TAC Review Comments

City of El Mirage — Regular Meeting (2023-07-11)

View PDF Item 3 Meeting page

Extracted text (via pymupdf) 16614 characters
PLANNING AND ZONING 
Development Services Department 
10000 N. El Mirage Road, El Mirage, Arizona 85335 
623-876-2996; Fax 623-876-4605; TDD 623-933-3258 
www.elmirageaz.gov 
 
 
MEMORANDUM 
TO: 
 
Matt Izzo, VESPRO 
FROM: 
Jose A. Macias, Senior Planner 
 
 
Development Services Department, Planning & Zoning  
RE: 
 
PZ23-05-09: Desert Truss Site Plan Amendment 
DATE: 
June 1, 2023 
Mr. Izzo, 
Please see the comments from the El Mirage Technical Advisory Committee (TAC) for the light 
manufacturing use site plan amendment.   
BUILDING & SAFETY 
1. Building Safety has reviewed Development Application PZ23-05-09 and found the Site 
Plan Amendment to meet the building planning code requirements.   
 
ECONOMIC DEVELOPMENT  
2. No comment. 
ENGINEERING 
3. See attached memorandum.  
FIRE DEPARTMENT 
4. No comment.  
PLANNING & ZONING 
5. A Site Plan zoning application will be required for City review and approval for when the 
undeveloped portion of the property is ready to be developed. 
6. A final plat if required shall be submitted for City review and approval to record any 
easements and or any dedication of land prior to issuing the Certificate of Occupancy. 
Separate fees apply.   
 
POLICE DEPARTMENT 
7. No comment.  
PUBLIC WORKS 
8. No comments on the site plan amendment for the Desert Truss project.

Engineering 
Development Services Department 
10000 N El Mirage Road, El Mirage 85335 
623-972-8116; Fax 623-876-4605; TDD 623-933-3258 
www.elmirageaz.gov 
 
 
MEMORANDUM  
 
TO: 
 
Jose Macias, Planner/GIS 
FROM: 
Bryce Christo, P.E., Assistant City Engineer 
SUBJECT: 
Desert Truss West Development Application Review - Updated 
DATE: 
05-31-23 
 
Below are the Engineering Department’s comments for the above referenced submittal provided 
in May 2023. These items will have to be addressed prior to the Planning and Zoning 
Meeting. 
 
1. None.  
 
The below items will have to be addressed during the Construction Plan Submittal. 
 
Narrative 
1. Section 3  
a. The majority of the site falls within Zone X (Shaded) which has a slightly 
different definition than the one shown.  
b. In general, development within or modification of the floodplain is discouraged. 
2. Section 6 – It is the City’s understanding that all farming activities along the west side of 
Dysart Road, between Peoria Avenue and Olive Avenue, has ceased. 
3. Section 7  
a. Eight foot wide detached sidewalks will be required along Dysart Road and shall 
be installed as part of the Desert Truss project.  
b. Additional right of way may be required along the proposed deceleration lane.  
See Comment #6 below. 
4. Section 8  
a. It is noted that this property will be developed in one phase.  It should be clarified 
that the layout shown on the Site Plan will be constructed in one phase but there is 
potential for other buildings to be constructed in the future. 
b. It is noted that the eastern half of the property will remain in agricultural 
production. It is believed that the proposed site is no longer served by irrigation 
water. 
5. No reference to the proposed rail spur is made in the Narrative. It is assumed that the 
construction of the spur would be a separate project for the future. Coordination with and 
approval from BNSF would be required. 
 
