TASK 100 101 Conduct & Attend Meetings $2,896 102 Monitor Progress & Prepare Status Reports $3,120 TASK 200 201 Background Data $1,656 202 Pipe Inspection Review & Assessment $5,023 203 Manhole Inspection & Assessment $12,771 204 Design Memorandum $10,335 TASK 300 301 Survey $39,637 302 Utility Research, Mapping & Coordination $10,046 303 Right-of-Way $4,834 304 Project Design & Contract Documents $88,749 305 Estimate of Probable Construction Cost $9,281 306 Design Submittals $21,072 307 MCESD ATC Permit $5,568 TASK 400 401 Respond to JOC RFIs $4,021 402 Review JOC Price Proposal $6,088 403 Addenda $5,135 TASK 500 501 On-Site Inspection & Review of Work $67,632 502 Interpretation of Construction Documents $3,078 503 Submittals, Shop Drawings & Test Results $7,165 504 Meetings $8,400 505 Change Orders $4,932 506 Records $2,100 507 Substantial & Final Inspections $6,364 TASK 600 601 Record Drawings $9,912 602 Obtain AOC from MCESD $2,116 $341,931 701 Pothole Services (TBD - 24 holes x $1,500/hole) $36,000 702 MCESD ATC Permit Fee $3,000 703 Design Contingency Allowance (PEC) $20,000 $59,000 $40,093 $441,024 OWNER'S CONTINGENCY TOTAL PROJECT MANAGEMENT SERVICES EVALUATION PHASE SERVICES DESIGN PHASE SERVICES PRE-CONSTRUCTION PHASE SERVICES CONSTRUCTION PHASE SERVICES POST-CONSTRUCTION PHASE SERVICES TASK 700 - MISCELLANEOUS ALLOWANCES SUBTOTAL SUBTOTAL ALLOWANCES PROFESSIONAL SERVICES EXHIBIT D PROJECT COMPENSATION SEWER & MANHOLE REHABILITATION PHASE 6 PROJECT NO. 212231