Agreement

City of Glendale — Regular Meeting (2022-11-22)

View PDF Item 14 Meeting page

Extracted text (via pymupdf) 250574 characters
City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
Project Name: Glendale Landfill North Cell Excavation Phase II 
Project No.: 
212261 
Amendment No: One 
Date: 
 
      
 
This Amendment to that certain Standard Form Agreement dated       by and between the City of Glendale and 
Rummel Construction, Inc. (CM@Risk) for services, deliverables and work related to Project No. 212261, Project 
Name: Glendale Landfill North Cell Excavation Phase II, (the “Agreement”) is made and entered into effective this 
      day of      , 2022. 
 
1. This Amendment #1 establishes a Guaranteed Maximum Price (“GMP”) and Construction Phase Fee for 
Construction Services and incorporates such terms into the Agreement, making the Agreement effective 
for Construction Phase Services: 
 
a. 
The total fee for Construction Phase Services, which is included in the Guaranteed Maximum Price (GMP) 
as defined under the Agreement, shall be fixed at Four Hundred Twenty-Nine Thousand Six Hundred 
Sixty-Two and 00/100 Dollars ($429,662.00).       
 
b. The Guaranteed Maximum Price (“GMP”) for Construction Services, as defined under the Agreement, shall 
be Three Million Eight Hundred Seventy-Five Thousand One Hundred Ninety-Seven and 47/100 Dollars 
($3,875,197.47).       
 
c. 
The total compensation under the Agreement, as amended by this Amendment, shall be: 
 
 
Pre-Construction Phase 
Construction Phase 
Total 
Original Agreement: 
$36,358.21 
$      
$36,358.21 
 
 
 
 
Previous Amendments: 
$      
$      
$      
 
 
 
 
This Amendment: 
$      
$3,875,197.47 
$3,875,197.47 
 
 
 
 
Total (including this 
Amendment): 
 
$36,358.21 
 
$3,875,197.47 
 
$3,911,555.68 
 
 
2. DELETE the blank template “Exhibit C – Cost of the Work – Schedule of Values” from the Agreement, 
and ADD “Exhibit C – Rummel Construction, Inc. Cost of the Work – Schedule of Values” dated October 
28, 2022 (24 Pages), attached herein. 
 
3. ADD “Exhibit E – Construction Documents necessary to define Scope of Work and deliverables for the 
Construction Phase Services, including plans, designs, drawings, specifications and other required 
Contract Documents” dated October, 22, 2022 (156 Pages), attached herein. 
 
4. ADD “Exhibit F - Statement of All Clarifications and Assumptions” dated October 28, 2022 (1 Pages), 
attached herein. 
 
5. ADD “Exhibit G – Schedule of Major Milestones” dated October 24, 2022 (1 Pages), attached herein. 
 
6. All other provisions, terms and conditions of the Agreement shall remain unchanged and in full effect. 
 
(Signature on following page)

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
IN WITNESS WHEREOF, the Parties hereto have duly executed this Amendment, effective as of the date first 
written above. 
OWNER 
CM@RISK 
City of Glendale 
Rummel Construction, Inc. 
5850 W. Glendale Avenue 
7250 East Adobe Drive 
Glendale, AZ 85301 
Scottsdale, Arizona 85255 
By: Its Authorized Representative: 
By Its Authorized Representative: 
Signature 
Signature 
Printed Name 
Printed Name 
Title 
Title 
Date 
Date 
ATTEST: 
___________________________ 
Julie K. Bower   (SEAL) 
City Clerk 
APPROVED AS TO FORM: 
___________________________ 
Michael D. Bailey 
City Attorney 
DESIGN PROFESSIONAL 
TetraTech 
22601 North 19th Avenue, Suite 225 
Phoenix, Arizona 85027 
By Its Authorized Representative: 
Signature (Reviewed in accordance with the “Agreement Between Owner and Design Professional” Section 4.8.1.14 
of Exhibit A “Scope of Services for the Design Professional”) 
Printed Name 
Title 
Date 
Dodd O'Neill
Vice President
11-07-2022
Dodd O'Neill
Digitally signed by Dodd O'Neill 
DN: cn=Dodd O'Neill, o=Rummel Construction 
Inc., ou, email=dodd@rummelconstruction.com, 
c=US 
Date: 2022.11.07 11:23:55 -07'00'

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
EXHIBIT C 
Cost of the Work 
(24 pages - final document to be included with GMP Amendment)

Glendale Municipal Landfill North Cell Excavation Phase II CMAR 
Project No. 212261 
October 28, 2022 
Submitted by Rummel Construction Inc. 
Rummel Construction Inc., serving as the Construction Manager at Risk, is providing GMP#1 for the 
Glendale Municipal Landfill North Cell Excavation Phase II. The scope of work for GMP#1 entails the 
excavation and stockpiling of material from Phase II to allow early access for landfill traffic from the 
scale house into the previously constructed Phase I Liner Cell. The GMP#2 will be generated in the future 
to complete the Phase II cell excavation. 
Exhibit C page 1/24

Rummel Construction, Inc.
CONSTRUCTION MANAGER AT RISK AGREEMENT ‐ Exhibit C ‐ Cost of the Work
Municipal Landfill North Cell Excavation Phase II CMAR ‐ Project No. 212261 ‐ October 24, 2022
DIRECT CONSTRUCTION COST
Cost Code
Item of Work
GMP No. 1
GMP No. 2 GMP No. 3 GMP No. 4 Total GMP
GENERAL CONDITIONS ‐ PERSONNEL STAFFING
171,562.00
$     
GENERAL CONDITIONS ‐ SITE OPERATIONS
63,656.58
$       
MOBILIZATION/DEMOBILIZATION
100,137.00
$     
PROJECT SURVEY
35,000.00
$       
AZPDES/SWPPP
8,026.00
$         
TRAFFIC CONTROL
5,000.00
$         
EXCAVATE, HAUL & STOCKPILE TO NORTH CELL
1,025,015.00
$  
EXCAVATE, HAUL & STOCKPILE TO SOUTH CELL
527,913.00
$     
GENERAL FILL FOR HAUL ROADS
174,492.00
$     
HAUL, PLACE & MAINTAIN AC MILLINGS
72,965.00
$       
SAFETY BARRIERS
123,767.00
$     
RIPRAP V‐DITCH
74,826.00
$       
RIPRAP SPLASH PAD
4,723.00
$         
STORMWATER CROSSINGS
34,525.00
$       
RELOCATE ASPHALT MILLINGS
22,096.00
$       
CONTINGENCIES
CONTRACTOR
86,400.00
$       
OWNER
583,390.00
$     
SUBTOTAL DIRECT CONSTRUCTION COST (DCC)
3,113,493.58
$  
CONSTRUCTION PHASE FEE
FEE
FIXED FEE, EQUAL TO 13.8% OF DCC
429,662.00
$     
* Fee = 8.02% for Overhead and 5.78% for Profit
SUBTOTAL CONSTRUCTION PHASE FEE
429,662.00
$     
INDIRECT CONSTRUCTION COSTS (ICC)
BONDS
CMR PERFORMANCE & PAYMENT BOND 1.5%
53,147.00
$       
INSURANCE
CMR INSURANCES (WORKER'S COMP, GENERAL LIABILITY, 
AUTO LIABILITY, UMBRELLA) 1.2%
42,518.00
$        
BUILDER'S RISK 0.5%
17,716.00
$       
TAXES
5.98% OF (DCC + FEE + BOND + INSURANCE)
218,660.89
$     
SUBTOTAL INDIRECT CONSTRUCTION COST (ICC)
332,041.89
$     
TOTAL GMP = DCC + FEE + ICC
3,875,197.47
$  
Exhibit C
Exhibit C page 2/24

Calculation for Rummel Construction Overhead & Profit (Fee Amount)
Audited Overhead (see attached)
9.22%
Deduct Insurance of 1.2% (from GMP line item)
‐1.20%
Subtotal Overhead Cost
8.02%
Rummel Construction Profit
5.78%
Rummel Construction Overhead & Profit
13.80%
Exhibit C page 3/24

Exhibit C page 4/24

Exhibit C page 5/24

Exhibit C page 6/24

Exhibit C page 7/24

Direct Cost Contingencies
Extended
Description of Cost
QTY
UOM
Unit Cost
Direct Cost
CONTRACTOR CONTINGENCIES
TOPO VERIFICATION ‐ QUANTITY ADJUSTMENTS                 
(5% EXCAVATION)
1 
LS
86,400.00
 
86,400.00
       
TOTAL CONTRACTOR CONTINGENCIES
1
                
LS
86,400.00
OWNER CONTINGENCIES
GROUTING RIPRAP DITCHES
2,731
        
LF
20.00
           
54,620.00
      
WATER VALVE VAULTS
3
                
EA
10,000.00
 
30,000.00
      
AC PAVING OF NW CORNER/SWITCHBACK/CORNER
6,750
        
SY
36.00
           
243,000.00
FUEL ESCALATION
1
                
AL
100,000.00
100,000.00
OWNER  CONTINGENCY 5% of DCC
1
                
LS
155,770.00
155,770.00
OWNER CONTINGENCIES
583,390.00
   
TOTAL CONTINGENCIES
669,790.00
   
Exhibit C Contingencies
Exhibit C page 8/24

Bid Item Direct Cost Breakdown
Extended
Description of Cost
QTY
UOM Unit Cost
Direct Cost
1 MOBILIZATION/DEMOBILIZATION
1
                
LS
100,137.00
  
100,137.00
        
2 PROJECT SURVEY
1
                
LS
35,000.00
     
35,000.00
          
3 AZPDES/SWPPP
1
                
LS
8,026.00
       
8,026.00
            
4 TRAFFIC CONTROL (MISC SIGNS)
1
                
LS
5,000.00
       
5,000.00
            
5 EXCAVATE, HAUL & STOCKPILE TO NORTH CELL
353,725
    
CY
2.90
               
1,025,015.00
    
6 EXCAVATE, HAUL & STOCKPILE TO SOUTH CELL
74,618
      
CY
7.07
               
527,913.00
        
7 GENERAL FILL FOR HAUL ROADS
46,292
      
CY
3.77
               
174,492.00
        
8 HAUL, PLACE & MAINTAIN AC MILLINGS
189,630
    
SF
0.38
               
72,965.00
          
9 SAFETY BARRIERS
1,860
        
LF
66.54
             
123,767.00
        
10 RIPRAP V‐DITCH
2,731
        
LF
27.40
             
74,826.00
          
11 RIPRAP SPLASH PAD
1
                
EA
4,723.00
       
4,723.00
            
12 STORMWATER CROSSINGS
1
                
EA
34,525.00
     
34,525.00
          
13 RELOCATE ASPHALT MILLINGS
9,507
        
CY
2.32
               
22,096.00
          
TOTAL DIRECT COST
2,208,485.00
$ 
Exhibit C Direct Cost Breakdown
Exhibit C page 9/24

General Conditions Breakdown
Extended
Description of Cost
QTY
UOM
Unit Cost
Direct Cost
GENERAL CONDITIONS ‐ PERSONNEL STAFFING
PROJECT SUPERVISION
4
             
MO
42,890.50
    
171,562.00
  
171,562.00
  
GENERAL CONDITIONS ‐ SITE OPERATIONS
KLEIN TANKS/STORAGE CONTAINERS
3.5
         
MO
2,477.14
       
8,670.00
       
GPS EQUIPMENT
3.5
         
MO
6,000.00
       
21,000.00
     
SAFETY SUPPLIES/J‐JOHNS/LATHE/ETC
3.5
         
MO
8,285.71
       
29,000.00
     
SITE SPECIFIC HEALTH & SAFETY PLAN
1
             
LS
2,889.45
       
2,889.45
       
ON‐SITE FUEL STORAGE & CONTAINMENT
1
             
LS
2,097.13
       
2,097.13
       
SITE OPERATIONS
63,656.58
$   
Exhibit C General Conditions
Exhibit C page 10/24

Rummel Construction, Inc.
Page 1
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=       100
Land Item       SCHEDULE:
1
100
Description =
GENERAL CONDITIONS - PERSONNEL STAFFING
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
140-00
Project Supervision
Quan:
80.00 S
Hrs/Shft:
8.00
Cal: 508 WC: NOUSE
**Unreviewed
LA-SUP
(Mod) Project Supervision
640.00
CH
Prod:
80.0000 S
Lab Pcs:
3.00
Eqp Pcs:
3.00
8TKPUPE
Project Engineer Picku
1.00
640.00 HR
14.250
9,120
9,120
8TKPUPM
Project Manager Pickup
0.50
320.00 HR
14.250
4,560
4,560
8TKPUS
Superintendent Pickup
1.00
640.00 HR
14.250
9,120
9,120
8TKPUSM
Safety Manager Pickup
0.50
320.00 HR
14.250
4,560
4,560
ZE10
Project Engineer
1.00
640.00 MH *
62.450
39,968
39,968
ZPM1
Project Manager
0.50
320.00 MH *
95.920
30,694
30,694
ZS01
Superintendent
1.00
640.00 MH *
83.680
53,555
53,555
ZSM1
Safety Manager
0.50
320.00 MH *
62.450
19,984
19,984
$171,561.60
24.0000 MH/S
1,920.00 MH
[ 1802.52 ]
144,202
27,360
171,562
0.1250
Units/Hr
268.0650 $/CrewHr
80.0000 Shifts
*
1,802.52
342.00
2,144.52
=====>
Item Totals:
       100
- GENERAL CONDITIONS - PERSONNEL STAFFING
$171,561.60
1,920.0000 MH/LS
1,920.00 MH
[ 144201.6 ]
144,202
27,360
171,562
171,561.600
         1 LS
144,201.60
27,360.00
171,561.60
BID ITEM
=       200
Land Item       SCHEDULE:
1
100
Description =
GENERAL CONDITIONS - SITE OPERATIONS
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
130-00
Safety and Supplies
Quan:
1.00 LS
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
6SAFETY
Safety and Supplies
1.00
1.00 LS
29,000.000
29,000
29,000
$29,000.00
[  ]
29,000
29,000
29,000.00
29,000.00
130-02
H&S Plan
Quan:
1.00 LS
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
8TKPUSM
==> Safety Manager Pickup 1.00
45.00 HR
14.250
641
641
ZSM1
==> Safety Manager
1.00
45.00 MH *
49.960
2,248
2,248
$2,889.45
45.0000 MH/LS
45.00 MH
[ 2248.2 ]
2,248
641
2,889
2,248.20
641.25
2,889.45
150-00
Misc. Equipment Costs
Quan:
70.00 S
Hrs/Shft:
8.00
Cal: 508 WC: NOUSE
**Unreviewed
MIKLEI
(Mod) Klein Tank / Conex
560.00
CH
Prod:
70.0000 S
Lab Pcs:
0.00
Eqp Pcs:
7.00
3METER
meter
1.00
1.00 LS
250.000
250
250
3PIPE
Pipe
1.00
1.00 LS
1,000.000
1,000
1,000
8YKLEIN
Klein Water Tower
2.00
1,120.00 HR
6.000
6,720
6,720
8YSC
Storage Containers
5.00
2,800.00 HR
0.250
700
700
$8,670.00
[  ]
1,250
7,420
8,670
0.1250
Units/Hr
13.2500 $/CrewHr
70.0000 Shifts
*
17.86
106.00
123.86
155-01
Fuel Storage Containment
Quan:
1.00 EA
Hrs/Shft:
8.00
Cal: 508 WC: NOUSE
**Unreviewed
ECFCLN
Fuel Containment Liner
4.00
CH
Prod:
4.0000 HU
Lab Pcs:
5.00
Eqp Pcs:
1.00
3PFCLNR
Fuel Containment Liner
1.00
2,100.00 SF
0.650
1,365
1,365
8LDGT
JD210 / Case 570 Ganno
1.00
4.00 HR
38.500
154
154
LACMN
Laborer, Common
4.00
16.00 MH *
27.385
438
438
OPGEN
Operator, General
1.00
4.00 MH *
34.993
140
140
$2,097.13
20.0000 MH/EA
20.00 MH
[ 475 ]
578
1,365
154
2,097
0.2500
Units/Hr
183.0325 $/CrewHr
0.5000 Shifts
578.13
1,365.00
154.00
2,097.13
Exhibit C page 11/24

Rummel Construction, Inc.
Page 2
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=       200
Land Item       SCHEDULE:
1
100
Description =
GENERAL CONDITIONS - SITE OPERATIONS
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
205-10
GPS Equipment
Quan:
70.00 S
Hrs/Shft:
8.00
Cal: 508 WC: NOUSE
**Unreviewed
excavation duration + finish grade = total shifts
MIGPS
(Mod) GPS Equipmnet
560.00
CH
Prod:
70.0000 S
Lab Pcs:
0.00
Eqp Pcs:
6.00
8SRVYBS
GPS Base Station
1.00
560.00 HR
4.000
2,240
2,240
8SRVYMC
GPS Machine Control
3.00
1,680.00 HR
8.500
14,280
14,280
8SRVYRV
GPS Rover
2.00
1,120.00 HR
4.000
4,480
4,480
$21,000.00
[  ]
21,000
21,000
0.1250
Units/Hr
37.5000 $/CrewHr
70.0000 Shifts
*
300.00
300.00
=====>
Item Totals:
       200
- GENERAL CONDITIONS - SITE OPERATIONS
$63,656.58
65.0000 MH/LS
65.00 MH
[ 2723.2 ]
2,826
31,615
29,215
63,657
63,656.580
         1 LS
2,826.33
31,615.00 29,215.25
63,656.58
BID ITEM
=       300
CLIENT# = 1
Land Item       SCHEDULE:
1
100
Description =
MOBILIZATION/DEMOBILIZATION
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
---------- Mobilization Load Calculator ----------
Legal Mobilization
Equipment
Qty    Trips
Total
Backhoes
1
2
2
D6 Dozer
1
2
2
308 Excavator
0
1
0
320 Excavator
2
2
4
950 Loader
1
2
2
966 Loader
0
1
0
Gannon Tractors
1
2
2
14 Motorgrader
3
2
6
140 Motorgrader
0
1
0
16 Motorgrader
0
1
0
160 Motorgrader
0
1
0
613 Scraper
0
1
0
Ag Tractor
0
1
0
Implements - Bee Gee, Discs  0
1
0
5K Waterpull
0
1
0
Water Truck - 2K
0
1
0
Water Truck - 4K
2
2
4
Hurricane Pumps
0
1
0
Klein Tank
1
2
2
Connex Boxes
2
2
4
HDPE Pipe
0
1
0
Attachments (from Heavy)     0
1
0
Misc.
6
2
12
Total Legal Loads
40
Oversize Mobilization
Equipment
Qty    Trips
Total
D8 Dozer
0
1
0
623 Scraper
2
4
8
627 Scraper
0
1
0
8K Waterpull
3
2
6
336 Excavator
0
1
0
740 / 475 Articulated Truck  0
1
0
Crusher
0
1
0
815 Compactor
0
1
0
Exhibit C page 12/24

Rummel Construction, Inc.
Page 3
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=       300
CLIENT# = 1
Land Item       SCHEDULE:
1
100
Description =
MOBILIZATION/DEMOBILIZATION
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
Total Oversize Loads
14
Oversize Heavy Mobilization
Equipment
Qty    Number of one way trips  Total
D10 Dozer
0
1
0
D9 Dozer
1
2
2
657 Scraper
0
1
0
637 Scraper
16     2
32
631 Scraper
0
1
0
988 Loader
0
1
0
349 Excavator
0
1
0
374 Excavator
0
1
0
773 Rigid Frame Truck
0
1
0
Total Oversize Heavy Loads
34
Total Equipment Prep Hours   2
Total Equipment Prep Cost    $394
------------------ End Assembly ------------------
190-10-02
Mobilization - Legal Move
Quan:
40.00 LDS Hrs/Shft:
8.00
Cal: 508 WC: NOUSE
**Unreviewed
MOBRUM
Mobilization Rumco
200.00
CH
Prod:
5.0000 HU
Lab Pcs:
1.00
Eqp Pcs:
1.00
6MBRUM
RUMCO Mob Outside Esc
1.00
40.00 EA
25.000
1,000
1,000
8LBLB
Truck and Trailer
1.00
200.00 HR
88.365
17,673
17,673
DRTP
Driver, Transport Low Boy 1.00
200.00 MH *
37.730
7,546
7,546
$26,219.02
5.0000 MH/LDS
200.00 MH
[ 155 ]
7,546
1,000
17,673
26,219
0.2000
Units/Hr
126.0951 $/CrewHr
25.0000 Shifts
188.65
25.00
441.83
655.48
190-10-03
Mobilization - Oversize Move
Quan:
14.00 LDS Hrs/Shft:
8.00
Cal: 508 WC: NOUSE
**Unreviewed
MOBLGL
Mobilization Legal
70.00
CH
Prod:
5.0000 HU
Lab Pcs:
1.00
Eqp Pcs:
2.00
6MBLGL
Legal Mob Outside Esc
1.00
14.00 EA
74.000
1,036
1,036
8LBJEEP
Jeep Trailer
1.00
70.00 HR
15.000
1,050
1,050
8LBLB
Truck and Trailer
1.00
70.00 HR
88.365
6,186
6,186
DRTP
Driver, Transport Low Boy 1.00
70.00 MH *
37.730
2,641
2,641
$10,912.66
5.0000 MH/LDS
70.00 MH
[ 155 ]
2,641
1,036
7,236
10,913
0.2000
Units/Hr
141.0951 $/CrewHr
8.7500 Shifts
188.65
74.00
516.83
779.48
190-10-04
Mobilization - Oversize-Heavy Move
Quan:
34.00 LDS Hrs/Shft:
8.00
Cal: 508 WC: NOUSE
**Unreviewed
MOBOVS
Mobilization Oversize
204.00
CH
Prod:
6.0000 HU
Lab Pcs:
3.00
Eqp Pcs:
5.00
6MBOVR
Oversize Mob Outside Esc
1.00
34.00 EA
100.000
3,400
3,400
8LBBOOS
Booster Trailer
1.00
204.00 HR
15.000
3,060
3,060
8LBJEEP
Jeep Trailer
1.00
204.00 HR
15.000
3,060
3,060
8LBLB
Truck and Trailer
1.00
204.00 HR
88.365
18,026
18,026
8LBPILOT
Lowbed Pilot Car
2.00
408.00 HR
14.490
5,912
5,912
DRPI
Driver, Pilot Car
2.00
408.00 MH *
29.210
11,918
11,918
DRTP
Driver, Transport Low Boy 1.00
204.00 MH *
37.730
7,697
7,697
$53,073.16
18.0000 MH/LDS
612.00 MH
[ 474 ]
19,615
3,400
30,058
53,073
0.1667
Units/Hr
243.4959 $/CrewHr
25.5000 Shifts
576.91
100.00
884.07
1,560.98
190-10-07
Mobilization Equipment Setup/Takedown
Quan:
2.00 H
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
MECH
Mech Transport Break
2.00
CH
Prod:
1.0000 HU
Lab Pcs:
3.00
Eqp Pcs:
2.00
8LD980
Cat 980 Wheel Loader (
1.00
2.00 HR
152.795
319
319
8ZMECHTRK
Mechanics Truck
1.00
2.00 HR
23.756
48
48
MECH
Mechanic
1.00
2.00 MH *
40.165
80
80
MECHHELP
Mechanic Helper
1.00
2.00 MH *
30.795
62
62
Exhibit C page 13/24

Rummel Construction, Inc.
Page 4
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=       300
CLIENT# = 1
Land Item       SCHEDULE:
1
100
Description =
MOBILIZATION/DEMOBILIZATION
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
OPLDR
Operator, Loader
1.00
2.00 MH *
40.835
82
82
$589.88
3.0000 MH/H
6.00 MH
[ 91.85 ]
224
366
590
1.0000
Units/Hr
294.9400 $/CrewHr
0.2000 Shifts
111.80
183.15
294.94
970-61
Pothole Exploration
Quan:
1.00 S
Hrs/Shft:
8.00
Cal: 508 WC: NOUSE
**Unreviewed
4POTHOLE
Pothole / Softdig Sub
1.00
8.00 HR
300.000
2,400
2,400
$2,400.00
[  ]
2,400
2,400
2,400.00
2,400.00
151-02
Clean Up / Miscellaneous
Quan:
1.00 S
Hrs/Shft:
8.00
Cal: 508 WC: NOUSE
**Unreviewed
MICU
Clean Up / Miscellaneous
24.00
CH
Prod:
3.0000 S
Lab Pcs:
4.00
Eqp Pcs:
3.00
7SWEEP
Sweeping Services
1.00
8.00 HR
110.000
880
880
8LDGT
JD210 / Case 570 Ganno
1.00
24.00 HR
38.500
924
924
8TKPU
Foreman pickup
1.00
24.00 HR
14.250
342
342
8WTK4
4,000 gal Water Truck
1.00
24.00 HR
55.000
1,320
1,320
LACMN
Laborer, Common
1.00
24.00 MH *
27.385
657
657
OPGEN
Operator, General
1.00
24.00 MH *
34.992
840
840
OPWT
Operator, Water Truck
1.00
24.00 MH *
34.079
818
818
ZFM1
General Foreman
1.00
24.00 MH *
48.398
1,162
1,162
$6,942.48
96.0000 MH/S
96.00 MH
[ 2826 ]
3,476
880
2,586
6,942
0.0417
Units/Hr
252.6033 $/CrewHr
3.0000 Shifts
*
3,476.48
880.00
2,586.00
6,942.48
=====>
Item Totals:
       300
- MOBILIZATION/DEMOBILIZATION
$100,137.20
984.0000 MH/LS
984.00 MH
[ 27495.7 ]
33,502
6,316
57,919
2,400
100,137
100,137.200
         1 LS
33,501.98
6,316.00 57,919.22 2,400.00 100,137.20
BID ITEM
=       400
CLIENT# = 2
Land Item       SCHEDULE:
1
100
Description =
PROJECT SURVEY
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
970-46
PROJECT SURVEY
Quan:
1.00 LS
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
7SURVEY
Survey Sub
1.00
1.00 LS
35,000.000
35,000
35,000
$35,000.00
[  ]
35,000
35,000
35,000.00
35,000.00
=====>
Item Totals:
       400
- PROJECT SURVEY
$35,000.00
[  ]
35,000
35,000
35,000.000
         1 LS
35,000.00
35,000.00
BID ITEM
=       500
CLIENT# = 3
Land Item       SCHEDULE:
1
100
Description =
AZPDES/SWPPP
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
120-00
Air Quality/Dust Control Permit
Quan:
1.00 LS
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
6DUST
Dust Control Permit
1.00
1.00 LS
3,855.000
3,855
3,855
$3,855.00
[  ]
3,855
3,855
3,855.00
3,855.00
120-02
NOI Permit
Quan:
1.00 LS
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
6NOICG
Construction General - NOI 1.00
1.00 EA
350.000
350
350
$350.00
[  ]
350
350
Exhibit C page 14/24

Rummel Construction, Inc.
Page 5
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=       500
CLIENT# = 3
Land Item       SCHEDULE:
1
100
Description =
AZPDES/SWPPP
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
350.00
350.00
810-12
SWPPP Plans
Quan:
1.00 LS
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
8TKPUPE
==> Project Engineer Picku 1.00
40.00 HR
14.250
570
570
ZE10
==> Project Engineer
1.00
40.00 MH *
49.960
1,998
1,998
$2,568.40
40.0000 MH/LS
40.00 MH
[ 1998.4 ]
1,998
570
2,568
1,998.40
570.00
2,568.40
810-16
SWPPP Inspections Etc.
Quan:
3.00 MOS Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
4SWPPP
SWPPP Inspections
1.00
3.00 MO
417.500
1,253
1,253
$1,252.50
[  ]
1,253
1,253
417.50
417.50
=====>
Item Totals:
       500
- AZPDES/SWPPP
$8,025.90
40.0000 MH/LS
40.00 MH
[ 1998.4 ]
1,998
4,205
570
1,253
8,026
8,025.900
         1 LS
1,998.40
4,205.00
570.00 1,252.50
8,025.90
BID ITEM
=       600
CLIENT# = 4
Land Item       SCHEDULE:
1
100
Description =
TRAFFIC CONTROL
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
701-00
Traffic Control - Sign Allowance
Quan:
1.00 LS
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
7TRAFFIC
Traffic Control Sub
1.00
1.00 LS
5,000.000
5,000
5,000
$5,000.00
[  ]
5,000
5,000
5,000.00
5,000.00
=====>
Item Totals:
       600
- TRAFFIC CONTROL
$5,000.00
[  ]
5,000
5,000
5,000.000
         1 LS
5,000.00
5,000.00
BID ITEM
=       700
CLIENT# = 5
Land Item       SCHEDULE:
1
100
Description =
EXCAVATE, HAUL & STOCKPILE TO NORTH CELL
Unit =
CY
Takeoff Quan:
353,725.000
Engr Quan: 353,725.000
203-00-54
Top Half of Cut
Quan: 176,863.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FPC = 5.5
50 / 5.5 = 9 rnds/hour
9*21*8 scrapers = 1512 cy per hour
8*21*8 = 1344
EXS378
(Mod) Excavation Scraper 637-8
131.59
CH
Prod: 1,344.0000 UH
Lab Pcs:
17.00
Eqp Pcs:
17.00
8DZ06
Cat D6/D6T/D6R2 Dozer
1.00
131.59 HR
108.500
14,278
14,278
8DZ09
Cat D9T Dozer (405 hp)
1.00
131.59 HR
225.000
29,608
29,608
8MG14
Cat 14 Motorgrader
2.00
263.19 HR
110.500
29,082
29,082
8SC637
Cat 637 Scraper
8.00
1,052.76 HR
260.000
273,718
273,718
8WP08K
8000 GAL WATER PULL 3.00
394.78 HR
123.000
48,558
48,558
8YGATOR
UTV Gator / Kubota
2.00
263.19 HR
6.000
1,579
1,579
LAGCK
Laborer, Grade Checker
2.00
263.19 MH *
41.838
11,011
11,011
OPBLD
Operator, Finish Motorgrad 2.00
263.19 MH *
49.536
13,037
13,037
OPDZR
Operator, Dozer
2.00
263.19 MH *
42.172
11,099
11,099
OPSCR
Operator, Scraper
8.00
1,052.76 MH *
40.834
42,988
42,988
OPWP
Operator, Waterpull
3.00
394.78 MH *
39.495
15,592
15,592
$490,550.30
0.0126 MH/CY
2,237.11 MH
[ 0.435 ]
93,728
396,822
490,550
Exhibit C page 15/24

