Update #10: Downtown Campus 
Reinvestment Project
City Council Workshop
March 28, 2023
Presenter: Kevin Phelps

Continuity of Operations
2
Adult Center
Civic Center Campus
GRPSTC
Airport
Sine Bldg.
Media Center

3
Continuity of Operations Status
Planning
Design
Construction
*Move In
Sine Building – Mar.  ‘22 thru Dec.‘22
Jan.
Media Center – June ‘22 thru June ‘23
*June
Adult Center – May ‘22 thru April ‘23
*April-May
GRPSTC – May ‘22 thru Dec. ‘22
Dec. 22
Airport – May ‘22 thru Dec. ‘22
Dec.22
Bead Museum – Aug. ‘22 thru Aug. ‘23
*July-Aug.
Annex – Aug. ‘22 thru Aug. ‘23
*July.-Aug.

Media Center
4
Budget
$415,450
Scope
Minor tenant improvements
Schedule
Revised –June 2023
Level 3
Level 2

Adult Center
5
Budget
$2,839,350
Scope
Remodel second floor
Schedule
Revised – April 2023

Bead Museum
6
Budget
$1,122,100
Revised  Feb. 14:  $2,360,700
Scope
Remodel / T.I.
Schedule
Revised – August 2023

Annex
7
Budget 
$494,850
Revised Feb. 14:   $839,300
Scope 
T.I. to meeting room & furniture
Schedule
Revised – August 2023

Community Engagement
8

Community Engagement
9
Heroes Library
Council Chambers
Foothills Recreation & Aquatics Center

10