Heroes Regional Park Fields Tuesday, December 13, 2022 2 Heroes Regional Park Fields 3 Project Cost Estimate: $17.3M Funding: $ 7.5M - American Rescue Plan Act (ARPA) Funding – FY2023 $ 4.0M* - Development Impact Fees (DIF) – FY2024 $11.5M - Total Available Funding for Project * Seeking Council Consensus 4 Heroes Regional Park Fields 5 • Consistent with the Parks and Recreation Master Plan • Design estimate, not final cost • Final cost will be determined once it is bid out • DIF budget from FY2024 CIP Heroes Regional Park Fields 6 Next Steps: • Draft RFQ started with a working group • Internal notification to the Clerk’s Office on 12/7 to run advertisement for 12/14 and 12/21 • Selection of consultant and contract approval sent to Council in spring Heroes Regional Park Fields 7 Questions?