Rummel Construction, Inc.
Page 6
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=       700
CLIENT# = 5
Land Item       SCHEDULE:
1
100
Description =
EXCAVATE, HAUL & STOCKPILE TO NORTH CELL
Unit =
CY
Takeoff Quan:
353,725.000
Engr Quan: 353,725.000
1,344.0459
Units/Hr
*
3,727.8691 $/CrewHr
13.1590 Shifts
0.53
2.24
2.77
203-00-54A
Bottom Half of Cut
Quan: 176,862.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FPC = 6.6
50 / 6.6 = 7.5 rnds/hour
7.5*21*8 scrapers = 1260 cy per hour
EXS378
(Mod) Excavation Scraper 637-8
140.36
CH
Prod: 1,260.0006 UH
Lab Pcs:
17.00
Eqp Pcs:
17.00
8DZ06
Cat D6/D6T/D6R2 Dozer
1.00
140.37 HR
108.500
15,230
15,230
8DZ09
Cat D9T Dozer (405 hp)
1.00
140.37 HR
225.000
31,583
31,583
8MG14
Cat 14 Motorgrader
2.00
280.73 HR
110.500
31,021
31,021
8SC637
Cat 637 Scraper
8.00
1,122.93 HR
260.000
291,962
291,962
8WP08K
8000 GAL WATER PULL 3.00
421.10 HR
123.000
51,795
51,795
8YGATOR
UTV Gator / Kubota
2.00
280.73 HR
6.000
1,684
1,684
LAGCK
Laborer, Grade Checker
2.00
280.73 MH *
41.838
11,745
11,745
OPBLD
Operator, Finish Motorgrad 2.00
280.73 MH *
49.536
13,906
13,906
OPDZR
Operator, Dozer
2.00
280.73 MH *
42.173
11,839
11,839
OPSCR
Operator, Scraper
8.00
1,122.93 MH *
40.834
45,853
45,853
OPWP
Operator, Waterpull
3.00
421.10 MH *
39.495
16,631
16,631
$523,250.61
0.0134 MH/CY
2,386.22 MH
[ 0.464 ]
99,975
423,275
523,251
1,260.0598
Units/Hr
*
3,727.9183 $/CrewHr
14.0360 Shifts
0.57
2.39
2.96
205-04
Finish Temporary Basins
Quan:
5,554.00 SY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FIN140
Finish Grade
10.00
CH
Prod:
555.4000 UH
Lab Pcs:
4.00
Eqp Pcs:
4.00
8MG150
Cat 150 Motorgrader (I
1.00
10.00 HR
97.000
970
970
8SC623
Cat 623 Scraper
1.00
10.00 HR
149.000
1,490
1,490
8WP08K
8000 GAL WATER PULL 1.00
10.00 HR
123.000
1,230
1,230
8YGATOR
UTV Gator / Kubota
1.00
10.00 HR
6.000
60
60
LAGCK
Laborer, Grade Checker
1.00
10.00 MH *
41.838
418
418
OPBLD
Operator, Finish Motorgrad 1.00
10.00 MH *
49.536
495
495
OPSCR
Operator, Scraper
1.00
10.00 MH *
40.834
408
408
OPWP
Operator, Waterpull
1.00
10.00 MH *
39.495
395
395
$5,467.03
0.0072 MH/SY
40.00 MH
[ 0.254 ]
1,717
3,750
5,467
555.4000
Units/Hr
*
546.7030 $/CrewHr
1.0000 Shifts
0.31
0.68
0.98
205-04A
Finish Areas around basins
Quan:
3,467.00 SY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FIN140
Finish Grade
5.00
CH
Prod:
693.4000 UH
Lab Pcs:
4.00
Eqp Pcs:
4.00
8MG150
Cat 150 Motorgrader (I
1.00
5.00 HR
97.000
485
485
8SC623
Cat 623 Scraper
1.00
5.00 HR
149.000
745
745
8WP08K
8000 GAL WATER PULL 1.00
5.00 HR
123.000
615
615
8YGATOR
UTV Gator / Kubota
1.00
5.00 HR
6.000
30
30
LAGCK
Laborer, Grade Checker
1.00
5.00 MH *
41.838
209
209
OPBLD
Operator, Finish Motorgrad 1.00
5.00 MH *
49.536
248
248
OPSCR
Operator, Scraper
1.00
5.00 MH *
40.834
204
204
OPWP
Operator, Waterpull
1.00
5.00 MH *
39.494
197
197
$2,733.50
0.0057 MH/SY
20.00 MH
[ 0.203 ]
859
1,875
2,734
693.4000
Units/Hr
*
546.7000 $/CrewHr
0.5000 Shifts
0.25
0.54
0.79
205-05
Trackwalk Slopes
Quan: 15,375.00 SY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FINTW
Trackwalk Slopes
20.00
CH
Prod:
768.7500 UH
Lab Pcs:
1.00
Eqp Pcs:
1.00
8DZ06
Cat D6/D6T/D6R2 Dozer
1.00
20.00 HR
108.500
2,170
2,170
OPDZR
Operator, Dozer
1.00
20.00 MH *
42.173
843
843
$3,013.45
0.0013 MH/SY
20.00 MH
[ 0.045 ]
843
2,170
3,013
768.7500
Units/Hr
*
150.6725 $/CrewHr
2.0000 Shifts
0.05
0.14
0.20
=====>
Item Totals:
       700
- EXCAVATE, HAUL & STOCKPILE TO NORTH CELL
Exhibit C page 16/24

Rummel Construction, Inc.
Page 7
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=       700
CLIENT# = 5
Land Item       SCHEDULE:
1
100
Description =
EXCAVATE, HAUL & STOCKPILE TO NORTH CELL
Unit =
CY
Takeoff Quan:
353,725.000
Engr Quan: 353,725.000
$1,025,014.89
0.0132 MH/CY
4,703.33 MH
[ 0.458 ]
197,122
827,893
1,025,015
2.898
         353725 CY
0.56
2.34
2.90
BID ITEM
=       800
CLIENT# = 6
Land Item       SCHEDULE:
1
100
Description =
EXCAVATE, HAUL & STOCKPILE TO SOUTH CELL
Unit =
CY
Takeoff Quan:
74,618.000
Engr Quan:
74,618.000
203-00-52
Excavation Scraper 637-4
Quan: 74,618.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FPC =12.3
50/12.3 = 4 rnds per hour
4x4x21 = 336
EXS374
(Mod) Excavation Scraper 637-4
270.00
CH
Prod:
276.3630 UH
Lab Pcs:
10.00
Eqp Pcs:
10.00
8MG14
Cat 14 Motorgrader
2.00
540.00 HR
110.500
59,670
59,670
8SC637
Cat 637 Scraper
4.00
1,080.00 HR
260.000
280,800
280,800
8WP08K
8000 GAL WATER PULL 2.00
540.00 HR
123.000
66,420
66,420
8YGATOR
UTV Gator / Kubota
2.00
540.00 HR
6.000
3,240
3,240
LAGCK
Laborer, Grade Checker
2.00
540.00 MH *
41.838
22,592
22,592
OPBLD
Operator, Finish Motorgrad 2.00
540.00 MH *
49.536
26,749
26,749
OPSCR
Operator, Scraper
4.00
1,080.00 MH *
40.834
44,100
44,100
OPWP
Operator, Waterpull
2.00
540.00 MH *
39.495
21,327
21,327
$524,899.48
0.0361 MH/CY
2,700.00 MH
[ 1.264 ]
114,769
410,130
524,899
276.3630
Units/Hr
*
1,944.0721 $/CrewHr
27.0000 Shifts
1.54
5.50
7.03
205-05
Trackwalk Slopes
Quan:
8,812.00 SY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FINTW
Trackwalk Slopes
20.00
CH
Prod:
440.6000 UH
Lab Pcs:
1.00
Eqp Pcs:
1.00
8DZ06
Cat D6/D6T/D6R2 Dozer
1.00
20.00 HR
108.500
2,170
2,170
OPDZR
Operator, Dozer
1.00
20.00 MH *
42.173
843
843
$3,013.45
0.0022 MH/SY
20.00 MH
[ 0.079 ]
843
2,170
3,013
440.6000
Units/Hr
*
150.6725 $/CrewHr
2.0000 Shifts
0.10
0.25
0.34
=====>
Item Totals:
       800
- EXCAVATE, HAUL & STOCKPILE TO SOUTH CELL
$527,912.93
0.0364 MH/CY
2,720.00 MH
[ 1.273 ]
115,613
412,300
527,913
7.075
         74618 CY
1.55
5.53
7.07
BID ITEM
=      1000
CLIENT# = 7
Land Item       SCHEDULE:
1
100
Description =
GENERAL FILL FOR HAUL ROADS
Unit =
CY
Takeoff Quan:
46,292.000
Engr Quan:
46,292.000
203-00-21
Excavation Scraper 623-1
Quan:
2,580.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
EXS231
(Mod) Excavation Scraper 623-1
30.00
CH
Prod:
86.0000 UH
Lab Pcs:
5.00
Eqp Pcs:
5.00
8DZ06
Cat D6/D6T/D6R2 Dozer
1.00
30.00 HR
108.500
3,255
3,255
8MG150
Cat 150 Motorgrader (I
1.00
30.00 HR
97.000
2,910
2,910
8SC623
Cat 623 Scraper
1.00
30.00 HR
149.000
4,470
4,470
8WP08K
8000 GAL WATER PULL 1.00
30.00 HR
123.000
3,690
3,690
8YGATOR
UTV Gator / Kubota
1.00
30.00 HR
6.000
180
180
LAGCK
Laborer, Grade Checker
1.00
30.00 MH *
41.838
1,255
1,255
OPBLD
Operator, Finish Motorgrad 1.00
30.00 MH *
49.536
1,486
1,486
OPDZR
Operator, Dozer
1.00
30.00 MH *
42.173
1,265
1,265
OPSCR
Operator, Scraper
1.00
30.00 MH *
40.834
1,225
1,225
OPWP
Operator, Waterpull
1.00
30.00 MH *
39.495
1,185
1,185
$20,921.25
0.0581 MH/CY
150.00 MH
[ 2.043 ]
6,416
14,505
20,921
86.0000
Units/Hr
*
697.3750 $/CrewHr
3.0000 Shifts
2.49
5.62
8.11
Exhibit C page 17/24

Rummel Construction, Inc.
Page 8
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=      1000
CLIENT# = 7
Land Item       SCHEDULE:
1
100
Description =
GENERAL FILL FOR HAUL ROADS
Unit =
CY
Takeoff Quan:
46,292.000
Engr Quan:
46,292.000
203-00-52
Excavation Scraper 637-4
Quan: 43,712.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
10 rnds/hour @ 21 = 210/hour/scraper
EXS374
(Mod) Excavation Scraper 637-4
52.03
CH
Prod:
840.0000 UH
Lab Pcs:
13.00
Eqp Pcs:
13.00
8DZ06
Cat D6/D6T/D6R2 Dozer
1.00
52.04 HR
108.500
5,646
5,646
8DZ09
Cat D9T Dozer (405 hp)
1.00
52.04 HR
225.000
11,709
11,709
8MG14
Cat 14 Motorgrader
2.00
104.08 HR
110.500
11,501
11,501
8RCVS
Cat CS54 Vib Steel Rol
1.00
52.04 HR
47.466
2,580
2,580
8SC637
Cat 637 Scraper
4.00
208.15 HR
260.000
54,119
54,119
8WP08K
8000 GAL WATER PULL 2.00
104.08 HR
123.000
12,802
12,802
8YGATOR
UTV Gator / Kubota
2.00
104.08 HR
6.000
624
624
LAGCK
Laborer, Grade Checker
2.00
104.08 MH *
41.838
4,354
4,354
OPBLD
Operator, Finish Motorgrad 2.00
104.08 MH *
49.536
5,156
5,156
OPDZR
Operator, Dozer
2.00
104.08 MH *
42.172
4,389
4,389
OPGEN
Operator, General
1.00
52.04 MH *
38.491
2,003
2,003
OPSCR
Operator, Scraper
4.00
208.15 MH *
40.834
8,500
8,500
OPWP
Operator, Waterpull
2.00
104.08 MH *
39.495
4,111
4,111
$127,494.23
0.0154 MH/CY
676.51 MH
[ 0.536 ]
28,513
98,982
127,494
840.1307
Units/Hr
*
2,450.3984 $/CrewHr
5.2030 Shifts
0.65
2.26
2.92
203-30
O.G. Compaction
Quan: 22,823.00 SY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
GPOGC
OG Compact
30.00
CH
Prod:
760.7667 UH
Lab Pcs:
2.00
Eqp Pcs:
2.00
8MG14
Cat 14 Motorgrader
1.00
30.00 HR
110.500
3,315
3,315
8WP08K
8000 GAL WATER PULL 1.00
30.00 HR
123.000
3,690
3,690
OPBLD
Operator, Finish Motorgrad 1.00
30.00 MH *
49.536
1,486
1,486
OPWP
Operator, Waterpull
1.00
30.00 MH *
39.495
1,185
1,185
$9,675.93
0.0026 MH/SY
60.00 MH
[ 0.096 ]
2,671
7,005
9,676
760.7667
Units/Hr
*
322.5310 $/CrewHr
3.0000 Shifts
0.12
0.31
0.42
205-00
Rough Finish
Quan: 23,551.00 SY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FIN140
Finish Grade
30.00
CH
Prod:
785.0333 UH
Lab Pcs:
4.00
Eqp Pcs:
4.00
8MG150
Cat 150 Motorgrader (I
1.00
30.00 HR
97.000
2,910
2,910
8SC623
Cat 623 Scraper
1.00
30.00 HR
149.000
4,470
4,470
8WP08K
8000 GAL WATER PULL 1.00
30.00 HR
123.000
3,690
3,690
8YGATOR
UTV Gator / Kubota
1.00
30.00 HR
6.000
180
180
LAGCK
Laborer, Grade Checker
1.00
30.00 MH *
41.838
1,255
1,255
OPBLD
Operator, Finish Motorgrad 1.00
30.00 MH *
49.536
1,486
1,486
OPSCR
Operator, Scraper
1.00
30.00 MH *
40.834
1,225
1,225
OPWP
Operator, Waterpull
1.00
30.00 MH *
39.495
1,185
1,185
$16,401.07
0.0050 MH/SY
120.00 MH
[ 0.18 ]
5,151
11,250
16,401
785.0333
Units/Hr
*
546.7023 $/CrewHr
3.0000 Shifts
0.22
0.48
0.70
=====>
Item Totals:
      1000
- GENERAL FILL FOR HAUL ROADS
$174,492.48
0.0217 MH/CY
1,006.51 MH
[ 0.759 ]
42,751
131,742
174,492
3.769
         46292 CY
0.92
2.85
3.77
BID ITEM
=      1100
CLIENT# = 8
Land Item       SCHEDULE:
1
100
Description =
HAUL, PLACE & MAINTAIN AC MILLINGS
Unit =
SF
Takeoff Quan:
189,630.000
Engr Quan: 189,630.000
203-00-22
Place Millings
Quan:
3,612.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
EXS232
(Mod) Excavation Scraper 623-2
20.00
CH
Prod:
180.6000 UH
Lab Pcs:
6.00
Eqp Pcs:
6.00
8MG150
Cat 150 Motorgrader (I
1.00
20.00 HR
97.000
1,940
1,940
Exhibit C page 18/24

Rummel Construction, Inc.
Page 9
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=      1100
CLIENT# = 8
Land Item       SCHEDULE:
1
100
Description =
HAUL, PLACE & MAINTAIN AC MILLINGS
Unit =
SF
Takeoff Quan:
189,630.000
Engr Quan: 189,630.000
8RCVS
Cat CS54 Vib Steel Rol
1.00
20.00 HR
47.466
992
992
8SC623
Cat 623 Scraper
2.00
40.00 HR
149.000
5,960
5,960
8WP08K
8000 GAL WATER PULL 1.00
20.00 HR
123.000
2,460
2,460
8YGATOR
UTV Gator / Kubota
1.00
20.00 HR
6.000
120
120
LAGCK
Laborer, Grade Checker
1.00
20.00 MH *
41.838
837
837
OPBLD
Operator, Finish Motorgrad 1.00
20.00 MH *
49.536
991
991
OPGEN
Operator, General
1.00
20.00 MH *
38.491
770
770
OPSCR
Operator, Scraper
2.00
40.00 MH *
40.834
1,633
1,633
OPWP
Operator, Waterpull
1.00
20.00 MH *
39.495
790
790
$16,492.10
0.0332 MH/CY
120.00 MH
[ 1.142 ]
5,021
11,472
16,492
180.6000
Units/Hr
*
824.6050 $/CrewHr
2.0000 Shifts
1.39
3.18
4.57
303-00
Finish Subgrade
Quan: 21,070.00 SY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FINRS
(Mod) Restore Street Subgrade
30.00
CH
Prod:
702.3330 UH
Lab Pcs:
5.00
Eqp Pcs:
4.00
8MG150
Cat 150 Motorgrader (I
1.00
30.00 HR
97.000
2,910
2,910
8RCVS
Cat CS54 Vib Steel Rol
1.00
30.00 HR
47.466
1,487
1,487
8SC623
Cat 623 Scraper
1.00
30.00 HR
149.000
4,470
4,470
8WTK4
4,000 gal Water Truck
1.00
30.00 HR
55.000
1,650
1,650
LACMN
Laborer, Common
1.00
30.00 MH *
30.123
904
904
OPBLD
Operator, Finish Motorgrad 1.00
30.00 MH *
49.536
1,486
1,486
OPGEN
Operator, General
1.00
30.00 MH *
38.491
1,155
1,155
OPSCR
Operator, Scraper
1.00
30.00 MH *
40.834
1,225
1,225
OPWT
Operator, Water Truck
1.00
30.00 MH *
37.487
1,125
1,125
$16,411.44
0.0071 MH/SY
150.00 MH
[ 0.23 ]
5,894
10,517
16,411
702.3333
Units/Hr
*
547.0480 $/CrewHr
3.0000 Shifts
0.28
0.50
0.78
303-20
Finish ABC
Quan: 21,070.00 SY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
FINABC
(Mod) Finish Grade ABC
30.00
CH
Prod:
702.3333 UH
Lab Pcs:
7.00
Eqp Pcs:
4.00
8MG150
Cat 150 Motorgrader (I
1.00
30.00 HR
97.000
2,910
2,910
8RCVS
Cat CS54 Vib Steel Rol
1.00
30.00 HR
47.466
1,487
1,487
8SC623
Cat 623 Scraper
1.00
30.00 HR
149.000
4,470
4,470
8WTK4
4,000 gal Water Truck
1.00
30.00 HR
55.000
1,650
1,650
LACMN
Laborer, Common
2.00
60.00 MH *
30.123
1,807
1,807
LAGCK
Laborer, Grade Checker
1.00
30.00 MH *
41.838
1,255
1,255
OPBLD
Operator, Finish Motorgrad 1.00
30.00 MH *
49.536
1,486
1,486
OPGEN
Operator, General
1.00
30.00 MH *
38.491
1,155
1,155
OPSCR
Operator, Scraper
1.00
30.00 MH *
40.834
1,225
1,225
OPWT
Operator, Water Truck
1.00
30.00 MH *
37.487
1,125
1,125
$18,570.26
0.0099 MH/SY
210.00 MH
[ 0.314 ]
8,053
10,517
18,570
702.3333
Units/Hr
*
619.0087 $/CrewHr
3.0000 Shifts
0.38
0.50
0.88
404
BITUMINOUS TREATMENTS
Quan: 21,070.00 SY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
4TACK
Tack Coat
1.00
21,070.00 SY
1.020
21,491
21,491
$21,491.40
[  ]
21,491
21,491
1.02
1.02
=====>
Item Totals:
      1100
- HAUL, PLACE & MAINTAIN AC MILLINGS
$72,965.20
0.0025 MH/SF
480.00 MH
[ 0.082 ]
18,968
32,506
21,491
72,965
0.385
         189630 SF
0.10
0.17
0.11
0.38
BID ITEM
=      1200
CLIENT# = 9
Land Item       SCHEDULE:
1
100
Description =
SAFETY BARRIERS
Unit =
LF
Takeoff Quan:
1,860.000
Engr Quan:
1,860.000
Exhibit C page 19/24

Rummel Construction, Inc.
Page 10
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=      1200
CLIENT# = 9
Land Item       SCHEDULE:
1
100
Description =
SAFETY BARRIERS
Unit =
LF
Takeoff Quan:
1,860.000
Engr Quan:
1,860.000
970-12
SAFETY BARRIERS
Quan:
1,860.00 LF
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
[[ Crew Notes: ***Copied***  ]]
LA-FAB
(Mod) Filter Fabric Install
20.00
CH
Prod:
93.0000 UH
Lab Pcs:
4.00
Eqp Pcs:
1.00
4BAR
Barricade Sub
1.00
1,860.00 LF
65.000
120,900
120,900
8TKPU
Foreman pickup
1.00
20.00 HR
14.250
285
285
LACMN
Laborer, Common
3.00
60.00 MH *
30.123
1,807
1,807
ZFM1
General Foreman
1.00
20.00 MH *
38.719
774
774
$123,766.76
0.0430 MH/LF
80.00 MH
[ 1.13 ]
2,582
285
120,900
123,767
93.0000
Units/Hr
*
143.3380 $/CrewHr
2.0000 Shifts
1.39
0.15
65.00
66.54
=====>
Item Totals:
      1200
- SAFETY BARRIERS
$123,766.76
0.0430 MH/LF
80.00 MH
[ 1.13 ]
2,582
285
120,900
123,767
66.541
         1860 LF
1.39
0.15
65.00
66.54
BID ITEM
=      1300
CLIENT# = 10
Land Item       SCHEDULE:
1
100
Description =
RIPRAP V-DITCH
Unit =
LF
Takeoff Quan:
2,731.000
Engr Quan:
2,731.000
913-01
Purchase Rip Rap Materials
Quan:
1,002.00 TN
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
2ARD506
Rip Rap, D50=6"
1.00
1,002.00 TN
33.850
33,918
33,918
2GF8OZ
8 oz Non-Woven Geofabric 1.00
4,000.00 SY
1.250
5,000
5,000
$38,917.70
[  ]
38,918
38,918
38.84
38.84
913-03-02
Install Loose Rip Rap 420
Quan:
607.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
RR420
(Mod) Rip Rap 420/950/Gannon
50.00
CH
Prod:
12.1400 UH
Lab Pcs:
6.00
Eqp Pcs:
3.00
8EX325
Cat 325 Excavator (57,
1.00
50.00 HR
67.500
3,375
3,375
8LD950
Cat 950 Wheel Loader (
1.00
50.00 HR
73.500
3,675
3,675
8WTK4
4,000 gal Water Truck
1.00
50.00 HR
55.000
2,750
2,750
LACMN
Laborer, Common
3.00
150.00 MH *
30.123
4,518
4,518
OPEXC
Operator, Excavator
1.00
50.00 MH *
41.503
2,075
2,075
OPLDR
Operator, Loader
1.00
50.00 MH *
40.834
2,042
2,042
OPWT
Operator, Water Truck
1.00
50.00 MH *
37.487
1,874
1,874
$20,309.66
0.4942 MH/CY
300.00 MH
[ 14.226 ]
10,510
9,800
20,310
12.1400
Units/Hr
*
406.1932 $/CrewHr
5.0000 Shifts
17.31
16.14
33.46
913-05-15
Excavate Rip Rap Pocket - 320
Quan:
1,214.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
EXE325
(Mod) Excavation Excavator 325
50.00
CH
Prod:
24.2800 UH
Lab Pcs:
3.33
Eqp Pcs:
3.33
8EX325
Cat 325 Excavator (57,
1.00
50.00 HR
67.500
3,375
3,375
8SC623
Cat 623 Scraper
0.33
16.50 HR
149.000
2,458
2,458
8WTK4
4,000 gal Water Truck
1.00
50.00 HR
55.000
2,750
2,750
8YGATOR
UTV Gator / Kubota
1.00
50.00 HR
6.000
300
300
LAGCK
Laborer, Grade Checker
1.00
50.00 MH *
41.838
2,092
2,092
OPEXC
Operator, Excavator
1.00
50.00 MH *
41.503
2,075
2,075
OPSCR
Operator, Scraper
0.33
16.50 MH *
40.834
674
674
OPWT
Operator, Water Truck
1.00
50.00 MH *
37.487
1,874
1,874
$15,598.63
0.1371 MH/CY
166.50 MH
[ 4.545 ]
6,715
8,883
15,599
24.2800
Units/Hr
*
311.9726 $/CrewHr
5.0000 Shifts
5.53
7.32
12.85
=====>
Item Totals:
      1300
- RIPRAP V-DITCH
$74,825.99
0.1708 MH/LF
466.50 MH
[ 5.182 ]
17,225
38,918
18,683
74,826
27.399
         2731 LF
6.31
14.25
6.84
27.40
Exhibit C page 20/24

Rummel Construction, Inc.
Page 11
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=      1400
CLIENT# = 11
Land Item       SCHEDULE:
1
100
Description =
RIPRAP SPLASH PAD
Unit =
EA
Takeoff Quan:
1.000
Engr Quan:
1.000
913-01
Purchase Rip Rap Materials
Quan:
68.00 TN
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
2ARD506
Rip Rap, D50=6"
1.00
68.00 TN
33.850
2,302
2,302
2GF8OZ
8 oz Non-Woven Geofabric 1.00
500.00 SY
1.250
625
625
$2,926.80
[  ]
2,927
2,927
43.04
43.04
913-03-02
Install Loose Rip Rap 325
Quan:
41.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
RR420
(Mod) Rip Rap 420/950/Gannon
2.50
CH
Prod:
16.4000 UH
Lab Pcs:
6.00
Eqp Pcs:
3.00
8EX325
Cat 325 Excavator (57,
1.00
2.50 HR
67.500
169
169
8LD950
Cat 950 Wheel Loader (
1.00
2.50 HR
73.500
184
184
8WTK4
4,000 gal Water Truck
1.00
2.50 HR
55.000
137
137
LACMN
Laborer, Common
3.00
7.50 MH *
30.124
226
226
OPEXC
Operator, Excavator
1.00
2.50 MH *
41.504
104
104
OPLDR
Operator, Loader
1.00
2.50 MH *
40.836
102
102
OPWT
Operator, Water Truck
1.00
2.50 MH *
37.488
94
94
$1,015.48
0.3658 MH/CY
15.00 MH
[ 10.531 ]
526
490
1,015
16.4000
Units/Hr
*
406.1920 $/CrewHr
0.2500 Shifts
12.82
11.95
24.77
913-05-15
Excavate Rip Rap Pocket - 320
Quan:
41.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
EXE325
(Mod) Excavation Excavator 325
2.50
CH
Prod:
16.4000 UH
Lab Pcs:
3.33
Eqp Pcs:
3.33
8EX325
Cat 325 Excavator (57,
1.00
2.50 HR
67.500
169
169
8SC623
Cat 623 Scraper
0.33
0.83 HR
149.000
124
124
8WTK4
4,000 gal Water Truck
1.00
2.50 HR
55.000
137
137
8YGATOR
UTV Gator / Kubota
1.00
2.50 HR
6.000
15
15
LAGCK
Laborer, Grade Checker
1.00
2.50 MH *
41.840
105
105
OPEXC
Operator, Excavator
1.00
2.50 MH *
41.504
104
104
OPSCR
Operator, Scraper
0.33
0.83 MH *
40.843
34
34
OPWT
Operator, Water Truck
1.00
2.50 MH *
37.488
94
94
$780.85
0.2031 MH/CY
8.33 MH
[ 6.733 ]
336
445
781
16.4000
Units/Hr
*
312.3400 $/CrewHr
0.2500 Shifts
8.19
10.85
19.05
=====>
Item Totals:
      1400
- RIPRAP SPLASH PAD
$4,723.13
23.3300 MH/EA
23.33 MH
[ 707.8 ]
861
2,927
935
4,723
4,723.130
         1 EA
861.48 2,926.80
934.85
4,723.13
BID ITEM
=      1500
CLIENT# = 12
Land Item       SCHEDULE:
1
100
Description =
STORMWATER CROSSINGS
Unit =
EA
Takeoff Quan:
1.000
Engr Quan:
1.000
501-12-00
12" CMP Ex/ Place/ Backfill
Quan:
170.00 LF
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
SDSM
(Mod) Pipe - Small Diameter
30.00
CH
Prod:
5.6667 UH
Lab Pcs:
7.00
Eqp Pcs:
6.00
8EX325
Cat 325 Excavator (57,
1.00
30.00 HR
67.500
2,025
2,025
8LD950
Cat 950 Wheel Loader (
1.00
30.00 HR
73.500
2,205
2,205
8RCHR
Walk Behin Hand roller
1.00
30.00 HR
28.250
899
899
8RCMX
Ramex
1.00
30.00 HR
12.000
360
360
8WTK4
4,000 gal Water Truck
1.00
30.00 HR
55.000
1,650
1,650
8YGATOR
UTV Gator / Kubota
1.00
30.00 HR
6.000
180
180
LACMN
Laborer, Common
3.00
90.00 MH *
30.123
2,711
2,711
LAGCK
Laborer, Grade Checker
1.00
30.00 MH *
41.838
1,255
1,255
OPEXC
Operator, Excavator
1.00
30.00 MH *
41.503
1,245
1,245
OPLDR
Operator, Loader
1.00
30.00 MH *
40.834
1,225
1,225
OPWT
Operator, Water Truck
1.00
30.00 MH *
37.487
1,125
1,125
Exhibit C page 21/24

