C-8630-1

AMENDMENT NO. 1
Supply, Placement, Removal and Thermal Reactivation of Granular Activated Carbon
Agreement
(City of Glendale, Contract No. C-8630)

This Amendment No. 1 (“Amendment”) to the Supply, Placement, Removal and Thermal
Reactivation of Granular Activated Carbon Agreement (“Agreement”) is made this

day of , 2022, (“Effective Date”), by and between the City of Glendale, an Arizona
municipal corporation (“City”) and Calgon Carbon Corporation, a Delaware corporation
authorized to do business in Arizona (“Contractor”).

RECITALS

A. City and Calgon Carbon Corporation (“Contractor”) previously entered into an
agreement, Contract No. C-8630, dated September 24, 2013 (“Agreement”); and

B. ‘The initial term expires September 23, 2023, with a Renewal and Extension Option
and the City desires to execute the option and to align the expiration date with other
cities in the metro-Phoenix area;

Cc. Annual price adjustments are calculated on several U.S. Department of Labor price
indices and as operating cost factors have changed, the parties desire to modify the
calculation components;

D. City and Contractor wish to modify and amend the Agreement subject to and strictly
in accordance with the terms of this Amendment.

AGREEMENT
In consideration of the mutual promises set forth herein and other good and valuable

consideration, the receipt and sufficiency of which are hereby acknowledged, the City and
Contractor hereby agtee as follows:

1. Recitals. The recitals set forth above are not merely recitals but form an integral part
of this Amendment.
2. Term and Extension. The term of the Agreement is extended for the period from

September 24, 2023 through January 17, 2027, unless otherwise terminated or canceled
as provided by the Agreement. All other provisions of the Agreement except as set
forth in this Amendment shall remain in their entirety.

3. Amendments to Agreement, Exhibit A and Exhibit B as follows:
1. Agreement, 2.3 Price Adjustment, Annual Adjustment.
Remove the section language in its entirety and replace with the following:

As further set forth in subsection 4.1 (F) of Exhibit A, the Local Service Price,
the Non-Local Service Price and the Additional Virgin GAC Price shall each be

4/29/2021

subject to annual adjustment in accordance with Exhibit B, Appendix 5. In no
event shall any such annual adjustment increase such prices by more than ten
percent (10%) or decrease such prices by more than five percent (5%). No
amounts in excess of these limits (either increases or decreases) shall be cattied
over to subsequent years.

. Exhibit A, Payments For GAC Services, 4.1 Unit Pricing (F) Annual
Adjustments to Unit Prices.

Remove the section language in its entirety and replace with the following:

‘The percent adjustment shall be calculated by taking the percent difference for
each index during the twelve-month period from July through June of the last
completed calendar year as compared to the twelve-month period from July
through June of the calendar year immediately preceding the last completed
calendar year. ‘These percentages will then be averaged per the proportions given
in Appendix 5 for calculating the final percent adjustment to which Virgin GAC
and Custom Municipal Reactivated (CMR) GAC will be subject. In no event shall
any such annual adjustment increase such prices by more than ten percent (10%)
or decrease such prices by more than five percent (5%). No amounts in excess of
these limits (either increases or decreases) shall be carried over to subsequent years.
In addition, regardless of any annual fee adjustment calculation, fees covered by
this Agreement will at no time be reduced below the Initial Fee.

Exhibit B, Appendix 5, Price Adjustment:
Remove appendix in its entirety and replace with the following:

Virgin GAC:
The fees payable pursuant hereto will be adjusted on January 18th for each year

after the renewal year of 2022 by the annual percentage change in the following
three price indices, in the proportion indicated next to each index:
1) US. Department of Labor PPI for Basic Organic Chemicals (WPU0614) @
35% weight
2) U.S. Department of Labor PPI for Other Petroleum and Coal Products Mfg.
(PCU32419-32419) @ 35% weight
3) Transportation: U.S. Department of Labor PPI by Commodity for
Transportation Services: Truck Transportation of Freight (WPU3012) @ 30%
weight

The percent adjustment shall be calculated by taking the percent difference for
each index during the twelve-month period from July through June of the last
completed calendar year as compared to the twelve month period from July
through June of the calendar year immediately preceding the last completed
calendar year. These percentages will then be averaged per the proportions shown

4/29/2021

above for calculating the final percent adjustment to which all virgin GAC will be
subject.

Annual Limits: Annual incteases are limited to a maximum of 10% regardless of
the above calculation, and annual decreases ate limited to a maximum of 5%
regardless of the above calculation. No amounts in excess of these limits (either
increases or decreases) shall be carried over to subsequent years.

Initial Fee Limit: Regardless of any annual fee adjustment calculation, fees
covered by this Agreement will at no time be reduced below the Initial Fee of $1.36
per pound.

Custom Municipal Reactivated (CMR) GAC:

The fees payable pursuant hereto will be adjusted on January 18" for each year
after the renewal year of 2022 by the annual percentage change in the following
three price indices, in the proportion indicated next to each index:

1) Natural Gas: U.S. Department of Labor PPI Commodity Data for Fuels and
Related Products: Natural Gas: (WPU055) @25% weight

2) Labor: U.S. Department of Labor CPI for Urban Wage Earners for the West
(CWUR0400SA0) @ 50% weight

3) Transportation: U.S. Department of Labor PPI by Commodity for
Transportation Services: Truck Transportation of Freight (WPU3012) @ 25%
weight

The percent adjustment shall be calculated by taking the percent difference for
each index during the twelve month period from July through June of the last
completed calendar year as compated to the twelve month period from July
through June of the calendar year immediately preceding the last completed
calendar year. These percentages will then be averaged per the proportions shown
above for calculating the final percent adjustment to which all reactivated carbon
will be subject.

