WHEN RECORDED RETURN TO:
Maricopa County Real Estate Department
2801 W. Durango Street
Phoenix, AZ 85009
EXEMPT A.R.S. ยง 11-1134, A.2
JC/ AH
TEMPORARY CONSTRUCTION EASEMENT
Parcel No.:
Project No.:
Project Name:
Item No.:
219-12-051
TT0609
Tonto Hills Low Volume Roads
D24285 (JC)
This Temporary Construction Easement is entered into by and between Kurt W. Finnie, an
unmarried man, hereinafter referred to as GRANTOR, the owner of the real property situated
in Maricopa County, Arizona, which property is set forth in instrument number 20100606720
in the official records of Maricopa County (the "Burdened Property"), and Maricopa County, a
political subdivision of the State of Arizona, its assigns and successors in title or interest,
hereinafter collectively called GRANTEE.
GRANTOR hereby grants a Temporary Construction Easement ("TCE"), together with
the right and privilege of entering upon the area subject to the conditions set forth herein, on, over,
under and across that portion of the Burdened Property legally described on Exhibit "A-1" and
depicted in Exhibit "A-2" attached hereto (the "Easement Area") for the purpose of facilitating
construction of the project known as TT0609 Tonto Hills Low Volume Roads("Project").
1.
Term and Consideration. This TCE is hereby granted for the stated purpose for a
period of 12 months ("Term") which shall commence upon the written notice to the GRANTOR
by the GRANTEE. GRANTEE estimates that the period of time stated above will be sufficient
for the completion of the work within the TCE Area. GRANTEE shall provide written notification to
GRANTOR of the initiation of construction activities no less than thirty (30) calendar days in
advance of construction activities. The consideration for the use of the TCE Area is Five
Hundred and No/100 Dollars ($500.00) plus an additional One Thousand Nine Hundred
Sixty-Four and No/100 Dollars ($1,964.00) for the improvements in the TCE area for a
total consideration of Two Thousand Four Hundred Sixty-Four and No/100 Dollars
($2,464.00) paid by GRANTEE to GRANTOR. This consideration is for
the
full
Term
described
above.
In
the
event
GRANTEE determines that additional
construction time within the TCE Area is needed for completion of the Project, GRANTEE shall
be permitted to extend the term of this TCE by notifying the GRANTOR in writing and
issuing a payment for the additional consideration in the amount of $42.00 for each additional
month or part thereof for the required extension.