Rummel Construction, Inc.
Page 12
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=      1500
CLIENT# = 12
Land Item       SCHEDULE:
1
100
Description =
STORMWATER CROSSINGS
Unit =
EA
Takeoff Quan:
1.000
Engr Quan:
1.000
$14,880.39
1.2352 MH/LF
210.00 MH
[ 36.543 ]
7,561
7,319
14,880
5.6667
Units/Hr
*
496.0130 $/CrewHr
3.0000 Shifts
44.48
43.06
87.53
501-12-01
12" CMP Materials
Quan:
170.00 LF
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
2ABED
Bedding Material
1.00
140.60 TN
20.000
2,812
2,812
2PM124
12 in. CMP Ga. #14
1.00
170.00 LF
22.700
3,859
3,859
2PM12BANDS
12 in. CMP Bands
1.00
8.00 EA
42.510
340
340
2PM12BEND
45 deg bend
1.00
2.00 EA
66.640
133
133
$7,144.36
[  ]
7,144
7,144
42.03
42.03
970-17
Headwall
Quan:
1.00 EA
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
4COS
Concrete Structure Sub
1.00
1.00 EA
12,500.000
12,500
12,500
$12,500.00
[  ]
12,500
12,500
12,500.00 12,500.00
=====>
Item Totals:
      1500
- STORMWATER CROSSINGS
$34,524.75
210.0000 MH/EA
210.00 MH
[ 6212.25 ]
7,561
7,144
7,319
12,500
34,525
34,524.750
         1 EA
7,560.92 7,144.36
7,319.47 12,500.00 34,524.75
BID ITEM
=      1600
CLIENT# = 13
Land Item       SCHEDULE:
1
100
Description =
RELOCATE ASPHALT MILLINGS
Unit =
CY
Takeoff Quan:
9,507.000
Engr Quan:
9,507.000
203-00-21
Excavation Scraper 623-1
Quan:
9,507.00 CY
Hrs/Shft:
10.00
Cal: 510 WC: NOUSE
**Unreviewed
EXS231
(Mod) Excavation Scraper 623-1
30.00
CH
Prod:
316.9000 UH
Lab Pcs:
5.00
Eqp Pcs:
5.00
8MG150
Cat 150 Motorgrader (I
1.00
30.00 HR
97.000
2,910
2,910
8SC623
Cat 623 Scraper
2.00
60.00 HR
149.000
8,940
8,940
8WP08K
8000 GAL WATER PULL 1.00
30.00 HR
123.000
3,690
3,690
8YGATOR
UTV Gator / Kubota
1.00
30.00 HR
6.000
180
180
LAGCK
Laborer, Grade Checker
1.00
30.00 MH *
41.838
1,255
1,255
OPBLD
Operator, Finish Motorgrad 1.00
30.00 MH *
49.536
1,486
1,486
OPSCR
Operator, Scraper
2.00
60.00 MH *
40.834
2,450
2,450
OPWP
Operator, Waterpull
1.00
30.00 MH *
39.495
1,185
1,185
$22,096.08
0.0157 MH/CY
150.00 MH
[ 0.551 ]
6,376
15,720
22,096
316.9000
Units/Hr
*
736.5360 $/CrewHr
3.0000 Shifts
0.67
1.65
2.32
=====>
Item Totals:
      1600
- RELOCATE ASPHALT MILLINGS
$22,096.08
0.0157 MH/CY
150.00 MH
[ 0.551 ]
6,376
15,720
22,096
2.324
         9507 CY
0.67
1.65
2.32
PARENT ITEM =
     10000
Description =
PROJECT INDIRECT COSTS
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
1.000
Listing of Sub-Biditems of Parent Item 10000: 
BID ITEM
=     10010
Land Item       SCHEDULE:
1
100
Description =
TIME DEPENDENT
Unit =
MO
Takeoff Quan:
1.000
Engr Quan:
0.000
=====>
Item Totals:
     10010
- TIME DEPENDENT
$0.00
[  ] 
Exhibit C page 22/24

Rummel Construction, Inc.
Page 13
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=     10010
Land Item       SCHEDULE:
1
100
Description =
TIME DEPENDENT
Unit =
MO
Takeoff Quan:
1.000
Engr Quan:
0.000
0.000
         1 MO 
BID ITEM
=     10020
Land Item       SCHEDULE:
1
100
Description =
NON TIME DEPENDENT
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
0.000
=====>
Item Totals:
     10020
- NON TIME DEPENDENT
$0.00
[  ] 
0.000
         1 LS 
Total of Above Sub-Biditems
=====>
Item Totals:
     10000
- PROJECT INDIRECT COSTS
$0.00
[  ] 
0.000
         1 LS 
$2,443,703.49
***  Report Totals  ***
12,848.67 MH
591,587
48,989
82,136 1,562,448 158,544 2,443,703 
>>> indicates Non Additive Activity
------Report Notes:------
The estimate was prepared with TAKEOFF Quantities.
This report shows TAKEOFF Quantities with the resources.
'Unreviewed' Activities are marked. 
Bid Date: 10/24/22  Owner: CITYOFGLENDALE  Engineering Firm: TETRATECH
 Estimator-In-Charge:
JOB NOTES
[[ Attached Files: CLass A Risk Classification 1.pdf, Class A Risk Classification 2.pdf, Class B Risk
Classifications.pdf ]]
Labor Rates Updated 05/24/2022 Labor Burden updated 04/05/2022 Equipment Rates Updated 07/12/2022
************Estimate created on: 10/12/2021 by User#: 52 - Chad Bryce
Source estimate used: J:\HCSS\HEAVYBID\MSTR_LIBEST\MASTEREST18
************Estimate created on: 10/18/2022 by User#: 103 - Mike Claflin
Source estimate used: J:\HCSS\HEAVYBID\MSTR_LIBEST\MASTEREST22
* on units of MH indicate average labor unit cost was used rather than base rate.
[   ] in the Unit Cost Column = Labor Unit Cost Without Labor Burdens
In equipment resources, rent % and EOE % not = 100% are represented as XXX%YYY where XXX=Rent% and YYY=EOE%
------Calendar Codes------
410
4 X 10 HR WEEK NO OT
508
5 X 8 HR WEEK
509
5 X 9 HR WEEK
510
5 x 10 HR WEEK (Default Calendar)
5E8
5 X 8 (Pay 9 - Work 8)
608
6 X 8 HR WEEK
610
6 X 10 HR WEEK
Exhibit C page 23/24

Rummel Construction, Inc.
Page 14
GLENDALELF2A
GLENDALE LANDFILL CMAR PHASE 2A
10/28/2022
14:08
Dodd O'Neill
Cost Report
Activity
Desc
Quantity
Unit
Perm
  Constr
   Equip
   Sub-
Resource
Pcs
Unit
Cost
   Labor Material Matl/Exp
  Ment Contract
Total
BID ITEM
=     10020
Land Item       SCHEDULE:
1
100
Description =
NON TIME DEPENDENT
Unit =
LS
Takeoff Quan:
1.000
Engr Quan:
0.000
6E8
6 X 8 (Pay 9 - Work 8)
Exhibit C page 24/24

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
EXHIBIT E 
Construction Documents necessary to define Scope of Work and Deliverables for the 
Construction Phase Services, including plans, designs, drawings, specifications and other 
required Contract Documents 
 
(156 pages - To be Incorporated by Amendment)

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
 
CONSTRUCTION SPECIFICATIONS 
 
CITY OF GLENDALE 
GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, 
HAUL, AND STOCKPILE PROJECT 
GLENDALE, ARIZONA 
 
PROJECT NO. 2023-0128-228 
 
OCTOBER 2022

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 1 of 6 
SECTION A01010 
SUMMARY OF WORK 
 
 
1.0 
GENERAL 
1.01 
BRIEF PROJECT DESCRIPTION 
 
A. 
The Glendale Landfill (Site) is located within the City of Glendale (OWNER), Arizona 
to the west of Phoenix.  The Site address is 11480 W. Glendale Avenue, Glendale, 
Arizona, 85307, Maricopa County.  Access to the Site is as follows: from Phoenix 
take I-10 west to the Loop 101, north on the Loop 101 to Glendale Avenue, and 
west on Glendale Avenue to the Glendale Landfill. 
 
B. 
General: Work included in the contract primarily consists of the excavation, 
hauling and stockpiling of soil from the Site’s north cell.  The CONTRACTOR will be 
required to stockpile the soil for future use.  The Work is detailed in these 
Specifications and on the Contract Drawings included herein. 
 
C. 
Principal Features: 
 
1. Mobilization and demobilization of equipment, labor, and construction of any 
temporary facilities that may be required; 
2. Moisture condition the area to be excavated; 
3. Excavate the soil in a systematic manner; 
4. Backfill and compact soil on all exposed North Cell slopes to the grades shown 
on the Contract Drawings. 
5. Haul soil to two specific stockpile locations as depicted on the Contract 
Drawings. All hauling of excavated material shall be confined to the site, and 
shall not take place on public roads; and 
6. Maintain haul roads and provide dust control. 
 
D. 
The CONTRACTOR shall replace in kind any existing improvements (drainage 
channels, asphalt millings roads, LFG wells & laterals, etc.) damaged during the 
course of construction as no cost to the OWNER. 
 
E. 
No additional and/or extra compensation will be given for all/or any increases to 
direct labor costs, subcontract costs, and costs of materials and equipment, which

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 2 of 6 
includes all fuels.  The only exception to this is a Fuel Cost Adjustment as described 
in subsection 1.07 of this Section. 
 
F. 
The above description of Work is for general information only, and does not limit 
the responsibility of the CONTRACTOR to accomplish the Work in strict accordance 
with the Contract Drawings and Specifications. 
 
G. 
The Work shall be performed in strict accordance with all applicable requirements 
of the City of Glendale, Maricopa County, State of Arizona, and other agencies 
having jurisdiction, and in accordance with the requirements of the General 
Conditions, Supplementary General Conditions, and Contract Drawings.  The 
CONTRACTOR shall provide a Site-specific Health and Safety Plan (HASP) for 
OWNER approval.  It shall be the CONTRACTOR’S responsibility to be fully apprised 
of Site conditions and to follow the approved HASP. 
 
1.02 
EXISTING SITE CONDITIONS 
 
A. 
The Site is currently an active landfill that receives residential and commercial 
waste on a daily basis. 
 
B. 
A limited geotechnical investigation has been conducted for this site.  Boring logs 
and laboratory analytical results from the north cell expansion borrow source are 
presented in Appendix A of these specifications.  Results of the geotechnical 
evaluation of the on-site material have been used to prepare two geologic cross-
sections which are also presented in Appendix A.  This information is available for 
review by the CONTRACTOR but does not represent a complete characterization 
of borrow material conditions.  Some “hard dig” conditions should be expected.   
 
C. 
The base topographic mapping contours shown on the Contract Drawings were 
prepared from July 1, 2022 aerial photographs.  Due to ongoing landfill operations 
and the need to excavate daily and intermediate cover, actual elevations and 
contours may vary at the time the CONTRACTOR is given notice to proceed. 
 
1.03 
CONTRACTOR’S USE OF PROPERTY 
 
A. 
The CONTRACTOR shall have unrestricted access and egress from the Site, as 
necessary, to perform the Work under this Contract.  The CONTRACTOR shall 
obtain approval for all necessary permits (dust control, stormwater, etc.) to 
accomplish the Work. 
 
B. 
The CONTRACTOR shall limit use of the Site to only the Work and storage

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 3 of 6 
requirements related to this Contract. 
 
C. 
The CONTRACTOR shall assume full responsibility for the protection and 
safekeeping of equipment and materials on or off the Site that are related to this 
Contract. 
 
D. 
The CONTRACTOR shall be responsible for the remediation of any fuel/petroleum 
spills.  Fuel/petroleum spills shall be remediated as soon as they are noticed.   
1.04 
WORK SEQUENCE 
 
A. 
A Notice to Proceed for beginning of Work under these Contract Documents will 
be given after bid award. 
 
B. 
The CONTRACTOR shall be responsible for planning, scheduling, and otherwise 
executing the Work in a manner that meets the requirements of the Contract 
Drawings and Specifications for this project. 
 
1.05 
SEPARATE CONTRACTS 
 
 
NOT USED 
 
1.06 
BROAD SCOPE 
 
This article describes the project in general and provides an overview of the intent of the 
Work to be performed under this Contract.  The CONTRACTOR shall review the entire set 
of Contract Documents to gain a thorough understanding of the detailed project 
requirements.  The following describes the general sequence of work for this project.   
 
A. 
The CONTRACTOR shall perform the Work in accordance with the Contract 
Documents: Project Construction Drawings, Construction Specifications, 
referenced design reports, subsequent addenda, and approved shop drawings and 
submittals.  The CONTRACTOR shall provide all labor, equipment, and materials 
for temporary utilities, roads, storage, and other facilities necessary for the 
completion of all Work included as part of this contract. 
 
B. 
The CONTRACTOR shall provide all labor, equipment, and materials for clearing 
and grubbing, subgrade preparation, excavation and engineered fill, moisture 
conditioning, and placing and compacting soil on the existing North Cell slopes to 
the lines and grades shown on the Construction Drawings. 
 
C. 
The CONTRACTOR shall provide all labor, equipment, and materials for the

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 4 of 6 
construction of the Glendale Landfill west slope temporary customer access road 
consisting of excavation, moisture conditioning, placing and compacting general 
fill, and placement of road surfacing material. 
 
D. 
The CONTRACTOR shall provide all labor, equipment, and materials to excavate 
soil from the North Cell and haul to a stockpile.  Soil shall be hauled to two 
separate stockpiles as shown on the Construction Drawings.  The CONTRACTOR 
shall moisture condition the soil before excavation and shall maintain dust control 
on all haul roads and stockpile locations.   
 
F. 
Throughout construction, the CONTRACTOR shall maintain one set of full-size 
(24”x36”) red-line field drawings showing as-constructed site conditions.  These 
drawings shall remain on-site during the project for periodic review by the OWNER 
or ENGINEER.  Upon completion of construction activities, one full-size set of 
ACAD drawings with revised survey data shall be submitted to the OWNER or 
ENGINEER for incorporation into As-built Drawings to be prepared by the 
ENGINEER. 
 
1.07 
WORK HOURS 
 
A. 
Unless otherwise approved by the OWNER, construction activities and material 
deliveries to the landfill shall be limited to the hours of 6 a.m. to 5 p.m.  The 
CONTRACTOR shall submit a project bid which in no way assumes work outside of 
these hours, i.e., night work, will not be allowed on this project. 
 
1.08 
USE OF EXPLOSIVES 
 
A. The CONTRACTOR shall not employ the use of explosives on this project without 
expressed written consent from the OWNER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 5 of 6 
1.09 
SUBSTANTIAL COMPLETION 
 
A. Substantial Completion means the project work is complete.  This shall include but is 
not limited to: 
 
1. All systems in place, functional, and displayed to the OWNER or its 
representatives; 
 
2. Construction Complete; 
 
3. Materials and equipment installed; 
 
4. All systems reviewed and accepted by the OWNER. 
 
5. Draft record documents reviewed and accepted by the OWNER; 
 
6. Landscaping and site work completed; 
 
7. Final cleaning; and 
 
8. Final Acceptance (following 30 days to correct punch-list items). 
 
1.10 
PROJECT SCHEDULE 
 
A. The anticipated project start date is November 2022. 
 
B. The CONTRACTOR shall substantially complete all work and receive final acceptance 
by March 2, 2023.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 6 of 6 
C. The City will consider alternative bid schedules with the exception that the 
Contractor will not miss the Substantial Completion deadline, March 2, 2023. 
 
1.11 
LIQUIDATED DAMAGES 
 
A. Liquidated damages shall be Five Thousand Dollars ($5,000) per day that substantial 
completion extends beyond the date determined by the contract time as adjusted. 
 
B. Liquidated damages shall be Two Thousand Five Hundred Dollars ($2,500) per day 
that final acceptance extends beyond the date determined by the contract time as 
adjusted. 
 
 
2.0 
PRODUCTS 
 
 
NOT USED 
 
 
3.0 
EXECUTION 
 
 
NOT USED 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025.  No payment will be made for meetings.  The bid price shall include the 
cost that may be incurred to attend and conduct any and all meetings and provide 
coordination. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 1 of 10 
SECTION A01015 
ABBREVIATIONS AND DEFINITIONS 
 
 
1.0 
GENERAL 
 
1.01 
ABBREVIATIONS 
 
In addition to the standard abbreviations in the MAG Specification, the following 
abbreviations have also been used: 
 
AASHTO        American Association of State Highway and Transportation Officials 
ACI           
American Concrete Institute 
ADEQ 
Arizona Department of Environmental Quality 
ADOT 
Arizona Department of Transportation  
AGA 
American Gas Association  
AIA  
American Institute of Architects 
AICHE 
American Institute of Chemical Engineers 
AISC 
American Institute of Steel Construction 
AISI 
American Iron and Steel Institute 
ANSI 
American National Standards Institute 
API 
American Petroleum Institute 
AREA 
American Railway Engineering Association 
ASCE 
American Society of Civil Engineers 
ASHRAE 
American Society of Heating, Refrigerating and Air Conditioning Engineers 
ASME 
American Society of Mechanical Engineers 
ASQC 
American Society for Quality Control 
ASTM 
American Society for Testing and Materials 
AWS 
American Welding Society 
AWWA 
American Water Works Association 
BMP 
Best Management Practices 
CBM 
Certified Ballast Manufacturers 
CFR 
Code of Federal Regulations 
CGA 
Compressed Gas Association 
COG 
City of Glendale 
CQA 
Construction Quality Assurance 
CRSI 
Concrete Reinforced Steel Institute 
CY 
Cubic Yard 
EPA 
Environmental Protection Agency 
ETL 
Electrical Testing Laboratories 
FS 
Federal Specification 
IEEE 
Institute of Electrical and Electronics Engineers

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 2 of 10 
IES 
Illuminating Engineering Society 
IPCEA 
Insulated Power Cable Engineer Association 
ISA 
Instrument Society of America 
ITL 
Independent Testing Laboratories 
LFG 
Landfill Gas 
LL 
Liquid Limit 
MAG 
Maricopa Association of Governments (Arizona) 
MIL 
U.S. Military Specification 
NEC 
National Electrical Code 
NEMA 
National Electrical Manufacturers Association 
NETA 
International Electrical Testing Association 
NFPA 
National Fire Protection Association 
NPDES 
National Pollutant Discharge Elimination System 
NSF 
National Sanitation Foundation 
OSHA 
Occupational Safety and Health Administration 
PI 
Plasticity Index 
PPl 
Plastics Pipe Institute 
SHSP 
Site Health and Safety Plan 
SMACNA 
Sheet Metal and Air Conditioning Contractor's National Association 
SRP 
Salt River Project 
SSPC 
Steel Structures Painting Council 
SWMF 
Solid Waste Management Facility 
SWPPP 
Storm Water Pollution Prevention Plan 
UBC 
Uniform Building Code 
UL 
Underwriters Laboratories 
UMC 
Uniform Mechanical Code 
UPC 
Uniform Plumbing Code 
USSPWC 
Uniform Standard Specifications for Public Works Construction 
USBR 
U.S. Bureau of Reclamation 
USCS 
Unified Soil Classification System 
WC 
Water Content 
WCRSI 
Western Concrete Reinforcing Steel Institute 
ZAV 
Zero Air Voids Curve 
 
 
1.02 
DEFINITION OF TERMS 
 
REGULATORY AGENCY - Regulatory Agency, which in this context is the Arizona Department 
of Environmental Quality (ADEQ), is responsible for compliance with the Agency’s 
regulations.  The Occupational Safety and Health Administration (OSHA) administers 
regulations for the CONTRACTOR’S Site safety requirements.  Maricopa County Air Quality 
Department (MCAQD) should be considered as an additional regulatory agency that may 
visit the site and review the work for dust emissions.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 3 of 10 
OWNER - OWNER refers to the City of Glendale, acting through its legally constituted 
officials or employees.  As OWNER of the Glendale Landfill, the City of Glendale is 
responsible for the overall compliance with various facility permits and operations 
requirements, initiation, progress, and completion of this Project, and the maintenance 
of the completed work.  The address and contact person of the OWNER shall be: 
 
City of Glendale (OWNER) 
Mr. Michael Carr 
6210 W. Myrtle Avenue, Suite 111 
Glendale, AZ  85301 
Phone:  (623) 930-2617 
Fax: (623) 915-3124 
 
 
OPERATOR - The City of Glendale is also the OWNER of the Site. 
In this document, the OWNER and the Operator are one in the same. 
 
ENGINEER - Also known as Designer Engineer and Construction Quality Assurance (CQA) 
Engineer, is an individual, a firm, or an organization who is responsible for preparation of 
the Contract Drawings, Specifications, and CQA Plan for the Project.  The OWNER’S 
Project ENGINEER shall decide on all questions which may arise as to the compliance and 
acceptability of materials furnished, work performed, and all questions as to the 
fulfillment of the technical and design issues of the Contract on the part of the 
CONTRACTOR.  The ENGINEER will make these decisions after consultation with the 
OWNER and, in some cases, the Design Engineer. 
 
The ENGINEER shall be responsible for the acceptance or rejection of work based on 
compliance with the Contract Drawings, Specifications and design intent; the ENGINEER 
will recommend suspension of work for unsafe conditions, failure by the CONTRACTOR to 
carry out provisions of the Contract, and for unsuitable weather conditions.  The 
ENGINEER shall also review the CONTRACTOR’S submittals, make recommendations, and 
review/approve the CONTRACTOR’S payment requests. 
 
The engineering consulting company Tetra Tech BAS, Inc. (Tt-BAS) was responsible for 
completion of the Design.  Tt-BAS was also responsible for development of the Contract 
Drawings and Specifications.  The address and contact name for Tt-BAS is provided below: 
 
Tetra Tech BAS, Inc. 
R. Todd Livermore, P.E. 
22601 N 19th Ave, Suite 225 
Phoenix, AZ 85027 
Phone: (602) 267-0336 
Fax: (602) 267-0446

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 4 of 10 
The ENGINEER shall be responsible for all CQA observation, testing, and documentation 
related to the north cell excavation, construction of the berms including drainage 
systems, perimeter roadways, and placement and compaction of all earth material 
backfill.  The ENGINEER shall be responsible for issuing daily reports, oversight of field and 
laboratory testing, data evaluation, issuance of documentation reports, attendance at 
and recording of construction progress meetings, informing the CONTRACTOR and the 
OWNER regarding the construction compliance evaluation, and oversight of testing for 
deficiency repairs identified during construction of the berms and stockpiles. 
 
The ENGINEER will also be responsible for addressing all concerns or questions which may 
arise as to the interpretation of the Contract Drawings, grading, design elements, 
Specifications, material evaluation, and testing.  In interpreting the Contract Drawings 
and Specifications, the ENGINEER may make modifications to the Work, which shall not 
involve extra work and shall not be inconsistent with the intent of the Work.  In cases 
where modifications are necessary to comply with Site conditions, unforeseen 
circumstances, changed conditions, or in emergency situations endangering life or 
property, the ENGINEER may, upon OWNER approval, modify the Contract Drawings and 
Specifications.  In such cases the CONTRACTOR shall be compensated at the rate 
previously established by the Contract Bid. 
 
CONSTRUCTION DOCUMENTATION REPORT - The Construction Documentation Report 
(also known as Documentation Report or Certification Report) is prepared by the Designer 
certifying that Project construction has been carried out in general compliance with the 
Contract Drawings and Specifications.  The report shall be signed and stamped by a 
Registered Professional Engineer and shall contain: 
 
• 
Project description; 
• 
All CQA testing and results, including test procedures; 
• 
Deficiencies and protocol used to repair the deficiencies; 
• 
Photographic documentation; and, 
• 
As-built drawings, noting deviations from the Contract Drawings. 
 
PROJECT PLANS - The Project Plans (also known as Drawings, Project Drawings, or 
Standard Drawings) shall be either black-and-white or blue-line copies with the original 
signature and seal of a Registered Professional Engineer, prepared for the construction of 
this Project and attached to the bid documents.  The Project Plans shall also include any 
modifications, which have been approved by the ENGINEER. 
 
SPECIFICATIONS - The Specifications (also known as the Project Specifications) are the 
documents which provide detailed provisions and requirements for performance of the 
prescribed Work.  The approved Specifications for the project are intended to be

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 5 of 10 
interpreted in the context of the General Conditions, Special Provisions and 
Supplementary Conditions. 
 
1.03 
REFERENCES 
 
Reference is made to test procedures of the American Society for Testing and Materials 
(ASTM).  Other documents referred to include the Drawings, Specifications, Engineering 
Drawings, Facility Permit Documents, Safety Regulations, and U.S. EPA’s “Technical 
Guidance Document: Quality Assurance and Quality Control for Waste Containment 
Facilities.” 
 
The pertinent ASTM referenced test standards are provided below: 
 
a) 
ASTM D 422 - Particle Size Analyses for Coarse Fraction of Soil Samples. 
b) 
ASTM D 698 (Standard Proctor)(Standard Effort - 12,400 foot-pound/foot) Test 
Methods for Moisture-Density Relations of Soils and Soil-Aggregate Mixture. 
c) 
ASTM D 1140 - Amount of Materials in Soils Finer than the No. 200 Sieve. 
d) 
ASTM D 1556 - Density and Unit Weight of Soil in Place by Sand-Cone Method. 
e) 
ASTM D 1557 (Modified Proctor) Test Methods for Moisture-Density Relations of Soils 
and Soil-Aggregate Mixture Using a 10-lb (4.54 kg) Rammer and 30-inch (457 mm) 
Drop. 
f) 
ASTM D 2216 - Laboratory Determination of Water Content of Soil and Rock. 
g) 
ASTM D 3087 - Classification of Soils for Engineering Purposes. 
h) 
ASTM D 3088 - Descriptions and Identification of Soils. 
i) 
ASTM D 2922 - Density of Soil and Aggregate In Place by Nuclear Methods (Shallow 
Depth). 
j) 
ASTM D 2937 - Density of Soil In Place by Drive - Cylinder Method. 
k) 
ASTM D 3017 - Moisture Content of Soil and Rock In Place by Nuclear Method (Shallow 
Depth). 
l) 
ASTM D 4220 - Preserving and Transporting Soil Samples. 
m) 
ASTM D 4330 - Liquid Limit, Plastic Limit, and Plasticity Index of Soils. 
n) 
ASTM D 4643 - Determination of Water Content of Soil by Microwave Method. 
o) 
ASTM D 4944 - Determination of Water Content of Soil by Calcium Carbide Gas 
Pressure Tester Method. 
p) 
ASTM D 5080 - Rapid Determination of Percent Compaction. 
q) 
ASTM D 5084 - Measurement of Hydraulic Conductivity of Saturated Porous Materials 
Using a Flexible Wall Perimeter. 
r) 
ASTM D 4546 - One-Dimensional Swell Potential of Remolded Soil Materials.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 6 of 10 
1.04 
DEFINITIONS OF TECHNICAL TERMINOLOGY 
 
Appurtenances: 
Detailed items such as drainage facilities, and items that are 
necessary and related to the proper functioning of the 
Landfill final cover system. 
Atterberg Limits: 
The liquid limit and plastic limit of soil. 
Caliche: 
Gravel, sand, or desert debris cemented by porous calcium 
carbonate; also calcium carbonate itself. 
Clay: 
Soil material with an equivalent mean grain size smaller 
than 0.002 mm.  Clay soils are also defined as plastic fines. 
Clay Clod: 
A chunk of cohesive soil or clay soils (also referred to as 
“clod”). 
Cohesive Soils: 
Soil material, which has a high plasticity index, is sticky, and 
tends to form clods when dry. 
Compaction Curve: 
Plot of dry unit weight versus molding water content, based 
on the data obtained from moisture-density relationship 
tests. 
Dry Density: 
The dry weight of soil material per total volume, including 
air space, also known as dry density.  The dry weight is 
usually measured after drying in an oven at 212 degrees F 
(°F) for 30 hours or until a constant weight is achieved. 
Electrical 
Conductivity: 
Electrical conductivity, abbreviated as EC, of soil is defined 
as the ease at which electrical current flows through soil 
mass.  According to Ohm’s law, EC equals the inverse of the 
electrical resistivity.  In soils, the resistivity of the individual 
soil grains are high and therefore, if there is to be a passage 
of current through a soil mass it will be exclusively through 
electrolytic action due to the presence of dissolved salts 
and solids within the pore spaces of the soil particles.  The 
EC of soil is indicative of the soil’s acidity or alkalinity. 
Geosynthetics: 
Generic term for all geosynthetic materials such as 
geotextiles, 
geomembranes, 
geonets, 
geogrids, 
geosynthetic clay liners, and geocomposites. 
Geotextile: 
A permeable geosynthetic material fabricated with only 
textiles, which may be woven, non-woven, or knitted. 
Gravel: 
Soil material, which is coarser than 4.76 mm in least 
dimension, or retained on a No. 4 sieve.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 7 of 10 
Hydraulic 
Conductivity: 
Also known as permeability, refers to the capacity of a 
material to discharge certain fluids through a material.  
Discharge of fluid through a unit cross-sectional area of a 
porous media under a unit hydraulic gradient, and standard 
temperature of 68 degrees F defines this property. 
Lift: 
Discrete layer of soil (usually 6 to 10 inches thick) placed 
and compacted for construction of engineered fill. 
Liquid Limit: 
The minimum water content of soil at which the soil 
behaves like a viscous liquid.  It is the arbitrary limit 
between the liquid and plastic state of soil. 
NICET: 
An acronym for  the National Institute for Certification in 
Engineering Technologies, an organization that administers 
examinations 
for 
bituminous 
material, 
concrete, 
geosynthetics, and earthen materials for construction. 
Outliers: 
Data points which do not fit into the specified or required 
maxima or minima values. 
Permittivity: 
For a geotextile, the volumetric flow rate of water per unit 
cross-sectional area, per unit head, under laminar flow 
conditions, in the normal direction through the fabric. 
pH of Soil: 
The pH of a soil sample measures the hydrogen-ion 
concentration and is indicative of the soil’s acidity or 
alkalinity. 
Plasticity or Plastic 
Index (PI): 
The range of moisture content of soil in which the soil 
behaves like a plastic solid.  The numerical value is the 
difference between the liquid limit and plastic limits. 
Plastic Limit (PL): 
The minimum water content, above which a soil material 
behaves like a plastic solid. 
Polymer: 
A macromolecular material formed by the chemical 
combination of monomers having either the same or 
different chemical composition.  Plastics, rubbers, and 
textile fibers are all high-molecular-weight polymers. 
 
Polyolefin: 
A family of polymeric materials that includes polypropylene 
and polyethylene, the former being very common in 
geotextiles, the latter in geomembranes.  Many variations 
of each exist.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 8 of 10 
Seam Strength: 
Strength of a seam of geotextile material measured either 
in shear or peel modes.  Strength of seams are reported 
either in absolute units (pounds per inch of width), or as a 
percent of the strength of the geotextiles. 
Unit Weight: 
Weight of soil samples per total volume including air space.  
May include weight of water present within the pore 
spaces. 
 
1.05 
DELINEATION OF RESPONSIBILITES 
 
 
A. 
The following are clarifications of the responsibilities and definitions of job titles 
to be adhered to during the period of time required to complete construction of 
the Project. 
 
B. 
The OWNER (also Operator) is responsible for compliance with all facility permit 
requirements, initiation, progress, and completion of this Project and the 
maintenance of the completed work. 
 
C. 
The OWNER’s Project Engineer (ENGINEER) will decide on all questions which may 
arise as to the compliance and acceptability of materials furnished, work 
performed, and all questions as to the fulfillment of technical and design issues of 
the contract on the part of the CONTRACTOR.  The ENGINEER will make these 
decisions after consultation with the OWNER. 
 
 
The ENGINEER shall be responsible for the acceptance or rejection of work based 
on compliance with the Contract Drawings, Specifications, and design intent; the 
ENGINEER may recommend the suspension of work for unsafe conditions, failure 
to carry out provisions of the Contract by the CONTRACTOR, and for unsuitable 
weather conditions.  The ENGINEER shall also review the CONTRACTOR’S 
submittals, make recommendations, and review/approve the CONTRACTOR’S 
payment requests. 
 
