for buildings and overhead door 
o 
Architectural – to match the existing building design and meet architectural requirements

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page 3 
o 
HVAC – for heating/cooling and ventilation requirements in new buildings and assistance 
with odor control ducting 
Electrical Assumptions: Based on existing drawings, this proposal assumes the existing SES and generators 
are both sized to provide supply power for the new equipment. The design will provide a new breaker to 
power the new MCC. The PLC cabinet design for controls is to be provided by the SBR manufacturer; PLC 
and SCADA programming to be performed by others and are not provided in this scope of services. The 
proposal also assumes the existing grounding system is sufficient to provide the required additional 
equipment protection. 
Key design requirements include: 
• 
New EQ Basin to be hydraulically connected to the existing EQ Basin. The design will need to 
allow flow through the headworks and into either basin. Neither will require a direct connection 
to or from the influent pump station. 
• 
New Surge Basin to be hydraulically and operationally connected to the existing Surge Basin. 
• 
Relocation of the existing manhole and sewer piping located towards the north side of the facility, 
near the west side of SBR 3, is to be avoided in the plant expansion design if possible. 
*Deferred Submittal Notes: 
The pre-engineered metal building will be designed as a deferred submittal. Wood will provide the 
preliminary structural foundation design and required specifications for the contractor to procure a pre-
engineered building meeting the design criteria provided. Design elements for the pre-engineering 
building have the following inclusions and exclusions: 
• 
Includes pre-engineered metal building (PEMB) specifications 
• 
Includes related specifications, e.g. Doors and Openings 
• 
Includes schematic plans, as required, to develop building specifications 
• 
Includes preliminary structural foundation design 
o 
Design to be confirmed/updated during construction to coordinate with the building 
manufacturer’s approved shop drawings 
• 
Includes ventilation design in conjunction with the ionization odor control 
• 
Includes electrical supply to the building 
• 
Excludes interior building electrical design, such as outlet receptacles and lighting 
• 
Excludes redesign of building or foundation after PEMB manufacturer has completed their design 
(may be added as an additional service with the construction services) 
• 
Excludes building design drawings (building will be shown essentially as a box) 
o 
Manufacturer is to provide sealed engineering design of building during construction 
• 
Excludes renderings of building and/or building elevations during design 
If during permitting additional design work is required to obtain initial permits to start the project 
construction, Wood can add these design services by change order to the contract. 
The following scope of service tasks are required for execution of the project.

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page 4 
2.0 
Project Task Descriptions 
The scope of services and fee proposal are based on project scope discussions with the City on August 18 
and 30, 2021. Additional scope items were provided in an email from the City dated September 21, 2021. 
The proposed scope of services is broken down into tasks and sub-tasks, as follows. 
2.1 
Task 1 – Project Management  
Wood will provide management for the Project Team under Task 1, which will include coordination, 
reporting, directing, administrative services for engineering services, and organizing and facilitating 
design-phase meetings. The specific tasks are broken down as follows. 
Task 1100 – Project Management and Coordination 
Project budget, schedule and progress will be monitored and tracked for deadline compliance, and the 
project budget does not exceed the approved contract value. Wood’s Project Manager will communicate 
with the City’s Project Representative via onsite meetings, email and phone calls throughout the project to 
report project progress and address comments and questions from the City. Wood will prepare progress 
reports and prepare consolidated invoices for submittal to the City on a monthly basis. 
Task 1200 – Project Meetings 
Organizing, attending, and conducting up to ten (10) design meetings with the Project Team are provided 
in the scope of services. The Project Team will consist of Wood, City staff and subconsultants, as required. 
Wood will provide a meeting agenda prior to each meeting and meeting notes that summarize any 
decisions and actions items resulting from each meeting. 
Project meetings will include a project kick-off meeting, a design concept review meeting, and up to three 
(3) design review meetings coordinated with the design submittal milestones. Design review meetings are 
scheduled two weeks after each design submittal to allow the City time to review the submittal. Although 
not necessary, Wood would prefer City review comments prior to the meeting to be able discuss specific 
comments in detail at the meeting. Wood will utilize the design review comments and discussion at these 
meetings to continue forward with the next phase of the design. 
2.2 
Task 2 – Conceptual Design / Design Concept Report 
The intent of the Detailed Design Services of the project is to prepare a complete set of Design Drawings, 
Technical Specifications, opinion of probable construction costs, and development of bid documents. The 
preparation of bid documents is included as an allowance and the scope will be developed once the 
construction approach is determined as this will determine the level of effort required. Each task and sub-
task will build upon the previous task to develop the final product for construction. 
Work product developed for the conceptual design includes the Design Concept Report (DCR) of the 
plant expansion and related improvements. The DCR will be submitted to Maricopa County Environmental 
Services Department (MCESD) as part of the Approval-to-Construct (ATC) application. In general, the task 
includes land survey, potholing, geotechnical investigations to determine existing site conditions, 
development of existing site drawings, and the DCR. A preliminary opinion of probable construction costs 
(OPCC) will be prepared for construction budget planning. The specific sub-tasks under Task 2 include:

