C-10844-3

AMENDMENT NO. 3
West Area Water Reclamation Facility Improvements
(City Project No. 141525, Contract No. C-10844)

This Amendment No. 3 (“Amendment”) to the Professional Services Agreement
(“Agreement”) is made this day of , 2021, (“Effective Date”), by and
between the City of Glendale, an Arizona municipal corporation (“City”) and Arcadis U.S.,
Inc., a Delaware Corporation authorized to do business in Arizona (“Contractor”).

RECITALS

City and Arcadis U.S., Inc. (“Contractor”) previously entered into Professional
Services Agreement, Contract No. C-10844, dated May 10, 2016 (“Agreement”); and

The initial study phase of the work has been completed with recommendations made
on how to proceed with critical plant improvements.

The detailed design of GMP1 (Headworks Improvements) has been completed and
is under construction. Arcadis provided CA services as noted in C-10844-2.
Construction will be completed June 2021.

Expanding the Scope of Work (attached under Exhibit B) under the original
Agreement will include the construction administration services related to the
construction, start-up, commissioning, and post-construction activities for GMP 2A,
the Primary Sedimentation Basin Improvements Project.

This amendment includes payment for two GMP 1 CA Services change order
requests, for the concrete and coating rehab professional services provided and the
time extension matching the term extension approved for the CMAR.

The use of the term "Contractor" under this Amendment No. 3 is used
interchangeably with the term "Consultant" defined under the Agreement and used
throughout the attached Exhibits.

City and Contractor wish to modify and amend the Agreement subject to and strictly
in accordance with the terms of this Amendment.

This amendment includes revised billing rates that will be used henceforth and
supersedes billing rates included with original Agreement.

AGREEMENT

In consideration of the mutual promises set forth herein and other good and valuable
consideration, the receipt and sufficiency of which are hereby acknowledged, the City and
Contractor hereby agtee as follows:

1/2/20

Recitals. The recitals set forth above are not merely recitals but form an integral
part of this Amendment.

Term. The term of the Agreement is extended for a two-year period from May 11,
2021 through May 10, 2023, unless otherwise terminated or canceled as provided by
the Agreement. All other provisions of the Agreement except as set forth in this
Amendment shall remain in their entirety.

Scope of Work. This project will provide professional engineering services to
complete the construction and selected design services described in Exhibit B.

Compensation. Including allowances, Phase 1/GMP1 (Facility Evaluation and
Headworks Improvements Design) resulted in previous compensation of $1,231,184.
Amendment 1, including allowances, Phase 1/GMP1A (Significant Amendment to
WAARF APP), Phase 1/GMP2A (Primary Sedimentation Basin Design), and Phase
2/GMP2 (WAWRF Improvements Design) resulted in a previous compensation of
$1,455,124. Including allowances; Phase 3/GMP1 (Headworks Construction
Administration) resulted in a previous compensation of $537,266. Including
allowances, Phase TIT - GMP 2A (Primary Sedimentation Basin Construction
Administration and GMP 1 CA services change order requests), will result in an
increase in compensation of $867,323 and as shown in the attached Exhibit D (for a
total compensation including allowances of $4,090,897).

Insurance Certificate. Current certificate will expire on June 1, 2021 and a new
certificate applying to the extended term must be provided prior to this date to
Materials Management and the Contract Administrator.

Non-discrimination. Contractor must not discriminate against any employee or
applicant for employment on the basis of race, color, religion, sex, national origin,
age, marital status, sexual orientation, gender identity or expression, genetic
characteristics, familial status, U.S. military veteran status or any disability.
Contractor will require any Sub-contractor to be bound to the same requirements as
stated within this section. Contractor, and on behalf of any subcontractors, warrants
compliance with this section.

No Boycott of Israel. The Parties agree that they are not currently engaged in and
agree that for the duration of the Agreement they will not engage in, a boycott of
Israel, as that term is defined in A.R.S. §35-393. Unless and until the District Court’s
injunction in Jordahl v Brnovich, 336 F. Supp.3d 1016 (D. Ariz. 2018) is stayed or lifted,
the Anti-Israel Boycott Provision (A.R.S. §35-393.01 (A)) (if applicable to this
agreement) is unenforceable and the City will take no action to enforce it.

Attestation of PCI Compliance. When applicable, the Contractor will provide the
City annually with a Payment Card Industry Data Security Standard (PCI DSS)
attestation of compliance certificate signed by an officer of Contractor with oversight
responsibility.

1/2/20

Ratification of Agreement. City and Contractor hereby agree that except as
expressly provided herein, the provisions of the original Agreement shall be, and
remain in full force and effect and that if any provision of this Amendment conflicts
with the Agreement, then the provisions of this Amendment shall prevail.

[Signatures on the following page.]