D. 
The ENGINEER shall be responsible for all CQA observation, testing, and 
documentation related to the north cell excavation, construction of the berms 
including drainage systems, perimeter roadways, and placement and compaction 
of all earth material backfill.  The ENGINEER shall be responsible for issuing daily 
reports, oversight of field and laboratory testing, data evaluation, issuance of 
documentation reports, attendance at and recording of construction progress 
meetings, informing the CONTRACTOR and the OWNER regarding the 
construction compliance evaluation, and oversight of testing for deficiency repairs 
identified during construction of the berms and stockpiles.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 9 of 10 
The ENGINEER will also be responsible for addressing all concerns or questions 
which may arise as to the interpretation of the Contract Drawings, grading, design 
elements, specifications, material evaluation, and testing.  In interpreting the 
Contract Drawings and Specifications, the ENGINEER may make modifications to 
the Work, which shall not involve extra work and shall not be inconsistent with 
the intent of the Work.  In cases where modifications are necessary to comply with 
Site conditions, unforeseen circumstances, changed conditions, or in emergency 
situations endangering life or property, the ENGINEER may, upon OWNER 
approval, modify the Contract Drawings and Specifications.  In such cases the 
CONTRACTOR shall be compensated at the rate previously established by the 
Contract Bid. 
 
The ENGINEER’S representative shall issue daily reports containing field 
monitoring such as: 
 
• 
Visual observations; 
• 
CQA test results; 
• 
Deficiencies encountered and retesting results; 
• 
Summary of significant event details; 
• 
Weather conditions; and 
• 
Other field observations deemed necessary for completion of the Project. 
 
E. 
The CONTRACTOR is responsible for quality control (QC) on all work activities 
contained in the Contract Documents.  The CONTRACTOR shall complete all work 
in accordance with the Project Plans, Specifications, CQA Plan, and Project 
Schedule (see Section A01010 – Project Schedule). 
 
The CONTRACTOR has overall control over construction operations; including level 
of effort and site safety.  The CONTRACTOR is also responsible for informing the 
OWNER and the ENGINEER of scheduling and occurrence of all construction 
activities.  The CONTRACTOR is responsible for the work performed by 
Subcontractor(s), if any.  This includes requiring Subcontractor(s) to comply with 
the HASP. 
 
The CONTRACTOR is responsible for the excavation, clearing, and construction of 
engineered fills and soil stockpiles, including excavation, processing and moisture 
conditioning, transportation of soil from the excavation to the stockpile locations, 
drainage facilities, and perimeter roadways, as contained in the Contract 
Documents, or as deemed necessary and in accordance with the Specifications.  
The CONTRACTOR is also responsible for coordinating his/her work with the 
ENGINEER, OWNER, and other related parties.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 10 of 10 
1.06 
QUALIFICATIONS AND TRAINING 
 
NOT USED 
 
 
2.0 
PRODUCTS 
NOT USED 
 
 
3.0 
EXECUTION 
 
NOT USED 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01019 - 1 of 2 
SECTION A01019 
MOBILIZATION AND DEMOBILIZATION 
 
 
1.0  
GENERAL 
 
1.01 
SECTION INCLUDES 
 
A. 
Mobilization of all construction equipment, materials, supplies, appurtenances, 
and the like, manned and ready for commencing and performing the Work.  
Mobilization will include assembly of equipment, or delivery of materials/supplies 
necessary for performance of the Work but which are not intended to be 
incorporated in the Work; preparation of the CONTRACTOR’S work area; 
preparation of a refueling area; personnel services preparatory to commencing 
actual Work (sanitary facilities, jobsite trailer, etc.); and all other preparatory 
Work required to permit commencement of actual Work for which payment is 
provided under the Contract. 
 
B. 
Subsequent removal from the Site of all construction facilities, equipment, 
materials, supplies, appurtenances, and the like; and cleaning and restoration of 
the Site upon completion of the Work to its original condition. 
 
1.02 
RELATED SECTIONS 
 
A. 
This section supplements the requirements specified in the Contract Documents.  
The CONTRACTOR shall obtain construction water and provide their own water 
storage tank in accordance with Section A01050, 3.14. 
 
 
2.0  
PRODUCTS 
 
NOT USED 
 
 
3.0 
EXECUTION 
 
NOT USED

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01019 - 2 of 2 
4.0  
MEASUREMENT AND PAYMENT 
 
4.01 
MEASUREMENT 
 
A. 
Mobilization and Demobilization: Measurement for payment for mobilization and 
demobilization will be by the lump sum basis. 
 
4.02 
PAYMENT 
 
A. 
Mobilization and Demobilization: Payment for mobilization and demobilization 
will be by the lump sum basis.  This task includes any and all temporary facilities 
and utilities, safety plans, permits, and construction equipment required for this 
project.  Twenty five (25) percent of the lump sum price bid will be paid with the 
first payment request following satisfactory evidence of mobilization of sufficient 
labor, equipment and material to adequately progress the work of this contract.  
Twenty-five (25) percent of the lump sum price bid will be paid with the second 
payment request.  Fifty (50) percent of the lump sum price bid will be paid with 
the Final Payment request after final acceptance of all Work.  The bid price of this 
item shall not exceed three (3) percent of the original total bid or contract 
amount. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 1 of 11 
SECTION A01025 
MEASUREMENT AND PAYMENT 
1.0  
GENERAL 
This section includes the items of work and the basis of payment for these items.  The 
CONTRACTOR shall bid items 1 through 14 below separately and provide a total sum for all work 
items.  The CONTRACTOR is responsible for supplying all materials and labor necessary for the 
complete construction and installation of all work as described in these specifications and as 
shown on the Construction Drawings.  Payment for each work item will be made on either a 
unit price or lump sum basis, and only after that portion of the project has been completed. 
Arrangements for construction water are the CONTRACTOR’s responsibility.  The CONTRACTOR 
is specifically reminded of the need to obtain the necessary environmental permits or file the 
necessary environmental notices.  Copies of these permits and notices must be provided to the 
City’s Project Manager prior to starting the permitted activity.  This provision does not 
constitute an assumption by the OWNER of an obligation of any kind for violation of said permit 
or notice requirements. 
Required construction water (see Section A01500 – 3.14 Construction Water) and fine grading 
of fill shall be considered incidental to the Work. 
1.01 
CONTRACT PAY ITEMS 
A. 
Proposal Item 1 - Mobilization and Demobilization 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS). The Work required for this item 
will be measured on the basis of satisfactory evidence of mobilization of 
sufficient labor, equipment and material to adequately advance the 
Work. 
2. 
Payment 
Basis of Payment: The Lump Sum Price for Mobilization and 
Demobilization shall be payment in full for, but not limited to, all labor, 
equipment, material and other incidentals to the site, as well as 
CONTRACTOR provided utilities and ongoing related expenses, 
considered normal for administration of the Work.  Twenty-five (25) 
percent of the Lump Sum price bid will be paid with the first payment 
request following satisfactory evidence of mobilization of sufficient

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 2 of 11 
labor, equipment and material to adequately progress the Work of this 
contract.  Twenty-five (25) percent of the Lump Sum price bid will be paid 
with the payment request subsequent to the payment request in which 
the initial payment for this item is made. Fifty (50) percent of the Lump 
Sum price bid will be paid with the Final Payment request.  The price bid 
in the proposal for this item shall not exceed three (3) percent of the 
original total bid or contract amount. 
B. 
Proposal Item 2 – Project Survey 
 
 
 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS). The Work required for this item 
will be measured on a lump sum basis. 
 
 
2. 
Payment 
Basis of Payment: The Lump Sum Price for Survey.  The CONTRACTOR 
shall employ a licensed Arizona surveyor to perform the layout and as-
builts of the project.  Survey’s documenting the amount of soil excavated 
shall be submitted to the OWNER and ENGINEER on a monthly basis.  Full-
size as-built drawings stamped by a licensed Arizona surveyor shall be 
provided by the CONTRACTOR.  As-built data shall be provided in an 
AutoCAD compatible electronic format.  This item shall be paid monthly 
based on the percentage of work completed. 
C. 
Proposal Item 3 – AZPDES/SWPPP/Dust Control Permits and Temporary Facilities 
and Controls 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS). 
2. 
Payment 
Basis of Payment: This item shall be paid monthly based on the 
percentage of work completed for obtaining and executing the provisions 
of AZPDES/SWPPP and Dust Control permit from Maricopa County for the 
construction activities relating to this Work. 
A completed (typed) NOI shall be submitted to the ENGINEER at the 
preconstruction conference.  See the Section AZPDES Compliance in the 
Information for Bidders.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 3 of 11 
A monthly Stormwater Pollution Prevention Plan (SWPPP) Report must 
be submitted with each Progress Payment.  Failure to submit this report 
will cause rejection of the payment request. 
A completed (typed) Notice of Termination (NOT) shall be submitted to 
the ENGINEER at final acceptance.  See the Section AZPDES Compliance 
in the Information for Bidders. 
D. 
Proposal Item 4 – Traffic Control 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS). 
2. 
Payment 
Basis of Payment: This item shall be paid monthly based on the 
percentage of work completed for obtaining and executing traffic 
control. 
E. 
Proposal Item 5 – Excavate, Haul, and Stockpile to North Cell 
Note: The CONTRACTOR shall place excavated soil stockpiles in the following 
locations at the direction of the OWNER: 
1. 
Measurement 
Basis of Measurement: Cubic Yard (CY). The CONTRACTOR shall provide 
a base line survey for the OWNER’S review and acceptance prior to 
beginning excavation.  Measurement of excavation will be made by 
comparing pre-construction base line topography with the monthly 
surveyed topography.  Survey will establish existing grades at a maximum 
100-foot grid and establish major grade breaks.  Calculations will be made 
by AutoCAD comparison between base line topography and surveyor 
provided monthly topography.  Required construction water and fine 
grading of fill shall be considered incidental to this item.  No load counts 
will be used for payment.  The CONTRACTOR shall provide all survey data 
used for volume calculations to the OWNER and ENGINEER. 
2. 
Payment 
Payment will be made for material excavation on a cubic yard basis.  The 
cost shall include moisture conditioning, material processing and 
segregation, 
excavation, 
screening, 
hauling, 
grading/shaping, 
compaction, vehicles, labor, and all other items necessary to complete

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 4 of 11 
the Work.  The overall quantity to be excavated will be based on the 
difference between the current north area topography (base line) and 
the final elevations shown on the Contract Drawings.  The CONTRACTOR 
must independently verify and agree to the cubic yardage quantity to be 
excavated prior to bid submittal.  The cost per cubic yard excavated will 
be the sole means of payment, including moisture conditioning, material 
processing and segregation, excavation, hauling, grading/shaping, 
compaction, vehicles, labor, and all other items necessary to complete 
the Work. 
F. 
Proposal Item 6 – Excavate, Haul, and Stockpile to South Cell 
Note: The CONTRACTOR shall place excavated soil stockpiles in the 
following locations at the direction of the OWNER: 
2. 
Measurement 
Basis of Measurement: Cubic Yard (CY). The CONTRACTOR shall provide 
a base line survey for the OWNER’S review and acceptance prior to 
beginning excavation.  Measurement of excavation will be made by 
comparing pre-construction base line topography with the monthly 
surveyed topography.  Survey will establish existing grades at a maximum 
100-foot grid and establish major grade breaks.  Calculations will be made 
by AutoCAD comparison between base line topography and surveyor 
provided monthly topography.  Required construction water and fine 
grading of fill shall be considered incidental to this item.  No load counts 
will be used for payment.  The CONTRACTOR shall provide all survey data 
used for volume calculations to the OWNER and ENGINEER. 
2. 
Payment 
Payment will be made for material excavation on a cubic yard basis.  The 
cost shall include moisture conditioning, material processing and 
segregation, 
excavation, 
screening, 
hauling, 
grading/shaping, 
compaction, vehicles, labor, and all other items necessary to complete 
the Work.  The overall quantity to be excavated will be based on the 
difference between the current north area topography (base line) and 
the final elevations shown on the Contract Drawings.  The CONTRACTOR 
must independently verify and agree to the cubic yardage quantity to be 
excavated prior to bid submittal.  The cost per cubic yard excavated will 
be the sole means of payment, including moisture conditioning, material 
processing and segregation, excavation, hauling, grading/shaping, 
compaction, vehicles, labor, and all other items necessary to complete 
the Work.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 5 of 11 
G. 
Proposal Item 7 – General Fill for Haul Roads (Excavate and Place) 
1. 
Measurement 
Basis of Measurement: In-place Cubic Yard (CY). Measurement of general 
fill will be made by comparing base line topography with post-
construction topography when haul road construction is complete.  
Surveys will establish existing grades at a maximum 100-foot grid and 
establish major grade breaks.  Calculations will be made by AutoCAD 
comparison between the base line topography and surveyor provided 
topography when haul road construction is complete.  Required 
construction water and fine grading of haul roads shall be considered 
incidental to this item. 
2. 
Payment 
Basis of Payment: shall be payment in full for, but not limited to, all costs 
to excavate, screen and/or process, condition, control dust, load, haul, 
place, moisture condition, compact, fine grade and maintain as shown on 
the Drawings and in accordance with the Specifications. 
H. 
Proposal Item 8 – Haul, Place and Maintain Asphalt Millings on Haul Roads 
 
 
1. 
Measurement 
Basis of Measurement: In-place Square Yard (SY) at 6-inch thickness. 
Measurement of asphalt millings will be made by inspection and 
verification of designated 6-inch depth and overall length and width of 
haul road to arrive at the square yardage quantity of 6-inch depth of 
asphalt millings in-place. 
2. 
Payment 
Basis of Payment: shall be payment in full for, but not limited to, all costs 
to haul, place, compact, fine grade and maintain as shown on the 
Drawings and in accordance with the Specifications. 
I. 
Proposal Item 9 – Safety Barriers (Purchase and Install) 
 
 
1. 
Measurement 
Basis of Measurement: In-place Linear Foot (LF). Measurement of safety 
barrier will be made by inspection and verification of designated length 
of installed safety barrier. 
2. 
Payment

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 6 of 11 
Basis of Payment: shall be payment in full for, but not limited to, all costs 
to obtain, haul, and place as shown on the Drawings and in accordance 
with the Specifications.  OWNER will retain ownership of all K-rail (safety 
barrier) at project completion. 
J. 
Proposal Item 10 – Riprap V-Ditch 
 
 
1. 
Measurement 
Basis of Measurement: In-place Linear Foot (LF). Measurement of riprap 
v-ditch will be made by inspection and verification of designated length 
of installed riprap v-ditch. 
2. 
Payment 
Basis of Payment: shall be payment in full for, but not limited to, all costs 
to obtain materials, haul, moisture condition, place, and fine grade as 
shown on the Drawings and in accordance with the Specifications. 
K. 
Proposal Item 11 – Riprap Splash Pad 
 
 
1. 
Measurement 
Basis of Measurement: Each (EA). Measurement of riprap splash pad will 
be made by inspection and verification installed riprap splash pad. 
2. 
Payment 
Basis of Payment: shall be payment in full for, but not limited to, all costs 
to obtain materials, haul, and install as shown on the Drawings and in 
accordance with the Specifications. 
L. 
Proposal Item 12 –Stormwater Crossings 
 
 
1.  
Measurement 
Basis of Measurement: Each (EA). Measurement will be made by 
inspection and verification of installed stormwater crossings. 
2. 
Payment 
Basis of Payment: shall be payment in full for, but not limited to, all costs 
to obtain, and install as shown on the Drawings and in accordance with 
the Specifications. 
M. 
Proposal Item 13 – Relocate Asphalt Millings

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 7 of 11 
 
 
1. 
Measurement 
Basis of Measurement: Cubic Yard (CY). Measurement of asphalt millings 
will be made using pre-construction topography of existing surrounding 
grade compared to topography of asphalt millings within the excavation 
boundary. Calculations will be made in AutoCAD between surrounding 
grade compared to the topography of the asphalt millings pile within the 
excavation boundary. 
2. 
Payment 
Basis of Payment: shall be payment in full for, but not limited to, all costs 
to haul, place, compact, fine grade and maintain as shown on the 
Drawings and in accordance with the Specifications. 
N. 
Proposal Item 14 – New Waterline Valve Vaults 
 
 
1. 
Measurement 
Basis of Measurement: Each (EA). Measurement will be made by 
inspection and verification of installed waterline valve vaults. 
2. 
Payment 
Basis of Payment: shall be payment in full for, but not limited to, all costs 
to obtain, and install as shown on the Drawings and in accordance with 
the Specifications. 
O. 
Proposal Item 15 – Fuel Cost Adjustment (Owners Contingency) 
 
 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS).  Refer to Subsection 1.07 of this 
Section. 
 
 
2. 
Payment 
Basis of Payment: This item shall be payment in full for, but not limited 
to provide a contingency fund for the OWNER.  Depending upon the 
outcome of the Project, these funds may not be expended.  Refer to 
Subsection 1.07 of this Section. 
1.02 
LOAD COUNTS AND DELIVERY TICKETS 
A. 
Load counts shall not be used as an acceptable means of measuring any and/or 
all material fills or excavation quantities for payment.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 8 of 11 
B. 
Any delivery tickets, concrete tickets, scale/weight tickets and invoices shall not 
be used for an acceptable means of measuring any and/or all quantities for 
payment purposes. 
1.03 
NON PAY ITEMS 
A. 
No separate payment will be made for items not specifically set forth in the bid 
proposal.  Include costs of such items in prices named in the bid proposal for 
identified items of Work.  Items of Work described in the Contract Documents, 
but not listed in the schedule of Work items of the bid form are, in general, 
applicable to more than one listed Work item.  No separate Work item is 
provided.  The CONTRACTOR shall include costs of Work not listed but necessary 
to complete the project per the Contract Documents in the listed Work items of 
the bid form.  The CONTRACTOR shall not use bid proposal item “Owner 
Allowance for Extra Work” without prior written approval of the ENGINEER. 
1.04 
TOTAL COST 
A. 
Bids for Work are intended to establish a total cost for the Work in its entirety.  
Should the CONTRACTOR feel that the cost for the Work has not been 
established by specific items in the bid form, the CONTRACTOR shall bring this to 
the attention of the ENGINEER or OWNER via email no later than 10 days prior 
to bid opening so that addendum and/or clarification as to whether such work 
is to be considered strictly as incidental or is to be included in a certain or new 
bid item may be issued and that his/her bid proposal reflects the total cost for 
completing the Work in its entirety. 
1.05 
QUANTITY OVERRUNS 
A. 
No payment will be made for quantity overruns unless the Work is expressly 
required by the Contract Documents and authorized in writing by the OWNER or 
ENGINEER prior to the performance of the Work. 
1.06 
PAYMENT 
A. 
The CONTRACTOR shall be bound by the pricing contained on and submitted 
with the project bid sheet. 
B. 
No extra monetary compensation or additional time will be authorized for claims 
that conditions differ from those anticipated.  It is the CONTRACTOR’s 
responsibility to make his own determination as to the actual existing conditions. 
C. 
No extra monetary compensations or additional time will be authorized for the 
removal, handling, or disposal of construction debris or waste/refuse.  Cost for 
this work shall be included in the bid price.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 9 of 11 
D. 
No additional and/or extra compensation will be given for all and/any increases 
to direct labor costs, subcontract costs, and costs of materials and equipment.  
The only exception to this is a Fuel Cost Adjustment as described in subsection 
1.07 of this Section. 
1.07 
FUEL COST ADJUSTMENT 
A. 
GENERAL 
a. The ENGINEER will adjust monthly progress payments up or down as 
appropriate for cost fluctuations in diesel fuel as determined in 
accordance with these special provisions. 
b. A fuel cost adjustment will be made when fluctuations in the price of 
diesel fuel, in excess of 15 percent, occur throughout this contract.  The 
ENGINEER will not provide such adjustments for fluctuations in the price 
of diesel fuel of 15 percent or less. 
c. No adjustments will be made for fluctuations in the price of fuels other 
than diesel. 
B. 
MEASUREMENT 
a. The base index price of fuel will be determined by the ENGINEER from 
the selling prices of diesel fuel published by OPIS (Oil Price Information 
Service).  The base index price to be used will be the price for Diesel fuel 
No. 2, Ultra Low Sulfur, PAD 5, City of Phoenix Rack.  The reported 
average value for the Phoenix area will be used. 
b. The base index price for each month will be the arithmetic average of the 
selling price for diesel fuel, as specified above, shown in the last four 
reports received prior to the last Wednesday of the month. 
c. This price will be effective as of the last Wednesday of each month.  The 
current price may be seen at the following website: 
https://www.azdot.gov/business/ContractsandSpecifications/PriceAdju
stmentforBituminousMaterialandDieselFuel 
d. This price will be deemed to be the "initial cost" (IC) for diesel fuel on 
projects for which bids are opened during the following month. 
e. The current index price for diesel fuel in subsequent months will be the 
base index price, determined as specified above, for the current month.  
For example; an adjustment for diesel fuel used in May, if applicable, will

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 10 of 11 
be based on the “current price” (CP) for May as posted on the last 
Wednesday of May.  The amount of adjustment per gallon will be the net 
difference between the "initial cost," adjusted by 15 percent, and the 
current index price.  The monthly adjustment will be determined by the 
ENGINEER and included in the payment estimate as a fuel adjustment.  
For fluctuations in excess of 15 percent, fuel cost adjustments will only 
be made for current price index increases greater than 1.15 times the 
"initial cost" or for decreases less than 0.85 times the "initial cost."  No 
calculation will be made for fluctuations in the current index price of 15 
percent or less when compared to the "initial cost." 
f. If the Fuel Cost Adjustment applies according to this Section A - GENERAL, 
then the number of gallons of diesel fuel used per month will be 
considered to equal 7.5 percent of the dollar amount of work reported 
by the CONTRACTOR for each month.  Such dollar amount will not include 
revenue accrued in the previous month for fuel price adjustments. 
g. A monthly adjustment, if applicable, will be made on this quantity, as 
shown below: 
 
S =
0.075(Q)
IC
x (CP −AC) 
 
 
 
Where; 
S = Monetary amount of the adjustment (plus or minus) in dollars 
 
 
 
 
Q = Dollar amount of work completed for the month 
 
 
 
 
CP = Current index price in dollars per gallon 
 
 
 
 
AC = Adjusted "initial cost" (1.15 or 0.85 times IC) in dollars per gallon 
 
 
 
 
IC = "Initial cost" as determined above, dollars per gallon 
 
 
 
 
 
As of today’s date, the following values have been determined: 
 
• IC for October 2022 = $3.69/gal 
• AC is calculated to be $3.69*1.15 = $4.24 or $3.69*0.85 = $3.14/gal 
 
h. If adjustments are made in the contract quantities, the CONTRACTOR 
shall accept any fuel adjustment as full compensation for increases or 
decreases in the price of fuel regardless of the amounts of overrun or 
underrun. 
i. The value calculated above (plus or minus) will be adjusted to include 
sales tax and other taxes as applicable.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 11 of 11 
j. No additional compensation will be made for any additional charges, 
costs, expenses, etc., which the CONTRACTOR may have incurred since 
the time of bidding and which may be the result of any fluctuation in the 
base index price of diesel fuel. 
k. No adjustments will be made for work performed after Substantial 
Completion, as defined in Section A01010 Subsection 1.09, has been 
achieved. 
C. 
PAYMENT 
a. Price adjustments will be shown on the monthly progress estimate, 
but will not be included in the total cost of work for determination of 
progress or for extension of contract time. 
1.08 
CONTRACT CONTINGENCY 
A. 
Contract contingency items are provided for the purpose of encumbering funds.  
No work shall be conducted under contract contingency without prior approval 
by the ENGINEER.  The amount, if any, of the contingency item is determined by 
the ENGINEER and is not subject to individual bid pricing.  All bidders shall 
incorporate the amount pre-entered in the bid proposal and shall reflect the 
same in the total amount bid for this project.  This amount may or may not be 
used. 
 
2.0  
PRODUCTS 
NOT USED 
 
3.0  
EXECUTION 
NOT USED 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01030 - 1 of 4 
SECTION A01030 
SPECIAL INSTRUCTIONS 
 
 
1.0  
GENERAL 
 
1.01 
REQUIREMENTS INCLUDED 
 
These instructions are site specific for the Glendale Landfill (GLF) site.  The 
CONTRACTOR shall comply with, but is not limited to, all Special Instructions listed 
in this Section. 
 
1.02 
SMOKING POLICY 
 
Smoking is not allowed at the GLF except in designated areas.  The smoking 
prohibition will be strictly enforced on this project due to the explosive nature of 
landfill gas. 
 
1.03 
SPECIAL CLEAN-UP 
 
Any trash generated on the project site by the CONTRACTOR, or his employees, 
will be cleaned up daily by the CONTRACTOR for disposal onsite (active face of the 
landfill).  Mud and dirt tracked off-site by the CONTRACTOR, his equipment, or his 
employees will be cleaned up daily by the CONTRACTOR.  Facility access roads and 
any other off-site roads will be scraped clean daily and washed down at least once 
per week. 
 
1.04 
LIMITING PUBLIC ACCESS 
 
All necessary precautions including barricades and/or traffic cones will be used to 
prevent the public from entering the working area.  The CONTRACTOR is reminded 
that the landfill is a hazardous area containing heavy equipment and explosive 
gases.   
 
1.05 
BIOHAZARDS 
 
The CONTRACTOR may encounter waste during the course of construction.  Waste 
may contain biohazards such as medical waste or dead animals.  The 
CONTRACTOR’s Health and Safety Plan shall address the potential for contact with 
biohazards and the specific measures to be taken to protect the CONTRACTOR’s 
workers, facility staff, and the public.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01030 - 2 of 4 
1.06 
MATERIALS DELIVERY 
 
The CONTRACTOR is to have all materials delivered to his work site and/or staging 
area.  The OWNER or ENGINEER will not accept delivery of materials. 
 
1.07 
EMERGENCIES 
 
The CONTRACTOR shall provide the ENGINEER with the phone numbers of at least 
two individuals who may be contacted in an emergency on a 24-hour, 7-day per 
week basis, including holidays.  To prepare for emergencies, the CONTRACTOR 
shall ensure that his employees know the location of appropriate fire and first aid 
equipment and emergency phone numbers.  In the event of an emergency, such 
as damage or rupture of an existing gas pipeline, the CONTRACTOR shall 
immediately notify the ENGINEER and/or the Operator.  Should such an 
emergency occur after hours, the CONTRACTOR shall notify the ENGINEER.  This 
is in addition to the CONTRACTOR taking appropriate immediate emergency 
response to correct the problem. 
 
1.08 
GENERAL SAFETY 
 
The CONTRACTOR shall be responsible for maintaining safety on the project site 
in accordance with the provisions of the contract and including OSHA and NFPA 
regulations.  In addition, the CONTRACTOR shall supply all necessary safety 
equipment for his employees and any site visitors.  Tool box safety meetings shall 
be performed a minimum of once per week for all site personnel. 
 
1.09 
SITE FAMILIARIZATION 
 
A. Familiarization 
 
1) Prior to implementing work, the CONTRACTOR shall become thoroughly 
familiar with the site, the site conditions, and all portions of the work 
falling within these Project Specifications and Project Drawings. 
 
B. Inspection 
 
1) If the CONTRACTOR has any concerns regarding the site, the CONTRACTOR 
shall notify the OWNER and ENGINEER in writing within 48 hours of the 
site visit.  Failure to notify the OWNER or the ENGINEER prior to installation 
of items will be construed as CONTRACTOR’s acceptance. 
 
2) The CONTRACTOR shall verify as-built conditions prior to placement 
and/or excavation of any material.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01030 - 3 of 4 
 
 
1.09 
STORM DAMAGE 
 
The CONTRACTOR shall be responsible for the repair of any storm damage to the 
Work prior to the Final Acceptance by the ENGINEER and OWNER.  Storm damage 
of engineered fill slopes and stockpiles will also be responsibility of the 
CONTRACTOR.  Prompt repair of any storm damage shall be the responsibility of 
the CONTRACTOR, at no cost to the OWNER. 
 
1.10 
EQUIPMENT FUELING AND MAINTENANCE 
 
The CONTRACTOR shall fuel and maintain equipment in designated areas of the 
site as directed by the ENGINEER.  The CONTRACTOR shall furnish and use drip 
pans for the fueling of vehicles or equipment.  Any fuel spills will be immediately 
cleaned up, and the contaminated soil removed from the site by the CONTRACTOR 
at the CONTRACTOR’s expense.  The CONTRACTOR will be allowed to place a 
temporary double-wall fuel tank on site, if fuel spill precautions, such as automatic 
fuel nozzle shutoff and visqueen barrier, are in place. 
 
1.11 
PROJECT DOCUMENT CHANGE CONTROL 
 
A structured process for controlling project Plan and Specification changes will be 
implemented by the ENGINEER.  “Controlled” copies of the Plans and 
Specifications will be issued to the CONTRACTOR and OWNER.  These “controlled” 
copies will be updated with any project changes, revisions, or addenda.  The 
ENGINEER will not be responsible for providing changes, revisions, or addenda to 
the Plans and Specifications, other than these “controlled” copies. 
 
1.12 
EXISTING ROADS 
 
The CONTRACTOR will return all existing roads to their original condition after 
completion of the Work.  The CONTRACTOR may be required to obtain and place 
asphalt millings, if the existing roads originally had a layer of millings.  For the 
purpose of replacing asphalt millings roads to their original condition the thickness 
of the original millings layer is assumed to be 6”.  The OWNER will not compensate 
the CONTRACTOR for the cost of returning the existing asphalt millings roads to 
their original condition.   
 
1.13 
HEALTH AND SAFETY PLAN 
 
Prior to proceeding with the construction activities, the CONTRACTOR shall submit 
(for the ENGINEER's approval), a site-specific Health & Safety Plan.  The

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01030 - 4 of 4 
CONTRACTOR shall also allow a period of two weeks for the ENGINEER's review 
time.  During the entire construction activity, the CONTRACTOR shall maintain at 
least one readily available copy of the Health & Safety Plan at the site at all times.  
Site safety is the responsibility of the CONTRACTOR.   
 
 
2.0 
MEASUREMENT AND PAYMENT 
 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025.  
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01050 - 1 of 3 
SECTION A01050 
SURVEYING 
 
 
1.0 
GENERAL 
 
1.01 
COORDINATION 
 
A. 
Work associated with this section includes labor, materials and equipment 
necessary to perform new construction layout and grade staking. 
 
B. 
This section also covers required surveying for the development and maintenance 
of redline and ACAD as-built drawings. 
 
1.02 
RELATED WORK SPECIFIED ELSEWHERE 
 
A. 
All Work covered by the Contract Documents. 
 
1.03 
QUALITY CONTROL 
 
 
A. 
The CONTRACTOR shall use adequate numbers of skilled workers who are 
thoroughly trained and experienced in the necessary skills and who are completely 
familiar with the specified requirements and methods needed for proper 
performance of the Work described in these Specifications.  The CONTRACTOR shall 
utilize a State of Arizona Registered Surveyor. 
 
