CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
TABLE OF CONTENTS 
TABLE OF CONTENTS 
 
 
SECTION A – GENERAL REQUIREMENTS 
 
SECTION A01010 
SUMMARY OF WORK 
SECTION A01015 
ABBREVIATIONS AND DEFINITIONS 
SECTION A01019 
MOBILIZATION AND DEMOBILIZATION 
SECTION A01025 
MEASUREMENT AND PAYMENT 
SECTION A01030 
SPECIAL INSTRUCTIONS 
SECTION A01050 
SURVEYING 
SECTION A01052 
LAYOUT OF WORK AND SURVEYS 
SECTION A01106 
COORDINATION AND MEETINGS 
SECTION A01310 
CONSTRUCTION WORK PLAN AND SCHEDULE 
SECTION A01400 
QUALITY CONTROL 
SECTION A01500 
TEMPORARY FACILITIES AND CONTROLS 
SECTION A01510 
TRAFFIC CONTROL 
SECTION A01810 
DRAWINGS 
 
SECTION B – SITEWORK 
 
SECTION B02200 
EARTHWORK 
SECTION B02211 
GRADING 
SECTION B02222 
EXCAVATION 
SECTION B02223 
BACKFILLING 
SECTION B02720 
DRAINAGE FACILITIES 
 
 
APPENDIX A – NORTH CELL GEOTECHNICAL INFORMATION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 1 of 5 
SECTION A01010 
SUMMARY OF WORK 
 
 
1.0 
GENERAL 
1.01 
BRIEF PROJECT DESCRIPTION 
 
A. 
The Glendale Landfill (Site) is located within the City of Glendale (OWNER), 
Arizona to the west of Phoenix.  The Site address is 11480 W. Glendale Avenue, 
Glendale, Arizona, 85307, Maricopa County.  Access to the Site is as follows: from 
Phoenix take I-10 west to the Loop 101, north on the Loop 101 to Glendale Avenue, 
and west on Glendale Avenue to the Glendale Landfill. 
 
B. 
General: Work included in the contract primarily consists of the excavation, hauling 
and stockpiling of soil from the Site’s north cell.  The CONTRACTOR will be 
required to stockpile the soil for future use.  The Work is detailed in these 
Specifications and on the Contract Drawings included herein. 
 
C. 
Principal Features: 
 
1. Mobilization and demobilization of equipment, labor, and construction of any 
temporary facilities that may be required; 
2. Moisture condition the area to be excavated; 
3. Excavate the soil in a systematic manner; 
4. Backfill and compact soil on all exposed North Cell slopes to the grades shown 
on the Contract Drawings. 
5. Haul soil to three specific stockpile locations as depicted on the Contract 
Drawings. All hauling of excavated material shall be confined to the site, and 
shall not take place on public roads; and 
6. Maintain haul roads and provide dust control. 
 
D. 
The CONTRACTOR shall replace in kind any existing improvements (drainage 
channels, asphalt millings roads, LFG wells & laterals, etc.) damaged during the 
course of construction as no cost to the OWNER. 
 
E. 
No additional and/or extra compensation will be given for all/or any increases to 
direct labor costs, subcontract costs, and costs of materials and equipment, which 
includes all fuels.  The only exception to this is a Fuel Cost Adjustment as described 
in subsection 1.07 of this Section.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 2 of 5 
F. 
The above description of Work is for general information only and does not limit 
the responsibility of the CONTRACTOR to accomplish the Work in strict 
accordance with the Contract Drawings and Specifications. 
 
G. 
The Work shall be performed in strict accordance with all applicable requirements 
of the City of Glendale, Maricopa County, State of Arizona, and other agencies 
having jurisdiction, and in accordance with the requirements of the General 
Conditions, Supplementary General Conditions, and Contract Drawings.  The 
CONTRACTOR shall provide a Site-specific Health and Safety Plan (HASP) for 
OWNER approval.  It shall be the CONTRACTOR’S responsibility to be fully 
apprised of Site conditions and to follow the approved HASP. 
 
1.02 
EXISTING SITE CONDITIONS 
 
A. 
The Site is currently an active landfill that receives residential and commercial 
waste on a daily basis. 
 
B. 
A limited geotechnical investigation has been conducted for this site.  Boring logs 
and laboratory analytical results from the north cell expansion borrow source are 
presented in Appendix A of these specifications.  Results of the geotechnical 
evaluation of the on-site material have been used to prepare two geologic cross-
sections which are also presented in Appendix A.  This information is available for 
review by the CONTRACTOR but does not represent a complete characterization 
of borrow material conditions.  Some “hard dig” conditions should be expected.   
 
C. 
The base topographic mapping contours shown on the Contract Drawings were 
prepared from July 1, 2022 aerial photographs.  Due to ongoing landfill operations 
and the need to excavate daily and intermediate cover, actual elevations and 
contours may vary at the time the CONTRACTOR is given notice to proceed. 
 
1.03 
CONTRACTOR’S USE OF PROPERTY 
 
A. 
The CONTRACTOR shall have unrestricted access and egress from the Site, as 
necessary, to perform the Work under this Contract.  The CONTRACTOR shall 
obtain approval for all necessary permits (dust control, stormwater, etc.) to 
accomplish the Work. 
 
B. 
The CONTRACTOR shall limit use of the Site to only the Work and storage 
requirements related to this Contract. 
 
C. 
The CONTRACTOR shall assume full responsibility for the protection and 
safekeeping of equipment and materials on or off the Site that are related to this 
Contract.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 3 of 5 
D. 
The CONTRACTOR shall be responsible for the remediation of any fuel/petroleum 
spills.  Fuel/petroleum spills shall be remediated as soon as they are noticed.   
1.04 
WORK SEQUENCE 
 
A. 
A Notice to Proceed for beginning of Work under these Contract Documents will 
be given after bid award. 
 
B. 
The CONTRACTOR shall be responsible for planning, scheduling, and otherwise 
executing the Work in a manner that meets the requirements of the Contract 
Drawings and Specifications for this project. 
 
1.05 
SEPARATE CONTRACTS 
 
 
NOT USED 
 
1.06 
BROAD SCOPE 
 
This article describes the project in general and provides an overview of the intent of the 
Work to be performed under this Contract.  The CONTRACTOR shall review the entire 
set of Contract Documents to gain a thorough understanding of the detailed project 
requirements.  The following describes the general sequence of work for this project.   
 
A. 
The CONTRACTOR shall perform the Work in accordance with the Contract 
Documents: Project Construction Drawings, Construction Specifications, 
referenced design reports, subsequent addenda, and approved shop drawings and 
submittals.  The CONTRACTOR shall provide all labor, equipment, and materials 
for temporary utilities, roads, storage, and other facilities necessary for the 
completion of all Work included as part of this contract. 
 
B. 
The CONTRACTOR shall provide all labor, equipment, and materials for clearing 
and grubbing, subgrade preparation, excavation and engineered fill, moisture 
conditioning, and placing and compacting soil on the existing North Cell slopes to 
the lines and grades shown on the Construction Drawings. 
 
C. 
The CONTRACTOR shall provide all labor, equipment, and materials for the 
construction of the Glendale Landfill west slope temporary customer access road 
consisting of excavation, moisture conditioning, placing and compacting general 
fill, and placement of road surfacing material. 
 
D. 
The CONTRACTOR shall provide all labor, equipment, and materials to excavate 
soil from the North Cell and haul to a stockpile.  Soil shall be hauled to two separate 
stockpiles as shown on the Construction Drawings.  The CONTRACTOR shall 
moisture condition the soil before excavation and shall maintain dust control on all

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 4 of 5 
haul roads and stockpile locations.   
 
E. 
Throughout construction, the CONTRACTOR shall maintain one set of full-size 
(24”x36”) red-line field drawings showing as-constructed site conditions.  These 
drawings shall remain on-site during the project for periodic review by the OWNER 
or ENGINEER.  Upon completion of construction activities, one full-size set of 
ACAD drawings with revised survey data shall be submitted to the OWNER or 
ENGINEER for incorporation into As-built Drawings to be prepared by the 
ENGINEER. 
 
1.07 
WORK HOURS 
 
A. 
Unless otherwise approved by the OWNER, construction activities and material 
deliveries to the landfill shall be limited to the hours of 6 a.m. to 5 p.m.  The 
CONTRACTOR shall submit a project bid which in no way assumes work outside 
of these hours, i.e., night work, will not be allowed on this project. 
 
1.08 
USE OF EXPLOSIVES 
 
A. The CONTRACTOR shall not employ the use of explosives on this project without 
expressed written consent from the OWNER. 
 
1.09 
SUBSTANTIAL COMPLETION 
 
A. Substantial Completion means the project work is complete.  This shall include but is 
not limited to: 
 
1. All systems in place, functional, and displayed to the OWNER or its 
representatives; 
 
2. Construction Complete; 
 
3. Materials and equipment installed; 
 
4. All systems reviewed and accepted by the OWNER. 
 
5. Draft record documents reviewed and accepted by the OWNER; 
 
6. Landscaping and site work completed; 
 
7. Final cleaning; and 
 
8. Final Acceptance (following 30 days to correct punch-list items).

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01010 - 5 of 5 
1.10 
PROJECT SCHEDULE 
 
A. The anticipated early project start date is August 2023 and the anticipated late project 
start date is April 2024. 
 
B. The CONTRACTOR shall substantially complete all work and receive final 
acceptance by June 30, 2024. 
 
1.11 
LIQUIDATED DAMAGES 
 
A. Liquidated damages shall be Five Thousand Dollars ($5,000) per day that substantial 
completion extends beyond the date determined by the contract time as adjusted. 
 
B. Liquidated damages shall be Two Thousand Five Hundred Dollars ($2,500) per day 
that final acceptance extends beyond the date determined by the contract time as 
adjusted. 
 
 
2.0 
PRODUCTS 
 
 
NOT USED 
 
 
3.0 
EXECUTION 
 
 
NOT USED 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025.  No payment will be made for meetings.  The bid price shall 
include the cost that may be incurred to attend and conduct any and all meetings 
and provide coordination. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 1 of 10 
SECTION A01015 
ABBREVIATIONS AND DEFINITIONS 
 
 
1.0 
GENERAL 
 
1.01 
ABBREVIATIONS 
 
In addition to the standard abbreviations in the MAG Specification, the following 
abbreviations have also been used: 
 
AASHTO        American Association of State Highway and Transportation Officials 
ACI           
American Concrete Institute 
ADEQ 
Arizona Department of Environmental Quality 
ADOT 
Arizona Department of Transportation  
AGA 
American Gas Association  
AIA  
American Institute of Architects 
AICHE 
American Institute of Chemical Engineers 
AISC 
American Institute of Steel Construction 
AISI 
American Iron and Steel Institute 
ANSI 
American National Standards Institute 
API 
American Petroleum Institute 
AREA 
American Railway Engineering Association 
ASCE 
American Society of Civil Engineers 
ASHRAE 
American Society of Heating, Refrigerating and Air Conditioning Engineers 
ASME 
American Society of Mechanical Engineers 
ASQC 
American Society for Quality Control 
ASTM 
American Society for Testing and Materials 
AWS 
American Welding Society 
AWWA 
American Water Works Association 
BMP 
Best Management Practices 
CBM 
Certified Ballast Manufacturers 
CFR 
Code of Federal Regulations 
CGA 
Compressed Gas Association 
COG 
City of Glendale 
CQA 
Construction Quality Assurance 
CRSI 
Concrete Reinforced Steel Institute 
CY 
Cubic Yard 
EPA 
Environmental Protection Agency 
ETL 
Electrical Testing Laboratories 
FS 
Federal Specification 
IEEE 
Institute of Electrical and Electronics Engineers

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 2 of 10 
IES 
Illuminating Engineering Society 
IPCEA 
Insulated Power Cable Engineer Association 
ISA 
Instrument Society of America 
ITL 
Independent Testing Laboratories 
LFG 
Landfill Gas 
LL 
Liquid Limit 
MAG 
Maricopa Association of Governments (Arizona) 
MIL 
U.S. Military Specification 
NEC 
National Electrical Code 
NEMA 
National Electrical Manufacturers Association 
NETA 
International Electrical Testing Association 
NFPA 
National Fire Protection Association 
NPDES 
National Pollutant Discharge Elimination System 
NSF 
National Sanitation Foundation 
OSHA 
Occupational Safety and Health Administration 
PI 
Plasticity Index 
PPl 
Plastics Pipe Institute 
SHSP 
Site Health and Safety Plan 
SMACNA 
Sheet Metal and Air Conditioning Contractor's National Association 
SRP 
Salt River Project 
SSPC 
Steel Structures Painting Council 
SWMF 
Solid Waste Management Facility 
SWPPP 
Storm Water Pollution Prevention Plan 
UBC 
Uniform Building Code 
UL 
Underwriters Laboratories 
UMC 
Uniform Mechanical Code 
UPC 
Uniform Plumbing Code 
USSPWC 
Uniform Standard Specifications for Public Works Construction 
USBR 
U.S. Bureau of Reclamation 
USCS 
Unified Soil Classification System 
WC 
Water Content 
WCRSI 
Western Concrete Reinforcing Steel Institute 
ZAV 
Zero Air Voids Curve 
 
 
1.02 
DEFINITION OF TERMS 
 
REGULATORY AGENCY - Regulatory Agency, which in this context is the Arizona Department 
of Environmental Quality (ADEQ), is responsible for compliance with the Agency’s 
regulations.  The Occupational Safety and Health Administration (OSHA) administers 
regulations for the CONTRACTOR’S Site safety requirements.  Maricopa County Air Quality 
Department (MCAQD) should be considered as an additional regulatory agency that may 
visit the site and review the work for dust emissions.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 3 of 10 
OWNER - OWNER refers to the City of Glendale, acting through its legally constituted 
officials or employees.  As OWNER of the Glendale Landfill, the City of Glendale is 
responsible for the overall compliance with various facility permits and operations 
requirements, initiation, progress, and completion of this Project, and the maintenance 
of the completed work.  The address and contact person of the OWNER shall be: 
 
City of Glendale (OWNER) 
Mr. Michael Carr 
6210 W. Myrtle Avenue, Suite 111 
Glendale, AZ  85301 
Phone:  (623) 930-2617 
Fax: (623) 915-3124 
 
 
OPERATOR - The City of Glendale is also the OWNER of the Site. 
In this document, the OWNER and the Operator are one in the same. 
 
