Extracted text (via pymupdf)
3789 characters
1 Mobilization LUMP SUM 1 60,280.00 $ 60,280.00 $ 2 Erosion Control LUMP SUM 1 7,568.00 $ 7,568.00 $ 3 Survey Control and Staking LUMP SUM 1 15,070.00 $ 15,070.00 $ 4 Traffic Control LUMP SUM 1 7,568.00 $ 7,568.00 $ 5 Remove and Replacements (Asphalt, Curbs, Sidewalks, Signs, Trees) LUMP SUM 1 17,600.00 $ 17,600.00 $ 6 Earthwork Complete In Place LUMP SUM 1 17,600.00 $ 17,600.00 $ 7 Earthwork Haul Off-Site LUMP SUM 1 13,200.00 $ 13,200.00 $ 8 Subgrade Preparation SY 2,952 8.00 $ 23,612.16 $ 9 2" Water Meter and Backflow for Irrigation Systems EACH 1 22,500.00 $ 22,500.00 $ 10 2" Asphaltic Pavement over Native Subgrade SY 3,376 35.00 $ 118,144.44 $ 11 ADA Sidewalk Ramps, Includes Detectable Domes EACH 2 6,250.00 $ 12,500.00 $ 12 Pedestrian Crossing Marking & Signage @ Myer Lane LUMP SUM 1 4,000.00 $ 4,000.00 $ 13 Trail Dashed Center Striping L.FT. 3,038 2.00 $ 6,076.00 $ 14 Cast In Place Retaining Wall (48" Tall) With MAG Safety Rail L.FT. 74 270.00 $ 19,980.00 $ 15 4" Concrete Integral SF 554 15.00 $ 8,310.00 $ 16 4" Concrete Plain SF 366 10.00 $ 3,660.00 $ 17 Irrigation Restoration along Trail Corridor SF 16,049 2.25 $ 36,110.25 $ 18 24" Box Shade Trees along trail Corridor EACH 38 415.00 $ 15,770.00 $ 19 1/2" Sized Decomposed Granite SF 16,049 0.92 $ 14,765.08 $ 20 15' Solar Light Fixture and Pole EACH 6 10,000.00 $ 60,000.00 $ 21 Trail Signage LUMP SUM 1 2,500.00 $ 2,500.00 $ 22 Seat Wall L.FT. 46 150.00 $ 6,900.00 $ 23 Litter Receptacles EACH 4 1,500.00 $ 6,000.00 $ 24 Bike Repair Station EACH 1 2,200.00 $ 2,200.00 $ 25 Pet Waste Station EACH 4 1,200.00 $ 4,800.00 $ 506,713.93 $ 26 Payment and Performance Bond, General Liability, and Builder's Risk Insurance (2.5% of Subtotal) 12,667.85 $ 27 General Contractor's Overhead and Profit (Fee) (6% of Subtotal) 30,402.84 $ 28 State Sales and Use Tax 65% or 9.9% (6.44% of Subtotal) 32,632.38 $ 29 Design Estimating and Bidding Contingency (20% of Subtotal) 101,342.79 $ 30 (City of El Mirage Owner Controlled Allowance (10% of Subtotal) 50,671.39 $ 734,431.18 $ DSD - Engineering Division 10000 N. El Mirage Road El Mirage, AZ 85335 Phone: (623) 876-2977 Fax: (623) 876-4605 ITEM No. ITEM DESCRIPTION UNIT QUANTITY UNIT COST IN WRITING UNIT COST IN FIGURES TOTAL COST ESTIMATE MULTI-USE TRAIL PHASE 2A TOTAL SUBTOTAL