Arcadis Agreement

City of Glendale — Regular Meeting (2022-01-11)

View PDF Item 26 Meeting page

Extracted text (via pymupdf) 211852 characters
1 
4/29/2021 
C      
PROFESSIONAL SERVICES AGREEMENT 
WATER METER REPLACEMENT CONSULTANT 
City of Glendale Solicitation No. RFP 21-52 
This Professional Services Agreement ("Agreement") is entered into and effective between CITY OF GLENDALE, 
an Arizona municipal corporation ("City") and Arcadis U.S., Inc., a Delaware corporation, 
authorized to do business in the State of Arizona,("Consultant") as of the _____ day of _________________, 
20      (“Effective Date”). 
RECITALS 
A. 
City intends to undertake a project for the benefit of the public and with public funds that is more fully set 
forth in Exhibit A, Project (the "Project"); 
B. 
City desires to retain the professional services of Consultant to perform certain specific duties and produce 
the specific work as set forth in the attached Exhibit B, Project Scope of Work (“Scope”); 
C. 
Consultant desires to provide City with professional services (“Services”) consistent with best consulting or 
architectural practices and the standards set forth in this Agreement, in order to complete the Project; and 
D. 
City and Consultant desire to memorialize their agreement with this document. 
AGREEMENT 
The parties hereby agree as follows: 
1. 
Key Personnel; Other Consultants and Subcontractors. 
1.1 
Professional Services.  Consultant will provide all Services necessary to assure the Project is 
completed timely and efficiently consistent within Project requirements, including, but not limited 
to, working in close interaction and interfacing with City and its designated employees, and working 
closely with others, including other consultants or contractors, retained by City. 
1.2 
Project Team. 
a. 
Project Manager. 
(1) 
Consultant will designate an employee as Project Manager with sufficient training, 
knowledge, and experience to, in the City's opinion, complete the project and 
handle all aspects of the Project such that the work produced by Consultant is 
consistent with applicable standards as detailed in this Agreement; and 
(2) 
The City must approve the designated Project Manager. 
b. 
Project Team. 
(1) 
The Project Manager and all other employees assigned to the Project by 
Consultant will comprise the "Project Team." 
(2) 
Project Manager will have responsibility for and will supervise all other employees 
assigned to the Project by Consultant. 
c. 
Discharge, Reassign, Replacement. 
(1) 
Consultant acknowledges the Project Team is comprised of the same persons and 
roles for each as may have been identified in Exhibit A. 
(2) 
Consultant will not discharge, reassign, replace or diminish the responsibilities of 
any of the employees assigned to the Project who have been approved by City 
without City's prior written consent unless that person leaves the employment of 
Consultant, in which event the substitute must first be approved in writing by City.

2 
4/29/2021 
(3) 
Consultant will change any of the members of the Project Team at the City's 
request if an employee's performance does not equal or exceed the level of 
competence that the City may reasonably expect of a person performing those 
duties, or if the acts or omissions of that person are detrimental to the 
development of the Project. 
d. 
Subcontractors. 
(1) 
Consultant may engage specific technical contractors (each a "Subcontractor") to 
furnish certain service functions. 
(2) 
Consultant will remain fully responsible for Subcontractor's services. 
(3) 
Subcontractors must be approved by the City. 
(4) 
Consultant will certify by letter that all contracts with Subcontractors have been 
executed incorporating requirements and standards as set forth in this Agreement. 
2. 
Schedule.  The Services will be undertaken in a manner that ensures the Project is completed timely and 
efficiently in accordance with the Project. 
3. 
Consultant’s Work. 
3.1 
Standard.  Consultant must perform Services in accordance with the standards of due diligence, 
care, and quality prevailing among consultants having substantial experience with the successful 
furnishing of Services for projects that are equivalent in size, scope, quality, and other criteria under 
the Project and identified in this Agreement. 
3.2 
Licensing.  Consultant warrants that: 
a. 
Consultant and its Subconsultants or Subcontractors will hold all appropriate and required 
licenses, registrations and other approvals necessary for the lawful furnishing of Services 
("Approvals"); and 
b. 
Neither Consultant nor any Subconsultant or Subcontractor has been debarred or 
otherwise legally excluded from contracting with any federal, state, or local governmental 
entity ("Debarment"). 
(1) 
City is under no obligation to ascertain or confirm the existence or issuance of any 
Approvals or Debarments, or to examine Consultant's contracting ability. 
(2) 
Consultant must notify City immediately if any Approvals or Debarment changes 
during the Agreement's duration. The failure of the Consultant to notify City as 
required will constitute a material default under the Agreement. 
3.3 
Compliance.   
a. 
Services will be furnished in compliance with applicable federal, state, county and local 
statutes, rules, regulations, ordinances, building codes, life safety codes, and other 
standards and criteria designated by City. 
b. 
Consultant must not discriminate against any employee or applicant for employment on 
the basis of race, color, religion, sex, national origin, age, marital status, sexual orientation, 
gender identity or expression, genetic characteristics, familial status, U.S. military veteran 
status or any disability.  Consultant will require any Sub-contractor to be bound to the 
same requirements as stated within this section.  Consultant, and on behalf of any 
subcontractors, warrants compliance with this section. 
3.4 
Coordination; Interaction. 
a. 
For projects that the City believes requires the coordination of various professional 
services, Consultant will work in close consultation with City to proactively interact with

3 
4/29/2021 
any other professionals retained by City on the Project ("Coordinating Project 
Professionals"). 
b. 
Consultant will meet to review the Project, Schedule and in-progress work with 
Coordinating Project Professionals and City as often and for durations as City reasonably 
considers necessary in order to ensure the timely work delivery and Project completion. 
c. 
For projects not involving Coordinating Project Professionals, Consultant will proactively 
interact with any other contractors when directed by City to obtain or disseminate timely 
information for the proper execution of the Project. 
3.5 
Work Product. 
a. 
Ownership.  Upon receipt of payment for Services furnished, Consultant grants to City, 
and will cause its Subconsultants or Subcontractors to grant to the City, the exclusive 
ownership of and all copyrights, if any, to evaluations, reports, drawings, specifications, 
project manuals, surveys, estimates, reviews, minutes, all "architectural work" as defined in 
the United States Copyright Act, 17 U.S.C § 101, et seq., and other intellectual work product 
as may be applicable ("Work Product"). 
(1) 
This grant is effective whether the Work Product is on paper (e.g., a "hard copy"), 
in electronic format, or in some other form. 
(2) 
Consultant warrants, and agrees to indemnify, hold harmless and defend City for, 
from and against any claim that any Work Product infringes on third-party 
proprietary interests. 
b. 
Delivery.  Consultant will deliver to City copies of the preliminary and completed Work 
Product promptly as they are prepared. 
c. 
City Use. 
(1) 
City may reuse the Work Product at its sole discretion. 
(2) 
In the event the Work Product is used for another project without further 
consultations with Consultant, the City agrees to indemnify and hold Consultant 
harmless from any claim arising out of the Work Product. 
(3) 
In such case, City will also remove any seal and title block from the Work Product. 
4. 
Compensation for the Project. 
4.1 
Compensation.  Consultant's compensation for the Project, including those furnished by its 
Subconsultants or Subcontractors will not exceed $765,398.40 as specifically detailed in Exhibit D 
("Compensation"). 
4.2 
Change in Scope of Project.  The Compensation may be equitably adjusted if the originally 
contemplated Scope as outlined in the Project is significantly modified. 
a. 
Adjustments to Compensation require a written amendment to this Agreement and may 
require City Council approval. 
b. 
Additional services which are outside the Scope of the Project contained in this Agreement 
may not be performed by the Consultant without prior written authorization from the City. 
c. 
Notwithstanding the incorporation of the Exhibits to this Agreement by reference, should 
any conflict arise between the provisions of this Agreement and the provisions found in 
the Exhibits and accompanying attachments, the provisions of this Agreement shall take 
priority and govern the conduct of the parties. 
4.3 
Allowances.  An “Allowance” may be identified in Exhibit D only for work that is required by the 
Scope and the value of which cannot reasonably be quantified at the time of this Agreement.

4 
4/29/2021 
a. 
As stated in Sec. 4.1 above, the Compensation must incorporate all Allowance amounts 
identified in Exhibit D and any unused allowance at the completion of the Project will 
remain with City. 
b. 
Consultant may not add any mark-up for work identified as an Allowance and which is to 
be performed by a Subconsultant. 
c. 
Consultant will not use any portion of an Allowance without prior written authorization 
from the City. 
d. 
Examples of Allowance items include, but are not limited to, subsurface pothole 
investigations, survey, geotechnical investigations, public participation, radio path studies 
and material testing. 
4.4 
Expenses.  City will reimburse Consultant for certain out-of-pocket expenses necessarily incurred 
by Consultant in connection with this Agreement, without mark-up (the “Reimbursable 
Expenses”), including, but not limited to, document reproduction, materials for book preparation, 
postage, courier and overnight delivery costs incurred with Federal Express or similar carriers, 
travel and car mileage, subject to the following: 
a. 
Mileage, airfare, lodging and other travel expenses will be reimbursable only to the extent 
these would, if incurred, be reimbursed to City of Glendale personnel under its policies 
and procedures for business travel expense reimbursement made available to Consultant 
for review prior to the Agreement’s execution, and which policies and procedures will be 
furnished to Consultant; 
b. 
The Reimbursable Expenses in this section are approved in advance by City in writing; and 
c. 
The total of all Reimbursable Expenses paid to Consultant in connection with this 
Agreement will not exceed the “not to exceed” amount identified for Reimbursable 
Services in the Compensation. 
5. 
Billings and Payment. 
5.1 
Applications. 
a. 
Consultant will submit monthly invoices (each, a "Payment Application") to City's Project 
Manager and City will remit payments based upon the Payment Application as stated 
below. 
b. 
The period covered by each Payment Application will be one calendar month ending on 
the last day of the month. 
5.2 
Payment. 
a. 
After a full and complete Payment Application is received, City will process and remit 
payment within 30 days. 
b. 
Payment may be subject to or conditioned upon City's receipt of: 
(1) 
Completed work generated by Consultant and its Subconsultants and 
Subcontractors; and 
(2) 
Unconditional waivers and releases on final payment from all Subconsultants and 
Subcontractors as City may reasonably request to assure the Project will be free of 
claims arising from required performances under this Agreement. 
5.3 
Review and Withholding.  City's Project Manager will timely review and certify Payment 
Applications. 
a. 
If the Payment Application is rejected, the Project Manager will issue a written listing of 
the items not approved for payment.

5 
4/29/2021 
b. 
City may withhold an amount sufficient to pay expenses that City reasonably expects to 
incur in correcting the deficiency or deficiencies rejected for payment. 
6. 
Termination. 
6.1 
For Convenience.  City may terminate this Agreement for convenience, without cause, by 
delivering a written termination notice stating the effective termination date, which may not be less 
than 15 days following the date of delivery. 
a. 
Consultant will be equitably compensated for Services furnished prior to receipt of the 
termination notice and for reasonable costs incurred. 
b. 
Consultant will also be similarly compensated for any approved effort expended, and 
approved costs incurred, that are directly associated with Project closeout and delivery of 
the required items to the City. 
6.2 
For Cause.  City may terminate this Agreement for cause if Consultant fails to cure any breach of 
this Agreement within seven days after receipt of written notice specifying the breach. 
a. 
Consultant will not be entitled to further payment until after City has determined its 
damages. If City's damages resulting from the breach, as determined by City, are less than 
the equitable amount due but not paid Consultant for Services furnished, City will pay the 
amount due to Consultant, less City's damages, in accordance with the provision of Sec. 5. 
b. 
If City's direct damages exceed amounts otherwise due to Consultant, Consultant must pay 
the difference to City immediately upon demand; however, Consultant will not be subject 
to consequential damages more than $1,000,000 or the amount of this Agreement, 
whichever is greater. 
7. 
Conflict.  Consultant acknowledges this Agreement is subject to A.R.S. § 38-511, which allows for 
cancellation of this Agreement in the event any person who is significantly involved in initiating, 
negotiating, securing, drafting, or creating the Agreement on City's behalf is also an employee, agent, or 
consultant of any other party to this Agreement. 
8. 
Insurance.  For the duration of the term of this Agreement, Consultant shall procure and maintain 
insurance against claims for injuries to persons or damages to property which may arise from or in 
connection with the performance of all tasks or work necessary to complete the Project as herein defined. 
Such insurance shall cover Consultant, its agent(s), representative(s), employee(s) and any subcontractors. 
8.1 
Minimum Scope and Limit of Insurance.  Coverage must be at least as broad as: 
a. 
Commercial General Liability (CGL):  Insurance Services Office Form CG 00 01, 
including products and completed operations, with limits of no less than $1,000,000 per 
occurrence for bodily injury, personal injury, and property damage. If a general aggregate 
limit applies, either the general aggregate limit shall apply separately to this project/location 
or the general aggregate limit shall be twice the required occurrence limit. 
b. 
Automobile Liability:  Insurance Services Office Form Number CA 0001 covering Code 1 
(any auto), with limits no less than $1,000,000 per accident for bodily injury and property 
damage. 
c. 
Professional Liability.   Consultant must maintain a Professional Liability insurance 
covering errors and omissions arising out of the work or services performed by Consultant, 
or anyone employed by Consultant, or anyone for whose acts, mistakes, errors and 
omissions Consultant is legally liability, with a liability insurance limit of $1,000,000 for 
each claim and a $1,000,000 annual aggregate limit. 
d. 
Worker’s Compensation:  Insurance as required by the State of Arizona, with Statutory 
Limits, and Employers’ Liability insurance with a limit of no less than $1,000,000 per 
accident for bodily injury or disease.

6 
4/29/2021 
8.2 
Indemnification. 
a. 
To the fullest extent permitted by law, Consultant must defend, indemnify, and hold 
harmless City and its elected officials, officers, employees and agents (each, an 
"Indemnified Party," collectively, the "Indemnified Parties") for, from, and against any and 
all claims, demands, actions, damages, judgments, settlements, personal injury (including 
sickness, disease, death, and bodily harm), property damage (including loss of use), 
infringement, governmental action and all other losses and expenses, including attorneys' 
fees and litigation expenses (each, a "Demand or Expense" collectively "Demands or 
Expenses") asserted by a third-party (i.e. a person or entity other than City or Consultant) 
and that arises out of or results from the breach of this Agreement by the Consultant or 
the Consultant’s negligent actions, errors or omissions (including any Subconsultant or 
Subcontractor or other person or firm employed by Consultant), whether sustained before 
or after completion of the Project. 
b. 
This indemnity and hold harmless provision applies even if a Demand or Expense is in 
part due to the Indemnified Party's negligence or breach of a responsibility under this 
Agreement, but in that event, Consultant will be liable only to the extent the Demand or 
Expense results from the negligence or breach of a responsibility of Consultant or of any 
person or entity for whom Consultant is responsible. 
c. 
Consultant is not required to indemnify any Indemnified Parties for, from, or against any 
Demand or Expense resulting from the Indemnified Party's sole negligence or other fault 
solely attributable to the Indemnified Party. 
8.3 
Other Insurance Provisions.  The insurance policies required by the Section above must contain, 
or be endorsed to contain the following insurance provisions: 
a. 
The City, its officers, officials, employees and volunteers are to be covered as 
additional insureds of the CGL and automobile policies for any liability arising from or 
in connection with the performance of all tasks or work necessary to complete the Project 
as herein defined. Such liability may arise, but is not limited to, liability for materials, parts 
or equipment furnished in connection with any tasks, or work performed by Consultant or 
on its behalf and for liability arising from automobiles owned, leased, hired or borrowed 
on behalf of the Consultant. General liability coverage can be provided in the form of an 
endorsement to the Consultant’s existing insurance policies, provided such endorsement is 
at least as broad as ISO Form CG 20 10, 11 85 or both CG 20 10 and CG 23 37, if later 
revisions are used. 
b. 
For any claims related to this Project, the Consultant’s insurance coverage shall be 
primary insurance with respect to the City, its officers, officials, employees, and 
volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, 
employees or volunteers shall be in excess of the Consultant’s insurance and shall not 
contribute with it. 
c. 
Each insurance policy required by this Section shall provide that coverage shall not be 
canceled, except after providing notice to the City. 
8.4 
Acceptability of Insurers.  Insurance is to be placed with insurers with a current A.M. Best rating of 
no less than A: VII, unless the Consultant has obtained prior approval from the City stating that a 
non-conforming insurer is acceptable to the City. 
8.5 
Waiver of Subrogation.  Consultant hereby agrees to waive its rights of subrogation which 
any insurer may acquire from Consultant by virtue of the payment of any loss. Consultant agrees 
to obtain any endorsement that may be necessary to effect this waiver of subrogation. The 
Workers’ Compensation Policy shall be endorsed with a waiver of subrogation in favor of the City 
for all work performed by the Consultant, its employees, agent(s) and subcontractor(s).

7 
4/29/2021 
8.6 
Verification of Coverage.  Within 15 days of the Effective Date of this Agreement, Consultant shall 
furnish the City with original certificates and amendatory endorsements, or copies of any applicable 
insurance language making the coverage required by this Agreement effective. All certificates and 
endorsements must be received and approved by the City before work commences. Failure to 
obtain, submit or secure the City’s approval of the required insurance policies, certificates or 
endorsements prior to the City’s agreement that work may commence shall not waive the 
Consultant’s obligations to obtain and verify insurance coverage as otherwise provided in this 
Section. The City reserves the right to require complete, certified copies of all required insurance 
policies, including any endorsements or amendments, required by this Agreement at any time 
during the Term stated herein. 
Consultant’s failure to obtain, submit or secure the City’s approval of the required insurance 
policies, certificates or endorsements shall not be considered a Force Majeure or defense for any 
failure by the Consultant to comply with the terms and conditions of the Agreement, including any 
schedule for performance or completion of the Project. 
8.7 
Subcontractors.  Consultant shall require and shall verify that all subcontractors maintain insurance 
meeting all requirements of this Agreement. 
8.8  
Special Risk or Circumstances.  The City reserves the right to modify these insurance requirements, 
including any limits of coverage, based on the nature of the risk, prior experience, insurer, coverage 
or other circumstances unique to the Consultant, the Project or the insurer. 
9. 
E-verify, Records and Audits. To the extent applicable under A.R.S. § 41-4401, the Consultant warrant 
their compliance and that of its subconsultants with all federal immigration laws and regulations that relate 
to their employees and compliance with the E-verify requirements under A.R.S. § 23-214(A). The 
Consultant or subconsultant’s breach of this warranty shall be deemed a material breach of the Agreement 
and may result in the termination of the Agreement by the City under the terms of this Agreement. The City 
retains the legal right to randomly inspect the papers and records of the other party to ensure that the other 
party is complying with the above-mentioned warranty. The Consultant and subconsultant warrant to keep 
their respective papers and records open for random inspection during normal business hours by the other 
party. The parties shall cooperate with the City’s random inspections, including granting the inspecting party 
entry rights onto their respective properties to perform the random inspections and waiving their respective 
rights to keep such papers and records confidential. 
10.  
No Boycott of Israel.  To the extent A.R.S § 35-393 through § 35-393.03 are applicable, the parties hereby 
certify that they are not currently engaged in, and agree for the duration of the Agreement to not engage in, 
a boycott of goods or services from Israel, as that term is defined in A.R.S § 35-393. 
11. 
Attestation of PCI Compliance.  When applicable, the Consultant will provide the City annually with a 
Payment Card Industry Data Security Standard (PCI DSS) attestation of compliance certificate signed by an 
officer of Consultant with oversight responsibility. 
12. 
Notices. 
12.1 
A notice, request or other communication that is required or permitted under this Agreement (each 
a "Notice") will be effective only if: 
a. 
The Notice is in writing; and 
b. 
Delivered in person or by overnight courier service (delivery charges prepaid), certified or 
registered mail (return receipt requested). 
c. 
Notice will be deemed to have been delivered to the person to whom it is addressed as of 
the date of receipt, if: 
(1) 
Received on a business day before 5:00 p.m. at the address for Notices identified 
for the Party in this Agreement by U.S. Mail, hand delivery, or overnight courier 
service; or 
(2) 
As of the next business day after receipt, if received after 5:00 p.m.

8 
4/29/2021 
d. 
The burden of proof of the place and time of delivery is upon the Party giving the Notice. 
e. 
Digitalized signatures and copies of signatures will have the same effect as original 
signatures. 
12.2 
Representatives. 
a. 
Consultant.  Consultant's representative (the "Consultant's Representative") authorized to 
act on Consultant's behalf with respect to the Project, and his or her address for Notice 
delivery is: 
Arcadis U.S., Inc. 
c/o Esteban Azagra 
410 North 44th Street, Suite 1000 
Phoenix, AZ 85008 
b. 
City.  City's representative ("City's Representative") authorized to act on City's behalf, and 
his or her address for Notice delivery is: 
City of Glendale 
c/o  Anthony Weathersby 
5850 W. Glendale Avenue, Suite 317 
Glendale, Arizona  85301 
With required copy to: 
City Manager 
City Attorney 
City of Glendale 
City of Glendale 
5850 West Glendale Avenue 
5850 West Glendale Avenue 
Glendale, Arizona  85301 
Glendale, Arizona  85301 
c. 
Concurrent Notices. 
(1) 
All notices to City's representative must be given concurrently to City Manager 
and City Attorney. 
(2) 
A notice will not be deemed to have been received by City's representative until 
the time that it has also been received by the City Manager and the City Attorney. 
(3) 
City may appoint one or more designees for the purpose of receiving notice by 
delivery of a written notice to Consultant identifying the designee(s) and their 
respective addresses for notices. 
d. 
Changes.  Consultant or City may change its representative or information on Notice, by 
giving Notice of the change in accordance with this section at least ten days prior to the 
change. 
13. 
Financing Assignment.  City may assign this Agreement to any City-affiliated entity, including a non-
profit corporation or other entity whose primary purpose is to own or manage the Project. 
14. 
Entire Agreement; Survival; Counterparts; Signatures. 
14.1 
Integration.  This Agreement contains, except as stated below, the entire agreement between City 
and Consultant and supersedes all prior conversations and negotiations between the parties 
regarding the Project or this Agreement. 
a. 
Neither Party has made any representations, warranties or agreements as to any matters 
concerning the Agreement's subject matter. 
b. 
Representations, statements, conditions, or warranties not contained in this Agreement will 
not be binding on the parties.

