PowerPoint Presentation
Extracted text (via pymupdf)
142555 characters
FY2023-2032 Capital Improvement Plan March 1, 2022 Agenda 2 1) Capital Improvement Plan (CIP) Overview 2) Capital Improvement Plan Projects a) Drainage b) Facility Maintenance c) Library d) Parks e) Public Safety f) Streets 3) Council Feedback and Questions Budget Calendar 3 Item Date Workshop #1 – Budget Overview / Revenues / Five-Year Financial Forecasts January 11, 2022 Workshop #2 – FY23-32 Capital Improvement Plan February 1, 2022 Workshop #3 – FY23-32 Capital Improvement Plan March 1, 2022 Workshop #4 – (All Day) FY23 Operating Budget Department Presentations April 5, 2022 Workshop #5 – (All Day) FY23 Operating Budget Department Presentations April 7, 2022 Workshop #6 – FY23 Final Budget Workshop April 19, 2022 Voting Meeting – Tentative Budget Adoption May 10, 2022 Voting Meeting – Final Budget Adoption / Property Tax Levy June 14, 2022 Voting Meeting – Property Tax Adoption June 28, 2022 CIP Funding Sources 4 • Development Impact Fees – One-time charges to developers for new development – New or expanded infrastructure • General Obligation Bonds – Debt issuance must be authorized by Voters – Streets, Public Safety, Parks, Government Facilities, Open Space/Trails, Libraries, and Flood Control – Debt service paid by Secondary Property Tax • Grants – Federal or state grant funding – Often require a match contribution to the project • Pay-As-You-Go – Cash funded projects CIP Funding Sources 5 • Transportation Sales Tax – Half cent sales tax – Improve service for all modes of transportation • Highway User Revenue Funds – Restricted Special Revenue Fund – Right of Way acquisition, construction, reconstruction, maintenance, and repair • Enterprise Funds – Water/Sewer o Funding can come from G. O. Bonds, revenue bonds, revenue obligations or cash financing o Debt service paid from future water/sewer fee revenue – Landfill – paid by Landfill user fees – Solid Waste – paid by Solid Waste user fees FY23-32 Draft CIP Report 6 • CIP Reports include Estimated FY22 Carryover – Estimates will continue to change as we get closer to the end of the fiscal year – Will be adjusted in April and updated before Final Budget Workshop • Drainage, Facility Maintenance, Parks, Public Safety, and Streets will be presented today 7 FY23-32 Drainage CIP Overview • Funded by Flood Control G. O. Bonds (63%), Grants (30%) and General Fund (7%) • Focus on Designing and Constructing Flood Control Drainage Improvements – Large projects broken into stand alone packages to continue progress – Design on Package 1 for Bethany Home Road from 43rd Ave to 51st Ave underway; Construction expected to begin FY23 • Work in coordination with internal and external partners – Maricopa County Flood Control District (MCFlood) – Maximizing matching funds – Arterial Reconstruction Program (Transportation) FY23-32 Drainage Projects 8 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPDR19040 CAMELBACK ROAD, 51ST TO 58TH 3,474,000 0 3,474,000 CIPDR19078 83RD AVE, BETHANY HM TO CAMELBACK 3,443,000 3,443,000 CIPDR19079 59TH AVE & T-BIRD RD STORM DRAIN 2,179,000 2,179,000 CIPDR21019 DRAINAGE IMP. GLENN DR., 59TH-52ND 50,000 732,000 3,202,000 0 3,984,000 CIPDR21034 BETHANY HOME SD, 43RD TO 51ST AVE 3,827,500 1,112,000 6,855,000 3,072,000 2,048,000 0 16,914,500 CIPDR79004 LOCAL DRAINAGE PROBLEMS 168,448 241,000 241,000 241,000 241,000 241,000 1,200,000 2,573,448 TOTAL 4,045,948 1,353,000 7,096,000 4,045,000 8,965,000 241,000 6,822,000 32,567,948 FY23-32 Drainage by Funding Source 9 FUND FUND NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 GENERAL FUND CAPITAL 19,065 241,000 241,000 241,000 241,000 241,000 1,200,000 2,424,065 2160 OTHER GRANTS 2,049,383 300,000 3,347,500 1,786,000 2,310,000 9,792,883 4110 FLOOD CONTROL G. O. BONDS 1,977,500 812,000 3,507,500 2,018,000 6,414,000 5,622,000 20,351,000 TOTAL 4,045,948 1,353,000 7,096,000 4,045,000 8,965,000 241,000 6,822,000 32,567,948 10 Camelback Road, 51st to 58th Avenue Project Number: CIPDR19040 Description: Installation of storm drain in Camelback Road from 51st to 58th Avenues. Project has been moved from FY25 to FY26. Justification: This project is identified in the Stormwater Management Plan (SMP). FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4110 – FLOOD CONTROL G. O. BONDS $3,474,000 $3,474,000 11 83rd Ave, Bethany Home Road to Camelback Road Project Number: CIPDR19078 Description: Installation of storm drain in 83rd Avenue from Bethany Home Road to Camelback Road. This project is currently programmed to begin design in FY28. Justification: This project is identified in the Stormwater Management Plan (SMP) completed and presented to the city and Flood Control District in July 2011. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4110 – FLOOD CONTROL G. O. BONDS $3,443,000 $3,443,000 12 59th Ave & Thunderbird Road Storm Drain Project Number: CIPDR19079 Description: Project will construct a storm drain in 59th Avenue between the Thunderbird Road intersection and the Arizona Canal Drainage Channel. It is currently programmed to begin design in FY28. Justification: Project is identified in the Stormwater Management Plan (SMP) presented to the city and Flood Control District of Maricopa County in July 2011. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4110 – FLOOD CONTROL G. O. BONDS $2,179,000 $2,179,000 13 Drainage Improvements Glenn Drive 59th Ave to 52nd Drive Project Number: CIPDR21019 Description: This project will install storm drainage in Glenn Drive from 59th Avenue to 52nd Avenue, to correct flooding in Glenn Drive, nearby alleys, and in Murphy Park. Justification: It is anticipated that project costs will be split between the City and the Maricopa County Flood Control District. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 2160 – OTHER GRANTS $286,000 $1,310,000 $1,596,000 4110 – FLOOD CONTROL G. O. BONDS $50,000 $446,000 $1,892,000 $2,388,000 14 Bethany Home Storm Drain 43rd Ave to 51st Ave Project Number: CIPDR21034 Description: Design and construction of storm drainpipe, inlets, catch basins and other appurtenances in a ½ square mile area centered on Bethany Home Road between 43rd Ave. and 51st Ave. Design began in FY21. Justification: Project is identified in the Storm Water Master plan adopted by the city in 2011. Maricopa County Flood Control District has budgeted to contribute $4.5 million toward completion of the project. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 2160 – OTHER GRANTS $1,900,000 $550,000 $3,347,500 $1,500,000 $1,000,000 $8,297,500 4110 – FLOOD CONTROL G. O. BONDS $1,927,500 $562,000 $3,507,500 $1,572,000 $1,048,000 $8,617,000 15 Local Drainage Problems Project Number: CIPDR79004 Description: Construct localized storm drainage improvements to mitigate drainage and/or flooding issues. Justification: Ongoing program addressing drainage issues in older neighborhoods and extends existing storm drain systems. The city will request grant contributions from Maricopa County Flood Control District. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL GOVERNMENT CIP $19,065 $241,000 $241,000 $241,000 $241,000 $241,000 $1,200,000 $2,424,065 2160 – OTHER GRANTS $149,383 $149,383 16 FY23-32 Facility Maintenance CIP Overview • Primarily Funded with General Fund (60%), Government Facility G. O. Bonds (15%), Cultural Facility G. O. Bonds (9%), ARPA Capital Projects (6%), • Focus on: – Improving existing assets through programmatic replacements • Follow industry standard replacement cycles – Replacing existing assets as needed – Downtown Campus Reinvestment • Updated pricing to current construction estimates and projected inflation FY23-32 Facility Maintenance Projects 17 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPFC19016 GLENDALE OPS CAMPUS-FIELD STAFF BLD 815,867 2,768,845 6,270,209 1,703,946 11,558,867 CIPFC19037 UNDERGROUND STORAGE TANK REPLACE 665,000 665,000 CIPFC19038 CITY HALL BUILDING REMODEL 866,523 10,000,000 23,973,300 5,000,000 39,839,823 CIPFC19061 ELECTRICAL SYSTEM RENEWAL 300,000 70,000 70,000 70,000 70,000 350,000 930,000 CIPFC19062 ELEVATOR SYSTEM RENEWAL 65,000 65,000 65,000 65,000 65,000 325,000 650,000 CIPFC19063 FIRE PROTECTION RENEWAL 210,000 240,000 200,000 200,000 200,000 1,050,000 CIPFC19064 SECURITY CAMERA IMPROVEMENTS 1,550,554 1,550,554 CIPFC19065 PLUMBING SYSTEM RENEWAL 180,000 100,000 100,000 100,000 100,000 500,000 1,080,000 CIPFC19068 ROOFING SYSTEM RENEWAL 18,840 565,000 770,000 797,500 770,000 310,000 310,000 3,541,340 CIPFC19071 HVAC REPAIR/REPLACEMENTS 710,000 600,000 475,000 290,000 100,000 500,000 2,675,000 CIPFC20023 ADULT CENTER WEST RENOVATION 250,100 1,016,000 1,266,100 FY23-32 Facility Maintenance Projects 18 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPFC22084 ROOF REPAIR/REPLACEMENTS 382,520 382,520 CIPFC22086 CITY HALL PARKING GARAGE 769,377 1,000,000 1,588,650 3,358,027 CIPFC23028 FLEET SHOP EQUIP. REPLACEMENT 75,000 75,000 CIPFC23033 ADULT CENTER EAST RENOVATION 328,250 1,245,000 1,573,250 CIPFC23034 AIRPORT MATERIALS LAB RENOVATION 139,216 363,509 502,725 CIPFC23035 CIVIC CENTER ANNEX RENOVATION 134,824 360,026 494,850 CIPFC23036 CIVIC CENTER BEAD MUSEUM RENOVATION 233,064 889,036 1,122,100 CIPFC23037 GRPSTC SECOND FLOOR RENOVATION 57,596 154,604 212,200 CIPFC23038 MEDIA CENTER RENOVATION 78,450 337,000 415,450 CIPFC23039 SINE BLDG 2ND FLOOR EAST RENOVATION 24,575 184,000 208,575 CIPFC23040 SINE BLDG 2ND FLOOR WEST RENOVATION 169,011 788,000 957,011 CIPFC23041 GLENDALE OPS CAMPUS RENOVATION 131,036 1,939,023 3,912,617 1,046,324 7,029,000 CIPFC23043 COUNCIL CHAMBERS 500,000 500,000 2,100,000 1,000,000 4,100,000 FY23-32 Facility Maintenance Projects 19 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPFC70800 BUILDING MAINT. RESERVE 139,734 2,000,000 2,500,000 2,500,000 2,500,000 2,500,000 12,500,000 24,639,734 CIPFC70801 CAMELBACK RANCH MAINTENANCE RESERVE 800,074 1,673,504 1,673,504 1,673,504 1,673,504 1,673,504 8,367,520 17,535,114 CIPPK70803 CAPITAL REPAIR-ARENA 153,845 877,648 1,391,121 500,000 500,000 500,000 2,500,000 6,422,614 CIPPK77516 AMPHITHEATER RENOVATIONS 2,771,140 1,000,000 4,000,000 5,000,000 12,771,140 TOTAL 10,183,560 27,927,172 45,472,820 21,023,973 10,081,121 6,564,828 25,352,520 146,605,994 FY23-32 Facility Maintenance Projects 20 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPFC70800 BUILDING MAINT. RESERVE 139,734 2,000,000 2,500,000 2,500,000 2,500,000 2,500,000 12,500,000 24,639,734 CIPFC70801 CAMELBACK RANCH MAINTENANCE RESERVE 800,074 1,673,504 1,673,504 1,673,504 1,673,504 1,673,504 8,367,520 17,535,114 CIPPK70803 CAPITAL REPAIR-ARENA 153,845 877,648 1,391,121 500,000 500,000 500,000 2,500,000 6,422,614 CIPPK77516 AMPHITHEATER RENOVATIONS 2,771,140 1,000,000 4,000,000 5,000,000 12,771,140 TOTAL 10,183,560 27,927,172 45,472,820 21,023,973 10,081,121 6,564,828 25,352,520 146,605,994 FY23-32 Facility Maintenance by Funding Source 21 FUND FUND NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 GENERAL GOVERNMENT CIP 4,441,054 14,401,392 22,610,913 9,939,886 6,168,504 5,518,504 25,352,520 88,432,773 4020 HURF CAPITAL PROJECTS 3,450 3,450 4030 TRANSPORTATION SALES TAX CIP 300,000 842,793 1,719,160 1,289,829 2,779,099 1,046,324 7,977,205 4060 GOVERNMENT FACILITY G. O. BONDS 1,934,279 3,770,436 12,529,434 3,090,312 1,133,518 22,457,979 4080 CULTURAL FACILITY G. O. BONDS 2,771,140 1,000,000 4,000,000 5,000,000 12,771,140 4610 ARPA CAPITAL PROJECTS 435,086 6,917,178 1,822,000 9,174,264 6020 WATER FUND 296,650 989,601 1,916,942 3,203,193 6030 SEWER FUND 2,322 2,322 6120 SOLID WASTE FUND 5,351 874,371 1,703,946 2,583,668 TOTAL 10,183,560 27,927,172 45,472,820 21,023,973 10,081,121 6,564,828 25,352,520 146,605,994 22 Glendale Ops Campus – Field Staff Building Project Number: CIPFC19016 Description: This project is for the design and construction of the field staff building located on the operations campus. The building will serve as the primary location for Water Services, Transportation, PFRSE, and Field Operations staff. Justification: Aging infrastructure, security, and operational efficiency concerns must be addressed in order to continue to provide effective service to the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030 – TRANS. SALES TAX CIP $300,000 $837,940 $1,632,952 $2,470,892 4060 – GOVT. FACILITIES G. O. BONDS $213,866 $947,236 $1,845,944 $2,793,180 6020 – WATER FUND $296,650 983,669 $1,916,942 $2,900,611 6120 – SOLID WASTE FUND $5,351 $874,371 $1,703,946 $2,578,317 23 Underground Storage Tank Replacement Project Number: CIPFC19037 Description: This project is for replacement of aging below-ground double-walled vaulted fuel storage tanks located at the Operations Complex, as well as associated piping. The tanks are tested at regular intervals, and are anticipated needing replacement in FY23. Justification: Fuel sites are essential for the continued operation of the City. All city departments use this fuel site, including Public Safety vehicles, Solid Waste trucks, Transit buses, Water Services vehicles etc. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4060 – GOVT. FACILITIES G. O. BONDS $665.000 $665,000 24 City Hall Building Remodel Project Number: CIPFC19038 Description: This project is to reinvest in the City Hall campus by recreating a fully updated, modernized environment to include a centralized customer service area, enhanced security, and accessible, vibrant and dynamic areas. Restoring the infrastructure and functionality will extend the center for multiple decades. The project will include a new exterior, rebuilding the interior floor by floor, replacing aged infrastructure, and improving the functionality to provide for better service to the community. The design will be refined via future council workshops and will involve multiple phases for continued operations. Justification: The existing City Hall building was constructed in approximately 1984. The building no longer effectively serve the needs of the organization and the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $298,007 $4,336,822 $13,101,288 $2,558,882 $19,996,992 4060 – GOVT. FACILITIES G. O. BONDS $568,516 $9,050,012 $2,441,118 $11,491,130 4610 – ARPA CAPITAL PROJECTS $5,663,178 $1,822,000 $7,485,178 25 Electrical System Renewal Project Number: CIPFC19061 Description: Initial funding to review the City's existing electrical systems for demand, capacity, and life safety issues. Building assessments will identify priorities based on electrical system conditions and detail repair recommendations. Justification: Programmed repair/replacement of electrical systems and components will protect public health and safety, reduce long term life cycle costs, and enable provision of service delivery to the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $300,000 $70,000 $70,000 $70,000 $70,000 $350,000 $930,000 26 Elevator System Renewal Project Number: CIPFC19062 Description: Initial funding to review the City's existing elevator systems for demand, capacity, and life safety issues. Building assessments will identify priorities based on electrical system conditions and detail repair recommendations. Justification: Programmed repair/replacement of elevator systems and components will protect public health and safety, reduce long term life cycle costs, and enable provision of service delivery to the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $65,000 $65,000 $65,000 $65,000 $65,000 $325,000 $650,000 27 Fire Protection Renewal Project Number: CIPFC19063 Description: This project is to keep fire protection systems, identified as a Tier 1 Infrastructure, in good working order. Capital repairs are needed for a City-wide study, Libraries, Civic Center Campus, Advocacy, and GRPSTC. Justification: Programmed repair/replacement of electrical systems and components will protect public health and safety, reduce long term life cycle costs, and enable provision of service delivery to the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $210,000 $240,000 $200,000 $200,000 $200,000 $1,050,000 $210,000 28 Security Camera Improvements Project Number: CIPFC19064 Description: This project is to keep security camera systems, identified as a Tier 1 infrastructure, in good working order. Capital repairs are needed at multiple public safety buildings, City Hall, and buildings on the Glendale Operations Campus. Priorities are based upon building usage (Mission critical are highest tier for this component) and identified need. Justification: Programmatic repair/replacement of components of security systems will protect public health and safety, reduce long term life cycle costs, and enable provision of service delivery to the community, aligning resources with the City's strategic priorities and the Building Asset Philosophy. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $1,550,554 $1,550,554 29 Plumbing System Renewal Project Number: CIPFC19065 Description: Initial funding to review the City's existing plumbing systems for current state and capacity issues. The review will be City-wide. Building assessments will identify priorities based on plumbing system conditions and detail repair recommendations. Justification: Programmed repair/replacement of plumbing systems and components will protect public health and safety, reduce long term life cycle costs, and enable provision of service delivery to the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $180,000 $100,000 $100,000 $100,000 $100,000 $500,000 $1,080,000 30 Roofing System Renewal Project Number: CIPFC19068 Description: This project is to keep roofing systems, identified as a Tier 1 infrastructure, in good working order. Capital repairs are needed in multiple locations. Priorities are based on building usage and identified need. Justification: Programmed repair/replacement of roofing systems and components will protect public health and safety, reduce long term life cycle costs, and enable provision of service delivery to the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $565,000 $770,000 $797,500 $770,000 $310,000 $310,000 $3,522,500 31 HVAC Repair/Replacements Project Number: CIPFC19071 Description: This project is to keep HVAC systems, identified as a Tier 1 infrastructure, in good working order. Capital repairs are needed at various locations. Priorities are based upon building usage and identified cost. Justification: Programmed maintenance of HVAC systems and components will protect public health and safety, reduce long term life cycle costs, and enable provision of service delivery to the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $710,000 $600,000 $475,000 $290,000 $100,000 $500,000 $2,675,000 32 Adult Center West Renovation Project Number: CIPFC20023 Description: Buildout of 8,600 Sq Ft of raw space at the Adult Center 2nd Floor to accommodate the temporary officing of 22 Human Resources and 1 Security Employee. This will include the office/meeting space for 22 employees. Justification: The City Hall Project requires the building to be vacated during the construction phase. The Adult Center 2nd Floor allows for 22 employees to move into a temporary space for the duration of the City Hall construction process. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $161,600 $513,975 $675,575 4060 – GENERAL GOVT. G.O. BONDS $121,025 $121,025 4610 – ARPA CAPITAL PROJECTS $88,500 $381,000 $469,500 33 Roof Repair / Replacements Project Number: CIPFC22084 Description: This project is to replace roof at various locations including the Glendale Operations Center Buildings A, B, F, N, O, P; Airport Maintenance Building; and Bead Museum. Justification: These roofs at mission critical locations need replacement to avoid structural damage. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4060 – GENERAL GOVT. G.O. BONDS $382,520 $382,520 34 City Hall Parking Garage Project Number: CIPFC22086 Description: This project is to complete critical structural repairs to the City Hall Parking Garage. Justification: The City Hall Parking Garage requires critical structural repairs to ensure continued safety and structural integrity. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4060 – GENERAL GOVT. G.O. BONDS $769,377 $1,000,000 $1,588,650 $3,358,027 35 Fleet Shop Equipment Replacement Project Number: CIPFC23028 Description: This project is to replace old and failing shop equipment used to service the city's vehicle fleet. Includes vehicle lifts, tire changer & parts washer. Justification: Various pieces of equipment are in need of replacement. Having reliable shop equipment reduces downtime and outside contract maintenance costs. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $28,360 $28,360 4020 – HURF CAPITAL PROJECTS $3,450 $3,450 4030 – TRANS. SALES TAX CAPITAL $4,853 $4,853 6020 – WATER FUND $5,932 $5,932 6030 – SEWER FUND $2,322 $2,322 6120 – SOLID WASTE FUND $30,083 $30,083 36 Adult Center East Renovation Project Number: CIPFC23033 Description: Buildout of 6,000 sq. ft. of raw space at the City of Glendale Adult Center 2nd Floor to accommodate the temporary relocation of 59 Employees. This will include the office/meeting space for 22 employees. Justification: The City Hall Project requires the building to be vacated during the construction phase. The Adult Center 2nd Floor allows the City of Glendale to move 59 employees into a temporary space for the duration of the City Hall construction process. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $234,750 $864,000 $1,098,750 4610 – ARPA CAPITAL PROJECTS $93,500 $381,000 $474,500 37 Airport Materials Lab Renovation Project Number: CIPFC23034 Description: Demolition and Renovation of 2,400 sq. ft. of space at the Airport Materials Lab to accommodate the permanent move of 17 Engineering Inspectors from City Hall. Justification: The City Hall Project requires reconsideration of what services should be relocated. The relocation of the 17 Building Inspectors puts them closer to the bulk of the City's growth and their work on the West Side of the City. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $69,716 $291,009 $360,725 4610 – ARPA CAPITAL PROJECTS $69,500 $72,500 $142,000 38 Civic Center Annex Renovation Project Number: CIPFC23035 Description: Renovation of 2,500 sq. ft space at the Civic Center Annex to accommodate temporary installation of the One Stop Shop. This includes the front facing setup required for customer service and office space for 37 One Stop Shop employees. Justification: The City Hall Project requires the building to be vacated during the construction phase. The Adult Center 2nd Floor allows the City of Glendale to move 59 employees into a temporary space for the duration of the City Hall construction process. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $103,324 $356,026 $459,350 4610 – ARPA CAPITAL PROJECTS $31,500 $4,000 $35,500 39 Civic Center Bead Museum Renovation Project Number: CIPFC23036 Description: Buildout of 5,000 sq. ft. of raw space at the Civic Center Campus - Bead Museum to accommodate the temporary officing of 57 Employees. This will include the office/meeting space for 57 employees including all HVAC, walls, ceilings, and flooring. Justification: The City Hall Project requires the building to be vacated during the construction phase. The Bead Museum allows the City of Glendale to move 57 employees into a temporary space for the duration of the City Hall construction process. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $142,064 $178,361 $320,425 4060 – GENERAL GOVT. G. O. BONDS $311,175 $311,175 4610 – ARPA CAPITAL PROJECTS $91,000 $399,500 $490,500 40 GRPSTC Second Floor Renovation Project Number: CIPFC23037 Description: Demolition and Renovation of 1,650 sq. ft. of space on the GRPSTC 2nd Floor to accommodate the permanent move of 20 Building Inspectors from City Hall. Justification: The City Hall Project requires reconsideration of what services should be relocated in the City Hall Building. The relocation of 20 Building Inspectors puts them closer to the bulk of the City's growth and their work on the West Side of the City. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $26,096 $150,604 $176,700 4610 – ARPA CAPITAL PROJECTS $31,500 $4,000 $35,500 41 Media Center Renovation Project Number: CIPFC23038 Description: Renovation of 2,500 sq. ft. of space at the City of Glendale Media Center to accommodate the temporary relocation of the Executive and Elected officials (4th Floor). This renovation will include office space for 35 employees. Justification: The City Hall Project requires the building to be vacated during the construction phase. The Media Center allows the City of Glendale to move the 4th Floor functions to an executive suite office space that supports their front facing functions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $78,450 $337,000 $415,450 42 Sine Building 2nd Floor East Renovation Project Number: CIPFC23039 Description: Completion of renovation of 4,000 sq. ft. of space at the East end of the 2nd Floor of the Sine Building to accommodate the permanent housing of the City Attorney's Department. Justification: The City Hall Project requires reconsideration of what services should be relocated. The relocation of 11 employees allows for a continuum of service with the City Attorney's Prosecutor & Code Enforcement, who will be located in Sine Building East. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $24,575 $184,000 $208,575 43 Sine Building 2nd Floor West Renovation Project Number: CIPFC23040 Description: Renovation of 4,000 sq. ft. of space at the West end of the 2nd Floor of the Sine Building to accommodate the permanent housing of the Code Enforcement Department. This will include office space for 17 employees tied to the Code Enforcement functions. Justification: The City Hall Project requires reconsideration of what services should be relocated. The relocation of the 17 Code Enforcement Employees allows for a continuum of service with the City Attorney, who will be located in Sine Building 2nd Floor East. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $139,425 $50,000 $189,425 4060 – GENERAL GOVT. G. O. BONDS $726,000 $726,000 4610 – ARPA CAPITAL PROJECTS $29,586 $12,000 $41,586 44 Glendale Ops Campus Renovation Project Number: CIPFC23041 Description: This project is to renovate and demolish the existing buildings at the operations campus for adaptive re- use. Future phases from the current Master Plan such as paving, future fire resources, and carwash replacement are not included nor funded. Justification: Aging infrastructure, security, and operational efficiency concerns must be addressed in order to continue to provide effective service to the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030 – TRANS. SALES TAX CAPITAL $39,656 $574,287 $1,002,728 $1,616,671 4060 – GENERAL GOVT. G. O. BONDS $44,828 $649,194 $1,133,518 $1,827,540 6020 – WATER FUND $46,552 $674,162 $1,177,115 $1,897,829 6120 – SOLID WASTE FUND $441,380 $599,256 $1,046,324 $1,686,960 45 Council Chambers Project Number: CIPFC23043 Description: In addition to the exterior/envelope upgrades to City Hall and One-Stop-Shop, the Council Chambers exterior will also be upgraded (including roof replacement) to align with the new envelope of City Hall. Council Chambers interiors will not be part of the modernization project. Justification: The existing City Hall Campus was constructed in 1984. In order to better serve the community and organization, the City Council Chambers needs to updated to match the esthetics of the City Hall Building. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $500,000 $500,000 $2,100,000 $1,000,000 $4,100,O00 46 Building Maintenance Reserve Project Number: CIPFC70800 Description: This project supports repair of major building components and systems such as HVAC, plumbing, electrical, roofing, interiors, elevators, and other building systems that have failed. Justification: Repairing buildings will align resources with the City's strategic priorities including- reducing long term life cycle costs, protecting public health and safety, and improving service delivery to the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $139,734 $2,000,000 $2,500,000 $2,500,000 $2,500,000 $2,500,000 $12,500,000 $24,639,734 47 Camelback Ranch Maintenance Reserve Project Number: CIPFC70801 Description: This project funds the capital repair and or replacement of contractually required components and systems such as HVAC, plumbing, electrical, roofing, interiors, elevators, and other building systems. Glendale's Camelback Ranch is a premier public facility. Justification: Programmatic replacement of capital systems and components of the complex will reduce overall lifecycle costs while aligning resources with the City's strategic priorities and the Building Asset Philosophy. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $800,074 $1,673,504 $1,673,504 $1,673,504 $1,673,504 $1,673,504 $8,367,520 $17,535,114 48 Capital Repair – Arena Project Number: CIPPK70803 Description: This project funds the capital repair and or replacement of required components and systems such as HVAC, plumbing, electrical, roofing, interiors, elevators, and other building systems. Glendale’s Gila River Arena is a premier public facility. Justification: Programmatic replacement of capital systems and components of the complex will reduce overall lifecycle costs while aligning resources with the City's strategic priorities and the Building Asset Philosophy. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $153,845 $877,648 $1,391,121 $500,000 $500,000 $500,000 $2,500,000 $6,422,614 49 Amphitheater Renovations Project Number: CIPPK77516 Description: Renovations of the E Lowell Rogers Amphitheater at City Hall. Design and construction is slated for FY26. Construction includes renovation of basement of Council Chambers. O&M does not include personnel or maintenance of audio-visual equip. Justification: The Amphitheater does not adequately serve as a performance venue. Much of the equipment & systems are in poor condition & must be replaced. The public experience is poor & does not meet modern accessibility standards. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4080 – CULTURAL FACILITY G. O. BONDS $500,000 $1,000,000 $4,000,000 $5,000,000 $10,500,000 50 FY23-32 Library CIP Overview • Funded by Library G. O. Bonds (99.9%) and Library DIF (<1%) • Focus on: – Improving existing facilities • Follow industry standard replacement cycles – Replacing existing assets as needed • Added Heroes Park Library Community Room Expansion • Updated pricing to current construction estimates and projected inflation FY23-32 Library Projects 51 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPLB19045 VELMA TEAGUE LIBRARY RENOVATION 5,400,000 5,400,000 CIPLB19046 MAIN LIBRARY RENOVATION 1,308,017 5,285,190 6,944,793 13,538,000 CIPLB19066 FOOTHILLS LIBRARY RENOVATION 225,000 716,565 3,252,372 4,970,029 9,163,966 CIPLB22088 YUCCA DISTRICT MEETING SPACE STUDY 10,000 10,000 CIPLB23029 HEROES PARK LIBRARY COMMUNITY ROOM 948,649 751,351 1,700,000 TOTAL 235,000 2,256,666 751,351 6,001,755 10,197,165 4,970,029 5,400,000 29,811,966 FY23-32 Library by Funding Source 52 FUND FUND NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4100 LIBRARY G. O. BONDS 225,000 2,256,666 751,351 6,001,755 10,197,165 4,970,029 5,400,000 29,801,966 4284 2019 LIBRARY DIF 10,000 10,000 TOTAL 235,000 2,256,666 751,351 6,001,755 10,197,165 4,970,029 5,400,000 29,811,966 53 Velma Teague Library Renovation Project Number: CIPLB19045 Description: Library renovation of electrical, plumbing, interior, exterior, HVAC, roof gutters, and improve functionality. Facility conditional assessment and study will refine the project and prioritize needs. Justification: This library needs renovation to better service the needs of the community. It is anticipated that the assessment will indicate substantial building infrastructure needs. This project will help establish libraries of the future. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4100 – LIBRARY G. O. BONDS $5,400,000 $5,400,000 54 Main Library Renovation Project Number: CIPLB19046 Description: This project is to renew all building systems, including interior renewal and functional remodeling, roofing, HVAC, ADA, and plumbing. Equipment and technology updates are also included. Justification: The library was built in 1987. This project is necessary to extend the life of the structure, to improve library services, community experience, and the lives of the people we serve. This project will help establish libraries of the future. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4100 – LIBRARY G. O. BONDS $1,308,017 $5,285,190 $6,944,793 $13,538,000 55 Foothills Library Renovation Project Number: CIPLB19066 Description: Renovation and updating of Foothills Library to major building systems, modernization of the functions, technology, and equipment. Cost will be refined as assessment is conducted. Justification: The library was built in 1999. This project is necessary to extend the life of the structure, to improve library services, community experience, and the lives of the people we serve. This project will help establish libraries of the future. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4100 – LIBRARY G. O. BONDS $225,000 $716,565 $3,252,372 $4,970,029 $9,163,966 56 Yucca District Meeting Space Study Project Number: CIPLB22088 Description: Study to assess current meeting space in Yucca district, to determine if additional space is needed to meet community needs. Justification: Meeting space in Yucca district is limited. Study will determine if additional space needs to be added to Heroes Regional Park Library or other designated location. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4284 – 2019 LIBRARY DIF $10,000 $10,000 57 Heroes Park Library Community Room Project Number: CIPLB23029 Description: New community room expansion, with flexible seating that accommodates approximately 75 seats. The addition is planned to be on the north side of the existing 7,515 sq. ft. library, allowing for future expansion. Justification: Library was planned for expansion due to frequent use of limited meeting space and demand for larger groups. This project funds meeting room space per study. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4100 – LIBRARY G. O. BONDS $948,649 $751,351 $1,700,000 58 FY23-32 Parks CIP Overview • Funded by Parks G. O. Bonds (64%), Open Space/Trail G. O. Bonds (17%), ARPA (15%), General Fund (4%) DIF (1%) and Cultural Facility G. O. Bonds (>1%) • Focus on Improving Infrastructure of Existing Parks • Select New Improvements • Emphasis on Lighting and Irrigation Upgrades, and Replacement of Playground Equipment FY23-32 Parks Projects 59 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPPK19008 SAHUARO RANCH PARK IMPROVEMENTS 1,723,149 1,723,149 CIPPK19032 PARK GROUND AND IRRIGATION 125,693 125,693 CIPPK19033 PARK LIGHTING 63,470 63,470 CIPPK19034 PARK INFRASTRUCTURE IMPROVEMENTS 4,550,000 7,840,000 5,600,000 17,990,000 CIPPK19036 HEROES REGIONAL PARK LAKE 937,614 937,614 CIPPK19077 THUNDERBIRD CONSV. PARK IMPS 999,853 4,000,000 6,629,200 11,629,053 CIPPK21033 HEROES REGIONAL PARK BUILD OUT 425,580 46,400,000 46,825,580 CIPPK21038 COMMUNITY CENTER UPGRADES 3,341,425 3,341,425 CIPPK21039 FRAC UPGRADES 8,460 8,460 CIPPK21040 ADULT CENTER IMPROVEMENTS 33,852 33,852 CIPPK21041 ROSE LANE POOL IMPROVEMENTS 115,410 115,410 CIPPK21042 PARK RESTROOM REPLACEMENT 3,591 3,591 CIPPK21054 PLAYGROUND EQUIP. AT FOOTHILLS PARK 300,000 300,000 CIPPK22007 ROSE LANE PARK IMPROVEMENTS 933,140 924,570 1,857,710 CIPPK22008 BONSALL PARK IMPROVEMENTS 46,592 879,000 925,592 FY23-32 Parks Projects 60 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPPK22009 ACOMA PARK IMPROVEMENTS 28,761 139,900 168,661 CIPPK22010 MONDO PARK IMPROVEMENTS 118,081 15,400 133,481 CIPPK22011 MARY SILVA PARK IMPROVEMENTS 50,000 146,935 115,985 412,920 CIPPK22012 HIDDEN MEADOW PARK IMPROVEMENTS 150,000 141,070 291,070 CIPPK22013 HERITAGE PARK IMPROVEMENTS 150,000 10,000 14,920 174,920 CIPPK22014 HILLCREST PARK IMPROVEMENTS 150,000 92,210 242,210 CIPPK22015 NEW WORLD PARK IMPROVEMENTS 150,000 1,241,801 1,391,801 CIPPK22016 MISSION PARK IMPROVEMENTS 576,112 125,000 701,112 CIPPK22017 O'NEIL PARK IMPROVEMENTS 1,082,016 1,082,016 CIPPK22018 MONTARA PARK IMPROVEMENTS 150,000 299,750 449,750 CIPPK22019 CARMEL PARK IMPROVEMENTS 228,500 281,580 510,080 CIPPK22020 DELICAS PARK IMPROVEMENTS 339,820 20,000 359,820 CIPPK22021 LIONS PARK IMPROVEMENTS 125,000 46,710 171,710 CIPPK22022 COUNTRY GABLES PARK IMPROVEMENTS 150,000 62,328 212,328 CIPPK22023 SUNNYSIDE PARK IMPROVEMENTS 150,000 87,500 347,220 584,720 CIPPK22024 TARRINGTON RANCH PARK IMPROV. 40,000 238,230 278,230 FY23-32 Parks Projects 61 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPPK22025 FOOTHILLS PARK IMPROVEMENTS 841,645 841,645 CIPPK22026 NORTHERN HORIZON PARK IMPROV. 150,000 766,520 916,520 CIPPK22027 MYRTLE PARK IMPROVEMENTS 39,500 47,870 87,370 CIPPK22028 CLAVELITO PARK IMPROVEMENTS 125,000 144,260 269,260 CIPPK22029 BUTLER PARK IMPROVEMENTS 58,000 284,940 342,940 CIPPK22030 CHOLLA PARK IMPROVEMENTS 60,000 284,900 344,900 CIPPK22031 SIERRA VERDE PARK IMPROV. 139,200 252,660 391,860 CIPPK22032 SKUNK CREEK LINEAR TRAIL 1,000,000 1,000,000 CIPPK22033 GRAND CANAL LINEAR PARK IMPROV. 1,000,000 4,000,000 5,000,000 CIPPK22034 THUNDERBIRD PASEO IMPROV. 1,000,000 4,125,000 5,125,000 CIPPK22035 MID-CITY SPLASH PAD 930,090 930,090 CIPPK22036 NEW RIVER TRAIL IMPROVEMENTS 552,489 552,489 CIPPK22096 SAHUARO RANCH SPLASH PAD 1,500,000 1,500,000 CIPPK22097 SIERRA VERDE SPLASH PAD 1,500,000 1,500,000 CIPPK22098 SMALL SPLASH PAD A 500,000 500,000 CIPPK22099 SMALL SPLASH PAD B 500,000 500,000 FY23-32 Parks Projects 62 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPPK22100 SMALL SPLASH PAD C 500,000 500,000 CIPPK22101 HEROES REGIONAL PARK BALLFIELDS 1,676,400 5,800,000 7,476,400 CIPPK22102 HEROES REGIONAL PARK SPLASH PAD 500,000 500,000 CIPPK22103 SYCAMORE GROVE SPLASH PAD 200,000 200,000 CIPPK22104 75TH / CAMELBACK SPLASH PAD 100,000 100,000 CIPPK22111 BONSALL NORTH PARK IRRIGATION 697,000 697,000 CIPPK22112 SUNSET PALMS PARK IRRIGATION 697,000 697,000 CIPPK22113 HILLCREST PARK IRRIGATION 697,000 697,000 CIPPK22117 GLENDALE COMMUNITY CENTER FIBER 170,984 170,984 CIPPK22118 O'NEIL RECREATION CENTER FIBER 187,789 187,789 CIPPK22119 ROSE LANE RECREATION CENTER FIBER 355,806 355,806 CIPPK23004 PLAZA ROSA PARK IMPROVEMENTS 143,699 143,699 CIPPK23005 KINGS PARK IMPROVEMENTS 716,900 716,900 CIPPK23006 DESERT VALLEY PARK IMPROVEMENTS 887,400 887,400 CIPPK23007 DESERT ROSE PARK IMPROVEMENTS 150,000 856,700 1,006,700 CIPPK23024 SANDS PARK IMPROVEMENTS 256,420 145,000 401,420 CIPPK23025 PASEO RACQUET SPORTS 450,000 450,000 FY23-32 Parks Projects 63 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPPK23026 PASEO SPORTS COMPLEX 925,000 925,000 CIPPK23027 CHAPPARAL PARK IMPROVEMENTS 1,121,722 1,121,722 CIPPK23044 MURPHY PARK 250,000 250,000 1,000,000 3,000,000 4,500,000 CIPPK23059 BICENTENNIAL PARK PLAYGROUND 150,000 150,000 CIPPK23064 SAHUARO RANCH PARK LED LIGHTING 700,000 700,000 CIPPK23065 DESERT MIRAGE PARK IRRIGATION 458,211 458,211 CIPPK23066 DISCOVERY PARK IRRIGATION 339,210 339,210 CIPPK23067 NEW WORLD PARK IRRIGATION 697,000 697,000 CIPPK70546 SAHUARO RANCH PK MASTER PLAN 105,929 105,929 CIPPK73475 CITYWIDE PARK IMPROVEMENTS 92,124 92,124 CIPPK73576 FOOTHILLS PARK PICKLEBALL COURTS 3,631 3,631 TOTAL 20,992,844 18,074,026 11,870,375 12,336,133 12,621,150 8,204,699 53,029,200 137,128,427 FY23-32 Parks by Funding Source 64 FUND FUND NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 GENERAL FUND CIP 5,557,975 5,557,975 4050 PARKS G. O. BONDS 2,471,263 3,929,605 6,317,886 7,211,133 12,621,150 8,204,699 46,400,000 87,155,736 4080 CULTURAL FACILITY G. O. BONDS 105,929 105,929 4090 OPEN SPACE/TRAIL G. O. BONDS 999,853 5,000,000 5,000,000 5,125,000 6,629,200 22,754,053 4325 2014 PARKS & REC DIF 933,721 552,489 1,486,210 4365 2012 PARKS & REC DIF 92,124 92,124 4610 ARPA CAPITAL PROJECTS 10,831,979 9,144,421 19,976,400 TOTAL 20,992,844 18,074,026 11,870,375 12,336,133 12,621,150 8,204,699 53,029,200 137,128,427 65 Sahuaro Ranch Park Improvements Project Number: CIPPK19008 Description: Project for improvements at Sahuaro Ranch Park. Improvements will include new LED lighting, new air conditioning units for historical buildings, and the renovation of the grand ramada. Justification: Replacement and renovation of historic infrastructure to address priority items identified in the assessment recommendations. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $1,723,149 $1,723,149 66 Park Ground and Irrigation Project Number: CIPPK19032 Description: This is phase one of replacing aging irrigation in selected parks. Items could include controllers, valves, main line and lateral pipe, spray head, drip and rain/flow sensors. The system will be operated with Bluetooth and satellite based technology. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; “maintain and improve what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $125,693 $125,693 67 Park Lighting Project Number: CIPPK19033 Description: This is phase one of replacing aging lighting in selected parks. Items could include security, site parking, field lighting and electrical service section, panels, wiring and conduit. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; “maintain and improve what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $63,470 $63,470 68 Park Infrastructure Improvements Project Number: CIPPK19034 Description: This project addresses the needs in park infrastructure improvements by renovating up to two thirds of the parks not currently covered in the CIP. Justification: As improvements are made and tracked in assets management future lifecycle cost and replacement decisions can be made, funding in a future bond program would be needed for this. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $4,550,000 $7,840,000 $5,600,000 $17,990,000 69 Heroes Park Regional Lake Project Number: CIPPK19036 Description: This project is for the construction of an urban lake at Heroes Regional Park. The originally approved concept is for an urban lake sized to provide the necessary pumping and irrigation system needs for the proposed turf and landscaping throughout the park and provide storage capacity. The lake would be part of the Urban Fishing Program. An analysis of current lake requirements is underway to determine phasing the design and construction. Justification: This project is for the phased design and construction of the Heroes Regional Park Lake per the originally approved 2005 Design Concept Report. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $32,088 $32,088 4050 – PARKS G. O. BONDS $905,526 $905,526 70 Thunderbird Conservation Park Improvements Project Number: CIPPK19077 Description: This project addresses key items developed through public input for the 2011 Glendale Parks and Recreation Master Plan Update. This request is for replacement of aging infrastructure at Thunderbird Conservation Park including repair of existing trails. and replacement/addition of restrooms, ramadas, parking spaces, and roadways. Justification: This project meets important elements of the master plan including Care of Infrastructure. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4090 – OPEN SPACE/TRAIL G. O. BONDS $999,853 $4,000,000 $6,629,200 $11,629,053 71 Heroes Regional Park Buildout Project Number: CIPPK21033 Description: This project is for the build out of the remaining amenities at Heroes Regional Park per the previously approved design concept plan to include: recreation and aquatics center, lighted soccer and baseball/softball fields, turf and irrigation system, parking, walkways, fencing, security lighting and related park amenities. Justification: This project is for the completion of the improvements at Heroes Regional Park per the originally approved 2005 design Concept Report. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $425,580 $46,400,000 $46,825,580 72 Community Center Upgrades Project Number: CIPPK21038 Description: This project will provide repairs and replacement of critical components at the three Community Centers: Glendale, Rose Lane, and O’Neil. Justification: City Staff has worked to identify and prioritize specific improvements to these facilities. Project is funded through General Fund fund balance, per Council consensus. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $3,341,425 $3,341,425 73 Adult Center Improvements Project Number: CIPPK21040 Description: This project will rehabilitate the entryway of the Glendale Adult Center. Justification: City staff has worked to identify and prioritize specific improvements to these facilities. Project is funded through General Fund fund balance, per Council consensus. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $33,852 $33,852 74 Rose Lane Pool Improvements Project Number: CIPPK21041 Description: This project will re-plaster two swimming pools at Rose Lane, restore the water features, replace aged pool equipment. Justification: City staff has worked to identify and prioritize specific improvements to these facilities. Project is funded through General Fund fund balance, per Council consensus. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $115,410 $115,410 75 Rose Lane Park Improvements Project Number: CIPPK22007 Description: This project is for improvements at Rose Lane Park. The improvements will include improved irrigation, court resurfacing and a new play structure. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $933,140 $924,570 $1,857,710 76 Bonsall Park Improvements Project Number: CIPPK22008 Description: This project is for improvements at Bonsall Park. The improvements will include improved irrigation, court resurfacing and a new play structure. These improvements are designed to accommodate the increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $46,592 $879,000 $925,592 77 Acoma Park Improvements Project Number: CIPPK22009 Description: This project is for park improvements at Acoma Park. The improvements will include improved irrigation, court resurfacing and a new play structure. These improvements are designed to accommodate increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $28,761 $139,900 $168,661 78 Mondo Park Improvements Project Number: CIPPK22010 Description: This project is for improvements at Mondo Park. The improvements will include improved lighting and a new play structure. These improvements are designed to accommodate increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $118,081 $15,400 $133,481 79 Mary Silva Park Improvements Project Number: CIPPK22011 Description: This project is for improvements at Mondo Park. The improvements will include improved lighting and a new play structure. These improvements are designed to accommodate increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $146,935 $115,985 $262,920 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 80 Hidden Meadow Park Improvements Project Number: CIPPK22012 Description: This project is for improvements at Hidden Meadow Park. The improvements will include park lighting and a new play structure. These improvements are designed to accommodate the increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $141,170 $141,170 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 81 Heritage Park Improvements Project Number: CIPPK22013 Description: This project is for improvements at Heritage Park. The improvements will include court resurfacing and a new play structure. These improvements are designed to accommodate the increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $10,000 $14,920 $24,920 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 82 Hillcrest Park Improvements Project Number: CIPPK22014 Description: This project is for improvements at Hillcrest Park. The improvements will include park lighting and a new play structure. These improvements are designed to accommodate the increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $92,210 $92,210 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 83 New World Park Improvements Project Number: CIPPK22015 Description: This project is for improvements at New World Park. The improvements will include improved park lighting and a new play structure. These improvements are designed to accommodate the increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $1,241,801 $1,241,801 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 84 Mission Park Improvements Project Number: CIPPK22016 Description: Improvements at Mission Park. Improvements include park lighting, a new play structure, and a new irrigation system. Improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $576,112 $125,000 $701,112 85 O’Neil Park Improvements Project Number: CIPPK22017 Description: This project is for improvements at O'Neil Park. The improvements will include improved park lighting and court resurfacing. These improvements are designed to accommodate the increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $1,082,016 $1,082,016 86 Montara Park Improvements Project Number: CIPPK22018 Description: This project is for improvements at O'Neil Park. The improvements will include improved park lighting and court resurfacing. These improvements are designed to accommodate the increased use and demand at the park. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $299,750 $299,750 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 87 Carmel Park Improvements Project Number: CIPPK22019 Description: This project is for improvements at Carmel Park. The improvements will include enhanced lighting, a new irrigation system, resurfaces courts and a new play structure. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $78,500 $281,580 $360,080 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 88 Delicas Park Improvements Project Number: CIPPK22020 Description: This project is for improvements at Delicas Park. The improvements will include a new playground and shade structure. These improvements are designed to accommodate the increased use and demand. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; ""maintain and improve what we have"". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $189,820 $20,000 $209,820 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 89 Lions Park Improvements Project Number: CIPPK22021 Description: This project is for improvements at Lions Park. The improvements will include park lighting and a new play structure with shade. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $46,710 $46,710 4610 – ARPA CAPITAL PROJECTS $125,000 $125,000 90 Country Gables Park Improvements Project Number: CIPPK22022 Description: This project is for improvements at Country Gables Park. The improvements will include park lighting and a new play structure with shade. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $62,328 $62,328 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 91 Sunnyside Park Improvements Project Number: CIPPK22023 Description: This project is for improvements at Sunnyside Park. The improvements will include park lighting and a new playground with shade. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $87,500 $347,220 $434,720 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 92 Tarrington Ranch Park Improvements Project Number: CIPPK22024 Description: This project is for improvements at Tarrington Ranch Park. The improvements will include park lighting and a new playground with shade. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $40,000 $238,230 $278,230 93 Foothills Park Improvements Project Number: CIPPK22025 Description: This project is for improvements at Foothills Park. The improvements will include park lighting and a new playground with shade. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $861,645 $861,645 94 Northern Horizon Park Improvements Project Number: CIPPK22026 Description: This project is for improvements at Northern Horizon Park. The improvements will include park lighting, irrigation system improvements and a new playground with shade. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $766,520 $766,520 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 95 Myrtle Park Improvements Project Number: CIPPK22027 Description: This project is for improvements at Myrtle Park. The improvements will include new park lighting. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $39,500 $47,870 $87,370 96 Clavelito Park Improvements Project Number: CIPPK22028 Description: This project is for improvements at Clavelito Park. The improvements will include park lighting, irrigation system improvements and a new playground with shade. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $39,500 $144,260 $144,260 4610 – ARPA CAPITAL PROJECTS $125,000 $125,000 97 Butler Park Improvements Project Number: CIPPK22029 Description: This project is for improvements at Butler Park. The improvements will include park lighting and a new playground with shade structure. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $58,000 $284,940 $342,940 98 Cholla Park Improvements Project Number: CIPPK22030 Description: This project is for improvements at Cholla Park. The improvements will include park lighting and a new playground with shade structure. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $60,000 $284,900 $344,900 99 Sierra Verde Park Improvements Project Number: CIPPK22031 Description: This project is for improvements at Sierra Verde Park. The improvements will include park lighting, court resurfacing and a new playground with shade. These improvements are designed to accommodate the increased use and demand at the park. Justification: Replacement of aging infrastructure in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $139,200 $252,660 $391,860 100 Skunk Creek Linear Trail Project Number: CIPPK22032 Description: Redesign and installation of irrigation and landscaping along paved trail on the Skunk Creek Linear Trail. This 4 + mile trail system was installed in 2002 and is in disrepair. Justification: Maintaining what we have is a top priority in master plan survey of residents. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4090 – OPEN SPACE/TRAILS G. O. BONDS $1,000,000 $1,000,000 101 Grand Canal Linear Park Improvements Project Number: CIPPK22033 Description: This project is for improvements at Grand Canal Linear Park. The improvements will include new infrastructure and amenities, including irrigation, ramadas, fencing, splash pad updates, etc. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4090 – OPEN SPACE/TRAILS G. O. BONDS $1,000,000 $4,000,000 $5,000,000 102 Thunderbird Paseo Park Improvements Project Number: CIPPK22034 Description: This project is for improvements at Thunderbird Paseo Park. The improvements will include enhanced lighting, improved irrigation, court resurfacing and a new play structure. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4090 – OPEN SPACE/TRAILS G. O. BONDS $1,000,000 $4,125,000 $5,125,000 103 Mid-City Splash Pad Project Number: CIPPK22035 Description: This project is for the design and construction of a new splashpad at a Mid-City Park. Justification: This project addresses aging amenities and the need for new water features in parks as per the current Parks and Recreation Master Plan and what was most important to residents. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4325 – 2014 PARKS & REC DIF $930,090 $930,090 104 New River Trail Improvements Project Number: CIPPK22036 Description: This project is designed to provide a connection between New River Trail South and Heroes Regional Park. The improvements include a new concrete walkway, enhanced lighting, irrigation and plantings. Justification: This project provides an improved link between existing parks as per the current Parks and Recreation Master Plan and what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4325 – 2014 PARKS & REC DIF $552,489 $552,489 105 Sahuaro Ranch Splash Pad Project Number: CIPPK22096 Description: This project will add a new amenity to the central area of Sahuaro Ranch Park. The splash pad will expand community access to parks. Justification: This project meets the goal of the Parks and Recreation Master Plan to increase park amenities at existing park locations. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $1,500,000 $1,500,000 106 Sierra Verde Splash Pad Project Number: CIPPK22097 Description: This project will add a new amenity to Sierra Verde Park. The splash pad will expand community access to a splash pad north of Loop 101. Justification: This project meets the goal of the Parks and Recreation Master Plan to increase park amenities at existing park locations. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $1,500,000 $1,500,000 107 Small Splash Pad A Project Number: CIPPK22098 Description: This project will add a new smaller scale splash pad amenity to small or neighborhood park. The splash pad will expand community access to parks and final location will be determined by further Council input. Justification: This project meets the goal of the Parks and Recreation Master Plan to increase park amenities at existing park locations. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $500,000 $500,000 108 Small Splash Pad B Project Number: CIPPK22099 Description: This project will add a new smaller scale splash pad amenity to small or neighborhood park. The splash pad will expand community access to parks and final location will be determined by further Council input. Justification: This project meets the goal of the Parks and Recreation Master Plan to increase park amenities at existing park locations. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $500,000 $500,000 109 Small Splash Pad C Project Number: CIPPK22100 Description: This project will add a new smaller scale splash pad amenity to small or neighborhood park. The splash pad will expand community access to parks and final location will be determined by further Council input. Justification: This project meets the goal of the Parks and Recreation Master Plan to increase park amenities at existing park locations. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $500,000 $500,000 110 Heroes Regional Park Ballfields Project Number: CIPPK22101 Description: This project will further develop the next phase of development for Heroes Regional Park. An updated park master plan will determine design plans to identify amenities which may include ballfields and other park amenities. Justification: This project meets the goal of the Parks and Recreation Master Plan to increase park amenities at existing park locations and to further the long-planned development of Heroes Regional Park. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $1,676,400 $5,800,000 $7,476,400 111 Heroes Regional Park Splash Pad Project Number: CIPPK22102 Description: This project consists of retrofitting and replumbing the aging infrastructure of the existing splash pad in Heroes Regional Park. Justification: This project meets the goal of the Parks and Recreation Master Plan to improve infrastructure within existing parks. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $500,000 $500,000 112 Sycamore Grove Splash Pad Project Number: CIPPK22103 Description: This project consists of retrofitting and replumbing the aging infrastructure of the existing to bring it operational. Justification: This project meets the goal of the Parks and Recreation Master Plan to improve infrastructure within existing parks. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $500,000 $500,000 113 75th Ave / Camelback Splash Pad Project Number: CIPPK22104 Description: This project consists of retrofitting and replumbing the aging infrastructure of the existing to bring it operational. Justification: This project meets the goal of the Parks and Recreation Master Plan to improve infrastructure within existing parks. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $100,000 $100,000 114 Bonsall Park North Irrigation Project Number: CIPPK22111 Description: The project is to replace irrigation infrastructure, bringing the system up to standards. May include controllers, taps, meters, valves, lateral lines, and sprinkler heads. Justification: Replacement of aging infrastructure in parks in the ARPA guidelines and per the current Parks and Recreation Master Plan for what was most important to residents: “maintain and improve what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $697,000 $697,000 115 Sunset Palms Park Irrigation Project Number: CIPPK22112 Description: The project is to replace irrigation infrastructure, bringing the system up to standards. May include controllers, taps, meters, valves, lateral lines, and sprinkler heads. Justification: Replacement of aging infrastructure in parks in the ARPA guidelines and per the current Parks and Recreation Master Plan for what was most important to residents: “maintain and improve what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $697,000 $697,000 116 Hillcrest Park Irrigation Project Number: CIPPK22113 Description: The project is to replace irrigation infrastructure, bringing the system up to standards. May include controllers, taps, meters, valves, lateral lines, and sprinkler heads. Justification: Replacement of aging infrastructure in parks in the ARPA guidelines and per the current Parks and Recreation Master Plan for what was most important to residents: “maintain and improve what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $697,000 $697,000 117 O’Neil Recreation Center Fiber Project Number: CIPPK22118 Description: The project brings fiber connectivity to the Community Centers (Rose Lane, Glendale Community Center, O’Neil) for tie into the city network for staff and improved connectivity for participants thru Wi-Fi. Justification: This project meets the goal of connectivity for impacted communities in the ARPA guidelines. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $187,789 $187,789 118 Rose Lane Recreation Center Fiber Project Number: CIPPK22119 Description: The project brings fiber connectivity to the Community Centers (Rose Lane, Glendale Community Center, O’Neil) for tie into the city network for staff and improved connectivity for participants thru Wi-Fi. Justification: This project meets the goal of connectivity for impacted communities in the ARPA guidelines. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $355,806 $355,806 119 Plaza Rosa Park Improvements Project Number: CIPPK23004 Description: This project is for park improvements for Plaza Rosa Park. The improvements will include a more efficient irrigation system, new park amenities and a new play structure. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and focuses on what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $143,699 $143,699 120 Kings Park Improvements Project Number: CIPPK23005 Description: This project is for park improvements at Kings Park. The improvements will include a more efficient irrigation system, lighting, a new play structure and new park amenities. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and focuses on what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $716,900 $716,900 121 Desert Valley Park Improvements Project Number: CIPPK23006 Description: This project is for park improvements at Desert Valley Park. The improvements will include a more efficient irrigation system, lighting, a new play structure, amenities and parking lot resurfacing. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and focuses on what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $887,400 $887,400 122 Desert Rose Park Improvements Project Number: CIPPK23007 Description: This project is for park improvements at Desert Rose Park. The improvements will include a more efficient irrigation system, lights, new play structures, sport court resurfacing and park amenities. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan and focuses on what was most important to residents; "maintain and improve what we have". FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $856,700 $856,700 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 123 Sands Park Improvements Project Number: CIPPK23024 Description: The project updates the security lights in the park to LED fixtures and replaces parks benches, tables and drinking fountains. Justification: Replacement of aging infrastructure per the approved Master Plan and what was most important to residents; “maintain what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $256,420 $145,000 $401,420 124 Paseo Racquet Sports Project Number: CIPPK23025 Description: The project updates the tennis court lights to LED fixtures. Justification: Replacement of aging infrastructure per the approved Master Plan and what was most important to residents; “maintain what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $450,000 $450,000 125 Paseo Sports Complex Project Number: CIPPK23026 Description: The project updates the sports complex field lights with LED fixtures and replaces backstops for improved safety. Justification: Replacement of aging infrastructure per the approved Master Plan and what was most important to residents; “maintain what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $925,000 $925,000 126 Chapparal Park Improvements Project Number: CIPPK23027 Description: The project improves the irrigation, updates the light fixtures with LED, resurfaces courts and relaces tables, benches and drinking fountains. Justification: Replacement of aging infrastructure per the approved Master Plan and what was most important to residents; “maintain what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $1,121,722 $1,121,722 127 Murphy Park Project Number: CIPPK23044 Description: Recognized as a great public space in downtown Glendale, modernization improvements will focus on a wholistic approach for a more integrated open space with the amphitheater, library, and City Hall facilities. This includes examining pedestrian corridors for better site circulation, arrival points, zones for various activities, wayfinding, hardscape design, and enhancing tree canopies, irrigation and drainage throughout the park. Justification: The existing City Hall Campus was constructed in 1984. In order to become a focal point of the downtown, it is important to modernize the park to make it more pedestrian friendly. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4050 – PARKS G. O. BONDS $500,000 $1,000,000 $3,000,000 $4,500,000 128 Bicentennial Park Playground Project Number: CIPPK23059 Description: Replace (2) playgrounds Justification: Replacement of aging infrastructure in parks meets the goal of the Parks and Recreation Master Plan to improve existing parks. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $150,000 $150,000 129 Sahuaro Ranch Park LED Lighting Project Number: CIPPK23064 Description: This project completes the installation of energy saving LED fixtures in the picnic area of the park. Justification: This project meets the goal of energy conservation in the ARPA guidelines. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $700,000 $700,000 130 Desert Mirage Park Irrigation Project Number: CIPPK23065 Description: The project is to replace irrigation infrastructure, bringing the system up to standards. May include controllers, taps, meters, valves, lateral lines, and sprinkler heads. Justification: Replacement of aging infrastructure in parks in the ARPA guidelines and per the current Parks and Recreation Master Plan for what was most important to residents: “maintain and improve what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $458,211 $458,211 131 Discovery Park Irrigation Project Number: CIPPK23066 Description: The project is to replace irrigation infrastructure, bringing the system up to standards. May include controllers, taps, meters, valves, lateral lines, and sprinkler heads. Justification: Replacement of aging infrastructure in parks in the ARPA guidelines and per the current Parks and Recreation Master Plan for what was most important to residents: “maintain and improve what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $339,210 $339,210 132 New World Park Irrigation Project Number: CIPPK23067 Description: The project is to replace irrigation infrastructure, bringing the system up to standards. May include controllers, taps, meters, valves, lateral lines, and sprinkler heads. Justification: Replacement of aging infrastructure in parks in the ARPA guidelines and per the current Parks and Recreation Master Plan for what was most important to residents: “maintain and improve what we have”. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4610 – ARPA CAPITAL PROJECTS $697,000 $697,000 133 Sahuaro Ranch Park Master Plan Project Number: CIPPK70546 Description: Improvements will include a drainage and grading study around the historical buildings, updating the building assessment and providing recommendations for mitigation. Justification: This project will continue the protection and restoration of this site which is on the National Registry of Historic Places. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4080 – CULTURAL FACILITY G. O. BONDS $105,929 $105,929 134 City-Wide Park Improvements Project Number: CIPPK73475 Description: This project funding source is Development Impact Fees (DIF) which are designed to cover a city’s increased costs for providing new or expanded infrastructure. The project would include the construction of additional amenities at DIF eligible parks. This project meets the 2011 Parks and Recreation Master Plan's primary action plan goals of "Develop and improve shade structures and amenities in parks" and "Revitalize conditions of neighborhood parks". Justification: Construction of addition amenities due to increased demand and growth and as recommended in the current Parks and Recreation master plan. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4365 – 2012 DIF PARKS & REC $92,124 $92,124 135 Foothills Park Pickleball Courts Project Number: CIPPK73576 Description: This project is for the construction of new pickleball courts at Foothills Park to accommodate increased interest and demand in the community. Justification: This project addresses aging amenities in parks as per the current Parks and Recreation Master Plan key strategy of “Maintain and enhance park and recreation facilities and programs to promote community interaction, healthy lifestyles and safety.” FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4325 – 2014 DIF PARKS & REC $3,631 $3,631 136 FY23-32 Public Safety CIP Overview • Funded by Public Safety G. O. Bonds (63%), General Fund (20%), Fire DIF (14%) and Police DIF (3%) • Focus on: – Improving existing facilities • Follow industry standard replacement cycles • Health, safety and functional improvements – Replacing existing assets as needed • Added Drone Facility Project and Parking Lot at Glendale Regional Public Safety Training Facility (GRPSTC) • Updated pricing to current construction estimates and projected inflation FY23-32 Public Safety Projects 137 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPFC21053 CITY COURT RENOVATIONS 2,755,532 2,755,532 CIPPS19029 FIRE STATION #153 REPLACEMENT 470,000 3,309,151 5,390,849 9,170,000 CIPPS19030 NEW POLICE EVIDENCE STORAGE 101,377 5,695,615 4,696,385 10,000,000 20,493,377 CIPPS19041 MAIN PUBLIC SAFETY BLDG REMODEL 2,000,000 2,500,000 2,500,000 3,500,000 10,500,000 CIPPS19042 FOOTHILLS POLICE STATION RENOVATION 541,685 500,000 1,306,043 2,340,479 2,340,479 7,028,686 CIPPS19043 GATEWAY POLICE STATION RENOVATION 618,910 2,201,073 8,348,927 11,168,910 CIPPS19044 FIRE STATION #154 RENOVATION 1,108,793 5,667,207 6,776,000 CIPPS19049 FIRE STATION - WESTERN AREA 20,518,889 20,518,889 CIPPS19050 FIRE STATION #155 RENOVATION 239,936 3,019,982 3,019,982 6,279,900 CIPPS19051 FIRE STATION #156 RENOVATION 254,411 2,921,839 3,176,250 CIPPS19052 FIRE STATION #157 RENOVATION 223,780 3,194,470 3,418,250 CIPPS19053 POLICE STATION -WEST AREA 4,529,000 4,529,000 CIPPS20033 PUBLIC SAFETY BUILDING REMODELS 50,052 50,052 FY23-32 Public Safety Projects 138 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPPS21055 FIRE STATION 156 ENHANCEMENTS 36,497 36,497 CIPPS22037 UNMANNED AERIAL VEHICLES 91,859 91,859 CIPPS22080 PUBLIC SAFETY HVAC REPLACEMENTS 6,405 6,405 CIPPS22083 FS158 FIRE SYSTEM REPLACEMENT 25,000 25,000 CIPPS22085 PUBLIC SAFETY ROOF REPAIR/REPLACE 348,240 348,240 CIPPS22094 GRPSTC RETAINING WALL/FIRE TOWER 30,644 574,000 604,644 CIPPS23002 LP15 HEART MONITOR REPLACEMENT 2,232,682 2,232,682 CIPPS23003 FIRE RADIO REPLACEMENT 2,629,100 2,629,100 CIPPS23013 DRUG BOX REFRIGERATOR REPLACE. 330,547 330,547 CIPPS23030 GRPSTC PARKING LOT 706,800 706,800 CIPPS23032 DRONE FACILITY 1,048,000 1,048,000 CIPPS23042 COURT RENOVATION PHASE 2 10,471,000 10,471,000 CIPPS70814 FIRE APPARATUS REPLACEMENT 474,944 4,374,039 2,294,398 2,316,880 2,386,386 1,616,688 10,755,056 24,218,391 TOTAL 5,551,145 21,167,252 15,723,107 20,724,023 9,466,822 15,823,841 60,157,821 148,614,011 FY23-32 Public Safety by Funding Source 139 FUND FUND NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 GENERAL FUND CIP 511,441 7,333,686 4,527,080 2,316,880 2,386,386 1,616,688 10,755,056 29,447,217 2200 TRAINING FACILITY REVENUE 30,644 574,000 604,644 4040 PUBLIC SAFETY G. O. BONDS 4,917,201 13,259,566 11,196,027 18,407,143 7,080,436 14,207,153 24,354,876 93,422,402 4173 2019 FIRE DIF 20,518,889 20,518,889 4191 2012 POLICE DIF 91,859 91,859 4223 2019 POLICE DIF 4,529,000 4,529,000 TOTAL 5,551,145 21,167,252 15,723,107 20,724,023 9,466,822 15,823,841 60,157,821 148,614,011 140 Fire Station #153 Replacement Project Number: CIPPS19029 Description: Total replacement of the current 7,400 gross sq. ft. (2-bay)fire station with a new approx. 13,300 gross sq.ft. (4 bay) facility. The project includes the demolition of a retired adjacent community center, approx. 5,000 gross sq.ft. Justification: The station was constructed in 1974 and components are beyond their useful life, and do not support additional apparatus or space for decontamination. Preventative measures should be taken to mitigate carcinogen exposure for firefighters. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G.O. BONDS $470,000 $3,309,151 $5,390,849 $9,170,000 141 Police Evidence Storage Facility Project Number: CIPPS19030 Description: New warehouse type facility for police evidence, property storage, and management. Located on 5 acres (formerly Lazy J Trailer Park). Estimate includes programming, design, construction for evidence storage facility. Added feasibility study to determine scope of future forensic lab in FY23 and placeholder for forensic lab construction adjacent to Property/Evidence facility in FY25. Justification: Current off-site storage facility (spring city) is being decommissioned. Remaining on site storage at Police station is at capacity, no growth. Co-locating forensic evidentiary processing with the storage of the evidence greatly reduces the risk of breaching Chain of Custody and is considered a best practice. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G.O. BONDS $101,377 $5,695,615 $4,696,385 $10,000,000 $20,493,377 142 Main Public Safety Building Remodel Project Number: CIPPS19041 Description: This project is for design and construction of a complete renovation of the main public safety building to include infrastructure needs as well as functionality. Infrastructure needs include HVAC, roof, plumbing, and electrical. Justification: Components of the building have exceeded their useful life. This location requires significant infrastructure and functionality modernization to meet the business needs of the department. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G.O. BONDS $1,000,000 $2,500,000 $2,500,000 $3,500,000 $10,500,000 143 Foothills Police Station Renovation Project Number: CIPPS19042 Description: This project is for design and construction of a complete renovation of the Foothills police substation to include infrastructure needs as well as functionality. Infrastructure needs include roof, exterior finishes, plumbing fixtures and parking. Justification: The Foothills police substation requires significant infrastructure and functionality modernization to meet the business needs of the police department. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G.O. BONDS $541,685 $500,000 $ 1,306,043 $2,340,479 $2,340,479 $7.028.686 144 Gateway Police Station Renovation Project Number: CIPPS19043 Description: This project is for design and construction of a complete renovation of the Gateway police substation to include infrastructure needs as well as functionality. Infrastructure needs identified in the building assessment include roof, and parking. Justification: The Gateway substation requires significant infrastructure and modernization to meet the business needs of the police department including additional space for parking to continue meeting the needs of the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G.O. BONDS $618,900 $2,201,073 $8,348,927 $11,168,910 145 Fire Station #154 Renovation Project Number: CIPPS19044 Description: Project will remodel FS 154 (43rd Ave & Peoria) as infrastructure components have reached the end of their useful life. Renovation will include new areas to protect firefighters' health and safety as well as functional improvements. Justification: The station was constructed in 1982 and components are beyond their useful life. The station house, drives, and equipment bays require replacement. Preventative measures should be taken to mitigate carcinogen exposure for firefighters. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G.O. BONDS $1,108,793 $5,667,207 $6,776,000 146 Fire Station – Western Area Project Number: CIPPS19049 Description: This project is for the design and construction of a new, 15,000 square feet, four bay fire station including furniture, fixtures and equipment, to support 18 personnel and one engine. Justification: Future growth in the area is projected to require an additional station to serve the needs of the community. The station will include space for future expansion as growth demands. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4173 – 2019 DIF FIRE $20,518,889 $20,518,889 147 Fire Station #155 Renovation Project Number: CIPPS19050 Description: Project will remodel FS 155 (62nd Ave & Union Hills) as infrastructure components have reached the end of their useful life. Renovation will include new areas to protect firefighters’ health and safety as well as functional improvements. Justification: The station was constructed in 1988 and components are beyond their useful life. The station house, drives, and equipment bays require replacement. Preventative measures should be taken to mitigate carcinogen exposure for firefighters. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G.O. BONDS $239,936 $3,019,982 $3,019,982 $6,279,900 148 Fire Station #156 Renovation Project Number: CIPPS19051 Description: Project will remodel FS 156 (68th Ave & Deer Valley) as infrastructure components have reached the end of their useful life. Renovation will include new areas to protect firefighters’ health and safety as well as functional improvements. Justification: The station was constructed in 1998 and components are beyond their useful life. The station house, drives, and equipment bays require replacement. Preventative measures should be taken to mitigate carcinogen exposure for firefighters. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G.O. BONDS $254,511 $2,921,839 $3,176,250 149 Fire Station #157 Renovation Project Number: CIPPS19052 Description: Project will remodel FS 157 (59th Ave and Brown) as infrastructure components have reached the end of their useful life. Renovation will include new areas to protect firefighters' health and safety as well as functional improvements. Justification: The station was constructed in 1997 and components are beyond their useful life. The station house, drives, and equipment bays require replacement. Preventative measures should be taken to mitigate carcinogen exposure for firefighters. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G.O. BONDS $223,780 $3,194,470 $3,418,250 150 Police Station – West Area Project Number: CIPPS19053 Description: This project is for design & construction of a 4,000 sq. ft police substation in conjunction with the proposed west area fire station. The facility will include future expansion as growth demands. Estimates include furniture, fixtures, and equipment. Justification: Future growth in the area is projected to require an additional station to serve the needs of the community. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4223 – 2019 DIF POLICE $4,529,000 $4,529,000 151 Public Safety Building Remodels Project Number: CIPPS20033 Description: The $800,000 in FY20 is for design of 2nd floor GRPSTC for Fire Admin, and design of Sine for Prosecutor, as well as construction of 2nd floor GRPSTC. Projects in FY21($7,532,000) include the remodel of Sine (up to $1.25m); Court imminent needs (up to $4m); and priority 2 and 3 deficiencies identified as part of Public Safety Buildings assessments. Planned projects include: exhaust venting/removal (all Fire Stations), parking assessments (Foothills, Gateway, FS 157), roof (Gateway), HVAC (Foothills), parking lot subsidence (FS 152), and generator replacement (FS 154). The exact list will depend on individual items costs. Justification: Many components are at the end of their useful life and require work or replacement in order to provide useable buildings. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G. O. BONDS $50,052 $50,052 152 City Court Renovations Project Number: CIPFC21053 Description: This project will renovate the existing city court which was built in 1991 and was last remodeled in 2003. Justification: The existing facility does not meet the courts operational needs in regards to safety, security, and storage. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G. O. BONDS $2,755,532 $2,755,532 153 Fire Station #156 Enhancements Project Number: CIPPS21055 Description: Painting of the fire station and adding additional trees and irrigation. Justification: This project will enhance the overall aesthetics of the fire station by painting the exterior and adding large trees to help disguise the existing monopole. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CIP $36,497 $36,497 154 Unmanned Aerial Vehicles Project Number: CIPPS22037 Description: This project is two unmanned aerial vehicles (drones), equipment and software. Drones can be remotely deployed and provide officers with real time information while increasing safety and efficiency. Justification: Drones are used to prevent dangerous situations for officers and bystanders. They can be used at accident scenes, to assess environmental issues, and follow fleeing suspects, reducing vehicle pursuits. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4191 – 2012 DIF POLICE $91,859 $91,859 155 Public Safety HVAC Replacements Project Number: CIPPS22080 Description: This project is to replace the HVAC systems at Fire Station 151, 159, and the Advocacy Center. Justification: The HVAC systems at these locations require replacement. Replacement is a proactive approach to maintaining the continuity of service to mission critical facilities. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G. O. BONDS $6,405 $6,405 156 FS158 Fire System Replacement Project Number: CIPPS22083 Description: This project is to replace the fire alarm system at Fire Station 158. Justification: The fire alarm system at Fire Station 158 needs replacement. The system is unreliable, difficult to service, and is a requirement for occupancy of the building. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G. O. BONDS $25,000 $25,000 157 Public Safety Roof Repair/Replacement Project Number: CIPPS22085 Description: This project is to replace roof at various public safety locations including- Fire Support, and GRPSTC Fire Station and Shooting Range. Justification: These roofs at mission critical locations need replacement to avoid structural damage. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G. O. BONDS $348,240 $348,240 158 GRPSTC Retaining Wall/Fire Tower Project Number: CIPPS22094 Description: This project it to perform a structural evaluation of the adjacent training wall, site and building at the GRPSTC Fire Training Building and any future construction to remediate the issues causing damage. Justification: The retention wall on the east and west side of the training facility are showing signs of cracking with water leakage, thus the commercial door is no longer operational and might create a safety issue. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 2200 – TRAINING FACILITY REVENUE $30,644 $574,000 $604,644 159 LP15 HEART MONITOR REPLACEMENT Project Number: CIPPS23002 Description: Purchase of 37 cardiac monitors. The life span is difficult to gauge as wear and tear is a factor that plays into how long these units last. Justification: These monitors are used multiple times daily. Emergency medical incidents account for over 80% of all calls for service. New technology also plays a part in how long we can continue to use older equipment. Currently, the department’s heart monitors are adequate through FY 2024, at which time they are expected to reach the end of their useful life. Heart monitors are considered a capital expenditure due to the type of equipment requiring to be updated all at the same time; which cannot be phased in when replaced. Personnel must all be able to train and work on the same type, make and model of equipment. Current annual maintenance contract for 36 monitors is $46,295.13. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 - GENERAL FUND CIP $2,232,682 $2,232,682 160 Fire Radio Replacement Project Number: CIPPS23003 Description: Replacement of all handheld (230) and apparatus-mounted (55) radios. To replace our radios, we need to include several accessories that go with the equipment - vehicle and bank chargers, extra batteries, shoulder microphones, antennas, holsters/slings, etc. Justification: Per Motorola, field support of our existing mobile (apparatus-mounted) radios will end September 2022 and our portable (handheld) radios in December 2023. We will be able to use the radios past those dates, but parts and replacements will not be available. As of December 2020, Motorola has announced they will no longer certify our portable radios as intrinsically safe and will stop making replacement batteries for our current model. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 - GENERAL FUND CIP $2,629,100 $2,629,100 161 Drug Box Refrigerator Replacement Project Number: CIPPS23013 Description: Purchase 31 new climate controlled narcotics storage units with built-in Comp X Elock 300 series to replace current units and locks on apparatus and vehicles and also provide a reserve of 2. Cost to purchase 31 units with built-in Elocks is $330,546.80. Each unit has a cost breakdown as follows: unit with Elock 300 series locks = $8,100; 5-year extended warranty = $1,800; Shipping = $50; Tax @ 8.8%. Justification: The current units are old and are at their end of life capabilities. The replacement cost per unit, including upgraded locks, 5- year warranty and shipping charges is just under $10,000 before tax. The elock 150 series is currently not working due to an overload of PINs. Currently we have people who are unable to access the drug box using their own PIN. New 300 series eLocks can be updated through a network connection eliminating the need to physically plug into each lock to update PINs. Current 150 series ELocks hold a maximum of 250 PINs. 300 series ELock can hold up to 3000 PINs. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 - GENERAL FUND CIP $330,547 $330,547 162 GRPSTC Parking Lot Project Number: CIPPS23030 Description: Project will create additional parking area west of the main building at GRPSTC. The proposed new parking area provides approximately 50 secured parking spaces. Justification: Current parking lot lacks appropriate parking spaces to accommodate staff. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G. O. BONDS $706,800 $706,800 163 Drone Facility Project Number: CIPPS23032 Description: This project is for design and construction of a drone facility, which includes HVAC, roof, plumbing and electrical. This is a smaller facility that will function as the pilot house for the drone operator and will be used as storage for the equipment. Justification: This location requires significant infrastructure and functionality design to meet the business needs of the department. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G. O. BONDS $1,048,000 $1,048,000 164 Court Renovation Phase 2 Project Number: CIPPS23042 Description: Recommended deferred maintenance of building systems and court security upgrades not included in Phase 1 renovation in CIPFC21053. Items include: update power distribution, ergonomic seating, HVAC cleaning, Kevlar at court benches, ballistic glass, intrusion security, visual evidence displays/controls at courtrooms, security bollards, back of house court expansion, and restroom addition. Justification: Facility is 30 years old plus with minimal upgrades. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4040 – PUBLIC SAFETY G. O. BONDS $10,471,000 $10,471,000 165 Fire Apparatus Replacement Project Number: CIPPS70814 Description: The project provides for the replacement of large GFD vehicles to ensure GFD may provide essential services. The plan is to replace engines & ladder tenders (LTs) every 7 yrs or 100K miles & ladders every 10 yrs or 100K miles. Quotes are updated. Justification: Programmatic replacement of vehicles will reduce overall lifecycle costs, protect public health and safety while aligning resources with the City's strategic priorities. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 – GENERAL FUND CAPITAL $474,944 $4,374,039 $2,294,398 $2,316,880 $2,386,386 $1,616,688 $10,755,056 $24,218,391 FY23-32 Streets CIP Overview 166 • Funded by Transportation Sales Tax (51%), Streets G.O. Bonds (28%), HURF (17%), General (3%), DIF (<1%), and Grants (<1%) • Focus on street pavement – Pavement Management – Arterial Reconstruction Program (G.O. Bonds) • Individual projects in years 1-5 of the proposed CIP • Street Reconstruction Program in years 6-10 of the proposed CIP – Arterial Street Reconstruction (Transportation Sales Tax) – Pavement Cut Repairs – Scallop Street Program FY23-32 Streets CIP Overview 167 • Safety projects – Flashing Yellow Arrow Phase 5 – 53rd Ave/Camelback Rd HAWK – 58th Ave/Bethany Home Rd HAWK – Olive Ave from 59th Ave to 67th Ave Street Lights – Northern Parkway Cable Barrier 2 – Guardrail Update – Transportation Safety Program – Speed Feedback Signs (School Zones) FY23-32 Streets CIP Overview 168 • Intersection Signalization/Improvement – 57th Ave/Greenway – 59th Ave/Northern Ave – 61st Ave/Olive Ave – Sarival Ave/Bethany Home Rd – Sarival Ave/Glendale Ave • Active Transportation (Bicycle/Pedestrian) – Central Core Sidewalk Gaps – 67th Ave Bike Lanes – Maryland Active Transportation Improvements – Missouri Active Transportation Improvements – Infill Sidewalk – Bike Projects (Match) FY23-32 Streets Projects 169 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPST19006 PAVEMENT MANAGEMENT 73,950 13,134,250 13,396,935 13,664,874 13,938,172 14,216,935 75,465,210 143,890,326 CIPST19010 BALLPARK BOULEVARD 1,256,917 1,256,917 CIPST19048 CAPITAL BRIDGE REPAIR PROGRAM 95,374 300,000 270,000 275,400 280,907 286,526 1,520,915 3,029,122 CIPST20012 FLASHING YELLOW ARROWS 465,794 465,794 CIPST20013 VEHICLE REPLACEMENT 696,264 520,000 540,800 562,432 584,930 608,326 3,426,688 6,939,440 CIPST20014 ST RECON BETHANY HM - 43RD-51ST 114,736 3,229,669 3,344,405 CIPST20016 ST RECON GLENDALE -101-EL MIRAGE 1,396,374 1,396,374 CIPST20021 ST RECON CAMELBACK - 83RD-91ST 294,268 294,268 CIPST20022 BIKE PROJECTS (MATCH) 170,769 143,208 146,072 148,994 790,876 1,399,919 CIPST21014 75TH AVENUE ASPERA IMPROVE. 