ENGINEER - Also known as Designer Engineer and Construction Quality Assurance (CQA) 
Engineer, is an individual, a firm, or an organization who is responsible for preparation of 
the Contract Drawings, Specifications, and CQA Plan for the Project.  The OWNER’S 
Project ENGINEER shall decide on all questions which may arise as to the compliance and 
acceptability of materials furnished, work performed, and all questions as to the 
fulfillment of the technical and design issues of the Contract on the part of the 
CONTRACTOR.  The ENGINEER will make these decisions after consultation with the 
OWNER and, in some cases, the Design Engineer. 
 
The ENGINEER shall be responsible for the acceptance or rejection of work based on 
compliance with the Contract Drawings, Specifications and design intent; the ENGINEER 
will recommend suspension of work for unsafe conditions, failure by the CONTRACTOR to 
carry out provisions of the Contract, and for unsuitable weather conditions.  The 
ENGINEER shall also review the CONTRACTOR’S submittals, make recommendations, and 
review/approve the CONTRACTOR’S payment requests. 
 
The engineering consulting company Tetra Tech BAS, Inc. (Tt-BAS) was responsible for 
completion of the Design.  Tt-BAS was also responsible for development of the Contract 
Drawings and Specifications.  The address and contact name for Tt-BAS is provided below: 
 
Tetra Tech BAS, Inc. 
R. Todd Livermore, P.E., CFM 
22601 N 19th Ave, Suite 225 
Phoenix, AZ 85027 
Phone: (602) 267-0336 
Fax: (602) 267-0446

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 4 of 10 
The ENGINEER shall be responsible for all CQA observation, testing, and documentation 
related to the north cell excavation, construction of the berms including drainage 
systems, perimeter roadways, and placement and compaction of all earth material 
backfill.  The ENGINEER shall be responsible for issuing daily reports, oversight of field and 
laboratory testing, data evaluation, issuance of documentation reports, attendance at 
and recording of construction progress meetings, informing the CONTRACTOR and the 
OWNER regarding the construction compliance evaluation, and oversight of testing for 
deficiency repairs identified during construction of the berms and stockpiles. 
 
The ENGINEER will also be responsible for addressing all concerns or questions which may 
arise as to the interpretation of the Contract Drawings, grading, design elements, 
Specifications, material evaluation, and testing.  In interpreting the Contract Drawings 
and Specifications, the ENGINEER may make modifications to the Work, which shall not 
involve extra work and shall not be inconsistent with the intent of the Work.  In cases 
where modifications are necessary to comply with Site conditions, unforeseen 
circumstances, changed conditions, or in emergency situations endangering life or 
property, the ENGINEER may, upon OWNER approval, modify the Contract Drawings and 
Specifications.  In such cases the CONTRACTOR shall be compensated at the rate 
previously established by the Contract Bid. 
 
CONSTRUCTION DOCUMENTATION REPORT - The Construction Documentation Report 
(also known as Documentation Report or Certification Report) is prepared by the Designer 
certifying that Project construction has been carried out in general compliance with the 
Contract Drawings and Specifications.  The report shall be signed and stamped by a 
Registered Professional Engineer and shall contain: 
 
• 
Project description; 
• 
All CQA testing and results, including test procedures; 
• 
Deficiencies and protocol used to repair the deficiencies; 
• 
Photographic documentation; and, 
• 
As-built drawings, noting deviations from the Contract Drawings. 
 
PROJECT PLANS - The Project Plans (also known as Drawings, Project Drawings, or 
Standard Drawings) shall be either black-and-white or blue-line copies with the original 
signature and seal of a Registered Professional Engineer, prepared for the construction of 
this Project and attached to the bid documents.  The Project Plans shall also include any 
modifications, which have been approved by the ENGINEER. 
 
SPECIFICATIONS - The Specifications (also known as the Project Specifications) are the 
documents which provide detailed provisions and requirements for performance of the 
prescribed Work.  The approved Specifications for the project are intended to be

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 5 of 10 
interpreted in the context of the General Conditions, Special Provisions and 
Supplementary Conditions. 
 
1.03 
REFERENCES 
 
Reference is made to test procedures of the American Society for Testing and Materials 
(ASTM).  Other documents referred to include the Drawings, Specifications, Engineering 
Drawings, Facility Permit Documents, Safety Regulations, and U.S. EPA’s “Technical 
Guidance Document: Quality Assurance and Quality Control for Waste Containment 
Facilities.” 
 
The pertinent ASTM referenced test standards are provided below: 
 
a) 
ASTM D 422 - Particle Size Analyses for Coarse Fraction of Soil Samples. 
b) 
ASTM D 698 (Standard Proctor)(Standard Effort - 12,400 foot-pound/foot) Test 
Methods for Moisture-Density Relations of Soils and Soil-Aggregate Mixture. 
c) 
ASTM D 1140 - Amount of Materials in Soils Finer than the No. 200 Sieve. 
d) 
ASTM D 1556 - Density and Unit Weight of Soil in Place by Sand-Cone Method. 
e) 
ASTM D 1557 (Modified Proctor) Test Methods for Moisture-Density Relations of Soils 
and Soil-Aggregate Mixture Using a 10-lb (4.54 kg) Rammer and 30-inch (457 mm) 
Drop. 
f) 
ASTM D 2216 - Laboratory Determination of Water Content of Soil and Rock. 
g) 
ASTM D 3087 - Classification of Soils for Engineering Purposes. 
h) 
ASTM D 3088 - Descriptions and Identification of Soils. 
i) 
ASTM D 2922 - Density of Soil and Aggregate In Place by Nuclear Methods (Shallow 
Depth). 
j) 
ASTM D 2937 - Density of Soil In Place by Drive - Cylinder Method. 
k) 
ASTM D 3017 - Moisture Content of Soil and Rock In Place by Nuclear Method (Shallow 
Depth). 
l) 
ASTM D 4220 - Preserving and Transporting Soil Samples. 
m) 
ASTM D 4330 - Liquid Limit, Plastic Limit, and Plasticity Index of Soils. 
n) 
ASTM D 4643 - Determination of Water Content of Soil by Microwave Method. 
o) 
ASTM D 4944 - Determination of Water Content of Soil by Calcium Carbide Gas 
Pressure Tester Method. 
p) 
ASTM D 5080 - Rapid Determination of Percent Compaction. 
q) 
ASTM D 5084 - Measurement of Hydraulic Conductivity of Saturated Porous Materials 
Using a Flexible Wall Perimeter. 
r) 
ASTM D 4546 - One-Dimensional Swell Potential of Remolded Soil Materials.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 6 of 10 
1.04 
DEFINITIONS OF TECHNICAL TERMINOLOGY 
 
Appurtenances: 
Detailed items such as drainage facilities, and items that are 
necessary and related to the proper functioning of the 
Landfill final cover system. 
Atterberg Limits: 
The liquid limit and plastic limit of soil. 
Caliche: 
Gravel, sand, or desert debris cemented by porous calcium 
carbonate; also calcium carbonate itself. 
Clay: 
Soil material with an equivalent mean grain size smaller 
than 0.002 mm.  Clay soils are also defined as plastic fines. 
Clay Clod: 
A chunk of cohesive soil or clay soils (also referred to as 
“clod”). 
Cohesive Soils: 
Soil material, which has a high plasticity index, is sticky, and 
tends to form clods when dry. 
Compaction Curve: 
Plot of dry unit weight versus molding water content, based 
on the data obtained from moisture-density relationship 
tests. 
Dry Density: 
The dry weight of soil material per total volume, including 
air space, also known as dry density.  The dry weight is 
usually measured after drying in an oven at 212 degrees F 
(°F) for 30 hours or until a constant weight is achieved. 
Electrical 
Conductivity: 
Electrical conductivity, abbreviated as EC, of soil is defined 
as the ease at which electrical current flows through soil 
mass.  According to Ohm’s law, EC equals the inverse of the 
electrical resistivity.  In soils, the resistivity of the individual 
soil grains are high and therefore, if there is to be a passage 
of current through a soil mass it will be exclusively through 
electrolytic action due to the presence of dissolved salts 
and solids within the pore spaces of the soil particles.  The 
EC of soil is indicative of the soil’s acidity or alkalinity. 
Geosynthetics: 
Generic term for all geosynthetic materials such as 
geotextiles, 
geomembranes, 
geonets, 
geogrids, 
geosynthetic clay liners, and geocomposites. 
Geotextile: 
A permeable geosynthetic material fabricated with only 
textiles, which may be woven, non-woven, or knitted. 
Gravel: 
Soil material, which is coarser than 4.76 mm in least 
dimension, or retained on a No. 4 sieve.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 7 of 10 
Hydraulic 
Conductivity: 
Also known as permeability, refers to the capacity of a 
material to discharge certain fluids through a material.  
Discharge of fluid through a unit cross-sectional area of a 
porous media under a unit hydraulic gradient, and standard 
temperature of 68 degrees F defines this property. 
Lift: 
Discrete layer of soil (usually 6 to 10 inches thick) placed 
and compacted for construction of engineered fill. 
Liquid Limit: 
The minimum water content of soil at which the soil 
behaves like a viscous liquid.  It is the arbitrary limit 
between the liquid and plastic state of soil. 
NICET: 
An acronym for  the National Institute for Certification in 
Engineering Technologies, an organization that administers 
examinations 
for 
bituminous 
material, 
concrete, 
geosynthetics, and earthen materials for construction. 
Outliers: 
Data points which do not fit into the specified or required 
maxima or minima values. 
Permittivity: 
For a geotextile, the volumetric flow rate of water per unit 
cross-sectional area, per unit head, under laminar flow 
conditions, in the normal direction through the fabric. 
pH of Soil: 
The pH of a soil sample measures the hydrogen-ion 
concentration and is indicative of the soil’s acidity or 
alkalinity. 
Plasticity or Plastic 
Index (PI): 
The range of moisture content of soil in which the soil 
behaves like a plastic solid.  The numerical value is the 
difference between the liquid limit and plastic limits. 
Plastic Limit (PL): 
The minimum water content, above which a soil material 
behaves like a plastic solid. 
Polymer: 
A macromolecular material formed by the chemical 
combination of monomers having either the same or 
different chemical composition.  Plastics, rubbers, and 
textile fibers are all high-molecular-weight polymers. 
 
Polyolefin: 
A family of polymeric materials that includes polypropylene 
and polyethylene, the former being very common in 
geotextiles, the latter in geomembranes.  Many variations 
of each exist.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 8 of 10 
Seam Strength: 
Strength of a seam of geotextile material measured either 
in shear or peel modes.  Strength of seams are reported 
either in absolute units (pounds per inch of width), or as a 
percent of the strength of the geotextiles. 
Unit Weight: 
Weight of soil samples per total volume including air space.  
May include weight of water present within the pore 
spaces. 
 
1.05 
DELINEATION OF RESPONSIBILITES 
 
 
A. 
The following are clarifications of the responsibilities and definitions of job titles 
to be adhered to during the period of time required to complete construction of 
the Project. 
 
B. 
The OWNER (also Operator) is responsible for compliance with all facility permit 
requirements, initiation, progress, and completion of this Project and the 
maintenance of the completed work. 
 
C. 
The OWNER’s Project Engineer (ENGINEER) will decide on all questions which may 
arise as to the compliance and acceptability of materials furnished, work 
performed, and all questions as to the fulfillment of technical and design issues of 
the contract on the part of the CONTRACTOR.  The ENGINEER will make these 
decisions after consultation with the OWNER. 
 
 
The ENGINEER shall be responsible for the acceptance or rejection of work based 
on compliance with the Contract Drawings, Specifications, and design intent; the 
ENGINEER may recommend the suspension of work for unsafe conditions, failure 
to carry out provisions of the Contract by the CONTRACTOR, and for unsuitable 
weather conditions.  The ENGINEER shall also review the CONTRACTOR’S 
submittals, make recommendations, and review/approve the CONTRACTOR’S 
payment requests. 
 
D. 
The ENGINEER shall be responsible for all CQA observation, testing, and 
documentation related to the north cell excavation, construction of the berms 
including drainage systems, perimeter roadways, and placement and compaction 
of all earth material backfill.  The ENGINEER shall be responsible for issuing daily 
reports, oversight of field and laboratory testing, data evaluation, issuance of 
documentation reports, attendance at and recording of construction progress 
meetings, informing the CONTRACTOR and the OWNER regarding the 
construction compliance evaluation, and oversight of testing for deficiency repairs 
identified during construction of the berms and stockpiles.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 9 of 10 
The ENGINEER will also be responsible for addressing all concerns or questions 
which may arise as to the interpretation of the Contract Drawings, grading, design 
elements, specifications, material evaluation, and testing.  In interpreting the 
Contract Drawings and Specifications, the ENGINEER may make modifications to 
the Work, which shall not involve extra work and shall not be inconsistent with 
the intent of the Work.  In cases where modifications are necessary to comply with 
Site conditions, unforeseen circumstances, changed conditions, or in emergency 
situations endangering life or property, the ENGINEER may, upon OWNER 
approval, modify the Contract Drawings and Specifications.  In such cases the 
CONTRACTOR shall be compensated at the rate previously established by the 
Contract Bid. 
 
The ENGINEER’S representative shall issue daily reports containing field 
monitoring such as: 
 
• 
Visual observations; 
• 
CQA test results; 
• 
Deficiencies encountered and retesting results; 
• 
Summary of significant event details; 
• 
Weather conditions; and 
• 
Other field observations deemed necessary for completion of the Project. 
 
E. 
The CONTRACTOR is responsible for quality control (QC) on all work activities 
contained in the Contract Documents.  The CONTRACTOR shall complete all work 
in accordance with the Project Plans, Specifications, CQA Plan, and Project 
Schedule (see Section A01010 – Project Schedule). 
 
The CONTRACTOR has overall control over construction operations; including level 
of effort and site safety.  The CONTRACTOR is also responsible for informing the 
OWNER and the ENGINEER of scheduling and occurrence of all construction 
activities.  The CONTRACTOR is responsible for the work performed by 
Subcontractor(s), if any.  This includes requiring Subcontractor(s) to comply with 
the HASP. 
 