1/2/20

ATTEST:

CITY OF GLENDALE, an Arizona
municipal corporation

Kevin R. Phelps, City Manager

Julie K. Bower, City Clerk

APPROVED AS TO FORM:

(SEAL)

Michael D. Bailey, City Attorney

Arcadis U.S., Inc.,
a Delaware Corporation

By: _Brian J. Bubela, P.E.

Its: Vice President

1/2/20

EXHIBIT A
Professional Services Agreement

CITY OF GLENDALE
WEST AREA WATER RECLAMATION FACILITY IMPROVEMENTS
Amendment 3
Project No. 141525

Phase III - GMP 2A WAWRE Improvements Project
Primary Sedimentation Basin Construction Administration (CA) Services

PROJECT

DESCRIPTION OF PROJECT:

The City of Glendale (City) West Area Water Reclamation Facility (WAWREF) provides Class A+
effluent with a rated capacity of 11.5 million gallons per day (MGD) for reuse and aquifer recharge.
The effluent is used at various lakes within the City and for recharge at the West Area Aquifer
Recharge Facility (ARF) and the New River Agua Fria Underground Storage Project (NAUSP).

The City has experienced challenges with high solids loading, operational issues associated with
grit/solids accumulation, and equipment deterioration. In addition, the City is concerned with
limitations of existing equipment at the facility and its ability to treat flows and loads at the
WAWRF that are outside of original design conditions.

Phase I of the project evaluated the plant’s treatment processes and critical treatment components.
The Consultant evaluated the plant process and treatment systems and recommended
improvements. The improvements were prioritized based on criteria developed between the City
and Consultant. Phase I also included design services for WAWRF headworks improvements,
which were implemented in advance of the remainder of the recommended improvements.

Award of this contract includes Phase II design services for recommended improvements and
Phase III construction administration services for recommended improvements. The Scope of
Work for Phase II and Phase III services are defined in Exhibit B, and this contract will be amended
as work progresses.

The project delivery mechanism is Construction Manager at Risk (CMAR). Phase IT and Phase
III services will assume an appropriate level of detail for the CMAR to develop guaranteed
maximum price (GMP) proposals and construction related services. The CMAR is assumed to
provide pre-construction services during design and will perform all cost, maintenance of plant
operations, and field-verification activities. The Consultant may assist City staff with review and
coordination with City-selected CMAR if defined in Exhibit B, Scope of Work.

30039962 A-l 3/17/2021

EXHIBIT B
Professional Services Agreement

CITY OF GLENDALE
WEST AREA WATER RECLAMATION FACILITY IMPROVEMENTS
Amendment 3
Project No. 141525

Phase III - GMP 2A WAWREF Improvements Project
Primary Sedimentation Basin Construction Administration (CA) Services

SCOPE OF WORK

This Scope of Work describes Engineering Services to be provided by Arcadis U.S., Inc.
(CONSULTANT) for the City of Glendale (CITY). The Engineering Services to be provided
under this Scope of Work shall include services related to the construction, start-up,
commissioning, and post-construction phases of the West Area Water Reclamation Facilities
Primary Sedimentation Basin Improvements Project. The Scope of Work to be performed
consists of the following services:

Project Administration Services during Construction; Section 200
Engineering Services during Construction; Section 300
Observation Services during Construction; Section 400

Special Services; Section 500

Allowances; Section 600

WPYWNH>

Other SUBCONSULTANTS working with CONSULTANT shall include the following:

- Nabar Stanley Brown of Gannett Fleming
- Southwest Protective Coatings

The Engineering Services are predicated on the following assumptions:

1. The Construction Manager at Risk (CMAR) will construct the work in one construction
package with an estimated 13-month project duration and an anticipated Notice to
Proceed date of May 2021.

2. The term “Contract Documents” as used herein refers to the combination of the CMAR’s
contract with the CITY and CONSULTANT’s construction documents.

3. The CMAR will complete certain portions of the work in advance of the overall project
substantial completion date defined in the Contract Documents. CONSULTANT shall
schedule the inspection, training, and commissioning services as required to meet the
substantial completion dates as defined in the CMAR project progress schedule.

30039962 B-1 3/17/2021

ARCADIS ssi

4. All construction, programming/configuration (by others), start-up, and commissioning
services will be complete by June 2022.

5. The 24-month post construction Warranty period to commence at Substantial
Completion as defined in the Contract Documents.

6. The CMAR shall receive and transmit to and from the CONSULTANT all submittals,
correspondence and necessary documentation from their suppliers and subcontractors.
The CMAR will review these for completeness in accordance with the Contract
Documents.

Engineering Services are to be provided throughout the duration of construction, start-up,
commissioning, and post-construction phases of the project. The overall project duration is 13-
months, with an anticipated Substantial Completion and final acceptance date as defined in the
Contract Documents, plus a 24-month warranty period.

The Contract Documents are defined as the Agreement, General Conditions, Supplemental
Conditions, Drawings, Standard Details, Specifications, Addendums, and executed change orders
prepared for construction of the project.