9 
4/29/2021 
c. 
Inconsistencies between the solicitation, any addenda attached to the solicitation, the 
response or any excerpts attached as Exhibit A, and this Agreement, will be resolved by 
the terms and conditions stated in this Agreement. 
14.2 
Interpretation. 
a. 
The parties fairly negotiated the Agreement's provisions to the extent they believed 
necessary and with the legal representation they deemed appropriate. 
b. 
The parties are of equal bargaining position and this Agreement must be construed equally 
between the parties without consideration of which of the parties may have drafted this 
Agreement. 
c. 
The Agreement will be interpreted in accordance with the laws of the State of Arizona. 
14.3 
Survival.  Except as specifically provided otherwise in this Agreement, each warranty, 
representation, indemnification and hold harmless provision, insurance requirement, and every 
other right, remedy and responsibility of a Party, will survive completion of the Project, or the 
earlier termination of this Agreement. 
14.4 
Amendment.  No amendment to this Agreement will be binding unless in writing and executed by 
the parties. Electronic signature blocks do not constitute execution for purposes of this Agreement. 
Any amendment may be subject to City Council approval. 
14.5 
Remedies.  All rights and remedies provided in this Agreement are cumulative and the exercise of 
any one or more right or remedy will not affect any other rights or remedies under this Agreement 
or applicable law. 
14.6 
Severability.  If any provision of this Agreement is voided or found unenforceable, that 
determination will not affect the validity of the other provisions, and the voided or unenforceable 
provision will be reformed to conform with applicable law. 
14.7 
Counterparts.  This Agreement may be executed in counterparts, and all counterparts will together 
comprise one instrument. 
15. 
Term.   
15.1 
Renewals.  The term of this Agreement commences upon the effective date and continues for a 
one (1) year initial period.  The City may, at its option and with the approval of the Consultant, 
extend the term of this Agreement an additional four (4) years, renewable on an annual basis.  
Consultant will be notified in writing by the City of its intent to extend the Agreement period at 
least thirty (30) calendar days prior to the expiration of the original or any renewal Agreement 
period.  Price adjustments will only be reviewed during the Agreement renewal period and will be a 
determining factor for any renewal.  There are no automatic renewals of this Agreement.  
15.2 
Extension for Procurement Process.  Upon the expiration of the Term of this Agreement, 
including the initial term and any renewals, at the City’s sole discretion, this Agreement may be 
extended on a month-to-month basis for a maximum of six (6) months to allow for the City to 
complete its procurement process to select a vendor to provide the services/materials similar to 
those provided under this Agreement.  The City will notify the Contractor in writing of its intent to 
extend the Agreement at least thirty (30) calendar days prior to the expiration of the Term.  Any 
extension provided under this subsection will continue under the same terms and conditions as in 
effect immediately prior to the expiration of the then-current term. 
16. 
Dispute Resolution.  Any controversy or claim arising out of or relating to this contract, or the breach 
thereof, shall be settled by arbitration administered according to the American Arbitration Association’s 
Commercial Arbitration Rules, and judgment on the award rendered by the arbitrator may be entered in any 
court having jurisdiction thereof. 
17. 
Cooperative Use of Contract.   This agreement may be extended for use by other governmental agencies

10 
4/29/2021 
And political subdivisions of the State.  Any such usage by other entities must be in accord with the 
ordinances, charter, rules and regulations of the respective entity and the approval of the Contractor and 
City.  For a list of SAVE members, click on the following link: 
http://www.mesaaz.gov/business/purchasing/save 
18. 
Exhibits.  The following exhibits, with reference to the term in which they are first referenced, are 
incorporated by this reference. 
Exhibit A 
Project 
Exhibit B 
Scope of Work 
Exhibit C 
Schedule 
Exhibit D 
Compensation 
 
(Signatures appear on the following page.)

11 
4/29/2021 
The parties enter into this Agreement effective as of the date shown above. 
City of Glendale, 
an Arizona municipal corporation 
_____________________________________ 
By:  Kevin R. Phelps 
Its:  City Manager 
ATTEST: 
 
 
 
 
 
 
Julie K. Bower 
(SEAL) 
City Clerk 
APPROVED AS TO FORM: 
 
 
 
 
 
 
Michael D. Bailey 
City Attorney 
Arcadis U.S., Inc., 
a Delaware corporation 
_____________________________________ 
By:        
Its:        
 
 
Esteban Azagra
Senior Vice President 
December 2, 2021

EXHIBIT A 
Professional Services Agreement 
PROJECT 
Consultant will help City of Glendale to assess the City's needs, selecting a water AMR system by way of a 
performance based contract.

EXHIBIT B 
Professional Services Agreement 
SCOPE OF WORK 
Consultant will help the City to assess needs in selecting a water AMR system through the Scope of Services 
outlined in RFP 21-52 and attached as Exhibit B.

CITY OF GLENDALE PROCUREMENT 
DIVISION REQUEST FOR PROPOSAL 
 
 
SOLICITATION NUMBER: 
RFP 21-52 
 
ONLINE BID NUMBER: 
 
 
42100072 
TITLE: 
WATER METER REPLACEMENT CONSULTANT 
 
 
PUBLISHED DATE: 
JUNE 24, 2021   
 
 
 
 
PRE-OFFER CONFERENCE: 
JULY 15, 2021, 2:00 PM Local Time 
Please join my meeting from your computer, tablet or smartphone. 
https://global.gotomeeting.com/join/288280621 
 
You can also dial in using your phone. 
United States: +1 (646) 749-3122 
 
Access Code: 348-514-757 
Attendance is NOT required 
 
 
OFFER DUE: 
JULY 27, 2021, 2:00 PM Local Time 
Offer Submission Through Vendor Self-Service (VSS) Online Bid 
System.  
https://glendaleaz.munisselfservice.com/Vendors/default.aspx  
NOTE:  This is a sealed proposal process requiring proposals 
to be submitted before the date/time shown above.  If errors 
occur when submitting through VSS, email or call using contact 
information below. 
 
 
CONTACT: 
Anthony Weathersby, Contract Analyst 
Purchasing-Procurement Division 
623-930-2864 
Aweathersby@glendaleaz.com 
 
 
Proposals shall be opened using the City’s electronic bidding system on the specified due 
time and date identified herein. All information contained in the proposals shall be 
confidential to avoid disclosure of contents prejudicial to competing Offerors.  
 
OFFERORS ARE STRONGLY ENCOURAGED TO CAREFULLY READ THE ENTIRE 
SOLICITATION 
 
Vendor Self-Service - New and Existing Vendor Registration Guide  
https://www.glendaleaz.com/common/pages/DisplayFile.aspx?itemId=16718352

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
2 
Table of Contents:  
 
RFP Package 
1. 
INTRODUCTION .............................................................................................................................................. 3 
2. 
BACKGROUND ................................................................................................................................................. 3 
3. 
OBJECTIVES ..................................................................................................................................................... 3 
4. 
SCOPE OF SERVICES ..................................................................................................................................... 3 
5. 
HOW WE CHOOSE ........................................................................................................................................... 7 
6. 
SUBMISSION CHECKLIST .......................................................................................................................... 10 
7. 
SUBMISSION REQUIREMENTS ................................................................................................................. 11 
 
Exhibit Package 
Exhibit 1:  Special Notices 
Exhibit 2:  RFP Terms and Conditions 
Exhibit 3:  Insurance Requirements 
Exhibit 4:  Template Agreement 
 
Fillable Forms 
 
Response Workbook – To be completed by Offeror and submitted as their response. 
     Cover Sheet 
     Offer Sheet 
            Required Responses 
 
       Fee Proposal Workbook – To be completed by Offeror and submitted as their response.

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
3 
1. 
INTRODUCTION  
 
The City has approximately 1,100 miles of waterline serving approximately 63,800 service 
connections and meters for residential, commercial, industrial and landscape customers. 
The City is planning to convert its existing ‘manually read’ water meter system to an 
automatic meter reading (AMR) / Advanced Metering Infrastructure system (AMI) over the 
next few years. The resultant contract shall be monitored under the supervision of the 
City’s Water Services, and Budget and Finance Departments. The City intends to make a 
single award. Note: The Consultant or Firm (Consultant) selected and awarded a contract 
as a result of this solicitation, will not be allowed to submit a proposal for an AMR / AMI 
System. 
 
2. 
BACKGROUND 
 
The City’s meter inventory consists of Badger and Sensus meters ranging in size from 
.75”- 6”.  There are approximately 5,000 AMR/AMI capable meters of which approximately 
2,900 meters have an Itron ERT attached to them.  The City is currently using Itron meter 
reading system, Harris NorthStar utility billing application and Lucity asset management 
application. The City currently changes out 2,500 to 3,500 meters each year program.   
 
3. 
OBJECTIVES 
 
The intent of this solicitation is to obtain professional services to assist the City in 
assessing the City’s needs, selecting a water AMR / AMI system by way of a performance-
based contract. In this context, a performance-based contract is one in which the 
Contractor guarantees a specific revenue increase or cost savings generated by the project 
which is then used to pay for the cost of the project. Consultant will also coordinate and 
monitor the implementation of the system 
 
4. 
SCOPE OF SERVICES 
 
4.1 
MANDATORY REQUIREMENTS: The Consultant must meet the following 
qualifications. Those who do not meet these mandatory minimums will be deemed 
non-responsive and removed from the evaluation process.  
1) 
Consultant must have a minimum of five (5) years of successful experience 
consulting, planning, implementing, and /or engaging in water meter AMR / AMI 
projects. 
2) 
Consultant must be able to show that they have an established record of 
successfully executing their services, as outlined in this solicitation, to the 
satisfaction of their customers. 
3) 
Consultant must be able to demonstrate that they have successfully consulted on 
water meter AMR / AMI solutions for systems of 50,000 service connections or 
more.

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
4 
 
 
4.2 
PREPARATION: Consultant shall, 
1) 
Have a clear understanding of current best practices and water meter AMR/AMI 
system trends in public water delivery systems and how to best apply them to City 
environment. 
2) 
Evaluate current equipment and systems; identify the immediate and long-term 
needs for the development of a water meter AMR/AMI program. 
3) 
Educate management level staff on advantages and challenges of converting to an 
AMI system.  
4) 
Develop a budget projection and timeline for the proposed project. 
5) 
Recommend resource plan requirements that consider all the resources (staff, 
space, equipment support, etc.) required for initial system setup/management for 
all proposed solutions. 
6) 
Provide a review of performance-based RFP’s from other agencies of similar 
size/scope that have recently replaced or implemented their water meter AMR/AMI 
system. 
 
4.3 
NEEDS ASSESSMENT: Consultant shall, 
1) 
Prepare a detailed financial analysis for AMI implementation using various network 
structures (i.e. fixed network vs. cellular) 
2) 
Perform a Needs Assessment Study to determine the current and future technology, 
interfaces, and infrastructure needs for the City. 
3) 
Develop a comprehensive process mapping document that identifies the data flow 
process within the City.  This should include workflow diagrams and related text for 
the City’s existing system/process and new system/process. 
4) 
Analyze the current system redundancy for fault tolerance and recommend system 
specifications that include system redundancy. 
5) 
Develop and update system documents where needed. 
6) 
Recommend and specify a new water meter AMR/AMI system and project 
acquisition strategy that best satisfies user requirements, offers long-term viability, 
and is suited to for the City’s infrastructure. 
7) 
Recommend new and/or improved existing workflows to increase operational 
efficiencies within the Utility. 
8) 
Provide a staffing analysis that details the current technical staff structure at the 
City and its suitability to support an implementation program of this size and 
complexity.  This analysis would include recommendations for changes in staff 
tasking and staffing levels throughout project implementation and after project 
completion, i.e., during on-going maintenance and operations. 
9) 
Recommend an appropriate scope and detailed strategy for the project including 
timelines and phasing for procurement of supplies, infrastructure deployment, and 
system testing. 
10) 
Determine the requirements and provide a recommendation for disaster recovery, 
backup, and business continuity. The consultant/firm will be required to identify the

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
5 
type and amount of hardware, software, connectivity and other key infrastructure 
components necessary to maintain acceptable operations 
 
4.4 
SOLICITATION DEVELOPMENT: Consultant shall, 
1) 
Assist the city in developing an RFP for an AMR/AMI system using performance-
based contracting that include Key Performance Indicator’s (KPI’). 
2) 
Respond to vendor inquiries regarding system requirements in conjunction with the 
Procurement Office. 
3) 
Participate in the process to evaluate proposals from vendors. 
4) 
Attend pre-proposal conferences and vendor interviews. 
5) 
Assist the city in reviewing and evaluating the proposals received from the RFP. 
6) 
Prepare a written report that outlines the evaluation, clarifications, and 
recommendations. 
7) 
Provide a report detailing a recommended system and program through site visits 
and on-site interviews. 
8) 
Make presentations, as necessary, explaining evaluation results and 
recommendations. 
 
4.5 
IMPLEMENTATION: Consultant shall, 
1) 
Coordinate with the selected water meter AMR/AMI system contractor to prepare an 
implementation plan for the selected system. 
2) 
Monitor vendor compliance as Glendale’s representative during system installation 
and start-up. 
3) 
Coordinate with software and hardware contractors to resolve system 
implementation issues.  
4) 
Develop a strategy for phasing project management of the AMR/AMI program to 
City staff at a defined project benchmark. 
 
4.6 
MILESTONES: Consultant shall work with the City project team to meet the 
following milestones to be further defined upon project kickoff: 
1) 
Project Kickoff with City project team  
2) 
Project Management 
3) 
Needs assessment 
4) 
Project plan with City project team   
5) 
RFP draft and release 
6) 
RFP evaluation 
7) 
Council presentation of project  
8) 
RFP award 
9) 
Implementation Project kickoff 
a. Project Phase 1 - Pilot/technology installation and testing of AMR/AMI and IT 
System automation. 
b. Optional Project Management Services   
10) 
Project Phase 2 - AMR Deployment – automate routes with AMR ready meters

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
6 
11) 
Project Phase 3 - Meter Replacement – automate routes with predominately older 
meters. 
12) 
Deliver a Final Report with findings from the tasks above and recommendations.

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
7 
5. 
HOW WE CHOOSE 
 
5.1 
SCORING RESPONSES:  
The evaluation criteria are weighted in accordance with the Submission 
Requirements.  Your response will be rated as follows: 
o 
35% Understanding of project and approach to performing services 
o 
25% Experience, proven performance, and qualifications 
o 
20% Capacity of Offeror 
o 
20% Cost 
 
5.2 
TYPE OF AWARD: The City reserves the right to make multiple awards or to 
award by group of line items, or to make an aggregate award, whichever is deemed 
most advantageous to the City. If the City determines that an aggregate award to 
one bidder is not in the City's best interest, "all or none" Bids shall be rejected.  
 
5.3 
LENGTH OF CONTRACT: The City will award for an initial one (1) year with four 
(4) additional one-year renewal options. 
 
5.4 
EVALUATION PANEL: Submittals will be evaluated by a panel based on the 
stated criteria and are responsible for selecting the proposal that is most 
advantageous to the City.  
 
5.5 
PANEL CONTACT: Offerors shall have no exclusive meetings, conversations or 
communications with an individual evaluation panel member on any aspect of the 
RFP, after submittal. 
 
5.6 
INTERVIEWS:  City may ask some or all Offerors to participate in an interview at 
any point during the evaluation process but is not required to do so. Information 
gathered in an interview will be used by the panel to make a selection.  Offeror is 
responsible for any costs incurred to participate in an interview. 
 
5.7 
ADDITIONAL INVESTIGATIONS: City may conduct additional investigations 
needed to determine the competence or financial stability of any Offeror. 
 
5.8 
BEST AND FINAL OFFERS: City may request best and final offers and will 
determine the scope and subject of any best and final request.   
 
5.9 
PROPOSAL EVALUATION: City reserves the right to secure additional 
information from the Offeror in various forms and to award based on submitted 
information. 
 
5.10 NOTICE OF INTENT TO AWARD AND PROTEST PERIOD: Information about 
the recommended award for this solicitation will be posted on the online at 
https://www.glendaleaz.com/your_government/city_finances/procurement/notice

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
8 
_of_intent_to_award   and will be available immediately after the City has 
completed its evaluation process.  Questions regarding the notice of intent to 
award must be directed to the listed Contract Analyst immediately.  Any protest 
must be submitted to the Procurement Administrator no later than seven (7) 
calendar days from the date of posting on the Internet.  For information and 
instructions on how to file a protest, visit:          
https://www.glendaleaz.com/your_government/city_finances/procurement/procur
ement_policies 
 
5.11 WITHDRAWAL OF PROPOSAL: Offeror may withdraw a submitted proposal at 
any time prior to the specified solicitation due date and time through the City’s 
online bidding system.  Withdrawals must be made by the Offeror or designated 
representative listed on the proposal.  Telephonic or oral withdrawals cannot be 
accepted. 
 
5.12 OFFER ERRORS OMISSIONS AND CORRECTIONS: City will not be responsible 
for any offeror errors or omissions. Any corrections shall be submitted through the 
City’s online bidding system prior to due date and time of the RFP. No corrections 
will be permitted after the offers have been opened. 
 
5.13 COMPETITIVE NEGOTIATIONS: City may negotiate with multiple Offerors at the 
same time.  Negotiations may result in changing the conditions, terms, or price of 
the proposed contract for the benefit of the City unless prohibited herein.  All 
Offerors shall be treated fairly and equally while conducting negotiations and the 
City is prohibited from disclosing any information submitted by competing 
Offerors. Entering into negotiations does not constitute a contract award or confer 
any rights to Offerors.  The City may formally terminate negotiations and enter into 
concurrent or exclusive negotiations with the next most qualified Offeror/s if it is in 
the City’s best interest to do so. 
 
5.14 NO CONTACT, NO INFLUENCE DURING THE RFP PROCESS: City is 
conducting a competitive RFP process for the contract, free from improper 
influence or lobbying.   There shall be no contact concerning this RFP from 
Offerors submitting a Proposal with any member of the City Council, RFP 
Evaluation Committee Members, or anyone connected with the process for or on 
behalf of the City.  Contact includes direct or indirect contact by the Offeror, its 
employees, attorneys, lobbyists, surrogates, etc. in an attempt to influence the RFP 
process. 
 
From the time the RFP is issued until the expiration of the protest period or the 
resolution of any protest, whichever is later (the “Silent”), Offerors, directly or 
indirectly through others, are restricted from attempting to influence in any 
manner the decision making process through, including but not limited to, the use 
of paid media; contacting or lobbying the City Council or City Manager or any other 
City employee (other than Material Management employees); the use of any media

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
9 
for the purpose of influencing the outcome; or in any other way that could be 
construed to influence any part of the decision-making process about this RFP.  
This provision shall not prohibit an Offeror from petitioning an elected official or 
engaging in any other protected first amendment activity after the protest period 
has run or any protest has been resolved, whichever is later. 
 
Violation of this provision will cause the proposal or offer of the Offeror to be found 
in violation and to be rejected. 
 
5.15 PROPRIETARY INFORMATION Offeror shall clearly mark any proprietary 
information contained in its bid with the words “Proprietary Information.” Offeror 
shall not mark any Solicitation Form as proprietary. Pricing data shall not be 
considered proprietary. Marking all, or nearly all, of a bid as proprietary may result 
in rejection of the bid.  
 
Offeror’s acknowledge that the City is required by law to make certain records 
available for public inspection. In the event that the City receives a request for 
disclosure of Proprietary Information by any person, court, agency or 
administrative body, or otherwise has a reasonable belief that it is obligated to 
disclose the Proprietary Information to any such person or authority, the City will 
provide Offeror with prompt written notice so that Offeror may seek a protective 
order or other appropriate remedy. The Offeror, by submission of materials 
marked Proprietary Information, acknowledges and agrees that the City will have 
no obligation to advocate for non-disclosure in any forum or any liability to the 
Offeror in the event that the City must legally disclose the Proprietary Information.

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
10 
6. 
SUBMISSION CHECKLIST 
 
This section provides an overview of the submission instructions including a checklist to 
aid in the submission of complete proposals.  Offeror’s shall complete the fillable 
“RESPONSE WORKBOOK” attachment and submit as their proposal. 
 
Vendors are strongly advised to read this section in its entirety and complete the 
checklist to avoid disqualification.  Please note that the City will NOT be able to 
consider proposals that are submitted late or that do not follow these guidelines. 
 
The Offeror shall bear all costs associated with submitting the proposal, including 
proposal preparation, site visitation or any travel connected with submission of the 
proposal. The City shall have no liability whatsoever for such costs. 
 
Checklist for Submitting Proposal 
Complete 
() 
Submission Requirements 
COVER SHEET (Response Workbook) 
Offeror Name 
Offeror Address 
 
COMPLETED OFFER SHEET (Response Workbook) 
 
1. UNDERSTANDING OF PROJECT AND APPROACH TO PERFORMING 
SERVICES 
(6 questions) 
 
2. EXPERIENCE, PROVEN PERFORMANCE, AND QUALIFICATIONS 
(3 questions) 
 
3. CAPACITY OF OFFEROR 
(3 questions) 
 
4. COST (Must be submitted in a separate electronic file) 
(1 question) 
 
ADDENDUM RESPONSES (if applicable) 
 
Return of Offer 
• 
Electronic copies of all "SUBMISSION REQUIREMENTS” listed 
above. Pricing Workbook must be submitted separately from the 
rest of the proposal.