The CONTRACTOR is responsible for the excavation, clearing, and construction of 
engineered fills and soil stockpiles, including excavation, processing and moisture 
conditioning, transportation of soil from the excavation to the stockpile locations, 
drainage facilities, and perimeter roadways, as contained in the Contract 
Documents, or as deemed necessary and in accordance with the Specifications.  
The CONTRACTOR is also responsible for coordinating his/her work with the 
ENGINEER, OWNER, and other related parties.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01015 - 10 of 10 
1.06 
QUALIFICATIONS AND TRAINING 
 
NOT USED 
 
 
2.0 
PRODUCTS 
NOT USED 
 
 
3.0 
EXECUTION 
 
NOT USED 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 1 of 9 
SECTION A01025 
MEASUREMENT AND PAYMENT 
1.0  
GENERAL 
This section includes the items of work and the basis of payment for these items.  The 
CONTRACTOR shall bid items 1 through 7 below separately and provide a total sum for all 
work items.  The CONTRACTOR is responsible for supplying all materials and labor necessary 
for the complete construction and installation of all work as described in these specifications and 
as shown on the Construction Drawings.  Payment for each work item will be made on either a 
unit price or lump sum basis, and only after that portion of the project has been completed. 
Arrangements for construction water are the CONTRACTOR’s responsibility.  The 
CONTRACTOR is specifically reminded of the need to obtain the necessary environmental 
permits or file the necessary environmental notices.  Copies of these permits and notices must 
be provided to the City’s Project Manager prior to starting the permitted activity.  This provision 
does not constitute an assumption by the OWNER of an obligation of any kind for violation of 
said permit or notice requirements. 
Required construction water (see Section A01500 – 3.14 Construction Water) and fine grading 
of fill shall be considered incidental to the Work. 
1.01 
CONTRACT PAY ITEMS 
A. 
Proposal Item 1 - Mobilization and Demobilization 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS). The Work required for this item 
will be measured on the basis of satisfactory evidence of mobilization of 
sufficient labor, equipment and material to adequately advance the Work. 
2. 
Payment 
Basis of Payment: The Lump Sum Price for Mobilization and 
Demobilization shall be payment in full for, but not limited to, all labor, 
equipment, material and other incidentals to the site, as well as 
CONTRACTOR provided utilities and ongoing related expenses, 
considered normal for administration of the Work.  Twenty-five (25) 
percent of the Lump Sum price bid will be paid with the first payment 
request following satisfactory evidence of mobilization of sufficient labor, 
equipment and material to adequately progress the Work of this contract.  
Twenty-five (25) percent of the Lump Sum price bid will be paid with the 
payment request subsequent to the payment request in which the initial

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 2 of 9 
payment for this item is made. Fifty (50) percent of the Lump Sum price 
bid will be paid with the Final Payment request.  The price bid in the 
proposal for this item shall not exceed three (3) percent of the original 
total bid or contract amount. 
B. 
Proposal Item 2 – Project Survey 
 
 
 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS). The Work required for this item 
will be measured on a lump sum basis. 
 
 
2. 
Payment 
Basis of Payment: The Lump Sum Price for Survey.  The CONTRACTOR 
shall employ a licensed Arizona surveyor to perform the layout and as-
builts of the project.  Survey’s documenting the amount of soil excavated 
shall be submitted to the OWNER and ENGINEER on a monthly basis.  
Full-size as-built drawings stamped by a licensed Arizona surveyor shall 
be provided by the CONTRACTOR.  As-built data shall be provided in an 
AutoCAD compatible electronic format.  This item shall be paid monthly 
based on the percentage of work completed. 
C. 
Proposal Item 3 – AZPDES/SWPPP/Dust Control Permits and Temporary 
Facilities and Controls 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS). 
2. 
Payment 
Basis of Payment: This item shall be paid monthly based on the percentage 
of work completed for obtaining and executing the provisions of 
AZPDES/SWPPP and Dust Control permit from Maricopa County for the 
construction activities relating to this Work. 
A completed (typed) NOI shall be submitted to the ENGINEER at the 
preconstruction conference.  See the Section AZPDES Compliance in the 
Information for Bidders. 
A monthly Stormwater Pollution Prevention Plan (SWPPP) Report must 
be submitted with each Progress Payment.  Failure to submit this report 
will cause rejection of the payment request. 
A completed (typed) Notice of Termination (NOT) shall be submitted to 
the ENGINEER at final acceptance.  See the Section AZPDES 
Compliance in the Information for Bidders.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 3 of 9 
D. 
Proposal Item 4 – Traffic Control 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS). 
2. 
Payment 
Basis of Payment: This item shall be paid monthly based on the percentage 
of work completed for obtaining and executing traffic control. 
E. 
Proposal Item 5 – Excavate, Haul, and Stockpile to South Cell 
Note: The CONTRACTOR shall place excavated soil stockpiles in the following 
locations at the direction of the OWNER: 
1. 
Measurement 
Basis of Measurement: Cubic Yard (CY). The CONTRACTOR shall 
provide a base line survey for the OWNER’S review and acceptance prior 
to beginning excavation.  Measurement of excavation will be made by 
comparing pre-construction base line topography with the monthly 
surveyed topography.  Survey will establish existing grades at a maximum 
100-foot grid and establish major grade breaks.  Calculations will be made 
by AutoCAD comparison between base line topography and surveyor 
provided monthly topography.  Required construction water and fine 
grading of fill shall be considered incidental to this item.  No load counts 
will be used for payment.  The CONTRACTOR shall provide all survey 
data used for volume calculations to the OWNER and ENGINEER. 
2. 
Payment 
Payment will be made for material excavation on a cubic yard basis.  The 
cost shall include moisture conditioning, material processing and 
segregation, excavation, screening, hauling, grading/shaping, compaction, 
vehicles, labor, and all other items necessary to complete the Work.  The 
overall quantity to be excavated will be based on the difference between 
the current north area topography (base line) and the final elevations 
shown on the Contract Drawings.  The CONTRACTOR must 
independently verify and agree to the cubic yardage quantity to be 
excavated prior to bid submittal.  The cost per cubic yard excavated will 
be the sole means of payment, including moisture conditioning, material 
processing and segregation, excavation, hauling, grading/shaping, 
compaction, vehicles, labor, and all other items necessary to complete the 
Work.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 4 of 9 
F. 
Proposal Item 6 – Excavate, Haul, and Stockpile to MRF 
Note: The CONTRACTOR shall place excavated soil stockpiles in the 
following locations at the direction of the OWNER: 
2. 
Measurement 
Basis of Measurement: Cubic Yard (CY). The CONTRACTOR shall 
provide a base line survey for the OWNER’S review and acceptance prior 
to beginning excavation.  Measurement of excavation will be made by 
comparing pre-construction base line topography with the monthly 
surveyed topography.  Survey will establish existing grades at a maximum 
100-foot grid and establish major grade breaks.  Calculations will be made 
by AutoCAD comparison between base line topography and surveyor 
provided monthly topography.  Required construction water and fine 
grading of fill shall be considered incidental to this item.  No load counts 
will be used for payment.  The CONTRACTOR shall provide all survey 
data used for volume calculations to the OWNER and ENGINEER. 
2. 
Payment 
Payment will be made for material excavation on a cubic yard basis.  The 
cost shall include moisture conditioning, material processing and 
segregation, excavation, screening, hauling, grading/shaping, compaction, 
vehicles, labor, and all other items necessary to complete the Work.  The 
overall quantity to be excavated will be based on the difference between 
the current north area topography (base line) and the final elevations 
shown on the Contract Drawings.  The CONTRACTOR must 
independently verify and agree to the cubic yardage quantity to be 
excavated prior to bid submittal.  The cost per cubic yard excavated will 
be the sole means of payment, including moisture conditioning, material 
processing and segregation, excavation, hauling, grading/shaping, 
compaction, vehicles, labor, and all other items necessary to complete the 
Work. 
G. 
Proposal Item 7 – Engineered Fill (Excavate and Place) 
1. 
Measurement 
Basis of Measurement: In-place Cubic Yard (CY). Measurement of in-
place engineered fill will be made by comparing base line topography with 
post-construction topography.  Surveys will establish existing grades at a 
maximum 100-foot grid and establish major grade breaks.  Calculations 
will be made by AutoCAD comparison between the base line topography 
and surveyor provided topography when in-place engineered fill 
construction is complete.  Required construction water and fine grading of 
in-place engineered fill shall be considered incidental to this item.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 5 of 9 
2. 
Payment 
Basis of Payment: shall be payment in full for, but not limited to, all costs 
to excavate, screen and/or process, condition, control dust, load, haul, 
place, moisture condition, compact, fine grade and maintain as shown on 
the Drawings and in accordance with the Specifications. 
H. 
Proposal Item 8 – Fuel Cost Adjustment (Owners Contingency) 
 
 
1. 
Measurement 
Basis of Measurement: Lump Sum (LS).  Refer to Subsection 1.07 of this 
Section. 
 
 
2. 
Payment 
Basis of Payment: This item shall be payment in full for, but not limited 
to provide a contingency fund for the OWNER.  Depending upon the 
outcome of the Project, these funds may not be expended.  Refer to 
Subsection 1.07 of this Section. 
1.02 
LOAD COUNTS AND DELIVERY TICKETS 
A. 
Load counts shall not be used as an acceptable means of measuring any and/or all 
material fills or excavation quantities for payment. 
B. 
Any delivery tickets, concrete tickets, scale/weight tickets and invoices shall not 
be used for an acceptable means of measuring any and/or all quantities for 
payment purposes. 
1.03 
NON PAY ITEMS 
A. 
No separate payment will be made for items not specifically set forth in the bid 
proposal.  Include costs of such items in prices named in the bid proposal for 
identified items of Work.  Items of Work described in the Contract Documents, 
but not listed in the schedule of Work items of the bid form are, in general, 
applicable to more than one listed Work item.  No separate Work item is provided.  
The CONTRACTOR shall include costs of Work not listed but necessary to 
complete the project per the Contract Documents in the listed Work items of the 
bid form.  The CONTRACTOR shall not use bid proposal item “Owner 
Allowance for Extra Work” without prior written approval of the ENGINEER. 
1.04 
TOTAL COST 
A. 
Bids for Work are intended to establish a total cost for the Work in its entirety.  
Should the CONTRACTOR feel that the cost for the Work has not been 
established by specific items in the bid form, the CONTRACTOR shall bring this 
to the attention of the ENGINEER or OWNER via email no later than 10 days

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 6 of 9 
prior to bid opening so that addendum and/or clarification as to whether such 
work is to be considered strictly as incidental or is to be included in a certain or 
new bid item may be issued and that his/her bid proposal reflects the total cost for 
completing the Work in its entirety. 
1.05 
QUANTITY OVERRUNS 
A. 
No payment will be made for quantity overruns unless the Work is expressly 
required by the Contract Documents and authorized in writing by the OWNER or 
ENGINEER prior to the performance of the Work. 
1.06 
PAYMENT 
A. 
The CONTRACTOR shall be bound by the pricing contained on and submitted 
with the project bid sheet. 
B. 
No extra monetary compensation or additional time will be authorized for claims 
that conditions differ from those anticipated.  It is the CONTRACTOR’s 
responsibility to make his own determination as to the actual existing conditions. 
C. 
No extra monetary compensations or additional time will be authorized for the 
removal, handling, or disposal of construction debris or waste/refuse.  Cost for 
this work shall be included in the bid price. 
D. 
No additional and/or extra compensation will be given for all and/any increases 
to direct labor costs, subcontract costs, and costs of materials and equipment.  The 
only exception to this is a Fuel Cost Adjustment as described in subsection 1.07 
of this Section. 
1.07 
FUEL COST ADJUSTMENT 
A. 
GENERAL 
a. The ENGINEER will adjust monthly progress payments up or down as 
appropriate for cost fluctuations in diesel fuel as determined in accordance 
with these special provisions. 
b. A fuel cost adjustment will be made when fluctuations in the price of 
diesel fuel, in excess of 15 percent, occur throughout this contract.  The 
ENGINEER will not provide such adjustments for fluctuations in the price 
of diesel fuel of 15 percent or less. 
c. No adjustments will be made for fluctuations in the price of fuels other 
than diesel.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 7 of 9 
B. 
MEASUREMENT 
a. The base index price of fuel will be determined by the ENGINEER from 
the selling prices of diesel fuel published by OPIS (Oil Price Information 
Service).  The base index price to be used will be the price for Diesel fuel 
No. 2, Ultra Low Sulfur, PAD 5, City of Phoenix Rack.  The reported 
average value for the Phoenix area will be used. 
b. The base index price for each month will be the arithmetic average of the 
selling price for diesel fuel, as specified above, shown in the last four 
reports received prior to the last Wednesday of the month. 
c. This price will be effective as of the last Wednesday of each month.  The 
current price may be seen at the following website: 
https://www.azdot.gov/business/ContractsandSpecifications/PriceAdjust
mentforBituminousMaterialandDieselFuel 
d. This price will be deemed to be the "initial cost" (IC) for diesel fuel on 
projects for which bids are opened during the following month. 
e. The current index price for diesel fuel in subsequent months will be the 
base index price, determined as specified above, for the current month.  
For example; an adjustment for diesel fuel used in May, if applicable, will 
be based on the “current price” (CP) for May as posted on the last 
Wednesday of May.  The amount of adjustment per gallon will be the net 
difference between the "initial cost," adjusted by 15 percent, and the 
current index price.  The monthly adjustment will be determined by the 
ENGINEER and included in the payment estimate as a fuel adjustment.  
For fluctuations in excess of 15 percent, fuel cost adjustments will only be 
made for current price index increases greater than 1.15 times the "initial 
cost" or for decreases less than 0.85 times the "initial cost."  No calculation 
will be made for fluctuations in the current index price of 15 percent or 
less when compared to the "initial cost." 
f. If the Fuel Cost Adjustment applies according to this Section A - 
GENERAL, then the number of gallons of diesel fuel used per month will 
be considered to equal 7.5 percent of the dollar amount of work reported 
by the CONTRACTOR for each month.  Such dollar amount will not 
include revenue accrued in the previous month for fuel price adjustments. 
g. A monthly adjustment, if applicable, will be made on this quantity, as 
shown below: 
 
S =
0.075(Q)
IC
x (CP −AC)