1.04 
SUBMITTALS 
 
 
A. 
The CONTRACTOR shall submit the following: 
 
1. 
Qualifications of persons proposed to be engaged for surveying services; and 
 
2. 
Certification, signed by the CONTRACTOR’S retained Registered Land Surveyor 
that elevations and locations are in conformance or non-conformance with 
requirements of the Contract. 
 
 
2.0 
PRODUCTS 
 
2.01 
EQUIPMENT AND MATERIALS 
 
 
A. 
Equipment and materials necessary for proper construction surveying will be at 
the CONTRACTOR’S discretion.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01050 - 2 of 3 
3.0 
EXECUTION 
 
3.01 
PROCEDURES 
 
A. 
Basic horizontal and vertical controls are shown on the Contract Drawings.  Three 
survey control points have been shown on the Contract Drawings.  The 
CONTRACTOR shall complete layout of all Work and shall be responsible for all 
requirements necessary for the execution of any Work in accordance with the 
locations, lines, and grades specified or shown on the Contract Drawings, subject 
to such modifications as the ENGINEER may require as work progresses.  
Construction staking shall be done in accordance with industry practice. 
 
 
B. 
The CONTRACTOR shall complete layout of the work and shall be responsible for all 
measurements that may be required for the preparation of the project as-built 
drawings to the location and limit marks prescribed in the specifications or on the 
Contract Drawings.  These locations and limits are subject to such modifications as 
the ENGINEER may require to meet changed conditions or as a result of necessary 
modifications to the Contract Work. 
 
 
C. 
The CONTRACTOR shall furnish, at his own expense, such stakes, templates, 
platforms, equipment, tools and material, and all labor as may be required in laying 
out any part of the work from the survey control.  It shall be the responsibility of the 
CONTRACTOR to maintain and preserve all stakes and other marks established until 
work is complete and record information is satisfactory to the ENGINEER. 
 
 
D. 
The ENGINEER may require Work be suspended at any time when location and limit 
marks established by the CONTRACTOR are not reasonably adequate to permit 
checking of the Work. 
 
 
E. 
The CONTRACTOR shall locate and protect control points before starting work on 
the site. 
 
 
F. 
The CONTRACTOR shall preserve permanent reference points during progress of the 
Work. 
 
 
G. 
The CONTRACTOR shall not change or relocate reference points for the Work 
without specific prior approval from the ENGINEER. 
 
 
H. 
The CONTRACTOR shall promptly advise the ENGINEER when a reference point is 
lost or destroyed or requires relocation because of other changes in the Work. 
 
 
 
1. 
The CONTRACTOR shall, upon direction of the ENGINEER, require the Survey 
Party Chief to replace reference stakes or markers.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01050 - 3 of 3 
 
 
2. 
The CONTRACTOR shall locate replacement stakes or markers according to 
the original survey control. 
 
 
I. 
The CONTRACTOR shall provide to the ENGINEER such surveys and volume 
computations as are necessary to determine the quantities of Work performed or 
placed during each month for which a progress payment is to be made.  All original 
field notes, volume computations and other records for the purpose of layout and 
progress surveys shall be furnished promptly to the ENGINEER at the Site of the 
Work.  A copy of the original notes, computations and records furnished to the 
ENGINEER shall be retained by the CONTRACTOR. 
 
 
J. 
The CONTRACTOR shall provide survey control during the installation of drainage 
structures/runoff collection channels within ±0.1 feet. 
 
 
K. 
The CONTRACTOR shall provide survey control before and after placement for 
structural fill within ±0.1 feet. 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 1 of 5 
SECTION A01052 
LAYOUT OF WORK AND SURVEYS 
 
 
1.0 
GENERAL 
 
1.01 
SUMMARY 
 
A. 
Section includes requirements for survey work to be provided by the 
CONTRACTOR for the following: 
 
B. 
Setting offset stakes, slope stakes, and grade stakes for field layout of features for 
performance of the Work. 
 
C. 
Surveys for measurement of quantities for payment. 
 
D. 
Record Drawings. 
 
1.02 
DESCRIPTION 
 
 
A. 
Reference Points.  The reference points provided by the OWNER include 
monuments and elevation bench marks in the vicinity of the Project.  If displaced 
during the project, replacement of these reference points will be at the expense of 
the CONTRACTOR.  All surveys for record drawings shall tie to a minimum of three 
of these reference points and shall use the site coordinate system previously 
established by the OWNER’s survey and utilized in the Design Plan Drawings. 
 
 
B. 
The OWNER reserves the right to perform any desired checking and correction of 
the CONTRACTOR’s layout work relative to OWNER's surveys but this does not 
relieve the CONTRACTOR of the responsibility for adequate performance of their 
Work. 
 
 
 
C. 
Equipment and Personnel.  Provide instruments and other survey equipment that 
are accurate, suitable for the surveys required in accordance with recognized 
professional standards, and in proper condition and adjustment at all times.  
Perform surveys under the direct supervision of a licensed surveyor. 
 
 
D. 
Field Notes and Records.  Record surveys in field notebooks. 
 
 
E. 
Use by the OWNER.  The OWNER may at any time use line and grade points and 
markers established by the OWNER or CONTRACTOR.  The CONTRACTOR’s surveys

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 2 of 5 
are a part of the Work and may be checked by the OWNER or representatives of the 
OWNER at any time. 
 
1.03 
RELATED SECTIONS 
 
A. 
Section 01025 – Measurement and Payment 
 
 
B. 
Section 01050 – Field Engineering 
 
1.04 
SURVEYS FOR LAYOUT AND PERFORMANCE OF WORK 
 
A. 
CONTRACTOR will perform all surveys for layout of the Work, reduce the field notes, 
make necessary calculations, and prepare drawings necessary to carry out such 
work.  CONTRACTOR’s layout work will include the following: 
 
1. Slope staking for excavations at 25-foot grid, and grade breaks. 
 
2. Blue top for subgrade at 25-foot grid and grade breaks. 
 
3. All as-built surveys specified in Section 01052. 
 
4. Surveys to measure completed units of work specified in Section 01025. 
 
B. 
CONTRACTOR must perform all additional slope staking, off-setting and other 
control staking necessary to perform the Work. 
 
1.05 
SURVEYS FOR RECORD DRAWINGS AND MEASUREMENT FOR PAYMENT 
 
A. 
When the Specifications require items of work to be measured by surveying 
methods, the CONTRACTOR will perform the surveys and perform necessary 
calculations to determine payment quantities.  The ENGINEER may perform 
independent checks. 
 
B. 
Items requiring surveys for determining pay quantities are given in Section 01025, 
Measurement and Payment. 
 
C. 
The Surveyor shall prepare drawings for each layer of the lining system (subgrade, 
top of compacted soil, and top of protective soil layer).  Points shall provide a 
comparison of the design elevation against the actual elevation at each point.  
Points shall be established on a 50-foot maximum grid.  Additionally, points shall be 
established at major changes in grade, changes in alignment, along flow lines, and 
at any specific points shown in the Drawings.  The difference in design versus

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 3 of 5 
constructed elevation for each point shall not exceed the tolerance described in 
Section 01050 paragraph 1.5. 
 
D. 
Provide the OWNER with Record (As-Built) Drawings.  Separate and distinct sheets 
shall be provided depicting existing conditions, top of subgrade/finished earth 
surface, top of containment system, and top of protective cover.  Sheets shall 
include the following items: 
 
1. Topography that depicts North Cell (NC) Earthwork grading at the start 
of construction and following excavation and fills.  In the event the 
CONTRACTOR must excavate below the design subgrade as required by 
these specifications or to remove unsuitable material (at the direction 
and approval of the ENGINEER or OWNER), CONTRACTOR shall provide 
as-built survey of the final excavated limits and grades, the limits of fill 
and grades after placement of engineered fill to establish subgrade and 
the final grade. 
 
2. Staking points, grade breaks and limit lines of earthwork as shown in the 
Design Drawings. 
 
3. Staking points, grade breaks and limits of liner as shown in the Design 
Drawings.  Where not coincident, limits shall be provided for 
geomembrane, GCL, and geotextile, including anchor trench alignment 
and temporary liner terminations (special attention to be given to 
specific as-built points as required in the Construction Drawings. 
 
4. Staking points, grade breaks and limits of operations layer as shown in 
the Design Drawings. 
 
5. Limits and Grades of earthwork in the perimeter berm.  Include staking 
points, grade breaks, and points of change in surface material. 
 
6. Miscellaneous Items - CONTRACTOR’S Surveyor shall include the 
following as-built information on one of the sheets identified above (as 
appropriate) or shall provide additional sheets, as needed.  The specific 
sheet for each element shall be as approved by the OWNER. 
 
a. Location and alignment of buried utilities and buried culverts. 
 
b. Initial and finish grades for storm water control features. 
 
c. Limits of temporary or permanent access roads.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 4 of 5 
d. Subgrade and finished grade of temporary or permanent access 
roads. 
 
e. Stockpile limits and grades (pre- and post-construction). 
 
f. Final site as-builts showing contours and any other miscellaneous 
constructions including fence, wells, probes, electrical, etc. 
 
g. OWNER-provided reference points shall be shown on all 
applicable as-built drawing sheets. 
 
E. 
Surveyor shall provide a Text/ASCII file containing all collected as-built locations.  As-
built drawings shall depict all collected locations with an associated point reference 
number such that points in the provided Text/ASCII file can be referenced on the 
drawings. 
 
F. 
Surveyor shall submit certified top of subgrade as-built point drawings within 2 days 
of completion of the subgrade.  Where applicable, Surveyor shall provide certified 
top of compacted soil as-built point drawings within 2 days of completion of this 
layer. These submittals must be approved by the OWNER before installation of the 
next liner component begins.  In order to avoid project delays, the Surveyor may 
provide submittals for portions of each completed surface for approval; however, a 
final consolidated drawing of each surface shall be provided at the completion of 
each surface. 
 
G. 
All final as-built topographic survey drawings are due within 10 days after 
Substantial Completion date. 
 
H. 
Provide sealed as-built survey drawings on a 22” x 34” bond print at same horizontal 
and vertical scale, same coordinate system, same stationing, and same orientation 
for each element as shown on the design drawings.  Provide as-built survey 
information and associated point data on the same datum and coordinate basis as 
design drawings.  All point data must have clear, easy to understand descriptions.  
Provide all point data in Text/ASCII format, printed and on compact disk (CD) or DVD 
along with list of descriptor abbreviations.  All information provided must be 
accompanied with a letter explaining what is being submitted and a list of what 
information is given in each CD/DVD.  Submit all survey information of any layer to 
the OWNER before that layer is covered. 
 
I. 
Surveyor shall provide all drawings in electronic format.  Provide information in 
AutoCAD 2018 or higher format in accordance with OWNER’S drafting standards.  
Surveyor shall also provide documents in Adobe .pdf format.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 5 of 5 
J. 
Submit survey information for items listed above to the OWNER before the items 
are covered. 
 
K. 
Provide surveys to measure the following items: 
 
1. Volume of Excavation; 
 
2. Volume of Engineered Fill; 
 
3. Volume of Unsuitable Material removed from the NC area below the 
design subgrade and replaced with Engineered Fill; 
 
4. Volume of General Fill; 
 
5. Volume of Screen Berm Fill; 
 
6. Area of Liner Subgrade Preparation; 
 
7. Volume of Operations Layer placement; 
 
8. Length of Anchor Trench (each type); 
 
9. Length of Liner Termination (each type); 
 
10. Area of GCL, HDPE Liner, and geotextile placement.  Area will be to the 
hinge point/limit of waste as shown on the drawings only and will not 
include the material in the run-out or anchor trench itself;  
 
11. Area of LCRS Gravel placement; and 
 
12. Length of HDPE Leachate Collection Drain and Risers, for each diameter 
and material (perforated or solid). 
 
2.0 
PRODUCTS 
 
 
Not Used. 
 
3.0 
EXECUTION 
 
 
Not Used. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01106 - 1 of 2 
SECTION A01106 
COORDINATION AND MEETINGS 
 
 
1.0 
GENERAL 
 
This section provides information on coordination, pre-construction meeting, progress meetings, 
and resolution meetings during construction. 
 
1.01 
COORDINATION 
 
A. 
The CONTRACTOR shall coordinate his work schedule, submittals, and various 
works to ensure an efficient sequence of the Work and material. 
 
B. 
The CONTRACTOR shall coordinate with the OWNER, ENGINEER, and other 
involved parties with regard to the Work, safety, and utilization of the Site.  The 
project will require open and continuous communication. 
 
1.02 
PRE-CONSTRUCTION MEETING 
 
A. 
A pre-construction meeting will be held at the project Site, which will be scheduled 
by the ENGINEER in consultation with the OWNER, and the CONTRACTOR. 
 
B. 
The meeting will be attended by the ENGINEER, the OWNER, and the CONTRACTOR.  
The ENGINEER shall conduct the meeting and will take minutes of the meeting. 
 
1.03 
PROGRESS MEETINGS 
 
 
A. 
Upon the request of the ENGINEER, progress meetings shall be held at the Site.  
These meetings shall occur every other week.   
 
 
B. 
The progress meetings will be attended by the ENGINEER, the OWNER, the 
CONTRACTOR, and if necessary, other affected parties. 
 
 
C. 
The agenda of the meetings and meeting minutes will be provided by the ENGINEER. 
 
1.04 
RESOLUTION MEETING(S) 
 
 
A. 
To resolve conflicts, discrepancies, and differences of opinion, the ENGINEER shall 
convene Resolution meetings.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01106 - 2 of 2 
 
B. 
Resolution meetings shall be attended by the affected parties. 
 
 
C. 
The agenda of Resolution meetings shall depend on circumstances. 
 
1.05 
DISPUTE RESOLUTION 
 
All claims, disputes and other matters in question between the OWNER and the 
CONTRACTOR arising out of, or relating to the Contract Documents, or the breach thereof 
will be decided by binding, unappealable arbitration, if the claim for compensation, costs 
and expenses or damages is equal or less than $50,000.  The CONTRACTORS sole legal 
remedy in relation to claims of $50,000 or less shall be binding, unappealable arbitration. 
 
All arbitration of claims shall be conducted in Glendale, Arizona, in accordance with the 
Uniform Rules of Procedure for Arbitration adopted by the Arizona Supreme Court (Court 
Rules) except for any rules therein allowing or concerning appeal.  Where necessary to allow 
arbitration to proceed, the OWNER and CONTRACTOR shall execute an Agreement of 
Reference consistent with the provisions of this paragraph and the Uniform Rules as 
modified by this paragraph. 
 
If any provision of the Agreement is held by a court of competent jurisdiction to be invalid, 
void or unenforceable, the remaining provisions shall nevertheless continue in full force 
without being impaired or invalidated in any way. 
 
Should either party to the Agreement begin an action to enforce any provision of the 
Agreement, the prevailing party shall be entitled to recover reasonable attorney’s fees and 
costs in connection therewith.  Except as otherwise specifically provided in the Contract 
Documents, no action or failure to act by the OWNER, ENGINEER, Designer, or 
CONTRACTOR shall constitute a waiver of any right or duty afforded any of them under the 
Contract Documents nor shall any such action or failure to act constitute an approval of or 
acquiescence in any breach thereof. 
 
 
No payment will be made for meetings.  The bid price shall include the cost that may be 
incurred to attend and conduct any and all meetings and provide coordination. 
 
2.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025.  No payment will be made for meetings.  The bid price shall include the 
cost that may be incurred to attend and conduct any and all meetings and provide 
coordination. 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 1 of 6 
SECTION A01310 
CONSTRUCTION WORK PLAN AND SCHEDULE 
 
1.0  
GENERAL  
1.01 
PRELIMINARY WORK PLAN AND SCHEDULE 
A. 
The CONTRACTOR shall prepare and submit at the pre-construction meeting, a 
Work Plan and construction schedule. 
B. 
The ENGINEER will review the preliminary Work Plan and construction schedule 
prior to the commencement of construction activities. 
C. 
The CONTRACTOR may be interviewed by the ENGINEER to determine the 
CONTRACTOR’S understanding of the project, and ability to complete the work in 
a timely and efficient manner. 
D. 
The CONTRACTOR shall submit copy of Arizona Pollutant Discharge Elimination 
System (AZPDES) and earthmoving permit at Pre-construction meeting. 
1.02 
CONTRACTOR’S WORK PLAN CONTENTS 
A. 
The CONTRACTOR shall include with Work Plan a drawing detailing various work 
areas, CONTRACTOR’S utilities, phasing of work, excavation, testing, and any other 
information related to proposed operations. 
B. 
The CONTRACTOR shall describe personnel, equipment, and procedures required 
to accomplish specific items of work, including: 
1. 
Method of coordinating Subcontractors, if any, and maintaining project 
schedule. 
2. 
Methods and routes for moving and stockpiling materials on site. Include 
detailed drawings showing haul routes and logistics.  
3. 
Methods for reducing or increasing the moisture content of wet or dry soils 
prior to using them for constructing engineered fills during construction.  
4. 
Methods and equipment for excavating, hauling, and placing materials. 
5. 
Dewatering methods, equipment and schedules. 
6. 
Site drainage during construction.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 2 of 6 
7. 
Methods and equipment for site clearing. 
8. 
Methods for erosion prevention and sediment control. 
9. 
Plans for maintaining as-built information. 
10. 
Health and Safety Plan. 
11. 
Project Schedule. 
12. 
List of Personnel and equipment. 
13. 
List of Subcontractors and Subconsultants. 
14. 
List and organizational chart of project personnel responsibility. 
15. 
Other information required in technical specifications. 
16. 
Emergency action plan and contacts’ telephone numbers. 
17. 
Spill Prevention Control and Countermeasures (SPCC) Plan, if required 
based on quantity of petroleum products stored. 
18. 
Stormwater Pollution Prevention Plan (SWPPP). 
1.03 
CONTRACTOR’S CONSTRUCTION SCHEDULE 
A. 
The CONTRACTOR shall prepare a schedule as described in Section 2.01 and 
meeting overall project scheduling listed Section A01010 1.10 – Project Schedule. 
B. 
The CONTRACTOR shall coordinate schedule with the ENGINEER for the 
CONTRACTOR supplied materials. 
C. 
All Work, including demobilization, shall be complete by February 28, 2023. 
1.04 
PROJECT MEETINGS 
 
A. 
Construction Meetings: 
 
 
1. 
The ENGINEER will conduct construction meetings involving: 
 
 
 
a. 
CONTRACTOR’s Project Manager. 
 
 
 
b. 
CONTRACTOR’s Project Superintendent. 
 
 
 
c. 
OWNER’s designated representative(s). 
 
 
 
d. 
ENGINEER’s designated representative(s).

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 3 of 6 
 
 
 
e. 
CONTRACTOR’s subcontractors as appropriate to the work in 
progress. 
 
 
 
f. 
OWNER’s Construction Quality Control Consultant. 
 
 
2. 
The ENGINEER shall conduct progress meetings every other week. 
 
 
3. 
The ENGINEER will take meeting minutes and submit copies of meeting 
minutes to participants and designated recipients identified at the 
Preconstruction Conference.  
 
 
 
a. 
Corrections, additions, or deletions to the minutes shall be noted 
and addressed at the following meeting. 
 
 
4. 
The ENGINEER will schedule meetings for most convenient time frame. 
 
 
5. 
The ENGINEER will have available at each meeting full chronological files 
of all previous meeting minutes.  
 
 
6. 
The CONTRACTOR shall have available at each meeting up-to-date record 
drawings. 
1.05 
VIDEO RECORDING 
 
A. 
The CONTRACTOR shall provide full access to OWNER or OWNER’s authorized 
representative to perform video recording of construction activities, training 
sessions, start-up, trouble shooting, etc. 
1.06 
CORRESPONDENCE 
 
A. 
The CONTRACTOR will provide a correspondence matrix identifying requirements 
for submitting and sharing correspondence among the parties involved in the 
Project.  
1.07 
SPECIAL CONSIDERATIONS 
 
A. 
The CONTRACTOR shall be responsible for negotiations of any waivers or alternate 
arrangements required to enable transportation of materials to the site.  
 
B. 
Maintain conditions of access road to site such that access is not hindered as the 
result of construction-related deterioration.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 4 of 6 
 1.08 FINAL WORK PLAN 
A. 
The CONTRACTOR shall resubmit the Work Plan to incorporate the information 
discussed during the pre-construction meeting. 
B. 
Work Plan and Schedule Revisions. 
1. 
The CONTRACTOR shall revise Work Plan as necessary to reflect changes 
in scope of work, but no less than once per month. 
2. 
The CONTRACTOR shall show changes occurring since previous submittal. 
a. 
Major changes in scope. 
b. 
Activities modified since previous submittal. 
c. 
Other identifiable changes. 
3. 
The CONTRACTOR shall submit to the ENGINEER. 
2.0  
PRODUCTS 
2.01 
CONSTRUCTION PROGRESS SCHEDULES 
A. 
The CONTRACTOR shall submit initial critical path method (CPM) schedule in 
duplicate at the Pre-construction meeting after date of execution of Agreement.  
The critical path construction tasks shall be clearly identified.   
B. 
Construction operations will be scheduled to allow uninterrupted operation of 
existing adjacent facilities. 
 
 
1. 
The CONTRACTOR shall coordinate connections with existing work to 
ensure timely completion of interfaced items. 
C. 
At no time shall CONTRACTOR or his employees modify operation of the existing 
facilities or start construction modifications without approval of the OWNER 
except in emergency to prevent or minimize damage.  
D. 
Within 10 days prior to construction startup, CONTRACTOR shall submit for 
approval a CPM schedule with the critical path tasks clearly identified.  
1. 
Schedule shall include any information discussed in preconstruction 
meeting.  
2. 
The schedule shall account for schedule of Subcontracts.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 5 of 6 
 
a. 
The schedule shall include proper sequence of construction, 
various crafts, purchasing time, Shop Drawing approval, material 
delivery, equipment fabrication, startup, demonstration, and 
similar time consuming factors.  
3. 
The schedule shall show as a minimum, earliest starting, earliest 
completion, latest starting, latest finish, and free and total float for each 
task or item.  
E. 
The CONTRACTOR shall evaluate schedule as necessary to reflect changes in Scope 
of Work, but no less than bi-weekly. 
 
1. 
Show changes since previous submittal including major scope changes, 
activities modified since previous submittal and other identifiable changes.  
2. 
The CONTRACTOR shall update, correct, and rerun schedule and submit to 
ENGINEER in triplicate with pay application to show rescheduling 
necessary to reflect true job conditions.  
3. 
When shortening of various time intervals is necessary to correct for 
behind schedule conditions, the CONTRACTOR shall indicate actions to be 
implemented in order to accomplish the work in a shorter duration.  
4. 
Information shall be submitted to ENGINEER in writing with revised 
schedule.  
 
a. 
Progress schedules shall be reviewed during progress meetings.  
 
b. 
The CONTRACTOR shall submit a computer-generated graphic type 
schedule with separate line for each item of Work or operation 
identifying first work day of each week.  
 
c. 
The schedule shall show complete sequence of construction by 
activity, identifying Work of separate stages and other logically 
grouped activities.  
 
 
1) 
The schedule shall indicate the early and late start, early 
and late finish, float dates, and duration, and critical items.  
 
d. 
The schedule shall indicate estimated percentage of completion for 
each item of Work at each submission.  
 
e. 
The schedule shall indicate submittal dates and review periods 
required for Shop Drawings, product data, samples, and product 
delivery dates, including those furnished by the OWNER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 6 of 6 
 
f. 
The CONTRACTOR shall coordinate schedule with ENGINEER for 
Engineer supplied information. 
 
g. 
The CONTRACTOR shall coordinate schedule with Work Plan. 
F. 
If CONTRACTOR does not take necessary action to accomplish work according to 
schedule, CONTRACTOR may be ordered by OWNER in writing to take necessary 
and timely action to improve work progress at CONTRACTOR’s expense.  
1. 
OWNER may require increased work forces, extra equipment, extra shifts 
or other action as necessary at CONTRACTOR’s expense.  
2. 
Should CONTRACTOR refuse or neglect to take such action authorized, 
under provisions of this contract, OWNER may take necessary actions 
including, but not necessarily limited to, withholding of payment and 
termination of Contract.  
G. 
The CONTRACTOR shall indicate submittal dates and review periods required for 
shop drawings, product data, samples, and product delivery dates, including those 
furnished by the OWNER. 
H. 
The schedule shall indicate surveys for layout, as-builts, and measurement for 
payment. 
3.0 
EXECUTION  
 
 
NOT USED 
 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
B. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 1 of 6 
SECTION A01400 
QUALITY CONTROL 
 
 
1.0 
GENERAL 
 
1.01 
SUMMARY DESCRIPTION 
 
A. 
This section specifies quality control descriptions and procedures and shall be 
applicable to all office, field, and shop work in the Contract Documents. 
 
1.02 
RELATED WORK SPECIFIED ELSEWHERE 
 
A. 
Section A - General Requirements 
B. 
Section B - Sitework 
 
1.03 
QUALITY CONTROL 
 
A. 
Quality control (QC) refers to the sampling, testing and measuring of all materials 
used at the Site and the verification checking of Contract Drawings and 
Specifications by the CONTRACTOR to ensure that the Work conforms to the 
requirements of the Contract Drawings and Specifications.  QC testing will comply 
with all pertinent codes, regulations and standards referenced within the Contract 
Documents. 
B. 
Unless specifically authorized in writing, no construction shall be started until the 
CONTRACTOR’S QC plan is approved. 
C. 
The CONTRACTOR shall establish and continuously provide a quality control 
system to perform sufficient inspection and testing of all items of Work, including 
that of subcontractors, to ensure conformance to applicable specifications and 
drawings with respect to the materials, workmanship, construction, finish, 
functional performance, and identification.  This control shall be established for 
all construction, except where the Technical Provisions of the contract provide for 
specific control inspections, tests or other means to be performed by the 
ENGINEER.  The CONTRACTOR’S control system shall specifically include the 
surveillance and testing required in the Contract Specifications. 
D. 
The CONTRACTOR’S quality control system is the means by which he assures 
himself that his construction complies with the requirements of the Contract plans 
and specifications.  The controls shall be adequate to cover all construction 
operations and shall be keyed to the proposed construction sequence.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 2 of 6 
E. 
The CONTRACTOR’S job supervisory staff may be used for quality control, 
supplemented as necessary by additional personnel for surveillance, special 
technicians, or testing facilities to provide capability for controls required by the 
Technical Provisions of the specifications.  Prior approval is required for facilities, 
equipment, and personnel used by the CONTRACTOR in performing the specified 
testing. 
 
1.04 
SUBMITTALS 
 
A. 
The CONTRACTOR shall submit to the OWNER and ENGINEER for approval a 
Quality Control Plan which shall include the procedures, instructions, and reports. 
1.05 
NOTICES 
 
A. 
Additional inspection and testing required due to defective work or ill-timed 
notices may be initiated by the ENGINEER and shall be at the CONTRACTOR’S 
expense. 
1.06 
PROJECT COOPERATION 
 
A. 
The CONTRACTOR shall provide representatives of the OWNER and ENGINEER 
access to the Work at all times and at all locations where Work is in progress. 
 
B. 
The CONTRACTOR shall allow the ENGINEER, OWNER, or their representatives 
access and time to conduct Quality Assurance sampling or testing.  Frequencies, 
time, and locations will be at the ENGINEER’s discretion.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 3 of 6 
1.07 
TESTING FREQUENCY 
 
 
A. 
SUBGRADE 
 
1. 
The CQA ENGINEER will perform testing on subgrade surfaces at 
frequencies as shown in the table below: 
 
TESTS AND OBSERVATIONS 
ON SUBGRADE PREPARATION 
 
           Parameter 
Test Method 
Minimum 
Testing 
Frequency 
Percent Compaction 
(Note 1) 
ASTM D 2922 
1 per acre (Note 2) 
Compaction Curve 
ASTM D 1557 
1 per 5 acres, 
1 minimum 
Preparation of 
Previously Compacted 
Lift 
Observation 
Part Time 
 
a. 
Percent compaction is defined as the dry density of the compacted 
soil divided by the maximum dry density measured in the 
laboratory with a specified method of compaction.  The test 
methods listed are for measurement of the dry density of the 
compacted soil.  Compaction shall be a minimum of 90 percent of 
modified proctor in accordance with ASTM D1557. 
 
b. 
At a minimum, at least one test should be performed each day the 
construction personnel prepare subgrade by compaction. 
 
B. 
GENERAL FILL (HAUL ROADS) 
 
1. 
General fill is required for the construction of temporary structures such 
as haul roads, ramps and other fills that will be removed in the future.  
Testing of general fill shall not be required.  These general fills may be 
constructed over the existing waste footprint. 
 
2. 
Compaction of general fill shall be, at a minimum, 85 percent of Modified 
Proctor in accordance with ASTM D1557.  The ENGINEER may perform spot

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 4 of 6 
testing of the fill to determine the actual percent compaction being 
achieved by the CONTRACTOR. 
 
3. 
The CONTRACTOR is responsible for the safety and maintenance of general 
fill structures until the completion of the Work.  After completion of the 
project general fill structures will be the responsibility of the Glendale 
Landfill staff. 
 
 
C. 
ENGINEERED FILL (PERMENANT SLOPES, ALL OTHER FILLS) 
 
1. 
Field Test Methods During Construction 
 
a. 
Testing frequency of structural fill during construction shall be as 
shown in the table below; 
 
ENGINEERED FILL 
 
Parameter 
Test Method 
Minimum Testing 
Frequency 
Water Content 
ASTM D 3017 1/acre/lift and at least 
1 per 1000 yd3 
Density 
ASTM D 2922 1/acre/lift and at least 
1 per 1000 yd3 
Compaction Curve 
ASTM D 1557 
1/5 acres/lift and at 
least 1 per 5000 yd3 
Construction 
Oversight 
Observation 
Part-Time 
 
b. 
Every tenth sample tested with ASTM D3017 should be tested by 
ASTM D4643; 
c. 
For Engineered Fill, compaction shall be a minimum of 90 percent 
of modified proctor in accordance with ASTM D1557; 
d. 
Moisture content shall be in a range of ±2% of the optimum 
moisture content as determined by ASTM D 1557; and 
e. 
The maximum un-compacted lift thickness shall be 10”. 
 
2. 
The CQA ENGINEER will review all CONTRACTOR submittals for 
construction plans, and laboratory results. 
3. 
The CQA ENGINEER will verify that the subgrade has been constructed to

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 5 of 6 
the thickness and final elevation as shown on the Drawings and specified 
herein. 
4 
The CQA ENGINEER will observe the installation of the structural fill to the 
lines and grades indicated on the drawings on a part time basis. 
 
