Arcadis Amendment Agreement

City of Glendale — Regular Meeting (2022-06-14)

View PDF Item 13 Meeting page

Extracted text (via pymupdf) 58949 characters
4/29/2021 
 
 
 
 
 
 
 
 
 
  C-10844-4 
AMENDMENT NO. 4 
West Area Water Reclamation Facility Improvements  
(City Project # 141525, Contract No. C-10844) 
 
This Amendment No. 4 (“Amendment”) to the Professional Services Agreement 
(“Agreement”) is made this ______ day of ________, 2022, (“Effective Date”), by and 
between the City of Glendale, an Arizona municipal corporation (“City”) and Arcadis U.S., 
Inc., A Delware Corporation authorized to do business in Arizona (“Contractor”). 
 
RECITALS 
 
A. 
City and Arcadis U.S., Inc. (“Contractor”) previously entered into Professional 
Services Agreement, Contract No. C-10844, dated May, 16,2016 (“Agreement”); and 
 
B. 
The initial study phase of the work has been completed with recommendation on 
how to proceed with critical plant improvements. 
 
C. 
GMP 1 construction (Headworks Improvements) has been completed. GMP2A 
design has been completed and is currently under construction (Primary 
Sedimentation Basin). Construction will be completed July 2022.  
 
D. 
The Detailed design of GMP2B: "UV, RAS, and RSPS Rehabilitation"; will be 
completed May 2022. Construction is planned to begin late summer/fall 2022. 
Expanding the Scope of Work (attached as Exhibit B) under the original agreement 
will include construction administration services and post construction activity for 
GMP 2B. 
 
E. 
The use of the term "Contractor" under this Amendment No. 4 is used 
interchangeably with the term "Consultant" defined under the Agreement and used 
throughout the attached exhibits. 
 
F.    This amendment includes revised billing rates that will be used henceforth and 
supersedes the billing rates of the original agreement. 
 
G. 
City and Contractor wish to modify and amend the Agreement subject to and strictly 
in accordance with the terms of this Amendment. 
 
AGREEMENT 
 
In consideration of the mutual promises set forth herein and other good and valuable 
consideration, the receipt and sufficiency of which are hereby acknowledged, the City and 
Contractor hereby agree as follows: 
 
1. 
Recitals.  The recitals set forth above are not merely recitals but form an integral 
part of this Amendment.

4/29/2021 
2. 
Term.  The term of the Agreement is extended for a one-year period from May 11, 
2023 through May 10, 2024, unless otherwise terminated or canceled as provided by 
the Agreement.  All other provisions of the Agreement except as set forth in this 
Amendment shall remain in their entirety. 
 
3. 
Scope of Work. This project will provide professional engineering services to 
complete construction administration and post construction activities for GMP 2B, 
as described in Exhibit B.   
 
4.  
Compensation. Including allowances, this original Contract C-10844 and Contract 
Amendments 1, 2, and 3 resulted in a previous compensation of $4,090,897.00. See 
Description of Project under Exhibit A for previous services breakdown. Including 
allowances, GMP 2B  Construction Administration Services will result in an increase 
in compensation of $809,383.00, as shown in attached Exhibit D (for a total 
compensation of $4,900,280).   
 
5. 
Insurance Certificate.  Current certificate will expire on June 1, 2022 and a new 
certificate applying to the extended term must be provided prior to this date to 
Materials Management and the Contract Administrator. 
 
6. 
Non-discrimination.   Contractor must not discriminate against any employee or 
applicant for employment on the basis of race, color, religion, sex, national origin, 
age, marital status, sexual orientation, gender identity or expression, genetic 
characteristics, familial status, U.S. military veteran status or any disability. 
Contractor will require any Sub-contractor to be bound to the same requirements as 
stated within this section. Contractor, and on behalf of any subcontractors, warrants 
compliance with this section.  
 
7.  
No Boycott of Israel.  To the extent A.R.S § 35-393 through § 35-393.03 are 
applicable, the parties hereby certify that they are not currently engaged in, and agree 
for the duration of the Agreement to not engage in, a boycott of goods or services 
from Israel, as that term is defined in A.R.S § 35-393. 
 
8. 
Attestation of PCI Compliance.  When applicable, the Contractor will provide the 
City annually with a Payment Card Industry Data Security Standard (PCI DSS) 
attestation of compliance certificate signed by an officer of Contractor with oversight 
responsibility. 
 
9. 
Ratification of Agreement.  City and Contractor hereby agree that except as 
expressly provided herein, the provisions of the Agreement shall be, and remain in 
full force and effect and that if any provision of this Amendment conflicts with the 
Agreement, then the provisions of this Amendment shall prevail. 
 
[Signatures on the following page.]

30001670 
A-1 
5/8/2022
 
 
EXHIBIT A 
Professional Services Agreement 
 
CITY OF GLENDALE 
WEST AREA WATER RECLAMATION FACILITY IMPROVEMENTS 
Amendment 4 
Project No. 141525 
 
Phase III – GMP2B WAWRF Improvements Project 
UV, RAS, RSPS, and ALS Construction Administration (CA) Services 
 
PROJECT 
 
DESCRIPTION OF PROJECT: 
The City of Glendale (City) West Area Water Reclamation Facility (WAWRF) provides Class A+ 
effluent with a rated capacity of 11.5 million gallons per day (MGD) for reuse and aquifer recharge. 
The effluent is used at various lakes within the City and for recharge at the West Area Aquifer 
Recharge Facility (ARF) and the New River Agua Fria Underground Storage Project (NAUSP). 
The City has experienced challenges with equipment related to several facilities both at the 
treatment plant and offsite facilities. Arcadis has previously evaluated these areas in 2018. 
Subsequent design and construction have occurred based on recommendations identified in the 
2018 Facilities Evaluation Report. Previous designs have included improvements at the 
preliminary treatment facility (GMP1) and design of primary sedimentation facilities (GMP2A). 
The most recent design (GMP2B) for the WAWRF was for improvements at the Returned 
Activated Sludge (RAS) pump station, Ultra-Violet (UV) Disinfection Facility, Raw Sewage 
Pump Station (RSPS), and Airport Lift Station (ALS). Design and construction administration 
services for previous designs were included under separate amendments, as generally shown 
below: 
• Original Contract – Facility Evaluation and Design of GMP1 Preliminary Treatment 
Facilities (Headworks) 
• Amendment 1 – WAARF APP Assistance (GMP1A), Forcemains Assessment, Design of 
Primary Sedimentation Facilities (GMP2A), and Design of UV/RAS Pump 
Station/RSPS/ALS Improvements (GMP2B) 
• Amendment 2 – Construction Administration (CA) services for GMP1 Preliminary 
Treatment Facilities (Headworks) 
• Amendment 3 – Construction Administration (CA) services for GMP2A Primary 
Sedimentation Facilities, Solar PV Evaluation, and Design of HVAC Controls Networks 
Upgrades 
This contract (Amendment 4) includes construction administration services for recommended 
design improvements at the UV, RAS, RSPS, and ALS facilities (GMP2B). The Scope of Work 
are defined in Exhibit B. The project delivery mechanism is Construction Manager at Risk 
(CMAR).  Services will assume an appropriate level of detail for the CMAR to develop guaranteed 
maximum price (GMP) proposals and construction related services. The CMAR is assumed to 
provide pre-construction services during design and will perform all cost, maintenance of plant 
operations, and field-verification activities. The Consultant may assist City staff with review and 
coordination with City-selected CMAR if defined in Exhibit B, Scope of Work.