City of Glendale 
Solicitation Number: RFP 21-52/ 42100072  
WATER METER REPLACEMENT CONSULTANT 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Avenue, 
Suite 317 
Glendale, Arizona 85301 
 
11 
 
7. 
SUBMISSION REQUIREMENTS 
 
The proposal is every element of your response to this RFP.  For this proposal, 
you must provide a completed OFFER SHEET in addition to answering the 
questions identified in the REQUIRED RESPONSES. (see Response Workbook) 
 
Responses must be numbered to correspond to the question numbers to aid in 
the evaluation process; failure to do so may result in disqualification.   
 
Should your offer contain any PROPRIETARY INFORMATION you must clearly 
mark that information with the words “Proprietary Information.” Only 
information contained in your response questions may be marked as such, 
information on the OFFER SHEET or PRICING SHEET (if applicable) are not 
considered proprietary. 
 
Offeror’s acknowledge that the City is required by law to make certain records 
available for public inspection.  By submitting any materials marked as 
Proprietary Information, Offeror acknowledges and agrees that the City will have 
no obligation to advocate for non-disclosure in any forum or any liability to the 
Offeror if the City must legally disclose the Proprietary Information. 
 
Helpful Hints: 
• Answer each question completely, your answers will be the only basis on 
which your proposal is scored. 
• Do not unnecessarily elaborate, keep your response complete and effective. 
• Do not provide general answers or reference to sales literature. 
• Only when applicable attach and reference supporting documents.

EXHIBIT C 
Professional Services Agreement 
SCHEDULE 
Consultant and City will work together on a timeline as shown in Response Workbook.

Mr. Anthony Weathersby 
Contract Analyst 
City of Glendale 
5850 West Glendale Avenue, Suite 317 
Glendale, AZ 85301 
 
Date: August 10, 2021 
Subject: Proposal for Water Meter Replacement Consultant, RFP 21-52/42100072 
 
Dear Mr. Weathersby, 
 
The City of Glendale (City) is embarking on an ambitious effort to enhance and improve its customers' 
experience through advanced metering technologies. As a leading consulting firm in the industry, Arcadis 
is helping clients around the world build the smart utility networks of the future. 
Our breadth of capabilities provides the City with access to the full range of services needed to 
successfully implement your automatic meter reading (AMR) / advanced metering infrastructure (AMI). 
Our proposed team has extensive experience in advanced metering infrastructure, and our approach to 
supporting the City for this project will result in a viable and economically justifiable meter replacement 
project by delivering the following features and benefits: 
• 
Arcadis’ approach to the needs assessment and procurement specifications will give special 
focus to the unique needs of a performance-based project, including the establishment of 
performance metric baselines and improvement opportunities, and estimating the associated 
potential cost savings.  
• 
Arcadis will perform a thorough economic analysis of the identified alternatives to determine 
which is most advantageous to the City. This will include a determination about the pros and cons 
of using various forms of a performance-based contracting mechanism. Additionally, Arcadis will 
perform an analysis of currently available project funding sources to determine if there are other 
viable means for the City to funding the meter replacement project. We have recently completed 
similar funding analysis for other clients undertaking meter replacement programs and are 
currently helping Greene County, OH and the Puerto Rico Aqueducts and Sewer Authority 
(PRASA)  obtain funding support for their meter replacement projects.  
• 
Arcadis brings over three decades of experience working with the City.  We understand your 
needs, policies, procedures and culture. We also bring significant relevant project experience in 
the greater Phoenix area, having performed similar projects for the City of Tempe and for the City 
of Mesa. We will provide a core project team based locally and supported with nationally 
recognized subject matter experts, providing immediate access for the City.   
• 
Arcadis is completely vendor agnostic and does not represent any specific metering or AMR/AMI 
technology. This allows us to act as the City’s owner’s agent whose only mission is to help 
achieve a successful meter replacement project.   
 
 
 
Arcadis U.S., Inc. 
410 N. 44th Street 
Suite 1000 
Phoenix 
Arizona 85008 
Phone: 602 438 0883 
Fax: 602 438 0102 
www.arcadis.com

Page: 
2/43 
We look forward to our continued working relationship with the City on this exciting project. If you have 
any questions or require any additional information, please do not hesitate to contact me. 
Sincerely, 
 
Arcadis U.S., Inc. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
D. Michael Rotunno 
Esteban Azagra 
Project Principal 
 
 
 
 
 
Project Manager 
 
Email: esteban.azagra@arcadis.com 
 
 
 
Email: michael.rotunno@arcadis.com 
Direct Line: 602-797-4678 
 
 
 
 
Direct Line: 330-515-5672  
Mobile: 602-405-7858  
 
 
 
 
Mobile: 216-374-5805 
 
 
Enclosures:  
 
Proposal Response Workbook 
 
Pricing Workbook

Page: 
3/43 
 
 
Offeror’s to complete this Response Workbook and submit as their response to this RFP. 
 
COVER SHEET 
 
OFFEROR NAME: 
    Arcadis U.S., Inc. 
 
OFFEROR ADDRESS:       410 North 44th Street 
Suite 1000 
Phoenix, Arizona 85008

Page: 
4/43 
OFFER SHEET (Must be printed, signed and returned) 
Offeror certifies that they have read, understand, and will fully and faithfully comply with this 
solicitation, its attachments and any referenced documents.  Offeror also certifies that the prices 
offered were independently developed without consultation with any of the other Offerors or 
potential Offerors. 
 
__________________________________________ 
__August 10, 2021_____________________________ 
Authorized Signature 
 
Date 
 
___Esteban Azagra ______________ 
 
   __ Arcadis U.S., Inc ____________________________ 
 
Printed Name (Authorized Signatory) 
         Legal Company Name 
 
___Senior Vice President_________ 
 
Offeror Certifies it is a (check only one): 
Job Title 
 
 Proprietorship 
 Partnership  
 Corporation 
 
___ esteban.azagra@arcadis.com ___________ _410 North 44th Street, Suite 1000 
Email Address 
 
Mailing Address 
 
__602 797 4678____________________________  
__ Phoenix, Arizona,85008              
Phone Number 
     
City, State & Zip Code 
 
Questions regarding this offer should be directed to (if different from above): 
 
________________________________ 
     _______________ 
     ______________________ 
Contact Name 
Phone Number             Email Address 
 
FEDERAL TAXPAYER ID NUMBER (Required):   _57-0373224 _________________________________ 
 
OFFEROR IS A MINORITY OR WOMEN OWNED BUSINESS:  
 Yes 
 No 
 
DO YOU HAVE AN ARIZONA TRANSACTION PRIVILEGE TAX (TPT) LICENSE? 
 
 
 Yes, Number   07632143-H      Tax Rate:        OR  
 No, not required to have an Arizona 
TPT License 
 
CONFLICT OF INTEREST (SPECIAL NOTICES):  
 
 No, I do not have a conflict of interest   
 Yes, I have a conflict of interest and response includes the disclosure required (see Exhibit 1, 
Item #3) 
 
ACKNOWLEDGEMENTS: 
By signing this Offer Sheet and submitting the accompanying solicitation response, Offeror is 
certifying that they have read, understand, and agree to comply with all required terms and 
conditions provided in the EXHIBITS PACKAGE and checked off below.  Failure to provide this 
acknowledgement will result in disqualification. 
 
 Exhibit 1 – Special Notices 
 Exhibit 2 – RFP Standard Terms and Conditions 
  Exhibit 3 – Insurance Requirements 
 
Exhibit 4 – Template Agreement

Page: 
5/43 
REQUIRED RESPONSES: 
 
Offeror’s answers to the following questions will comprise the Offeror’s response to this 
RFP.  It should be noted that all attachments or exhibits prepared by the City and 
referenced herein are incorporated by reference into the Offeror’s response and shall be 
included in a final contract with the successful Offeror. Information prepared by the 
Offeror and submitted with their proposal may be incorporated into a final contract (for 
example program offerings, curriculum, key personnel, or performance metrics). 
Supporting documents, exhibits, etc. not clearly identified to correlating question will not 
be evaluated.  
 
1. MANDATORY REQUIREMENTS 
 
1) 
Can your firm provide proof that it has a minimum of five (5) years of successful 
experience consulting, planning, implementing, and /or engaging in water meter 
AMR / AMI projects? 
 
 
YES 
 NO 
 
 
 
Arcadis has been engaged in water metering projects including both AMR and AMI since 
2005. Arcadis has been in the business of providing AMR and AMI related services 
since the inception of AMR systems for the water industry in the late early 2000s. 
Partnered with our subconsultant, SL-serco, our combined experience delivering water, 
natural gas and electric AMR/AMI projects is about 22 years.  As an example, in the last 
ten years our team has provided AMR/AMI related services to key clients like 
Birmingham Water Works Board, AL (2010-2014), City of Tempe, AZ (2015-2018),  
Youngstown, OH (2015-2016), Washington Suburban Sanitary Commission (2018-
2021), or City of Mesa (2019 - Ongoing) 
2) 
Can your firm show that there is an established record of successfully executing 
services that have been provided by your firm, as outlined in this solicitation, to 
the satisfaction of your customers? 
 
 YES 
 
 NO 
The Arcadis team has an established track record of successful meter replacement and 
AMR/AMI projects. As part of our response to Question 3.1, we have included client 
references for a sampling of our recent clients, including City of Mesa, City of Tempe, 
and Puerto Rico Aqueduct and Sewer Authority (PRASA). We have the ability to provide 
additional references upon request.

Page: 
6/43 
3) 
Can your firm demonstrate that it has successfully consulted on water meter AMR 
/ AMI solutions for systems of 50,000 service connections or more?  
 
 YES 
 
 NO 
As shown in our response to question 3.2, the Arcadis team has successfully completed 
AMR/AMI projects ranging from 5,000 endpoints to over 1M endpoints. Clients that we 
have supported of similar size to the City of Glendale include City of Tempe, AZ, City of 
Youngstown, OH, Lee County Water, FL, Town of Cary, NC; and West Virginia Water 
Authority. 
 
2. UNDERSTANDING OF PROJECT AND APPROACH TO PERFORMING SERVICES 
 
1) 
Introduce your company and demonstrate that your firm has a clear 
understanding of current best practices, water meter AMR/AMI system trends in 
public water delivery systems and how to best apply them to City environment. 
Proposer History 
Arcadis U.S., Inc. is a leading global natural and built asset design and 
consultancy firm working in partnership with our clients to deliver exceptional 
and sustainable outcomes through the application of design, consultancy, engineering, and project 
management services. For more than a century, Arcadis has provided consultation services with a 
concentration in water and the environment. Over the past 50 years, we have been providing 
engineering and project management services across industries, including water and wastewater. 
Our team includes professionals that span the industry from all regions of the United States. 
With more than 27,000 people worldwide, approximately 5,000 U.S. professionals and support 
personnel, and more than 100+ staff members in Arizona, Arcadis has the capacity to provide the 
resources necessary to meet your project’s objectives. This contract will be managed from our 
office in Phoenix, AZ where Arcadis has one of our national centers of excellence for technology 
and management consulting services.  
Arcadis is the right firm to support the City to define, select and procure an AMR/AMI system. Our 
firm offers the following benefits to the City: 
 
The Arcadis team consists of water utility experts who have worked through all facets of 
planning, procurement, and system implementation for complex meter-to-bill systems. 
Arcadis stays constantly abreast of developments in the AMR/AMI marketplace, and 
remains independent of the system vendors so that we can advise our clients in an 
unbiased manner. 
Arcadis has successfully helped clients obtain funding for their meter replacement and 
AMR/AMI programs.  We will combine this expertise with over three decades of 
experience working with the City that will help us align the proposed AMR/AMI system 
with your needs, procedures and culture.

Page: 
7/43 
Our proven approach to AMR/AMI planning and procurement results in the City achieving a 
best fit solution for a known price and acceptable level of risk. 
 
Qualifications 
Arcadis is helping clients around the world build intelligent water systems of the future. We provide a 
full range of services from planning and procurement to implementation and deployment of new 
meter reading solutions, and to exploit them to advance broader intelligent water and smart cities 
initiatives for our clients. Our staff possess deep technical and managerial experience in areas such 
as metering, customer service, engineering, information technology and business consulting. We use 
this knowledge to help clients successfully implement complex water metering and intelligent water 
projects. Services we offer include: 
• Program and project management 
• Needs Assessment and Master Planning—AMR/AMI, Intelligent Water, Smart Cities 
• AMR/AMI planning and business case evaluations 
• System selection and procurement consulting 
• Quality assurance 
• Organizational change management 
• Engineering and technical design services 
• Business process engineering and value management 
• System optimization 
• Intelligent utility data analytics, strategy, design and 
implementation 
• Water conservation programming 
• Distribution system engineering and optimization 
 
Subconsultants 
For this project, Arcadis has enhanced our team with SL-serco to provide specialized AMR/AMI 
experience.SL-serco specializes in advanced metering solutions for water, gas and electric utilities. 
They employ experts located across the U.S. who are implementing meter reading systems and have 
specific experience integrating AMR/AMI systems with utility billing systems. SL-serco’s significant 
subject matter experience in advanced metering, from all corners of the industry, will provide the City 
with the technical advice necessary for a successful project. Arcadis has a successful history working 
with SL-serco, and our teams are currently engaged together on a number of active projects. 
SL-serco’s goal is to work collaboratively with the utility team to achieve the desired project results 
and ensure they are involved throughout the process. As always, their goal is to enable clients to 
make the best decision for their organization and stakeholders. 
 
 
2) 
What is the approach your firm will use to evaluate existing equipment and 
systems that will result in identifying the immediate and long-term needs for the 
development of a water meter AMR/AMI program?  Include the following items:

Page: 
8/43 
a. Advantages and challenges of converting to an AMI system 
b. Educate City Staff 
c. Budget projection 
d. Project timeline  
e. Projected resource requirements 
f. Process to review of performance-based RFP’s of similar size/scope from 
other agencies who have recently replaced or implemented an AMI/AMR 
system. 
Our approach to this project has been developed based on our understanding of the City’s needs 
coupled with our experience with similar projects, both nationally and in Arizona. AMI projects are 
unique in many ways, including that they are cross-functional in nature, impact many areas of 
utility operations, and are highly visible to customers. Our knowledge in these areas will allow us to 
address the City’s immediate and long-term needs for the development of a water meter AMR/AMI 
program. Our approach is summarized in Figure 1 and further described in our responses to the 
following questions.  
As part of our project preparation our team will conduct a kick-off meeting where we will provide an 
educational presentation to City staff about the current state of the water meter AMR/AMI market, 
advantage and challenges of converting to an AMR/AMI, various contracting mechanisms 
commonly used and their advantages and disadvantages, and major considerations for the 
project. Arcadis has the ability to provide Continuing Education Units (CEUs) for attendees of this 
session.  
As part of the needs assessment, Arcadis will evaluate various contracting and funding vehicles 
for the project, including the use of performance-based contracts. We will augment the library of 
examples that we already have by gathering information from comparable utilities that have used 
performance based contracts for similar projects. Based on this review, we will suggest the best 
practices for the City to apply in their AMR/AMI procurement.  
As part of our needs assessment approach described in our responses to the following questions, 
we will develop a complete business case for different AMR/AMI alternatives including budget 
projections. The budget projections and project timeline will then be finalized as part of the project 
plan based on the selected alternative and defined system requirements.   
The Implementation phase of the project will be further broken down into releases as defined 
based on the results of the Needs Assessment. In responding to this RFP, we are anticipating 
three implementation release phases as the City has described in your RFP, to include:  
• 
Implementation Phase 1 – Pilot/technology installation and testing for AMR/AMI and IT 
System Automation. 
• 
Implementation Phase 2 – AMR Deployment – Automate routes with AMR ready meters.  
• 
Implementation Phase 3 – Meter Replacement.

Page: 
9/43 
 
Figure 1 – Proposed Approach 
 
Project Initiation (Preparation) 
We will facilitate a kickoff meeting and introductory workshop with the City’s staff, including the 
project sponsors, key staff, subject matter experts, and other stakeholders, as appropriate, to 
review the project tasks and schedule, as well as the overall project objectives. The kick-off 
meeting will help orient all participants on the project approach, gather their expectations and 
identify the areas of input that will be required for project success.  
The Arcadis team stays abreast of all current developments in the AMI marketplace and remains in 
contact with the major AMI vendors on a regular basis. As part of the kick-off meeting we will provide 
an educational presentation to City staff about the current state of the water meter AMR/AMI market. 
Arcadis’ AMI technical experts will develop a summary of the AMI Vendors in the market and an 
overview of firms that are providing meter replacement project using performance based contracting 
mechanisms. This summary will include, but not limited to the following details: 
 
• 
Overview of their solution and capabilities 
• 
Company size and revenue 
• 
Key differentiators 
The presentation will also describe the advantage and challenges of converting to an AMR/AMI, 
various contracting mechanisms commonly used and their advantages and disadvantages, and 
major considerations for the project. Arcadis has the ability to provide Continuing Education Units 
(CEUs) for attendees of this session. 
 
 
 
 
(Implementation Phases 1, 2 & 3)

Page: 
10/43 
3) 
Describe your firm’s approach that reflects your firm’s knowledge for completing 
the following Needs Assessment objectives:  
a. Provide a detailed financial analysis for AMR/AMI implementation using 
various network structures (i.e. fixed network vs. cellular) 
b. Perform a Needs Assessment Study to determine the current and future 
technology, interfaces, and infrastructure needs for the City. 
c. Develop a comprehensive process mapping document that identifies the data 
flow process within the City.  This should include workflow diagrams and 
related text for the City’s existing system/process and new system/process. 
d. Analyze the current system redundancy for fault tolerance and recommend 
system specifications that include system redundancy. 
e. Develop and update system documents where needed. 
f. Recommend and specify a new water meter AMR/AMI system and project 
acquisition strategy that best satisfies user requirements, offers long-term 
viability, and is suited to for the City’s infrastructure. 
g. Recommend new and/or improved existing workflows to increase operational 
efficiencies within the Utility. 
h. Provide a staffing analysis that details the current technical staff structure at 
the City and its suitability to support an implementation program of this size 
and complexity.  This analysis would include recommendations for changes in 
staff tasking and staffing levels throughout project implementation and after 
project completion, i.e., during on-going maintenance and operations. 
i. Recommend an appropriate scope and detailed strategy for the project 
including timelines and phasing for procurement of supplies, infrastructure 
deployment, and system testing. 
j. 
Determine the requirements and provide a recommendation for disaster 
recovery, backup, and business continuity. The consultant/firm will be 
required to identify the type and amount of hardware, software, connectivity 
and other key infrastructure components necessary to maintain acceptable 
operations 
Needs Assessment 
Arcadis views the Needs Assessment as a critical component of any project, as the results will 
form the basis for project planning and the implementation sequence for the remainder of the 
project. Figure 2 summarizes our approach to the development of a Needs Assessment, which 
we have successfully used in multiple location to establish the foundation for a successful 
AMR/AMI project. We divide the needs assessment into the following four key project elements, 
each led by a subject matter expert from the Arcadis team:

Page: 
11/43 
• Meters and Sensors  
• Data Collection Technology  
• Software and Integration  
• People and Processes 
 
Figure 2 – Needs Assessment Approach 
The needs assessment will address all the elements described by the City.  Our team will identify 
and document business and technical requirements taking into consideration current and future 
needs, industry trends, and the financial and people aspects of the proposed solution.  The analysis 
will seek the optimal alternative and will involve identification of process improvements, which will be 
documented to support the implementation phase of the project. 
Upon given the notice to proceed, Arcadis will immediately prepare a Request for Information (RFI), 
which will catalog the information and documentation that Arcadis will review in preparation for 
subsequent project tasks. Examples of the types of information we will request include:  
 
• 
Exports of meter inventory, water consumption, and billing data  
• 
Meter testing results from past testing efforts 
• 
Meter specifications, standard details, and/or recent procurement information 
• 
Meter sizing and installation procedures 
• 
Meter reading, maintenance, and billing procedures 
• 
Existing operational cost information 
• 
Existing water rates and wholesale water agreements 
After initiating the project, Arcadis will conduct a series of interviews with key project 
stakeholders and subject matter experts. The project team interviews will be cross-function and 
will include participation from staff responsible for IT, finance, customer service, billing, meter 
operations, and engineering.

Page: 
12/43 
Figure 3 – Arcadis Meter Replacement Planning Analysis Tool 
The results of the needs assessment will provide a primary input into other project activities, and 
will define the functional and technical requirements for the AMR/AMI system that will be 
included in the procurement documents.  
 
Meters 
The Arcadis team will evaluate the 
current state of the City’s water 
meters to determine the most 
advantageous approach to 
modernizing the City’s water meter 
population based on both technical 
and economic considerations. We will 
collect, organize, and evaluate the 
City’s exiting water meter population 
using our proven meter replacement 
planning analytical approach. Using 
our existing meter replacement 
planning analysis tools developed in 
Microsoft PowerBI, we will: 
• Summarize water meter inventory 
data based on key parameters 
such as meter manufacturer, size, age, location, and cumulative flow. 
• Estimate current water meter accuracies, using readily available City data and published 
meter accuracy test literature.  
• Determine the total value of water lost due to meter inaccuracy based on existing water rates 
for the City. This information is used during the roadmap development to compute the 
economic opportunity of replacement for the various meter sizes based on cumulative flow 
through the water meter. The cost of the new replacement meter and the labor for removal 
and replacement of the existing meter are keys to the economic optimum. When the value of 
lost water and meter replacement cost are equivalent at a specific cumulative water use, the 
meter should be replaced. 
 
Data Collection Technology 
The AMR/AMI marketplace is rapidly evolving, resulting in a wide range of meter reading 
technology architecture considerations. The Arcadis team will evaluate the key areas of 
technology and security, including: 
 
• Telecommunication methods and protocols used, including evaluation of cellular and open-
standards networks 
• The data collector type and design 
• The backhaul methods used 
• Considerations for cloud-based architectures 
• Technology standards 
• Mounting and connection options for meters, endpoints, repeaters, and data collectors 
• Requirements for disaster recovery, backup, and business continuity 
• Battery life and warranty provisions

Page: 
13/43 
• Availability of advanced sensors, including leak detection and water quality sensors 
• Review of City owned assets, which could be useful for siting AMI equipment. 
 
