RE: DRAFT - Dysart Road: Contract Modification for Construction Management Services 
Dear Mr. Christo, 
As requested, we have modified our scope of services to include the inspection and construction 
management services required to support the construction phase of this project.  This work will be 
comprised of the following: 
•
Based on an assumed 15 month construction schedule, we will attend up to sixty four (64)
weekly construction progress meetings at the project site or City offices.  It is presumed that
one (1) EPS staff member would attend all the meetings and an additional EPS staff member
would attend half of the meetings.  EPS will conduct the meetings on behalf of the City staff.
EPS will prepare meeting agenda, attend the meetings, and prepare meeting minutes.
•
Based on an assumed 15 month construction schedule, we will provide inspection services
for the duration of construction activities.  EPS will provide one (1) full time inspector at an
assumed 20 hours per week for month 2 and 16 and 40 hours per week for months 3-15.
Should construction activities require the support of a second inspector, the City will
provide that additional support.
•
Review and approve change orders received from the Contractor.  Approvals of change
order will be contingent on receiving concurrence from City staff.
•
Review and recommend for approval to the City pay applications as submitted by the
contractor. There will be 4 separate pay applications required for each of the following:
Dysart Road, Olive Avenue/Microsoft frontage, TI Cold & the basin at Peoria/Dysart.
•
Review RFI’s, materials and other submittals with the support of the design engineer.
•
Review test results for compliance with specifications.
The following assumptions have been made in association with this modified scope of work: 
•
The inspector will provide services for no more than 20 hours per week for month 2 and 16
and 40 hours per week for months 3-15.

1130 N. Alma School Road, Suite 120, Mesa, AZ 85201  |  T: 480.503.2250  |  F: 480.503.2258  |  www.epsgroupinc.com 
•
The Construction Manager will provide services for no more than 21.5 hours per week for
months 1 through 17, on average, per week.
•
Quality Assurance and Quality Control (QA/QC) materials testing, or other requiring testing
(such as pressure tests) will be provided by the contractor.
•
As-built plans will be provided by the contractor.  EPS will review the as-built plans once
submitted.
We appreciate this opportunity to assist the City with the construction of this Dysart Road project.  
If you have any questions concerning the proposed scope and fee, please let me know.  
Sincerely, 
Greg Froehlich, P.E. 
Project Manager

Date: 4-17-23
Job No.: 18-081.3
Labor Class Rate
$220.00
$185.00
$115.00
$145.00
$110.00
$105.00
$60.00
$140.00
$100.00
$80.00
$140.00
$125.00
$90.00
DESCRIPTION
Principal
Construction 
Manager
Project 
Inspector
Sr. Engineer
Engineer
CAD 
Tecnician
Clerical
Landscape 
Architect
Senior 
Landscape 
Designer
Landscape 
Designer
Survey 2-
man
Project 
Surveyor
Survey Tech
Task Cost
Project Inspection Services
17
2400
$279,740.00
Project Management Services
64
1536
120
$305,440.00
TOTAL HOURS
81
1536
2400
0
0
0
120
0
0
0
0
0
0
4137
SUBTOTAL FEES
$17,820.00
$284,160.00 $276,000.00
$0.00
$0.00
$0.00
$7,200.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$585,180.00
Assumptions:
* EPS will provide one inspector fulltime (20 hrs/week) for 2 months (8 weeks) and (40 hrs/week) for 13 months (56 weeks)
$10,200.00
$200.00
$595,580.00
$50,000.00
$645,580.00
Fee Estimation Worksheet
PROJECT: City of El Mirage Dysart Road - Construction Management Services
Reimburseables
TOTAL HOURLY FEE
TOTAL HOURLY FEE w/ Allowances
Allowances
Miscelleanous Services at Client Request
* QA/QC materials testing and construction survey will be provided by the contractor
* As-builts will be provided by the contractor
Mileage (@ $0.68/mile for 15000 miles (est))
Deliveries
Subconsultants
* EPS will provide one construction manager parttime (20 hrs/week) for 17 months (72 weeks). 
   In addition,  construction manager is estimated to spend 1.5 hours per week for 64 weeks to complete 4 separate Pay Apps.