30001670 
B-1 
5/8/2022
 
 
EXHIBIT B 
Professional Services Agreement 
 
CITY OF GLENDALE 
WEST AREA WATER RECLAMATION FACILITY IMPROVEMENTS 
Amendment 4 
Project No. 141525 
 
Phase III – GMP2B WAWRF Improvements Project 
UV, RAS, RSPS, and ALS Construction Administration (CA) Services  
 
SCOPE OF WORK 
 
This Scope of Work describes Engineering Services to be provided by Arcadis U.S., Inc. 
(CONSULTANT) for the City of Glendale (CITY). The Engineering Services to be provided under 
this Scope of Work shall include services related to the construction, start-up, commissioning, and 
post-construction phases of the West Area Water Reclamation Facilities UV Disinfection/RAS 
Pump Station/RSPS/ALS Improvements Project. The Scope of Work to be performed consists 
of the following services: 
1. 
Project Administration Services during Construction; Section 200 
2. 
Engineering Services during Construction; Section 300 
3. 
Observation Services during Construction; Section 400 
4. 
Special Services; Section 500 
5. 
Allowances; Section 600 
Other SUBCONSULTANTS working with CONSULTANT shall include the following: 
- 
Nabar Stanley Brown of Gannett Fleming 
- 
Southwest Protective Coatings 
The Engineering Services are predicated on the following assumptions: 
1. 
The Construction Manager at Risk (CMAR) will construct the work in one construction 
package with an estimated 9-month construction duration and an anticipated Notice to 
Proceed date of June 2022. 
2. 
The term “Contract Documents” as used herein refers to the combination of the CMAR’s 
contract with the CITY and CONSULTANT’s construction documents. 
3. 
The CMAR will complete certain portions of the work in advance of the overall project 
substantial completion date defined in the Contract Documents. CONSULTANT shall 
schedule the inspection, training, and commissioning services as required to meet the 
substantial completion dates as defined in the CMAR project progress schedule.

30001670 
B-2 
5/8/2022
 
 
4. 
All construction, programming/configuration (by others), start-up, and commissioning 
services will be complete by September 2023. 
 
5. 
The 24-month post construction Warranty period to commence at Substantial 
Completion as defined in the Contract Documents. 
 
6. 
The CMAR shall receive and transmit to and from the CONSULTANT all submittals, 
correspondence and necessary documentation from their suppliers and subcontractors. 
The CMAR will review these for completeness in accordance with the Contract 
Documents. 
 
Engineering Services are to be provided throughout the duration of construction, start-up, 
commissioning, and post-construction phases of the project. The overall project duration is 15-
months, with an anticipated Substantial Completion and final acceptance date as defined in the 
Contract Documents, plus a 24-month warranty period.  
 
The Contract Documents are defined as the Agreement, General Conditions, Supplemental 
Conditions, Drawings, Standard Details, Specifications, Addendums, and executed change orders 
prepared for construction of the project. 
 
SECTION 200 - PROJECT ADMINISTRATION SERVICES DURING 
CONSTRUCTION 
 
Task 210 
Representation on Behalf of CITY 
 
The CONSULTANT shall consult with and advise CITY and act as its representative during 
construction. The extent and limitations of the duties, responsibilities and authority of 
CONSULTANT as assigned herein shall not be modified, except as CONSULTANT may 
otherwise agree, in writing. 
 
The CONSULTANT will assist the CITY in issuing the CITY's instructions to CMAR; issue 
necessary interpretations and clarifications of the Contract Documents; have authority, as CITY'S 
representative, to require special inspection or testing of the work; act as initial interpreter of the 
requirements of the Contract Documents and evaluate the acceptability and completeness of the 
CMAR’s work thereunder, and make decisions on claims as directed by the CITY, to the CMAR 
relating to the acceptability of the work or the interpretation of the requirements of the Contract 
Documents pertaining to the execution and progress of the work. The CONSULTANT shall render 
all interpretations or decisions in good faith and in accordance with the requirements of the 
Contract Documents. 
 
CONSULTANT shall not be responsible for the means, methods, techniques, sequences, or 
procedures of construction selected by CMAR (unless otherwise specified in the Contract 
Documents) or the safety precautions and programs incident to the work of CMAR.

30001670 
B-3 
5/8/2022
 
 
CONSULTANT's efforts shall be directed toward advising the CITY whether the completed work 
of CMAR will conform to the Contract Documents, but CONSULTANT shall not be responsible 
for the failure of CMAR to perform the work in accordance with the Contract Documents.  
 
On the basis of on-site examination of materials, equipment, and workmanship, CONSULTANT 
shall keep CITY informed of the progress of the work, shall endeavor to protect the CITY against 
defects and deficiencies in such work and may disapprove or reject work failing to conform to the 
Contract Documents. This task shall include the following subtasks: 
 
210.1 
Project Management: The CONSULTANT shall perform overall Project Management of 
the work, which consists of the administrative tasks necessary to maintain the overall 
project budget and schedule and includes the preparation of and assembly of the monthly 
reports and invoices. Under this task the CONSULTANT shall meet monthly with the 
CITY’S representative to discuss the services, the costs associated with the cash flow 
projections, and the schedule of services performed under this Scope of Work, and the 
overall status, progress, and issues on the project. 
 
210.2 
Construction Procedures and Communications:  The CONSULTANT will utilize 
existing construction procedures and communications established under GMP1. 
 
210.3 
Attend Pre-Construction Conferences conducted by the CMAR:  The CMAR shall 
conduct Pre-Construction Conference for the work. The conference will be held in 
accordance with the Contract Documents. At the conference, the CONSULTANT and 
CMAR shall identify field services to be provided by the CONSULTANT, CMAR and 
the CITY and discuss appropriate coordination procedures. The CMAR will conduct all 
conferences, and shall prepare and distribute all meeting minutes. 
 