 
D. 
SOIL STOCKPILES 
 
1. 
Testing of the fill during construction of the soil stockpile(s) will not be 
required.  These stockpiles may be constructed over the existing waste 
footprint. 
 
2. 
The daily and intermediate cover stockpile(s) shall be at a nominal 85 
percent of Modified Proctor in accordance with ASTM D1557. 
 
1.08 
DEFICIENCIES 
 
A. 
When deficiencies (items that do not meet specified values) are discovered, the 
ENGINEER shall immediately determine the nature and extent of the problem, 
notify the CONTRACTOR, and complete required documentation.  In all cases, the 
ENGINEER will notify the CONTRACTOR within 1 hour of discovering the 
deficiency.  If the deficiency will cause construction delays of more than 1 hour or 
will necessitate substantial rework, the CQA ENGINEER shall also notify the 
OWNER. 
B. 
The CONTRACTOR shall correct the deficiency to the satisfaction of the ENGINEER 
or OWNER.  If the CONTRACTOR is unable to correct the problem, the ENGINEER 
will develop and present to the OWNER suggested solutions for approval.  The 
corrected deficiency shall be retested before additional work is performed by the 
CONTRACTOR.  All retests and the steps taken to correct the problem shall be 
documented by the ENGINEER. 
 
2.0 
PRODUCTS 
NOT USED 
 
 
3.0 
EXECUTION 
 
NOT USED

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 6 of 6 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 1 of 14 
SECTION A01500 
TEMPORARY FACILITIES AND CONTROLS 
 
1.0  
GENERAL 
1.01 
REQUIREMENTS 
A. 
The CONTRACTOR shall furnish, install and maintain required construction aids 
and barriers as required to prevent public entry, and to protect the Work, 
existing facilities, trees and plants from construction operations and other 
temporary facilities required to complete the Work. 
B. 
The CONTRACTOR shall provide and maintain methods, equipment, and 
temporary construction, as necessary to provide controls over environmental 
conditions at the construction site and related areas under the CONTRACTOR’s 
control. 
C. 
The CONTRACTOR shall remove all temporary facilities at completion of the 
Work or when no longer necessary. 
D. 
The CONTRACTOR shall not interfere with the normal business traffic and the 
operations of the Glendale Landfill including not using customer traffic 
circulation roads. 
E. 
In addition to any other remedy available by law or equity to the OWNER, the 
parties expressly agree that the CONTRACTOR shall be liable for and shall pay to 
the OWNER the sum of five thousand dollars ($5,000.00) for each notice of 
violation and/or citation of a federal, state, county, city, agency, or 
administrative law, rule, regulation, ordinance or court order resulting from the 
CONTRACTOR’s acts, errors, or omissions on the Project.  This sum will be taken 
out of the CONTRACTOR’s Contract with the OWNER.  This sum is in addition to 
any penalty, fine, or fee imposed by a court of law or administrative agency 
related to the notice of violation and/or citation, and in addition to the 
CONTRACTOR’s acts, errors, or omissions on the Project.  The parties expressly 
agree that the sum fixed above is reasonable and approximates the actual 
anticipated loss to the OWNER at the time and making of this agreement in the 
event that a notice of violation and/or citation is levied on the Project.  The 
parties expressly acknowledge and agree to the fixed sum set forth above 
because of the difficulty of proving the OWNER’s actual damages in the event 
that a notice of violation and/or citation is levied on the Project.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 2 of 14 
1.02 
DUST CONTROL 
A. 
Dust control is absolutely critical on this Project. Due to residences and 
institutions in close proximity to this landfill, its operations are under public 
scrutiny at all times. Under Maricopa County’s requirements for an Earthmoving 
Permit, the CONTRACTOR must place a sign for public viewing, with a telephone 
number that can be used by the public to make complaints to the Maricopa 
County Air Quality Department.  Such a call will result in a visit to the site by 
County Dust Enforcement personnel and may result in a Notice of Violation 
(NOV).  Notices of violation are issued to the holder of the Earthmoving Permit 
(the CONTRACTOR), but they reflect unfavorably on the City of Glendale. 
The CONTRACTOR shall be prepared to spend as much time as required to keep 
dust controlled in accordance with regulatory requirements.  The air 
contaminant emission at the Work area shall not exceed 20-percent opacity 
during the Contract period.  Local regulatory requirements may be more 
stringent than the maximum allowable stated above.  The CONTRACTOR is 
responsible for identifying and complying with all applicable regulatory levels.  
Whenever any dust emissions that can be seen by the naked eye, rising from the 
operation, and/or fugitive emissions obstructing the view of the operations, the 
CONTRACTOR is in violation of these Specifications.  If the CONTRACTOR fails to 
provide the necessary dust control, to the ENGINEER’S satisfaction, the Project 
will be shut down, at the CONTRACTOR’s expense, until the CONTRACTOR 
presents satisfactory evidence to the ENGINEER that he can continue Work and 
prevent dust as required. 
B. 
The CONTRACTOR shall provide continuous positive methods and apply dust 
control measures to prevent rising dust from construction operations, and 
provide positive means to prevent airborne dust from dispersing into the 
atmosphere.  Chemical dust suppressants must be approved by the ENGINEER 
prior to use. 
C. 
The CONTRACTOR shall control dust by preventing blowing and movement of 
dust from exposed soil surfaces and access roads to reduce on- and off-site 
damage and health hazards.  Control may be achieved by irrigation in which the 
site shall be sprinkled with water until the surface is moist.  The process shall be 
repeated as needed. 
1.03 
NOISE CONTROL 
A. 
The CONTRACTOR’s vehicles and equipment shall be such as to minimize noise to 
the greatest degree practicable. Noise levels shall conform to the latest OSHA 
standards and in no case will noise levels be permitted which interfere with the 
Work of the OWNER or others.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 3 of 14 
1.04 
PEST AND RODENT CONTROL 
A. 
Provide rodent and pest control as necessary to prevent infestation of construction 
or storage areas.  
1. 
Employ methods and use materials that will not adversely affect conditions 
at the site or on adjoining properties. 
1.05 
SURFACE WATER CONTROL 
A. 
The CONTRACTOR shall provide methods to control surface water to prevent 
damage to the Project, the site, or adjoining properties.  The CONTRACTOR shall 
control fill, grading and ditching to direct surface drainage away from 
excavations, pits, tunnels and other construction areas; and to direct drainage to 
proper run-off. 
B. 
The CONTRACTOR shall provide, operate, and maintain equipment of adequate 
capacity to control surface erosion. 
C. 
The CONTRACTOR shall dispose of drainage water in a manner to prevent 
flooding, erosion, or other damage to any portion of the site or to adjoining 
areas. 
1.06 
DEBRIS CONTROL 
A. 
All areas under the CONTRACTOR’s control shall be maintained free of 
extraneous debris. 
B. 
The CONTRACTOR shall initiate and maintain a specific program to prevent 
accumulation of debris at the Project site, storage and parking areas, or along 
access roads and haul routes. 
1. 
The CONTRACTOR shall utilize only City of Glendale Solid Waste Collection 
Services containers and/or vehicles for any and all debris control measures. 
2. 
The CONTRACTOR shall prohibit overloading of trucks to prevent spillage 
on access and haul routes. Traffic areas shall be periodically inspected to 
enforce requirements. 
C. 
The CONTRACTOR shall schedule periodic collection and disposal of debris. 
Additional collections and disposal of debris shall be provided whenever the 
periodic schedule is inadequate to prevent accumulation.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 4 of 14 
1.07 
POLLUTION CONTROL 
A. 
The CONTRACTOR shall provide methods, means and facilities required to 
prevent contamination of soil, water or atmosphere by the discharge of noxious 
substances from construction operations. If such contamination should occur, 
the CONTRACTOR shall immediately notify the OWNER and ENGINEER. 
B. 
The CONTRACTOR shall provide equipment and personnel to perform 
emergency measures required to contain any spillage and to remove 
contaminated soils or liquids; and, shall excavate and dispose of any soil 
contaminated by the construction operations off-site in accordance with all 
Federal, state, and local regulations and replace with suitable compacted fill, 
topsoil and/or vegetation as directed by the ENGINEER. 
C. 
The CONTRACTOR shall take special measures to prevent harmful substances 
from entering public waters; and, shall prevent disposal of wastes, effluents, 
chemicals, sediments, or other such substances adjacent to streams, or in 
sanitary or storm sewers. 
D. 
The CONTRACTOR shall provide systems for control of atmospheric pollutants 
and shall: 
1. 
Prevent toxic concentrations of chemicals and 
2. 
Prevent harmful dispersal of pollutants into the atmosphere. 
E. 
The CONTRACTOR shall provide adequate secondary containment structures for 
any above ground petroleum storage tanks and/or drums. If required based on 
the quantity of petroleum products stored, the CONTRACTOR shall prepare and 
implement a Spill Prevention, Control, and Countermeasures (SPCC) Plan, 
pursuant to and complying with the requirements of 40 Code of Federal 
Regulations, Part 112. The SPCC Plan shall be sealed by a Professional Engineer 
registered in the State of Arizona.  
F. 
The CONTRACTOR shall obtain a construction AZPDES permit and develop a 
Storm Water Pollution Prevention Plan (SWPPP) for the construction phase of 
the Project. 
1.08 
EROSION CONTROL 
A. 
General: The construction procedures outlined herein shall be implemented to 
assure minimum damage to the environment during construction. The 
CONTRACTOR shall take any and all additional measures required to conform to 
the requirements of applicable codes and regulations.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 5 of 14 
1. 
Whenever possible, access and temporary roads shall be located and 
constructed to avoid environmental damage. Provisions shall be made to 
regulate drainage, avoid erosion, and minimize damage to vegetation. 
2. 
Where areas must be cleared for storage of materials or temporary 
structures, provisions shall be made for regulating drainage and 
controlling erosion, subject to the ENGINEER’s approval.  
3. 
Remove only those shrubs and grasses that must be removed for 
construction. Protect the remainder to preserve their erosion-control 
value.  
B. 
Control Measures: Measures shall be applied to control erosion and to minimize 
the siltation of the existing waterways, and natural ponding areas. Such 
measures shall include, but are not limited to, the use of berms, baled straw silt 
barriers, gravel or crushed stone, mulch, slope drains, and other methods. 
1. 
Install erosion and sediment control practices where shown and 
according to applicable standards, codes, and Specifications. The 
practices shall be maintained in effective working condition during 
construction and until the drainage area has been permanently 
stabilized.  
2. 
Temporary measures shall be coordinated with the construction of 
permanent drainage facilities and other Work to the extent practicable 
to assure economical, effective, and continuous erosion and siltation 
control. 
3. 
The CONTRACTOR shall provide special care in areas with steep slopes. 
Disturbance of vegetation shall be kept to a minimum to maintain 
stability.  
4. 
After stabilization, remove all straw bale dikes, debris, etc., from the site.  
C. 
Failure to Comply: In the event the CONTRACTOR repeatedly fails to satisfactorily 
control erosion and siltation, the OWNER reserves the right to employ outside 
assistance or to use its own forces to provide the corrective measures indicated. 
The cost of such Work, plus engineering costs, will be deducted from monies due 
the CONTRACTOR.  
D. 
The CONTRACTOR shall plan and execute construction and earthwork by 
methods to control surface drainage from cuts and fills, and from borrow and 
waste disposal areas, to prevent erosion and sedimentation. 
1. 
Hold the areas of bare soil exposed at one time to a minimum.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 6 of 14 
2. 
Provide temporary control measures such as berms, dikes, and drains. 
E. 
The CONTRACTOR shall construct fills and waste areas by selective placement to 
eliminate surface silts or clays, which will erode.  
F. 
The CONTRACTOR shall periodically inspect earthwork to detect any evidence of 
the start of erosion and apply corrective measures as required to control erosion.  
2.0  
PRODUCTS 
2.01 
MATERIALS, GENERAL 
A. 
Materials shall be new and suitable for the intended purpose, but must not 
violate requirements of applicable codes and standards. 
2.02 
CONSTRUCTION AIDS 
A. 
The CONTRACTOR shall provide any and all construction aids, equipment and 
materials required to facilitate execution of the Work, including but not limited 
to: scaffolds, staging, ladders, stairs, signs, ramps, runways, platforms, railings, 
hoists, cranes, chutes and other such facilities and equipment. 
3.0  
EXECUTION 
3.01 
PREPARATION 
A. 
The CONTRACTOR shall consult with the ENGINEER and review site conditions 
and factors which affect construction procedures and construction aids, 
including adjacent properties and public facilities which may be affected by 
execution of the Work.  
3.02 
GENERAL 
A. 
Installation of facilities shall be of a neat and reasonable uniform appearance, 
structurally adequate for required purposes. 
B. 
The CONTRACTOR shall maintain barriers during entire construction period. 
C. 
The CONTRACTOR shall relocate barriers as required by progress of construction. 
3.03 
TREE AND PLANT PROTECTION 
A. 
The CONTRACTOR shall preserve and protect existing trees and plants at the site 
and those adjacent to the site.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 7 of 14 
B. 
The CONTRACTOR shall consult with the ENGINEER and remove agreed-upon 
roots and branches which interfere with construction. The CONTRACTOR shall 
employ a qualified tree surgeon to remove roots and branches, and to treat cuts. 
C. 
The CONTRACTOR shall provide temporary barriers to a height of six feet around 
each tree or plant or around each group of trees or plants which are in the area 
of the Work. 
D. 
The CONTRACTOR shall protect root zones of trees and plants and shall perform 
the following in areas of protected trees and plants: 
1. 
Not allow vehicular traffic or parking; 
2. 
Not store materials or products; 
3. 
Prevent dumping of refuse or chemically injurious materials or liquids; and 
4. 
Prevent puddling or continuous running water. 
E. 
The CONTRACTOR shall carefully supervise excavating, grading and filling, and 
subsequent construction operations, to prevent damage to existing vegetation, 
utilities, or monitoring devices. 
F. 
The CONTRACTOR shall replace, or suitably repair, trees and plants, and 
irrigation systems which have been damaged or destroyed due to construction 
operations at the CONTRACTOR’s expense. 
G. 
Land Protection: 
1. 
Except for any Work or storage area and access routes specifically 
assigned for the use of the CONTRACTOR, the land areas outside the 
limits of construction shall be preserved in their present condition. The 
CONTRACTOR shall confine his construction activities to areas defined for 
Work within the Specifications and the Contract Documents.  
2. 
The CONTRACTOR shall manage and control all stockpile/borrow areas, 
Work or storage areas, access routes and embankments to prevent 
sediment from entering nearby water or land adjacent to the Project site.  
3. 
The CONTRACTOR shall restore all disturbed areas including 
stockpile/borrow and haul areas and establish permanent type of locally 
adaptable vegetative cover.  
4. 
Unless earthwork is immediately paved or surfaced, the CONTRACTOR 
shall protect all side slopes and backslopes immediately upon completion 
of final grading.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 8 of 14 
5. 
The CONTRACTOR shall plan and execute earthwork in a manner to 
minimize duration of exposure of unprotected soils.  
6. 
The CONTRACTOR shall construct fills by selective placement to eliminate 
surface soils that are susceptible to erosion.  
7. 
The CONTRACTOR shall periodically inspect earthwork to detect any 
evidence of the start of erosion, and apply corrective measures as 
required to control erosion.  
8. 
Except for areas designated by the Drawings, Specifications and the 
Contract Documents to be cleared and grubbed, the CONTRACTOR shall 
not deface, injure, or destroy trees and vegetation, nor remove, cut, or 
disturb them without approval of the ENGINEER. Any damage caused by 
the CONTRACTOR’s equipment or operations shall be restored as nearly 
as possible to its original condition at the CONTRACTOR’s expense.  
3.04 
REMOVAL 
A. 
The CONTRACTOR shall completely remove temporary barriers, materials, 
equipment, and services: 
1. 
When construction needs can be met by use of permanent construction; or 
2. 
At completion of Project. 
B. 
The CONTRACTOR shall clean and repair damage caused by installation or by use 
of temporary facilities including: 
1. 
Removal of foundations and underground installations for construction 
aids; 
2. 
Grading areas of site affected by temporary installations to required 
elevations and slopes; and 
3. 
Cleaning of the area. 
C. 
The CONTRACTOR shall restore existing facilities used for temporary purposes to 
specified or original condition. 
D. 
The CONTRACTOR shall restore permanent facilities, if any, used for temporary 
purposes to condition existing prior to construction. 
3.05 
HISTORICAL AND ARCHAEOLOGICAL 
 
A. 
If, during the course of construction, evidence of deposits of historical or 
archaeological interest is found, the CONTRACTOR shall cease operations 
affecting the find and shall notify OWNER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 9 of 14 
 
 
1. 
No further disturbance of the deposits shall ensue until the CONTRACTOR 
has been notified by the OWNER that the CONTRACTOR may proceed. 
 
 
2. 
OWNER will issue a notice to proceed after appropriate authorities have 
surveyed the find and made a determination to the OWNER.  
 
 
3. 
The site has been previously investigated and has no known history of 
historical or archaeological finds.  
3.06 
TEMPORARY SANITARY FACILITIES 
 
A. 
Toilet Facilities: The OWNER will not provide on-site toilet facilities for the 
CONTRACTOR’s use. The CONTRACTOR shall be responsible for providing on-site 
toilet facilities for his/her employees. All toilet facilities shall be maintained in a 
neat and clean manner and shall not cause an eyesore. All toilet facilities shall 
follow all applicable regulations, laws, and ordinances. If the CONTRACTOR 
abuses the toilet facilities, the OWNER has the right to revoke all on-site toilet 
access, and the CONTRACTOR will have to provide his or her own toilet facilities, 
further away from the job site.  
 
B. 
The CONTRACTOR shall provide temporary sanitary toilet facilities conforming to 
state and local health and sanitation regulations, in sufficient number for use by 
the OWNER’s designated Project Representatives, CONTRACTOR’s and 
Subcontractor’s employees. 
 
C. 
The CONTRACTOR shall maintain in sanitary condition and properly supply with 
toilet paper.  
 
D. 
No sanitary sewer pipe is located at the Project site. 
 
 
1. 
The CONTRACTOR shall arrange for portable toilet units and holding 
tanks. 
 
 
2. 
The CONTRACTOR shall pipe all wastes from trailer offices to a holding 
tank. 
 
E. 
The CONTRACTOR shall arrange for routine vacuuming, cleaning, and 
maintenance services.  
 
F. 
Proper sanitary, vector, and odor control shall be required and maintained at all 
times.  
3.07 
TEMPORARY ELECTRICITY, TELEPHONE, AND DOMESTIC WATER  
A. 
Electrical power for the CONTRACTOR’S use will not be provided by the OWNER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 10 of 14 
B. 
The CONTRACTOR shall provide power for all construction operations until final 
completion of Project. 
C. 
The CONTRACTOR shall provide temporary lighting as required during 
construction. 
D. 
The CONTRACTOR shall provide illumination Levels: In accordance with OSHA 
requirements for construction lighting. 
E. 
Equipment and materials need not be new. 
F. 
Temporary wiring shall be sized and fused in accordance with NEC requirements. 
G. 
Relamp fixtures during construction period to meet requirements of the 
CONTRACTOR and Subcontractors, to satisfy applicable safety requirements, and 
as directed by the OWNER. 
H. 
The CONTRACTOR shall provide ventilated enclosed areas to achieve curing of 
materials, to dissipate humidity, and to prevent accumulation of dust, fumes, 
vapors, or gases. 
I. 
The CONTRACTOR shall provide and pay for suitable quality water service as 
needed to maintain specified conditions for construction operations (see Section 
A01050 – 3.14 – Construction Water). 
J. 
Telephone and fax machines for the CONTRACTOR’s use will not be provided by 
the OWNER. 
K. 
Domestic water for human consumption shall be obtained by the CONTRACTOR. 
L. 
Obtain written approval from the OWNER a minimum of 72 hours prior to 
disconnection or shutting off any service or utility. 
3.08 
TEMPORARY FIRE PROTECTION 
 
A. 
The CONTRACTOR shall: 
 
 
1. 
Provide and maintain in working order a minimum of one fire 
extinguisher in each trailer or as required by codes;  
 
 
2. 
Be required to contact local fire department and meet all necessary fire 
codes at the Project site; 
 
 
3. 
Make arrangements for fire department audits, 30 days after Notice to 
Proceed; and 
 
 
4. 
Make roadways accessible to fire trucks.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 11 of 14 
3.09 
TEMPORARY SITE AND OTHER ROADS 
 
A. 
The CONTRACTOR shall construct and maintain temporary site roadways in 
drivable condition necessary to carry out construction operations.  
 
B. 
The CONTRACTOR shall maintain the OWNER’s existing roads and public roads 
used during construction free from accumulations of dirt, mud, and construction 
debris resulting from construction operations. Roads shall be considered 
“maintained” when material has been removed by a mechanical sweeper. 
 
C. 
Paved roads damaged during routine and normal construction shall be repaired 
at the CONTRACTOR’s expense per the City of Glendale paving requirements. 
 
D. 
The CONTRACTOR shall provide photographs of road conditions before start of 
the Project.  
 
E. 
Security will not be provided by the OWNER. 
 
F. 
The CONTRACTOR shall be responsible for loss or injury to persons or property 
where Work is involved, and shall provide security and take precautionary 
measures to protect the CONTRACTOR’s and OWNER’s interests.  
 
G. 
The CONTRACTOR shall provide insurance against loss of materials, contents of 
trailer(s), equipment, and other property at the Project site and Project trailer.  
3.10 
TEMPORARY PARKING 
 
A. 
Temporary parking areas shall be provided by the CONTRACTOR at no additional 
cost to the OWNER.  
 
 
1. 
The OWNER and ENGINEER will require on-site parking for at least five 
vehicles.  
 
B. 
The CONTRACTOR shall maintain designated parking areas with 1-inch 
decomposed granite or other suitable material. 
 
C. 
No heavy machinery shall be allowed on the OWNER’s parking area.  
3.11 
TEMPORARY FENCING 
 
A. 
If for any reason, the existing perimeter landfill fencing is altered or removed by 
the CONTRACTOR, the CONTRACTOR shall provide temporary fencing sufficient 
to prevent trespassing. 
 
 
1. 
The CONTRACTOR shall provide fencing that is sufficiently secure against 
trespass of children and stray animals.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 12 of 14 
 
B. 
Materials shall be sufficiently durable to be effective for duration of construction 
period. 
 
C. 
The CONTRACTOR shall coordinate with the OWNER for the removal any and all 
temporary fencing around the Project site to be replaced with new permanent 
site fencing following construction. 
3.12 
PROGRESS CLEANING AND WASTE REMOVAL 
 
A. 
The CONTRACTOR shall maintain areas free of waste materials, debris, and 
rubbish. 
 
 
1. 
Maintain site in a clean and orderly condition. 
 
B. 
The CONTRACTOR shall remove debris and rubbish from pipe manholes, and 
other closed or remote spaces, prior to enclosing the space.  
 
C. 
The CONTRACTOR shall broom and vacuum clean interior areas prior to start of 
surface finishing, and continue cleaning to eliminate dust.  
 
D. 
The CONTRACTOR shall collect and remove waste materials, debris, and rubbish 
from site work area weekly and dispose of it at the active working face on-site. 
If the material is HazMat, the CONTRACTOR shall dispose of the HazMat material 
off-site.  
 
E. 
Open free-fall chutes are not permitted. 
 
 
1. 
The CONTRACTOR shall terminate closed chutes into appropriate 
containers with lids.  
3.13 
BARRIERS 
 
A. 
The CONTRACTOR shall provide barriers to prevent unauthorized entry to 
construction areas to allow for the OWNER’s use of site and to protect existing 
facilities and adjacent properties from damage from construction operations and 
demolition. 
 
B. 
The CONTRACTOR shall provide barricades and covered walkways required by 
governing authorities for public rights-of-way. 
 
C. 
The CONTRACTOR shall protect non-owned vehicular traffic, stored materials, 
site and structures from damage.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 13 of 14 
3.14 
CONSTRUCTION WATER 
A. 
The CONTRACTOR is responsible for transporting water per the Drawings and 
Specifications. 
B. 
The CONTRACTOR shall not use any water from the OWNER’s two existing Site 
water stands, unless approved by the OWNER. 
C. 
The CONTRACTOR is responsible for obtaining construction water.  There is no 
potable water main on-site.  There is a potable water main adjacent to the 
Glendale Landfill’s north cell along the South side of Northern Avenue.  The 
CONTRACTOR shall contact the City of Glendale Water Department to make 
necessary arrangements to provide water services during construction.  The 
CONTRACTOR is responsible for paying for all connection and usage fees 
associated with the water services and for providing his own water storage tank. 
3.15 
CONTRACTOR’S WATER USAGE LOG 
A. 
The CONTRACTOR shall submit a monthly log of water used for dust control to 
the ENGINEER with each pay application.  The log shall be updated every month. 
1. The water usage log shall include the following: 
a. 
Date water was used; 
b. 
How many hours each day the water was used; 
c. 
Number of loads per day; 
d. 
Number of water trucks/pulls used per day; 
e. 
Loads of water per hour per day; 
f. 
Subcontractor gallons of water used on any date the CONTRACTOR used 
water; 
g. 
Pre-wet water usage, gallons per day; 
h. 
Identify size of water trucks/pulls used and how many gallons each piece 
of equipment placed per day; and 
i. 
Cumulative total per day and total gallons of water used per month.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 14 of 14 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01510 - 1 of 2 
SECTION A01510 
TRAFFIC CONTROL 
 
1.0  
GENERAL 
1.01 
TRAFFIC REGULATIONS 
A. 
The following shall be considered major streets: Glendale Avenue and Northern 
Avenue.  
B. 
All traffic and/or traffic control devices on this Project shall be provided, maintained 
and/or controlled as specified in the City of Glendale Traffic Barricade Manual, 
latest revision. 
C. 
Permission to restrict major streets, sidewalks, and alleys shall be requested 
through the City of Glendale and/or Maricopa County Department of 
Transportation (MCDOT).  
D. 
Unless otherwise provided for the following “Special Traffic Regulations”, all traffic 
on this Project shall be regulated as specified in Section IV of the Traffic Barricade 
Manual. 
E. 
No deviation to the “Special Traffic Regulations” will be allowed or implemented 
unless submitted to the ENGINEER for review and approval (2) weeks prior to 
proposed Work. 
1.02 
LOCAL ACCESS REQUIREMENTS 
A. 
The CONTRACTOR shall maintain local access to all site haul roads, access roads, 
and driveways at all times. The CONTRACTOR shall restore the access as soon as 
possible. If the primary access cannot be restored in a timely manner, the 
CONTRACTOR shall provide an alternative which shall be pre-determined with the 
OWNER. Any local street restrictions imposed shall be such that local area traffic 
circulation is maintained.  
1.03 
SPECIAL SIGN REQUIREMENTS  
A. 
The CONTRACTOR shall provide, erect, and maintain advance notification, 
informational and directional access signs that may be required by the ENGINEER. 
The cost of signage is incidental to traffic control cost.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01510 - 2 of 2 
1.04 
TRAFFIC CONTROL PLAN 
A. 
The CONTRACTOR shall submit a traffic control plan for approval, showing 
placement of all traffic control devices, including all conflicting signs to be 
covered/removed or relocated, or other features that may conflict with the 
placement of temporary signage. Included in the plan shall be designated routes 
for the CONTRACTOR’s equipment during construction. The CONTRACTOR shall not 
deviate from designated routes, unless otherwise approved by the ENGINEER, and 
shall not interfere with the traffic and operations of other Contractors, landfill 
haulers or the OWNER. This plan shall be professionally drawn on 24"x36" 
reproducible medium, and shall be submitted to the ENGINEER at the Pre-
Construction meeting. 
B. 
The CONTRACTOR is responsible for furnishing all traffic control-related materials 
and personnel, including but not limited to flagmen, barricades, signs and barriers. 
The cost is incidental to the traffic control cost. 
2.0  
PRODUCTS 
NOT USED 
3.0  
EXECUTION 
NOT USED 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025.   
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01810 - 1 of 1 
SECTION A01810 
DRAWINGS 
 
1.0  
GENERAL 
1.01 
DESCRIPTION 
 
The Drawings, showing the scope, extent and character of the Work to be furnished and 
performed by the CONTRACTOR are provided under separate cover and are included as 
part of the Specifications and Contract Documents.  The Drawings are listed as follows: 
INDEX OF DRAWINGS 
C-1 
Title Sheet 
C-2 
Plan View 
C-3 
Excavation Plans 
C-4 
Excavation Plans 
C-5 
Stockpiling Plans 
C-6 
Stockpiling Plans 
C-7 
Details 
2.0  
PRODUCTS 
NOT USED 
3.0  
EXECUTION 
NOT USED 
 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 1 of 10 
SECTION B02200 
EARTHWORK 
 
1.0  
GENERAL 
1.01 
DESCRIPTION OF WORK 
A. 
The CONTRACTOR shall furnish all labor, materials, tools, supervision, 
transportation, and installation equipment necessary to perform all related 
Work as specified herein, as shown on the Contract Drawings. 
B. 
The Work of this Section shall include, but not necessarily be limited to: 
excavating, separating, hauling, stockpiling, backfilling, compacting, and grading 
of soils. The Work of this Section may pertain in whole or in part to construction 
of the following: the landfill’s north cell, excavation, filling, haul road 
development, stockpiling for soils, and hauling soil to stockpile locations. The 
Work of this Section also includes protection of Work partially completed. 
C. 
The CONTRACTOR shall conform to the dimensions, lines, and grades specified 
on the Drawings. 
D. 
No extra monetary compensation or additional time will be authorized for claims 
that soil conditions differ from those anticipated. It is the CONTRACTOR’s 
responsibility to make his own determination as to the actual existing conditions.  
1.02 
SUBMITTALS AND QUALIFICATIONS 
 
A. 
The CONTRACTOR shall submit 7 days prior to commencement of work to the 
OWNER and the ENGINEER for review a work plan describing the proposed 
methods of construction, including stripping, dewatering, excavation, filling, 
compaction, stockpiling, and backfilling for the various portions of the work. The 
review shall be for method only. The CONTRACTOR shall remain responsible for 
the adequacy and safety of the methods. 
B. 
The CONTRACTOR shall notify the OWNER Representative in writing at least 7 
days in advance of intention to perform the work of this Section. 
C. 
If work is interrupted for reasons other than inclement weather, the 
CONTRACTOR shall notify the OWNER and the ENGINEER a minimum of 24 hours 
prior to the resumption of work.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 2 of 10 
1.03 
PROTECTION 
A. 
The CONTRACTOR shall contact utility companies and locate, mark and protect 
all existing utilities before commencement of construction activities. Mounding 
of soil to construct an equipment crossing may be required for any natural gas 
lines, water sewer, or drainage culverts. The CONTRACTOR shall provide design 
by an engineer registered in the State of Arizona for any pipeline crossing. The 
CONTRACTOR shall not cross a gas line with heavy equipment until obtaining 
clearance from the utility companies and from the OWNER. 
B. 
The CONTRACTOR shall protect trees, shrubs, lawns, sprinkler/irrigation 
systems, rock outcroppings and other features remaining as part of final 
landscaping unless otherwise noted. 
C. 
The CONTRACTOR shall protect benchmarks, survey markers, fences, roads, 
sidewalks, paving, curbs and other existing structures from damage due to the 
CONTRACTOR’S activities unless otherwise noted. 
D. 
The CONTRACTOR shall repair damage caused by the construction operations at 
the CONTRACTOR’S expense. 
E. 
Erosion control must be maintained. Erosion control measures shall be as noted 
on the Grading Plan or as directed by the ENGINEER. 
2.0  
PRODUCTS 
2.01 
GENERAL FILL MATERIAL 
A. 
The General Fill for ramps, haul roads, etc. shall consist of on-site soil materials 
and shall be free of debris, foreign objects, roots, organic and other materials 
considered deleterious by the ENGINEER. 
2.02 
ENGINEERED FILL MATERIAL 
A. 
The Engineered Fill material shall be on-site soil materials, or other materials, as 
approved by the OWNER or ENGINEER.  The Engineered Fill shall be free of rock 
greater than 6 inches in diameter retained on a 6-inch mechanical screen.  The 
location of all screening and crushing equipment shall be approved by the 
OWNER and ENGINEER prior to the production of the Engineered Fill materials. 
The Engineered Fill Material shall be free of debris, foreign objects, roots, and 
organic and other materials considered deleterious by the ENGINEER.  The 
Engineered Fill material shall be composed of cohesive materials.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 3 of 10 
2.03 
PIPE BEDDING MATERIAL 
A. 
The Pipe Bedding aggregate shall be washed ASTM C33 Coarse Aggregate Size 
Number 57 with the following gradation. Alternate particle sizes will be 
considered by the OWNER or ENGINEER. 
 