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 8 of 9 
 
 
Where; 
S = Monetary amount of the adjustment (plus or minus) in dollars 
 
 
 
 
Q = Dollar amount of work completed for the month 
 
 
 
 
CP = Current index price in dollars per gallon 
 
 
 
 
AC = Adjusted "initial cost" (1.15 or 0.85 times IC) in dollars per gallon 
 
 
 
 
IC = "Initial cost" as determined above, dollars per gallon 
 
 
 
 
 
As of today’s date, the following values have been determined: 
 
• IC for October 2022 = $3.69/gal 
• AC is calculated to be $3.69*1.15 = $4.24 or $3.69*0.85 = 
$3.14/gal 
 
h. If adjustments are made in the contract quantities, the CONTRACTOR 
shall accept any fuel adjustment as full compensation for increases or 
decreases in the price of fuel regardless of the amounts of overrun or 
underrun. 
i. The value calculated above (plus or minus) will be adjusted to include 
sales tax and other taxes as applicable. 
j. No additional compensation will be made for any additional charges, 
costs, expenses, etc., which the CONTRACTOR may have incurred since 
the time of bidding and which may be the result of any fluctuation in the 
base index price of diesel fuel. 
k. No adjustments will be made for work performed after Substantial 
Completion, as defined in Section A01010 Subsection 1.09, has been 
achieved. 
C. 
PAYMENT 
a. Price adjustments will be shown on the monthly progress estimate, but 
will not be included in the total cost of work for determination of 
progress or for extension of contract time. 
1.08 
CONTRACT CONTINGENCY 
A. 
Contract contingency items are provided for the purpose of encumbering funds.  
No work shall be conducted under contract contingency without prior approval 
by the ENGINEER.  The amount, if any, of the contingency item is determined 
by the ENGINEER and is not subject to individual bid pricing.  All bidders shall 
incorporate the amount pre-entered in the bid proposal and shall reflect the same 
in the total amount bid for this project.  This amount may or may not be used.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01025 - 9 of 9 
2.0  
PRODUCTS 
NOT USED 
 
3.0  
EXECUTION 
NOT USED 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01030 - 1 of 4 
SECTION A01030 
SPECIAL INSTRUCTIONS 
 
 
1.0  
GENERAL 
 
1.01 
REQUIREMENTS INCLUDED 
 
These instructions are site specific for the Glendale Landfill (GLF) site.  The 
CONTRACTOR shall comply with, but is not limited to, all Special Instructions 
listed in this Section. 
 
1.02 
SMOKING POLICY 
 
Smoking is not allowed at the GLF except in designated areas.  The smoking 
prohibition will be strictly enforced on this project due to the explosive nature of 
landfill gas. 
 
1.03 
SPECIAL CLEAN-UP 
 
Any trash generated on the project site by the CONTRACTOR, or his employees, 
will be cleaned up daily by the CONTRACTOR for disposal onsite (active face of 
the landfill).  Mud and dirt tracked off-site by the CONTRACTOR, his equipment, 
or his employees will be cleaned up daily by the CONTRACTOR.  Facility access 
roads and any other off-site roads will be scraped clean daily and washed down at 
least once per week. 
 
1.04 
LIMITING PUBLIC ACCESS 
 
All necessary precautions including barricades and/or traffic cones will be used to 
prevent the public from entering the working area.  The CONTRACTOR is 
reminded that the landfill is a hazardous area containing heavy equipment and 
explosive gases.   
 
1.05 
BIOHAZARDS 
 
The CONTRACTOR may encounter waste during the course of construction.  
Waste may contain biohazards such as medical waste or dead animals.  The 
CONTRACTOR’s Health and Safety Plan shall address the potential for contact 
with biohazards and the specific measures to be taken to protect the 
CONTRACTOR’s workers, facility staff, and the public.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01030 - 2 of 4 
1.06 
MATERIALS DELIVERY 
 
The CONTRACTOR is to have all materials delivered to his work site and/or 
staging area.  The OWNER or ENGINEER will not accept delivery of materials. 
 
1.07 
EMERGENCIES 
 
The CONTRACTOR shall provide the ENGINEER with the phone numbers of at 
least two individuals who may be contacted in an emergency on a 24-hour, 7-day 
per week basis, including holidays.  To prepare for emergencies, the 
CONTRACTOR shall ensure that his employees know the location of appropriate 
fire and first aid equipment and emergency phone numbers.  In the event of an 
emergency, such as damage or rupture of an existing gas pipeline, the 
CONTRACTOR shall immediately notify the ENGINEER and/or the Operator.  
Should such an emergency occur after hours, the CONTRACTOR shall notify the 
ENGINEER.  This is in addition to the CONTRACTOR taking appropriate 
immediate emergency response to correct the problem. 
 
1.08 
GENERAL SAFETY 
 
The CONTRACTOR shall be responsible for maintaining safety on the project site 
in accordance with the provisions of the contract and including OSHA and NFPA 
regulations.  In addition, the CONTRACTOR shall supply all necessary safety 
equipment for his employees and any site visitors.  Tool box safety meetings shall 
be performed a minimum of once per week for all site personnel. 
 
1.09 
SITE FAMILIARIZATION 
 
A. Familiarization 
 
1) Prior to implementing work, the CONTRACTOR shall become thoroughly 
familiar with the site, the site conditions, and all portions of the work falling 
within these Project Specifications and Project Drawings. 
 
B. Inspection 
 
1) If the CONTRACTOR has any concerns regarding the site, the 
CONTRACTOR shall notify the OWNER and ENGINEER in writing 
within 48 hours of the site visit.  Failure to notify the OWNER or the 
ENGINEER prior to installation of items will be construed as 
CONTRACTOR’s acceptance. 
 
2) The CONTRACTOR shall verify as-built conditions prior to placement 
and/or excavation of any material.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01030 - 3 of 4 
1.09 
STORM DAMAGE 
 
The CONTRACTOR shall be responsible for the repair of any storm damage to the 
Work prior to the Final Acceptance by the ENGINEER and OWNER.  Storm 
damage of engineered fill slopes and stockpiles will also be responsibility of the 
CONTRACTOR.  Prompt repair of any storm damage shall be the responsibility of 
the CONTRACTOR, at no cost to the OWNER. 
 
1.10 
EQUIPMENT FUELING AND MAINTENANCE 
 
The CONTRACTOR shall fuel and maintain equipment in designated areas of the 
site as directed by the ENGINEER.  The CONTRACTOR shall furnish and use drip 
pans for the fueling of vehicles or equipment.  Any fuel spills will be immediately 
cleaned up, and the contaminated soil removed from the site by the 
CONTRACTOR at the CONTRACTOR’s expense.  The CONTRACTOR will be 
allowed to place a temporary double-wall fuel tank on site, if fuel spill precautions, 
such as automatic fuel nozzle shutoff and visqueen barrier, are in place. 
 
1.11 
PROJECT DOCUMENT CHANGE CONTROL 
 
A structured process for controlling project Plan and Specification changes will be 
implemented by the ENGINEER.  “Controlled” copies of the Plans and 
Specifications will be issued to the CONTRACTOR and OWNER.  These 
“controlled” copies will be updated with any project changes, revisions, or addenda.  
The ENGINEER will not be responsible for providing changes, revisions, or 
addenda to the Plans and Specifications, other than these “controlled” copies. 
 
1.12 
EXISTING ROADS 
 
The CONTRACTOR will return all existing roads to their original condition after 
completion of the Work.  The CONTRACTOR may be required to obtain and place 
asphalt millings, if the existing roads originally had a layer of millings.  For the 
purpose of replacing asphalt millings roads to their original condition the thickness 
of the original millings layer is assumed to be 6”.  The OWNER will not 
compensate the CONTRACTOR for the cost of returning the existing asphalt 
millings roads to their original condition.   
 
1.13 
HEALTH AND SAFETY PLAN 
 
Prior to proceeding with the construction activities, the CONTRACTOR shall 
submit (for the ENGINEER's approval), a site-specific Health & Safety Plan.  The 
CONTRACTOR shall also allow a period of two weeks for the ENGINEER's 
review time.  During the entire construction activity, the CONTRACTOR shall 
maintain at least one readily available copy of the Health & Safety Plan at the site 
at all times.  Site safety is the responsibility of the CONTRACTOR.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01030 - 4 of 4 
2.0 
MEASUREMENT AND PAYMENT 
 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025.  
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01050 - 1 of 3 
SECTION A01050 
SURVEYING 
 
 
1.0 
GENERAL 
 
1.01 
COORDINATION 
 
A. 
Work associated with this section includes labor, materials and equipment 
necessary to perform new construction layout and grade staking. 
 
B. 
This section also covers required surveying for the development and maintenance 
of redline and ACAD as-built drawings. 
 
1.02 
RELATED WORK SPECIFIED ELSEWHERE 
 
A. 
All Work covered by the Contract Documents. 
 
1.03 
QUALITY CONTROL 
 
 
A. 
The CONTRACTOR shall use adequate numbers of skilled workers who are 
thoroughly trained and experienced in the necessary skills and who are completely 
familiar with the specified requirements and methods needed for proper 
performance of the Work described in these Specifications.  The CONTRACTOR shall 
utilize a State of Arizona Registered Surveyor. 
 
1.04 
SUBMITTALS 
 
 
A. 
The CONTRACTOR shall submit the following: 
 
1. 
Qualifications of persons proposed to be engaged for surveying services; and 
 
2. 
Certification, signed by the CONTRACTOR’S retained Registered Land Surveyor 
that elevations and locations are in conformance or non-conformance with 
requirements of the Contract. 
 
 
2.0 
PRODUCTS 
 
2.01 
EQUIPMENT AND MATERIALS 
 
 
A. 
Equipment and materials necessary for proper construction surveying will be at the 
CONTRACTOR’S discretion.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01050 - 2 of 3 
3.0 
EXECUTION 
 
3.01 
PROCEDURES 
 
A. 
Basic horizontal and vertical controls are shown on the Contract Drawings.  Three 
survey control points have been shown on the Contract Drawings.  The 
CONTRACTOR shall complete layout of all Work and shall be responsible for all 
requirements necessary for the execution of any Work in accordance with the 
locations, lines, and grades specified or shown on the Contract Drawings, subject 
to such modifications as the ENGINEER may require as work progresses.  
Construction staking shall be done in accordance with industry practice. 
 
 
B. 
The CONTRACTOR shall complete layout of the work and shall be responsible for all 
measurements that may be required for the preparation of the project as-built 
drawings to the location and limit marks prescribed in the specifications or on the 
Contract Drawings.  These locations and limits are subject to such modifications as 
the ENGINEER may require to meet changed conditions or as a result of necessary 
modifications to the Contract Work. 
 
 
C. 
The CONTRACTOR shall furnish, at his own expense, such stakes, templates, 
platforms, equipment, tools and material, and all labor as may be required in laying 
out any part of the work from the survey control.  It shall be the responsibility of the 
CONTRACTOR to maintain and preserve all stakes and other marks established until 
work is complete and record information is satisfactory to the ENGINEER. 
 
 
D. 
The ENGINEER may require Work be suspended at any time when location and limit 
marks established by the CONTRACTOR are not reasonably adequate to permit 
checking of the Work. 
 
 
E. 
The CONTRACTOR shall locate and protect control points before starting work on 
the site. 
 
 
F. 
The CONTRACTOR shall preserve permanent reference points during progress of the 
Work. 
 
 
G. 
The CONTRACTOR shall not change or relocate reference points for the Work 
without specific prior approval from the ENGINEER. 
 
 
H. 
The CONTRACTOR shall promptly advise the ENGINEER when a reference point is 
lost or destroyed or requires relocation because of other changes in the Work. 
 
 
 
1. 
The CONTRACTOR shall, upon direction of the ENGINEER, require the Survey 
Party Chief to replace reference stakes or markers.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01050 - 3 of 3 
 
 
2. 
The CONTRACTOR shall locate replacement stakes or markers according to 
the original survey control. 
 
 
I. 
The CONTRACTOR shall provide to the ENGINEER such surveys and volume 
computations as are necessary to determine the quantities of Work performed or 
placed during each month for which a progress payment is to be made.  All original 
field notes, volume computations and other records for the purpose of layout and 
progress surveys shall be furnished promptly to the ENGINEER at the Site of the 
Work.  A copy of the original notes, computations and records furnished to the 
ENGINEER shall be retained by the CONTRACTOR. 
 
 
J. 
The CONTRACTOR shall provide survey control during the installation of drainage 
structures/runoff collection channels within ±0.1 feet. 
 
 
K. 
The CONTRACTOR shall provide survey control before and after placement for 
structural fill within ±0.1 feet. 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in Section 
A01025. 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 1 of 5 
SECTION A01052 
LAYOUT OF WORK AND SURVEYS 
 
 
1.0 
GENERAL 
 
1.01 
SUMMARY 
 
A. 
Section includes requirements for survey work to be provided by the 
CONTRACTOR for the following: 
 
B. 
Setting offset stakes, slope stakes, and grade stakes for field layout of features for 
performance of the Work. 
 
C. 
Surveys for measurement of quantities for payment. 
 
D. 
Record Drawings. 
 
1.02 
DESCRIPTION 
 
 
A. 
Reference Points.  The reference points provided by the OWNER include 
monuments and elevation bench marks in the vicinity of the Project.  If displaced 
during the project, replacement of these reference points will be at the expense of the 
CONTRACTOR.  All surveys for record drawings shall tie to a minimum of three of 
these reference points and shall use the site coordinate system previously established 
by the OWNER’s survey and utilized in the Design Plan Drawings. 
 
 
B. 
The OWNER reserves the right to perform any desired checking and correction of 
the CONTRACTOR’s layout work relative to OWNER's surveys but this does not 
relieve the CONTRACTOR of the responsibility for adequate performance of their 
Work. 
 
 
 
C. 
Equipment and Personnel.  Provide instruments and other survey equipment that 
are accurate, suitable for the surveys required in accordance with recognized 
professional standards, and in proper condition and adjustment at all times.  Perform 
surveys under the direct supervision of a licensed surveyor. 
 
