Extracted text (via pymupdf)
5910 characters
Proposal March 1, 2023 VIA ELECTRONIC MAIL Cason Chambers City of El Mirage El Mirage, AZ 1 GPA - #18-15PV-05 23-04-019 - CoEM - City of El Mirage Street Light Install Dear Cason, On behalf of CORE Construction, I am pleased to submit our proposal. Enclosed you will find the basis of estimate clarifications and schedule of values which includes the requested scope of work, general conditions, sales tax, bonds, insurances, and fee. Total Proposal – $57,888 We look forward to a successful and enjoyable project together. Thank you for this opportunity, please do not hesitate to contact me directly with any questions or comments. Respectfully submitted, J.D. Jordan J.D. Jordan CORE Construction, Inc. Basis of Estimate Page 2 of 3 This proposal is based upon the most recent plans and/or specifications issued to CORE, dated December 19, 2022, and the scope clarifications below. Assumptions, Clarifications, & Exclusions Schedule • Anticipated Start: TBD • Long Lead Items: Light Pole 10 weeks • Projected Duration: ~1 weeks Contingency & Allowances • We have included a Contractor Contingency in this proposal – This is intended to be used at CORE’s discretion to cover costs that have not been identified as a trade specific scope established in this proposal and may require further clarification or coordination. These costs may include but are not limited to scope gap, coordination issues between trades, overtime, expediting, missed scope during subcontractor bidding process, etc. Construction Contingency does not account for design revisions or additional scope requests made by the Owner or Architect. • We have NOT included a Design Contingency in this proposal – This is intended to be used at CORE’s discretion to cover costs associated with the completion of the design and/or scopes of work for which sufficient detail was not available to determine a definitive cost. • We have NOT included an Owner Contingency in this proposal – This is intended to be used to cover any added scopes of work which are unknown and therefore not included at time of this proposal to determine a definitive cost for wish list or extra items. • We have NOT included an Escalation Contingency in this proposal – This is intended to be used to cover escalation of materials, equipment and labor if the project scheduled start is known to be X+ months from date of this proposal. General Assumptions • This cost proposal is considered a Lump Sum, not line-item Estimate. • Unless otherwise included in scope below, CORE has not included any costs for permits, including but not limited to: building permit, systems permit, or dust control. • All approved value engineering savings will be added to the Contractor’s Contingency. • All un-used Contingency or Allowance will be credited back to Owner. • We assume normal working hours. • General Conditions and/or General Requirements are considered cost of the work. • Normal shrinkage cracking of the slab is expected and shall not be cause for removal or replacement of structurally sound slabs • A registered professional did not provide sealed plans or specifications and therefore no form of permit is in place. CORE Construction, Inc. shall not be held responsible for performance of systems or equipment, code interpretations, engineering, etc. requirements and will perform the requested scope of work as defined by the Owner representative(s). • Proposal valid for 10 days, unless otherwise directed by CORE Construction. • The Date of Commencement of the Work shall mean the date of commencement of the Construction Phase. The Construction Phase shall be approximately five (5) days from Construction Manager’s receipt of the latter of the following: Basis of Estimate Page 3 of 3 o Fully executed Job Order. o Issuance of Site Permit, Building Permit, and any other permits required to commence the Work. o Owner’s Notice To Proceed with Construction. Specific Assumptions DEMOLITION – N/A SITE WORK (ROUGH) – N/A SITE WORK (FINISH) – N/A STRUCTURE – N/A ENCLOSURE – N/A INTERIOR FINISHES – N/A SPECIALTIES – N/A EQUIPMENT – N/A MEP SYSTEMS – • Electrical System – Includes Bore and install (1) 2 ½’’ conduit. Provide and install (1) light pole with cobra LED light head. Install in ground pull box with grounding as shown. a) · Bore and install UG conduit b) · Traffic control c) · In ground pull box and grounding d) · Provide and install light pole and cobra LED light head e) · R&R for bore pits SPECIAL SYSTEMS – N/A Specific Exclusions • Hazardous Material Abatement • Costs associated with Material Testing and/or Special Inspections • Costs associated with General Building Inspections • FF & E – Furniture, Fixtures, and Equipment (by Owner) • Structural modifications (i.e. - Steel, Concrete & Masonry removal or replacement) • Signage (by Owner) • Permits • ROW permit • Wire in conduit – APS to pull in • Bringing existing electrical up to code • Transformer CORE PROJECT #: 23-04-019 LOCATION: El Mirage, AZ ARCHITECT: N/A PROCUREMENT: 1 GPA - #18-15PV-05 BID TYPE: OPEN BOOK DURATION(mnths): 0.25 WARRANTY(yrs): 1 TAX METHOD: GROSS RECEIPTS GENERAL REQUIREMENTS $160 GR1 General Requirements $160 DEMOLITION $0 SITE WORK (ROUGH) $0 SITE WORK (FINISH) $0 STRUCTURE $0 ENCLOSURE $0 INTERIOR FINISHES $0 SPECIALTIES $0 EQUIPMENT $0 MEP SYSTEMS $34,650 88 Electrical Systems Armstrong $34,650 SPECIAL SYSTEMS $0 CONTINGENCY $5,789 10.0% Construction Contingency $5,789 GC + GR's GENERAL CONDITIONS $5,430 Subtotal $46,029 CoEM - City of El Mirage Street Light Install Estimate #1 - 03/01/2023 SUBCONTRACTOR Subtotal (with Insurance, Tax, & Fee) $57,888 Subtotal (with Insurance, & Tax) Total $57,888 Description # Base Price $52,678