Sieve 
Designation 
Percent 
Passing 
1 1/2" 
100 
1" 
95-100 
1/2" 
25-60 
#4 
0-10 
#8 
0-5 
 
B. 
Native soil backfill may be used for backfill for the temporary culverts. 
2.04 
ACCESS ROAD SEGMENT SURFACING 
A. 
Access roads shall be surfaced with Asphalt Surface Millings and oil mixture 
(millings). The millings are reclaimed asphalt pavement (AP) material meeting 
the requirements of MAG Section 709.1. The millings shall be free of detrimental 
quantities of organic, non-granular soils and deleterious materials. The millings 
shall be stored in such a manner as to permit ready inspection and shall be 
protected from contamination. Any portion of the stockpile that has been 
consolidated so that the uniformity is affected will require reprocessing prior to 
use.  Reclaimed asphalt millings are available on site and are to be used along 
with the specified emulsion mixture.   
3.0  
EXECUTION 
3.01 
PREPARATION 
A. 
The CONTRACTOR shall establish and identify required lines and levels. 
B. 
The CONTRACTOR shall maintain benchmarks, monuments, and other reference 
points and re-establish if disturbed or destroyed, at no additional cost to the 
OWNER. 
C. 
Before start of the Work, the CONTRACTOR shall locate utilities in the Work 
areas. The CONTRACTOR shall notify utilities to remove and relocate lines that

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 4 of 10 
are in the way of construction and are not to be relocated as a part of the Work 
covered by these Specifications. 
D. 
The CONTRACTOR shall maintain, protect, reroute, or extend as required existing 
utilities to remain which pass through the Work area. 
E. 
The CONTRACTOR shall develop access to the construction area in accordance 
with the requirements of the Drawings and Specifications. 
F. 
The CONTRACTOR shall install barriers and other devices to protect areas 
adjacent to construction. 
G. 
The CONTRACTOR shall install silt fences or other means to control surface 
erosion in accordance with the Construction AZPDES Permit. 
3.02 
STOCKPILING 
A. 
Excavated material classified as General Fill material and/or Engineered Fill 
material shall be segregated from other materials and stockpiled in the manner 
shown on the Drawings or as specified by the OWNER or ENGINEER. 
B. 
Excavated materials classified as oversize material (defined as rock materials 
larger than 6 inches in any direction), rejects from any screening or crushing 
operation, and the Crushed Rock material shall be stockpiled in designated areas 
separate from General Fill material and/or Engineered Fill material and from 
incompatible soil, clearing debris, or other objectionable materials. Stockpile 
areas will be shown on the Drawings or designated by the OWNER or ENGINEER. 
C. 
Stockpiles of Engineered Fill material and General Fill material shall be no steeper 
than 2:1 (horizontal: vertical) or their respective angle of repose, whichever is 
flatter, without approval of the ENGINEER, graded to drain, sealed by track walk 
with a Dozer parallel to the slope or other means approved by the ENGINEER, 
and graded uniformly daily during periods when fill is taken from the stockpile.  
Upon completion of a stockpile the CONTRACTOR shall soak the surface and shall 
form a ¼ inch thick crust on all surfaces.  After creation of the crust, no further 
vehicle traffic will be allowed. Any screening berms will be sealed by tracking 
parallel to the slope with a Dozer or other means approved by the ENGINEER and 
graded to remove loose materials and provide a smooth even surface. 
D. 
The CONTRACTOR shall perform watering as necessary to control dust. 
E. 
Soil from the cell excavation shall be stockpiled within the area specified on the 
Construction Drawings. Stockpile sideslopes shall be no greater than 2:1, unless 
otherwise approved by the ENGINEER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 5 of 10 
3.03 
EXCAVATION – GENERAL 
A. 
Excavation shall be performed, at a minimum, to the lines and grades indicated 
on the Drawings. Additional excavation shall be performed to achieve a stable 
working base or filled to bridge over weak subgrade materials. The limits of 
additional excavation shall be determined by the ENGINEER. 
B. 
All excavation shall be open cut unless otherwise shown on Plans or approved 
by the OWNER or ENGINEER. 
C. 
Excavated materials shall be transported to stockpile locations, as indicated on 
the Drawings or as directed by the ENGINEER. 
D. 
The tolerances from the dimensions and elevations shown on the Drawings for 
excavation activities only shall be: 
1. 
Trenches: 
Line 
±0.1 foot 
 
 
Grade 
±0.1 foot 
2. 
Cell Floor and  
Line 
±0.5 foot 
 
Slope 
Grade 
±0.1 foot 
to be lined(1): 
 
 
3. 
Unlined Cell Slopes: Line 
±0.5 foot 
 
 
Grade 
± 0.2 foot 
4. 
Road Excavations: 
Line 
±0.5 foot 
 
Grade 
±0.2 foot 
(1) – These areas to be left 1 foot “fat” from depicted grades as indicated on the 
Drawings. 
3.04 
SHEETING, SHORING, AND BRACING 
A. 
When necessary, the CONTRACTOR shall furnish, put in place, and maintain such 
sheeting, bracing, etc., as may be required to support the sides of the excavation 
and to prevent movement. 
B. 
Care shall be taken to prevent voids outside the sheeting. 
C. 
If voids are formed, they shall be immediately filled and compacted. 
D. 
Unless adjacent facilities will be damaged, the CONTRACTOR shall remove all 
sheeting, shoring, and bracing after backfill has been placed to a depth of 18 
inches over the pipeline.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 6 of 10 
E. 
Shoring shall be completely removed prior to closure of the trench.  
F. 
The CONTRACTOR shall be responsible for performance and safety on all 
sheeting, shoring, and bracing. 
3.05 
UNAUTHORIZED EXCAVATION 
A. 
All excavation outside or below the proposed lines and grades shown on the 
Drawings shall be considered unauthorized excavation. 
B. 
The CONTRACTOR shall backfill areas of unauthorized excavation with 
Engineered Fill in accordance with this Section at no additional cost to the 
OWNER, to insure the stability of the structure or construction involved. 
3.06 
OBSTRUCTIONS 
A. 
Obstructions shown on the Drawings are for information only and do not 
guarantee their exact locations nor exclude the presence of other obstructions. 
B. 
The CONTRACTOR shall exercise due care in excavating adjacent to existing 
obstructions and shall not disturb them. 
C. 
In the event obstructions are disturbed, the CONTRACTOR shall repair or replace 
them as quickly as possible to the condition existing prior to their disturbance. 
This repair or replacement will be at the CONTRACTOR’s expense. 
D. 
If desired by the utility or the OWNER, the CONTRACTOR shall pay for the repair 
or replacement Work performed by the forces of the utility, the OWNER or other 
appropriate party. 
E. 
If replacement or repair of disturbed obstructions is not performed after a 
reasonable period of time, the OWNER may have the necessary Work done and 
deduct the cost of same from payments to the CONTRACTOR. 
3.07 
PUMPING AND DRAINAGE 
A. 
At all times during construction, the CONTRACTOR shall provide, maintain and 
operate equipment and facilities to remove all water entering excavations and 
keep such excavations dry so as to obtain a satisfactory subgrade to allow the 
construction of the Work. 
B. 
Drainage shall be disposed of only in an area approved by the OWNER and the 
ENGINEER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 7 of 10 
3.08 
SURVEY CONTROL 
A. 
The CONTRACTOR shall survey the location and elevation of the excavations. He 
or she shall also Survey the location and elevation of the top of subgrade shown 
on the Drawings. Surveying shall be performed in accordance with Specifications 
Section 01050. 
B. 
The CONTRACTOR shall provide As-built Drawings of the location and elevation 
of the excavations and the top of subgrade, in accordance with the requirements 
of Specifications Section 01050. The CONTRACTOR shall submit this As-built 
Drawing to the OWNER or ENGINEER at least 48 hours prior to the start of fill 
placement. The CONTRACTOR may submit a partial As-built Drawing to obtain 
approval for a portion of Work. The OWNER or ENGINEER will define the 
minimum requirements for a partial Submittal. 
3.09 
PIPE BEDDING PLACEMENT 
A. 
Place pipe bedding only when trench subgrade has been prepared and approved 
by the ENGINEER. 
B. 
Compact pipe bedding according to Part 2.04 of this Section. 
C. 
Place pipe in pipe bedding to lines and grades indicated on Drawings. 
D. 
Place additional pipe bedding to springline of pipe, then compact. 
E. 
Do not damage pipe. 
F. 
Place and compact additional pipe bedding to lines, grades and cross-sectional 
dimensions shown on the Drawings and Specifications, then compact. 
G. 
Install pipe bedding to the thickness and elevations shown on the Drawings to a 
tolerance of minus zero to plus 0.10 feet. 
3.10 
SUBGRADE PREPARATION AND COMPACTION 
A. 
General: The CONTRACTOR may be required to reconstruct the subgrade in areas 
where over-excavations are determined necessary by the OWNER or ENGINEER 
at the CONTRACTOR’s expense. 
B. 
Prior to placing any fill material over undisturbed subsoil or upon completion of 
excavation to subgrade, the subgrade shall be proof-rolled with loaded dump 
truck or similar pneumatic tired vehicle under the observation of the ENGINEER. 
Should subgrade soils pump, yield or fail to achieve density required, the 
CONTRACTOR shall disc, blade, scarify and allow to dry or add moisture to aid 
the compaction process. The CONTRACTOR shall then recompact the soil in

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 8 of 10 
layers as specified in this Section under the observation of the ENGINEER. This 
procedure shall be repeated as necessary as the weather permits, to facilitate 
the drying and recompaction of the soil. After recompaction, the subgrade shall 
be fine graded within tolerance specified in this Section and rolled to form a 
smooth surface using a steel-drum vibratory roller under the observation of the 
ENGINEER. 
C. 
The CONTRACTOR shall grade the subgrade. Uneven areas and low spots shall be 
eliminated. Debris, roots, branches, stones, etc., in excess of 6 inches in size shall 
be removed.  Remove subsurface soils that have been contaminated with 
petroleum products. Rocks/stones in excess of 12 inches in size shall be 
relocated to the rock stockpile. 
D. 
Prior to placing the Engineered Fill materials, the existing ground surface shall be 
scarified to a minimum depth of 8 inches, moisture-conditioned to within 
±2 percent of the optimum moisture content and compacted to 90 percent of 
the maximum dry density as determined by ASTM D1557.  
E. 
Should efforts to achieve required density be unsuccessful, the CONTRACTOR 
shall excavate the material and replace with Engineered Fill material as specified 
in this Section. Undercutting shall not be permitted except at the direction of the 
ENGINEER. 
3.11 
GENERAL FILL 
A. 
The General Fill materials shall be placed in a single uniform lift thickness of 24 
inches and/or as specified on the Drawings. 
 
3.12 
ENGINEERED FILL PLACEMENT 
A. 
Engineered Fill material shall be compacted to 90 percent of the maximum dry 
density as determined by ASTM D1557.  Moisture content shall be uniform 
throughout a compacted lift and shall be within a moisture content range of 
±2 percent of optimum moisture content. 
B. 
Engineered Fill material shall be placed in 8 inch (maximum) uniform lift 
thickness and compacted to a uniform density. 
3.13 
ACCESS ROAD SURFACING 
A. The subgrade shall be moisture-conditioned and prepared as necessary to meet the 
final surface performance specified under paragraph D of this Subsection.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 9 of 10 
B. Placement shall be by methods that will minimize segregation. Any damage to 
underlying or surrounding material or structures during placement of the millings 
shall be repaired before proceeding with Work. 
C. Millings shall be placed to fill layer thickness in one operation in such a manner as to 
minimize segregation and avoid damage to underlying materials. 
D. Millings shall be with an emulsion/rejuvenator application rate of 0.2 GAL/SY x 2 
with SS-1H. The millings will have a total moisture content of 6% by weight and be 
compacted to 95% Standard Proctor Density. Prior to acceptance, the surface of the 
placed millings shall be proof-rolled and shall be smooth, firm, and unyielding. At the 
completion of this activity no wheel ruts or other irregularities shall exist on the 
surface. Place millings to the lines, grades, cross-sections, and dimensions shown on 
the Drawings.  
E. Millings shall be compacted by a smooth drum vibratory compactor, as approved by 
the ENGINEER, which shall make a minimum of three passes in each direction over 
the millings. 
F. After asphalt millings are compacted, a final coat of emulsion/rejuvenator will be 
applied at an application rate of 0.25 GAL/SY. 
 
3.14 
FIELD QUALITY ASSURANCE 
A. 
The minimum frequency and details of quality assurance testing are provided in 
Specifications Section 01400. The CONTRACTOR shall be aware of all field quality 
assurance activities, as these may affect the schedule. 
B. 
All perforations resulting from testing the backfill material shall be filled with soil 
and compacted to the satisfaction of the ENGINEER. 
C. 
If a defective area is discovered in the earthwork, the ENGINEER shall 
immediately determine the extent and nature of the defect by additional tests, 
observations, a review of records, or other means that the ENGINEER deems 
appropriate. 
D. 
After determining the extent and nature of a defect, the CONTRACTOR shall 
correct the deficiency at the CONTRACTOR’s expense. 
E. 
Additional testing shall be performed by the ENGINEER to verify that the defects 
have been corrected before any additional Work is performed by the 
CONTRACTOR in the area of the deficiency.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 10 of 10 
3.15 
PRODUCT PROTECTION 
A. 
The CONTRACTOR shall use all means necessary to protect all prior Work, 
including all materials and completed Work of other Sections. 
B. 
In the event of damage, the CONTRACTOR shall immediately make all repairs and 
replacements necessary, to the approval of the ENGINEER at no additional cost 
to the OWNER. 
C. 
At the end of each day, the CONTRACTOR shall verify that the entire Work area 
was left in a state that promotes surface drainage off and away from the area 
and from finished Work. If threatening weather conditions are forecast, 
compacted surfaces shall be seal-rolled to protect finished Work. 
 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02211 - 1 of 3 
SECTION B02211 
GRADING 
 
 
1.0 
GENERAL 
 
1.01 
SUMMARY DESCRIPTION 
 
A. 
Work consists of general grading (filling and excavation) required to establish a 
final Site grade as designated on the Contract Drawings.  The excavation shall be 
rough graded to the tolerances indicated in Section B02200.  Grades in the area of 
the future installation of the Module 2A liner (Not in this Contract) shall be left 1 
foot “fat” of the depicted contours as indicated on the Drawings.  These slopes 
will be trimmed back by others before the landfill liner is installed. 
B. 
The CONTRACTOR shall perform rough grading of the north cell excavation (fine 
grading will be done by others). 
C. 
The CONTRACTOR shall perform rough grading of soil stockpiles. 
D. 
The CONTRACTOR shall grade, cut, fill, and contour adjacent areas or washes in 
the immediate vicinity the work zone as required to slope to drain. 
 
1.02 
RELATED WORK SPECIFIED ELSEWHERE 
 
A. 
Section B02222 – Excavation 
B. 
Section B02223 – Backfilling 
 
1.03 
PROTECTION 
 
A. 
The CONTRACTOR shall protect bench marks, any existing structures, fences and 
roads. 
B. 
The CONTRACTOR shall protect above or below grade utilities and wells which are 
to remain. 
C. 
The CONTRACTOR shall repair all damage to any appurtenances disturbed as 
directed by the OWNER. 
 
 
2.0 
PRODUCTS 
 
NOT USED

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02211 - 2 of 3 
3.0 
EXECUTION 
 
3.01 
PREPARATION 
 
A. 
The CONTRACTOR shall identify required lines, levels, contours, and datum. 
B. 
The CONTRACTOR shall identify known below-grade utilities and stake and flag 
locations. 
C. 
The CONTRACTOR shall identify and flag above grade utilities. 
D. 
The CONTRACTOR shall maintain and protect remaining existing utilities which 
pass through the Work area. 
E. 
The CONTRACTOR shall notify appropriate utility agencies to remove and relocate 
utilities. 
F. 
The CONTRACTOR shall upon discovery of unknown utilities or concealed 
conditions, discontinue affected work and notify the ENGINEER. 
 
3.02 
BOULDER EXCAVATION 
 
A. 
The CONTRACTOR shall excavate boulders (average diameter more than 12 
inches) from areas to be graded and stockpile in area(s) designated by the OWNER 
in accordance with Section B02222. 
B. 
The CONTRACTOR shall pothole with backhoe equipment as necessary to remove 
boulders protruding beyond the final grade and elevation. 
 
3.03 
GRADING 
 
A. 
The CONTRACTOR shall cut and fill areas to contours or elevations as shown on 
the Contract Drawings. 
B. 
The CONTRACTOR shall place and compact materials in continuous layers in 
conformance with Section B02223. 
C. 
The CONTRACTOR shall maintain the optimum moisture content of fill materials 
to attain required compaction densities. 
D. 
The CONTRACTOR shall make grade changes gradual and blend slopes into level 
areas. 
E. 
The CONTRACTOR shall remove excess soil, unsuitable material, and boulders 
from the Work area during rough and final grading and stockpile on-site at a 
stockpile area designated by the ENGINEER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02211 - 3 of 3 
3.04 
TOLERANCES 
 
A. 
The CONTRACTOR shall rough grade the surface of excavation subgrade to plus or 
minus 0.1 feet. 
B. 
The CONTRACTOR shall fine grade screening berm surfaces to plus or minus 0.1 
feet. 
C. 
The CONTRACTOR shall perform general rough grading of all slopes such that they 
will not create a safety hazard. 
 
 
3.05 
FIELD QUALITY CONTROL 
 
A. 
CQA field inspection and testing will be performed under provisions of Section A01400. 
B. 
The CONTRACTOR’s tests and analyses of fill material shall be performed in accordance 
with ASTM D1557. 
C. 
The CONTRACTOR shall be responsible for quality control measures and corrective 
actions in accordance with Section A01400 and the results of CQA testing. 
D. If tests indicate Work does not meet specified requirements the CONTRACTOR shall Re-
Work or remove Work prior to replacing and retesting Work at no cost to the OWNER. 
 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
Separate measurements or payment will not be made for work required under this 
Section.  All costs in connection with the work specified herein will be considered 
incidental to the Project. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02222 - 1 of 3 
SECTION B02222 
EXCAVATION 
 
 
1.0 
GENERAL 
 
1.01 
LOCAL BORROW 
 
A. 
The north cell excavation is located between the active landfill and Northern 
Avenue.  The excavation was previously mined for aggregate, and the existing cut 
slopes are near vertical.  The OWNER has completed a limited geotechnical 
investigation consisting of exploratory test borings, soil sampling. This information 
is included in Appendix A. 
 
B. 
It is estimated that approximately 50% of the material to be excavated will be fine 
grained (fines sands, silts and clays) and will be acceptable for construction of 
Engineered Fill.  The ENGINEER will determine in the field during excavation which 
materials are classified as fine grained to be used as Engineered Fill.  The 
CONTRACTOR will be required to screen Engineered Fill materials containing rocks 
greater than 6-inches in diameter as part of this Contract. 
 
C. 
The CONTRACTOR shall haul coarse grained materials (gravel) to the stockpiles or 
for the Landfill’s use as daily cover. 
 
 
2.0 
PRODUCTS 
 
NOT USED 
 
3.0 
EXECUTION 
 
3.01 
OVER EXCAVATION 
 
The CONTRACTOR shall take care not to excavate below the depth indicated on the 
Contract Drawings.  Unauthorized excavation below specified grade lines shall be refilled 
at the CONTRACTOR’S expense with clean soil material per Section B02223.  The 
CONTRACTOR will not be paid for amount of material over excavated or for backfilling 
over excavated areas.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02222 - 2 of 3 
3.02 
EXCAVATION 
 
A. 
The CONTRACTOR shall, during excavation, uniformly moisture condition and 
remove materials in an orderly manner.  Material with excessive or inadequate 
moisture content shall not be considered suitable for proper compaction.  The 
CONTRACTOR, at his own expense, shall remove or add moisture to material being 
excavated to bring it within a range of ±2 percent of the optimum moisture 
content.  Where tests indicate that moisture content of the material being 
excavated is below the Project requirements, the moisture content of the material 
shall be adjusted by the CONTRACTOR and retested.  No material will be excavated 
and hauled to stockpile locations until it meets the moisture content requirements 
of these Specifications to the satisfaction of the ENGINEER. 
 
B. 
Where work is interrupted by heavy rains, fill operations shall not be resumed 
until observations and field tests by the ENGINEER indicate the moisture content 
of the materials being excavated are within the limits previously specified.  This 
requirement does not preclude the CONTRACTOR from disking or aerating 
excessively wet areas to enhance drying. 
 
C. 
Throughout construction, all excavation areas shall be graded to provide positive 
drainage to appropriate detention basins or drainage structures to prevent 
ponding of water.  Surface water shall be controlled to avoid damage to adjoining 
properties or to finished work on the Site.  The CONTRACTOR shall assume all 
responsibility for surface water damage to completed work or adjoining 
properties arising from the CONTRACTOR’S work. 
 
D. 
The CONTRACTOR shall inspect the condition of all existing slopes prior to bid to 
determine the extent of remedial work necessary to construct the slopes shown 
on the Contract Drawings.  The submission of a bid will be considered proof that 
the bidder has examined the Site and understands the conditions to be 
encountered in performing the Work.  The CONTRACTOR shall use material from 
the north area excavation to complete the required remedial slope fills.  The 
CONTRACTOR will be responsible for the stability and safety of the existing slopes 
during remedial slope filling. 
 
E. 
The CONTRACTOR shall not haul any material excavated from the north area 
excavation to locations other than General or Engineered Fill areas shown on the 
Drawings or the stockpile locations shown on the Contract Drawings, unless 
otherwise directed by the ENGINEER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02222 - 3 of 3 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 1 of 9 
SECTION B02223 
BACKFILLING 
 
1.0 
GENERAL 
 
1.01 
SUMMARY DESCRIPTION 
 
A. 
This Section describes the general requirements for subgrade preparation, 
backfill placement, and structural fill. 
 
1.02 
RELATED WORK SPECIFIED ELSEWHERE 
 
A. 
Section B02211 – Grading 
B. 
Section B02222 – Excavation 
 
1.03 
REFERENCES 
 
A. 
American Society for Testing and Materials (ASTM): 
 
1. 
D 422 
Method for Particle-Size Analysis for Soils 
2. 
D 854 
Test Method for Specific Gravity of Soils 
3. 
D 1556 
Test Method for Density of Soil in Place by the Sand-Cone 
Method 
4. 
D 1557 
Test Methods for Moisture-Density Relations of Soils and 
Soil-Aggregate Mixture Using 10-lb (4.54 kg) Rammer and 
30-in. (457 mm) Drop 
5. 
D 3034 
Standard Test Method for Permeability of Granular Soils 
(Constant Head) 
6. 
D 2850 
Test 
Methods 
for 
Unconsolidated, 
Undrained 
Compressive Strength of Cohesive Soils in Triaxial 
Compression 
7. 
D 3087 
Classifications of Soils for Engineering Purposes 
8. 
D 2922 
Test Methods for Density of Soil and Soil-Aggregate in 
Place by Nuclear Methods (Shallow Depth) 
9. 
D 2937 
Test Methods for Density of Soil in Place by the 
Drive-Cylinder Method

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 2 of 9 
10. D 3017 
Test Methods for Moisture Content of Soil and Soil-
Aggregate Mixtures. 
11. D 4330 
Test Method for Liquid Limit, Plastic Limit, and Plasticity 
Index of Soils 
12. D 4643 
Test Method for Determination of Water (Moisture) 
Content of Soil by the Microwave Oven Method 
 
B. 
United States Environmental Protection Agency (USEPA): 
 
 
 
1. 
USEPA Test Method 9100 
 
1.04 
GENERAL REQUIREMENTS 
 
A. 
The CONTRACTOR shall be solely responsible for the safety of temporary 
cuts and fills. 
B. 
The CONTRACTOR shall, except as otherwise required by Engineer or 
Specifications, maintain the finished surface or subgrade adjacent to or 
forming the foundation for backfill within normal industry tolerance for 
the specific Work. 
C. 
The CONTRACTOR shall use equipment, tools, and machines to perform 
the Work in accordance with requirements covered by the Specifications.  
The CONTRACTOR shall maintain equipment, tool and machines in 
satisfactory working condition.  Compaction equipment shall be suitable 
for the soils to be compacted so as to consistently produce the required 
strengths throughout the compacted soil mass as required by the 
Specifications. 
D. 
The CONTRACTOR shall exclusively use excavated materials for structural 
fill. 
E. 
The CONTRACTOR shall grade and restore areas disturbed in any manner 
not required for completion of the Work during construction and restore 
disturbed areas to their original grade and profile. 
F. 
The CONTRACTOR shall conduct work to reduce erosion/sedimentation to 
as little as possible and shall provide temporary erosion control as 
required. 
G. 
The CONTRACTOR is responsible for quality control measures for 
conducting the Work and corrective actions required by CQA testing and 
inspection.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 3 of 9 
1.05 
PERFORMANCE REQUIREMENTS 
 
A. 
The daily and intermediate cover stockpiles shall at a nominal 85% of 
Modified Proctor in accordance with ASTM D1557. 
 
 
1.06 
QUALITY CONTROL 
 
A. 
General 
 
1. 
CQA observation, sampling and testing will be performed by the 
ENGINEER to confirm that materials and construction are in 
compliance with the requirements of the Contract Documents in 
accordance with Section 01400. 
 
2. 
The CONTRACTOR shall implement the necessary quality control 
measures for earthwork preparation, excavation, backfill, and 
compaction of the Work. 
 
B. 
Laboratory Test Methods 
 
1. 
It shall be the responsibility of the CQA Engineer to perform any 
laboratory tests on the soils being excavated by the CONTRACTOR.  The 
CONTRACTOR shall perform laboratory Quality Control testing in 
accordance with the approved Quality Control Plan.  
 
C. 
Field Test Methods 
 
1. 
It shall be the responsibility of the CQA Engineer to perform 
Construction Quality Assurance field testing.  The CONTRACTOR shall 
perform field Quality Control testing in accordance with the 
approved Quality Control Plan. 
 
1.07 
SUBMITTALS 
 
A. 
The CONTRACTOR shall submit for the ENGINEER’s review, specifications 
of the equipment proposed for the excavation, hauling and compaction 
and its application at least 15 days before commencing each application. 
 
B. 
Verification shall also be made after the first month of operation that the 
equipment proposed is of sufficient size and quantity to accomplish the

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 4 of 9 
work within the term of the Contract. 
 
1.08 
ENGINEERED FILL AREAS 
 
A. 
Areas of Engineered Fill shall be remedial slope fills, and any other areas 
so designated by the ENGINEER. 
 
1.09 
STRUCTURES 
 
A. 
Structures shall be defined as improvements such as soil stockpiles, 
drainage ditches, piping, and culverts. 
 
2.0 
PRODUCTS 
 
2.01  RIPRAP 
 
A. Riprap shall be obtained from off-site sources selected by the CONTRACTOR 
and shall be approved by the ENGINEER. The riprap shall be hard, durable, 
angular to sub-rounded in shape; resistant to weathering and to water action; 
free from overburden, spoil, and organic material; and shall meet the 
gradation requirements for the size specified. Rounded shaped stone such as 
“river rock” shall not be acceptable for use as riprap material. Neither the 
width nor thickness of a single stone should be less than one-third its length. 
Not more than 25 percent of the stone reasonably distributed throughout the 
gradation shall have a length of more than 2.5 times the width or thickness. 
The minimum unit weight of the stone shall be 157 pounds per cubic foot. 
 
B. The gradation requirements for 6-inch riprap are as follows:

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 5 of 9 
 
TABLE B02223-1 
RIPRAP GRADATION 
 
Stone Size 
for 6-in 
riprap 
(in inches) 
Percent Total Weight Smaller 
(than the Given Size) 
12 
100-90 
9 
85-70 
6 
50-30 
4 
15-5 
2 
5-0 
 
 
3.0 
EXECUTION 
 
3.01 
PREPARATION FOR FILL PLACEMENT 
 
A. 
Before placing fill materials, the CONTRACTOR shall prepare the Work area 
by clearing existing obstructions, vegetation, and debris.  Unsuitable 
material shall be removed where directed. 
B. 
The CONTRACTOR shall maintain proper and adequate surface drainage to 
the satisfaction of the ENGINEER in order to keep the Site dry and in such 
condition that placement and compaction of fill may proceed unhindered 
by saturation of the Work area. 
C. 
The CONTRACTOR shall proof roll existing surfaces in the presence of the 
ENGINEER prior to fill placement.  Proof rolling shall be performed with 
available heavy construction equipment of not less than 10-ton wheel 
load.  Soft or unstable areas shall be removed and replaced with suitable 
materials as directed by the ENGINEER and recompacted.  Rock subgrades 
exposed during grading shall be observed by the ENGINEER and repaired 
for voids, cracks or other weaknesses as directed by the ENGINEER. 
D. 
Except as noted on the Contract Drawings or as required by the ENGINEER, 
sloped ground surfaces steeper than one vertical to 5 horizontal, on 
structural fill on which structures are constructed, shall be cut to form 
benches as the Work is brought up in layers. 
 