 
D. 
Field Notes and Records.  Record surveys in field notebooks. 
 
 
E. 
Use by the OWNER.  The OWNER may at any time use line and grade points and 
markers established by the OWNER or CONTRACTOR.  The CONTRACTOR’s 
surveys are a part of the Work and may be checked by the OWNER or representatives 
of the OWNER at any time.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 2 of 5 
1.03 
RELATED SECTIONS 
 
A. 
Section 01025 – Measurement and Payment 
 
 
B. 
Section 01050 – Field Engineering 
 
1.04 
SURVEYS FOR LAYOUT AND PERFORMANCE OF WORK 
 
A. 
CONTRACTOR will perform all surveys for layout of the Work, reduce the field 
notes, make necessary calculations, and prepare drawings necessary to carry out such 
work.  CONTRACTOR’s layout work will include the following: 
 
1. Slope staking for excavations at 25-foot grid, and grade breaks. 
 
2. Blue top for subgrade at 25-foot grid and grade breaks. 
 
3. All as-built surveys specified in Section 01052. 
 
4. Surveys to measure completed units of work specified in Section 01025. 
 
B. 
CONTRACTOR must perform all additional slope staking, off-setting and other 
control staking necessary to perform the Work. 
 
1.05SURVEYS FOR RECORD DRAWINGS AND MEASUREMENT FOR PAYMENT 
 
A. 
When the Specifications require items of work to be measured by surveying methods, 
the CONTRACTOR will perform the surveys and perform necessary calculations to 
determine payment quantities.  The ENGINEER may perform independent checks. 
 
B. 
Items requiring surveys for determining pay quantities are given in Section 01025, 
Measurement and Payment. 
 
C. 
The Surveyor shall prepare drawings for each layer of the lining system (subgrade, 
top of compacted soil, and top of protective soil layer).  Points shall provide a 
comparison of the design elevation against the actual elevation at each point.  Points 
shall be established on a 50-foot maximum grid.  Additionally, points shall be 
established at major changes in grade, changes in alignment, along flow lines, and at 
any specific points shown in the Drawings.  The difference in design versus 
constructed elevation for each point shall not exceed the tolerance described in 
Section 01050 paragraph 1.5. 
 
D. 
Provide the OWNER with Record (As-Built) Drawings.  Separate and distinct sheets 
shall be provided depicting existing conditions, top of subgrade/finished earth 
surface, top of containment system, and top of protective cover.  Sheets shall include 
the following items:

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 3 of 5 
 
1. Topography that depicts North Cell (NC) Earthwork grading at the start 
of construction and following excavation and fills.  In the event the 
CONTRACTOR must excavate below the design subgrade as required by 
these specifications or to remove unsuitable material (at the direction and 
approval of the ENGINEER or OWNER), CONTRACTOR shall provide 
as-built survey of the final excavated limits and grades, the limits of fill 
and grades after placement of engineered fill to establish subgrade and the 
final grade. 
 
2. Staking points, grade breaks and limit lines of earthwork as shown in the 
Design Drawings. 
 
3. Staking points, grade breaks and limits of liner as shown in the Design 
Drawings.  Where not coincident, limits shall be provided for 
geomembrane, GCL, and geotextile, including anchor trench alignment 
and temporary liner terminations (special attention to be given to specific 
as-built points as required in the Construction Drawings. 
 
4. Staking points, grade breaks and limits of operations layer as shown in the 
Design Drawings. 
 
5. Limits and Grades of earthwork in the perimeter berm.  Include staking 
points, grade breaks, and points of change in surface material. 
 
6. Miscellaneous Items - CONTRACTOR’S Surveyor shall include the 
following as-built information on one of the sheets identified above (as 
appropriate) or shall provide additional sheets, as needed.  The specific 
sheet for each element shall be as approved by the OWNER. 
 
a. Location and alignment of buried utilities and buried culverts. 
 
b. Initial and finish grades for storm water control features. 
 
c. Limits of temporary or permanent access roads. 
d. Subgrade and finished grade of temporary or permanent access 
roads. 
 
e. Stockpile limits and grades (pre- and post-construction). 
 
f. Final site as-builts showing contours and any other miscellaneous 
constructions including fence, wells, probes, electrical, etc. 
 
g. OWNER-provided reference points shall be shown on all 
applicable as-built drawing sheets.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 4 of 5 
 
E. 
Surveyor shall provide a Text/ASCII file containing all collected as-built locations.  
As-built drawings shall depict all collected locations with an associated point 
reference number such that points in the provided Text/ASCII file can be referenced 
on the drawings. 
 
F. 
Surveyor shall submit certified top of subgrade as-built point drawings within 2 days 
of completion of the subgrade.  Where applicable, Surveyor shall provide certified 
top of compacted soil as-built point drawings within 2 days of completion of this 
layer. These submittals must be approved by the OWNER before installation of the 
next liner component begins.  In order to avoid project delays, the Surveyor may 
provide submittals for portions of each completed surface for approval; however, a 
final consolidated drawing of each surface shall be provided at the completion of each 
surface. 
 
G. 
All final as-built topographic survey drawings are due within 10 days after 
Substantial Completion date. 
 
H. 
Provide sealed as-built survey drawings on a 22” x 34” bond print at same horizontal 
and vertical scale, same coordinate system, same stationing, and same orientation for 
each element as shown on the design drawings.  Provide as-built survey information 
and associated point data on the same datum and coordinate basis as design drawings.  
All point data must have clear, easy to understand descriptions.  Provide all point data 
in Text/ASCII format, printed and on compact disk (CD) or DVD along with list of 
descriptor abbreviations.  All information provided must be accompanied with a letter 
explaining what is being submitted and a list of what information is given in each 
CD/DVD.  Submit all survey information of any layer to the OWNER before that 
layer is covered. 
 
I. 
Surveyor shall provide all drawings in electronic format.  Provide information in 
AutoCAD 2018 or higher format in accordance with OWNER’S drafting standards.  
Surveyor shall also provide documents in Adobe .pdf format. 
 
J. 
Submit survey information for items listed above to the OWNER before the items are 
covered. 
 
K. 
Provide surveys to measure the following items: 
 
1. Volume of Excavation; 
 
2. Volume of Engineered Fill; 
 
3. Volume of Unsuitable Material removed from the NC area below the 
design subgrade and replaced with Engineered Fill;

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01052 - 5 of 5 
2.0 
PRODUCTS 
 
 
Not Used. 
 
3.0 
EXECUTION 
 
 
Not Used. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01106 - 1 of 2 
SECTION A01106 
COORDINATION AND MEETINGS 
 
 
1.0 
GENERAL 
 
This section provides information on coordination, pre-construction meeting, progress meetings, 
and resolution meetings during construction. 
 
1.01 
COORDINATION 
 
A. 
The CONTRACTOR shall coordinate his work schedule, submittals, and various 
works to ensure an efficient sequence of the Work and material. 
 
B. 
The CONTRACTOR shall coordinate with the OWNER, ENGINEER, and other 
involved parties with regard to the Work, safety, and utilization of the Site.  The 
project will require open and continuous communication. 
 
1.02 
PRE-CONSTRUCTION MEETING 
 
A. 
A pre-construction meeting will be held at the project Site, which will be scheduled 
by the ENGINEER in consultation with the OWNER, and the CONTRACTOR. 
 
B. 
The meeting will be attended by the ENGINEER, the OWNER, and the 
CONTRACTOR.  The ENGINEER shall conduct the meeting and will take minutes 
of the meeting. 
 
1.03 
PROGRESS MEETINGS 
 
 
A. 
Upon the request of the ENGINEER, progress meetings shall be held at the Site.  
These meetings shall occur every other week.   
 
 
B. 
The progress meetings will be attended by the ENGINEER, the OWNER, the 
CONTRACTOR, and if necessary, other affected parties. 
 
 
C. 
The agenda of the meetings and meeting minutes will be provided by the 
ENGINEER. 
 
1.04 
RESOLUTION MEETING(S) 
 
 
A. 
To resolve conflicts, discrepancies, and differences of opinion, the ENGINEER shall 
convene Resolution meetings.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01106 - 2 of 2 
 
B. 
Resolution meetings shall be attended by the affected parties. 
 
 
C. 
The agenda of Resolution meetings shall depend on circumstances. 
 
1.05 
DISPUTE RESOLUTION 
 
All claims, disputes and other matters in question between the OWNER and the 
CONTRACTOR arising out of, or relating to the Contract Documents, or the breach thereof 
will be decided by binding, unappealable arbitration, if the claim for compensation, costs and 
expenses or damages is equal or less than $50,000.  The CONTRACTORS sole legal remedy 
in relation to claims of $50,000 or less shall be binding, unappealable arbitration. 
 
All arbitration of claims shall be conducted in Glendale, Arizona, in accordance with the 
Uniform Rules of Procedure for Arbitration adopted by the Arizona Supreme Court (Court 
Rules) except for any rules therein allowing or concerning appeal.  Where necessary to allow 
arbitration to proceed, the OWNER and CONTRACTOR shall execute an Agreement of 
Reference consistent with the provisions of this paragraph and the Uniform Rules as 
modified by this paragraph. 
 
If any provision of the Agreement is held by a court of competent jurisdiction to be invalid, 
void or unenforceable, the remaining provisions shall nevertheless continue in full force 
without being impaired or invalidated in any way. 
 
Should either party to the Agreement begin an action to enforce any provision of the 
Agreement, the prevailing party shall be entitled to recover reasonable attorney’s fees and 
costs in connection therewith.  Except as otherwise specifically provided in the Contract 
Documents, no action or failure to act by the OWNER, ENGINEER, Designer, or 
CONTRACTOR shall constitute a waiver of any right or duty afforded any of them under 
the Contract Documents nor shall any such action or failure to act constitute an approval of 
or acquiescence in any breach thereof. 
 
 
No payment will be made for meetings.  The bid price shall include the cost that may be 
incurred to attend and conduct any and all meetings and provide coordination. 
 
2.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025.  No payment will be made for meetings.  The bid price shall 
include the cost that may be incurred to attend and conduct any and all meetings 
and provide coordination. 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 1 of 6 
SECTION A01310 
CONSTRUCTION WORK PLAN AND SCHEDULE 
 
1.0  
GENERAL  
1.01 
PRELIMINARY WORK PLAN AND SCHEDULE 
A. 
The CONTRACTOR shall prepare and submit at the pre-construction meeting, a 
Work Plan and construction schedule. 
B. 
The ENGINEER will review the preliminary Work Plan and construction schedule 
prior to the commencement of construction activities. 
C. 
The CONTRACTOR may be interviewed by the ENGINEER to determine the 
CONTRACTOR’S understanding of the project, and ability to complete the work 
in a timely and efficient manner. 
D. 
The CONTRACTOR shall submit copy of Arizona Pollutant Discharge 
Elimination System (AZPDES) and earthmoving permit at Pre-construction 
meeting. 
1.02 
CONTRACTOR’S WORK PLAN CONTENTS 
A. 
The CONTRACTOR shall include with Work Plan a drawing detailing various 
work areas, CONTRACTOR’S utilities, phasing of work, excavation, testing, and 
any other information related to proposed operations. 
B. 
The CONTRACTOR shall describe personnel, equipment, and procedures required 
to accomplish specific items of work, including: 
1. 
Method of coordinating Subcontractors, if any, and maintaining project 
schedule. 
2. 
Methods and routes for moving and stockpiling materials on site. Include 
detailed drawings showing haul routes and logistics.  
3. 
Methods for reducing or increasing the moisture content of wet or dry soils 
prior to using them for constructing engineered fills during construction.  
4. 
Methods and equipment for excavating, hauling, and placing materials. 
5. 
Dewatering methods, equipment and schedules. 
6. 
Site drainage during construction. 
7. 
Methods and equipment for site clearing.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 2 of 6 
8. 
Methods for erosion prevention and sediment control. 
9. 
Plans for maintaining as-built information. 
10. 
Health and Safety Plan. 
11. 
Project Schedule. 
12. 
List of Personnel and equipment. 
13. 
List of Subcontractors and Subconsultants. 
14. 
List and organizational chart of project personnel responsibility. 
15. 
Other information required in technical specifications. 
16. 
Emergency action plan and contacts’ telephone numbers. 
17. 
Spill Prevention Control and Countermeasures (SPCC) Plan, if required 
based on quantity of petroleum products stored. 
18. 
Stormwater Pollution Prevention Plan (SWPPP). 
1.03 
CONTRACTOR’S CONSTRUCTION SCHEDULE 
A. 
The CONTRACTOR shall prepare a schedule as described in Section 2.01 and 
meeting overall project scheduling listed Section A01010 1.10 – Project Schedule. 
B. 
The CONTRACTOR shall coordinate schedule with the ENGINEER for the 
CONTRACTOR supplied materials. 
C. 
All Work, including demobilization, shall be complete by June 30, 2024. 
1.04 
PROJECT MEETINGS 
 
A. 
Construction Meetings: 
 
 
1. 
The ENGINEER will conduct construction meetings involving: 
 
 
 
a. 
CONTRACTOR’s Project Manager. 
 
 
 
b. 
CONTRACTOR’s Project Superintendent. 
 
 
 
c. 
OWNER’s designated representative(s). 
 
 
 
d. 
ENGINEER’s designated representative(s). 
 
 
 
e. 
CONTRACTOR’s subcontractors as appropriate to the work in 
progress. 
 
 
 
f. 
OWNER’s Construction Quality Control Consultant.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 3 of 6 
 
 
2. 
The ENGINEER shall conduct progress meetings every other week. 
 
 
3. 
The ENGINEER will take meeting minutes and submit copies of meeting 
minutes to participants and designated recipients identified at the 
Preconstruction Conference.  
 
 
 
a. 
Corrections, additions, or deletions to the minutes shall be noted and 
addressed at the following meeting. 
 
 
4. 
The ENGINEER will schedule meetings for most convenient time frame. 
 
 
5. 
The ENGINEER will have available at each meeting full chronological files 
of all previous meeting minutes.  
 
 
6. 
The CONTRACTOR shall have available at each meeting up-to-date record 
drawings. 
1.05 
VIDEO RECORDING 
 
A. 
The CONTRACTOR shall provide full access to OWNER or OWNER’s authorized 
representative to perform video recording of construction activities, training 
sessions, start-up, trouble shooting, etc. 
1.06 
CORRESPONDENCE 
 
A. 
The CONTRACTOR will provide a correspondence matrix identifying 
requirements for submitting and sharing correspondence among the parties 
involved in the Project.  
1.07 
SPECIAL CONSIDERATIONS 
 
A. 
The CONTRACTOR shall be responsible for negotiations of any waivers or 
alternate arrangements required to enable transportation of materials to the site.  
 