SECTION 200 - PROJECT ADMINISTRATION SERVICES DURING
CONSTRUCTION

Task 210 Representation on Behalf of CITY

The CONSULTANT shall consult with and advise CITY and act as its representative during
construction. The extent and limitations of the duties, responsibilities and authority of
CONSULTANT as assigned herein shall not be modified, except as CONSULTANT may
otherwise agree, in writing.

The CONSULTANT assist the CITY in issuing the CITY's instructions to CMAR; issue necessary
interpretations and clarifications of the Contract Documents; have authority, as CITY'S
representative, to require special inspection or testing of the work; act as initial interpreter of the
requirements of the Contract Documents and evaluate the acceptability and completeness of the
CMAR’s work thereunder, and make decisions on claims as directed by the CITY, to the CMAR
relating to the acceptability of the work or the interpretation of the requirements of the Contract
Documents pertaining to the execution and progress of the work. The CONSULTANT shall render
all interpretations or decisions in good faith and in accordance with the requirements of the
Contract Documents.

CONSULTANT shall not be responsible for the means, methods, techniques, sequences, or

procedures of construction selected by CMAR (unless otherwise specified in the Contract
Documents) or the safety precautions and programs incident to the work of CMAR.

30039962 B-2 3/17/2021

AARCADIS se

CONSULTANT'S efforts shall be directed toward advising the CITY whether the completed work
of CMAR will conform to the Contract Documents, but CONSULTANT shall not be responsible
for the failure of CMAR to perform the work in accordance with the Contract Documents.

On the basis of on-site examination of materials, equipment, and workmanship, CONSULTANT
shall keep CITY informed of the progress of the work, shall endeavor to protect the CITY against
defects and deficiencies in such work and may disapprove or reject work failing to conform to the
Contract Documents. This task shall include the following subtasks:

210.1

210.2

210.3

210.4

210.5

30039962

Project Management: The CONSULTANT shall perform overall Project Management of
the work, which consists of the administrative tasks necessary to maintain the overall
project budget and schedule and includes the preparation of and assembly of the monthly
reports and invoices. Under this task the CONSULTANT shall meet monthly with the
CITY’S representative to discuss the services, the costs associated with the cash flow
projections, and the schedule of services performed under this Scope of Work, and the
overall status, progress, and issues on the project.

Construction Procedures_and Communications: The CONSULTANT will utilize
existing construction procedures and communications established under GMP 1.

Attend Pre-Construction Conferences conducted by the CMAR: The CMAR shall
conduct Pre-Construction Conference for the work. The conference will be held in
accordance with the Contract Documents. At the conference, the CONSULTANT and
CMAR shall identify field services to be provided by the CONSULTANT, CMAR and
the CITY and discuss appropriate coordination procedures. The CMAR will conduct all
conferences, and shall prepare and distribute all meeting minutes.

Provide Construction Administration, Quality Assurance, and Coordination: The

CONSULTANT shall provide construction administration and quality assurance services
during the course of the project to advise of the overall technical correctness of the work
and construction services and that specified procedures are being followed and that the
project schedule is being met. The CONSULTANT shall provide coordination functions
during the construction phase as follows:

1. Hold required coordination meetings with CITY Representatives.

2. Coordinate the work of the CONSULTANT?’s specialty subconsultants assigned to
the project.

3. Participate in weekly construction progress meetings, conducted by the CMAR.

Perform Regulatory Agency Coordination: The CONSULTANT shall work with the
CITY’s staff and the CMAR to coordinate with regulatory agencies involved in the
completion of this project; the following regulatory agencies are anticipated:

1. Arizona Department of Environmental Quality (ADEQ)
2. Maricopa County Department of Environmental Services (MCDES)

B-3 3/17/2021

The CONSULTANT shall document all coordination and correspondence with the
agencies. The CONSULTANT shall prepare and submit requests for approval of
construction to MCDES for the work specified by the CITY under the Contract
Documents. Per MCESD, each approval of construction will contain the following, at a
minimum:

CONSULTANT'S Engineer’s Certificate of Completion

Equipment/Piping Test Summary

Operations and Maintenance Manual (one hard copy and one electronic copy)
Record Drawings

CONSULTANT's Startup Plan

wWPYenyr

210.6 Coordination with City Building Services Department: The CONSULTANT shall work
with the CMAR and CITY staff to coordinate with the Building Services Department in
the Completion of this project. This effort is based on the preparation of special
inspection certificates, providing special structural and electrical inspections for the
work, and preparing the required monthly reports.

210.7 Provide Project Documents: The CONSULTANT shall maintain and provide the
following detailed project records and documentation during the construction phase:

1. The project records shall include correspondence, schedules, submittal, test data,
project data, payments, allowance requests, meeting minutes, clarifications, digital
control system documentation and other such documentation the CONSULTANT
receives. Project records shall be delivered to the CITY upon completion of the
project. Records shall be maintained as defined under Section 400 of this Scope of
Work at the CMAR’s field office or electronically through a collaboration
website/software.