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page 5 
Task 2100 – Background Investigations 
Wood will review and utilize the background information relevant for the project design. This task consists 
of gathering, organizing, and reviewing available information, including record drawings, equipment 
nameplate data, permits, and plant operational and performance data. Wood will work with plant 
personnel to identify project constraints. 
Land Survey 
The land survey will identify the surface contour elevations and locate coordinates of the existing 
surface features, soil boring locations and underground features that are identified by review of 
existing records and the potholing activity. Site facility locations will be in accordance with the 
Arizona Plane Coordinate (1983) System Datum and North American Vertical Datum of 1988 
(NAVD 88). 
Geotechnical Investigations 
Geotechnical investigations will include soil borings to determine soil characteristics and 
structural load capacity of the underlying soils of the new EQ, SBR, and Surge Basin. The proposal 
includes up to 7 borings, each up to 35 feet deep. Data from a previous boring for Filter #4 will be 
used along with the other borings for the new Influent Channel Building foundation 
consideration. Wood geotechnical engineers and/or geologists will supervise the field 
investigation to be performed by a sub-contracted drill rig and drill crews. Laboratory testing will 
be performed to provide data for the engineering analysis. A geotechnical report will be prepared 
to document the localized site conditions for design and construction. 
Potholing 
It is anticipated that existing underground utilities are not located on record drawings, or not 
located in accordance with the available documentation. The proposal includes a potholing 
allowance to uncover the location and depths of buried utilities. A detailed proposal will be 
developed with costs that will be submitted to the City for approval before proceeding with the 
work. 
Task 2200 – Conceptual Design 
Wood will develop a conceptual design of the facility for discussions with the City. The conceptual design 
will present the basic features and arrangements of equipment and systems for the expanded plant. The 
basic layouts include the EQ Basin, SBR Basin, expanded Surge Basin, Blower Building, new centrifuge, and 
existing centrifuge relocation. The presentation of the conceptual design will be directed to focus on key 
design approaches, including screen installation, EQ basin and Surge basin hydraulic connections, and 
centrifuge layout/relocation. The discussions will focus on making decisions on key equipment and 
layouts, as well as making preliminary selections on major equipment. 
In the conceptual design task, Wood will develop a Table of Contents (TOC) for the Technical 
Specifications to be developed for the project. Outlines of the major equipment design criteria will be 
included.

