PowerPoint Presentation (Updated on 10/22/21)

City of Glendale — Regular Meeting (2021-10-26)

View PDF Item 3 Meeting page

Extracted text (via pymupdf) 2927 characters
CIOSI: Gate Standards for Alley Access Control 
Program

Presentation Overview
•Background
•Alley Access Control Program
•Review of Other City’s Gate and Service 
Standards
•Discussion of Options With Cost
•Staff Recommendation
2

Background
3
•May 11, 2021, CIOSI Requested by Council Member 
Turner
•June 22, 2021, Council Workshop
–Purpose: To get Council direction on staff expanding the gates standards 
created as part of the Alley Access Control Program as well as funding 
options.

Alley Access Control History
• CIOSI – March 2016 requested by Council Member Aldama
• Workshop June 2016
• Pilot Program
• Alley Program
• Alley Gating To Date
• Alley Service Levels
4

Approved Alley Access Control Gate
5

6
Location of Alleys
Gated -
Not Gated -
YUCCA
*Map 1 of 3

7
Location of Alleys
Not Gated -
*Map 2 of 3

8
Location of Alleys
Gated -
Not Gated -
YUCCA
*Map 3 of 3

Alley Access Control Challenges
•Gates Unlocked
•Outreach in 2020 due to COVID
•Some Gate Locations
9

Modified/Recessed Gate Location Candidates
10
2-Foot Wall 
6-Foot Wall

Gate Placement Option
11
Parking Lot for Apartments
Gate Location

Alleys Not Program Candidates
12

Alleys Not Program Candidates
13

Review of Other City Programs

Avondale
15

Mesa
16

Gilbert
17

Tolleson
18

Phoenix (Pilot Program)
19

Summary of Other City’s Standards
•Same standard of gate used throughout program
•Secured with chains and locks (padlock - key or combination)
•Colors used (none, brown, green, black) 
20

Costs

Current Cost Per Alley
Chain Link Double Swing Gate at both ends 
of alley segment - $4,200
• ~$194,000 to complete program if all 
alleys gated
22

Cost Difference Per Alley
Colored - Chain Link - $5,300
~$1,100 Additional Cost Over Existing Standard
~$240,000 If Chosen To Upgrade Existing Gates
~$242,000 for 46 Possible Future Segments
~$482,000 Total Cost for Upgrade & Future
23

Cost Difference Per Alley
Ornamental Iron - $5,900
~$1,700 Additional Cost
~$266,00 Upgrade Existing Gates
~$272,000 for 46 Possible Future Segments
~$538,000 Total Cost for Upgrade & Future
24

Cost Difference Per Alley
Custom – estimated $8,200
~$4,000 Additional Cost
~$369,000 Upgrade Existing Gates
~$378,000 for 46 Possible Future Segments
~$747,000 Total Cost for Upgrade & Future
25

Gate Options Summary
26
Ornamental
$5,900 Per Segment
~$538,000 Upgrade & Future
~$359,000 Increase From     
Current Standard
Colored Chain
$5,300 Per Segment
~$482,000 Upgrade & Future
~$288,000 Increase From            
Current Standard
Current Standard
$4,200 Per Alley Segment
~$194,000 To Complete Program
Custom
$8,200 Per Segment
~$747,000 Upgrade & Future
~$553,000 Increase From     
Current Standard

Funding Options

Options to Fund Upgraded Gates
28
•City Budgeted
•Council District Funds
•Neighborhood Contribution

Staff Recommendations
29
•Provide a consistent standard across city
•Continue program with current existing gate standard