PSA - PEC Manhole Rehab Phase VI Signed

City of Glendale — Regular Meeting (2023-01-10)

View PDF Item 12 Meeting page

Extracted text (via pymupdf) 1497 characters
TASK 100
101
Conduct & Attend Meetings
$2,896
102
Monitor Progress & Prepare Status Reports
$3,120
TASK 200
201
Background Data
$1,656
202
Pipe Inspection Review & Assessment
$5,023
203
Manhole Inspection & Assessment
$12,771
204
Design Memorandum
$10,335
TASK 300
301
Survey
$39,637
302
Utility Research, Mapping & Coordination
$10,046
303
Right-of-Way
$4,834
304
Project Design & Contract Documents
$88,749
305
Estimate of Probable Construction Cost
$9,281
306
Design Submittals
$21,072
307
MCESD ATC Permit
$5,568
TASK 400
401
Respond to JOC RFIs
$4,021
402
Review JOC Price Proposal
$6,088
403
Addenda
$5,135
TASK 500
501
On-Site Inspection & Review of Work
$67,632
502
Interpretation of Construction Documents
$3,078
503
Submittals, Shop Drawings & Test Results
$7,165
504
Meetings
$8,400
505
Change Orders
$4,932
506
Records
$2,100
507
Substantial & Final Inspections
$6,364
TASK 600
601
Record Drawings
$9,912
602
Obtain AOC from MCESD
$2,116
$341,931
701
Pothole Services (TBD - 24 holes x $1,500/hole)
$36,000
702
MCESD ATC Permit Fee
$3,000
703
Design Contingency Allowance (PEC)
$20,000
$59,000
$40,093
$441,024
OWNER'S CONTINGENCY 
TOTAL 
PROJECT MANAGEMENT SERVICES
EVALUATION PHASE SERVICES
DESIGN PHASE SERVICES
PRE-CONSTRUCTION PHASE SERVICES
CONSTRUCTION PHASE SERVICES
POST-CONSTRUCTION PHASE SERVICES
TASK 700 - MISCELLANEOUS ALLOWANCES
SUBTOTAL 
SUBTOTAL ALLOWANCES 
PROFESSIONAL SERVICES
EXHIBIT D
PROJECT COMPENSATION
SEWER & MANHOLE REHABILITATION PHASE 6
PROJECT NO. 212231