Performance Based 
Contracts
Investment Grade Audits (IGA)

Background
2
•On March 23, 2021, staff 
introduced Performance Based 
Contracting and discussed 
preliminary assessments.

Energy Saving Performance 
Contracts Process
3
Performance Contract
Includes guaranteed savings
Investment Grade Audit
Measures identified, quantified
Preliminary Assessment
Identifies locations, systems, measures
Council approval in June of 2021
Council Approval Required
We Are Here

4
Investment Grade Audit Explained

Pilot Project #1 Overview
Performance Based Contracts

Project #1 Preliminary 
Assessment (2021)
6
• Foothills Library
– FY22 CIP has $225,000 for HVAC
• Main Library
– FY23 CIP has $1,000,000
• Park Lighting
Conversion Cost
$2,065,255
Capital Replacement 
Cost Savings
$1,225,000
Conversion less 
capital contribution
$840,255
Annual Energy 
Savings
$200,066
Payback
4.2 years
Simple Payback with Capital Contribution
Conversion Cost
$2,065,255
Annual Energy 
Savings
$200,066
Payback
10.3 years
Simple Payback without Capital Contribution

Pilot Project #1 Audit Results 
(2022)
7

8
Pilot Project #1 Audit Results 
(2022)

9
Pilot Project #1 Audit Results 
(2022)

10
Pilot Project #1 Audit Results 
(2022)

Park Lighting Example
11
Acoma Park Before LED
Acoma Park After LED

Pilot Project #1 Audit Results 
(2022)
12

13
• Foothills Library
– FY22 CIP has $225,000 for HVAC
• Main Library
– FY23 CIP has $1,308,017
– $455,00 is for the chiller
• Park Lighting
Conversion Cost
$1,842,479
Capital Replacement 
Cost Savings
$1,533,017
Conversion less 
capital contribution
$309,462
Annual Energy 
Savings
$135,710
Payback
2.3 years
Simple Payback with Capital Contribution
Conversion Cost
$1,842,479
Annual Energy 
Savings
$135,710
Payback
13.6 years
Simple Payback without Capital Contribution
Pilot Project #1 Totals (2022)

Pilot Project #2 Overview
Performance Based Contracts

Project #2 Preliminary 
Assessment (2021)
15
• HVAC:
•
Rooftop units at Advocacy Center 
& Bead Museum
•
New split system and mini-splits 
at Civic Center
•
Cooling Tower replacement  and 
variable speed chilled water 
pumping at Adult Center
• Lighting: Eleven Locations
• Solar: GRPSTC, Civic Center, FRAC, 
Adult Center
• Note – lighting from FRAC not factored 
into Capital Equipment Contribution
Conversion Cost
$5.9M
Annual Energy 
Savings
$327,000
Payback
18 years
Conversion Cost
$5.9M
Capital Equipment 
Contribution
$950,000
Conversion less 
capital contribution
$4,950,000
Annual Energy 
Savings
$327,000
Payback
15.1 years
Simple Payback
Simple Payback with Capital 
Replacement Savings

Pilot Project #2 Audit Results 
(2022)
16
Project cost - $77,561

Pilot Project #2 Audit Results 
(2022)
17
Project cost - $554,532

Pilot Project #2 Audit Results 
(2022)
18
Project cost - $560,889
Foothills Recreation & Aquatics Center

Pilot Project #2 Audit Results 
(2022)
19
Project cost - $1,279,244
Lighting Upgrade Site List

Solar Evaluation Preliminary 
Assessment (2021)
20

Solar Preliminary Assessment 
(2021)
21
Facility
System Size,
kW-dc
Yr. 1 Bill Savings
Estimated 
Conversion Cost
Payback, Years
GRPSTC
737
$73,800
Civic Center
295
$47,300
FRAC
583
$71,400
Adult Center
162
$17,600
Total
1,776
$210,100
$3,255,000
15.5

Solar Evaluation Audit Results 
(2022)
22
Facility
System Size,
kW-dc
Yr. 1 Bill Savings
Conversion Cost
Payback, Years
GRPSTC
524.9
$67,852
$2,174,872
32.05
Civic Center
182.3
$36,110
$870,020
24.09
FRAC
619.7
$79,708
$2,226,172
27.92
Adult Center
Removed
Removed
$0
Total
1,326.9
$183,670
$5,271,064
28.70

Project #2 Audit Results – Power 
ED
23
Project cost - $234,900.00

Project #2 Totals (2022)
24
• HVAC:
•
Cooling Tower replacement  and 
variable speed chilled water 
pumping at Adult Center
•
Cooling tower replacement – FRAC
•
Cooling Tower replacement – Civic 
Center
• Lighting: Eleven Locations
• Solar: GRPSTC, Civic Center, and FRAC
• Note – lighting from FRAC not factored into 
Capital Equipment Contribution
Conversion Cost
$8.2M
Annual Energy 
Savings
$342,777
Payback
23.9 years
Conversion Cost
$8.2M
Capital Equipment 
Contribution
$443,600
Conversion less 
capital contribution
$7,756,400
Annual Energy 
Savings
$342,777
Payback
22.6 years
Simple Payback
Simple Payback with Capital 
Replacement Savings

25
Total Performance Based 
Contract Summary
Preliminary 
Assessment (2021)
Investment Grade 
Audit (2022)
Project 1 and 2 total cost
$7,965,255
$10,042,479
Total Annual Energy Saving
$527,066
$478,487
Total Capital Contribution
$2,175,000
$1,976,617
Total Project Cost minus Capital 
Contribution
$5,790,255
$8,065,862
Total Payback without Capital 
Contribution
15.1 years
21 years
Total Payback with Capital 
Contribution
11 years
16.9 years

• Combining projects allows us to enhance 
savings
• Coordination goes through contractors
• Commissioning goes through contractors
• Measurement and Verification included 
26
Benefits

• Use $1,976,617 from FY23 CIP
• Program $8,065,862 to FY24 CIP*
27
Funding
*Cost of project(s) could change all the way up to contract execution

28
Consensus 
Provide consensus to continue with pilot 
projects
Formal approval at upcoming voting meeting