Site Plan/Civil Plans  
6. The City will construct the five lane (2-M-2) roadway section for the ultimate Dysart 
Road and both the right of way and 8-foot PUE along the Desert Truss property has

2 
 
already been dedicated per the Copperwing Final Plat. The project is responsible for an 
eight-foot-wide detached meandering sidewalk, streetlights, ITS conduit and 
landscaping/irrigation along the Dysart Road frontage. The project will also be 
responsible for any deceleration/turn lanes and associated right of way/easement 
revisions. Offsite Plans will be required to show these improvements. 
7. The Zoning is PAD/EI. 
8. Show the square footage of the southernmost Gantry. Verify whether the area of the 
Gables building is 2,500 or 1,875 square feet. 
9. Show the dimension from the southern face of curb of the proposed driveway to the 
northern right of way line of the railroad. 
10. The retention basin south of the proposed buildings cannot be within the building setback 
line. 
11. A stop sign is recommended for the driveway at the intersection with Dysart Road.  
12. The driveway shall be able to accommodate a WB-67 vehicle without encroaching into 
the adjacent lane. 
13. Any fire access road shall be designed to handle 75,000 lbs. A Geotechnical Report will 
be required for this project, and it should provide a recommended design section for this 
access road.  
14. It appears additional right of way will need to be dedicated along Dysart Road near the 
deceleration lane. Right turn lanes may be 11.5 feet wide. 
15. Plans shall include applicable City Notes. Call out MAG, City, etc. details to be used. 
Use the City’s Design & Development Standards Manual (DDSM) as a guide for the final 
design. 
 
Preliminary Grading & Drainage Plan (Updated Grading & Drainage Plans were not provided 
with this submittal so the August 2022 comments have been provided below) 
16. Verify the slope does not exceed 2% in any direction within ADA parking spaces. 
17. Side slopes adjacent to the public right of way, areas where pedestrian access is permitted 
and within Public Utility Easements (PUE) shall be 6:1 or flatter. There shall be at least 
two feet of level ground between any wall or vertical obstruction and the top of any side 
slope grading.  
18. The proposed retention basins shall be located a minimum of 4 feet away from any 
structures and shall not be located within any building setbacks, easements, or fire lanes.  
19. Basin DB1 appears to be too close to the proposed rail spur. Please verify. 
20. The volume provided for Basin DB1 should be 115,273 cubic feet per the Drainage 
Report. 
21. Label basin volumes required and the basin overflow elevations for each basin. 
22. This plan shows portions of the existing irrigation ditches to be removed. Any removal of 
these ditches shall be coordinated with the farmer prior to the release of any Engineering 
permit. 
 
Preliminary Utility Plans (Updated Utility Plans were not provided with this submittal so the 
August 2022 comments have been provided below) 
23. The Utility Plans shall show all utilities and utility easements including electric, gas, 
phone and cable, if applicable. 
24. Onsite sanitary sewer and water mains/services will be private and will be reviewed by 
the City. The water main between the backflow preventer and main will be reviewed by 
EPCOR. The sanitary sewer connection will be reviewed by EPCOR. 
25. Water meters/vaults shall be located within the right of way and backflow preventers 
shall be located on private property but not within the PUE.

3 
 
26. The landscaping service requires its own meter and backflow preventer. 
27. The maximum length of a dead end water main is 400 feet.   
28. Fire hydrants shall adhere to City Details EM-360, 361 and 362. If bollards are required, 
they shall adhere to City Detail EM-364. The backflow preventers shall adhere to City 
Details EM-351, 352 or 353.   
29. Water valves are required along the fire line, approximately every 500 feet, and at 
locations so that the maximum number of hydrants to be out of service is two. 
30. Hydrant location/spacing will be reviewed and approved by the Fire Department.  
31. All utilities shall maintain a minimum of 6 feet of clearance from all fire hydrants and 
fire suppression devices per City Detail EM-361. 
32. Any hydrants within the project site will be private and painted “Safety Red” per City 
Detail EM-360. All hydrants require markers per MAG Detail 122. 
33. Water and sewer lines or services are not recommended to run through retention basins as 
shown on the plans.  If this is desired, the utilities must have a minimum of 4 feet of 
cover from the bottom of the basin to the top of the pipe. 
34. Is the 6-inch sanitary sewer considered a service line or a main.  What is the slope? Will 
there be manholes or cleanouts? 
35. Each new building will require a backwater valve per City Detail EM-442. 
36. See Section 6-3 of the City’s Design and Development Standards Manual (DDSM) to 
determine if a pretreatment device is required. 
37. Show utility horizontal and vertical clearance information per MAG Detail 404 and City 
Detail EM-402. 
38. Each proposed driveway shall have at least one streetlight. 
 