Arcadis will review existing security, hardware, and software standards across the City with the 
objective of evaluating existing preferred vendor list for equipment. Arcadis will assess 
AMR/AMI network alternatives and provide recommendations for suitability to the City’s 
standards and comparison to best practices. 
 
Arcadis will assess the City’s cyber security risk management approach and will provide 
recommendations regarding its robustness, scalability, functionality, and overall alignment with 
industry best practices as it relates to the system impacted by the project. 
 
Finally, Arcadis will evaluate the City’s existing network support model and provide guidance on 
how to support the AMI infrastructure long-term, including recommended organizational models, 
skills, training, and certification requirements. 
 
Software and Integration 
For the AMI system to be fully functional it will need to be successfully integrated with the City’s 
existing applications and business processes, including the NorthStar Customer Information 
System (CIS). We will determine the integration needs that will be brought about by the 
AMR/AMI system and will coordinate those needs as required. Specific areas that we will 
evaluate include: 
 
• Determine the need for a meter data management (MDM) system. 
• Determine how City will use existing data and systems to support the meter installation 
project. 
• Identify the future needed AMR/AMI interfaces and the overall integration architecture that 
will be needed to get the most from the AMR/AMI system. 
• Document the current and planned use of mobile computing and determine if change or 
expansion of the use of mobile computing will be required by the AMR/AMI project. 
• Evaluate the need to integrate with the City’s asset management application (Lucity) to 
streamline work orders to support field customer support and meter replacement efforts, and 
recommend the timing of such integration.  
• Understand the current tools being used or planned to support data analytics and reporting, 
including tools for managing nonrevenue water. 
• Determine the process and technology integration requirements for the AMR/AMI related to 
other on-going distribution system optimization efforts, including the hydraulic model and 
water quality monitoring systems. 
• Evaluate available options for the field deployment management system, considering 
available technologies and commercially available systems. 
 
People and Processes 
The AMR/AMI system will bring about significant changes to the meter reading, meter 
maintenance, operations, billing, non-revenue water management, and analytical business 
processes at the City. As part of the needs assessment, the Arcadis team will evaluate the 
business processes improvement opportunities that the AMR/AMI will bring about and then use

Page: 
14/43 
this information to support other project planning activities such as procurement and change 
management. Using information gathered during interviews, coupled with our deep 
understanding of utility meter-to-cash business processes, Arcadis will pre-draft “as-is” business 
process models for each functional area. We will then conduct a series of process modelling 
review workshops with the City to validate and refine the “as-is” models. We have found that 
process modelling workshops are much more effective when a pre-drafted model is used as a 
starting point.  
 
We will review the business processes and workflows with the project team to verify their 
relative correctness and to provide a complete, consistent, and common view among 
stakeholders of the existing business environment, which we will then use to drive all AMR/AMI 
planning and decision making. Using the documented current state processes as a tool, Arcadis 
will work with the City to identify process improvement opportunities and to determine which 
improvements will be expected as outcomes of the AMR/AMI implementation. 
 
Based on our past work with similar organizations, we believe that the following process 
improvements can be attained with the new AMR/AMI system, and we will work to expand this 
list as part of the business process needs assessment: 
 
• Meter reading processes, including the process to perform final reads and move-in/move out 
actions, will significantly improve with the new AMR/AMI. 
• Customer service processes related to account servicing and response to billing inquiries will 
improve significantly, as agents will have significantly more usable meter reading information 
at their disposal. 
• The AMR/AMI may allow for optimizing meter read routes and billing cycles. 
• New processes will be required to monitor and maintain the new AMR/AMI. 
• New processes for water leak detection and water loss reduction will be possible with the 
new AMR/AMI. 
 
As part of the needs assessment, the Arcadis team will identify the areas that will be most 
impacted by the new AMR/AMI through the development of a change impact assessment. We 
will perform a staffing analysis that details the current technical staff structure at the City and 
recommends staffing required to support an implementation program of this size and 
complexity. This analysis will make recommendations for changes in staff tasking and staffing 
levels throughout project implementation and after project completion.  
 
AMI Business Case Evaluation 
Based on the preliminary requirements identified as part of prior tasks, Arcadis will develop a 
business case for the implementation of AMR/AMI and metering technologies compared to the 
current state. The business case evaluation will evaluate alternatives for AMR and AMI, 
compared to the current state. The analysis will look at the total cost of ownership, including 
meter replacement, network maintenance, software maintenance and support, and integration.  
We will also look at scenarios that involve solutions fully managed by a third party, as well as 
hybrid options in which the City plays a role by maintaining components of the AMR/AMI 
solution.

Page: 
15/43 
Arcadis will perform an economic analysis as part of the business case that will form the 
basis for determining the feasibility of the performance based contracting model. The 
business case evaluation will include the development of the estimated cost for each potential 
technical alternative that meets the requirements identified by the team. Cost estimation 
capabilities are built into our meter replacement analytical model and are based on our meter 
replacement cost estimating database. We break down the cost estimate into the major system 
components including cost categories such as water metering, AMI/AMR endpoints, data 
collection equipment, software and integration, installations, etc.  
The cost estimate is them compared to the anticipated benefits that will result from the 
AMR/AMI, including items such as enhanced water revenue, improved customer service, and 
re-allocation of meter maintenance staff.  
The business case will consider:  
Summarized problem statements 
We will use the results of the prior tasks to define a 
concise set of current-state problems.  
Detailed description of alternatives 
We will identify and define up to three relevant alternatives 
based on the current state and system requirements.  
Life-cycle costs for identified alternatives 
Using data from recent successful AMI procurements and 
vendor information, we will develop life-cycle costs for 
each identified alternative.  
Benefits of each alternative 
Benefits are the core of the business case, and as such 
we will place special emphasis on their definition. We will 
identify both tangible and intangible benefits, using the 
tangible benefits to calculate key investment metrics, such 
as return on investment, benefit-cost ratio, and pay-back 
period.  
Implementation schedule for identified alternatives 
We will consider schedule differences for each identified 
alternative and will develop the planning level schedule for 
the recommended alternative.  
Risks 
We will identify potential risks for the identified project 
alternatives.  
Key assumptions 
We will document assumptions used during the 
development of the business case.  
Key Performance Indicators (KPIs) 
We will suggest metrics that can be used in the future to 
confirm the benefits of the program.  
 
Alternative Funding Analysis 
Many utilities are challenged with securing funding for entire meter replacement and AMR/AMI 
project. Incomplete funding can protract the project timeline and erode the anticipated benefits. 
If funding is a challenge for the City, Arcadis recommends considering alternative funding 
options such as federal grants and/or loans which are available in the water utilities. Arcadis’ 
funding team has a great track record supporting our clients with identifying possible grants

Page: 
16/43 
that align with the project objectives and can support the City with the grant application 
process. Since we began this work on grant funding efforts, we have supported our clients to 
win grant funding of about $5 billion. Last year, we secured grant awards of nearly $30 million 
for non-disaster grants. We are currently assisting Greene County, OH and PRASA with 
securing funding for their meter replacement and AMI programs.  
Arcadis shall identify sources that the City can employ to support the funding, in whole or in 
part, for the full implementation of a meter replacement program inclusive of new meter reading 
systems and processes. Specific activities include:  
• Inform and assist the City with identifying relevant funding options and narrow potential 
options to ones that the City may explore further.  
• The research will study traditional funding sources, federal grants, and other innovative 
options for the City’s consideration. 
• For grants, Arcadis will summarize the key steps to obtain funding, high-level lifecycle, and 
timeline, and any applicable restrictions or caps. 
• Explore alternative delivery and cost sharing models, including the use of utility partners like 
telecommunication companies and other specialized firms, which can address the partial or 
total funding for the AMR/AMI solution, in exchange for a service concession.   
 
Requirements Definition 
Arcadis will develop the technical requirements for the meter replacement and AMR/AMI with 
emphasis on the following areas: 
 
• Meter replacement approach, including meter types, applications, and related specifications. 
• System deployment model giving consideration for options such as software-as-a-service 
(SaaS) and network-as-a-service (NaaS)  
• System performance specifications and warranty provisions   
• Telecommunication methods and protocols used  
• The data collector type and design  
• The backhaul methods used and available City assets  
• Technology standards 
• Mounting and connection options for meters, endpoints, repeaters, and data collectors  
• Software functional and technical requirements for the AMR/AMI, with a an emphasis on the 
software interfaces.  
 
We will then conduct a series of requirements workshops where we will present for discussion 
the requirements ranking, focusing on clear definition and agreement on the high-priority 
requirements. 
Project Plan 
At the completion of the needs assessment Arcadis will develop a project plan that will 
establish the path forward for the selection AMR/AMI system. The project plan will include an 
updated estimate of project cost, and will recommend an appropriate scope and detailed 
strategy for the project including timelines and phasing for procurement of supplies, 
infrastructure deployment, and system testing.

Page: 
17/43 
4) 
Describe your firm’s approach for completing the objectives as they relate to the 
development of the solicitation to procure an AMR/AMI system: 
a. Assist the city in developing an RFP for an AMR/AMI system using 
performance-based contracting that include Key Performance Indicator’s 
(KPI’). 
b. Respond to vendor inquiries regarding system requirements in conjunction 
with the Procurement Office. 
c. Participate in the process to evaluate proposals from vendors. 
d. Attend pre-proposal conferences and vendor interviews. 
e. Assist the city in reviewing and evaluating the proposals received from the 
RFP. 
f. Prepare a written report that outlines the evaluation, clarifications, and 
recommendations. 
g. Provide a report detailing a recommended system and program through site 
visits and on-site interviews. 
h. Make presentations, as necessary, explaining evaluation results and 
recommendations. 
Procurement (Solicitation Development) 
Arcadis will support the City throughout the solicitation development process as an 
owner's agent and will help with activities such as RFP development, issuance of 
addenda, proposal evaluation, award recommendations, and contract negotiations. The 
result of these efforts will be a signed contract or contracts for the AMR/AMI system that 
most closely matches the needs and requirements of the City. We will work with the City to 
develop the AMR/AMI solicitation and to complete the procurement of the AMR/AMI, following 
the guidelines defined by the City’s procurement department for the required contract 
vehicles, resulting in the best value selection of the AMR/AMI. We will leverage our AMI 
experience and support from the City’s procurement team to document a procurement and 
proposal evaluation process that will result in the selection of the best fit solution. 
 
RFP Development 
Arcadis will use the outcomes from needs assessment to develop the RFP package. Our team 
will work closely with the City’s procurement department to ensure we are compliant with the 
City’s purchasing rules and regulations. This effort will also include reviewing and 
validating the performance metrics suggested during the requirements phase of the project.  
Arcadis will work with the City to identify final KPIs, which will be used to manage the 
implementation progress and benefits of the AMR/AMI system.

Page: 
18/43 
Proposal Evaluation 
Arcadis will provide a robust proposal evaluation process and methodology that stems from 
our experience deploying AMI solutions. Our typical methodology is a four round proposal 
evaluation process as shown in Figure 4. We will work with the City to tailor this proposal 
evaluation methodology to align with the City’s procurement policies and procedures. 
Arcadis will manage the RFP process, including conducting a pre- proposal meeting and 
managing the development and distribution of any required RFP addenda. 
We develop a balanced scorecard that will enable the selection team to rate the candidate 
AMI vendors objectively based on the set of criteria that were established as part of the 
procurement planning process in alignment with the requirements of the City’s procurement 
department and the State of Arizona. Our technical experts review all vendor proposals to 
determine compliance with procurement requirements and minimum qualifications. Arcadis will 
facilitate a thorough review and assessment of technical responses with the City’s selection 
team members. During these sessions, our technical experts will provide clarity and 
explanation to support the team’s understanding of the responses to fairly assess the 
technical proposals. 
Additionally, our team will prepare a cost comparison analysis from all proposers and prepare 
a cost comparison deliverable for the City team. Developing a cost comparison model starts 
with the RFP Package Pricing Forms. The RFP will include pricing forms, which will guide the 
proposer to provide the right level of pricing detail. 
 
Figure 4 – Example Proposal Evaluation Approach 
 
The cost analysis will use capital costs, annual recurring costs, and the project deployment timeline 
to develop a lifecycle cost analysis. Arcadis uses a net present value (NPV) approach for the lifecycle 
cost analysis using the City’s solution life (typically 15 or 20 years).  
With this initial technical and pricing assessment complete, the City selection team will be ready to 
identify a shortlist to invite for interviews. Arcadis will prepare for and facilitate interviews with 
vendors to include an implementation approach, qualifications, and vendor specific questioning. 
Demonstration evaluation guidelines are developed and provided to selection team members. 
At the completion of all demonstrations, Arcadis will facilitate the final selection process. Upon our 
final selection, we will prepare City staff to bring the recommendation for final approval.

Page: 
19/43 
Contract Negotiation and Award 
Once the vendor selection is final, we begin to move the requirements from the proposal 
request document into the contract to ensure the utility’s desired responsibilities, timeline and 
outcomes are crystal clear to all parties. The contract must include an agreement that all system 
elements will be met to achieve project success and precisely how success will be measured.  
 
Arcadis provides experienced practitioners who have negotiated multiple AMI and installation 
contracts in the past. This experience will result in a contract that is favorable to the City and 
covers all project elements. We will facilitate the work plan development between the selected 
vendor and project team to include identified resources, timelines, responsibilities, professional 
services, high level project plan, detailed Statement of Work (SOW), and change management 
procedures, both in-house and with the selected vendor(s). 
 
Solid contracts will at minimum include the following sections: 
 
• Specifications/deliverables 
• Delivery schedule 
• Definition of payment schedule and earned value management 
• Testing and acceptance criteria 
• Service levels to meet (response times, batch billing window, meter read and transmission 
rates, etc.) 
• Customer service protocols 
• Support and maintenance (hours of support, limits on annual fee increases, enhancements 
incorporated into future base releases, etc.) 
• Documentation (installation guide, operating guide, training material, etc.) 
• Allow assignment of agreement to subsidiary or subcontractor 
• Contract termination procedures 
• Confidentiality clause 
• Warranties and remedies (time to fix defects, location of warranty service, compatibility with 
operating systems, hardware and other system components) 
• Performance bond and/or payment terms upon completion of agreed to milestones 
• Dispute resolution processes (use of arbitrator, location). 
 
Once the contract is signed and agreed upon, we will notify all vendors of the selection and 
proceed with onboarding the AMR/AMI vendor and implementation team.

Page: 
20/43 
5) 
Describe your firm’s approach for completing the objectives as they relate to the 
implementation of the chosen AMR/AMI system: 
a. Coordinate with the selected water meter AMR/AMI system contractor to 
prepare an implementation plan for the selected system. 
b. Monitor vendor compliance as Glendale’s representative during system 
installation and start-up. 
c. Coordinate with software and hardware contractors to resolve system 
implementation issues.  
d. Develop a strategy for phasing project management of the AMR/AMI program 
to City staff at a defined project benchmark. 
Our AMR.AMI implementation approach has been constructed based on the Arcadis team’s 
experience with similar large-scale meter replacement and AMR/AMI projects. Our approach 
places a large emphasis on formal project management processes and thorough quality control 
processes, which ensure proper contractor coordination and oversight. It is rooted solidly in 
Project Management Institute’s (PMI) project management body of knowledge, which we have 
built-out to reflect the unique needs of a large-scale customer service transformation and AMI 
project. We accomplish the implementation objectives by performing the following activities.  
Implementation Coordination / Project Management 
The Arcadis team, led by their project manager Michael Rotunno, will perform on-going 
implementation coordination, framed within the project management, monitoring, and control 
activities for the duration of the AMR/AMI implementation project. The following activities will be 
performed on an on-going basis and adjusted as required based on the project phase.  
 
Integrated Schedule Management. Develop, monitor, and maintain in integrated project 
schedule using MS Project or an equivalent schedule management package. 
 
Scope Management and Change Control. Manage overall project scope and identify to the City 
when a task is outside of scope. Institute and manage change management processes.  This 
effort will include coordinating with the selected water meter AMR/AMI system contractor to 
prepare an implementation plan for the selected system. 
 
Cost and Earned Value Management. Manage the financial performance of all project elements, 
including evaluation of earned value as needed to support payments to the system vendors and 
installation services firms, based on the performance criteria defined in the contract documents.  
 
Project Human Resources. Monitor project staffing needs, team performance, and on-boarding 
processes.  This activity will include working with the City to develop an AMR/AMI system 
phasing strategy and staffing plan, which will ensure proper transfer of responsibilities over to 
the City staff at the right time. 
 
Project Risk Management. Implement the risk management processes and provide continued 
update to the risk register and controlling processes, including coordination with meter installers,

Page: 
21/43 
network solution implementors, and software and hardware contractors to resolve system 
implementation issues. 
 
Maintain Project Documentation. Publish and maintain all project documentation. This includes 
producing minutes at all meetings, maintaining all documentation of decisions, tracking of 
issues, and management of other project-related documentation and deliverables. Deliverables 
will be electronically deposited in a central repository for the capture and re-use of intellectual 
assets. The project manager will manage all deliverable review and approval processes, and 
will obtain sign-off from the City on all project deliverables. 
 
Conduct Status Meetings and Develop Status Reports. Arcadis will conduct regular project 
status meetings with project team members from the City, the project management team, the 
AMR/AMI vendor, and other stakeholders as needed. Meetings will be accompanied by regular 
project status reports that will summarize work performed, upcoming work, schedule, risk, action 
items, and budget performance. 
 
Quality Control Planning. Arcadis will develop a detailed quality control plan that will account 
for all require quality control and acceptance testing activities for the project. In general, we 
expect that the plan will address the software, integration, meter installation, and AMR/AMI 
endpoint deployment.  
Executive Steering Committee Meetings. In addition to the regular project team status reports 
and status meetings, Arcadis will conduct regular Executive Steering Committee (ESC) 
Meetings, generally on a monthly basis. Project information is provided to ESC in the form of 
Monthly Project Status Reports, which include project key performance dashboards. The report 
will be reviewed as part of a monthly steering team meeting, the outcome of which will include 
decisions about resources, change items, and overall project direction. 
Software and Interfaces Quality Control 
As indicated before, Arcadis will work with the selected water meter AMR/AMI system contractor 
to prepare an implementation plan for the selected system. The implementation plan will include 
a testing strategy and approach that will define the test activities to be performed, the test data 
strategy, testing environments, testing tools, testing procedures, and the sign-off process. 
Arcadis will prepare a quality assurance plan that will define the required testing 
activities for the project, which will be a critical element to help monitor vendor 
compliance as during system implementation and start-up.  The elements of the quality 
assurance plan may include: 
Functional Testing. Functional testing ensures that the delivered AMR/AMI control and 
monitoring software is tested and aligned with the City’s business requirements. Modifications, 
enhancements, and reports are tested during this phase. Functional testing will be performed by 
the City testing team with assistance from the Arcadis project management team.  
 
Integrated System Testing. Integrated system testing ensures all application components are 
working as a complete solution rather than merely in isolation, with an emphasis on the 
integration with the NorthStar utility billing system. This include testing of all system interfaces 
and testing of all end-to-end processes, such as for meter installation, meter reading, and billing

Page: 
22/43 
operations. System testing is performed by end users with involvement from the project 
management team and the power users. 
 
Test Script Design, Planning, and Tracking. The Arcadis testing team will design test scripts 
and a tracking method to ensure the system is fully tested prior to the final cutover. They will 
facilitate testing of all impacted systems in conjunction with City staff, and will periodically report 
upon testing progress through the overall project reporting process.  
 
Issues Tracking. The Arcadis testing team will design an issues tracking method to monitor 
issues, gaps, and defects found during testing activities, and report on progress towards their 
resolution. 
 
Arcadis will manage all testing activities for the AMR/AMI project. Based on the detailed test 
plans for each system, the Arcadis project management team will support the City by: 
 
• Developing test cases and scripts 
• Prepare testing environments and data, in conjunction with the system administrators and the 
AMR/AMI contractor 
• Work with City staff to execute the test cases 
• Identify, log, analyze, and assign defect 
• Manage defect resolution 
Installation Quality Control 
Arcadis will provide quality control for AMR/AMI deployments related to hardware installation, 
including best practices, data validation, and verification. Our team of industry experts 
understands the impact of proper installation and accurate data gathering, has been involved in 
the business for many years and have curated a group of tests and best practice 
recommendations that have helped hundreds of customers across the country. 
 
In general, the deployment quality assurance will include things such as: 
 
• Verification of endpoint availability and meter read transmissions to confirm that the 
AMR/AMI meets the established system performance specifications. 
• Installer quality reviews to determine the competence of new AMR/AMI installers. 
• Data quality reviews, to verify that device and installation data collected in the field is correct.  
  
Figure 5 – Example Meter and Endpoint Installation Acceptance Dashboard

Page: 
23/43 
Arcadis will manage installation quality assurance as defined in the quality management plan 
and installation vendor contract. Once the equipment is installed, our quality control team 
verifies the installations in a few different ways. First, and most critically, is investigating the data 
coming into the AMR/AMI system. This data can provide information on which specific 
installations should be investigated physically in the field. Once the data is provided from the 
installation team, we also verify the numbers reported match the AMR/AMI system, preventing 
billing errors. Finally, the project’s field team is deployed to investigate issues as well as to 
perform random sampling.  
Customer Communication  
This project will be particularly visible and touch the public in a very personal way. Arcadis will 
ensure that the implementation plan incorporates a section to address customer 
engagement and communication.  The AMR/AMI system implementation effort will require 
targeted and consistent communication to inform stakeholders, excite them about the benefits 
the new infrastructure offers and garner their support for the transition to an AMR/AMI system. 
Arcadis typically recommends that a customer communication program be initiated early in the 
project, starting with the development of a communication plan. 
We will identify the various audiences (such as residential customers, local area businesses, 
larger commercial customers, impacted City personnel, etc.) to appropriately segment 
stakeholders and allow for customized messaging that meets the needs of each constituency. 
For example, commercial and critical care providers may require different communications than 
residential customers. 
To develop the communication plan, the Arcadis team will perform the following activities: 
• Communication Planning Workshop. We will facilitate a workshop with the City project 
team members to present our current view of the issues at play; to collectively think through 
potential approaches; and gain consensus among the decision makers on your team about 
an appropriate communication strategy. 
• Communication Plan Development. We will draft a communication plan crystallizing our 
audiences, their wants and needs, strategies and tactics to provide a better offer, and a 
phased timeline for the project. 
• Quick-Launch Materials. We have found that having a base set of informational materials 
very quickly into the project is important, as it is possible for residents and elected officials to 
start asking questions very early in the process. We will use our past project examples to 
quickly produce a set of communication tools such as internet page updates, frequently 
asked questions (FAQs), project briefings, and system overview materials.