Task 215 Administer the Construction Schedule

Review the CMAR's As-Planned Progress Schedule Submittal: The CONSULTANT shall review
and critique the CMAR's As-Planned Progress Schedule submittal specific to completion. The
CONSULTANT shall examine the work sequence, durations, interim milestones and other
appropriate scheduling features in accordance with the requirements of the Contract Documents.
The CONSULTANT shall provide review comments and shall meet and discuss the schedule
comments with the CMAR, Subcontractors, and the CITY. The CONSULTANT shall review:

A. The logic diagram and mathematical tabulations

B. The narrative report

C. The resource loading

D. Schedule of Values and cost distribution as related to the resource loading

Review Monthly Progress Schedule Submittals: In accordance with the Contract Documents, the

CONSULTANT shall review the monthly updates to the CMAR’s Progress Schedule. The
CONSULTANT shall perform a review of progress accomplished during the month and compare

30039962 B-4 3/17/2021

@ARCADIS s"”

it to the as-planned schedule and discuss significant discrepancies at the Construction Progress
Meeting. CMAR and CONSULTANT shall establish, based on the data, the percent of completion
of each element of the schedule.

Task 220 Perform Site Visits

The CONSULTANT's design staff will make periodic site visits appropriate for the type of
construction at periods appropriate to the various stages of construction to observe, as an
experienced and qualified professional, the progress and quality of the executed work and to
determine in general if the work is proceeding in accordance with the design intent. The
CONSULTANT's Design Manager will periodically attend the Construction Progress Meetings
and make site visits to assist with field issues.

Task 230 Review Shop Drawings and Test Results

The CONSULTANT shall receive, review, evaluate, and distribute Shop Drawings, samples, test
results, and other data which CMAR is required to submit. The CONSULTANT's review shall
only be for conformance with the design concept of the Project and compliance with the
information given in the Contract Documents. Such review or other action shall not extend to
means, methods, sequences, techniques, or procedures of construction selected by CMAR, or to
safety precautions and programs incident thereto. The CONSULTANT shall receive and review
(for general contents as required by the Contract Documents) maintenance and operating schedules
and instructions, Operation and Maintenance Manuals, Lesson Plans, guarantees, bonds and
certificates of inspection which are to be assembled by CMAR in accordance with the Contract
Documents.

Task 240 _ Issue Interpretations and Clarifications

The CONSULTANT shall respond to the CMAR to clarify and/or interpret technical, design
related questions. Routine technical interpretations shall be responded to under Task 400. The
CONSULTANT shall assist the CITY, as required, in resolution of these issues. The
CONSULTANT shall respond to issues raised during construction regarding interpretation and
clarification of the contractual administrative and technical requirements of the Contract
Documents. Interpretations — Request for Information (RFI) and Engineer’s Clarifications (EC)
shall be issued to the CMAR under Task 400.

Task 245 Review Requests for Alterations

The CONSULTANT shall respond to the CMAR’s Request for Alterations (RFA’s). Routine
technical interpretations shall be responded to under Task 400. RFA’s shall be responded to under
this task. The CONSULTANT shall respond to requests for alterations requested by the CMAR
during the construction phase.

Task 250 Certify Progress Payments

The CONSULTANT shall inform the CITY of approval of the CMAR's Schedule of Values, after

30039962 B-5 3/17/2021

ARCADIS sii

any updates or adjustments have been made by the CMAR in accordance with the Contract
Documents. The monthly Progress Schedule update in combination with the CONSULTANT's
field observations and the progress schedule shall be used by the CONSULTANT to determine the
appropriateness of the CMAR's Application for Payment.

Based on CONSULTANT'S on-site observations, as an experienced and qualified professional,
and on review of Applications for Payment and the any accompanying data and schedules required
to review Applications for Payment, the CONSULTANT shall determine the amounts owed to the
CMAR and recommend, in writing, that payments to the CMAR in such amounts be submitted by
the CITY; such recommendations of payment will constitute a representation to the CITY, based
on such observations and review, that the work has progressed to the point indicated, that, to the
best of CONSULTANT's knowledge, information and belief, the quality of such work is in
accordance with the Construction Documents (subject to an evaluation of such work as a
functioning Project upon Substantial Completion, to the results of subsequent tests called for in
the Construction Documents, and to qualifications stated in the recommendation), and that
payment of the amount recommended from the review of the Application for Payment is due to
the CMAR.

Task 260 Substantial Completion and Final Acceptance Inspection

Following notice from the CMAR, the CONSULTANT shall conduct an inspection to determine
if the Project is substantially complete in accordance with the Contract Documents. If the CITY
and the CONSULTANT considers the work substantially complete, the CONSULTANT shall
deliver to the CITY and CMAR the Certificate of Substantial Completion and the punch list, the
date for completion of the punch list, and recommend the division of responsibilities between the
CITY and the CMAR.

