AGREEMENT FOR 
DEZURIK, KROHNE AND REXA EQUIPMENT, PARTS & SERVICES 
City of Glendale Sole Source 
This Agreement for Dezurik, Krohne and Rexa Equipment, Parts & Services ("Agreement") is effective and entered 
into between CI1Y OF GLENDALE, an Arizona municipal corporation ("City"), and Industrial Automation 
Services, Inc., an Arizona Corporation, authorized to do business in Arizona, (the "Contractor"), as of the    2022. 
RECITALS 
A.
City intends to undertake a project for the benefit of the public and with public funds that is more fully set
forth in Exhibit A, (the "Project");
B.
City desires to retain the services of Contractor to perform those specific duties and produce the specific
work as set forth in the Project attached hereto;
C.
City and Contractor desire to memorialize their agreement with this document.
AGREEMENT 
In consideration of the Recitals, which are confirmed as true and correct and incorporated by this reference, the 
mutual promises and covenants contained in this Agreement, and other good and valuable consideration, City and 
Contractor agree as follows; 
1.
Key Personnel; Sub-contractors.
1.1 
Services. Contractor will provide all services necessary to assure the Project is completed timely 
and efficiently consistent with Project requirements, including, but not limited to, working in close 
interaction and interfacing with City and its designated employees, and working closely with others, 
including other contractors or consultants, retained by City. 
1.2 
Project Team. 
a.
Project Manager.
(1)
Contractor will designate an employee as Project Manager with sufficient training,
knowledge, and experience to, in the City's option, complete the Project and
handle all aspects of the Project such that the work produced by Contractor is
consistent with applicable standards as detailed in this Agreement;
(2)
The City must approve the designated Project Manager; and
(3)
To assure the Project schedule is met, Project Manager may be required to devote
no less than a specific amount of time as set out in Exhibit A.
b.
Project Team.
(1)
The Project Manager and all other employees assigned to the project by
Contractor will comprise the "Project Team."
(2)
Project Manager will have responsibility for and will supervise all other employees
assigned to the Project by Contractor.
c.
Discharge, Reassign, Replacement.
(1)
Contractor acknowledges the Project Team is comprised of the same persons and
roles for each as may have been identified in the response to the Project's
solicitation.