Page: 
24/43 
6) 
Provide a detailed project plan that includes tasks, resources (City and 
Consultant), and timelines to include the following milestones:  
a. Project Kickoff with City project team  
b. Project Management 
c. Needs assessment 
d. Project plan with City project team   
e. RFP draft and release 
f. RFP evaluation 
g. Council presentation of project  
h. RFP award 
i. Implementation Project kickoff 
j. Project Phase 1 - Pilot/technology installation and testing of AMR/AMI and IT 
System automation. 
k. Optional Project Management Services   
l. Project Phase 2 - AMR Deployment – automate routes with AMR ready meters 
m. Project Phase 3 - Meter Replacement – automate routes with predominately 
older meters. 
n. Deliver a Final Report with findings from the tasks above and 
recommendations. 
Arcadis has aligned our standard AMI program implementation methodology with the 
requested scope of work. We have divided the implementation into three phases as 
requested in the RFP and will confirm the implementation sequencing as part of the 
needs assessment and project planning:  
• 
Implementation Phase 1 – Pilot/technology installation and testing for AMR/AMI and 
IT System Automation 
• 
Implementation Phase 2 – AMR Deployment – Automate routes with AMR ready 
meters  
• 
Implementation Phase 3 – Meter Replacement 
 
As part of the project preparation and initiation, Arcadis will prepare a detailed work 
breakdown structure (WBS) and schedule model using MS Project showing additional 
details about significant activities and deliverables for all phases.

Page: 
25/43 
Figure 6 – Project Plan

Page: 
26/43 
EXPERIENCE, PROVEN PERFORMANCE, AND QUALIFICATIONS 
 
1) 
Provide 1-3 valid references from those who can confirm your experience in 
providing the services stated within this RFP.  The reference may be from 
governmental agency, municipality, schools or companies which the Offeror has 
provided similar services within the last five (5) years.   
Reference 1: 
City of Mesa, AZ 
200 S. Center Street, Mesa, AZ 85210 
Kristi Uyeshiro, Senior Project Manager 
480.283.7797 
Kristi.Uyeshiro@mesaaz.gov 
Ongoing 
Provide a brief summary of Services provided:  
Arcadis provides project management leadership and AMI technical expertise for the planning, 
procurement and Phase 1 implementation of the City's AMI solution. The importance of this 
project with the alignment to the City's Smart City strategy is to advance the City's utility 
services with advanced metering technologies to improve utility operations and enhance their 
customers' experience. The City is focused on empowering utility staff and customers using 
information and data from AMI. 
 
The Smart Meters Project was undertaken by the City of Mesa to install ‘smart’ meters across 
its three utility service offerings. The City has a population of 500,000 and provides water, gas 
and electric services for customers both in City limits and surrounding areas. The City’s water 
system has approximately 153,000 service connections for residential, commercial and 
industrial customers. The City’s natural gas utility serves over 44,000 homes and businesses 
inside City limits and an additional 25,000 in the Magma service area southeast of the City. 
The City also provides electric utility services to approximately 17,000 residential and 
commercial customers located within a 5.5 square mile area centered around Mesa’s 
downtown area. 
 
The project implementation is about three to four years. It is expected that the City will 
conclude an initial deployment of about 2,000 smart meters in 2022. City-wide deployment 
across all three utilities is targeted to be completed in 2025 – 2026.  
 
In 2018, the City established their Smart City vision and master plan, Smarter Mesa. The City’s 
vision is to leverage technologies and data-driven insights to improve quality of life, citizen 
engagement, public safety, economic development, service delivery and community vibrancy. 
 
The City desires to provide responsive solutions that enhance the live, work and play 
experiences of people in the community. 
 
The overarching Smart Metering Project goals are: 
 
• Align with the City’s overall Smart City initiative. The Smart Metering Project is an 
• initiative under the City’s Smart City Program which supports the City’s Smarter 
• Mesa themes, Smart Government and Smart Infrastructure. 
• Improve or enhance utility to customer communication. The City wants to

Page: 
27/43 
• enhance their customer’s experience in every interaction, making things easier to 
• resolve concerns and do business with the City. 
• Improve operational effectiveness and productivity. Streamlined processes, less 
• rework, less manual processes, less truck rolls, better response times, improved 
• safety and more employee opportunity are all key expectations and outcomes 
• from the AMI project. 
• Encourage a forward-thinking culture across the City’s three utility offerings. The 
• City is on their journey to transform the utility into a smarter utility. Leveraging 
• advanced technologies is part of this foundation to enable employees and change 
• the culture to one that incorporates data-driven insights into their day-to-day 
• work. 
 
Total project cost: $1.5 million 
 
Reference 2: 
Puerto Rico Aqueducts and Sewer Authority 
(PRASA) 
  
 
Maria Bartok 
787.620.2277 
Maria.Bartok@acueductospr.com 
On-going 
Provide a brief summary of Services provided:  
 
Arcadis has been engaged by PRASA since 2006 as its Consulting Engineer and has provided 
business advisory as well as financial support services. PRASA serves approximately 3.2 
million residents plus approximately 1 million tourists annually. Through this engagement, 
Arcadis has provided a variety of services including:  
 
• Asset Valuation 
• Cost of Service 
• Rate Restructuring 
• Financial Modeling 
• Cost and Rate Projections 
• P3 Procurement / Advisory 
• Bond Issuance 
• Affordability 
• Policy Review 
• Financial Modeling 
 
Of special relevance to the City’s AMR/AMI project, Arcadis provided Public-Private 
Partnership (P3) Assistance. Arcadis provided technical advisory and assistance for the P3 
procurement of a design-build- finance team for the design and construction of PRASA’s 
$200M dam, reservoir and raw water intake pump station project in the Valenciano Region. 
Activities included development of request for qualifications, comprehensive evaluation of 
prospective bidders’ statements of qualifications and development of detailed request for

Page: 
28/43 
proposals, including finance and agreement terms, issued the pre-qualified bidders. Arcadis 
also served as technical advisory and transaction consultant for the P3 procurement for 
implementation of AMR/AMI system and provision of customer services. We developed the 
specifications for the system, assisted with the evaluation, and supported the contract 
negotiations. 
 
Total project cost: $9 million (Multiple projects over 15-yr period) 
 
  
Reference 3: 
City of Tempe, AZ 
31 E. 5th Street, Tempe, AZ 85281 
Tarja Nummela, Customer Service 
Administrator 
480.350.8361 
tarja_nummela@tempe.gov  
On-going 
Provide a brief summary of Services provided:  
 
SL-serco is currently providing AMI consulting services to the City of Tempe. To start the 
process of deploying an advanced metering system, SL-serco has helped the City of Tempe 
with strategic and project planning, including education and documentation. To begin this 
process, SL-serco and the City of Tempe established a project team with key stakeholders 
from each department. This team, including SL-serco’s subject matter experts and change 
management experts, developed a set of requirements and goals for the program. Using these 
requirements and goals for the utility, SL-serco presented possible advanced metering 
solutions that would suit the utility. To best educate the project team, the project team then 
invited local vendors to present solutions and the technology available today. SL-serco then 
narrowed the cases down to four possible solutions to be evaluated for the City of Tempe. The 
cases were then evaluated for their costs and benefits. SL-serco recommended a full AMI 
deployment in a three-year period, and this was ultimately the direction taken. 
 
SL-serco provided assistance through the procurement of a full AMI system after this decision. 
Using the requirements and documentation created in the planning phase, SL-serco’s team 
assisted the City of Tempe in the creation of an RFP. Once released, SL-serco facilitated 
vendor questions and requests for the document. Upon the receipt of vendor responses, SL-
serco and the project team evaluated the proposals and came to a decision that best suited the 
City’s needs. SL-serco then facilitated contract negotiations between the City of Tempe and its 
selected vendor. 
 
As of this proposal, SL-serco has finalized deployment and validated the system; SL-serco is 
now helping the City of Tempe build a digital twin and analyzing their AMI data with SCADA 
information to build better rate structures. Key values that SL-serco provided include system 
verification, including user acceptance testing and system acceptance testing; tightly monitored 
and corrected vendor performance; and multi-system data integration, including large data 
management efforts. As SL-serco works with the City of Tempe to better use the data coming 
from their systems, we continue to refine their business processes and program success KPI’s. 
 
Total project cost: $600,000

Page: 
29/43 
 
2) 
Provide a brief history of your organization including the past performance on 
project of similar scope and size, level of knowledge, reliability, flexibility and how 
your firm is able to meet project deadlines.  
Arcadis has the proper experience to fully support the City through all phases of your 
AMR/AMI project. The following table provides a summary of our relevant experience.  
 
Client Name 
 
 
 
Project Name 
Approx. # of 
Customer 
Accounts/ Meter 
Endpoints 
Water, 
Wastewater, 
Gas, Electric 
WSSC Water 
AMI Project Management 
W, WW 
City of Phoenix, AZ 
Meter-to-Bill Evaluation 
W, WW 
City of South Bend, OH 
Meter-to-Cash Evaluation and Utility 
Billing Implementation Management 
485,000 
420,000 
43,000 
W, WW 
Birmingham Water Works Board, AL 
SAP Customer Relationship and 
Billing Implementation and 
Upgrades 
270,000 
W, WW 
City of Wichita, KS 
Metering and Billing Improvements Plan 
W 
City of Mesa, AZ 
AMI Consulting and Project Management 
W, G, E 
City of Scottsdale, AZ 
Residential Water Meter Study 
W 
Youngstown, OH 
Water Meter Engineering Services 
W, WW 
City of Tucson, AZ 
Water AMI Strategic Plan and Pilot 
W 
St. Marys, OH 
AMI Planning and Selection 
W, E 
City of Columbus, OH 
Water Audit and Non-Revenue Water 
Analytics 
150,000   
230,000 
88,000 
55,000 
30,000 
5,000 
300,000 
W, WW 
Puerto Rico Aqueduct & Sewer 
Authority 
Owners Agent for Optimizing PRASA’s 
Metering Infrastructure and Customer 
Service Experience 
1,200,000 
W 
Chicago Department of Water Management 
Water Infrastructure Program 
W 
USEPA 
Advanced Metering Infrastructure Primer 
W 
Greene County, OH 
Advanced Metering Study 
W 
Chesterfield County Utilities (SL-serco) 
AMI System Plan 
W, WW 
City of Tempe, AZ (SL-serco) 
AMI System Plan, Procure, Deploy 
W, WW 
City of Winter Park, FL (SL-serco) 
AMI System Deploy and Optimization 
162,000 
NA 
22,000 
115,000 
80,000 
28,500 
W, WW, E 
Fort Worth Water District, TX (SL-serco) 
AMI System Plan, Procure, Deploy 
W, WW 
Huntsville Electric Co-op (SL-serco) 
AMI System Deploy 
W, G, E 
Lee County Water (SL-serco) 
AMI System Deploy and Optimization 
W, WW 
Town of Cary, NC (SL-serco) 
AMI System Deploy and Optimization 
W, WW 
WV Water Authority (SL-serco) 
AMI System Deploy and Optimization 
240,000 
63,000 
85,000 
52,000 
64,000 
W, WW

Page: 
30/43 
 
3) 
Describe how your firm is prepared to respond promptly to problems and any 
changes to scope of work. 
Arcadis has supported the City for over three decades, addressing your needs in very diverse 
areas, from the design, construction and automation of your treatment plants, to the design and 
construction oversight of your fiber optic network, just to name a few examples. Arcadis is 
committed to bring the same level of support, expertise and responsiveness expected by the 
City to this project.  We have assembled a team of national experts, who will be supported by 
local staff with first-hand experience delivering similar projects in the Valley. The following 
elements of our team and approach demonstrate that we are fully prepared to respond promptly 
to problems and any changes to scope of work: 
 
• Our Project Principal, Esteban Azagra, is local and knows the City well. In fact, he 
started his career supporting the City during the construction and automation of your West 
Area Water Reclamation facility. 
• Our project manager, Michael Rotunno, is a national expert fully committed to 
delivering projects locally. He has supported local clients like the City of Phoenix and the 
City of Mesa in a similar fashion, and will be responsible for managing the elements of the 
project management plan described earlier in the document, which will ensure proper risk 
management, change control, and overall quality management. 
• Our proposed local project team are members of our Arizona technology and IT 
consulting center of excellence, which is located 15 miles away from the City.  The 
team has a proven track record delivering technology solutions for other cities in the Valley 
and is ready to respond locally to any immediate need right away.  
 
3. CAPACITY OF OFFEROR 
 
1) 
Identify the key team members to be committed to the project and provide the 
following for each: 
a. Role of the person and Responsibilities 
b. Qualifications 
c. Home office location 
d. Length of time with firm 
e. Availability of key staff members 
f. Percent of their work to be done locally for this project if awarded 
g. Relevant experience on similar or related projects. 
h. Demonstrated performance record.

Page: 
31/43 
 
Figure 7 – Project Team Organization 
Name 
Esteban Azagra, PMP, EurIng, IAM 
Role of the person 
and Responsibilities 
Project Principal 
As the Project Principal, Mr. Azagra will be responsible for allocating 
company resources to the project, will serve as a point of escalation, 
and will participate in the executive management for the project.   
Qualifications 
Licenses and Certifications  
Project Management Professional - AZ (416947) 
Federation Europeenne d'Associations Nationales d'Ingenieurs (2433) 
Professional Engineer, Spanish Society of Agricultural Engineers 
(3383) 
IAM Certificate, The Institute of Asset Management (1041974) 
 
Degrees 
MS, Civil Engineering, The University of Texas, 1999 
MS, Agricultural Engineering, Universidad Politecnica de Madrid, 1995 
 
Home office location 
Phoenix, AZ 
Length of time with 
firm / Total 
experience 
20/20 
Availability of key 
staff members 
25% 
Percent of their work 
to be done locally for 
this project if 
100%

Page: 
32/43 
awarded 
Relevant experience 
on similar or related 
projects 
 
Demonstrated 
performance record 
 
 
Mr. Azagra leads Arcadis’ Business Advisory Services in North 
America, which focuses on delivering IT/automation, asset 
management, risk & resilience, and financial services to the water 
industry. He has provided extensive management consulting services 
and is an expert in applying technology solutions to the water industry, 
including design and implementation of meter-to-cash solutions. 
 
Smart Metering Project, City of Mesa, AZ 
Project Principal supporting the City of Mesa AMI program. Project 
involves RFP development, solution design and selection, and 
implementation oversight for the replacement of water, gas, and electric 
meters and the creation of an AMI network. 
 
AMI Program, Washington Suburban Sanitary Commission 
(WSSC), DC 
Lead for the Technical Review Board – AMI planning, selection and 
implementation 
 
Planning and Implementing CIS and AMR/AMI Projects (WRF On-
line Report #4583), Water Research Foundation, Denver, CO 
Member of the project advisory committee. 
 
Technology Master Plan, City of Scottsdale Water, AZ 
Project Manager responsible the evaluation of current and future use of 
information technology and industrial control systems to support the 
Scottsdale Water’s future business needs. The technology master plan 
identified, prioritized, and quantified proposed technology investments, 
and served the purpose of future budget planning. Arcadis assessed 
and recommended investments to improve the city’s network 
infrastructure, SCADA, CMMS, AMR/AMI, technology governance, 
compliance management systems, cyber security, non-revenue water 
determination, IoT, and smart water networks. 
 
Birmingham Water Works Board, AL: Billing System 
Implementation 
Quality control reviewer for the implementation of SAP Customer 
Relationship and Billing project.  
 
Name 
D. Michael Rotunno, PE, PMP 
Role of the person 
and Responsibilities 
Project Manager 
As the Project Manager, Mr. Rotunno is responsible for the day-to-day 
management and technical oversight of all facets of the project.  
Qualifications 
Licenses and Certifications  
Professional Engineer – OH 
Project Management Professional, Project Management Institute, 2017 
Lean Sensei, Villanova University, 2013

Page: 
33/43 
Degrees 
BS Civil Engineering Pennsylvania State University, 1997 
MBA Business Administration Case Western Reserve University, 2001 
Home office location 
Cleveland, OH 
Length of time with 
firm / Total 
experience 
9 / 24 
Availability of key 
staff members 
60% 
Percent of their work 
to be done locally for 
this project if 
awarded 
50% 
Relevant experience 
on similar or related 
projects 
 
Demonstrated 
performance record 
 
 
Michael Rotunno is an experienced utility professional with over 20 
years of broad management and consulting experience and 
demonstrated experience leveraging technology to improve 
organizational performance. With Arcadis, Mr. Rotunno is responsible 
for leading large and complex information technology projects for water 
utilities nationally and serves as the Discipline Leader for the North 
America Digital Consulting practice. He has been involved in AMI and 
meter-to-cash programs for the past 10 years, having filled leadership 
roles in AMI programs ranging from 5,000 to over 480,000 endpoints. 
 
Meter Replacement Project Management, Green County Sanitary 
Engineering Department, Greene County, OH 
Mr. Rotunno is serving as the project manager for this effort to replace 
approximately 22,000 water meters and to implement new AMI 
technology. He is leading a team that is responsible for the planning, 
procurement, management, and quality control for the project.  
 
Advanced Metering Infrastructure Project Management, 
Washington Suburban Sanitary Commission, Laurel, MD 
Mr. Rotunno served as the project manager for Washington Suburban 
Sanitary Commission’s (WSSC) during the planning for their AMI 
system. WSSC supplies water and sewer service to 485,000 customers 
located in Montgomery and Price Georges Counties Maryland. Mr. 
Rotunno lead the effort to develop the project  needs assessment and 
business case, and led the development of procurement documents for 
all required goods and services.  
 
Meter Automation and Replacement Program 
City of Cleveland, Division of Water, OH 
Mr. Rotunno served  as Technical Director for CWD’s Clear Reads 
Program, a major initiative to modernize its water meters, deploy AMI, 
and improve meter reading process. The program was initiated in 
spring of 2008, and Mr. Rotunno served as part of the project 
leadership team until his departure from CWD in early 2012.

Page: 
34/43 
AMI Planning and Selection  
City of St. Marys, Ohio    
Arcadis assisted the City of St. Marys with the planning and 
procurement for a new AMI system capable of reading the City’s 5,000 
water and electric meters. Beginning in spring 2014, Mr. Rotunno led 
the development of the project business case which found that the City 
would benefit from an AMI. He then led the development of a Request 
for Proposals (RFP) for the new system and for installation services, 
and managed the procurement process. He was responsible for 
performing technical review of all received proposals, and for 
developing a life-cycle cost analysis for the various solutions. The City 
selected the Sensus FlexNet AMI, and Mr. Rotunno facilitated the 
contract negotiations for the new solution.   
 
Water Meter Engineering Services 
City of Youngstown, OH  
Arcadis assisted the City of Youngstown, OH with an upgrade to their 
55,000 water meters by providing water meter engineering services. 
Mr. Rotunno served as the project manager for this effort. Arcadis first 
developed specification documents and helped to City bid new 
replacement water meters. Arcadis then developed the project business 
case and request for proposals for the new AMI system, and supported 
the City through the selection and procurement process. The City is 
now in the process of installing the Sensus FlexNet AMI solution, using 
Sensus iPearl water meters. Mr. Rotunno supported the deployment of 
a mobile service order application that will be used by City staff to 
support the AMI installation and meter replacement program, as well as 
on-going meter service order work.    
 
Name 
Gary Trachtman, PE, CDT 
Role of the person 
and Responsibilities 
Subject Matter Expert – Water Metering 
As the water metering subject matter expert, Mr. Trachtman will lead 
the meter replacement planning analysis performed as part of the 
needs assessment and will advise the project on the technical aspects 
of water metering throughout the life of the project.  
Qualifications 
Licenses and Certifications  
Professional Engineer 
Certified Construction Documents Technologist (CDT) 
 
Degrees 
MSCE Sanitary Engineer New York University 1972 
BSCE Sanitary Engineering Northeastern University 1969 
 
Home office location 
Boston, MA 
Length of time with 
firm / Total 
experience 
49/49

Page: 
35/43 
Availability of key 
staff members 
25% 
Percent of their work 
to be done locally for 
this project if 
awarded 
10% 
Relevant experience 
on similar or related 
projects 
 
Demonstrated 
performance record 
 
 
Mr. Trachtman has a wide range of experience in water master 
planning, water loss control, non-revenue water auditing, and water 
meter engineering. Mr. Trachtman has been a member of the AWWA 
Water Loss Control Committee (WLCC) for 15 years, contributed to the 
3rd and 4th editions of Manual M36 Water Audits and Loss Control 
Programs and peer-reviewed USEPA’s guidance document on Best 
Practices to Consider. 
 