B. 
Maintain conditions of access road to site such that access is not hindered as the 
result of construction-related deterioration.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 4 of 6 
 1.08 FINAL WORK PLAN 
A. 
The CONTRACTOR shall resubmit the Work Plan to incorporate the information 
discussed during the pre-construction meeting. 
B. 
Work Plan and Schedule Revisions. 
1. 
The CONTRACTOR shall revise Work Plan as necessary to reflect changes 
in scope of work, but no less than once per month. 
2. 
The CONTRACTOR shall show changes occurring since previous 
submittal. 
a. 
Major changes in scope. 
b. 
Activities modified since previous submittal. 
c. 
Other identifiable changes. 
3. 
The CONTRACTOR shall submit to the ENGINEER. 
2.0  
PRODUCTS 
2.01 
CONSTRUCTION PROGRESS SCHEDULES 
A. 
The CONTRACTOR shall submit initial critical path method (CPM) schedule in 
duplicate at the Pre-construction meeting after date of execution of Agreement.  The 
critical path construction tasks shall be clearly identified.   
B. 
Construction operations will be scheduled to allow uninterrupted operation of 
existing adjacent facilities. 
 
 
1. 
The CONTRACTOR shall coordinate connections with existing work to 
ensure timely completion of interfaced items. 
C. 
At no time shall CONTRACTOR or his employees modify operation of the existing 
facilities or start construction modifications without approval of the OWNER 
except in emergency to prevent or minimize damage.  
D. 
Within 10 days prior to construction startup, CONTRACTOR shall submit for 
approval a CPM schedule with the critical path tasks clearly identified.  
1. 
Schedule shall include any information discussed in preconstruction 
meeting.  
2. 
The schedule shall account for schedule of Subcontracts.  
 
a. 
The schedule shall include proper sequence of construction, various 
crafts, purchasing time, Shop Drawing approval, material delivery,

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 5 of 6 
equipment fabrication, startup, demonstration, and similar time 
consuming factors.  
3. 
The schedule shall show as a minimum, earliest starting, earliest 
completion, latest starting, latest finish, and free and total float for each task 
or item.  
E. 
The CONTRACTOR shall evaluate schedule as necessary to reflect changes in 
Scope of Work, but no less than bi-weekly. 
 
1. 
Show changes since previous submittal including major scope changes, 
activities modified since previous submittal and other identifiable changes.  
2. 
The CONTRACTOR shall update, correct, and rerun schedule and submit 
to ENGINEER in triplicate with pay application to show rescheduling 
necessary to reflect true job conditions.  
3. 
When shortening of various time intervals is necessary to correct for behind 
schedule conditions, the CONTRACTOR shall indicate actions to be 
implemented in order to accomplish the work in a shorter duration.  
4. 
Information shall be submitted to ENGINEER in writing with revised 
schedule.  
 
a. 
Progress schedules shall be reviewed during progress meetings.  
 
b. 
The CONTRACTOR shall submit a computer-generated graphic 
type schedule with separate line for each item of Work or operation 
identifying first work day of each week.  
 
c. 
The schedule shall show complete sequence of construction by 
activity, identifying Work of separate stages and other logically 
grouped activities.  
 
 
1) 
The schedule shall indicate the early and late start, early and 
late finish, float dates, and duration, and critical items.  
 
d. 
The schedule shall indicate estimated percentage of completion for 
each item of Work at each submission.  
 
e. 
The schedule shall indicate submittal dates and review periods 
required for Shop Drawings, product data, samples, and product 
delivery dates, including those furnished by the OWNER.  
 
f. 
The CONTRACTOR shall coordinate schedule with ENGINEER 
for Engineer supplied information.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01310 - 6 of 6 
 
g. 
The CONTRACTOR shall coordinate schedule with Work Plan. 
F. 
If CONTRACTOR does not take necessary action to accomplish work according 
to schedule, CONTRACTOR may be ordered by OWNER in writing to take 
necessary and timely action to improve work progress at CONTRACTOR’s 
expense.  
1. 
OWNER may require increased work forces, extra equipment, extra shifts 
or other action as necessary at CONTRACTOR’s expense.  
2. 
Should CONTRACTOR refuse or neglect to take such action authorized, 
under provisions of this contract, OWNER may take necessary actions 
including, but not necessarily limited to, withholding of payment and 
termination of Contract.  
G. 
The CONTRACTOR shall indicate submittal dates and review periods required for 
shop drawings, product data, samples, and product delivery dates, including those 
furnished by the OWNER. 
H. 
The schedule shall indicate surveys for layout, as-builts, and measurement for 
payment. 
3.0 
EXECUTION  
 
 
NOT USED 
 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025. 
B. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 1 of 5 
SECTION A01400 
QUALITY CONTROL 
 
 
1.0 
GENERAL 
 
1.01 
SUMMARY DESCRIPTION 
 
A. 
This section specifies quality control descriptions and procedures and shall be 
applicable to all office, field, and shop work in the Contract Documents. 
 
1.02 
RELATED WORK SPECIFIED ELSEWHERE 
 
A. 
Section A - General Requirements 
B. 
Section B - Sitework 
 
1.03 
QUALITY CONTROL 
 
A. 
Quality control (QC) refers to the sampling, testing and measuring of all materials 
used at the Site and the verification checking of Contract Drawings and 
Specifications by the CONTRACTOR to ensure that the Work conforms to the 
requirements of the Contract Drawings and Specifications.  QC testing will comply 
with all pertinent codes, regulations and standards referenced within the Contract 
Documents. 
B. 
Unless specifically authorized in writing, no construction shall be started until the 
CONTRACTOR’S QC plan is approved. 
C. 
The CONTRACTOR shall establish and continuously provide a quality control 
system to perform sufficient inspection and testing of all items of Work, including 
that of subcontractors, to ensure conformance to applicable specifications and 
drawings with respect to the materials, workmanship, construction, finish, 
functional performance, and identification.  This control shall be established for all 
construction, except where the Technical Provisions of the contract provide for 
specific control inspections, tests or other means to be performed by the 
ENGINEER.  The CONTRACTOR’S control system shall specifically include the 
surveillance and testing required in the Contract Specifications. 
D. 
The CONTRACTOR’S quality control system is the means by which he assures 
himself that his construction complies with the requirements of the Contract plans 
and specifications.  The controls shall be adequate to cover all construction 
operations and shall be keyed to the proposed construction sequence. 
E. 
The CONTRACTOR’S job supervisory staff may be used for quality control, 
supplemented as necessary by additional personnel for surveillance, special

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 2 of 5 
technicians, or testing facilities to provide capability for controls required by the 
Technical Provisions of the specifications.  Prior approval is required for facilities, 
equipment, and personnel used by the CONTRACTOR in performing the specified 
testing. 
 
1.04 
SUBMITTALS 
 
A. 
The CONTRACTOR shall submit to the OWNER and ENGINEER for approval a 
Quality Control Plan which shall include the procedures, instructions, and reports. 
1.05 
NOTICES 
 
A. 
Additional inspection and testing required due to defective work or ill-timed notices 
may be initiated by the ENGINEER and shall be at the CONTRACTOR’S expense. 
1.06 
PROJECT COOPERATION 
 
A. 
The CONTRACTOR shall provide representatives of the OWNER and 
ENGINEER access to the Work at all times and at all locations where Work is in 
progress. 
 
B. 
The CONTRACTOR shall allow the ENGINEER, OWNER, or their 
representatives access and time to conduct Quality Assurance sampling or testing.  
Frequencies, time, and locations will be at the ENGINEER’s discretion.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 3 of 5 
1.07 
TESTING FREQUENCY 
 
 
A. 
SUBGRADE 
 
1. 
The CQA ENGINEER will perform testing on subgrade surfaces at 
frequencies as shown in the table below: 
 
TESTS AND OBSERVATIONS 
ON SUBGRADE PREPARATION 
 
           Parameter 
Test Method 
Minimum 
Testing 
Frequency 
Percent Compaction 
(Note 1) 
ASTM D 
2922 
1 per acre (Note 2) 
Compaction Curve 
ASTM D 
1557 
1 per 5 acres, 
1 minimum 
Preparation of 
Previously Compacted 
Lift 
Observation 
Part Time 
 
a. 
Percent compaction is defined as the dry density of the compacted 
soil divided by the maximum dry density measured in the laboratory 
with a specified method of compaction.  The test methods listed are 
for measurement of the dry density of the compacted soil.  
Compaction shall be a minimum of 90 percent of modified proctor 
in accordance with ASTM D1557. 
 
b. 
At a minimum, at least one test should be performed each day the 
construction personnel prepare subgrade by compaction. 
 
B. 
GENERAL FILL (HAUL ROADS) 
 
1. 
General fill is required for the construction of temporary structures such as 
haul roads, ramps and other fills that will be removed in the future.  Testing 
of general fill shall not be required.  These general fills may be constructed 
over the existing waste footprint. 
 
2. 
Compaction of general fill shall be, at a minimum, 85 percent of Modified 
Proctor in accordance with ASTM D1557.  The ENGINEER may perform 
spot testing of the fill to determine the actual percent compaction being 
achieved by the CONTRACTOR.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 4 of 5 
 
3. 
The CONTRACTOR is responsible for the safety and maintenance of 
general fill structures until the completion of the Work.  After completion 
of the project general fill structures will be the responsibility of the Glendale 
Landfill staff. 
 
 
C. 
ENGINEERED FILL (PERMENANT SLOPES, ALL OTHER FILLS) 
 
1. 
Field Test Methods During Construction 
 
a. 
Testing frequency of structural fill during construction shall be as 
shown in the table below; 
 
ENGINEERED FILL 
 
Parameter 
Test Method 
Minimum Testing 
Frequency 
Water Content 
ASTM D 
3017 
1/acre/lift and at least 
1 per 1000 yd3 
Density 
ASTM D 
2922 
1/acre/lift and at least 
1 per 1000 yd3 
Compaction Curve 
ASTM D 
1557 
1/5 acres/lift and at 
least 1 per 5000 yd3 
Construction 
Oversight 
Observation 
Part-Time 
 
b. 
Every tenth sample tested with ASTM D3017 should be tested by 
ASTM D4643; 
c. 
For Engineered Fill, compaction shall be a minimum of 90 percent 
of modified proctor in accordance with ASTM D1557; 
d. 
Moisture content shall be in a range of ±2% of the optimum moisture 
content as determined by ASTM D 1557; and 
e. 
The maximum un-compacted lift thickness shall be 10”. 
 
2. 
The CQA ENGINEER will review all CONTRACTOR submittals for 
construction plans, and laboratory results. 
3. 
The CQA ENGINEER will verify that the subgrade has been constructed to 
the thickness and final elevation as shown on the Drawings and specified 
herein. 
4 
The CQA ENGINEER will observe the installation of the structural fill to 
the lines and grades indicated on the drawings on a part time basis.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01400 - 5 of 5 
 
D. 
SOIL STOCKPILES 
 
1. 
Testing of the fill during construction of the soil stockpile(s) will not be 
required.  These stockpiles may be constructed over the existing waste 
footprint. 
 
2. 
The daily and intermediate cover stockpile(s) shall be at a nominal 85 
percent of Modified Proctor in accordance with ASTM D1557. 
 
1.08 
DEFICIENCIES 
 
A. 
When deficiencies (items that do not meet specified values) are discovered, the 
ENGINEER shall immediately determine the nature and extent of the problem, 
notify the CONTRACTOR, and complete required documentation.  In all cases, the 
ENGINEER will notify the CONTRACTOR within 1 hour of discovering the 
deficiency.  If the deficiency will cause construction delays of more than 1 hour or 
will necessitate substantial rework, the CQA ENGINEER shall also notify the 
OWNER. 
B. 
The CONTRACTOR shall correct the deficiency to the satisfaction of the 
ENGINEER or OWNER.  If the CONTRACTOR is unable to correct the problem, 
the ENGINEER will develop and present to the OWNER suggested solutions for 
approval.  The corrected deficiency shall be retested before additional work is 
performed by the CONTRACTOR.  All retests and the steps taken to correct the 
problem shall be documented by the ENGINEER. 
 