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page 6 
As part of this task, Wood will convert the relevant existing plant drawings in pdf format to digital 
AutoCAD drawings for purposes of designing the new facilities. Wood to provide as-built electrical 
drawings of the existing SES and MCCs based on site visits as part of this effort. 
Task 2300 –Design Concept Report 
Wood will develop a Design Concept Report (DCR) for the facility expansion. The design report is 
necessary to obtain an ATC through MCESD. The DCR will define the project elements and include the 
number and size of equipment and systems, criteria of design, and other information to demonstrate 
compliance with wastewater treatment standards and guidelines, and with the existing APP permit and 
MCESD requirements, as well. 
Task 2400 – Preliminary Opinion of Probable Construction Costs 
Wood will prepare an opinion of probable construction costs (OPCC) based on the DCR, conceptual 
design facilities, equipment, and systems. The costs estimate will be in alignment with the level of project 
detail and will be in accordance with an American Association of Cost Engineers (AACE) Estimate Class 3.   
2.3 
Task 3 – 60% Design Services 
Task 3 consists of continuing the development of the conceptual design and preparing detailed design 
drawings at a 60% level. The design will incorporate the comments from the City at the conceptual design 
review meeting. A draft of the design specifications for major equipment, and development of an updated 
opinion of probable construction costs will be included in the 60% design package. 
Task 3100 – 60% Drawings 
The conceptual design will be advanced by incorporating City comments, to develop the 60% drawings 
providing general arrangements of each equipment space, sections and details for the civil/mechanical 
drawing set, and development of structural, electrical, architectural, and HVAC drawings. Process 
schematics and preliminary hydraulic diagrams will show the interrelation of the equipment and systems. 
Equipment Selection and Layout 
Wood will work with the City to select equipment and develop location and spatial arrangements 
in plan views of the major equipment and systems. The number of units/systems will be included 
on the drawings. Sections and Details will be developed in this set. 
Manufacturer Coordination 
Wood will contact equipment manufacturers or manufacturer’s representatives to obtain the 
latest information and data for the proposed equipment and to determine system spatial 
requirements and costs. 
Task 3200 – Technical Specifications Update 
Wood will add detail to the design criteria for the major equipment outlined in the conceptual design 
phase. Specifications will be reviewed with the selected (or equal) equipment manufacturers and/or 
manufacturer’s representatives.

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page 7 
Task 3300 – Opinion of Probable Construction Costs Update 
The quantity takeoffs and equipment pricing will be reviewed, and the opinion of probable construction 
costs will be modified based on updated cost and quantities information developed in the 60% design. 
2.4 
Task 4 – 90% Design Services 
Wood will continue to develop the design documents up through a 90% level, including the full set of 
technical specifications and incorporating comments from the City at the 60% design review meeting. The 
90% design documents can be shared with contractor(s) for additional design critique, if the City should 
chose to follow a Construction-Manager-at-Risk (CMAR) project delivery. These design documents will be 
ready for submittal for permit application pending any final comments from the City and contractor(s), if 
any, at the 90% design review meeting. This submittal will include an updated design report, technical 
specifications, and opinion of probable construction costs. 
Task 4100 – Technical Specifications Update 
A complete set of technical specifications will be available with the 90% design documents; this excludes 
the front-end specifications. The Bid Preparation Allowance can be used to prepare front-end 
specifications and other bid documents in coordination with the City, as needed. The specific scope will be 
developed with the City once the construction approach is determined. 
Task 4200 – Design Report Update 
The Design Report will be updated to reflect modifications necessitated by the design process. The Design 
Report will be submitted with the MCESD ATC permit application. 
Task 4300 – 90% Drawings 
Drawings of the 60% design phase will be advanced to the 90% design, including the incorporation of 
comments from the 60% design review. The drawings will describe and detail the project for construction 
by a competent contractor. 
Task 4400 – Opinion of Probable Construction Costs Update 
The quantity takeoffs and equipment pricing will be reviewed, and the opinion of probable construction 
costs will be refined based upon updated cost and quantities information. The cost estimate will be in 
accordance with an American Association of Cost Engineers (AACE) Estimate Class 2.    
2.5 
Task 5 – 100% Design Services 
The 100%, or final, design documents will incorporate comments provided by the City based on the 90% 
submittal review and will serve as the set of construction documents. 
Task 5100 – 100% Design Set 
The final design documents will be sealed and signed by an Arizona-registered Professional Engineer for 
each discipline. The sealed design documents will be submitted to MCESD and the City. Comments 
received from MCESD and City permit applications will be addressed and a final conformed set of design