210.4 
Provide Construction Administration, Quality Assurance, and Coordination:  The 
CONSULTANT shall provide construction administration and quality assurance services 
during the course of the project to advise of the overall technical correctness of the work 
and construction services and that specified procedures are being followed and that the 
project schedule is being met. The CONSULTANT shall provide coordination functions 
during the construction phase as follows: 
 
1. Hold required coordination meetings with CITY Representatives. 
2. Coordinate the work of the CONSULTANT’s specialty subconsultants assigned to 
the project. 
3. Participate in weekly construction progress meetings, conducted by the CMAR. 
 
210.5 
Perform Regulatory Agency Coordination: The CONSULTANT shall work with the 
CITY’s staff and the CMAR to coordinate with regulatory agencies involved in the final 
approval of this project; the following regulatory agencies are anticipated:   
 
1. Maricopa County Environmental Services Department (MCESD) 
2. Maricopa County Air Quality Department (MCAQD)

30001670 
B-4 
5/8/2022
 
 
The CONSULTANT shall document all coordination and correspondence with the 
agencies. The CONSULTANT shall prepare and submit requests for approval of 
construction to MCESD for the work specified by the CITY under the Contract 
Documents. Per MCESD, each approval of construction will contain the following, at a 
minimum: 
 
1. CONSULTANT'S Engineer’s Certificate of Completion 
2. Equipment/Piping Test Summary 
3. Operations and Maintenance Manual (one hard copy and one electronic copy) 
4. Record Drawings  
5. CONSULTANT's Startup Plan and Commissioning 
 
The CONSULTANT shall document all coordination and correspondence with the 
agencies. The CONSULTANT shall prepare and submit requests for Air Quality Permit 
for the Airport Lift Station’s generator.  
 
Any payments made to MCESD or MCAQD for permits will be paid through Allowance 
item Task 610. 
 
210.6 
Coordination with City Building Services Department:  The CONSULTANT shall work 
with the CMAR and CITY staff to coordinate with the Building Services Department in 
the Completion of this project. This effort is based on the preparation of special 
inspection certificates, providing special structural and electrical inspections for the 
work, and preparing the required monthly reports. 
 
210.7 
Provide Project Documents:  The CONSULTANT shall maintain and provide the 
following detailed project records and documentation during the construction phase: 
 
1. The project records shall include schedules, submittal, test data, project data, 
payments, allowance requests, clarifications, digital control system documentation 
and other such documentation the CONSULTANT receives. Project records shall be 
delivered to the CITY upon completion of the project. Records shall be maintained 
as defined under Section 400 of this Scope of Work at the CMAR’s field office or 
electronically through a collaboration website/software. 
 
Task 215 
Administer the Construction Schedule 
 
Review the CMAR's As-Planned Progress Schedule Submittal:  The CONSULTANT shall receive 
a schedule from the CMAR to review and critique the As-Planned Progress Schedule submittal 
specific to completion. The CONSULTANT shall in general examine the work sequence, 
durations, interim milestones and other appropriate scheduling features in accordance with the 
requirements of the Contract Documents. The CONSULTANT shall provide review comments 
and shall meet and discuss the schedule comments with the CMAR, Subcontractors, and the CITY.  
Review Monthly Progress Schedule Submittals:  In accordance with the Contract Documents, the 
CONSULTANT shall review the monthly updates to the CMAR’s Progress Schedule. The 
CONSULTANT shall perform a review of progress accomplished during the month and compare

30001670 
B-5 
5/8/2022
 
 
it to the as-planned schedule and discuss significant discrepancies at the Construction Progress 
Meeting. CMAR and CONSULTANT shall establish, based on the data, the percent of completion 
of each element of the schedule. 
 
Task 220 
Perform Site Visits 
 
The CONSULTANT's design staff will make periodic site visits appropriate for the type of 
construction at periods appropriate to the various stages of construction to observe, as an 
experienced and qualified professional, the progress and quality of the executed work and to 
determine in general if the work is proceeding in accordance with the design intent. No more than 
one site visits of two staff biweekly, excluding start up and testing efforts. The CONSULTANT's 
Construction Manager will attend the biweekly Construction Progress Meetings and make site 
visits to assist with field issues. 
 
Task 230 
Review Shop Drawings and Test Results 
 
The CONSULTANT shall receive, review, evaluate, and distribute Shop Drawings, samples, test 
results, and other data which CMAR is required to submit. The CONSULTANT's review shall 
only be for conformance with the design concept of the Project and compliance with the 
information given in the Contract Documents. Such review or other action shall not extend to 
means, methods, sequences, techniques, or procedures of construction selected by CMAR, or to 
safety precautions and programs incident thereto. Review by the CONSULTANT does not 
guarantee completeness of submitted information and does not remove responsibility of the 
CONTRACTOR to ensure proper fitment and conformance to Contract Documents unless 
specifically allowed in writing. The CONSULTANT shall receive and review (for general contents 
as required by the Contract Documents) maintenance and operating schedules and instructions, 
Operation and Maintenance Manuals, Lesson Plans, guarantees, bonds and certificates of 
inspection which are to be assembled by CMAR in accordance with the Contract Documents. 
 
Task 235 
Issue Interpretations and Clarifications  
 
The CONSULTANT shall respond to the CMAR to clarify and/or interpret technical, design 
related questions. Routine technical interpretations shall be responded to under Task 400. The 
CONSULTANT shall assist the CITY, as required, in resolution of these issues. The 
CONSULTANT shall respond to issues raised during construction regarding interpretation and 
clarification of the contractual administrative and technical requirements of the Contract 
Documents. Interpretations – Request for Information (RFI) and Engineer’s Clarifications (EC) 
shall be issued to the CMAR under Task 400.  
 
Task 240  
Review Requests for Alterations 
 
The CONSULTANT shall respond to the CMAR’s Request for Alterations (RFA’s). Routine 
technical interpretations shall be responded to under Task 400. RFA’s shall be responded to under 
this task. The CONSULTANT shall respond to requests for alterations requested by the CMAR 
during the construction phase.

30001670 
B-6 
5/8/2022
 
 
Task 250 
Certify Progress Payments 
 
The CONSULTANT shall inform the CITY of approval of the CMAR's Schedule of Values, after 
any updates or adjustments have been made by the CMAR in accordance with the Contract 
Documents. The monthly Progress Schedule update in combination with the CONSULTANT's 
field observations and the progress schedule shall be used by the CONSULTANT to determine the 
appropriateness of the CMAR's Application for Payment. 
 
Based on CONSULTANT'S on-site observations, as an experienced and qualified professional, 
and on review of Applications for Payment and any accompanying data and schedules required to 
review Applications for Payment, the CONSULTANT shall determine the amounts owed to the 
CMAR and recommend, in writing, that payments to the CMAR in such amounts be submitted by 
the CITY; such recommendations of payment will constitute a representation to the CITY, based 
on such observations and review, that the work has progressed to the point indicated, that, to the 
best of CONSULTANT's knowledge, information and belief, the quality of such work is in 
accordance with the Construction Documents (subject to an evaluation of such work as a 
functioning Project upon Substantial Completion, to the results of subsequent tests called for in 
the Construction Documents, and to qualifications stated in the recommendation), and that 
payment of the amount recommended from the review of the Application for Payment is due to 
the CMAR. 
 