Water Meter Technical Review, DeKalb County, Georgia 
Technical lead for assessment and technical comparison of various 
mechanical (positive displacement) and static (ultrasonic and magnetic) 
3/4’’ and 1’’ residential water meters that are compatible with DeKalb 
County’s existing Sensus FlexNet® Advanced Metering Infrastructure 
(AMI) system and that best meet the County’s metering and AMI goals. 
Compared the functional characteristics of existing installed meters in 
DeKalb County and alternate meters that met minimum criteria 
established by DeKalb County and the project team. Also compared 
operating characteristics of these meters, such as flow range, operating 
pressure, head loss, and accuracy at different flow rates. Qualifying 
meters were bench tested via coordination with Department of 
Watershed Management (DWM) metering staff and local vendor 
representatives. Bench tests confirmed the compatibility of selected 
meters with DeKalb County’s AMI infrastructure through connection to a 
radio endpoint as well as determined the workability of each selected 
meter in a simulated field setting. A life cycle cost analysis was 
performed to outline the various costs of each meter at stages 
throughout its service life. Warranty and life expectancy comparisons 
were also conducted for these meters within the life cycle cost analysis.  
 
Meter-to-Bill Evaluation, City of Phoenix, Arizona Water Services 
Department 
Technical lead for examination of the City’s current meter-to-bill 
business processes and meter-to-bill accuracy, with focus on random 
sampling and testing (at WSD testing facility) of approximately 400 
customer meters 1” and smaller, in accordance with standard industry 
practice. Evaluation included accuracy of generated bills, correct meter 
number assignment to premise and customer account, premise’s meter 
size correctly coded in the utility billing system, and meter, register, and 
the encoder-receiver-transmitter (ERT) are the correct combination.  
Weighted average meter tested accuracy was compared with 
manufacturer’s new meter accuracy. Prepared summary report and 
material for presentation by WSD to Water Rate Advisory Committee.

Page: 
36/43 
 
Name 
Wes Gamble 
Role of the person 
and Responsibilities 
Subject Matter Expert – Data Collection Technology 
As the data collection technology matter expert, Mr. Gamble will lead 
the evaluation of AMR/AMI data collection technologies performed as 
part of the needs assessment, will develop the technical requirements 
for the AMR/AMI systems, and will advise the project on the technical 
aspects of data collection throughout the life of the project. 
Qualifications 
Licenses and Certifications  
 
None 
 
Home office location 
Nashville, TN 
Length of time with 
firm / Total 
experience 
9 / 11 
Availability of key 
staff members 
25% 
Percent of their work 
to be done locally for 
this project if 
awarded 
50% 
Relevant experience 
on similar or related 
projects 
 
Demonstrated 
performance record 
 
 
Since 2005, Wesley Gamble has been active in the utility industry 
working directly for a combined municipal utility, as well as in the 
private sector, assisting utilities in the planning, implementation, and 
operation of utility systems. 
 
Smart Metering Program, Mesa, AZ 
• 
Performed Advanced Metering Education Sessions 
• 
Procurement and Deployment Planning 
 
AMI Planning, Procurement, and Deployment, Tempe, AZ 
• Facilitated Advanced Metering Vendor Meetings 
• Documented Advanced Metering System Integration, and Data 
Flow Map 
• Facilitated Project Requirements Creation 
• Developed Request Document and Evaluated Vendor Responses 
• Facilitated Contract Negotiation 
• Pilot Deployment Performance Testing and Project Management 
 
AMI & Customer Portal Plan, Procure, Deploy, Fort Worth Water 
Department 
• Consulted on IT System Purchases and Integrations 
• Consulted on Business Process Development 
• Developed Request Document and Evaluated Vendor Responses

Page: 
37/43 
• Facilitated Contract Negotiation 
• Consulted on Implementation of Advanced Data Analytics 
 
 
 
Name 
Brian Wopershall, PE, PMP, GISP 
Role of the person 
and Responsibilities 
Subject Matter Expert – Software and Integration 
As the software and integration subject matter expert, Mr. Wopershall 
will lead the project planning for these areas performed during the 
needs assessment, will lead the development of the functional and 
technical requirements for software and integration, and will lead the 
software quality control activities for the project.  
Qualifications 
Licenses and Certifications  
Professional Engineer – OH 
Registered GIS Professional (GISP) 
Project Management Professional (PMP) 
AWWA Customer Service Program Certification 
 
Degrees 
BS Civil Engineering Case Western Reserve University 1997 
MS Civil Engineering and City Planning- Focus on Information Systems 
Georgia Institute of Technology 1999 
Home office location 
Cleveland, OH 
Length of time with 
firm / Total 
experience 
1/20 
Availability of key 
staff members 
50% 
Percent of their work 
to be done locally for 
this project if 
awarded 
50% 
Relevant experience 
on similar or related 
projects 
 
Demonstrated 
performance record 
 
 
Implementation and Operations Manager, CWD, Cleveland, OH. 
Transformative project which upgraded approximately 425,000 water 
meters to AMI using the Itron Choice Connect Solution and integrating 
the AMI with Oracle Customer Care and Billing (CC&B). Served as 
integration manager and AMI application manager during the AMI 
deployment and system operation. Managed a team of up to 75 
members made up of representatives from the utility, consultants, AMI 
vendor and subcontractors. Directed team regularly on issues related to 
contractor performance, contract terms, interfaces, customer 
complaints, installation and data collection quality, and IT system 
reliability. 
 
Managed team responsible for providing up to 25,000 meter reads per 
day after transition from quarterly to monthly billing at completion of

Page: 
38/43 
AMI implementation. Led project with senior staff, customer service, IT 
and public affairs departments on roll-out of customer porta  
(clevelandwater.com) and automated leak notification system to alert 
residential customers with continuous water consumption. 
 
AMI Procurement Consultancy, Singapore Public Utilities Board, 
SG.  
Technical lead during the planning for the deployment of 300,000 smart 
water meters for the Public Utilities Board (PUB), Republic of 
Singapore. Met with Singapore PUB to discuss industry best practices 
and provide direction on the development of the specification for a 
vendor to install meters, manage the implementation, and perform 
operation and maintenance after deployment.  
 
AMI Program Management, Louisville Water, Louisville, KY.  
Acted as owner’s agent through selection of AMI solution. Co-led 
vendor interview and scoring process with client project manager, held 
preparation sessions with department leads and coordinated Q&A 
sessions between Louisville Water and vendors. Held workshops to 
develop as-is and to-be work processes leveraging the benefits of Itron 
Riva AMI. Met with customer service, meters, engineering, IT and 
training departments to outline employee AMI training requirements. 
Collaborated with client on test plan to make sure requirements are met 
in system integration with Oracle CC&B and Work and Asset 
Management (WAM). 
 
AMI Program Management, Columbia Water, Columbia, SC. 
Developed and helped execute test plan for integration between 
Badger Beacon cellular AMI system and Columbia’s Banner billing 
system. Collaborated with client to design a two-phased validation of 
project workflows through an alpha phase with closely scrutinized 
installations, followed by a beta phase of 100 installations. Facilitated 
transition into main implementation phase of 500 installs per day. 
 
Name 
Melissa Darr, PE 
Role of the person 
and Responsibilities 
Subject Matter Expert – People and Process 
As the people and processes subject matter expert, Ms. Darr will lead 
the business process mapping and analysis performed as part of the 
needs assessment, will contribute to the software functional 
requirements, and will support the software quality control for the 
project.  
Qualifications 
Licenses and Certifications  
Professional Engineer: AZ 
LEED AP O&M 10958917 
ENVISION Sustainability Professional 
Microsoft Technology Associate Database Fundamentals 
IAM Certificate in Asset Management Registration no. 5003378

Page: 
39/43 
 
Degrees 
MS, Civil and Environmental Engineering: Energy, Civil Infrastructure, 
and Climate, UC Berkeley 
BS, Civil and Environmental Engineering, UC Berkeley 
 
Home office location 
Phoenix, AZ 
Length of time with 
firm / Total 
experience 
7/7 
Availability of key 
staff members 
50% 
Percent of their work 
to be done locally for 
this project if 
awarded 
100% 
Relevant experience 
on similar or related 
projects 
 
Demonstrated 
performance record 
 
 
AMI Program Management, City of Mesa, Mesa, Arizona 
Completed a needs assessment and other activities necessary to write 
a comprehensive RFP for the replacement of water, gas, and electric 
meters and the creation of an AMI network. Worked collaboratively with 
the City to collect information about Mesa’s unique needs and educate 
the City on AMI best practices. In progress – RFP expected to be 
issued in summer 2020. 
 
Scottsdale Water Technology Master Plan , Scottsdale, Arizona 
Assessed the current state of the Work Order, Asset Management, 
Smart Meter, Enterprise Architecture, and Non-Revenue Water 
programs for inefficiencies and recommended upgrades to address 
gaps in current technology offerings and presented to the City’s Board 
of Directors. 
 
Primavera and Maximo Program Support, Salt River Project, 
Phoenix, Arizona 
Led Maximo upgrade activities for the Generation Engineering group. 
Processed a scheduling backlog of over 100 FY18 projects, updated 
work orders in Maximo and scheduled these through to Primavera. 
Developed training materials and standard operating procedures to 
capture the processes used by the group throughout the work order 
lifecycle. 
 
West Area Water Reclamation Facility, Glendale, Arizona 
Assessed the current state of facilities and recommended upgrades to 
the UV disinfection system. Designed and built sampling equipment 
and performed sampling activities on site. 
 
Name 
Yinan Zhu 
Role of the person 
Technical Analyst

Page: 
40/43 
and Responsibilities 
As the technical analyst, Ms. Zhu will support the subject matter experts 
during the needs assessment by performing business process 
modelling, and documenting functional and technical requirements, and 
will support the software quality control for the project. 
Qualifications 
Licenses and Certifications  
Oracle Certified Professional, Java SE 6 Programmer 
Microsoft Certified: Azure Fundamentals 
SAP ABAP Professional Training 
SQL Server Management Training 
 
Degrees 
MS, Management Information Systems, University of Arizona, 2012 
BS, Computer Science, Jinan University, 2011 
 
Home office location 
Phoenix, AZ 
Length of time with 
firm / Total 
experience 
8/8 
Availability of key 
staff members 
50% 
Percent of their work 
to be done locally for 
this project if 
awarded 
100% 
Relevant experience 
on similar or related 
projects 
 
Demonstrated 
performance record 
 
 
Meter-to-Bill Evaluation, City of Phoenix, Phoenix, AZ 
Developed business process models for meter-to-bill processes. 
Performed water meter data analysis.  
 
AMI Program Management, City of Mesa, Mesa, Arizona 
Supported interface integration needs and other requirements analysis 
and solution design efforts. 
 
Drinking Water Regulatory Database System Implementation, City 
of Phoenix, Phoenix, AZ 
As a Software Developer, responsible for eDWaRD maintenance and 
feature enhancement for both City of Phoenix and City of Chandler. 
Helped migrating eDWaRD system from Oracle to Microsoft SQL 
Server for City of Phoenix and also helped with database schema 
comparison, validation and database migration. eDWaRD is a custom 
web-based, integrated information system that provides dashboards for 
drinking water regulatory compliance functions. The system enables the 
city’s Compliance and Regulatory Affairs Office (CRAO) to manage 
complex drinking water regulations and reduces the risk of regulatory 
non-compliance. It is a configurable system that can be adapted as 
distribution systems and regulations evolve. 
 
SCADA Data Reporting Service, City of Austin, TX 
As a Software Engineer, developed and improved SQL Server

Page: 
41/43 
Reporting Services (SSRS) reports to assist client analysis and monitor 
SCADA data getting directly from PLCs in the fields and data gathered 
from Historian servers. She helped processing collected SCADA data 
from PLCs into SQL Server database automatically by creating stored 
procedures and database jobs. SSRS reporting assists users to view 
historical and real-time records over a certain timeframe and 
customized reporting indicators allow users to view the big picture of 
overall field operations. 
 
 
Name 
Monte Merkle 
Role of the person 
and Responsibilities 
Meter Installation Quality Control 
As the meter installation quality control analyst, Mr. Merkle will design 
and implement processes for meter installation and AMR/AMI endpoint 
installation acceptance, and will monitor performance of the installation 
teams.  
Qualifications 
Licenses and Certifications  
None 
 
Home office location 
Bloomington, IN 
Length of time with 
firm / Total 
experience 
2/14 
Availability of key 
staff members 
50% 
Percent of their work 
to be done locally for 
this project if 
awarded 
25% 
Relevant experience 
on similar or related 
projects 
 
Demonstrated 
performance record 
 
 
City of Trinidad, CO.  
Delivery standards manager and consultant for project that included 
4,500 water meters, 4,300 electric meters and 4,300 gas retrofits. 
Project included national municipal utility project oversite; project 
management support; procurement and deployment planning; and 
defined and implemented daily billing system data synchronizations 
with data collection systems. 
 
City of Evansville, IN.  
Delivery standards manager for project that included 65,000 water 
meters. Project included national municipal utility project oversite; 
project management support; develop and implement data QC 
procedures; and project management training for operations team. 
 
City of Martinsville, VA.  
Delivery standards manager for project that included 7,000 water 
meters. Project included national municipal utility project oversite; 
project management support; AMI full deployment project management

Page: 
42/43 
and performance testing; project management training for operations 
team. 
 
2) 
Provide the contact information of the Project Manager assigned to the resulting 
contract who will be directly responsible for implementing the proposed solution 
and services. This Project manager will be responsible for the day-to-day 
management of project tasks and will be the primary point of contact with your 
firm.  
The project will be led by our project manager, Michael Rotunno, who will be the 
primary contact for the day-to-day project execution. 
 
D. Michael Rotunno, P.E., PMP  
Associate Vice President 
Arcadis U.S., Inc. 
1111 Superior Avenue Suite 1300 Cleveland OH | 44114 | USA  
T. 330-515-5672 | M. 216-374-5805 
michael.rotunno@arcadis.com  
3) 
 
Describe the project manager's experience with similar projects and managing 
and leading interdisciplinary teams. 
Mr. Rotunno has more than 20 years of overall experience working in all facets of water 
utility management and over 10 years of experience specifically providing management 
and technical leadership for AMI projects. He has held leadership roles for a variety of 
AMI projects, including Cleveland Water (450,000 meters) WSSC Water (485,000 
meters), Youngstown, OH (55,000 meters), and Greene County, OH (22,0000 meters). 
Beyond his AMI experience, Mr. Rotunno has led many other customer billing and utility 
enterprise asset management projects. He brings the City a unique combination of 
experience in program management, water system engineering, information technology, 
and meter-to-cash business processes. 
 
Prior to joining Arcadis, Mr. Rotunno served as the Assistant Commission of IT for the 
City of Cleveland, Division of Water (CWD), one of the largest water utilities in the 
United States. He had overall responsibility for IT strategy and operations of the $240M 
regional water utility serving 1.5M customers. In this role, he developed and executed a 
strategy to modernize major portions of the application portfolio, instituting a new IT 
program management model and system development lifecycle methodology that 
successfully delivered over $43M worth of new IT investments in a three-year period. 
The resultant systems provided a host of new customer-facing technology services. 
With Arcadis, Mr. Rotunno is responsible for leading large and complex information 
technology projects for water utilities nationally and serves as the Discipline Leader for 
the North America Digital Consulting practice. 
 
4. COST Please use the Price Workbook and submit as a separate attachment.

Page: 
43/43 
VENDOR EXCEPTIONS: 
 
Per Exhibit 2.2, Offeror shall note any exceptions to the solicitation documents in this 
section using the example below:   
 
Document Name: 
Exhibit 3 – Insurance Requirements 
Section: 
 
1.a.i. Commercial General Liability – General Aggregate $5,000,000  
Exception: 
 
Vendor’s General Aggregate is only $3,000,000   
 
None 
 
ADDENDUM RESPONSES AND ACKNOWLEDGEMENT:   
 
Attach addendum response(s) and acknowledgement(s) here. 
 
Our executed addendums are attached to this response workbook. 
 
CONFLICT OF INTEREST STATEMENT 
If Offeror indicated they have a conflict of interest on the Offer Sheet, Offeror must 
provide details here.  Please refer to the CONFLICT OF INTEREST section on page 1 of 
the EXHIBITS PACKAGE for required information to be included here. 
 
Arcadis has no conflicts of interest related to the water meter replacement project.

SOLICITATION ADDENDUM 
 CITY OF GLENDALE 
Procurement Division 
5850 W. Glendale Avenue 
Suite 317 
Glendale, AZ 85301 
Phone: (623) 930-2864 
 
Solicitation Number: RFP 21-52/ 42100072 
 
Addendum #1    Page 1 of 1 
 
Solicitation Due Date:  August 10, 2021, 2:00 p.m. (Local 
Time) 
 
RFP 21-52 
WATER METER REPLACEMENT CONSULTANT 
 
 
 
 
As a result of questions raised about this solicitation, the following revisions and clarifications have 
been made to Requests for Proposals No. 21-52: 
 
 
 
DUE DATE: The Due Date for this solicitation has been extended to Tuesday, August 10, 2021 at 
2:00 PM Local Time.  
 
Name of Company:  ________________________________________________________________________ 
 
Address:                ________________________________________________________________________ 
 
Authorized Signature: ________________________________________________________________________ 
 
Print Name and Title:  ________________________________________________________________________ 
 
 
Arcadis U.S., Inc.
410 North 44th Street, Suite 1000, Phoenix, AZ 85008
Esteban Azagra / Senior Vice President

SOLICITATION ADDENDUM 
 CITY OF GLENDALE 
Procurement Division 
5850 W. Glendale Avenue 
Suite 317 
Glendale, AZ 85301 
Phone: (623) 930-2864 
 
Solicitation Number: RFP 21-52/ 42100072 
 
Addendum #2    Page 1 of 5 
 
Solicitation Due Date:  August 10, 2021, 2:00 p.m. (Local 
Time) 
 
RFP 21-52 
WATER METER REPLACEMENT CONSULTANT 
 
 
 
 
As a result of questions raised about this solicitation, the following revisions and clarifications have 
been made to Requests for Proposals No. 21-52: 
 
 
1. Why are only 7 business days provided to respond to this RFP after the pre-proposal meeting?  
If any addendum is issued, how many business days does the City’s procurement rules require they 
must be issued prior to the submission of proposals?  An addendum can be sent out no later than 5 
days before the due date.  We are considering pushing the due date out until August 4th.  
 
2. What are the make, size, age and model of 5,000 AMR/AMI capable meters? 
a. Badger HRE LCD – 5/8 X ¾ (at the most they have been installed three years) 
b. Badger HRE LCD – 1” (at the most they have been installed three years) 
c. Badger HRE LCD – 1.5” (at the most they have been installed three years) 
d. Badger HRE LCD – 2” (at the most they have been installed three years) 
e. SENSUS OMNI T2 - 2” to 4” (at the most they have been installed 9 years) 
f. 
SENSUS OMNI C2 - 2” to 4” (at the most they have been installed 9 years) 
 
3. What are the models and ages of the 2,900 ERT attached to the meters.  Itron ERTs, 50W, 60W, and 
100W 
 
4. Does the city plan to install the AMR/AMI system itself or contract it out in whole or in part? This is 
something that we would like the consultant to review these options and help us to decide.  
a. What is the basis for the 2,500 to 3,500 meters replaced each year?   
Currently the basis for replacing meters is usage:  
• 
5/8 x ¾ meters are replaced at 3 million gal.  
• 
1” meters are replaced at 3.5 million gal. 
• 
1.5” meters are replaced at 35 million gal. 
• 
2” meters are replaced at 35 million gal.  
 
b. What meters are they being replaced with? 
Up to recently we replaced meters with Badger HRE LCD. Soon we will start to replace meters with 
SENSUS SR2 with electronic registers. Medium to large meters are replaced with OMNI C2 & T2 
METERS 
 
5. What type of lids are in the system for pits and vaults that have the existing ERTs?  Metal lids 
a. What materials are the existing lids made of that don’t have AMR devices? Metal

SOLICITATION ADDENDUM 
 CITY OF GLENDALE 
Procurement Division 
5850 W. Glendale Avenue 
Suite 317 
Glendale, AZ 85301 
Phone: (623) 930-2864 
 
Solicitation Number: RFP 21-52/ 42100072 
 
Addendum #2    Page 2 of 5 
 
Solicitation Due Date:  August 10, 2021, 2:00 p.m. (Local 
Time) 
 
b. Was anything done to modify these lids to aid in RF transmission?  No. 
c. Are the existing lids manufactured to be drilled for AMR/AMI devices?  No, they are not 
specifically manufactured for that.  They are metal, however, and it’s possible to drill a hole through 
them.   
 
6. How are the current 2,900 ERT read?  Drive by routes read with Itron MC3Lite; Itron IMRs (Itron Mobile 
Radios) also used by individual reps. 
a. On what types of accounts are they installed?  Commercial and residential 
b. Is this a concentrated installation or spread out? Majority are concentrated, commercial 
accounts. Some others are residential and commercial that are spread out. 
 
7. Is there an engineer’s estimate or budget for these consulting services?  If so, what is that estimate?  
No.  
a. Over what period of time are these resources scheduled? 
 
8. Were these consulting service requirements developed by an outside consultant?  If so, are such 
consultants allowed to participate in this procurement?  No.  
 
9. For AMR/AMI system procurement – why a performance-based contract?  The City is currently seeking 
performance-based contracts for better tracking and conformance with vendor compliance.  
 
10. What is the current accuracy level of the existing meter population?  Large meters are tested annually 
and tested according to the AWWA overall weighted averages. Small to medium size meters are tested in 
house after they are replaced.    
a. How was this accuracy level determined?  We use the AWWA recommended overall weighted 
average 
b. For the cost savings performance associated with the AMR/AMI system proposed by a 
vendor, does the city plan on shifting staff to allow the vendor to recover costs savings 
associated with the proposed reading technology?  This is something that we would like the 
proposer to help us figure out.   
 
11. Are there any established deadlines for completion of any of the milestones?  
a. Are there any restrictions imposed by either budgeting concerns or other financial issues?  
b. When does the City of Glendale anticipate making an award of this contract?  Award is 
intended to take place after final evaluation.  We are hoping that the process can be approved by 
City Council by the end of the calendar year.  
12. Was there an AMI business case developed for this project or is this part of the needs assessment?  
A business case has not been developed for this project.  
a.  If so, who developed it?  Can we get a copy of it prior for review to the submission of the 
proposal?  
 