2.0 
PRODUCTS 
NOT USED 
 
 
3.0 
EXECUTION 
 
NOT USED 
 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025. 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 1 of 13 
SECTION A01500 
TEMPORARY FACILITIES AND CONTROLS 
 
1.0  
GENERAL 
1.01 
REQUIREMENTS 
A. 
The CONTRACTOR shall furnish, install and maintain required construction aids 
and barriers as required to prevent public entry, and to protect the Work, existing 
facilities, trees and plants from construction operations and other temporary 
facilities required to complete the Work. 
B. 
The CONTRACTOR shall provide and maintain methods, equipment, and 
temporary construction, as necessary to provide controls over environmental 
conditions at the construction site and related areas under the CONTRACTOR’s 
control. 
C. 
The CONTRACTOR shall remove all temporary facilities at completion of the 
Work or when no longer necessary. 
D. 
The CONTRACTOR shall not interfere with the normal business traffic and the 
operations of the Glendale Landfill including not using customer traffic 
circulation roads. 
E. 
In addition to any other remedy available by law or equity to the OWNER, the 
parties expressly agree that the CONTRACTOR shall be liable for and shall pay 
to the OWNER the sum of five thousand dollars ($5,000.00) for each notice of 
violation and/or citation of a federal, state, county, city, agency, or administrative 
law, rule, regulation, ordinance or court order resulting from the 
CONTRACTOR’s acts, errors, or omissions on the Project.  This sum will be 
taken out of the CONTRACTOR’s Contract with the OWNER.  This sum is in 
addition to any penalty, fine, or fee imposed by a court of law or administrative 
agency related to the notice of violation and/or citation, and in addition to the 
CONTRACTOR’s acts, errors, or omissions on the Project.  The parties expressly 
agree that the sum fixed above is reasonable and approximates the actual 
anticipated loss to the OWNER at the time and making of this agreement in the 
event that a notice of violation and/or citation is levied on the Project.  The parties 
expressly acknowledge and agree to the fixed sum set forth above because of the 
difficulty of proving the OWNER’s actual damages in the event that a notice of 
violation and/or citation is levied on the Project. 
1.02 
DUST CONTROL 
A. 
Dust control is absolutely critical on this Project. Due to residences and 
institutions in close proximity to this landfill, its operations are under public

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 2 of 13 
scrutiny at all times. Under Maricopa County’s requirements for an Earthmoving 
Permit, the CONTRACTOR must place a sign for public viewing, with a 
telephone number that can be used by the public to make complaints to the 
Maricopa County Air Quality Department.  Such a call will result in a visit to the 
site by County Dust Enforcement personnel and may result in a Notice of 
Violation (NOV).  Notices of violation are issued to the holder of the Earthmoving 
Permit (the CONTRACTOR), but they reflect unfavorably on the City of 
Glendale. 
The CONTRACTOR shall be prepared to spend as much time as required to keep 
dust controlled in accordance with regulatory requirements.  The air contaminant 
emission at the Work area shall not exceed 20-percent opacity during the Contract 
period.  Local regulatory requirements may be more stringent than the maximum 
allowable stated above.  The CONTRACTOR is responsible for identifying and 
complying with all applicable regulatory levels.  Whenever any dust emissions 
that can be seen by the naked eye, rising from the operation, and/or fugitive 
emissions obstructing the view of the operations, the CONTRACTOR is in 
violation of these Specifications.  If the CONTRACTOR fails to provide the 
necessary dust control, to the ENGINEER’S satisfaction, the Project will be shut 
down, at the CONTRACTOR’s expense, until the CONTRACTOR presents 
satisfactory evidence to the ENGINEER that he can continue Work and prevent 
dust as required. 
B. 
The CONTRACTOR shall provide continuous positive methods and apply dust 
control measures to prevent rising dust from construction operations, and provide 
positive means to prevent airborne dust from dispersing into the atmosphere.  
Chemical dust suppressants must be approved by the ENGINEER prior to use. 
C. 
The CONTRACTOR shall control dust by preventing blowing and movement of 
dust from exposed soil surfaces and access roads to reduce on- and off-site 
damage and health hazards.  Control may be achieved by irrigation in which the 
site shall be sprinkled with water until the surface is moist.  The process shall be 
repeated as needed. 
1.03 
NOISE CONTROL 
A. 
The CONTRACTOR’s vehicles and equipment shall be such as to minimize noise 
to the greatest degree practicable. Noise levels shall conform to the latest OSHA 
standards and in no case will noise levels be permitted which interfere with the Work 
of the OWNER or others. 
1.04 
PEST AND RODENT CONTROL 
A. 
Provide rodent and pest control as necessary to prevent infestation of construction 
or storage areas.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 3 of 13 
1. 
Employ methods and use materials that will not adversely affect conditions 
at the site or on adjoining properties. 
1.05 
SURFACE WATER CONTROL 
A. 
The CONTRACTOR shall provide methods to control surface water to prevent 
damage to the Project, the site, or adjoining properties.  The CONTRACTOR shall 
control fill, grading and ditching to direct surface drainage away from 
excavations, pits, tunnels and other construction areas; and to direct drainage to 
proper run-off. 
B. 
The CONTRACTOR shall provide, operate, and maintain equipment of adequate 
capacity to control surface erosion. 
C. 
The CONTRACTOR shall dispose of drainage water in a manner to prevent 
flooding, erosion, or other damage to any portion of the site or to adjoining areas. 
1.06 
DEBRIS CONTROL 
A. 
All areas under the CONTRACTOR’s control shall be maintained free of 
extraneous debris. 
B. 
The CONTRACTOR shall initiate and maintain a specific program to prevent 
accumulation of debris at the Project site, storage and parking areas, or along 
access roads and haul routes. 
1. 
The CONTRACTOR shall utilize only City of Glendale Solid Waste 
Collection Services containers and/or vehicles for any and all debris control 
measures. 
2. 
The CONTRACTOR shall prohibit overloading of trucks to prevent spillage 
on access and haul routes. Traffic areas shall be periodically inspected to 
enforce requirements. 
C. 
The CONTRACTOR shall schedule periodic collection and disposal of debris. 
Additional collections and disposal of debris shall be provided whenever the 
periodic schedule is inadequate to prevent accumulation. 
1.07 
POLLUTION CONTROL 
A. 
The CONTRACTOR shall provide methods, means and facilities required to 
prevent contamination of soil, water or atmosphere by the discharge of noxious 
substances from construction operations. If such contamination should occur, the 
CONTRACTOR shall immediately notify the OWNER and ENGINEER. 
B. 
The CONTRACTOR shall provide equipment and personnel to perform 
emergency measures required to contain any spillage and to remove contaminated 
soils or liquids; and, shall excavate and dispose of any soil contaminated by the

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 4 of 13 
construction operations off-site in accordance with all Federal, state, and local 
regulations and replace with suitable compacted fill, topsoil and/or vegetation as 
directed by the ENGINEER. 
C. 
The CONTRACTOR shall take special measures to prevent harmful substances 
from entering public waters; and, shall prevent disposal of wastes, effluents, 
chemicals, sediments, or other such substances adjacent to streams, or in sanitary 
or storm sewers. 
D. 
The CONTRACTOR shall provide systems for control of atmospheric pollutants 
and shall: 
1. 
Prevent toxic concentrations of chemicals and 
2. 
Prevent harmful dispersal of pollutants into the atmosphere. 
E. 
The CONTRACTOR shall provide adequate secondary containment structures for 
any above ground petroleum storage tanks and/or drums. If required based on the 
quantity of petroleum products stored, the CONTRACTOR shall prepare and 
implement a Spill Prevention, Control, and Countermeasures (SPCC) Plan, 
pursuant to and complying with the requirements of 40 Code of Federal 
Regulations, Part 112. The SPCC Plan shall be sealed by a Professional Engineer 
registered in the State of Arizona.  
F. 
The CONTRACTOR shall obtain a construction AZPDES permit and develop a 
Storm Water Pollution Prevention Plan (SWPPP) for the construction phase of the 
Project. 
1.08 
EROSION CONTROL 
A. 
General: The construction procedures outlined herein shall be implemented to 
assure minimum damage to the environment during construction. The 
CONTRACTOR shall take any and all additional measures required to conform 
to the requirements of applicable codes and regulations.  
1. 
Whenever possible, access and temporary roads shall be located and 
constructed to avoid environmental damage. Provisions shall be made to 
regulate drainage, avoid erosion, and minimize damage to vegetation. 
2. 
Where areas must be cleared for storage of materials or temporary 
structures, provisions shall be made for regulating drainage and 
controlling erosion, subject to the ENGINEER’s approval.  
3. 
Remove only those shrubs and grasses that must be removed for 
construction. Protect the remainder to preserve their erosion-control value.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 5 of 13 
B. 
Control Measures: Measures shall be applied to control erosion and to minimize 
the siltation of the existing waterways, and natural ponding areas. Such measures 
shall include, but are not limited to, the use of berms, baled straw silt barriers, 
gravel or crushed stone, mulch, slope drains, and other methods. 
1. 
Install erosion and sediment control practices where shown and according 
to applicable standards, codes, and Specifications. The practices shall be 
maintained in effective working condition during construction and until 
the drainage area has been permanently stabilized.  
2. 
Temporary measures shall be coordinated with the construction of 
permanent drainage facilities and other Work to the extent practicable to 
assure economical, effective, and continuous erosion and siltation control. 
3. 
The CONTRACTOR shall provide special care in areas with steep slopes. 
Disturbance of vegetation shall be kept to a minimum to maintain stability.  
4. 
After stabilization, remove all straw bale dikes, debris, etc., from the site.  
C. 
Failure to Comply: In the event the CONTRACTOR repeatedly fails to 
satisfactorily control erosion and siltation, the OWNER reserves the right to 
employ outside assistance or to use its own forces to provide the corrective 
measures indicated. The cost of such Work, plus engineering costs, will be 
deducted from monies due the CONTRACTOR.  
D. 
The CONTRACTOR shall plan and execute construction and earthwork by 
methods to control surface drainage from cuts and fills, and from borrow and 
waste disposal areas, to prevent erosion and sedimentation. 
1. 
Hold the areas of bare soil exposed at one time to a minimum.  
2. 
Provide temporary control measures such as berms, dikes, and drains. 
E. 
The CONTRACTOR shall construct fills and waste areas by selective placement 
to eliminate surface silts or clays, which will erode.  
F. 
The CONTRACTOR shall periodically inspect earthwork to detect any evidence 
of the start of erosion and apply corrective measures as required to control erosion.  
2.0  
PRODUCTS 
2.01 
MATERIALS, GENERAL 
A. 
Materials shall be new and suitable for the intended purpose, but must not violate 
requirements of applicable codes and standards.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 6 of 13 
2.02 
CONSTRUCTION AIDS 
A. 
The CONTRACTOR shall provide any and all construction aids, equipment and 
materials required to facilitate execution of the Work, including but not limited 
to: scaffolds, staging, ladders, stairs, signs, ramps, runways, platforms, railings, 
hoists, cranes, chutes and other such facilities and equipment. 
3.0  
EXECUTION 
3.01 
PREPARATION 
A. 
The CONTRACTOR shall consult with the ENGINEER and review site 
conditions and factors which affect construction procedures and construction aids, 
including adjacent properties and public facilities which may be affected by 
execution of the Work.  
3.02 
GENERAL 
A. 
Installation of facilities shall be of a neat and reasonable uniform appearance, 
structurally adequate for required purposes. 
B. 
The CONTRACTOR shall maintain barriers during entire construction period. 
C. 
The CONTRACTOR shall relocate barriers as required by progress of 
construction. 
3.03 
TREE AND PLANT PROTECTION 
A. 
The CONTRACTOR shall preserve and protect existing trees and plants at the 
site and those adjacent to the site. 
B. 
The CONTRACTOR shall consult with the ENGINEER and remove agreed-upon 
roots and branches which interfere with construction. The CONTRACTOR shall 
employ a qualified tree surgeon to remove roots and branches, and to treat cuts. 
C. 
The CONTRACTOR shall provide temporary barriers to a height of six feet 
around each tree or plant or around each group of trees or plants which are in the 
area of the Work. 
D. 
The CONTRACTOR shall protect root zones of trees and plants and shall perform 
the following in areas of protected trees and plants: 
1. 
Not allow vehicular traffic or parking; 
2. 
Not store materials or products; 
3. 
Prevent dumping of refuse or chemically injurious materials or liquids; and 
4. 
Prevent puddling or continuous running water.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 7 of 13 
E. 
The CONTRACTOR shall carefully supervise excavating, grading and filling, 
and subsequent construction operations, to prevent damage to existing vegetation, 
utilities, or monitoring devices. 
F. 
The CONTRACTOR shall replace, or suitably repair, trees and plants, and 
irrigation systems which have been damaged or destroyed due to construction 
operations at the CONTRACTOR’s expense. 
G. 
Land Protection: 
1. 
Except for any Work or storage area and access routes specifically 
assigned for the use of the CONTRACTOR, the land areas outside the 
limits of construction shall be preserved in their present condition. The 
CONTRACTOR shall confine his construction activities to areas defined 
for Work within the Specifications and the Contract Documents.  
2. 
The CONTRACTOR shall manage and control all stockpile/borrow areas, 
Work or storage areas, access routes and embankments to prevent 
sediment from entering nearby water or land adjacent to the Project site.  
3. 
The CONTRACTOR shall restore all disturbed areas including 
stockpile/borrow and haul areas and establish permanent type of locally 
adaptable vegetative cover.  
4. 
Unless earthwork is immediately paved or surfaced, the CONTRACTOR 
shall protect all side slopes and backslopes immediately upon completion 
of final grading.  
5. 
The CONTRACTOR shall plan and execute earthwork in a manner to 
minimize duration of exposure of unprotected soils.  
6. 
The CONTRACTOR shall construct fills by selective placement to 
eliminate surface soils that are susceptible to erosion.  
7. 
The CONTRACTOR shall periodically inspect earthwork to detect any 
evidence of the start of erosion, and apply corrective measures as required 
to control erosion.  
8. 
Except for areas designated by the Drawings, Specifications and the 
Contract Documents to be cleared and grubbed, the CONTRACTOR shall 
not deface, injure, or destroy trees and vegetation, nor remove, cut, or 
disturb them without approval of the ENGINEER. Any damage caused by 
the CONTRACTOR’s equipment or operations shall be restored as nearly 
as possible to its original condition at the CONTRACTOR’s expense.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 8 of 13 
3.04 
REMOVAL 
A. 
The CONTRACTOR shall completely remove temporary barriers, materials, 
equipment, and services: 
1. 
When construction needs can be met by use of permanent construction; or 
2. 
At completion of Project. 
B. 
The CONTRACTOR shall clean and repair damage caused by installation or by 
use of temporary facilities including: 
1. 
Removal of foundations and underground installations for construction aids; 
2. 
Grading areas of site affected by temporary installations to required 
elevations and slopes; and 
3. 
Cleaning of the area. 
C. 
The CONTRACTOR shall restore existing facilities used for temporary purposes 
to specified or original condition. 
D. 
The CONTRACTOR shall restore permanent facilities, if any, used for temporary 
purposes to condition existing prior to construction. 
3.05 
HISTORICAL AND ARCHAEOLOGICAL 
 
A. 
If, during the course of construction, evidence of deposits of historical or 
archaeological interest is found, the CONTRACTOR shall cease operations 
affecting the find and shall notify OWNER. 
 
 
1. 
No further disturbance of the deposits shall ensue until the 
CONTRACTOR has been notified by the OWNER that the 
CONTRACTOR may proceed. 
 
 
2. 
OWNER will issue a notice to proceed after appropriate authorities have 
surveyed the find and made a determination to the OWNER.  
 
 
3. 
The site has been previously investigated and has no known history of 
historical or archaeological finds.  
3.06 
TEMPORARY SANITARY FACILITIES 
 
A. 
Toilet Facilities: The OWNER will not provide on-site toilet facilities for the 
CONTRACTOR’s use. The CONTRACTOR shall be responsible for providing 
on-site toilet facilities for his/her employees. All toilet facilities shall be 
maintained in a neat and clean manner and shall not cause an eyesore. All toilet 
facilities shall follow all applicable regulations, laws, and ordinances. If the 
CONTRACTOR abuses the toilet facilities, the OWNER has the right to revoke 
all on-site toilet access, and the CONTRACTOR will have to provide his or her 
own toilet facilities, further away from the job site.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 9 of 13 
 
B. 
The CONTRACTOR shall provide temporary sanitary toilet facilities conforming 
to state and local health and sanitation regulations, in sufficient number for use by 
the OWNER’s designated Project Representatives, CONTRACTOR’s and 
Subcontractor’s employees. 
 