Annual Limits: Annual increases are limited to a maximum of 10% regardless of
the above calculation, and annual decreases are limited to a maximum of 5%
regardless of the above calculation. No amounts in excess of these limits (either
increases or decreases) shall be carried over to subsequent years.

Initial Fee Limit: Regardless of any annual fee adjustment calculation, fees
covered by this Agreement will at no time be reduced below the Initial Fee of $0.73
pet pound.

Additional Virgin Make-Up Pricing for CMR:

The custom reactivated carbon (CMR) fee in the Agreement includes 15% virgin
make-up GAC. In those cases where additional virgin make-up GAC in excess of
15% is required to meet quality control requirements or to replace spent GAC that
was fouled and could not be cleaned, the additional virgin make-up GAC shall be
provided at the same price as Virgin GAC at that time of make-up. This price shall
also be adjusted on an annual basis, using the calculation as for Virgin GAC above.

4/29/2021

Fuel Surcharge:
The Fuel Surcharge shall consist of a mileage charge based on the difference

between the base of $4.00/gallon and the fuel index at time of actual delivery in
accordance with Table 1 in this Appendix. The mileage and surcharge amount will
be established at time of delivery by the Company.

Each Monday at 5:00pm Eastern Standard Time, the Company will determine
the Average Diesel Price. The Non-Local Fuel Surcharge will become effective
on Tuesday of that week (except if Monday is a National Holiday, then it will be
Wednesday) and will be effective for the following seven (7) day period.

In computing charges, fractions of less than one-half cent will be dropped and
fractions of one-half cent or more will be increased to the next whole cent.

If the Average Diesel Price is greater than $5.50 per gallon, the Non-Local Fuel
Surcharge will increase one (1) cent for every five (5) cent increase of the
Average Diesel Price. If the Average Diesel Price is less than $4.50 per
gallon, the Company will not charge a Fuel Surcharge.

The rest of this page is left blank.

4/29/2021

TABLE 1

When the When the When the
Fuel Index Fuel Index Fuel Index
Is: Is: Is:
At But Fuel At But Fuel At But Fuel
Least | Less | Surcharge Least | Less | Surchatge Least | Less | Surcharge
Than Than Than
$4.00 | $4.05 | 0 Cent per $4.50 | $4.55 1 Cents $5.00 | $5.05 | 11 Cents
Mile per Mile pet Mile
$4.05 | $4.10] 0 Cents $4.55 | $4.60 | 2 Cents $5.05 | $5.10 | 12 Cents
pet Mile pet Mile per Mile
$4.10 | $4.15 | 0 Cents $4.60 | $4.65 | 3 Cents $5.10 | $5.15 | 13 Cents
pet Mile per Mile pet Mile
$4.15 | $4.20} 0 Cents $4.65 | $4.70 | 4 Cents $5.15 | $5.20] 14 Cents
pet Mile per Mile per Mile
$4.20 | $4.25 0 Cents $4.70 | $4.75 5 Cents $5.20 | $5.25 | 15 Cents
pet Mile per Mile per Mile
$4.25 | $4.30! 0 Cents $4.75 | $4.80 | 6 Cents $5.25 | $5.30 | 16 Cents
pet Mile per Mile per Mile
$4.30 | $4.35 0 Cents $4.80 | $4.85 7 Cents $5.30 | $5.35 | 17 Cents
per Mile per Mile per Mile
$4.35 | $4.40 | 0 Cents $4.85 | $4.90] 8 Cents $5.35 | $5.40 | 18 Cents
pet Mile per Mile per Mile
$4.40 | $4.45 | 0 Cents $4.90 | $4.95] 9 Cents $5.40 | $5.45 | 19 Cents
pet Mile per Mile per Mile
$4.45 | $4.50 | 0 Cents $4.95 | $5.00 | 10 Cents $5.45 | $5.50 | 20 Cents
per Mile per Mile pet Mile

Insurance Certificate. Current certificate will expire on June 1, 2022 and a new
certificate applying to the extended term must be provided prior to this date to
Materials Management and the Contract Administrator.

Non-discrimination. Contractor must not disctiminate against any employee or
applicant for employment on the basis of race, color, religion, sex, national origin, age,
marital status, sexual orientation, gender identity or expression, genetic characteristics,
familial status, U.S. military veteran status or any disability. Contractor will require any
Sub-contractor to be bound to the same requirements as stated within this section.
Contractor, and on behalf of any subcontractors, warrants compliance with this
section.

4/29/2021

No Boycott of Israel. To the extent A.R.S § 35-393 through § 35-393.03 are
applicable, the parties hereby certify that they are not currently engaged in, and agree
for the duration of the Agreement to not engage in, a boycott of goods or services
from Israel, as that term is defined in A.R.S § 35-393,

Attestation of PCI Compliance. When applicable, the Contractor will provide the
City annually with a Payment Card Industry Data Security Standard (PCI DSS)
attestation of compliance certificate signed by an officer of Contractor with oversight
responsibility.

Ratification of Agreement. City and Contractor hereby agree that except as
expressly provided herein, the provisions of the Agreement shall be, and remain in full
force and effect and that if any provision of this Amendment conflicts with the
Agreement, then the provisions of this Amendment shall prevail.

[Signatures on the following page.]

4/29/2021

CITY OF GLENDALE, an Arizona
municipal corporation

Kevin R. Phelps, City Manager

ATTEST:

Julie K. Bower, City Clerk (SEAL)

APPROVED AS TO FORM:

Michael D. Bailey, City Attorney

Calgon Carbon Corporation
A Delaware Corporation

OWS-

By: Jeremy J. Jones, DWS Project
Manager
Its: _Authorized Representative

4/29/2021