Preliminary Landscape Plans 
39. Add City Landscaping and Irrigation Notes (City Detail EM-101-4) to the plan set. 
40. Show the sight distance requirements at the proposed driveway per City Detail EM-158 
and the TIS.  
41. The Water Report calls out a 2-inch landscape service and meter while these plans call 
for 1.5-inch. Please verify which is correct. 
42. Palo Verde trees are not allowed within the City. Please revise. 
43. All plantings at maturity shall maintain a minimum of 6 feet of clearance from all fire 
hydrants and fire suppression devices per City Detail EM-361. 
44. No walls or trees shall be placed within the Public Utility Easement (PUE).  
45. Trees shall not be placed within 5 feet of any City curb or sidewalk or within 6 feet of 
any public utility. 
46. DG, or another approved soil stabilization measure, is required on all non-paved, 
improved areas both on site and within the right of way adjacent to the project site. 
47. Add a note to the plans that the maintenance for all landscaping and irrigation shown on 
the plans will be the responsibility of the property owner. 
48. Update all of the City Details to the 2023 versions. 
 
Preliminary Photometric Lighting Plans 
49. Any light or combination of lights which cause light on a public street, other than lights 
specifically intended for that purpose, shall not exceed one foot candle as measured from 
the center line of the street. Show the foot candles along the centerline of Dysart Road to 
verify that the proposed lighting will not exceed the maximum limit. 
 
Exterior Elevations 
50. No comments.

4 
 
 
Preliminary Drainage Report (An updated Drainage Report was not provided with this submittal 
so the August 2022 comments have been provided below) 
51. Section 3.1 
a. The report states that a berm and chain link fence is proposed for construction 
along the north shared property line. This is not shown on the plans by either 
Desert Truss or G3. 
b. The report states that G3 will reduce, if not eliminate, all offsite flows from the 
north. What if Desert Truss develops first? 
52. Section 4.3 - Use the City Runoff Coefficients per City Code Section 155.054(B)(6)(a). 
Concrete = 0.95, roofs/asphalt = 0.85, grass = 0.15 and desert/rock lawn = 0.70.  
53. Section 4.4 – The report states the ultimate outfall as 1101.72 but the Grading Plans show 
1101.00.  Please verify which is correct. 
54. Section 4.5 – Remove the dissipation rate from the calculations.   
55. Appendix A - The City’s Dysart Road plans only show one proposed scupper that will 
drain to the Desert Truss property, approximately 200 feet north of the south property 
line. The Desert Truss plans show a proposed scupper, approximately 50 feet south of the 
north property line.  Calculations will be required for this scupper and the basin that it 
drains to. This Drainage Area (DA-6?) must extend to the ultimate Dysart Road 
centerline? This will also reduce the size of Catchment Area E per the Dysart Road 
Drainage Report. 
 
Final Water Report  
56. The water service area for the Copperwing Logistics Center is in the process of being 
transferred to EPCOR. The City of El Mirage will still be responsible for fire protection 
and the design of that system will be reviewed and approved by the City. 
57. Section 3.3 – Add the referenced City of Phoenix criteria in the Appendix. 
58. Section 3.4 – Section 3.2 states that the 50,000 square foot future building would be used 
for the fire flow calculations. This building size would require 4,750 gpm before the 
reduction. 
59. Appendix B – The Fire Flow Test shows the static pressure exceeds 80 psi which may 
require individual pressure reducing valves be installed on private services. 
60. Provide a Table that shows the maximum velocity, head loss in ft/1000 ft and minimum 
pressures for the Average Day, Maximum Day and Peak Hour Demands. 
 