14,930 14,930 CIPST21015 CENTRAL CORE SIDEWALK GAPS 359,720 226,520 586,240 CIPST21016 67TH AVENUE BIKE LANES 728,119 504,213 1,232,332 CIPST21017 STREET RECON BELL RD - 51ST-59TH 129,941 129,941 CIPST21018 ST RECON GLENDALE – 101-91ST 2,656,252 347,782 3,004,034 CIPST21044 ST RECON CACTUS - 51ST-59TH 1,288,054 1,288,054 FY23-32 Streets Projects 170 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPST21051 ST RECON 75TH-GLENDALE TO NORTHERN 7,370 7,370 CIPST21052 ST RECON 83RD-GLENDALE TO NORTHERN 163,233 163,233 CIPST22043 ST RECON 67TH - GREENWAY TO BELL 3,702 3,702 CIPST22044 ST RECON 67TH DEER VLY-PINNACLE PK 3,893,399 3,893,399 CIPST22046 ST RECON 83RD - GLENDALE TO BHR 111,395 3,901,034 4,012,429 CIPST22047 ST RECON GLENDALE - 43RD TO 51ST 118,179 118,179 CIPST22049 ST RECON BETHANY HM - 59TH TO 67TH 3,787,413 3,787,413 CIPST22050 ST RECON BETHANY HM - 67TH TO 75TH 3,787,413 3,787,413 CIPST22051 ST RECON CAMELBACK - 59TH TO 67TH 108,150 3,787,413 3,895,563 CIPST22052 ST RECON CAMELBACK - 67TH TO 75TH 3,677,100 3,677,100 CIPST22053 ST RECON CAMELBACK - 75TH TO 83RD 3,677,100 3,677,100 CIPST22054 ST RECON 67TH - PEORIA TO OLIVE 3,901,034 3,901,034 CIPST22058 ST RECON NORTHERN – 43RD TO 51ST 118,179 118,179 CIPST22060 ST RECON BELL RD - 59TH TO 67TH 111,395 3,901,034 4,012,429 CIPST22062 PAVEMENT CUT REPAIR 96,238 106,999 109,140 111,323 113,549 115,820 614,787 1,267,856 CIPST22063 PEDESTRIAN LED CONVERSION 2,000,000 2,000,000 FY23-32 Streets Projects 171 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPST22064 TRANSPORTATION SAFETY PROGRAM 385,734 480,000 432,001 440,640 449,452 458,442 2,433,465 5,079,734 CIPST22065 SCALLOP STREET PROGRAM 4,000,000 4,000,000 1,000,000 9,000,000 CIPST22067 57TH AND GREENWAY INTERSECT IMPROV. 200,000 200,000 CIPST22068 59TH AND NORTHERN INTERSECT IMPROV. 43,185 1,124,658 1,167,843 CIPST23014 OLIVE AVE 59-67 STREET LIGHTS 53,950 315,433 369,383 CIPST23015 61ST/OLIVE TRAFFIC SIGNAL UPGRADE 50,423 211,371 261,794 CIPST23016 53RD/CAMELBACK NEW HAWK 112,050 390,167 502,217 CIPST23017 NORTHERN PARKWAY CABLE BARRIER 2 155,625 1,042,750 1,198,375 CIPST23018 TMC UPGRADE 228,692 2,013,998 2,242,690 CIPST23019 MARYLAND ACTIVE TRANSPORTATION IMPR 15,942 95,155 111,097 CIPST23020 MISSOURI ACTIVE TRANSPORTATION IMPR 22,487 123,278 145,765 CIPST23021 ST RECON GLENDALE EL MIRAGE-LITCHFI 229,473 8,036,134 8,265,607 CIPST23047 SARIVAL AVENUE / BETHANY HOME ROAD 124,560 967,896 1,092,456 CIPST23048 SARIVAL AVENUE/GLENDALE AVENUE 124,560 967,896 1,092,456 CIPST23049 INFILL STREETLIGHTS 168,156 493,627 503,499 513,569 1,678,851 CIPST23050 58TH AVENUE/BETHANY HOME ROAD 89,683 679,643 769,326 CIPST23051 EXTEND FIBER OPTIC NETWORK 249,120 645,264 658,169 671,332 2,223,885 FY23-32 Streets Projects 172 PROJECT # PROJECT NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL CIPST23052 SPEED FEEDBACK SIGNS 90,000 81,000 82,620 84,273 85,958 456,275 880,126 CIPST23053 INFILL SIDEWALK 180,000 162,000 165,241 168,544 171,916 912,551 1,760,252 CIPST23054 GUARDRAIL UPDATE 120,000 108,001 110,160 112,363 114,611 608,367 1,173,502 CIPST23055 ARTERIAL PAVEMENT TREATMENT 1,605,001 1,605,001 CIPST23056 ARTERIAL SREET RECONSTRUCTION 8,841,361 3,706,776 12,548,137 CIPST23057 FLASHING YELLOW ARROWS PHASE 5 104,970 924,426 1,029,396 CIPST65005 ITS UPGRADES 424,642 228,000 205,200 209,304 213,491 217,760 1,155,895 2,654,292 CIPST65006 BUS PULLOUTS 144,509 360,000 324,000 330,479 337,089 343,831 1,825,099 3,665,007 CIPST65016 NORTHERN PARKWAY 133,910 670,000 670,000 670,000 670,000 670,000 3,483,910 CIPST65063 NEW RIVER - MULTI-USE PATHWAY 6,258 6,258 CIPST68125 STREET RECONSTRUCTION PROGRAM 34,009,748 34,009,748 CIPST68918 INFILL LIGHTING PROGRAM 1,089,606 180,000 162,001 165,240 168,545 171,915 912,549 2,849,856 CIPST68922 STREETLIGHT POLE PROGRAM 779,998 90,000 81,000 82,620 84,273 85,958 456,274 1,660,123 TOTAL 15,105,111 33,286,768 41,133,952 30,877,134 32,692,770 30,637,148 125,588,699 309,321,582 FY23-32 Streets by Funding Source 173 FUND FUND NAME CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080 GENERAL FUND CIP 4,000,000 4,000,000 8,000,000 2050 HURF 72,900 3,424,000 3,492,480 3,562,330 3,633,576 3,706,247 19,673,211 37,564,744 2060 TRANSPORTATION GRANTS 503,767 503,767 2070 TRANSPORTATION SALES TAX 1,050 9,710,250 9,904,455 10,102,544 10,304,596 10,510,688 55,791,999 106,325,582 4010 STREET G. O. BONDS 5,939,195 347,782 11,355,749 11,585,029 12,047,311 11,502,161 35,009,748 87,786,975 4020 HURF CAPITAL PROJECTS 4,405,402 1,116,999 1,054,542 1,081,039 1,108,284 1,136,298 6,130,419 16,032,983 4030 TRANS. SALES TAX CIP 3,171,533 13,563,079 10,822,959 4,546,192 5,599,003 3,781,754 8,983,322 50,467,842 4410 2014 STREETS DIF 1,244,918 1,244,918 4431 2019 STREETS DIF 270,114 1,124,658 1,394,772 TOTAL 15,105,111 33,286,768 41,133,952 30,877,134 32,692,770 30,637,148 125,588,699 309,321,582 174 Pavement Management Project Number: CIPST19006 Description: Project provides for street pavement treatments. Specific activities included in this project involve surface preparation, repairs, and overlays as needed. Justification: This project targets street segments that are in need of pavement treatments. Street rehabilitation is necessary to maximize the life of the city’s residential, collector, and arterial street network. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 2050 – HURF $72,900 $3,424,000 $3,492,480 $3,562,330 $3,633,576 $3,706,247 $19,673,211 $37,491,844 2070 – TRANS. SALES TAX $1,050 $9,710,250 $9,904,455 $10,102,544 $10,304,596 $10,510,688 $55,791,999 $106,324,532 Total $73,950 $13,134,250 $13,396,935 $13,664,874 $13,938,172 $14,216,935 $75,465,210 $143,890,326 175 Ballpark Boulevard Project Number: CIPST19010 Description: Project to design and construct Ballpark Boulevard. This is Phase II of this project to build the roadway to its ultimate configuration and tile the Roosevelt irrigation ditch. Justification: This project was identified as necessary for network connectivity in the region. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4410-2014-DIF Streets $1,244,918 $1,244,918 4431-2019-DIF-Streets $11,999 $11,999 Total $1,256,917 $1,256,917 176 Capital Bridge Repair Program Project Number: CIPST19048 Description: This program is needed to maintain city bridges to meet Federal Highway Administration standards. There are approximately 43 bridges that are inspected by Arizona Department of Transportation (ADOT) semi-annually. Justification: Under the National Bridge Inspection Program, administered by ADOT, the city is required to maintain its bridges to a satisfactory standard. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $95,374 $300,000 $270,000 $275,400 $280,907 $286,526 $1,520,915 $3,029,122 177 FLASHING YELLOW ARROWS Project Number: CIPST20012 Description: The project is to convert left-turn movements at existing signalized intersections to flashing yellow arrow operation with the purpose of improving safety. The project involves median modifications to provide better alignment. Justification: According to national data, Flashing Yellow Arrows can reduce left-turn crashes by offering motorists more opportunities to make left turns. This project provides Glendale matching funds. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $465,794 $465,794 178 VEHICLE REPLACEMENT Project Number: CIPST20013 Description: Replacement of existing vehicles that support transportation operations. Justification: Replacing existing vehicles will enable efficiency and reduce maintenance costs. This includes vehicles and equipment in the Transportation Department. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4410-2014-DIF Streets Zone $53,826 $260,000 $270,400 $281,216 $292,465 $304,163 $1,713,344 $3,121,588 4431-2019-DIF-Streets $642,438 $260,000 $270,400 $281,216 $292,465 $304,163 $1,713,344 $3,121,588 Total $696,264 $1,216,264 $540,800 $562,432 $584,930 $608,326 $3,426,688 $6,939,440 179 ST RECON BETHANY HM - 43RD TO 51ST Project Number: CIPST20014 Description: Project to reconstruct street segment between Bethany Home Road from 51st Avenue to 43rd Avenue and related improvement. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $114,736 $3,229,669 $3,344,405 180 ST RECON GLENDALE -101 TO EL MIRAGE Project Number: CIPST20016 Description: Project to reconstruct street segment between Glendale Avenue from Loop 101 to El Mirage Road and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $1,396,374 $1,396,374 181 ST RECON CAMELBACK - 83RD TO 91ST Project Number: CIPST20021 Description: Project to reconstruct street segment between Camelback Road from 91st Avenue to 83rd Road and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $294,268 $294,628 182 BIKE PROJECTS (MATCH) Project Number: CIPST20022 Description: This funding provides matching funds for bicycle and pedestrian related projects. Justification: This project enhances the quality of life for the residents and visitors by providing additional bicycle and pedestrian facilities. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $170,769 $143,208 $146,072 $148,994 $790,876 $1,399,919 183 75TH AVENUE ASPERA IMPROVEMENTS Project Number: CIPST21014 Description: Project includes median reconfiguration, street widening and wayfinding signage on Aspera Boulevard as well as restriping and signage on 75th Avenue and right-of-way acquisition. Justification: This project derives from a development agreement to complete infrastructure improvements in this area to allow for better traffic flow and mitigate congestion in the vicinity of Aspera Boulevard and 75th Avenue. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4431-2019-DIF-Streets $14,930 $14,930 184 CENTRAL CORE SIDEWALK GAPS Project Number: CIPST21015 Description: This project identifies matching funds for the installation of continuous sidewalks in the central core area. Justification: Project addresses General Plan, identifying the need to improve sidewalks. The City was awarded $2.1 M in Federal funding for the design and construction of this project. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $359,720 $226,520 $586,240 185 67TH AVENUE BIKE LANES Project Number: CIPST21016 Description: This project identifies matching funds for the installation of bike lanes on 67th avenue between Missouri Avenue and Cholla Street. Justification: The city was awarded $4.3M in Federal funding for the design and construction of this project. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $728,119 $504,213 $1,232,332 186 STREET RECON BELL RD - 51ST TO 59TH Project Number: CIPST21017 Description: Project to surface reconstruct street segment between Bell Road from 51st Avenue to 59th Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $129,941 $129,941 187 ST RECON GLENDALE - 101 TO 91ST Project Number: CIPST21018 Description: Project to surface reconstruct street segment between Glendale Avenue from Loop 101 to 91st Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $2,656,252 $347,782 $3,004,034 188 ST RECON CACTUS - 51ST TO 59TH Project Number: CIPST21044 Description: Project to reconstruct street segment between Cactus Road from 51st Avenue to 59th Avenue. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $1,288,054 $1,288,054 189 ST RECON 75TH-GLENDALE TO NORTHERN Project Number: CIPST21051 Description: Project to reconstruct street segment between 75th Ave from Glendale Avenue to Northern Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $7,370 $7,370 190 ST RECON 83RD-GLENDALE TO NORTHERN Project Number: CIPST21052 Description: Project to reconstruct street segment between 83rd Ave from Glendale Avenue to Northern Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $163,233 $163,233 191 ST RECON 67TH - GREENWAY TO BELL Project Number: CIPST22043 Description: Project to reconstruct 67th Avenue from Greenway Road to Bell Road and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $3,702 $3,702 192 ST RECON 67TH DEER VLY-PINNACLE PK Project Number: CIPST22044 Description: Project to reconstruct 67th Avenue from Deer Valley Road to Pinnacle Peak Road and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $3,893,399 $3,893,399 193 ST RECON 83RD - GLENDALE TO BHR Project Number: CIPST22046 Description: Project to reconstruct 83rd Avenue from Glendale Avenue to Bethany Home Road and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $111,395 $3,901,034 $4,012,429 194 ST RECON GLENDALE - 43RD TO 51ST Project Number: CIPST22047 Description: Project to reconstruct Glendale Avenue from 43rd Avenue to 51st Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $118,179 $118,179 195 ST RECON BETHANY HM - 59TH TO 67TH Project Number: CIPST22049 Description: Project to reconstruct Bethany Home Road from 59th Avenue to 67th Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $3,787,413 $3,787,413 196 ST RECON BETHANY HM - 67TH TO 75TH Project Number: CIPST22050 Description: Project to reconstruct Bethany Home Road from 67th Avenue to 75th Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $3,787,413 $3,787,413 197 ST RECON CAMELBACK - 59TH TO 67TH Project Number: CIPST22051 Description: Project to reconstruct Camelback Road from 59th Ave-67th Ave and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $108,150 $3,787,413 $3,895,563 198 ST RECON CAMELBACK - 67TH TO 75TH Project Number: CIPST22052 Description: Project to reconstruct Camelback Road from 67th Avenue to 75th Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $3,677,100 $3,677,100 199 ST RECON CAMELBACK - 75TH TO 83RD Project Number: CIPST22053 Description: Project to reconstruct Camelback Road from 75th to 83rd Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $3,677,100 $3,677,100 200 ST RECON 67TH - PEORIA TO OLIVE Project Number: CIPST22054 Description: Project to reconstruct 67th Avenue from Peoria Avenue to Olive Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $3,901,034 $3,901,034 201 ST RECON NORTHERN – 43RD TO 51ST Project Number: CIPST22058 Description: Project to reconstruct Northern Ave from 43rd Avenue to 51st Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $118,179 $118,179 202 ST RECON BELL RD - 59TH TO 67TH Project Number: CIPST22060 Description: Project to reconstruct Bell Road from 59h Avenue to 67th Avenue and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be surface reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $111,395 $3,901,034 $4,012,429 203 PAVEMENT CUT REPAIR Project Number: CIPST22062 Description: Project to repair street pavement cuts. Justification: Street pavement cut repair costs are to be reimbursed by contractors or other parties that have to cut streets as part of their projects. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4020-Hurf Capital Projects $96,238 $106,999 $109,140 $111,323 $113,549 $115,820 $614,787 $1,267,856 204 PEDESTRIAN LED CONVERSION Project Number: CIPST22063 Description: Convert 830 downtown pedestrian lights to LED luminaires that comply with the city's dark skies ordinance. Justification: This project promotes or enhances the quality of life for residents and visitors in the downtown area by providing improved and energy efficient lighting. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4020-Hurf Capital Projects $2,000,000 $2,000,000 205 TRANSPORTATION SAFETY PROGRAM Project Number: CIPST22064 Description: Project for safety street components such as raised medians, flashing yellow-arrows, intersection signalization, crash barriers and other related components. Justification: This project enables safer streets. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4020-Hurf Capital Projects $385,734 $480,000 $432,001 $440,640 $449,452 $458,442 $2,433,465 $5,079,734 206 SCALLOP STREET PROGRAM Project Number: CIPST22065 Description: Glendale has streets that were initially constructed without all typical street components. These “scalloped streets” are missing one or more of the following elements: full width pavement; curb and gutter; or sidewalk on one or both sides. Justification: This project is to complete street improvement to enhance traffic flow, provide safety to adjacent pedestrian traffic, mitigate property flooding and meet Glendale’s Design Standards. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 1080-General Government Construction $4,000,000 $4,000,000 $900,000 $8,900,000 4010-Streets Construction $100,000 $100,000 Total $4,000,000 $4,000,000 $100,000 $9,000,000 207 57TH AND GREENWAY INTERSECT IMPROV. Project Number: CIPST22067 Description: Installation of Traffic Signal and deceleration lane at the intersection of 57th Avenue and Greenway Road. Justification: This project emerged as development related through the approval of the Planned Area Development “Village at Thunderbird.” The City is to pay a share of the cost for this improvement to accommodate increased traffic in this area. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4431-2019-DIF-Streets $200,000 $200,000 208 59TH AND NORTHERN INTERSECT IMPROV. Project Number: CIPST22068 Description: Right turn lane along southbound 59th Avenue to westbound Northern Avenue. Justification: Increase capacity of southbound 59th Avenue for growth in traffic due to developments in the DIF zone. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4431-2019-DIF-Streets $43,185 $1,124,658 $1,167,843 209 OLIVE AVE 59-67 STREET LIGHTS Project Number: CIPST23014 Description: This project is to add streetlights on Olive Avenue between 59th Avenue and 67th Avenue. Justification: This is a safety improvement recommendation from the Road Safety Assessment (RSA). This project has 202,123 in funding identified from Maricopa Association of Governments (MAG) towards the construction phase. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 2060-Transportation Grants $301,644 $301,644 4030-Transportation Capital Projects $53,950 $13,789 $67,739 210 61ST/OLIVE TRAFFIC SIGNAL UPGRADE Project Number: CIPST23015 Description: The project is to Upgrade the existing traffic signal at the intersection of Olive Avenue and 61st Avenue. Justification: This is a safety improvement recommendation from the Roadway Safety Assessment (RSA). The project has 301,644 in Maricopa Association of Governments (MAG) funding identified towards construction phase. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 2060-Transportation Grants $202,123 $202,123 4030-Transportation Capital Projects $50,423 $9,248 $59,671 211 53RD/CAMELBACK NEW HAWK Project Number: CIPST23016 Description: This project is to install a high-intensity activated crosswalk beacon also known as HAWK at the intersection of 53rd Avenue and Camelback Road. Justification: A safety study conducted for this location identified a high-intensity activated crosswalk beacon also known as HAWK as a need. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $112,050 $390,167 $502,217 212 NORTHERN PARKWAY CABLE BARRIER 2 Project Number: CIPST23017 Description: The project is to install a median cable barrier between 143rd Avenue and 1/4-mile west of Dysart Road. This will close the gap in the median of the portion of Northern Parkway that Glendale owns and operates. Justification: The median cable barrier is intended to address safety concerns related to the potential crossover traffic. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $155,625 $1,042,750 $1,198,375 213 TMC UPGRADE Project Number: CIPST23018 Description: Upgrade the traffic management system equipment and furnish the new operations campus location for a fully functional traffic management center. Justification: The project is needed to replace failing and outdated equipment. The TMC is critical to managing traffic operations for day-to-day needs and during large/mega-events. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $228,692 $2,013,998 $2,242,690 214 MARYLAND ACTIVE TRANSPORTATION IMPR Project Number: CIPST23019 Description: The project is to install sidewalks and bike lanes in the area immediately south of Downtown Glendale. The project area is between Maryland Ave in the north, Bethany Home Rd in the south, 59th Ave in the west, and 43rd Ave in the east. Justification: This grant funded project is to close gaps in the pedestrian and bicycle system. The project will also improve access to businesses, residences, and bus stops. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $15,942 $95,155 $111,097 215 MISSOURI ACTIVE TRANSPORTATION IMPR Project Number: CIPST23020 Description: The project is to install sidewalks and bike lanes in the area immediately west of Grand Avenue. The project area is between Missouri Ave in the south, Bethany Home Rd in the south, 61st Ave in the west, and 51st Ave in the east. Justification: This grant funded project is to close gaps in the pedestrian and bicycle infrastructure system. The project will also improve access to businesses, residences, and bus stops. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $22,487 $123,278 $145,765 216 ST RECON GLENDALE EL MIRAGE-LITCHFI Project Number: CIPST23021 Description: Project to reconstruct street segment between Glendale Ave from El Mirage Road to Litchfield Road and related improvements. Justification: This street segment has been identified in the Pavement Management Plan and Pavement Condition Inventory to be reconstructed due to poor pavement conditions. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $229,473 $8,036,134 $8,265,607 217 SARIVAL AVENUE / BETHANY HOME ROAD Project Number: CIPST23047 Description: This project will install a traffic signal at the intersection of Sarival Avenue and Bethany Home Road. The project includes right-of-way acquisition and utility relocation efforts. Justification: This intersection location is anticipated to have an increase in traffic volume due to growth in the general vicinity requiring a new traffic signal. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $124,560 $967,896 $1,092,456 218 SARIVAL AVENUE / GLENDALE AVENUE Project Number: CIPST23048 Description: This project will install a traffic signal at the intersection of Sarival Avenue and Glendale Avenue. The project includes right-of-way acquisition and utility relocation efforts. Justification: This intersection location is anticipated to have an increase in traffic volume due to growth in the general vicinity requiring a new traffic signal. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $124,560 $967,896 $1,092,456 219 INFILL STREETLIGHTS Project Number: CIPST23049 Description: Install new streetlights along Bethany Home Road from 43rd Avenue to 59th Avenue, and 80 other locations citywide. Justification: The locations identified as part of this project have gaps in the street lighting system requiring an infill project to improve safety. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $168,156 $493,627 $503,499 $513,569 $1,678,851 220 58TH AVENUE/BETHANY HOME ROAD Project Number: CIPST23050 Description: This project will install a High-intensity Activated crossWalK (HAWK) and wrought iron fencing along both sides of Bethany Home Road adjacent to the park to direct pedestrian traffic to the designated crossing locations. The project will also install a westbound right turn lane at 59th Avenue & Bethany Home Road. Justification: This project location is identified as needing a HAWK beacon to serve the high volume of pedestrians crossing the street. The wrought iron fence will aid in diverting pedestrian traffic from both park locations to designated crossing locations. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $89,683 $679,643 $769,326 221 EXTEND FIBER OPTIC NETWORK Project Number: CIPST23051 Description: This project will extend the City fiber and conduit network into west Glendale by approximately 18 miles of fiber optic cable and conduit. Justification: Traffic signals in west Glendale currently are not connected to the Glendale Traffic Management Center. Additional traffic signals are planned for west Glendale to accommodate growing traffic in the area. This infrastructure is critical to good traffic operations in the City. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $249,120 $645,264 $658,169 $671,332 $2,223,885 222 SPEED FEEDBACK SIGNS Project Number: CIPST23052 Description: This project will install five (5) school zone signs and flashing beacons along arterials throughout the City. These installations will address traffic in both directions approaching each school zone. Justification: This project is intended to remind motorists to slow down in school zones in an effort to improve traffic safety. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $90,000 $81,000 $82,620 $84,273 $85,958 $456,275 $880,126 223 INFILL SIDEWALK Project Number: CIPST23053 Description: The project is to install approximately one mile of new sidewalk in the City each year. Justification: This project will address gaps in the sidewalk system in the City of Glendale. Incomplete sidewalk system is an impediment to pedestrian mobility including ADA users. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $180,000 $162,000 $165,2341 $168,544 $171,916 $912,551 $1,760,252 224 GUARDRAIL UPDATE Project Number: CIPST23054 Description: This project is to upgrade existing bridge attenuators and guardrails at multiple locations citywide. Justification: Replacing bridge attenuators and guardrails that do not meet current standards provides safer transportation infrastructure for motorists in the City of Glendale. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $120,000 $108,001 $110,160 $112,363 $114,611 $608,367 $1,173,502 225 ARTERIAL PAVEMENT TREATMENT Project Number: CIPST23055 Description: This project will provide pavement treatment for approximately three to five miles of arterials citywide. The mileage of improvements may vary due to cost escalation. Justification: This is to address arterial reconstruction locations that have been delayed due to the lack of bond authorization. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $1,605,001 $1,605,001 226 ARTERIAL STREET RECONSTRUCTION Project Number: CIPST23056 Description: This project will reconstruct up to two miles of arterial street pavement in FY 2023 and one mile in FY 2024. The mileage of improvements may vary due to cost escalation. Justification: This is to address arterial reconstruction locations that have been delayed due to the lack of bond authorization. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $8,841,361 $3706,776 $12,548,137 227 FLASHING YELLOW ARROWS PHASE 5 Project Number: CIPST23057 Description: This project will address intersection locations that were originally part of flashing yellow arrow (FYA) Phase 3, but could not be completed due to cost escalation. Justification: Studies indicate that crashes are reduced when FYA traffic signals are implemented. The FYA treatment has a positive benefit, especially for total crashes, injury and fatal crashes, and crashes related to left-turn movements. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $104,970 $924,426 $1,029,396 228 ITS UPGRADES Project Number: CIPST65005 Description: Project provides local match funds for Federally Funded Intelligent Transportation Systems (ITS) citywide. Justification: An enhanced system with updated communications infrastructure, traffic cameras, message signs, and networking equipment will make the traffic signal system more responsive. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $424,642 $228,000 $205,200 $209,304 $213,491 $217,760 $1,155,895 $2,654,292 229 BUS PULLOUTS Project Number: CIPST65006 Description: Design and construction of Bus Pullouts. Justification: Bus pullouts relieve congestion, improve air quality, and provide traffic and pedestrian safety. They will be constructed at major intersections for new routes, and to extend existing routes. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $144,509 $360,000 $324,000 $330,479 $337,089 $343,831 $1,825,099 $3,665,007 230 NORTHERN PARKWAY Project Number: CIPST65016 Description: Northern Parkway is a 12.5-mile partial access-controlled roadway between Sarival and Grand avenues. The current funded phase of the project is between Sarival and 87th avenues. Justification: Per intergovernmental agreement, Glendale’s portion of local funding is $37.9 million. To date, Glendale has expended approximately $32.5 million towards this project. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $133,910 $670,000 $670,000 $670,000 $670,000 $670,000 $3,483,910 231 NEW RIVER - MULTI-USE PATHWAY Project Number: CIPST65063 Description: This project is to construct a multi-use path from the Bethany Home Road alignment to Northern Avenue. The project will provide a safe and convenient off-street facility for bicyclists and pedestrians that is part of the regional West Valley Rivers Multi-modal Corridor Master Plan. This project has federal funds towards construction costs. Justification: This funding is for pending potential settlement agreement costs. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4030-Transportation Capital Projects $6,258 $6,258 232 STREET RECONSTRUCTION PROGRAM Project Number: CIPST68125 Description: Street reconstruction on various arterial and collector streets as identified on the Pavement Management Plan. Justification: FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4010-Streets Construction $34,009,748 $34,009,748 233 INFILL LIGHTING PROGRAM Project Number: CIPST68918 Description: This project installs additional street lighting in areas determined to be inadequate due to a spacing of 350 feet or greater. Infill street lighting requests are initiated by residents or staff and require the approval of affected residents. Justification: This project promotes or enhances the quality of life for the residents and visitors by providing well-lit areas in the city. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4020-Hurf Capital Projects $1,089,606 $180,000 $162,001 $165,240 $168,545 $171,915 $912,549 $2,849,856 234 STREETLIGHT POLE PROGRAM Project Number: CIPST68922 Description: This project is to remove and replace existing streetlight poles that have been identified for replacement in the pole inspection program. Justification: This project reduces safety concerns. This program is to mitigate safety hazards and provide better service. FUND CARRYOVER FY23 FY24 FY25 FY26 FY27 FY28-32 TOTAL 4020-Hurf Capital Projects $779,998 $90,000 $81,000 $82,620 $84,273 $85,958 $456,274 $1,660,123 DRAFT 10-Year CIP by Project Type 235 Streets $309.3 23.28% Water $251.2 18.91% Public Safety $148.6 11.19% Wastewater $146.7 11.04% Facility Maintenance $144.4 10.87% Parks $137.1 10.32% Landfill $50.5 3.80% Solid Waste $38.9 2.93% Drainage $32.6 2.45% Library $29.8 2.24% Airport $24.0 1.81% Transit $11.7 0.88% Parking Lots $2.0 0.15% Arts $1.4 0.11% Finance $0.3 0.02% Total DRAFT 10-Year CIP $1,328.5M FY22-23 DRAFT CIP by Project Type 236 Streets $48.4 18.16% Water $46.2 17.34% Parks $39.1 14.67% Facility Maintenance $35.8 13.43% Wastewater $30.8 11.56% Public Safety $26.7 10.02% Landfill $11.8 4.43% Airport $8.8 3.30% Drainage $5.4 2.03% Transit $4.6 1.73% Solid Waste $4.5 1.69% Library $2.5 0.94% Arts $1.4 0.53% Finance $0.3 0.11% Total DRAFT FY22-23 CIP $266.5M Budget Calendar 237 Item Date Workshop #1 – Budget Overview / Revenues / Five-Year Financial Forecasts January 11, 2022 Workshop #2 – FY23-32 Capital Improvement Plan February 1, 2022 Workshop #3 – FY23-32 Capital Improvement Plan March 1, 2022 Workshop #4 – (All Day) FY23 Operating Budget Department Presentations April 5, 2022 Workshop #5 – (All Day) FY23 Operating Budget Department Presentations April 7, 2022 Workshop #6 – FY23 Final Budget Workshop April 19, 2022 Voting Meeting – Tentative Budget Adoption May 10, 2022 Voting Meeting – Final Budget Adoption / Property Tax Levy June 14, 2022 Voting Meeting – Property Tax Adoption June 28, 2022