Substantial Completion and Final Acceptance Inspection shall be done for the following
construction elements:

Site work excavation for the yard piping, primary sedimentation basin and pump station
Installation of the yard piping, primary sedimentation basin structure and pump station
structure

Installation of the primary sedimentation basin mechanical and electrical elements
Installation of the pump station mechanical and electrical elements

Instrumentation and Controls upgrades

Services by the CMAR as described in SECTION 500 - SPECIAL SERVICES

All remaining work, site work, and site improvements

O=™MOO BD

It is anticipated that the final punch list correction period shall occur during a thirty (30) day
period immediately following the Substantial Completion Inspection associated with each
construction element.

The CONSULTANT shall, upon completion of the punch list items, make final inspection to

determine if the finished work has been completed to the standard required by the Contract
Documents, and CMAR has fulfilled the obligations thereunder so that CONSULTANT may

30039962 B-6 3/17/2021

Design & Consultancy
for natural and
buitt assets

recommend, in writing, final payment to CMAR and may give written notice to CITY and the
CMAR that the work is acceptable subject to conditions therein expressed.

CONSULTANT shall not be responsible for the acts or omissions of the CMAR or any of the
CMAR's Subcontractor's, agents or employees or any other persons (except CONSULTANT'S
own employees and agents) at the site or otherwise performing any of the CMAR's work; however,
nothing contained in Tasks 210 through 260, inclusive, shall be construed to release
CONSULTANT from liability for negligent acts, errors or omissions in the performance of
CONSULTANT's duties in accordance with this Scope of Work.

SECTION 300 - ENGINEERING SERVICES DURING CONSTRUCTION
Task 310 Surveying

The CONSULTANT shall coordinate surveying services as specified as being performed by the
CITY or CMAR in the Contract Documents. This includes:

A. Verifying the CMAR's understanding of the plant grid system and the existing horizontal and
vertical controls used to locate and layout the project.
B. Coordination with the CMAR's surveyor during the construction of the project.

All survey services will be performed by CMAR.
Task 320 Changes

The CONSULTANT shall perform services in connection with allowance requests to reflect
changes requested by CITY or CMAR, for evaluating substitutions proposed by CMAR and in
making revisions to Drawings and Specifications occasioned thereby, and resulting from
significant delays, changes or price increases occurring as a direct or indirect result of material or
equipment shortages. Changes and RFA’s shall be limited to the scope of the Project as defined
by the Contract Documents or additional work as may be requested by the CITY. The
CONSULTANT shall prepare drawings, details and specifications needed to describe the change.
The CONSULTANT shall prepare an estimate of the cost and time impact of the change and
conduct negotiations with the CMAR in conjunction with the CITY.

Task 330 Material Testing

The CONSULTANT shall coordinate materials inspection and testing services as required to be
performed by the CITY in the Contract Documents.

The CITY will provide the services of a Professional Construction Materials Inspection and
Testing Laboratory that meets ASTM E 329 requirements. Inspection and testing shall be
coordinated with the construction schedule. Testing and inspection services shall include
placement inspection and testing of compacted select fill and backfill, ordinary backfill, paving
base, pavement subgrade, and subgrade courses; asphaltic concrete pavement inspection and field
density tests and concrete testing and inspection. Samples for testing shall be collected from the

30039962 B-7 3/17/2021

construction site and delivered to the on-site laboratory. The laboratory shall provide a
construction materials technician (technicians) to perform the field construction materials
inspection and field-testing services herein outlined.

CONSULTANT shall review laboratory reports and reports of inspection and testing activities
describing the tests and inspections made. Written reports of all testing results, which identify the
required data and identify conformance or non-conformance with the Contract Document shall be
maintained by the CONSULTANT and provided to the CITY at the completion of the project.

SECTION 400 - OBSERVATION SERVICES DURING CONSTRUCTION

The CONSULTANT shall provide appropriate personnel and expertise in order to observe
performance of the work of the CMAR. Through increased on-site observations of the work in
progress and field checks of materials and equipment by CONSULTANT staff, CONSULTANT
shall endeavor to provide further protection for CITY against defects and deficiencies in the work
of CMAR; but the furnishing of such representation will not make CONSULTANT responsible
for construction means, methods, techniques, sequences or procedures, or for safety precautions
or programs, or for CMAR failure to perform the work in accordance with the Contract
Documents.

CONSULTANT’ onsite observers shall not:

A. Authorize any deviations from the Contract Documents or approve any substitute materials
or equipment which may impact cost, time, or design intent without approval from the CITY.

B. Undertake the responsibilities of CMAR, Subcontractors or CMAR's superintendent, or
expedite the work.

C. Advise on or issue directions relative to the means, methods, techniques, sequences, or
procedures of construction unless such is specifically called for in the Contract Documents.