3.02 
MATERIAL PROCESSING

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 6 of 9 
 
A. 
All soil materials to be utilized for construction of the remedial slope fills 
shall be processed in the excavation area before transporting the material 
to the fill locations except for minor adjustments to be made in moisture 
content specified in the construction method.  The processing of the soil 
materials shall involve the following tasks: 
• 
Water content adjustment; 
• 
Removal of oversized material (boulders averaging more than 6” in 
diameter); 
• 
Reduction or pulverization of clay clods; and 
• 
Mixing of soil. 
 
The ENGINEER may observe, periodically test, and document processing of 
the material.  The ENGINEER shall perform visual classification of soils by 
utilizing field tests such as dry strength, fines content, toughness tests 
(ASTM D2488) and perform fines content (ASTM D1140), moisture content 
with calcium carbide (ASTM D4944) or nuclear gauge (ASTM D3017) or 
microwave method (ASTM D4643). 
 
B. 
Due to the climatic conditions in Glendale, Arizona, it will be necessary for 
the CONTRACTOR to process the material before placement so that the 
moisture content remains at the target or within the specified range, the 
consistency of the soil is uniform, and the amount of clods are minimal. 
 
3.03 
GENERAL REQUIREMENTS FOR BACKFILLS 
 
A. 
The CONTRACTOR shall obtain fill materials from the required excavation.  
Materials shall be free of objectionable material, with no stone dimension 
greater than as specified by material type.   
B. 
The CONTRACTOR shall not operate heavy equipment over pipes and 
buried structures until at least 1.5 feet of fill material has been placed and 
compacted over the top in conformance with the requirements specified 
herein, or as directed by the ENGINEER.  The CONTRACTOR shall select and 
operate compaction equipment so that structures are not damaged nor 
over stressed during compaction operations.  The CONTRACTOR shall use 
hand-operated mechanical tampers for compaction of fill material 
adjacent to structures where rolling equipment is impractical for use in 
compaction. 
C. 
The CONTRACTOR shall place fill materials in horizontal layers not 
exceeding the allowable lift thickness and which, after compaction, meet

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 7 of 9 
or exceed established compaction requirements.  The CONTRACTOR shall 
place material containing stones in a manner to prevent segregation of the 
material and to prevent the formation of rock nests and voids in the fill. 
D. 
The CONTRACTOR shall place and compact fill materials while at their 
required water content. 
E. 
The CONTRACTOR shall provide general fill to lines, grades, and elevations 
as shown on the Contract Drawings or as required in writing by the OWNER 
or ENGINEER. 
F. 
The CONTRACTOR shall place material in continuous layers not exceeding 
the required loose condition depth unless otherwise directed or approved.  
The cross fall of each layer shall not exceed one foot in 20 feet. 
G. 
The CONTRACTOR shall backfill systematically, as early as possible, to allow 
maximum time for natural settlement.  The CONTRACTOR shall not backfill 
over porous, wet, or spongy subgrade surfaces. 
H. 
The CONTRACTOR shall make changes in grade gradual and blend slopes 
into level areas. 
I. 
The CONTRACTOR shall compact each layer with a sufficient number of 
passes of the soil compactor.  The number of passes shall be determined 
such that in the opinion of ENGINEER, sufficient compaction has been 
obtained. 
J. 
Soils which cannot be placed and compacted to the criteria indicated in the 
Specifications due to excessive moisture content should be air dried for a 
sufficient amount of time such that they may be placed and compacted to 
meet the criteria or removed and replaced. 
K. 
In the event of a failing test, supplemental testing shall be performed prior 
to placing additional fill in order to define the area that has been 
inadequately compacted.  The area shall be reworked and/or removed and 
replaced, then retested prior to subsequent material being placed over the 
area. 
 
3.04 
REMEDIAL SLOPE FILLS 
 
A. 
The CONTRACTOR shall provide Engineered Fill to lines, grades and 
elevations as shown on the Contract Drawings and as approved by the 
ENGINEER. 
B. 
The CONTRACTOR shall place the processed soil materials in approximately 
ten-inch loose lifts to produce a compacted lift thickness of approximately 
eight inches.  The CONTRACTOR shall compact each lift to meet the

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 8 of 9 
requirements specified herein. 
C. 
Compaction shall be performed with appropriate equipment capable of 
providing compactive forces commensurate with the densities required. 
D. 
Engineered fill materials are to be compacted to at least 90 percent 
compaction as specified by ASTM D 1557 unless otherwise specified or 
approved by the ENGINEER. 
E. 
Moisture content shall be maintained uniform throughout and within the 
limits of ±2 percent of optimum moisture content. 
F. 
The maximum compacted lift thickness shall be 8”. 
G. 
The CONTRACTOR shall separate/segregate fine grained and course 
grained materials as directed by the ENGINEER.  Fine grained materials will 
be used for remedial slope fills. 
H. 
Where work is interrupted by rains, fill operations shall not be resumed 
until observations and field tests by the ENGINEER indicate that the 
moisture content and density of the in-place fills are within specified limits. 
I. 
Unless otherwise specified by the ENGINEER, no permanent cut slopes 
shall be excavated steeper than allowed by the ENGINEER, the OWNER or 
the Regulator. 
 
3.05 
UNSUITABLE MATERIALS 
 
A. 
Unsuitable material encountered below the natural ground surface in fill 
areas or below the grading plane in excavation areas shall be excavated 
and disposed of as directed by the ENGINEER.  Unsuitable material is 
defined as material the ENGINEER determines to be one of the following: 
 
1. 
Of such unstable nature as to be incapable of being compacted to 
specified density using ordinary methods at optimum moisture 
content; 
2. 
Too wet to be properly compacted and circumstances prevent 
suitable in-place drying prior to incorporation into the Work; or 
3. 
Otherwise unsuitable for the planned use. 
 
The presence of excessive moisture in a material is not, by itself, sufficient 
cause for determining that the material is unsuitable. 
B. 
When unsuitable material is removed and disposed of, the resulting space 
shall be filled with material suitable for the planned use.  Such suitable

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 9 of 9 
material shall be placed and compacted in layers as herein specified 
C. 
The CONTRACTOR shall dispose of foreign materials, rubble, abandoned 
construction waste, and material that is unacceptable to the ENGINEER for 
fill in accordance with local regulations. 
D. 
The CONTRACTOR shall grade temporary waste holding areas to maintain 
a natural appearing variable percentage slope and to prevent slope 
failures. 
 
3.06 
TEMPORARY DRAINAGE 
 
A. 
The CONTRACTOR shall be responsible for constructing, operating and 
maintaining temporary drainage systems while construction occurs prior 
to the permanent drainage system being constructed and operational.  
Temporary drainage systems shall be required to handle existing drainage 
and the revised drainage patterns as they occur during construction.  
Temporary drainage systems shall not impact the ability to construct 
permanent drainage systems.  The CONTRACTOR shall be solely 
responsible for repairing/replacing appurtenances and/or Work damaged 
due to inadequate stormwater management during construction at no 
cost to the OWNER. 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not 
specifically listed in Section A01025 will be considered incidental to the 
Project.  The CONTRACTOR will not be compensated for Work not 
specifically listed in Section A01025.  
 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02720 - 1 of 3 
SECTION B02720 
DRAINAGE FACILITIES 
 
1.0  
GENERAL 
1.01 
DESCRIPTION OF WORK 
A. 
The CONTRACTOR shall furnish all labor, materials, tools, supervision, 
transportation, and installation equipment necessary for installation of all storm 
drain materials and appurtenances as specified herein, as shown on the Contract 
Drawings. 
1.02 
SUBMITTALS 
A. 
The CONTRACTOR shall submit to the ENGINEER for approval within 14 days 
after signing of the Contract and at least 28 days before the start of work, 
complete, detailed shop drawings of all storm drain materials, a list of materials 
to be furnished, names of the suppliers and the proposed dates of delivery of 
the materials to the site. 
B. 
The CONTRACTOR shall submit to the ENGINEER the manufacturer's certification 
of compliance with this Section for all materials delivered to the site, and shall 
comply with the manufacturer's recommendations for handling, storing, and 
installing of all storm drain materials. 
2.0  
PRODUCTS 
2.01 
CORRUGATED HIGH DENSITY POLYETHYLENE (CHDPE) PIPE 
A. 
The CHDPE pipe shall be a smooth-walled interior, corrugated exterior pipe (ADS 
N-12 or approved equivalent). 
B. 
The CHDPE pipe shall be in accordance with the requirements of AASHTO M-294 
and have a minimum cell classification of PE 335420C. 
C. 
CHDPE pipe shall be supplied in standard laying lengths. 
D. 
The 12-inch CHDPE pipe material shall comply with the notched constant 
ligament-stress (NCLS) test as specified in Sections 9.5 and 5.1 of AASHTO M294 
and ASTM 2306 respectively.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02720 - 2 of 3 
2.02 
CORRUGATED METAL PIPE (CMP) 
A. 
Corrugated metal 12-inch pipe shall be plain galvanized metal pipe conforming 
to the requirements of AASHTO M-36 with a minimum wall thickness of 2.8 mm. 
B. 
Field joints shall provide circumferential and longitudinal strength to maintain 
alignment, prevent separation of the pipe, prevent infiltration of side fill 
material, and prevent leakage of water into the surrounding soil. 
C. 
The external coating and internal lining of the pipe shall be in accordance with 
AASHTO M-190. 
3.0  
EXECUTION 
3.01 
HANDLING AND PLACEMENT 
A. 
The CONTRACTOR shall exercise care when transporting, handling and placing 
CHDPE and CMP pipe and fittings, such that they will not be cut, kinked, twisted, 
or otherwise damaged. 
B. 
Pipe or fittings shall not be dropped onto rocky or unprepared ground.  Under 
no circumstances shall pipe or fittings be dropped into trenches, or dragged over 
sharp and or abrasive objects. 
C. 
CHDPE and CMP pipe shall be stored on clean level ground, preferably turf or 
sand, free of sharp objects that could damage the pipe. 
D. 
Bedding and backfill material for storm drain structures shall be the same as the 
final cover fill and placed in accordance with Section 02200 and the drawings. 
3.02 
INSTALLATION 
A. 
General: 
1. 
All storm drain materials shall be installed in accordance with the 
manufacturer's instructions and MAG Specifications. 
2. 
The CONTRACTOR shall carefully examine all structures for damage or 
defects before installation. Defective materials shall be immediately 
removed from the site and replaced at no additional cost to the OWNER. 
3. 
The interior of all pipe and fittings shall be inspected, and any foreign 
material shall be completely removed from the pipe interior before it is 
moved into final position.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02720 - 3 of 3 
4. 
All structures and pipes shall be laid or placed to the lines and grades 
shown on the Drawings with bedding and backfill material shown on the 
Drawings and as specified in this Section. 
5. 
Field-cutting of pipes, where required, shall be made with a machine. No 
structures or pipes shall be laid until the OWNER or the ENGINEER has 
approved the bedding conditions. 
6. 
No pipes shall be brought into position until the preceding length has 
been bedded and secured in its final position. 
3.03 
JOINTS AND CONNECTIONS 
A. 
Assembly of the gasketed joints shall be in accordance with the pipe 
manufacturer’s recommendations.  All joints shall be water tight. 
3.04 
PRODUCT PROTECTION 
A. 
The CONTRACTOR shall use all means necessary to protect all prior work and 
materials and completed work of other Sections. 
B. 
In the event of damage to any structure or pipe during construction activities, 
the CONTRACTOR shall immediately make all repairs, recoating as necessary, and 
replacements necessary, to the approval of the OWNER or the ENGINEER and at 
no additional cost to the OWNER. 
 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2A EXCAVATION, HAUL, AND STOCKPILE PROJECT 
 
 
 
 
APPENDIX A 
 
NORTH CELL GEOTECHNICAL INFORMATION

MAYOR
CITY COUNCIL
CITY MANAGER
CITY CLERK
CITY ATTORNEY
JERRY P. WEIERS
KEVIN R. PHELPS
JULIE K. BOWER
MICHAEL D. BAILEY
PINNACLE PEAK RD.
DEER VALLEY RD.
BEARDSLEY RD.
UNION HILLS DR.
BELL RD.
GREENWAY RD.
THUNDERBIRD RD.
CACTUS RD
PEORIA AVE.
OLIVE AVE.
NORTHERN AVE.
GLENDALE AVE.
BETHANY HOME RD.
CAMELBACK RD.
GRAND AVE.
115TH AVE
107TH AVE.
99TH AVE.
91ST AVE.
83RD AVE.
75TH AVE.
67TH AVE.
59TH AVE.
51ST AVE.
43RD AVE.
VICINITY      MAP
CITY OF GLENDALE
KEY      MAP
EL MIRAGE RD.
SARIVAL AVE.
REEMS RD.
BULLARD AVE.
LITCHFIELD RD.
DYSART RD.
GLENDALE, ARIZONA
SITE
JOYCE V. CLARK
LAUREN TOLMACHOFF
BART TURNER
RAY MALNAR
JAMIE ALDAMA
IAN HUGH
GLENDALE LANDFILL
NORTH CELL EXCAVATION PHASE 2A
OCTOBER 2022
SHEET INDEX
SHEET NO.
DESCRIPTION
1
TITLE SHEET
2
PLAN VIEW
BENCHMARK DATUMS & POINTS
HORIZONTAL DATUM: NAD 83
VERTICAL DATUM: NAVD 88
CONTROL POINT #1: N 928199.38 E 583693.57 ELEV 1082.60
CONTROL POINT #2: N 928207.398 E 580355.01 ELEV 1064.723
CONTROL POINT #3: N 925551.414 E 583695.891 ELEV 1072.763
3
EXCAVATION PLANS
4
EXCAVATION PLANS
5
STOCKPILING PLANS
6
STOCKPILING PLANS
7
DETAILS

W
W
W
W
W
W
W
0
GRAPHIC SCALE:1''=
50
100'
100
200
1.
THE EXISTING UTILITIES SHOWN ON THESE DRAWINGS ARE APPROXIMATE, AND
UTILITY LINES MAY EXIST WHERE NONE ARE SHOWN. SOME INFORMATION MAY
HAVE BEEN DERIVED FROM INFORMATION PROVIDED TO THE ENGINEER BY
OTHERS. SUCH INFORMATION MAY BE INCOMPLETE OR MAY BE OBSOLETE BY THE
TIME CONSTRUCTION COMMENCES. CONTACT BLUE STAKE AT 811 AND ANY
NON-PARTICIPATING UTILITY COMPANIES AT LEAST 48 HOURS BEFORE
CONSTRUCTION. THE CONTRACTOR SHALL EXCAVATE AND VERIFY THE
HORIZONTAL AND VERTICAL LOCATIONS OF PERTINENT UTILITIES, LANDFILL
LINERS, AND OTHER EXISTING FEATURES IN OR NEAR THE AREA OF WORK,
WHETHER INDICATED ON THESE DRAWINGS OR NOT. SHOULD A CONFLICT EXIST,
THE CONTRACTOR SHALL NOTIFY THE ENGINEER AS SOON AS POSSIBLE. THE
CONTRACTOR SHALL EXERCISE DUE CARE TO AVOID DISTURBING ANY
UNDERGROUND UTILITIES. THE CONTRACTOR SHALL COORDINATE ANY
POTENTIAL DISRUPTIONS IN UTILITY SERVICE WITH THE UTILITY COMPANIES
AFFECTED AT LEAST 24 HOURS PRIOR TO THE DISRUPTION. THE CONTRACTOR
SHALL REPAIR DAMAGE TO EXISTING UTILITIES AT THE CONTRACTOR’S EXPENSE.
2.
CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND COORDINATE SITE
CONDITIONS WITH THE DRAWINGS PRIOR TO CONSTRUCTION, ANY
DISCREPANCIES OR OMISSIONS SHALL BE RESOLVED WITH THE PROJECT
ENGINEER. DO NOT USE SCALED DIMENSIONS.
NOTES:

W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
0
GRAPHIC SCALE:1''=
30'
60'
60'
120'
W

0
GRAPHIC SCALE:1''=
30'
60'
60'
120'

0
GRAPHIC SCALE:1''=
30'
60'
60'
120'

0
GRAPHIC SCALE:1''=
30'
60'
60'
120'

NTS
A
ASPHALT MILLINGS ROADWAY
REFERENCE SHEET 3 & 4
40'
6"
2'
6'
NTS
B
JENSEN PRECAST 10' K-RAIL
REFERENCE SHEET 3
1'
Point Table
Point #
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Elevation
1054.00
1054.00
1052.00
1052.00
1060.00
1060.00
1056.00
1056.00
1057.25
1060.00
1060.00
1062.00
1062.00
1068.00
1068.00
1068.00
1060.00
1066.00
1066.00
1030.00
1030.00
Northing
926648.48
926648.41
926710.47
926705.62
926972.98
926969.97
927184.85
927194.93
927609.62
927755.21
927756.38
927788.22
927789.38
927894.29
927846.06
927905.74
927862.68
928031.11
927959.75
927977.71
927920.21
Easting
581032.79
581072.29
581032.60
581072.39
581050.63
581090.54
581057.83
581067.95
581069.18
581040.37
581080.35
581039.44
581079.25
581084.71
581105.09
581158.25
581159.89
581184.77
581160.43
581565.53
581538.52
Description
V GRADEBREAK
V GRADEBREAK
H GRADEBREAK
H GRADEBREAK
GRADEBREAK
GRADEBREAK
VALVE
VALVE
VALVE
GRADEBREAK
GRADEBREAK
GRADEBREAK
GRADEBREAK
GRADEBREAK
GRADEBREAK
GRADEBREAK
GRADEBREAK
GRADEBREAK
GRADEBREAK
GRADEBREAK
GRADEBREAK
Point Table
Point #
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
Elevation
1054.00
1054.00
1025.94
1026.66
1019.48
1030.00
1016.00
1013.74
1008.50
1005.50
986.50
986.00
981.80
982.95
976.50
975.50
950.00
950.02
0.00
0.00
0.00
Northing
927895.74
927855.56
927801.68
927762.40
927788.95
927730.11
927769.97
927713.31
927659.09
927599.18
927629.47
927570.01
927560.20
927553.71
927459.68
927455.10
927030.39
927043.69
927815.74
927556.11
927685.84
Easting
581358.25
581358.25
581847.38
581840.73
581948.88
581937.18
582034.19
582009.74
582005.38
582008.91
581664.51
581672.44
581599.78
581659.60
581603.76
581643.60
581578.84
581618.80
581128.63
581674.66
582011.39
Description
GRADEBREAK
GRADEBREAK
40' to 60' TRANSITION
40' to 60' TRANSITION
40' to 60' TRANSITION
40' to 60' TRANSITION
CURVE
CURVE
CURVE
CURVE
CURVE
CURVE
CURVE
CURVE
40' TO 60' TRANSITION
40' TO 60' TRANSITION
GRADEBREAK
GRADEBREAK
CURVE CP
CURVE CP
CURVE CP
NTS
C
MAG STANDARD 501-5 HEADWALL (MOD.)
REFERENCE SHEET 3

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S P A G E I S B L A N K

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
EXHIBIT F 
Statement of All Clarifications and Assumptions (if any) 
 
(1 pages - To be Incorporated by Amendment)

Date: 10‐28‐2022 
Exhibit F  
Municipal Landfill North Cell Excavation Phase II CMAR – Project 212261 
Qualifications: 
1.
GMP is based on the following documents:
a.
Revised Specifications dated 10/24/2022
b.
Revised Plans (sheets 1‐7) signed 10/24/2022 and revised per CAD file received
10/19/2022
c.
Order of Precedence
i.
RFIs
ii.
Plans
iii.
Specifications
2.
GMP is based on the following comments/clarifications
a.
No end treatments shown for stormwater crossing in basin nor provided.
b.
Any landfill gas well or line adjustments to be done for south stockpile to be done under
existing landfill maintenance contract.  Those costs are not accounted for in the GMP
c.
City of Glendale to provide construction water at no cost. Extension of waterline will be
done under the existing landfill maintenance contract.
d.
All embankments are general fill and do not require QC testing
e.
Plans do not indicate date of existing topography.  We will perform a pre‐topo to verify
and use the contractor’s contingency for any adjustments.
Exhibit F page 1/1

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S P A G E I S B L A N K

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
EXHIBIT G 
Schedule of Major Milestones 
 
(1 pages - To be Incorporated by Amendment)

ID
Task Name
Duration
Start
Finish
1
Submittal of GMP1
0 days
Mon 10/24/22
Mon 10/24/22
2
City Review
22 days
Mon 10/24/22
Tue 11/22/22
3
Council Approval
0 days
Tue 11/22/22
Tue 11/22/22
4
Construct North Cell Phase 2A
70 days
Wed 11/30/22
Thu 3/9/23
5
Mobilization
5 days
Wed 11/30/22
Tue 12/6/22
6
Relocate AC Millings
3 days
Wed 12/7/22
Fri 12/9/22
7
General Fill for Haul Roads
6 days
Mon 12/12/22
Mon 12/19/22
8
Excavate to North Stockpile
27 days
Tue 12/20/22
Fri 1/27/23
9
Excavate To South Stockpile
27 days
Tue 12/20/22
Fri 1/27/23
10
Rough Grade Haul Road
3 days
Mon 1/30/23
Wed 2/1/23
11
Excavate Ditch and Place Riprap
6 days
Thu 2/2/23
Thu 2/9/23
12
Install Stormwater crossing & riprap
4 days
Fri 2/10/23
Wed 2/15/23
13
Finegrade for AC Millings
3 days
Tue 2/14/23
Thu 2/16/23
14
Place & Finish AC Millings
5 days
Fri 2/17/23
Thu 2/23/23
15
Apply Fog Coat
3 days
Fri 2/24/23
Tue 2/28/23
16
Install Safety Barriers
2 days
Wed 3/1/23
Thu 3/2/23
17
Substantial Completion
0 days
Thu 3/2/23
Thu 3/2/23
18
Punch list & Debmobilization
5 days
Fri 3/3/23
Thu 3/9/23
19
Final Completion
0 days
Thu 3/9/23
Thu 3/9/23
10/24
11/22
3/2
3/9
10/1610/2310/3011/611/1311/2011/2712/412/1112/1812/25 1/1 1/8 1/15 1/22 1/29 2/5 2/12 2/19 2/26 3/5 3/12 3/19 3
November
December
January
February
March
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Rummel Construction, Inc.
CONSTRUCTION MANAGER AT RISK AGREEMENT - Exhibit G - Preliminary Project Schedule
Municipal Landfill North Cell Excavation Phase II CMAR - Project No. 212261 - October 24,2022
Page 1
Project: Preliminary Schedule
Date: Mon 10/24/22

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
T H I S P A G E I S B L A N K

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
EXHIBIT H 
Dispute Resolution Procedures 
 
1. 
Disputes. 
1.1 
Each Dispute arising out of or related to this Agreement (including Disputes 
regarding any alleged breaches of this Agreement) shall be initiated and decided 
under the provisions of this Exhibit. 
1.2 
CMAR and City shall each designate in writing to the other party, from time to 
time, a member of senior management who shall be authorized to attempt to 
expeditiously resolve any Dispute relating to the subject matter of this Agreement 
in an equitable manner. 
1.3 
A party shall initiate a Dispute by delivery of written notice to the members of 
management designated by the respective parties under Section 1.2 of this Exhibit.   
1.4 
The parties must:   
(A) 
Attempt to resolve all Disputes promptly, equitably and in a good faith 
manner; and  
(B) 
Provide each other with reasonable access during normal business hours to 
any and all non-privileged records, information and data pertaining to any 
such Dispute. 
1.5 
With respect to matters concerning modification of the GMP or any schedule, 
CMAR must first follow the provisions of any Claim procedure established by the 
Design-Build Agreement before seeking relief under these Procedures. 
2. 
Emergency Arbitration. 
2.1 
If the parties are unable to accomplish resolution of a Dispute, the expedited 
resolution of which either party considers necessary to prevent or mitigate a 
material delay to the critical path of the Services (a "Time Sensitive Dispute") 
within two days after the Time Sensitive Dispute has been initiated by a party, either 
party may thereafter seek emergency relief before an emergency arbitrator (the 
"Emergency Arbitrator") appointed as follows:   
(A) 
The parties will exercise best efforts to pre-select an Emergency Arbitrator 
within 20 days after entering into this Agreement;  
(B) 
If the Emergency Arbitrator has not been selected at the time a party delivers 
Notice of a Time Sensitive Dispute, the parties will each select a 
representative within one day after the Notice is delivered and the two 
representatives will then select the Emergency Arbitrator by the third day 
following delivery of the Notice. 
(C) 
The Emergency Arbitrator shall be an attorney with at least ten (10) years’ 
experience with commercial construction legal matters in Maricopa County, 
Arizona, be independent, impartial, and not have engaged in any business 
for or adverse to either party for at least ten (10) years.   
2.2 
The Emergency Arbitrator will conduct a hearing and render a written 
determination on the Dispute to both parties within five business days of the matter 
being referred to him or her, all in accordance with Rules O-1 to O-8 of the

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
American Arbitration Association ("AAA") Commercial Rules-Optional Rules for 
Emergency Protection Commercial Rules ("AAA Emergency Rules"). 
2.3 
Although the hearing will be conducted using AAA rules, unless both parties agree 
otherwise, this dispute process will not be administered by the AAA but will be 
conducted by the parties in accordance with these procedures.  
2.4 
If, however, an Emergency Arbitrator has not selected within three days after 
delivery of the Notice, either party may upon three days additional notice, thereafter 
seek emergency relief before the AAA, in accordance with the AAA Emergency 
Rules, provided that the Emergency Arbitrator meets the qualifications set forth 
above.   
2.5 
All proceedings to arbitrate Time Sensitive Disputes shall be conducted in 
Glendale, Arizona.   
2.6 
Presentation, request for determination (i.e., a party’s prayer), and the Emergency 
Arbitrators decision will adhere to the procedures required in Section 3.6 of this 
Exhibit. 
2.7 
The finding of the Emergency Arbitrator with respect to any Time Sensitive 
Dispute will be binding upon the parties on an interim basis during progress of the 
Services, subject to review de novo by arbitration after the Project Substantial 
Completion Date. 
2.8 
The time and extent of discovery will be as determined by the Emergency 
Arbitrator. 
(A) 
 Discovery orders of the Emergency Arbitrator will consider the time 
sensitivity of the matter and the parties desire to resolve the issue in the 
most time and costs efficient manner; 
(B) 
The parties are obligated to cooperate fully and completely in the provision 
of documents and other information, including joint interviews of 
individuals with knowledge such that the matter moves toward resolution 
in the most time and costs efficient manner and the Emergency Arbitrator 
is empowered to fashion any equitable penalty against a party that fail to 
meet this obligation. 
3. 
Non-Emergency Arbitration. 
3.1 
Except as provided in Section 5 of this Exhibit, any Dispute that is either a non-
emergency Dispute that has not been resolved by negotiation, or a de novo review 
of an AAA emergency arbitration will be decided by binding arbitration by a panel 
of three arbitrators in accordance with, but not necessarily administered by, the 
Construction Industry Rules of the AAA.   
(A) 
The parties shall each select an arbitrator within 15 days after notice that a 
party desires to resolve a dispute by arbitration.   
(B) 
The two arbitrators shall then each select a third arbitrator.  If an arbitrator 
is not selected within any such 15 day period, then the arbitrator shall be 
appointed by the AAA.   
3.2 
The arbitrator(s) shall meet the qualifications of Emergency Arbitrators as provided 
in Section 2 of this Exhibit.

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
3.3 
The arbitrators do not have the authority to consider or award punitive damages as 
part of the arbitrators' award.   
3.4 
In connection with such arbitration, each party shall be entitled to conduct up to 
five depositions, and, no less than 90 days prior to the date of the arbitration hearing, 
each party shall deliver to the other party copies of all documents in the delivering 
party's possession that are relevant to the dispute.   
3.5 
The arbitration hearing shall be held within 150 days of the appointment of the 
arbitrators. 
3.6 
At the arbitration hearing, each party will argue its position to the arbitrators in 
support of one proposed resolution to the dispute (a “Proposed Resolution”).   
(A) 
Each party’s Proposed Resolution must be fully dispositive of the dispute.   
(B) 
The arbitrators must select one Proposed Resolution by majority consent 
and are not free to fashion any alternative resolutions. 
(C) 
The parties must submit their proposed resolution of the matter to the 
arbitrators and the other party 15 days prior to the date set for 
commencement of the arbitration proceeding. 
(D) 
The decision of the arbitrators will be forwarded to the parties within 15 
days after the conclusion of the arbitration hearing. 
(E) 
The decision of the arbitration panel is final and binding on the parties and 
may be entered in any court of competent jurisdiction for the purpose of 
securing an enforceable judgment.   
(F) 
All costs and expenses associated with the arbitration, including the 
reasonable legal fees and costs incurred by the prevailing party, must be 
paid by the party whose position was not selected by the arbitrators. 
4. 
Continuing Work.  Unless otherwise agreed to in writing, CMAR must continue to 
perform and maintain progress of the Work during any Dispute Resolution or arbitration 
proceedings, and City will continue to make payment to CMAR in accordance with the 
Agreement. 
5. 
Exceptions. 
5.1 
Neither City nor CMAR are required to arbitrate any third-party claim, cross-claim, 
counter claim, or other claim or defenses in any action that is commenced by a 
third-party who is not obligated by contract to arbitrate disputes with City and 
CMAR. 
5.2 
City or CMAR may commence and prosecute a civil action to contest a lien or stop 
notice, or enforce any lien or stop notice (but only to the extent the lien or stop 
notice the party seeks to enforce is enforceable under Arizona law), including, 
without limitation, an action under A.R.S. § 33-420, without the necessity of 
initiating or exhausting the procedures of this Exhibit. 
5.3 
This Exhibit does not apply to, and may not be construed to require arbitration of, 
any claims, actions or other process undertaken, filed, or issued by the City of 
Glendale Building Safety Department, Code Compliance Department, Police 
Department, Fire Department, or any other agency of City acting in its

City of Glendale Standard Form Agreement Between Owner and CM@Risk (April 15, 2022) 
 
 
governmental permitting, for the benefit of public health, safety, and welfare, or 
other regulatory capacity. 
5.4 
In connection with any arbitration, the arbitrators do not have the authority to, and 
may not enforce, any provision of the Federal or Arizona Rules of Civil Procedure.