Public Works Facility
Overview
Request Owner
Nick Russo, Public Works Director
Est. Start Date
07/01/2023
Est. Completion Date
06/30/2024
Department
Water
Type
Capital Improvement
Project Number
62343
Description
The Master Plan gave the Public Works Administration building and the Water Reclamation Facility (WRF) building an overall rating of average. This item
includes a new building to consolidate most of Public Works. The lab/WRF operations will remain in the current location.
Images
PW Facility Rendering
Details
Type of Project
New Construction
Strategic Priority
Effective Government
Grant Funding
No
Bond Eligible
No
Project Status
New
Location
Supplemental Attachments
Public Works Facility(/resource/cleargov-prod/projects/documents/acb39b726ccb52d09ea7.pdf)
City of El Mirage | Budget Book 2024
Page 98

Capital Cost Breakdown
Capital Cost
FY2024
Total
Construction/Maintenance
$2,667,000
$2,667,000
Total
$2,667,000
$2,667,000
Capital Cost
FY2024 Budget
$2,667,000
Total Budget (all years)
$2.667M
Project Total
$2.667M
Capital Cost by Year
(Adopted)
Construction/Maintenance
2024
$2,667,000.00
$0
$800K
$1.6M
$2.4M
Capital Cost for Budgeted Years
(Adopted)
TOTAL
$2,667,000.00
Construction/Maintenance (100%)$2,667,000.0
City of El Mirage | Budget Book 2024
Page 99

Funding Sources Breakdown
Funding Sources
FY2024
Total
511 - Water
$1,333,500
$1,333,500
541 - Sewer
$1,333,500
$1,333,500
Total
$2,667,000
$2,667,000
Funding Sources
FY2024 Budget
$2,667,000
Total Budget (all years)
$2.667M
Project Total
$2.667M
Funding Sources by Year
(Adopted)
511 - Water
541 - Sewer
2024
$2,667,000.00
$0
$800K
$1.6M
$2.4M
Funding Sources for Budgeted Years
(Adopted)
TOTAL
$2,667,000.00
511 - Water (50%)
$1,333,500.00
541 - Sewer (50%)
$1,333,500.00