Task 260 
Substantial Completion and Final Acceptance Inspection 
 
Following notice from the CMAR, the CONSULTANT shall conduct an inspection to determine 
if the Project is substantially complete in accordance with the Contract Documents. If the CITY 
and the CONSULTANT considers the work substantially complete, the CONSULTANT shall 
deliver to the CITY and CMAR the Certificate of Substantial Completion and the punch list, the 
date for completion of the punch list, and recommend the division of responsibilities between the 
CITY and the CMAR. 
 
Substantial Completion and Final Acceptance Inspection shall be done for the following 
construction elements: 
 
A. Replacement of drain valves within the Secondary Sedimentation Basins. 
B. Installation of the yard piping and UV drain pump station 
C. Installation of new UV Disinfection equipment and area associated electrical and 
communication upgrades. 
D. Installation of all RAS pumps, flow meters, VFDs, and area associated electrical and 
communication upgrades. 
E. Installation of all RSPS pumps, flow meters, VFDs, and area associated electrical, site security, 
and communications upgrades. 
F. Installation of ALS generator, electrical gear in new building, flow meter, bypass piping 
connection and other area associated electrical, site security, and communications upgrades. 
G. Site wide painting of structures and piping 
H. Services by the CMAR as described in SECTION 500 - SPECIAL SERVICES  
I. All remaining work, site work, and site improvements

30001670 
B-7 
5/8/2022
 
 
 
It is anticipated that the final punch list correction period shall occur during a thirty (30) day 
period immediately following the Substantial Completion Inspection associated with each 
construction element. 
 
The CONSULTANT shall, upon completion of the punch list items, make final inspection to 
determine if the finished work has been completed to the standard required by the Contract 
Documents, and CMAR has fulfilled the obligations thereunder so that CONSULTANT may 
recommend, in writing, final payment to CMAR and may give written notice to CITY and the 
CMAR that the work is acceptable subject to conditions therein expressed. 
 
CONSULTANT shall not be responsible for the acts or omissions of the CMAR or any of the 
CMAR's Subcontractor's, agents or employees or any other persons (except CONSULTANT'S 
own employees and agents) at the site or otherwise performing any of the CMAR's work; however, 
nothing contained in Tasks 210 through 260, inclusive, shall be construed to release 
CONSULTANT from liability for negligent acts, errors or omissions in the performance of 
CONSULTANT's duties in accordance with this Scope of Work. 
 
SECTION 300 - ENGINEERING SERVICES DURING CONSTRUCTION 
 
Task 310 
Changes  
 
The CONSULTANT shall perform services in connection with allowance requests to reflect 
changes requested by CITY or CMAR, for evaluating substitutions proposed by CMAR and 
making revisions to Drawings and Specifications, resulting from significant delays, performing 
services not accounted for or defined within this agreement, changes or price increases occurring 
as a direct or indirect result of material, labor, or equipment shortages. Changes and RFA’s shall 
be limited to the scope of the Project as defined by the Contract Documents or additional work as 
may be requested by the CITY. The CONSULTANT shall prepare drawings, details and 
specifications needed to describe the change. The CONSULTANT shall prepare an estimate of the 
cost and time impact of the change and conduct negotiations with the CMAR in conjunction with 
the CITY. 
 
Task 320 
Material Testing 
 
The CONSULTANT shall coordinate materials inspection and testing services as required to be 
performed by the CITY in the Contract Documents.  
 
The CITY will provide the services of a Professional Construction Materials Inspection and 
Testing Laboratory that meets ASTM E 329 requirements. Inspection and testing shall be 
coordinated with the construction schedule. Testing and inspection services shall include 
placement inspection and testing of compacted select fill and backfill, ordinary backfill, paving 
base, pavement subgrade, and subgrade courses; asphaltic concrete pavement inspection and field 
density tests and concrete testing and inspection. Samples for testing shall be collected from the 
construction site and delivered to the on-site laboratory. The laboratory shall provide a

30001670 
B-8 
5/8/2022
 
 
construction materials technician (technicians) to perform the field construction materials 
inspection and field-testing services herein outlined. 
 
CONSULTANT shall review laboratory reports and reports of inspection and testing activities 
describing the tests and inspections made. Written reports of all testing results, which identify the 
required data and identify conformance or non-conformance with the Contract Document shall be 
summarized in weekly construction observation  reports. 
 
SECTION 400 - OBSERVATION SERVICES DURING CONSTRUCTION 
 
The CONSULTANT shall provide appropriate personnel and expertise in order to observe 
performance of the work of the CMAR. Through increased on-site observations of the work in 
progress and field checks of materials and equipment by CONSULTANT staff, CONSULTANT 
shall endeavor to provide further protection for CITY against defects and deficiencies in the work 
of CMAR; but the furnishing of such representation will not make CONSULTANT responsible 
for construction means, methods, techniques, sequences or procedures, or for safety precautions 
or programs, or for CMAR failure to perform the work in accordance with the Contract 
Documents. 
 
CONSULTANT’s onsite observers shall not: 
 
A. Authorize any deviations from the Contract Documents or approve any substitute materials 
or equipment which may impact cost, time, or design intent without approval from the CITY.  
B. Undertake the responsibilities of CMAR, Subcontractors or CMAR's superintendent, or 
expedite the work. 
C. Advise on or issue directions relative to the means, methods, techniques, sequences, or 
procedures of construction unless such is specifically called for in the Contract Documents. 
D. Advise on or issue directions as to safety precautions and programs in connection with the 
work. Advise the CITY to occupy and/or start-up equipment which may have been impacted 
by the Project in whole or in part, outside of the terms stated in Task 470 Substantial 
Completion.  
E. Remain located permanently onsite. CONSULTANT staff will attend weekly meetings and 
inspections as required by Contract Documents. CONSULTANT will be on-site part-time for 
scheduled inspections and meetings only (this is not a full-time position, but periodic onsite 
observation for confirmation of compliance with the Contract Documents). 
F. The CONSULTANT will not approve changes to any equipment or material for which the 
Contract Documents approved after acceptance of the CMAR’s guaranteed maximum price 
unless approved by the CITY.  
G. The CONSULTANT will not deliver to the CITY a set of indexed shop drawings. 
 
CONSULTANT’s dealings in matters pertaining to the on-site work shall in general be only with 
CITY and CMAR, and dealings with CMAR Subcontractors shall only be through or with the full 
knowledge of CMAR.  
 