13. Under 4.3 it notes that a detailed financial analysis for AMI implementation is needed.  Does this 
also apply to AMR? Yes. A detailed financial analysis is requested for both options.

SOLICITATION ADDENDUM 
 CITY OF GLENDALE 
Procurement Division 
5850 W. Glendale Avenue 
Suite 317 
Glendale, AZ 85301 
Phone: (623) 930-2864 
 
Solicitation Number: RFP 21-52/ 42100072 
 
Addendum #2    Page 3 of 5 
 
Solicitation Due Date:  August 10, 2021, 2:00 p.m. (Local 
Time) 
 
 
14. Based on the Milestones in Section 4.6, is the City expecting milestones 1 through 8 to be 
completed by Consultant within the first (contract) year of the engagement?  The City would be 
expecting to hopefully get this completed within the first contract year but would need to work with 
consultant on a timeline.  
 
15. Item 5.2 notes that the City reserves the right to make multiple awards.  How does the city plan to 
manage these services if there are multiple consultants?  What provisions would there be for 
confidentiality between consultant work products to avoid transferring know-how from one 
consultant to another competing consultant?  This is standard language within all RFPs.  The goal for 
this procurement would be to select one vendor.   
Pricing Workbook Document 
The Pricing Workbook appears to be in a different format than the Scope of Services defined in the RFP 
document.  For example: 
1. Where are the scope requirements for 4.2 Preparation tasks to be accounted for and priced?  
Preparation should be accounted for in Project Management.   
a. Where are the scope requirements for the Project Management line item?  4.2 Preparation.  
b. Over what period of time does the city expect the Project Management line item to cover and 
how might that interrelate with project management functions that might be included in 
Phases 1 through 3? Project management should be the entire process from Preparation to RFP 
completion.  
 
2. Solicitation development scope has 8 subsections of which only the RFP draft and release task and 
RPF evaluation are noted in the Pricing workbook.  Pricing workbook shows council presentation and 
RFP pricing lines, but no description in the Scope for determining the requirements for these items.  
A Council presentation would have to be discussed before presentation.  This could include a presentation 
being created by the consultant to just having a consultant at a meeting to help answer questions.   
 
3. There does not appear to be a scope section defining Project Phase 1 activities noted in the pricing 
workbook. What are the optional Project Management services the city is considering in subsection 
b?  What is the scope of work associated with such services?  If this is optional, why does it appear 
to be included in the main body of the proposal and how will it be used in making an award?  Project 
Phase 1 activities are activities that would be done after award of this RFP.  This would be the startup phase 
for after a vendor is awarded the AMR/AMI and meter installation.   
 
4. Does Phase 2 AMR deployment and Phase 3 Meter Replacement mean all of the tasks associated 
with the Scope of Work item 4.5?  Yes.

SOLICITATION ADDENDUM 
 CITY OF GLENDALE 
Procurement Division 
5850 W. Glendale Avenue 
Suite 317 
Glendale, AZ 85301 
Phone: (623) 930-2864 
 
Solicitation Number: RFP 21-52/ 42100072 
 
Addendum #2    Page 4 of 5 
 
Solicitation Due Date:  August 10, 2021, 2:00 p.m. (Local 
Time) 
 
5. Since the workbook lists these pricing items, are these the ones that are subject to multiple awards?  
The City intends to make a single award as mentioned in the Introduction.    
 
6. The Final Report does not have a scope of work defined except it notes from the “above tasks and 
recommendations”.  Are the above items limited to the items noted in the Milestone section or does 
it include Items 4.2, 4.3, 4.4, and 4.5?  The Final report will encompass all sections and findings related 
to consultant work.   
 
7. The pricing schedule only supplies one hourly rate.  Is this rate to be based on the average rate that 
might be applied to the line item as there are normally multiple consultants assigned to various 
work tasks and their rates might differ?  Please insert under Other at bottom of Price Sheet.  
 
8. The pricing workbook line item for travel shows an hourly rate.  Does this mean that the consultant 
is allowed to charge for travel time to and from the project site? No.  Since only an hourly rate for 
travel is noted, how does the consultant recover travel costs such as flights, hotels, meals, etc. for 
any onsite visits from out of the area consultants? For travel this is an estimated for flights, hotels and 
meals.   Is there a minimum amount of on-site time that the city is expecting for the performance of 
this contract?  No.  
 
9. The Payment section notes that the “itemized statement shall not exceed the proposal fee for this 
Section”.  Is that referring to the total project or for each line item?  The section refers to the total 
project.  Why is there no total project amount noted in the pricing workbook?  There is no total project 
amount because that can be calculated during evaluation.   
 
10. How does the City apply pricing for any of the “Other” Services that the consultant might offer or 
suggest in its proposal?   Other services are viewed as optional task.   
a. Is this considered in making the award for the basic, defined services?  Not Applicable. 
b. If the city likes any of the proposed “Other” Services, will it request other proposers to 
provide pricing on that as well in order to make an award decision?   Not Applicable. 
 
11. Are the 2% 20 days discount terms used to make an award decision?  Price is not the determining 
factor.  
a. Does the city apply the 2% discount in the setup of the contract and PO?  Price is not the 
determining factor.  
b. Does the city have a prompt payment requirement that it must pay within a specific number 
of days or it is subject to paying interest on the unpaid balance?  Price is not the determining 
factor.  
c. The Payment Terms in the Exhibit Package notes that the 30 day payment period starts with 
either the receipt of invoice or final acceptance of invoice.  Is the awardee informed of when 
the invoice has been accepted?  No.  
d.  Does the city pay partial invoices on the portion of the invoice that is accepted?  No.

SOLICITATION ADDENDUM 
 CITY OF GLENDALE 
Procurement Division 
5850 W. Glendale Avenue 
Suite 317 
Glendale, AZ 85301 
Phone: (623) 930-2864 
 
Solicitation Number: RFP 21-52/ 42100072 
 
Addendum #2    Page 5 of 5 
 
Solicitation Due Date:  August 10, 2021, 2:00 p.m. (Local 
Time) 
 
Response Workbook Document 
1. Many of the items listed in the Needs Assessment section appear to be very broadly worded.  Are 
these assessments limited to metering and reading automation items or are there other 
expectations that the city might have?  The City depends on the Consultant to use best practices to 
address the needs of the City.   
 
2. For Item 4g, are the interviews and site visits limited to city personnel or does this include interviews 
and site visits to AMR/AMI system proposers to help determine which system should be selected?  
This would be related to site visits and interviews for prospective vendors for the AMR/AMI system.   
 
3. In the Response Workbook (Section 2, items 2-5 and Section 4, item 1) there is instructions saying 
“(Offeror to reference corresponding letter in their response)”.  What is meant by “corresponding 
letter”?  If you have to attach a separate sheet for your response please make sure to label your response 
with the corresponding letter, i.e. 4g.   
 
 
Name of Company:  ________________________________________________________________________ 
 
Address:                ________________________________________________________________________ 
 
Authorized Signature: ________________________________________________________________________ 
 
Print Name and Title:  ________________________________________________________________________ 
 
 
Arcadis U.S., Inc
410 North 44th Street, Suite 1000, Phoenix, AZ 85008
Esteban Azagra / Senior Vice President

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 1 - 
1/29/18 
EXHIBIT 1:  SPECIAL NOTICES   
 
By signing on the Offer/Bid page, solicitation Amendment(s), or cover letter accompanying the 
submittal documents, Offerors are certifying that they understand the following notices and 
agree to comply with all required terms and conditions. 
1. RETURN OF OFFER The Offeror shall submit the Response Workbook electronically in 
Vendor Self Service (VSS)  
Offeror is required to register in VSS prior to submitting a proposal if they have not already 
registered.  https://glendaleazvendors.munisselfservice.com/Vendors/default.aspx 
Guide to Register as a new vendor: 
https://www.glendaleaz.com/your_government/city_finances/procurement/vendor_self_service___v_s_s_  
(This is a PDF document “Vendor Registration Instructions” at the bottom of page.) 
The Offeror shall complete all sections of the solicitation in the format given and in the 
spaces provided.  Proposals that do not conform to the above format may be rejected.  
a. The Offeror shall bear all costs associated with submitting the proposal, including 
proposal preparation, site visitation or any travel connected with submission of the 
proposal. The City shall have no liability whatsoever for such costs. 
2. PRE-OFFER CONFERENCE & SITE VISITS 
A Pre-Offer meeting will be held on July 15, 2021, 2:00 PM, Arizona Time, online through 
GoToMeeting at the following link: 
Please join my meeting from your computer, tablet or smartphone. 
https://global.gotomeeting.com/join/288280621 
 
You can also dial in using your phone. 
United States: +1 (646) 749-3122 
 
Access Code: 288-280-621 
Attendance is not required. Copies of the Request for Proposal (RFP) will NOT be available. 
The purpose of the conference will be to clarify the contents of the solicitation to prevent any 
misunderstanding of the City of Glendale’s position. Any doubt as to the requirements of the 
solicitation or any apparent omission or discrepancy should be presented to the City at the 
conference. The City will determine the appropriate action necessary, if any, and issue a 
written amendment to the solicitation if required. Oral statements or instructions will not 
constitute an amendment to the solicitation. 
3. NO CONTACT, NO INFLUENCE DURING THE RFP PROCESS 
 
The City is conducting a competitive RFP process for the contract, free from improper 
influence or lobbying.   There shall be no contact concerning this RFP from Offerors submitting 
a Proposal with any member of the City Council, RFP Evaluation Committee Members, or

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 2 - 
1/29/18 
anyone connected with the process for or on behalf of the City.  Contact includes direct or 
indirect contact by the Offeror, its employees, attorneys, lobbyists, surrogates, etc. in an 
attempt to influence the RFP process. 
From the time the RFP is issued until the expiration of the protest period or the resolution of 
any protest, whichever is later (the “Silent Period”), Offerors, directly or indirectly through 
others, are restricted from attempting to influence in any manner the decision making process 
through, including but not limited to, the use of paid media; contacting or lobbying the City 
Council or City Manager or any other City employee (other than Procurement employees); the 
use of any media for the purpose of influencing the outcome; or in any other way that could 
be construed to influence any part of the decision-making process about this RFP.  This 
provision shall not prohibit an Offeror from petitioning an elected official or engaging in any 
other protected first amendment activity after the protest period has run or any protest has 
been resolved, whichever is later. 
 
Violation of this provision will cause the proposal or offer of the Offeror to be found in violation 
and to be rejected. 
4. CONFLICT OF INTEREST  Contractor shall disclose the following:  1) the name(s) and 
position(s) of each Contractor’s employee or subcontractor that participated in the 
preparation of the submittal or who will be involved, directly or indirectly, with performing the 
contract, if awarded; 2) the name(s) of any City of Glendale employee who is a relative of 
persons identified pursuant to No. 1;  3) the name(s) and position(s) of Contractor’s  personnel 
that have a financial or proprietary interest in the contract; 4) the name(s) of any City of 
Glendale employee who is a relative of persons identified pursuant to No. 3.   
 
 
Providing such disclosure will not necessarily disqualify a Contractor.  Failure to disclose the 
requested information or any potential conflict of interest pursuant to A.R.S. § 38-511 et seq. 
may result in rejection of the proposal or bid or any contract being void or terminated. 
 
For purposes of this provision, the following definitions apply: 
 
“Employee” means all persons who are employed on a full-time, part-time or contract basis 
by the City of Glendale. 
 
“Relative” means the spouse, child, child’s child, parent, grandparent, brother or sister of the 
whole or half blood and their spouses and the parent, brother, sister or child of a spouse. 
5. INQUIRIES Any question related to the Request for Proposal shall be directed to the Contract 
Analyst whose name appears above. An Offeror shall not contact or ask questions of the 
department for whom the requirement is being procured. The Contract Officer may require 
any and all questions be submitted in writing. Offerors are encouraged to submit written 
questions via electronic mail or facsimile, no later than FIVE days prior to the proposal due 
date. Any correspondence related to a solicitation should refer to the appropriate Request for 
Proposal number, page and paragraph number. An envelope containing questions should be 
identified as such; otherwise it may not be opened until after the official proposal due date 
and time. Oral interpretations or clarifications will be without legal effect. Only questions 
answered by a formal written amendment to the Request for Proposal will be binding.

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 3 - 
1/29/18 
 
6.  SPECIAL TERMS AND CONDITIONS Additional terms and conditions specific to the provision 
of the services referenced will be negotiated with the successful bidder for inclusion in the 
contract. 
7.  PUBLIC RECORD REQUIREMENTS Offeror acknowledges that the City is a public agency and 
must comply with all Public Records laws and proposals submitted become the property of 
the City and are subject to public disclosure requirements in accordance with Arizona Public 
Records Law.  Any portion of the proposal that the offeror deems confidential or proprietary 
must be clearly labeled as such.  Labeling material does not automatically preclude the 
material from public disclosure, as the City is required to make an appropriate determination 
as to the confidentiality of the material in accordance with Arizona Public Records Law.  It is 
the offeror’s sole responsibility and cost to take action, including legal actions, to protect such 
material.  Price is not confidential and will not be withheld 
8.  PERMITS AND LICENSES It is the offeror’s sole responsibility to determine and secure any 
and all licenses and permits the contractor needs to operate the facility, from any regulatory 
body having jurisdiction related to the services being provided.  Such costs are the exclusive 
responsibility of the operator, operator must also ensure appropriate licensing of any sub-
contractors, operator shall notify the City in writing within two (2) working days of any 
suspension, revocation or renewal. 
9.  NO COLLUSION OR ANTI-COMPETITIVE PRACTICES The submission of the offer did not 
involve collusion, and without any agreement, understanding or planned common course of 
action with, any other vendor of materials, supplies, equipment or services described in the 
invitation to bid, designed to limit independent bidding or competition or other anti-
competitive practices.  
10. NON-DISCRIMINATION Contractor agrees not to discriminate against any employee or 
applicant for employment on the basis of race, color, religion, sex, national origin, age, marital 
status, sexual orientation, gender identity or expression, genetic characteristics, familial 
status, U.S. military veteran status or any disability. Contractor will require any Sub-contractor 
to by bound to the same requirements as stated within this section. Contractor, and on behalf 
of any subcontractors, warrants compliance with this section. 
11. NO CONSIDERATIONS The Contractor has not given, offered to give, nor intends to give at 
any time hereafter, any economic opportunity, future employment, gift, loan, gratuity, special 
discount, trip, favor, meal or service to a public servant in connection with the submitted offer.  
12. AUTHORIZED AGENT The individual signing the submittal is an authorized agent and has the 
authority to bind the Offeror to the proposal and subsequent contract if awarded. 
13. KEY PERSONNEL If awarded, Offeror shall assign a specific individual as the key point of 
contact for the management of the contract, subject to specific notification requirements to 
be included in the final contract.  
14. SITE INSPECTION It is the responsibility of the Offeror to become familiar with any conditions 
which may affect the performance and cost of providing the service and this submission will 
serve as evidence that the Offeror did, in fact, make a site inspection and is aware of all 
conditions.

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 4 - 
1/29/18 
15. OFFICIAL TIME CLOCK The official time clock used to verify the date and time an offer is 
received is in the online bid system.  
 
16. DEFINITIONS For purposes of this Request for Proposal and Resultant contract, the following 
definitions apply: 
a. “City” means the municipal corporation of the City of Glendale, Arizona 
b. “Contract” means the agreement for the procurement of goods, services and work. 
c. “Contractor” means an Offeror responding to a Request for Proposal who has been 
awarded a Contract with the City. 
d. “Offer” means a written offer to furnish goods, services, work, materials and/or 
construction to the City, in conformity with the standards, specifications, delivery terms 
and conditions, and all other requirements established in a competitive solicitation. 
e. “Offeror” means the business, entity or person who submits an Offer in response to a 
competitive solicitation. 
f. “Public Record” means proposals and all other documents submitted in response to this 
solicitation shall become the property of the City and shall be a matter of public record 
available for review following the Contract award. 
g. “Purchase Order” means a document issued by the City Procurement Office directing the 
Contractor to deliver goods, services, work, materials and/or construction. 
h. “Request for Proposal” means a competitive solicitation issued by the City for the 
procurement of goods, services, work, materials and/or construction.

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 5 - 
1/29/18 
EXHIBIT 2: SPECIAL TERMS AND CONDITIONS 
By signing on the Offer/Bid page, solicitation Amendment(s), or cover letter accompanying the 
submittal documents, Offerors are certifying that they understand the following notices and 
agree to comply with all required terms and conditions.  The following terms are found on the 
City’s Website and are applicable to Request for Proposal:  
https://www.glendaleaz.com/your_government/city_finances/procurement/procurement_polici
es 
Standard Terms and Conditions, Request for Proposal – Revised 04-24-2009 
1. TYPE OF AWARDS The City reserves the right to make multiple awards or to award by 
individual line items, by group of line items, or to make an aggregate award, whichever is 
deemed most advantageous to the City. If the City determines that an aggregate award to one 
offeror is not in the City's best interest, "all or none" offers shall be rejected. 
 
2. ALTERNATE OFFERS Offers submitted as alternates, or on the basis of exceptions to specific 
conditions of purchase and/or required specifications, must be submitted as an attachment 
referencing the specific paragraph number(s) and adequately defining the alternate or 
exception submitted. Detailed product brochures and/or technical literature, suitable for 
evaluation, must be submitted with the offer. If no exceptions are taken, City will expect and 
require complete compliance with the specifications and all Conditions of Purchase. 
 
3. EFFECTIVE PERIOD OF OFFER Offers shall be valid for a minimum of 120 days following the 
deadline for submitting offers. If an award is not made during that period, all offers shall be 
automatically extended for another 120 days. Offers will be automatically renewed until such 
time as either an award is made, or proper Notice is given to the Procurement Officer of 
Offeror’s intent to withdraw its offer. Offers may only be withdrawn by submitting Notice at 
least 15 days before the expiration of the then current 120-day period. 
 
4. PAYMENT TERMS If payment terms are not indicated, terms of NET 30 days shall be applied 
by the City. Payment terms to apply after receipt of invoice or final acceptance of the 
products/services, whichever is later. Payment terms offering less than 20 days for payment 
will not be considered. 
 
5. UNIT PRICE TO PREVAIL In the event of a price disparity between the unit and extended price, 
the unit price shall prevail unless judged obviously in error by the City. 
 
6. OFFER ERRORS OMISSIONS AND CORRECTIONS The City will not be responsible for any 
offeror errors or omissions. All prices and notations shall be written in ink or typed. Changes 
or corrections made on the offer form must be initialed in ink by the individual signing the 
offer. No corrections will be permitted after the offers have been opened.  
 
7. BRAND NAME REFERENCES AND TECHNICAL SPECIFICATIONS Brand names or 
manufacturer's references shall be construed as a quality or performance level and does not 
indicate the item cited is mandatory. Technical specifications define the acceptable standard. 
 
8. RESTRICTIVE OFFER PROVISIONS If specifications preclude an otherwise qualified offeror 
from submitting an offer, a written request for modification must be received by the Buyer at

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 6 - 
1/29/18 
least seven (7) calendar days prior to the proposal due date. All offerors will be notified by a 
written addendum to the solicitation of any approved changes. 
 
9. DEFAULT In case of default by the contractor, the City may, by written notice, cancel this 
contract and repurchase from another source and may recover the excess costs by (1) 
deduction from an unpaid balance due; (2) collection against the bid and/or performance 
bond; or (3) a combination of the aforementioned remedies or other remedies as provided by 
law. 
10. TERMINATION FOR CONVENIENCE The City reserves the right to terminate any order or 
contract upon thirty days written notice. The City will be responsible only for those standard 
items which have been delivered and accepted. If the items are unique and not saleable or 
useable for any other application, the City will reimburse the Seller for actual labor, material, 
and burden costs, plus a profit not to exceed 8%. Title to all materials, work-in-process, and 
completed but undelivered goods will pass to the City after costs are claimed and allowed. 
 
11. SUB-CONTRACTING The contract or any portion thereof, shall not be sub-contracted without 
the prior written approval of the Materials Manager. No such approval will be construed as 
making the City a party of or to such sub-contract, or subjecting the City to liability of any kind 
to any sub-contractor. No sub-contract shall, under any circumstances, relieve the contractor 
of liability and obligation under this contract; and despite any such subletting the City shall 
deal through the contractor. Sub-contractors will be dealt with as workmen and 
representatives of the contractor. 
 
12. SAFETY DATA SHEETS (SDS). Contractor is to supply SDS) in accordance with Federal 
requirements for The Globally Harmonized System of Classification and Labeling of Chemicals 
(GHS). Contractor entering the City workplace with hazardous materials will supply the City 
with a Safety Data Sheets (SDS) covering those particular products the contractor may expose 
City employees or the general public to while working at the site. 
 
13. GENERAL INDEMNIFICATION:  Contractor shall indemnify, defend, save and hold harmless 
the City of Glendale and its officers, officials, agents, and employees (hereinafter referred to 
as “Indemnitee”) from and against any and all claims, actions, liabilities, damages, losses, or 
expenses (including court costs, attorneys’ fees, and costs of claim processing, investigation 
and litigation) (hereinafter referred to as “Claims”) for bodily injury or personal injury 
(including death), or loss or damage to tangible or intangible property caused, or alleged to 
be caused, in whole or in part, by the negligent or willful acts or omissions of Contractor or 
any of its owners, officers, directors, agents, employees or subcontractors.  This indemnity 
includes any claim or amount arising out of or recovered under the Workers’ Compensation 
Law or arising out of the failure of such Contractor to conform to any Federal, State or local 
law, statute, ordinance, rule, regulation or court decree.  It is the specific intention of the 
parties that the Indemnitee shall, in all instances, except for Claims arising solely from the 
negligent or willful acts or omissions of the Indemnitee, be indemnified by Contractor from 
and against any and all claims.  It is agreed that Contractor will be responsible for primary 
loss investigation, defense and judgment costs where this indemnification is applicable. In 
consideration of the award of this contract, the Contractor agrees to waive all rights of 
subrogation against the City, its officers, officials, agents, and employees for losses arising 
from the work performed by the Contractor for the City.