D. Advise on or issue directions as to safety precautions and programs in connection with the
work.

E. Advise the CITY to occupy and/or start-up equipment which may have been impacted by the
Project in whole or in part, outside of the terms stated in Task 465 Substantial Completion.

F. Remain located permanently onsite. CONSULTANT staff will attend weekly meetings and
inspections as required by Contract Documents, CONSULTANT will be on-site part-time
for scheduled inspections and meetings only (this is not a full-time position, but periodic
onsite observation for confirmation of compliance with the Contract Documents).

G. The CONSULTANT will not approve changes to any equipment or material for which the

Contract Documents required a Pre-Bid approval for such a change unless approved by the
CITY.

30039962 B-8 3/17/2021

ARCADIS sss”

H. The CONSULTANT will not deliver to the CITY a set of indexed shop drawings.
CONSULTANT’s dealings in matters pertaining to the on-site work shall in general be only with
CITY and CMAR, and dealings with CMAR or Subcontractors shall only be through or with the
full knowledge of CMAR.

CONSULTANT shall be responsible for performing the following tasks:

Task 405 Schedules

Review the Progress Schedule, schedule of CMAR's submittal and Schedule of Values prepared
by CMAR, and consult with CITY concerning their acceptability.

Task 410 Meetings and Conferences

Attend Pre-Construction Conferences as described under Task 210.3. Attend Weekly Construction
Progress Meetings.

Task 415 = Liaison

A. Serve as CONSULTANT'S liaison with CMAR, working principally through CMAR's
Project Manager and assist the Project Manager in understanding the intent of the Contract
Documents. Serve as CITY'S liaison with CMAR, in support of CMAR's coordination of
construction operations that affect CITY'S operations.

B. Assist in obtaining from CITY additional details or information, when required at the job site
for proper execution of the work.

Task 420 Shop Drawings and Samples

A. Submittals which are furnished by CMAR shall be received and reviewed as defined in Task
230.

B. Advise CITY prior to the commencement of work requiring a Shop Drawing or sample
submission if the submission has not been approved and inform the CMAR.

Task 425 Review of Work, Rejection of Defective Work, Inspections and Tests

A. Conduct on-site observations of the work in progress to assist CONSULTANT in determining
if the work is proceeding in accordance with the Contract Documents and that completed
work conforms to the Contract Documents.

B. Report to CITY whenever it is believed that work is unsatisfactory, faulty, defective or does
not conform to the Contract Documents, or does not meet the requirements of inspections,
tests or approval required to be made, or has been damaged prior to final payment; and advise
CITY in writing when it is believed work should be corrected or rejected or should be

30039962 B-9 3/17/2021

@ARCADIS se"

uncovered for observation, or requires special testing, inspection or approval.

C. Verify that tests, equipment, and systems start-up and operating and maintenance instructions
are conducted as required by the Contract Documents and in presence of the required
personnel, and that CMAR maintains required records thereof; observe, record and report to
CONSULTANT appropriate details relative to the test procedures and start-ups. Conduct
field checks to ensure that Shop Drawings have been approved for equipment that is being
installed and verify that installers are using the approved Shop Drawings.

D. Accompany visiting inspectors representing public or other agencies having jurisdiction over
the Project, record the outcome of these inspections and report to CITY.

Task 430 Interpretation of Contract Documents

Receive and transmit all clarifications and interpretations of the Contract Documents, to/from the
CMAR and CITY as described above.

Task 435 =‘ Field Alteration and Verification
Receive, review, and respond to the CMAR’s RFA’s and confirmation of Field Order agreements.
Task 440 Changes

Consider and evaluate CMAR’s suggestions for changes in drawings or specifications and report
them with recommendations to CITY. Notify the CITY's Representative of any changes or
alterations believed to be in the CITY'S best interest.

Task 445 ~—- Records

A. Maintain orderly files for correspondence, reports of job conferences, Shop Drawings and
samples submissions, reproductions of original Contract Documents including all Addenda,
Allowance Requests, Field Orders, additional Drawings issued subsequent to the execution
of the Contract, CONSULTANT's clarifications and interpretations of the Contract
Documents, progress reports and other Project related documents.

B. Prepare observation reports recording CMAR and Subcontractors work performed on the job
site, major construction equipment on-site, conditions, data relative to questions of extras or
deductions, list of visiting officials and representatives of manufacturers, fabricators,
suppliers and distributors, daily activities, decisions, on-site equipment, Subcontractors on-
site, observations in general and specific observations in detail as in the case of observing test
procedures.

C. Record names, addresses and telephone numbers of the CMAR, subcontractors and major
suppliers of materials and equipment.

D. Maintain notes to be capable of cross-referencing the CMAR's record drawing information

30039962 B-10 3/17/2021

MARCADIS sx

for accuracy and completeness.
E. Receive, review and process testing reports.

