B&F Proposal

City of El Mirage — Regular Meeting (2023-04-18)

View PDF Item 3 Meeting page

Extracted text (via pymupdf) 2974 characters
El Mirage Street Light Pole 4th Ave & Well St
4th Ave & Well St
Submitted to: City of El Mirage
Project:
Bid Number:
22143
Bid Date:
1/30/2023
El Mirage, AZ
12145 N. W. Grand Ave
El Mirage, AZ  85335   USA
Addendum #:
0
Bryce Christo Phone Number: (623) 876-2974 Cell Number: (623) 980-9980 Email: bchristo@elmirageaz.gov
Attention:
Total Price
Unit Price
Unit
Item Description
Item #
Estimated Quantity
******************************************************************************************************
$7,399.65
$7,399.65
1.00
1
EACH
Install Direct Bury 30'6" APS Pole With 5,100 Lumen LED
$1,877.11
$1,877.11
1.00
2
EACH
Install APS Pull Box
$7,176.65
$110.41
65.00
3
LF
Bore 2.5 In SL Conduit To Single Phase Transformer
$6,063.25
$242.53
25.00
4
LF
Tie Into Pull Box & Transformer
$6,646.54
$6,646.54
1.00
4
LS
Asphalt Restoration
$2,101.96
$2,101.96
1.00
5
LS
GC-Traffic Control
$31,265.16
Total Bid Price:
• Terms: Net 30 Days
******************************************************************************************************
• This proposal is based on the following information:
Plans: El Mirage Street Light WA685523
Plans used were: El Mirage Street Light WA685523
Prepared by: APS
Addenda Received: 0
******************************************************************************************************
•
· Exclusions: Sales Tax, Permits, Bonding Fees, Const. Survey/Staking, Compaction Testing & Inspection Fees. Engineering, Locate, Hard Dig
or Rock Excavation. Hard Dig Defined As Any Material A 416 Cannot Dig Effectively At A Production Rate OF 30 LF Per Hour At An Average
Depth of 5ft. Century Link TMB/TTC- Provided By Others. Existing Utilities. Dust Control Permit, SWPP by Other. Prices are good for 30
days. Quantities are approximate and final payment is to be based on actual field measurement. Irrigation Permit.
******************************************************************************************************
• Inclusions: We propose to furnish labor, equipment, and materials - complete in accordance with the plans and specifications supplied to us for the
above mentioned project. All material is guaranteed to be as specified. All work will be completed in a workmanlike manner according to the
standard practices. Any alternations or deviations from the above specifications involving extra costs, will be executed only upon written orders and
will become an extra charge over the above proposed estimate.
******************************************************************************************************
Page 1 of 2
1/30/2023 4:03:16 PM
B&F Contracting Inc.    bfcontracting.com

ACCEPTED:
The above prices, specifications and conditions are satisfactory
and hereby accepted.
Buyer:
Signature:
Date of Acceptance:
CONFIRMED:
B&F Contracting, Inc. (Proposal)
Authorized Signature:
Estimator:
Cole Anderson
602-292-6516   canderson@bfcontracting.com
Page 2 of 2
1/30/2023 4:03:16 PM
B&F Contracting Inc.    bfcontracting.com