CONSULTANT shall be responsible for performing the following tasks:

30001670 
B-9 
5/8/2022
 
 
Task 405 
Schedules 
 
As described under Task 215 CONSULTANT shall, review the Progress Schedule, schedule of 
CMAR's submittal and Schedule of Values prepared by CMAR, and consult with CITY concerning 
their acceptability. 
 
Task 410 
Meetings and Conferences 
 
Attend Pre-Construction Conferences as described under Task 210.3. Attend biweekly 
Construction Progress Meetings.  
 
Task 415 
Liaison 
 
A. Serve as CONSULTANT'S liaison with CMAR, working principally through CMAR's 
Project Manager and assist the Project Manager in understanding the intent of the Contract 
Documents. Serve as CITY'S liaison with CMAR, in  support of CMAR's coordination of 
construction operations that affect CITY'S operations. 
 
B. Assist in obtaining from CITY additional details or information, when required at the job site 
for proper execution of the work. 
 
Task 420 
Shop Drawings and Samples 
 
A. Submittals which are furnished by CMAR shall be received and reviewed as defined in Task 
230. 
 
B. Advise CITY prior to the commencement of work requiring a Shop Drawing or sample 
submission if the submission has not been approved and inform the CMAR. 
 
Task 425 
Material Testing 
 
A. Results of Material Tests furnished by the CMAR shall be received and reviewed as defined 
in Task 330. 
 
 
Task 430 
Review of Work, Rejection of Defective Work, Inspections and Tests 
 
A. Conduct on-site observations of the work in progress to assist CONSULTANT in determining 
if the work is proceeding in accordance with the Contract Documents and that completed 
work conforms to the Contract Documents. 
 
B. Report to CITY whenever it is believed that work is unsatisfactory, faulty, defective or does 
not conform to the Contract Documents, or does not meet the requirements of inspections, 
tests or approval required to be made, or has been damaged prior to final payment; and advise 
CITY in writing when it is believed work should be corrected or rejected or should be 
uncovered for observation, or requires special testing, inspection or approval.

30001670 
B-10 
5/8/2022
 
 
 
C. Verify that tests, equipment, and systems start-up and operating and maintenance instructions 
are conducted as required by the Contract Documents and in presence of the required 
personnel, and that CMAR maintains required records thereof; observe, record and report to 
CONSULTANT appropriate details relative to the test procedures and start-ups. Conduct field 
checks to ensure that Shop Drawings have been approved for equipment that is being installed 
and verify that installers are using the approved Shop Drawings.  
 
D. Accompany visiting inspectors representing public or other agencies having jurisdiction over 
the Project, record the outcome of these inspections and report to CITY. 
 
Task 435 
Interpretation of Contract Documents 
 
Receive and transmit all clarifications and interpretations of the Contract Documents, to/from the 
CMAR and CITY as described above. 
 
Task 440 
Field Alteration and Verification 
 
Receive, review, and respond to the CMAR’s RFA’s and confirmation of Field Order agreements. 
 
Task 445 
Changes 
 
Consider and evaluate CMAR’s suggestions for changes in drawings or specifications, including 
Requests for Alterations as described under Task 240 and report them with recommendations to 
CITY. Notify the CITY's Representative of any changes or alterations believed to be in the CITY'S 
best interest.  
 
Task 450 
Records 
 
A. Maintain orderly files for correspondence, reports of job conferences, Shop Drawings and 
samples submissions, reproductions of original Contract Documents including all Addenda, 
Allowance Requests, Field Orders, additional Drawings issued subsequent to the execution 
of the Contract, CONSULTANT's clarifications and interpretations of the Contract 
Documents, progress reports and other Project related documents. 
 
B. Prepare observation reports recording CMAR and Subcontractors work performed on the job 
site, major construction equipment on-site, conditions, data relative to questions of extras or 
deductions, list of visiting officials and representatives of manufacturers, fabricators, 
suppliers and distributors, daily activities, decisions, on-site equipment, Subcontractors on-
site, observations in general and specific observations in detail as in the case of observing test 
procedures.  
 
C. Record names, addresses and telephone numbers of the CMAR, subcontractors and major 
suppliers of materials and equipment. 
 
D. Maintain notes to be capable of cross-referencing the CMAR's record drawing information

30001670 
B-11 
5/8/2022
 
 
for accuracy and completeness. 
 
E. Receive, review and process testing reports. 
 
F. 
The CONSULTANT will maintain a weekly digital photo file of the progress of the 
construction activities throughout the duration of the project as required to capture key aspects 
of the CMAR’s work. This photo file will consist of color digital photographs taken to 
document specific construction activities that may be of value to future modifications to the 
facility. The photographs will be labeled as to the subject and date of the photo and the photos 
will be kept in file folders, which have been formatted to represent the specific construction 
area of the project. 
 
G. The CONSULTANT will inspect the CMAR's marked up record drawings weekly, to 
determine if the mark-ups are up to date and reflect the record condition of the Work. If 
deficiencies are evident, CONSULTANT will provide written notification of said deficiencies 
to CMAR and will recommend to the CITY the withholding of appropriate payments to the 
CMAR. It is assumed the CMAR will provide and maintain a readily available live electronic 
version for the CONSULTANT to view remotely using Bluebeam Software©, or equal. 
 
Task 455 
Reports 
 
A. The CONSULTANT shall furnish the CITY a Job Status Report with the following items: 
 
1. 
Important dates 
2. 
Specific project issues 
3. 
Identify pending meetings and their topics 
 
B. CONSULTANT shall consult with CITY in advance of scheduled major tests, inspections or 
start of important phases of the work. 
 
C. CONSULTANT shall report immediately to CITY upon the occurrence of any accident. 
 
Task 460 
Payment Application 
 
Review applications for payment as described in Task 250 with CMAR for compliance with the 
established procedure for their submission and forward them with recommendations to CITY, 
noting particularly their relation to the Schedule of Values, work completed, and materials and 
equipment delivered at the site but not incorporated in the work. 
 
Task 465 
Certificates, Maintenance and Operation Manuals 
 
During the course of the work, review and determine that certificates, Operation and Maintenance 
Manuals and other data required to be assembled and furnished by CMAR are applicable to the 
items actually installed; and deliver this material to CITY following CONSULTANT’s review 
prior to final acceptance of the work. The CMAR will develop, with assistance from the 
CONSULTANT and CITY, an indexing and volume identification system for all Operation and

30001670 
B-12 
5/8/2022
 
 
Maintenance Manuals. 
 
Task 470 
Substantial Completion and Final Acceptance 
 
A. Before CONSULTANT issues a Certificate of Substantial Completion, submit to CMAR a 
list of observed items requiring completion or correction in accordance with the requirements 
of the Contract Documents. 
 
B. After the CMAR has completed the work and upon request of the CMAR, the 
CONSULTANT shall conduct final inspection in the company of CITY and CMAR. Prepare 
a final list of items to be completed or corrected in accordance with the requirements of the 
Construction Documents.  
 