F. The CONSULTANT will maintain a weekly digital photo file of the progress of the
construction activities throughout the duration of the project as required to capture key aspects
of the CMAR’s work. This photo file will consist of color digital photographs taken to
document specific construction activities that may be of value to future modifications to the
facility. The photographs will be labeled as to the subject and date of the photo and the photos
will be kept in file folders, which have been formatted to represent the specific construction
area of the project.

G. The CONSULTANT will inspect the CMAR's marked up record drawings weekly, to
determine if the mark-ups are up to date and reflect the record condition of the Work. If
deficiencies are evident, CONSULTANT will provide written notification of said deficiencies
to CMAR and will recommend to the CITY the withholding of appropriate payments to the
CMAR.

Task 450 Reports

A. The CONSULTANT shall furnish the CITY a Job Status Report shall identify the following
items:

1. Important dates
2. Specific project issues
3. Identify pending meetings and their topics

B. CONSULTANT shall consult with CITY in advance of scheduled major tests, inspections or
start of important phases of the work.

C. CONSULTANT shall report immediately to CITY upon the occurrence of any accident.
Task 455 Payment Application

Review applications for payment as described in Task 250 with CMAR for compliance with the
established procedure for their submission and forward them with recommendations to CITY,
noting particularly their relation to the Schedule of Values, work completed, and materials and
equipment delivered at the site but not incorporated in the work.

Task 460 Certificates, Maintenance and Operation Manuals

During the course of the work, review and determine that certificates, Operation and Maintenance
Manuals and other data required to be assembled and furnished by CMAR are applicable to the
items actually installed; and deliver this material to CITY following CONSULTANT’s review
prior to final acceptance of the work. The CMAR will develop, with assistance from the
CONSULTANT and CITY, an indexing and volume identification system for all Operation and

30039962 B-11 3/17/2021

@MARCADIS see"

Maintenance Manuals.
Task 465 Substantial Completion and Final Acceptance

A. Before CONSULTANT issues a Certificate of Substantial Completion, submit to CMAR a
list of observed items requiring completion or correction in accordance with the requirements
of the Contract Documents.

B. After the CMAR has completed the work and upon request of the CMAR, the
CONSULTANT shall conduct final inspection in the company of CITY and CMAR. Prepare
a final list of items to be completed or corrected in accordance with the requirements of the
Construction Documents.

C. After the CMAR has completed the work and upon written notice from the CMAR, review
and determine that items on final list have been completed or corrected and make
recommendations to CITY concerning acceptance.

SECTION 500 - SPECIAL SERVICES

Task 510 Warranty

The CONSULTANT will provide services after completion of the Construction Phase, such as
inspections during the 24-month guarantee/warranty period, reporting observed discrepancies
under guarantees called for in the Contract Documents, and provide assistance for resolution of
defects to be corrected under warranty.

Task 520 Electronic Operations and Maintenance Manuals (EOMM)
Under this Scope of Services, the CONSULTANT will update existing West Area Water
Reclamation Facility Electronic Operations and Maintenance Manuals (EOMM) content to reflect
modifications to existing facilities.
The existing EOMM chapters to be updated include:

1. Preliminary Treatment

2. Support Systems

3. Electrical Distribution and Power Supply

Each chapter for the major systems will consist of the following sections:

e Background e Design Criteria
e Theory e Troubleshooting
© Operating Strategies e Safety

e Equipment & Control Description e Alarms

e Procedures e Figures

30039962 B-12 3/17/2021

A ARCADI frre ;

The West Area Water Reclamation Facility EOMM will cover other operational basics: design
criteria, intended operation of the processes, start-up, shutdown, monitoring and troubleshooting
procedures; alternate operations modes; and special process safety considerations. Standard
monitoring procedures will be included to cover required monitoring for odor control effluent
quality. These procedures will be field verified by the CONSULTANT with assistance from the
Plant Staff.

The West Area Water Reclamation Facility EOMM will be developed for integration with the
CITY’s existing Lucity asset management database, per CITY requirements. The CONSULTANT
will assist the CITY in developing methods to link information associated with the EOMM to the
Lucity asset management database. The CITY will provide the asset management database
requirements at the project kickoff meeting.

Up to two (2) workshops will be held with the CITY prior to content development activities to
provide an overview of the content to be developed, to identify key CITY staff to review draft
chapters, and to establish a review schedule. The CITY will be provided with interim deliverables
of completed EOMM sections as the construction of major areas of the plant are completed. As
each chapter is completed, the CONSULTANT will submit draft chapters to the City for their
review and comment over a two-week period. The CITY will provide comments to the
CONSULTANT for the CONSULTANT to incorporate into the final documents. The interim
deliverables will be installed and operational on the CITY’s server prior to start-up of these
facilities. A schedule for the interim deliverables will be provided to the CITY at the start of the
project.