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page 8 
documents will be issued. The final design documents will include drawings, specifications, design report, 
and opinion of probable construction costs. 
2.6 
Task 6 – Permit Assistance 
Permit assistance includes completing and submitting applications to MCESD and the City Fire, Building, 
and Life Safety Department (FBLSD). Wood will prepare and submit the MCESD Approval-to-Construct 
(ATC) application and the City of El Mirage permit applications. This proposal does not include any fees 
associated with the permits, which are to be paid by the City. 
Task 6100 – MCESD ATC 
Under this task, Wood will fill out the necessary paperwork and compile the required information needed 
to be submitted with the Approval to Construct (ATC) permit application. After review with the City wood 
will submit the application to MCEESD. Wood will address comments received from the MCESD and will 
provide any updates to the design package required to obtain the permit. 
Task 6200 – City FBLSD 
Wood will complete and submit the applications for construction of the expanded plant facilities to the 
City FBLSD, as required for permits, approvals, and Engineering review. Wood will address comments 
received from the City and will provide any updates to the design package required to receive required 
permits and approvals. 
3.0 
Schedule 
Based on the scope of services detailed above, Wood anticipates the following milestone schedule for the 
design portion of the project: 
Deliverable / Meeting 
Weekly Estimate 
Example Dates 
NTP 
NTP 
10-20-2021 
Kick-off Meeting 
NTP + 1 week 
10-27-2021 
Conceptual Design Review Meeting 
NTP + 12 weeks 
01-12-2022 
60% Design Submittal 
NTP + 20 weeks   
03-09-2022 
60% Design Review Meeting 
NTP + 22 weeks 
03-23-2022 
90% Design Submittal 
NTP + 32 weeks 
06-01-2022 
90% Design Review Meeting 
NTP + 34 weeks 
06-15-2022 
100% Design Documents 
NTP + 36 weeks 
06-29-2022 
MCESD / City FBLSD Submittals 
NTP + 36 weeks 
06-29-2022 
 
4.0 
Fee Proposal 
Based on the scope and schedule outlined above, Wood estimates approximately 6,518 man-hours for the 
anticipated tasks, with a $20,000 potholing allowance, a $15,000 bid document preparation allowance, 
and $77,417 for other Direct Expenses that include architectural, survey, geotechnical drilling sub-
contractors, and geotechnical testing costs for a total lump sum contract amount of $1,028,140.

El Mirage WRF Expansion Project 
Wood Proposal No.: PW21-08-02 
October 6, 2021 
 
Page 9 
A Fee Proposal table, showing the estimated hours by task, is presented in Attachment A. The fee table is 
not to be considered as the basis for billing but is provided for informational purposes. 
Hours are assigned in the Fee Proposal table for the following team members: 
 QA/QC – Quality Assurance/Quality Control Engineer 
 PM – Project Manager 
 SME – Subject Matter Expert 
 PE – Project Engineer 
 EIT – Engineer-in-Training 
 SrEE – Senior Electrical and Instrumentation & Controls Engineer 
 EE – Electrical and Instrumentation & Controls Engineer 
 SrSE – Senior Structural Engineer 
 Sr. GEO – Senior Geotechnical Engineer or Geologist 
 GEO – Geotechnical Engineer or Geologist 
 HVAC – Heating, Ventilating and Air Conditioning Engineer 
 CAD –Computer-Aided Designer 
 ECAD – Electrical Computer-Aided Designer 
 SCAD – Structural Computer-Aided Designer 
 ADM – Administration/Clerical 
 
The fee and proposal exclude the following scope of service items: 
• 
SCADA programming  
• 
Hydrogeological Report 
• 
APP Amendment 
• 
AZPDES Update 
• 
Permit Fees 
• 
SKM electrical transient analysis 
• 
Full PEMB design (see notes in section 1.2) 
• 
Redesign work for PEMB building elements and/or foundation after PEMP manufacturer has 
completed design 
• 
Construction Engineering Services 
o 
Submittal Review / RFI Response and Conflict Resolution 
o 
Inspection Services 
o 
Materials Testing 
o 
Change Order Reviews 
o 
Associated Project Management, Coordination, Construction Meetings, and Direct Costs 
• 
MCESD Approval-Of-Construction (AOC) Permitting Assistance 
• 
Record Drawings 
Wood can provide the last 4 items under a separate construction management services agreement.