C. After the CMAR has completed the work and upon written notice from the CMAR, review 
and determine that items on final list have been completed or corrected and make 
recommendations to CITY concerning acceptance. 
 
SECTION 500 - SPECIAL SERVICES 
 
Task 510 
Warranty  
 
The CONSULTANT will provide services after completion of the Construction Phase, such as 
inspections during the 24-month guarantee/warranty period, reporting observed discrepancies 
under guarantees called for in the Contract Documents, and provide assistance for resolution of 
defects to be corrected under warranty.  
 
Task 520 
Electronic Operations and Maintenance Manuals (EOMM) 
 
Under this Scope of Services, the CONSULTANT will update existing West Area Water 
Reclamation Facility Electronic Operations and Maintenance Manuals (EOMM) content to reflect 
modifications to existing facilities. 
 
The existing EOMM chapters to be updated include: 
 
1. UV Disinfection 
2. RAS Pump Station 
3. Raw Sewage Pump Station 
4. Airport Lift Station 
 
Each chapter for the major systems will consist of the following sections: 
 
 
 
 
 
 
• Background  
• Theory  
• Operating Strategies 
• Equipment & Control Description  
• Procedures  
• Design Criteria 
• Troubleshooting 
• Safety 
• Alarms  
• Figures

30001670 
B-13 
5/8/2022
 
 
 
The West Area Water Reclamation Facility EOMM will cover operational basics: design criteria, 
intended operation of the processes, start-up, shutdown, monitoring and troubleshooting 
procedures; alternate operations modes; and special process safety considerations. Standard 
monitoring procedures will be included to cover required monitoring for odor control effluent 
quality. These procedures will be field verified by the CONSULTANT with assistance from the 
Plant Staff.  
 
The West Area Water Reclamation Facility EOMM will be developed for integration with the 
CITY’s existing Lucity asset management database, per CITY requirements. The CONSULTANT 
will assist the CITY in developing methods to link information associated with the EOMM to the 
Lucity asset management database. The CITY will provide the asset management database 
requirements at the project kickoff meeting. 
 
Up to two (2) workshops will be held with the CITY prior to content development activities to 
provide an overview of the content to be developed, to identify key CITY staff to review draft 
chapters, and to establish a review schedule. The CITY will be provided with interim deliverables 
of completed EOMM sections as the construction of major areas of the plant are completed. As 
each chapter is completed, the CONSULTANT will submit draft chapters to the City for their 
review and comment over a two-week period. The CITY will provide comments to the 
CONSULTANT for the CONSULTANT to incorporate into the final documents. The interim 
deliverables will be installed and operational on the CITY’s server prior to start-up of these 
facilities. A schedule for the interim deliverables will be provided to the CITY at the start of the 
project. 
 
Before submitting the final version of the EOMM and transferring to the CITY, the 
CONSULTANT will conduct a detailed final validation and field verification process. Through 
this critical quality control activity, the CONSULTANT will verify that: 
 
1. Content has been field-verified and checked at the installation.  
2. All photographs are current and are reflective of well-maintained and clean conditions. 
3. All relevant documentation, such as scanned documents, figures and drawings are 
appropriately categorized for insertion into the database. 
4. Standard Operating Procedures (SOPs) are accurate and reflect actual as-operated 
conditions. 
 
The CONSULTANT will also assist in the installation and configuration of the EOMM on the 
CITY’s server and conform to CITY standards for Lucity developed during the content 
development workshops.  
 
Task 530 
Training 
 
The CONSULTANT shall review the CMAR's training plan and instruction materials for 
compliance with contract documents. The CMAR or manufacturer training presentations shall be 
scheduled and coordinated with CITY personnel and facility operation. CONSULTANT shall 
provide instruction to CITY personnel on the project objectives, design intent, and system

30001670 
B-14 
5/8/2022
 
 
operational procedures. 
 
Specific training services shall consist of the following: 
 
A. CMAR's and Manufacturer's training. 
 
1. CONSULTANT shall coordinate and monitor the CMAR's and Manufacturer's training 
of the CITY'S personnel. 
a. Discuss the preliminary course and lesson plan development with the CMAR and the 
manufacturer. One meeting shall be held with CITY's Staff and the CMAR for this 
discussion. 
b. Review and approve lesson plans and course materials. 
c. Liaison between CITY and CMAR. 
d. Monitor Training Sessions. 
1) Monitor attendance 
2) Evaluate course 
3) Assist classroom discussions 
4) Ensure Manufacturer’s training hours are fulfilled 
5) Confirm delivery of Professional Development Hours are supplied to CITY’s Staff 
by the Manufacturer. 
 
Task 540 
Commissioning 
 
The CONSULTANT shall assist the CITY with commissioning of the facilities. (Commissioning 
is defined as the process in which the newly constructed facilities are placed into routine 
operation.)  The commissioning process will include the CMAR’s planned, systematic approach 
to verify that facility systems operate as intended and there is an orderly transition from 
construction through start-up to routine operation. The CONSULTANT shall witness CMAR 
equipment testing and performance testing; review CMAR’s start-up planning, systems start-up, 
operation and troubleshooting; and monitor CMAR’s transition support to CITY operations to 
ensure a properly operating and performing system at the completion of the commissioning 
process. 
 
The Commissioning process progresses along three general phases, as follows: 
 
1. Phase I 
- Equipment Testing and Systems Performance Testing 
2. Phase II 
- Start-up and Transition Planning 
3. Phase III - Start-up, Initial Operation and Transition of Major Systems by CMAR to 
CITY 
 
The following equipment will be commissioned, once they are substantially completed by the 
CMAR: 
 
1. RAS Pumps 1 and 2 
2. RAS Pumps 3 and 4 
3. RAS pumps 5, 6, and 7

30001670 
B-15 
5/8/2022
 
 
4. RAS and WAS Facilities 
5. UV Disinfection System and Drain Pump Station 
6. RSPS 250 HP pumps and Electrical Improvements 
7. ALS Electrical System and Generator 
 
Once all newly constructed facilities are substantially completed by the CMAR, completed 
facilities will be commissioned by CMAR to demonstrate that the facility meets the design 
treatment capacity and effluent quality parameters established by the CONSULTANT during 
detailed design development. 
 
The CONSULTANT shall provide operations and technical assistance during the commissioning 
process under the overall direction of the CITY. The CONSULTANT will act as the CITY’s agent 
during the commissioning process under the direct guidance of CITY operations staff. The CMAR 
will be responsible for all equipment and systems maintenance during the commissioning process. 
The CITY shall assume full responsibility for compliance with all permits and other regulatory 
and policy requirements during the commissioning process. The CITY will provide all analytical 
testing and process chemicals.  
 