Final Sewer Report 
61. Section 1.0 – The City has never owned the existing sewer main adjacent to the site. That 
main was designed, constructed and is maintained by EPCOR. 
62. Section 4.1 – The section states the City does not allow tapping into an existing manhole 
without written authorization, The manhole in question belongs to EPCOR so that 
decision shall be made by that agency. 
63. Table 4.1  
a. Where did the Daily Unit Rate of 0.400 gpd/unit for the offices come from? 
b. The Qp for the Manager’s Office should be 1.67 gpm. 
c. This report assumes the future buildings are warehouses while the Water Report 
assumed they were commercial. There is also no mention of the future buildings 
in the report. 
64. Table 4.2 – For pipes under 12 inches, the d/D = 0.50. 
65. Section 5.0 – ATCs will be signed by EPCOR as it is their collection system.

5 
 
Traffic Impact Statement (TIS) 
66. The City’s Dysart Road project is now anticipated to be complete in late 2024. 
 
ALTA Survey 
67. Some of the text on Sheet 1 is shown as squares. Please revise the PDF. 
68. The Schedule B number references on Sheet 3 appear to be off by 1 (i.e., #11 should 
actually be #12). 
69. Schedule B Item #20 is noted as “shown” but does not appear on the plans (keeping 
Comment #75 in mind). 
 
Deed 
70. No comments 
 
Phase I Environmental Site Assessment 
71. Section 3.2 & 7.2 – The project site lies within a Water and Wastewater Service Area that 
is in the process of being transferred to EPCOR. 
72. Section 3.3 – The “stormwater manhole” found on the southern boundary of the site is 
actually an irrigation manhole that helps direct the water from the existing concrete ditch 
through the TI Cold site to the south. 
73. Section 3.4.5 – The sanitary sewer manhole found at the southeast corner of the property 
was installed by EPCOR and is located within the right of way, not on the subject 
property. 
 
Miscellaneous 
74. A Final Plat will be required prior to Certificate of Occupancy. The Plat shall show any 
right of way and/or easement dedications including: 
a. Additional right of way due to the deceleration lane. 
b. 1-foot VNAE  
c. A Public Access Easement where the proposed driveway encroaches onto the 
private property. 
75. Due to the location of the adjacent Flood Zone “A”, a Floodplain Use Permit (FUP) or 
similar permit may be required. Contact the Flood Control District of Maricopa County to 
determine what is required. A copy of the FUP shall be provided to the City prior to the 
release of any Engineering permit. 
76. A Geotechnical Report will be required to provide on-site pavement sections. Verify the 
proposed pavement sections can handle 75,000 lbs. for the fire access lane. 
77. A Haul Permit will be required if 500 cubic yards or more of material will be brought 
into or out of the site. This will require a separate application, an exhibit showing the haul 
route and insurance from the company performing the haul. The fee is $300. 
78. An Approval to Construct (ATC) will be required from MCESD for the water and sewer 
line extensions. A copy shall be provided to the City prior to the release of any 
Engineering permit. 
79. A Dust Control Permit from the County will be required prior to the release of any 
Engineering permit. 
80. A Stormwater Pollution Prevention Plan (SWPPP) will be required per the City’s SWPPP 
Guidelines document. A Notice of Intent (NOI) from ADEQ will be required prior to 
release of any Engineering permit. 
81. Any cutting of the pavement in the reconstructed Dysart Road will require Pavement Cut 
Fees per the most current Fee Schedule and would require the street to be renovated with

6 
 
a slurry seal or micro seal for 10 feet on either side of the cut for the full width of all 
lanes affected. 
82. The City will not release any permits until EPCOR provides the City with their approval 
of the water and sewer plans and reports. The applicant is responsible for submitting 
plans to EPCOR for review and approval. 
 
The above comments are meant to be general in nature and are not considered to be all inclusive. 
Additional comments will arise during the formal permit submittal.