Attachment A 
Fee Table

City of El Mirage
FEE PROPOSAL
El Mirage WRF Expansion
 
PW21-08-02 R1
Task No.
Description
QA/QC
PM
SME
PE
EIT
CAD
SrGEO2
GEO
SrEE
EE
ECAD
HVAC
SrSE
SCAD
ADM
Total
 
RATES
$205.00
$160.00
$205.00
$140.00
$95.00
$125.00
$215.00
$125.00
$190.00
$145.00
$120.00
$145.00
$190.00
$120.00
$75.00
Hours
Total
Task 1 - Project Management
1100
Project Management and Coordination
10
80
16
106
$16,050 
1200
Project Meetings
12
40
20
50
20
16
158
$24,550 
TOTAL HOURS AND COSTS
22
120
20
0
50
0
0
0
20
0
0
0
16
0
16
264
$40,600 
Task 2 - Conceptual Design / Design Concept Report
2100
Background Investigations (Incl Geo/Survey)
24
4
40
120
20
40
8
4
24
284
$39,420 
2200
Conceptual Design
16
64
24
60
164
120
40
80
40
60
120
148
936
$130,680 
2300
Design Concept Report
8
40
16
40
124
24
60
24
80
4
420
$60,940 
2400
Preliminary OPCC
4
16
2
12
44
24
12
24
138
$19,430 
TOTAL HOURS AND COSTS
28
144
46
112
372
240
20
40
72
168
40
96
248
148
4
1,778
$250,470 
Task 3 - 60% Design Services
3100
60% Drawings
16
100
24
80
316
416
48
172
240
80
164
316
1,972
$260,960 
3200
Technical Specifications
4
16
4
20
44
24
40
32
64
4
252
$38,640 
3300
OPCC Update
2
8
2
24
4
16
6
16
78
$11,370 
TOTAL HOURS AND COSTS
22
124
30
100
384
416
0
0
76
228
240
118
244
316
4
2,302
$310,970 
Task 4 - 90% Design Services
4100
Technical Specifications Update
2
16
4
20
48
16
20
36
20
4
186
$26,410 
4200
Design Report Update
4
8
4
16
32
4
68
$8,500 
4300
90% Drawings
4
80
40
60
256
416
48
136
160
80
120
200
1,600
$212,980 
4400
OPCC Update
2
8
2
20
16
4
16
68
$9,940 
TOTAL HOURS AND COSTS
12
112
50
96
356
416
0
0
64
172
160
120
156
200
8
1,922
$257,830 
Task 5 - 100% Design Services
5100
100% Design Package
4
16
2
8
40
60
4
16
16
8
20
16
4
214
$28,390 
TOTAL HOURS AND COSTS
4
16
2
8
40
60
0
0
4
16
16
8
20
16
4
214
$28,390 
Task 6 - Permitting Assistance
6100
MCESD ATC
4
16
8
28
$3,160 
6200
City of El Mirage Building Permit (FBLSD)
2
8
10
$1,080 
TOTAL HOURS AND COSTS
0
6
0
0
24
8
0
0
0
0
0
0
0
0
0
38
$4,240 
TOTAL PROJECT HOURS AND COSTS
88
522
148
316
1,226
1,140
20
40
236
584
456
342
684
680
36
6,518
$892,500 
OTHER DIRECT COSTS
1
Architect Sub-consultant
$74,393 
2
Geotech Drilling Sub-consultant
$3,493 
3
Geotech Testing Costs
$4,700 
4
Survey
$15,554 
5
Potholing Allowance
$20,000 
6
Bid Document Preparation Allowance
$15,000 
7
Local Travel and Printing Costs
$2,500 
TOTAL OTHER DIRECT COSTS
$135,640
TOTAL PROJECT COST
$1,028,140