Phase I - Equipment Operational Readiness Testing and Systems Performance Testing 
 
The CONSULTANT shall witness equipment testing and performance testing by the CMAR for 
each system listed above. The CONSULTANT shall: 
 
A. Observe and develop a detailed understanding of the operating characteristics of the equipment 
and systems. 
 
B. Verify the testing process is conducted in accordance with intended operating practices during 
Commissioning and ensure CMAR testing covers the full function and alarms of equipment as 
supplied and specified in Contract Documents. Verify the CMAR has completed point to point 
testing of wiring, Integrated System Field Test, Operational Availability Demonstration, prior 
to Equipment Operational Readiness. CONSULTANT shall be available to assist the CMAR 
in troubleshooting and  
 
C. Identify if specific operating and monitoring requirements are to be used during Start-up and 
initial operation. 
 
The testing by CMAR will be provided to the CONSULTANT and CITY with detailed 
understanding of system performance characteristics, operating requirements, and monitoring 
needs during start-up and operation under the direction of the CITY.  
 
Phase II - Start-up and Transition Planning  
 
The CMAR, shall prepare a detailed start-up and transition plan to facilitate smooth and orderly 
placing of new facilities into service through their initial operation and successful transition to the 
CITY. The start-up and transition plan shall be developed with assistance from CONSULTANT 
and CITY staff. The start-up and transition plan shall include prestart-up checklists and required

30001670 
B-16 
5/8/2022
 
 
conditions; identification of impacts to other processes; analytical testing and sampling 
requirements, start-up procedures; health and safety equipment requirements; monitoring 
equipment requirements; roles and responsibilities and staffing requirements of CITY and the 
CMAR. The start-up and transition plan shall also include training requirements, and an estimated 
timeline of the start-up, initial operation, and transition process. 
 
Phase III - Start-Up, Initial Operation and Transition of Major Systems  
 
The purpose of Phase III is for CMAR’s start-up of new facilities and verification of their 
successful function in manual and computer-control modes.  Phase III will consist of the following 
activities: 
 
A. The CONSULTANT shall observe and verify that each process and its associated mechanical 
and control elements operates as specified under actual operating conditions. The 
CONSULTANT shall document the results of the commissioning process and issue a summary 
report to the CITY. 
 
B. The CONSULTANT shall provide input to the CMAR who is responsible for equipment 
maintenance and repair and instrument calibration during the commissioning. The 
CONSULTANT shall document its concerns and promptly notify the CMAR of all warranty 
issues. The CONSULTANT will return after correction of concerns and repairs to confirm 
work is complete and equipment is in functioning order, as intended. 
 
C. The CONSULTANT shall advise CITY operations staff as-needed on established procedures 
and monitoring requirements on new facilities. 
 
D. Major system commissioning durations shall be as identified in Table 540-1 
 
Table 540-1 Phase III Commissioning Durations 
 
System 
Duration1 
RAS Pumps 1 and 2
2 days
RAS Pumps 3 and 4
2 days
RAS Pumps 5 and 6 and 7
2 days
RAS and WAS Facilities 
5 days
UV Disinfection System and Drain Pump Station
10 days
RSPS 250 HP Pumps and Electrical Improvements
10 days
ALS Electrical System and Generator 
10 days
1. Duration of System commissioning based on a 5 day work weeks period and assumes Systems will be 
tested individually as they become available. 
 
Task 550 
Record Documents 
 
A. The CONSULTANT shall prepare Record Drawings for this Project. The Record Drawings 
shall be prepared as follows:

30001670 
B-17 
5/8/2022
 
 
 
1. CONSULTANT shall coordinate with the CMAR to obtain CMAR’s record construction 
work, including reviewing CMAR red-lined drawings, and incorporating project changes 
made through the progress of the work, on the Record Drawings. CONSULTANT shall 
make the revisions to the drawings electronically.  
 
B. The CONSULTANT shall utilize the Record Drawings to assist the CITY in receiving County 
Approvals of Construction. 
 
C. At the completion of the project, the CONSULTANT shall prepare two (1) flash drives with 
AutoCAD files and one (1) full size blackline copy and three (1) 11 x 17 copies of the Record 
Drawings will also be provided. The record specifications shall be conformed to reflect shop 
drawing submittals, substitutions, clarifications and change orders. One (1) hard copy and one 
(1) flash drive of record specifications will be prepared by the CONSULTANT and delivered 
to the CITY within 45 days from the end of the commissioning period. 
 
SECTION 600 - ALLOWANCES 
 
Task 610 Additional or Extended Services 
 
The CONSULTANT will perform additional services as determined by the CITY. An allowance 
of $34,980 has been established for this task.  
 
Task 620 
Services Involving Travel 
 
Services involving travel shall require separate specific authorization by the CITY prior to 
performing the travel. Task 620 is for services requiring out-of-town travel required by the 
CONSULTANT to witness factory tests, visit, and inspect fabrication shops or to have experts 
from the CONSULTANT'S staff visit the plant site. The CONSULTANT will prepare a written 
report of the results from the tests and/or inspection and submit to the CITY. An allowance of 
$3,000 has been established for this task.  
 
Task 630 
Special Paint/Coating Inspections 
 
The CONSULTANT shall provide a SUBCONSULTANT that is ASTM and NACE certified to 
perform special paint/coating inspections at the WAWRF facilities and architectural structures as 
defined in the Contract Documents. Subconsultant will attend the pre-job meeting to coordinate 
with paint applicators and contractor. Inspections are anticipated for Architectural steel structures 
and canopies throughout the WAWRF and administration building, mechanical piping at the UV, 
RAS Pump Station, RSPS, and ALS. Inspection services will be as needed and will include: pre-
construction surface evaluation; surface preparation and profiling; observation of applications; 
measurement of coating thickness; environmental monitoring; inspection of substrates between 
coats; and material sampling and testing. The CONSULTANT will review the CMAR's 
painting/coating schedule and have the SUBCONSULTANT onsite to observe applications and 
inspect any paintings or coatings performed by the CMAR. SUBCONSULTANT shall coordinate 
with CONTRACTOR’s Safety Officer prior to entering the confined space for inspection.

30001670 
B-18 
5/8/2022
 
 
  
The SUBCONSULTANT will verify the CMAR is applying successive coats of paint within the 
time recommended by the manufacturer based on the ambient conditions. Based upon the 
recommendation of the special paint/coating SUBCONSULTANT, the CONSULTANT shall 
recommend acceptance or rejection of the paint or coating application. An allowance of $36,465 
has been established for the special paint/coating SUBCONSULTANT. The presented allowance 
includes a 10% addition for coordination with and management of the SUBCONSULTANT.   
 
Assumptions: The following assumption(s) were used to develop the level of effort for Task 630: 
 
1. CMAR to perform all surface preparation work prior to surface evaluation. 
2. CONSULTANT and SUBCONSULTANT to operate under the CMAR’s Confined Space 
Entry permit. 
3. CMAR to provide all Confined Space Entry equipment required to safely access work 
zone. 
 