Before submitting the final version of the EOMM and transferring to the CITY, the
CONSULTANT will conduct a detailed final validation and field verification process. Through
this critical quality control activity, the CONSULTANT will verify that:

1. Content has been field-verified and checked at the installation.

2. All photographs are current and are reflective of well-maintained and clean conditions.

3. All relevant documentation, such as scanned documents, figures and drawings are
appropriately categorized for insertion into the database.

4. SOPs are accurate and reflect actual as-operated conditions.

The CONSULTANT will also assist in the installation and configuration of the EOMM on the
CITY’s server and conform to CITY standards for Lucity developed during the content
development workshops.

Task 530 = Training

The CONSULTANT shall review the CMAR's training plan and instruction materials for
compliance with contract documents. The CMAR or manufacturer training presentations shall be
scheduled and coordinated with CITY personnel and facility operation. CONSULTANT shall
provide instruction to CITY personnel on the project objectives, design intent, and system
operational procedures.

30039962 B-13 3/17/2021

ARCADIS iss

Specific training services shall consist of the following:
A. CMAR's and Manufacturer's training.

1. CONSULTANT shall coordinate and monitor the CMAR's and Manufacturer's training
of the CITY'S personnel.

a. Discuss the preliminary course and lesson plan development with the CMAR and the
manufacturer. One meeting shall be held with CITY'S Staff and the CMAR for this
discussion.

b. Review and approve lesson plans and course materials.

Liaison between CITY and CMAR.
d. Monitor Training Sessions.

1) Monitor attendance

2) Evaluate course

3) Assist classroom discussions

9

Task 540 Commissioning

The CONSULTANT shall assist the CITY with during commissioning of the facilities.
(Commissioning is defined as the process in which the newly constructed facilities are placed into
routine operation.) The commissioning process will include the CMAR’s planned, systematic
approach to verify that facility systems operate as intended and there is an orderly transition from
construction through start-up to routine operation. The CONSULTANT shall witness CMAR
equipment testing and performance testing; review CMAR’s start-up planning, systems start-up,
operation and troubleshooting; and monitor CMAR’s transition support to CITY operations to
ensure a properly operating and performing system at the completion of the commissioning
process.

The Commissioning process progresses along three general phases, as follows:

1. PhaseI - Equipment Testing and Systems Performance Testing

2. Phase II - Start-up and Transition Planning

3. Phase III - Start-up, Initial Operation and Transition of Major Systems by CMAR to
CITY

The following equipment will be commissioned, once they are substantially completed by the
CMAR:

Process Control Slide Gates

Primary Sedimentation Basin Mechanical Elements
Progressive Cavity Sludge Pumps

Inline Grinders

Sump Pumps

WYN >

Once all newly constructed facilities are substantially completed by the CMAR, completed
facilities be commissioned by CMAR to demonstrate that the facility meets the design treatment

30039962 B-14 3/17/2021

ARCADIS se

capacity and effluent quality parameters established by the CONSULTANT during detailed design
development.

The CONSULTANT shall provide operations and technical assistance during the commissioning
process under the overall direction of the CITY. The CONSULTANT will act as the CITY’s agent
during the commissioning process under the direct guidance of CITY operations staff. The CMAR
will be responsible for all equipment and systems maintenance during the commissioning process.
The CITY shall assume full responsibility for compliance with all permits and other regulatory
and policy requirements during the commissioning process. The CITY will provide all analytical
testing and process chemicals.

Phase I - Equipment Testing and Systems Performance Testing

The CONSULTANT shall witness equipment testing and performance testing by the CMAR for
each system listed above. The CONSULTANT shall:

A. Observe and develop a detailed understanding of the operating characteristics of the equipment
and systems.

B. Verify the testing process is conducted in accordance with intended operating practices during
Commissioning.

C. Identify if specific operating and monitoring requirements are to be used during Start-up and
initial operation.

The testing by CMAR will provide CONSULTANT and CITY with detailed understanding of
system performance characteristics, operating requirements, and monitoring needs during start-up
and operation under the direction of the CITY.

Phase II - Start-up and Transition Planning

The CMAR, shall prepare a detailed start-up and transition plan to facilitate smooth and orderly
placing of new facilities into service through their initial operation and successful transition to the
CITY. The start-up and transition plan shall be developed with assistance from CONSULTANT
and CITY staff. The start-up and transition plan shall include prestart-up checklists and required
conditions; identification of impacts to other processes; analytical testing and sampling
requirements, start-up procedures; health and safety equipment requirements; monitoring
equipment requirements; roles and responsibilities and staffing requirements of CITY and the
CMAR. The start-up and transition plan shall also include training requirements, and an estimated
timeline of the start-up, initial operation, and transition process.

Phase III - Start-Up, Initial Operation and Transition of Major Systems
The purpose of Phase III is for CMAR’s start-up of new facilities and verification of their

successful function in manual and computer-control modes. — Phase III will consist of the
following activities:

30039962 B-15 3/17/2021