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 7 - 
1/29/18 
 
14. RESPONSIBILITY FOR COMPLIANCE WITH LEGAL REQUIREMENTS The offeror's products, 
services, and facilities shall be in full compliance with all applicable Federal, State, and local 
health, environmental, and safety laws, regulations, standards, and ordinances, regardless of 
whether or not they are referred to by the City. 
 
15. RESPONSIBILITY FOR CORRECTION It is agreed that the offeror shall be fully responsible for 
making any correction, replacement, or modification necessary for specification or legal 
compliance. In the event of a call back, Offeror agrees to give the City first priority. Offeror 
agrees that if the product or service offered does not comply with the written specification, 
the Materials Manager has the right to cancel the sale at any time with full refund within thirty 
(30) calendar days after notice of noncompliance and offeror further agrees to be fully 
responsible for any consequential damages suffered by the City. 
16. WARRANTY Unless otherwise specified, all items shall be guaranteed for a minimum period 
of one year against defects in material and workmanship. During the period, if a defect should 
occur, that item shall be repaired or replaced by the Seller at no obligation to the City, except 
where it be shown that the defect was caused by misuse and not by faulty manufacture. The 
offeror expressly warrants all items to be new, free from defects in design, materials, and 
workmanship, and to be fit and sufficient for their intended purpose. Any sample submitted 
shall create an expressed warranty that the whole of the goods shall conform to the sample 
or model. 
 
17. REJECTION OF OFFERS The City reserves the right to reject any or all offers, or any part 
thereof; to accept any offer or any part thereof; or to waive any informalities when it is deemed 
to be in the City's best interest. 
 
18. DELAY IN EXERCISING CONTRACT REMEDY Failure or delay by the City to exercise any right, 
power, or privilege shall not be deemed a waiver thereof. 
 
19. TAX EXEMPTION The City is exempt from paying Federal Excise Taxes and will furnish an 
exemption certificate upon request. 
 
20. ORDER OF PRECEDENCE In the event of conflict, the following precedence shall prevail: (1) 
Special Terms and Conditions incorporated by attachment; (2) Special Terms and Conditions; 
(3) Drawings and Specifications; (4) referenced documents; and (5) the Standard Terms and 
Conditions. 
 
21. CHANGES The City reserves the right to make changes in any of the following: (a) 
specifications; (b) methods of shipment; (c) place of delivery; (d) time of delivery; (e) 
quantities. If any change causes an increase or decrease in the cost of or the time required 
for performance, an equitable adjustment may be made in the price or delivery schedule, or 
both. Any claim for adjustment shall be deemed waived unless asserted in writing within thirty 
days from receipt of the change. Price increases or extensions of delivery time shall not be 
binding on the City unless in writing and approved by the Materials Manager prior to the 
institution of the change.

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 8 - 
1/29/18 
22. PRICE ADJUSTMENTS Price adjustments shall be addressed a minimum of sixty (60) days 
prior to the contract renewal date, shall be in writing and include supportive justification for 
the proposed increase. Supportive justification means that the request shall include detailed 
information and calculations that make it clear how the claimed increase has an impact on 
the contract unit prices.  The requested price increase must be based upon a cost increase 
that was clearly unpredictable at the time of the offer and can be shown to directly affect price 
of the item concerned.  The rate increase shall only be considered at time of contract 
extension. The City will review the request and shall determine if the increase shall be granted 
or if an alternate option is in the best interest of the City. The price increase adjustment, if 
approved, will be effective and executed via a contract amendment. 
 
23. LATE SUBMISSION OF CLAIM The City will not honor any invoices or claims which are 
tendered one year after the last item of the account accrued. 
 
24. PROTEST OF AWARD Any person who has an objection to the awarding of a solicitation by the 
City, pursuant to competitive solicitation procedures, shall lodge that protest, in writing, with 
the Materials Manager. The protest should specifically identify the objection to the award, 
pursuant to the formal purchase procedure. The protest must be submitted no later than 
seven (7) calendar days after the notice of intent to award is posted on the City's Materials 
Management, 
Internet 
home 
page 
at 
https://www.glendaleaz.com/your_government/city_finances/procurement/procurement_policies. 
Untimely protests will not be considered.  
 
25. REMEDIES City shall have, in addition to the remedies provided herein, all remedies afforded 
by the Uniform Commercial Code as adopted by the State of Arizona. Contractor shall have, 
subject to the limitation imposed by the terms of this agreement, all remedies afforded by the 
Uniform Commercial Code as adopted by the State of Arizona. 
 
26. ASSIGNMENT Neither an order nor monies due thereunder shall be assigned in whole or in 
part without the City's prior written consent. 
 
27. ADDENDA Any change to the proposal will be in the form of a numbered addendum issued by 
the Procurement Division. The addendum will be furnished to all who received the proposal. 
The City will not be responsible for any oral or written instructions made by any employees, 
officers, contracted consultant or agent of the City in regard to the proposal. The City will not 
be responsible for offerors adjusting their offer based on oral or written instructions. 
 
28. SPECIAL ACCOMMODATIONS Please contact Procurement at 930-2862 at least 3 days prior 
to the meeting for special accommodation. Hearing impaired persons, please use the Arizona 
Relay Service (1-800-367-8939). 
 
29. OFFER IDENTIFICATION The City is not responsible for the pre-opening of, post-opening of, 
or the failure to open, an offer not properly addressed or identified. 
 
30. OFFER TABULATION An electronic copy of the scoring may be requested by e-mailing the 
Procurement office at procurement@glendaleaz.com and referencing the proposal title and 
number. The information will be available for distribution when the City has completed its 
evaluation process of the offers received.

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 9 - 
1/29/18 
 
31. LIABILITY Except for the sole negligence of the City, its officers, managers, employees, or 
agents, Contractor shall be liable to the City for any physical damage to City property or for 
the death of, or personal injury to, City personnel arising out of Contractor's occupancy, 
maintenance, repair, replacement, installation and/or any other work performed pursuant to 
the contract. Contractor agrees to indemnify, defend and hold the City harmless from any 
claim or loss arising from such damage or injury. 
 
32. OSHA GUIDELINES The contractor shall be familiar with and operate within the guidelines set 
forth by the Occupational Safety and Health Act. 
 
33. PATENTS Seller agrees to defend City at seller's own expense, in all suit, actions, or 
proceedings in which City is made a defendant for actual or alleged infringement of any United 
States of America or foreign letters patent resulting from City’s use of the goods purchased 
as a result of this RFP. Seller further agrees to pay and discharge any and all judgments or 
decrees, which may be rendered in any such suit, action or proceedings against City. Seller 
agrees to indemnify and hold harmless the City from any and all license, royalty and 
proprietary fees or costs, including legal costs, which may arise out of City’s purchase and 
use of goods supplied by the seller. It is expressly agreed by seller, that these covenants are 
irrevocable and perpetual. 
 
34. VENDOR PERFORMANCE Prior offeror performance in regard to product, service, or 
representation of/from the offeror may be used in evaluation of this offer. Unsatisfactory 
performance to the City may be considered sufficient grounds for rejection of this offer. No 
offer will be awarded to any offeror who is in default on any contract with the City. 
 
35. PERFORMANCE SURETY REQUIREMENTS The performance sureties shall be in the form 
of a bond, cashier's check, certified check or money order. Personal or company checks are 
not acceptable unless certified. Letters of credit are not acceptable. Individual sureties 
are not acceptable. 
 
PERFORMANCE SURETY The successful proposer shall, at the time of entering into the 
contract, furnish a performance surety in the form of a bond, money order or certified or 
cashier's check, in the amount of 10 percent of the contract amount guaranteeing the 
faithful performance of the contract by the proposer. 
 
If a bond is submitted, it shall be written on the form provided by the City as an attachment 
to the proposal documents. The attorney-in-fact who executes the bond on behalf of the 
surety shall affix to the bond a certified and current copy of the power of attorney. The 
bond must be written by a surety with a Best Rating no less than an A and must be 
authorized and licensed to do business in this State by the Arizona Department of 
Insurance. Individual sureties and letters of credit are not acceptable. 
 
36. FUND APPROPRIATION CONTINGENCY The contractor and the City recognize that the 
continuation of any contract after the close of any given fiscal year of the City; which ends on 
June 30, shall be subject to the approval of the budget of the City providing the contract item 
is an expenditure therein. The City does not guarantee that the budget item will be actually 
adopted, as it is the determination of the City Council at the time of the adoption of the budget.

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 10 - 
1/29/18 
37. NOTIFICATION OF AWARD The successful offeror(s) will be notified that their offer has been 
accepted by the City Council as recommended for award. 
 
38. NON-EXCLUSIVITY  The City, in its sole discretion, reserves the right to request the materials 
or services set forth herein from other sources when deemed necessary and appropriate.  No 
exclusive rights are included in this Agreement.  
 
39. COOPERATIVE USE OF CONTRACT This agreement may be extended for use by other 
governmental agencies and political subdivisions of the State. Any such usage by other entities 
must be in accord with the ordinances, charter, rules and regulations of the respective entity 
and the approval of the Contractor and City.  For a list of SAVE members, click on the following 
link:  http://www.mesaaz.gov/business/purchasing/save  
 
40. PROHIBITIONS - Contractor, and on behalf any subcontractor, certifies, to the extent 
applicable under A.R.S. §§ 35-391 et seq and 35-393 et seq, that neither has "scrutinized" 
business operations, as defined in the proceeding statutes, in the countries of Sudan or Iran. 
 
41. IMMIGRATION LAW COMPLIANCE Contractor, and on behalf any subcontractor, warrants, to 
the extent applicable under A.R.S. § 41-4401, compliance with all federal immigration laws 
and regulations that relate to their employees as well as compliance with A.R.S. § 23-214(A) 
which requires registration and participation with the E-Verify Program.  Any breach of 
warranty described above is considered a material breach of this Agreement and is subject to 
penalties up to and including termination of this Agreement.  City of Glendale (“City”) retains 
the legal right to inspect the papers of Contractor or subcontractor employee who performs 
work under this Agreement to ensure that Contractor or any subcontractor is compliant with 
the warranty described above.  City may conduct random inspections, and upon request of 
the City, Contractor shall provide copies of papers and records demonstrating continued 
compliance with the warranty described above.  Contractor agrees to keep papers and records 
available for inspection by the City during normal business hours and will cooperate with City 
in exercise of its statutory duties and not deny access to its business premises or applicable 
papers or records for the purposes of enforcement of this Section.  Contractor agrees to 
incorporate into any subcontracts under this Agreement the same obligations imposed upon 
itself and expressly accrue those obligations directly to the benefit of the City.  Contractor also 
agrees to require any subcontractor to incorporate into each of its own subcontracts under 
this Agreement the same obligations above and expressly accrue those obligations to the 
benefit of the City.  Contractor’s warranty and obligations under this Section I to the City is 
continuing throughout the term of this Agreement or until such time as the City determines, 
in its sole discretion, that Arizona law has been modified in that compliance with this section 
is no longer a requirement.  The “E-Verify Program” above means the employment verification 
program administered by the United States Department of Homeland Security, the Social 
Security Administration, or any successor program. 
 
42. CONTRACT ADMINISTRATOR The staff member identified as the Contract Administrator for 
a solicitation serves as the liaison between Materials Management, the city and the successful 
contractor.   The Contract Administrator manages the contract, overseeing the daily 
operations, scheduling, performance and compliance of the agreement by all parties.  The 
Contract Administrator is responsible for:

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 11 - 
1/29/18 
a. Establishing and maintaining records and documentation 
b. Monitoring the contractor’s performance 
c. Handling issues and disputes 
d. Exercising extension options 
e. Initiating contract modifications 
f. Initiating rebids or new solicitations 
 
43. FORCE MAJEURE  
a. 
Except for payment of sums due, neither party shall be liable to the other nor 
deemed in default under this contract if and to the extent that such party’s 
performance of this Contract is prevented by reason of force majeure.  The term 
“force majeure” means an occurrence that is beyond the control of the part 
affected and occurs without its fault or negligence.  Without limiting the 
foregoing, force majeure includes acts of God; acts of the public enemy; war; 
riots; strikes; mobilization; labor disputes; civil disorders, fire; flood; lockouts; 
injunctions-interventions-acts; or failures or refusals to act by government 
authority; and other similar occurrences beyond the control of the party 
declaring force majeure which such party is unable to prevent by exercising 
reasonable diligence. 
b. 
Force majeure shall not include the following circumstances: 
i. 
Late delivery of equipment or materials caused by congestion at a 
manufacturer’s plant or elsewhere, or an oversold condition of the market. 
ii. 
Late performance by a subcontractor unless the delay arises out of a force 
majeure occurrence in accordance with this force majeure term and 
condition; or 
iii. 
Inability of either the Contractor or any subcontractor to acquire or maintain 
any required insurance, bonds, licenses or permits.

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 12 - 
1/29/18 
EXHIBIT 3: Insurance Requirements 
By signing on the Offer/Bid page, solicitation Amendment(s), or cover letter accompanying the 
submittal documents, Offerors are certifying that they understand the following notices and 
agree to comply with all required terms and conditions. 
1) INSURANCE REQUIREMENTS. OFFEROR shall procure and maintain until all their obligations 
have been discharged, insurance against claims for injury to persons or damage to property 
that may arise from or in connection with this Solicitation.  The insurance requirements herein 
are minimum requirements for this Solicitation and in no way limit the indemnity covenants 
contained herein. The City of Glendale in no way warrants that the minimum limits contained 
herein is sufficient to protect the OFFEROR from liabilities that might arise.  OFFEROR is free 
to purchase such additional insurance as OFFEROR determines necessary. 
 
a) Minimum Scope and Limits Of Insurance: OFFEROR shall provide coverage with limits of 
liability not less than those stated below. 
 
i) Commercial General Liability – Occurrence Form 
 
Policy shall include bodily injury, property damage, personal and advertising injury and 
broad form contractual liability coverage.  
 
General Aggregate                                          
 
$2,000,000 
Products – Completed Operations Aggregate  
$1,000,000 
Personal and Advertising Injury                       
$1,000,000 
Each Occurrence                                              
$1,000,000 
 
(1) The policy shall be endorsed to include the following additional insured 
language: “The City of Glendale, and its departments, officers, officials, agents, 
employees and volunteers shall be named as additional insureds with respect to 
liability arising out of the solicitation.   Such additional insured shall be covered 
to the full limits of liability purchased by the OFFEROR, even if those limits of 
liability are in excess of those required herein. 
 
(2) Policy shall contain a waiver of subrogation endorsement in favor of the “City of 
Glendale, and its departments, officers, officials, agents, employees and 
volunteers”.  This provision applies regardless of whether or not the City of 
Glendale has received a waiver of subrogation endorsement from the insurer.   
 
ii) Business Automobile Liability – (if driving is not a part of the scope of work, excluding 
driving from the place of business and to the City departments, this coverage can be 
eliminated.) 
Bodily Injury and Property Damage for any owned, hired, and/or non-owned vehicles 
used 
in 
the 
performance 
of 
this 
Agreement. 
Combined 
Single 
Limit 
(CSL)           $1,000,000. 
 
(1) The policy shall be endorsed to include the following additional insured 
language: “The City of Glendale, and its departments, officers, officials, agents, 
employees and volunteers shall be named as additional insureds with respect to

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 13 - 
1/29/18 
liability arising out of the activities performed by or on behalf of the OFFEROR, 
involving automobiles owned, Licensed, hired or borrowed by the OFFEROR." Such 
additional insured shall be covered to the full limits of liability purchased by the 
OFFEROR, even if those limits of liability are in excess of those required by this 
License. 
 
(2) Policy shall contain a waiver of subrogation endorsement in favor of the “City of 
Glendale, and its departments, officers, officials, agents, employees and 
volunteers” for losses arising from work performed by or on behalf of the 
OFFEROR.  This provision applies regardless of whether or not the City of Glendale 
has received a waiver of subrogation endorsement from the insurer.   
 
iii) Worker's Compensation and Employers' Liability 
Workers' Compensation Statutory  
Employers' Liability     
Each Accident                          $1,000,000 
Disease – Each Employee 
$1,000,000 
Disease – Policy Limit              $1,000,000 
 
(1) Policy shall contain a waiver of subrogation endorsement in favor of the “City of 
Glendale, and its departments, officers, officials, agents, employees and 
volunteers” for losses arising from OFFEROR activities.  This provision applies 
regardless of whether or not the City of Glendale has received a waiver of 
subrogation endorsement from the insurer.   
 
iv) Fidelity Insurance (Crime Bond) 
(1) The policy shall be issued with minimum limits of $1,000,000. 
(2) The policy shall include coverage for all directors, officers, agents and employees 
of the Offeror. 
(3) The policy shall include coverage for third party fidelity. 
(4) The policy shall include coverage for theft. 
(5) The policy shall contain no requirement for arrest and conviction. 
(6) The policy shall cover loss outside the premises of the Named Insured. 
(7) The Department shall be endorsed (Blanket Endorsements are not acceptable) as 
a Loss Payee as our interest may appear. 
 
v) Professional Liability (Errors & Omissions) – no less than $2,000,000 per occurrence 
or claim, $4,000,000 aggregate. Should include coverage for Plan administration and 
fiduciary administrative duties. Full description of the E&O Coverage provided. 
 
Errors & Omissions are written as Claims Made Policies. If any of the policies provide 
coverage on a claims-made basis the following shall apply:   
(1) The Retroactive Date must be shown and must be before the date of the contract or 
the beginning of contract work. 
(2) Insurance must be maintained and evidence of insurance must be provided for at least 
five (5) years after completion of the contract of work.

City of Glendale 
Solicitation Number: RFP 21-52 /42100072 
WATER METER REPLACEMENT CONSULTANT 
 
EXHIBITS PACKAGE 
CITY OF GLENDALE 
Procurement Division 
5850 West Glendale Ave, 
Suite 317 
Glendale, Arizona 85301 
 
- 14 - 
1/29/18 
(3) If coverage is canceled or non-renewed, and not replaced with another claims-made 
policy form with a Retroactive Date prior to the contract effective date, the Consultant 
must purchase “extended reporting” coverage for a minimum of five (5) years after 
completion of contract work 
 
vi) Cyber Liability – with limits not less than $5,000,000 per occurrence or claim, 
$10,000,000 aggregate.  Coverage shall be sufficiently broad to respond to the duties 
and obligations as is undertaken by the Vendor in this agreement and shall include but 
not be limited to, claims involving infringement of intellectual property, including but 
not limited to infringement copyright, trademark, trade dress, invasion of privacy 
violations, information theft, damage to or destruction of electronic information, 
release of private information, alteration of electronic information, extortion and 
network security.  The policy shall provide coverage for breach response costs as well 
as regulatory fines and penalties as well as credit monitoring expenses with limits 
sufficient to respond to these obligations.  If the policy is written on a claims-made 
basis a Retroactive Date must be shown as indicated item v) above.     
 
vii) Additional Insurance Requirements:  The policies shall include, or be endorsed to 
include, the following provisions: 
 
(1) Policies shall stipulate that the insurance afforded by the organization shall be 
primary insurance and that any insurance carried by the City of Glendale shall be 
excess and not contributory insurance. 
 
(2) Coverage provided by the organization shall not be limited to the liability assumed 
under the indemnification provisions of the license or contract. 
(3) If the Vendor maintains broader coverage and/or higher limits than the minimum 
shown, the City requires and shall be entitled to the broader coverage and/or the 
higher limits maintained by the Vendor.  Any available insurance proceeds in excess 
of the specified minimum of insurance and coverage shall be available to the City. 
(4) Vendor shall require and verify that all subcontractors (subconsultants) maintain 
insurance meeting all the requirements stated herein, and Vendor shall ensure that 
City is an additional insured on insurance required from subcontractors 
(subconsultants).  
(5) If the Vendor is awarded the solicitation, the Vendor shall furnish the City with 
original Certificates of Insurance including all required amendatory endorsements 
before the work begins.  However, failure to obtain the required documents prior to 
the work beginning shall not waive the Vendor’s obligation to provide them.  The 
City reserves the right to require complete, certified copies of all required insurance 
policies including endorsements required by these specifications, at any time

EXHIBIT D 
Professional Services Agreement 
COMPENSATION 
METHOD AND AMOUNT OF COMPENSATION 
Method and amount of compensation is determined based on RFP 21-52 Pricing Sheet. 
NOT-TO-EXCEED AMOUNT 
The total amount of compensation paid to Consultant for full completion of all work required by the Project during 
the entire term of the Project must not exceed $765,398.40.  
DETAILED PROJECT COMPENSATION 
See attached Price Sheet.

Arcadis U.S., Inc. 
Pricing Sheet 
Labor Category
2022
2023
2024
2025
Project Principal
$           297.00
 $           308.88
 $           321.24
 $           334.08
Project Manager
$           250.00
 $           260.00
 $           270.40
 $           281.22
Principal Consultant II
$           225.00
 $           234.00
 $           243.36
 $           253.09
Principal Consultant I
$           180.00
 $           187.20
 $           194.69
 $           202.48
Senior Consultant II
$           160.00
 $           166.40
 $           173.06
 $           179.98
Senior Consultant I
$           140.00
 $           145.60
 $           151.42
 $           157.48
Management Consultant I
$           125.00
 $           130.00
 $           135.20
 $           140.61
Management Consultant I
$           110.00
 $           114.40
 $           118.98
 $           123.74
Project Assistant II
$           142.00
 $           147.68
 $           153.59
 $           159.73
Project Assistant I
$           110.00
 $           114.40
 $           118.98
 $           123.74
Technical Consultant
$           245.00
 $           254.80
 $           264.99
 $           275.59
Data Quality Control
$           207.00
 $           215.28
 $           223.89
 $           232.85
Data Analyst
$           235.00
 $           244.40
 $           254.18
 $           264.34
Billable Labor Rates ($/Hr)