Task 640 
Concrete Inspections 
 
The CONSULTANT shall provide a SUBCONSULTANT that is a licensed structural professional 
engineer to perform concrete inspections on the UV Channel repair and wall construction and the 
foundation slab for electrical building at the ALS, as defined in the Contract Documents. Services 
also include review of CMAR material submittals. Inspection services will be as needed and will 
include: a minimum of (2) concrete inspection on the UV Channel and (1) concrete inspection on 
the ALS electrical building foundation. SUBCONSULTANT shall coordinate with CMAR’s 
Safety Officer prior to entering the confined space for inspection. SUBCONSULTANT shall 
provide Special Structural Inspections as necessary for City Building Services Department. 
 
An allowance of $39,666 has been established for the concrete inspection SUBCONSULTANT. 
The presented allowance includes a 10% addition for coordination with and management of the 
SUBCONSULTANT. 
 
Assumptions: The following assumption(s) were used to develop the level of effort for Task 640: 
 
1. CONSULTANT and SUBCONSULTANT to operate under the CMAR’s Confined Space 
Entry permit. 
2. CMAR to provide all Confined Space Entry equipment required to safely access work 
zone. 
 
Task 650 
Arc Flash Hazard Analyses 
 
The CONSULTANT will update the Arc Flash Hazard analysis for the WAWRF for the required 
5 year update, which will include the new equipment installed by the CMAR. New hazard labels 
and laminated drawings will be provided. An allowance of $21,144 has been established for this 
task. 
 
The CONSULTANT will update the Arc Flash Hazard analysis for the Raw Sewage Pump

30001670 
B-19 
5/8/2022
 
 
Station for the required 5 year update, which will include the new equipment installed by the 
CMAR. New hazard labels and laminated drawing(s) will be provided. An allowance of $11,856 
has been established for this task. 
 
The CONSULTANT will update the Arc Flash Hazard analysis for the Airport Lift Station for 
the required 5 year update, which will include the new equipment installed by the CMAR. New 
hazard labels and laminated drawing(s) will be provided. An allowance of $11,856 has been 
established for this task.

30001670 
C-1 
5/8/2022
 
 
EXHIBIT C 
Professional Services Agreement 
 
WEST AREA WATER RECLAMATION FACILITY IMPROVEMENTS 
Amendment 4 
Project No. 141525 
 
Phase III – GMP2B WAWRF Improvements Project 
UV, RAS, RSPS, and ALS Construction Administration (CA) Services  
 
SCHEDULE 
 
Engineering services shall be provided in five major tasks in accordance with the approximate 
schedule listed below. Tasks will run concurrently, as completion times are all shown in weeks 
after Notice-to-Proceed.  
 
 
Tasks 
Approximate 
Completion1 
(in weeks after 
Notice-to-Proceed)
SECTION 200: PROJECT ADMINISTRATION SERVICES DURING 
CONSTRUCTION
662 
SECTION 300: ENGINEERING SERVICES DURING 
CONSTRUCTION
40 
SECTION 
400: 
OBSERVATION 
SERVICES 
DURING 
CONSTRUCTION
403 
SECTION 500: SPECIAL SERVICES
662
SECTION 600: ALLOWANCES
662
 
Notes: 
1. Completion Schedule doesn’t include 24-month Warranty period. 
2. Completion Schedule for Sections 200, 500 and 600 account for additional time associated with Allowance 
Tasks. 
3. Section 400  assumes 5  months  of inspection at half time, and 5 months of inspection at quarter time.

30001670 
D-1 
5/8/2022 
EXHIBIT D 
Professional Services Agreement 
 
WEST AREA WATER RECLAMATION FACILITY IMPROVEMENTS 
Amendment 4 
Project No. 141525 
 
Phase III – GMP2B WAWRF Improvements Project 
UV, RAS, RSPS, and ALS Construction Administration (CA) Services  
 
COMPENSATION 
 
 
METHOD AND AMOUNT OF COMPENSATION 
 
Compensation shall be based on an hourly billing rate plus reimbursable expenses for 
CONSULTANT and all SUBCONSULTANTS. Documentation for reimbursable 
expenses must be included with each payment application. 
 
NOT-TO-EXCEED AMOUNT 
 
The total amount of compensation paid to Arcadis U.S., Inc., for completion of 
Amendment No. 4 Work, for Phase III, must not exceed $809,383. 
 
DETAILED PROJECT COMPENSATION 
 
See Page D-2 for Task and Compensation Summary.

30001670 
D-2  
5/8/2022 
EXHIBIT D 
Professional Services Agreement 
 
CITY OF GLENDALE 
WEST AREA WATER RECLAMATION FACILITY IMPROVEMENTS 
Amendment 4 
Project No. 141525 
 
Phase III – GMP2B WAWRF Improvements Project 
UV, RAS, RSPS, and ALS Construction Administration (CA) Services  
Description / Task 
Compensation 
TASK 200 – PROJECT ADMINISTRATION SERVICES DURING CONSTRUCTION 
Task 210 Representation on Behalf of the City
$153,413
Task 215 Administer the Construction Schedule
$7,524
Task 220 Perform Site Visits
$18,464
Task 230 Review Shop Drawings and Test Results
$79,410
Task 235 Issue Interpretations and Clarifications
$19,335
Task 240 Review Requests for Alterations
$11,090
Task 250 Certify Progress Payments
$6,120
Task 260 Substantial Completion and Final Acceptance Inspection
$14,668
TASK 300 – ENGINEERING SERVICES DURING CONSTRUCTION 
Task 310 Changes
$28,040
Task 320 Material Testing
$8,160
TASK 400 – OBSERVATION SERVICES DURING CONSTRUCTION 
Task 400 Observation Services
$121,770
TASK 500 – SPECIAL SERVICES 
Task 510 Warranty
$19,688
Task 520 Electronic Operations and Maintenance Manuals (EOMM)
$42,458
Task 530 Training
$19,032
Task 540 Commissioning
$61,868
Task 550 Record Documents
$39,376
Subtotal Phase III GMP2B – UV/RAS/RSPS/ALS Construction 
Administration Basic Services  
$650,416 
TASK 600 – ALLOWANCES
Task 610 Additional or Extended Services
$34,980
Task 620 Services Involving Travel
$3,000
Task 630 Special Paint/Coating Inspections
$36,465
Task 640 Concrete Inspections
$39,666
Task 650 Arc Flash Hazard Analyses
Plant Wide Analysis
$21,144
RSPS Analysis
$11,856
ALS Analysis
$11,856
Subtotal Phase III GMP2B – UV/RAS/RSPS/ALS Section 600 
Allowance Tasks 
$158,967 
GRAND TOTAL 
TOTAL PROFESSIONAL SERVICES FEE 
$809,383