C. 
The CONTRACTOR shall maintain in sanitary condition and properly supply 
with toilet paper.  
 
D. 
No sanitary sewer pipe is located at the Project site. 
 
 
1. 
The CONTRACTOR shall arrange for portable toilet units and holding 
tanks. 
 
 
2. 
The CONTRACTOR shall pipe all wastes from trailer offices to a holding 
tank. 
 
E. 
The CONTRACTOR shall arrange for routine vacuuming, cleaning, and 
maintenance services.  
 
F. 
Proper sanitary, vector, and odor control shall be required and maintained at all 
times.  
3.07 
TEMPORARY ELECTRICITY, TELEPHONE, AND DOMESTIC WATER  
A. 
Electrical power for the CONTRACTOR’S use will not be provided by the 
OWNER.   
B. 
The CONTRACTOR shall provide power for all construction operations until 
final completion of Project. 
C. 
The CONTRACTOR shall provide temporary lighting as required during 
construction. 
D. 
The CONTRACTOR shall provide illumination Levels: In accordance with 
OSHA requirements for construction lighting. 
E. 
Equipment and materials need not be new. 
F. 
Temporary wiring shall be sized and fused in accordance with NEC requirements. 
G. 
Relamp fixtures during construction period to meet requirements of the 
CONTRACTOR and Subcontractors, to satisfy applicable safety requirements, 
and as directed by the OWNER. 
H. 
The CONTRACTOR shall provide ventilated enclosed areas to achieve curing of 
materials, to dissipate humidity, and to prevent accumulation of dust, fumes, 
vapors, or gases.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 10 of 13 
I. 
The CONTRACTOR shall provide and pay for suitable quality water service as 
needed to maintain specified conditions for construction operations (see Section 
A01050 – 3.14 – Construction Water). 
J. 
Telephone and fax machines for the CONTRACTOR’s use will not be provided 
by the OWNER. 
K. 
Domestic water for human consumption shall be obtained by the 
CONTRACTOR. 
L. 
Obtain written approval from the OWNER a minimum of 72 hours prior to 
disconnection or shutting off any service or utility. 
3.08 
TEMPORARY FIRE PROTECTION 
 
A. 
The CONTRACTOR shall: 
 
 
1. 
Provide and maintain in working order a minimum of one fire extinguisher 
in each trailer or as required by codes;  
 
 
2. 
Be required to contact local fire department and meet all necessary fire 
codes at the Project site; 
 
 
3. 
Make arrangements for fire department audits, 30 days after Notice to 
Proceed; and 
 
 
4. 
Make roadways accessible to fire trucks. 
3.09 
TEMPORARY SITE AND OTHER ROADS 
 
A. 
The CONTRACTOR shall construct and maintain temporary site roadways in 
drivable condition necessary to carry out construction operations.  
 
B. 
The CONTRACTOR shall maintain the OWNER’s existing roads and public 
roads used during construction free from accumulations of dirt, mud, and 
construction debris resulting from construction operations. Roads shall be 
considered “maintained” when material has been removed by a mechanical 
sweeper. 
 
C. 
Paved roads damaged during routine and normal construction shall be repaired at 
the CONTRACTOR’s expense per the City of Glendale paving requirements. 
 
D. 
The CONTRACTOR shall provide photographs of road conditions before start of 
the Project.  
 
E. 
Security will not be provided by the OWNER. 
 
F. 
The CONTRACTOR shall be responsible for loss or injury to persons or property 
where Work is involved, and shall provide security and take precautionary 
measures to protect the CONTRACTOR’s and OWNER’s interests.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 11 of 13 
 
G. 
The CONTRACTOR shall provide insurance against loss of materials, contents 
of trailer(s), equipment, and other property at the Project site and Project trailer.  
3.10 
TEMPORARY PARKING 
 
A. 
Temporary parking areas shall be provided by the CONTRACTOR at no 
additional cost to the OWNER.  
 
 
1. 
The OWNER and ENGINEER will require on-site parking for at least five 
vehicles.  
 
B. 
The CONTRACTOR shall maintain designated parking areas with 1-inch 
decomposed granite or other suitable material. 
 
C. 
No heavy machinery shall be allowed on the OWNER’s parking area.  
3.11 
TEMPORARY FENCING 
 
A. 
If for any reason, the existing perimeter landfill fencing is altered or removed by 
the CONTRACTOR, the CONTRACTOR shall provide temporary fencing 
sufficient to prevent trespassing. 
 
 
1. 
The CONTRACTOR shall provide fencing that is sufficiently secure 
against trespass of children and stray animals. 
 
B. 
Materials shall be sufficiently durable to be effective for duration of construction 
period. 
 
C. 
The CONTRACTOR shall coordinate with the OWNER for the removal any and 
all temporary fencing around the Project site to be replaced with new permanent 
site fencing following construction. 
3.12 
PROGRESS CLEANING AND WASTE REMOVAL 
 
A. 
The CONTRACTOR shall maintain areas free of waste materials, debris, and 
rubbish. 
 
 
1. 
Maintain site in a clean and orderly condition. 
 
B. 
The CONTRACTOR shall remove debris and rubbish from pipe manholes, and 
other closed or remote spaces, prior to enclosing the space.  
 
C. 
The CONTRACTOR shall broom and vacuum clean interior areas prior to start 
of surface finishing, and continue cleaning to eliminate dust.  
 
D. 
The CONTRACTOR shall collect and remove waste materials, debris, and 
rubbish from site work area weekly and dispose of it at the active working face

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 12 of 13 
on-site. If the material is HazMat, the CONTRACTOR shall dispose of the 
HazMat material off-site.  
 
E. 
Open free-fall chutes are not permitted. 
 
 
1. 
The CONTRACTOR shall terminate closed chutes into appropriate 
containers with lids.  
3.13 
BARRIERS 
 
A. 
The CONTRACTOR shall provide barriers to prevent unauthorized entry to 
construction areas to allow for the OWNER’s use of site and to protect existing 
facilities and adjacent properties from damage from construction operations and 
demolition. 
 
B. 
The CONTRACTOR shall provide barricades and covered walkways required by 
governing authorities for public rights-of-way. 
 
C. 
The CONTRACTOR shall protect non-owned vehicular traffic, stored materials, 
site and structures from damage. 
3.14 
CONSTRUCTION WATER 
A. 
The CONTRACTOR is responsible for transporting water per the Drawings and 
Specifications. 
B. 
The CONTRACTOR shall not use any water from the OWNER’s two existing 
Site water stands, unless approved by the OWNER. 
C. 
The CONTRACTOR is responsible for obtaining construction water.  There is no 
potable water main on-site.  There is a potable water main adjacent to the Glendale 
Landfill’s north cell along the South side of Northern Avenue.  The 
CONTRACTOR shall contact the City of Glendale Water Department to make 
necessary arrangements to provide water services during construction.  The 
CONTRACTOR is responsible for paying for all connection and usage fees 
associated with the water services and for providing his own water storage tank. 
3.15 
CONTRACTOR’S WATER USAGE LOG 
A. 
The CONTRACTOR shall submit a monthly log of water used for dust control to 
the ENGINEER with each pay application.  The log shall be updated every month. 
1. The water usage log shall include the following: 
a. 
Date water was used; 
b. 
How many hours each day the water was used;

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01500 - 13 of 13 
c. 
Number of loads per day; 
d. 
Number of water trucks/pulls used per day; 
e. 
Loads of water per hour per day; 
f. 
Subcontractor gallons of water used on any date the CONTRACTOR used 
water; 
g. 
Pre-wet water usage, gallons per day; 
h. 
Identify size of water trucks/pulls used and how many gallons each piece of 
equipment placed per day; and 
i. 
Cumulative total per day and total gallons of water used per month. 
 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025. 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01510 - 1 of 2 
SECTION A01510 
TRAFFIC CONTROL 
 
1.0  
GENERAL 
1.01 
TRAFFIC REGULATIONS 
A. 
The following shall be considered major streets: Glendale Avenue and Northern 
Avenue.  
B. 
All traffic and/or traffic control devices on this Project shall be provided, maintained 
and/or controlled as specified in the City of Glendale Traffic Barricade Manual, 
latest revision. 
C. 
Permission to restrict major streets, sidewalks, and alleys shall be requested through 
the City of Glendale and/or Maricopa County Department of Transportation 
(MCDOT).  
D. 
Unless otherwise provided for the following “Special Traffic Regulations”, all traffic 
on this Project shall be regulated as specified in Section IV of the Traffic Barricade 
Manual. 
E. 
No deviation to the “Special Traffic Regulations” will be allowed or implemented 
unless submitted to the ENGINEER for review and approval (2) weeks prior to 
proposed Work. 
1.02 
LOCAL ACCESS REQUIREMENTS 
A. 
The CONTRACTOR shall maintain local access to all site haul roads, access roads, 
and driveways at all times. The CONTRACTOR shall restore the access as soon as 
possible. If the primary access cannot be restored in a timely manner, the 
CONTRACTOR shall provide an alternative which shall be pre-determined with the 
OWNER. Any local street restrictions imposed shall be such that local area traffic 
circulation is maintained.  
1.03 
SPECIAL SIGN REQUIREMENTS  
A. 
The CONTRACTOR shall provide, erect, and maintain advance notification, 
informational and directional access signs that may be required by the ENGINEER. 
The cost of signage is incidental to traffic control cost.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01510 - 2 of 2 
1.04 
TRAFFIC CONTROL PLAN 
A. 
The CONTRACTOR shall submit a traffic control plan for approval, showing 
placement of all traffic control devices, including all conflicting signs to be 
covered/removed or relocated, or other features that may conflict with the placement 
of temporary signage. Included in the plan shall be designated routes for the 
CONTRACTOR’s equipment during construction. The CONTRACTOR shall not 
deviate from designated routes, unless otherwise approved by the ENGINEER, and 
shall not interfere with the traffic and operations of other Contractors, landfill haulers 
or the OWNER. This plan shall be professionally drawn on 24"x36" reproducible 
medium, and shall be submitted to the ENGINEER at the Pre-Construction meeting. 
B. 
The CONTRACTOR is responsible for furnishing all traffic control-related 
materials and personnel, including but not limited to flagmen, barricades, signs and 
barriers. The cost is incidental to the traffic control cost. 
2.0  
PRODUCTS 
NOT USED 
3.0  
EXECUTION 
NOT USED 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025. 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION A01810 - 1 of 1 
SECTION A01810 
DRAWINGS 
 
1.0  
GENERAL 
1.01 
DESCRIPTION 
 
The Drawings, showing the scope, extent and character of the Work to be furnished and 
performed by the CONTRACTOR are provided under separate cover and are included as 
part of the Specifications and Contract Documents.  The Drawings are listed as follows: 
INDEX OF DRAWINGS 
1 
Title Sheet 
2 
Plan View 
3 
Excavation Plans 
4 
Stockpiling Plans 
5 
Stockpiling Plans 
6 
Details 
2.0  
PRODUCTS 
NOT USED 
3.0  
EXECUTION 
NOT USED 
 
4.0  
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 1 of 10 
SECTION B02200 
EARTHWORK 
 
1.0  
GENERAL 
1.01 
DESCRIPTION OF WORK 
A. 
The CONTRACTOR shall furnish all labor, materials, tools, supervision, 
transportation, and installation equipment necessary to perform all related Work 
as specified herein, as shown on the Contract Drawings. 
B. 
The Work of this Section shall include, but not necessarily be limited to: 
excavating, separating, hauling, stockpiling, backfilling, compacting, and grading 
of soils. The Work of this Section may pertain in whole or in part to construction 
of the following: the landfill’s north cell, excavation, filling, haul road 
development, stockpiling for soils, and hauling soil to stockpile locations. The 
Work of this Section also includes protection of Work partially completed. 
C. 
The CONTRACTOR shall conform to the dimensions, lines, and grades specified 
on the Drawings. 
D. 
No extra monetary compensation or additional time will be authorized for claims 
that soil conditions differ from those anticipated. It is the CONTRACTOR’s 
responsibility to make his own determination as to the actual existing conditions.  
1.02 
SUBMITTALS AND QUALIFICATIONS 
 
A. 
The CONTRACTOR shall submit 7 days prior to commencement of work to the 
OWNER and the ENGINEER for review a work plan describing the proposed 
methods of construction, including stripping, dewatering, excavation, filling, 
compaction, stockpiling, and backfilling for the various portions of the work. The 
review shall be for method only. The CONTRACTOR shall remain responsible 
for the adequacy and safety of the methods. 
B. 
The CONTRACTOR shall notify the OWNER Representative in writing at least 
7 days in advance of intention to perform the work of this Section. 
C. 
If work is interrupted for reasons other than inclement weather, the 
CONTRACTOR shall notify the OWNER and the ENGINEER a minimum of 24 
hours prior to the resumption of work. 
1.03 
PROTECTION 
A. 
The CONTRACTOR shall contact utility companies and locate, mark and protect 
all existing utilities before commencement of construction activities. Mounding 
of soil to construct an equipment crossing may be required for any natural gas

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 2 of 10 
lines, water sewer, or drainage culverts. The CONTRACTOR shall provide design 
by an engineer registered in the State of Arizona for any pipeline crossing. The 
CONTRACTOR shall not cross a gas line with heavy equipment until obtaining 
clearance from the utility companies and from the OWNER. 
B. 
The CONTRACTOR shall protect trees, shrubs, lawns, sprinkler/irrigation 
systems, rock outcroppings and other features remaining as part of final 
landscaping unless otherwise noted. 
C. 
The CONTRACTOR shall protect benchmarks, survey markers, fences, roads, 
sidewalks, paving, curbs and other existing structures from damage due to the 
CONTRACTOR’S activities unless otherwise noted. 
D. 
The CONTRACTOR shall repair damage caused by the construction operations 
at the CONTRACTOR’S expense. 
E. 
Erosion control must be maintained. Erosion control measures shall be as noted 
on the Grading Plan or as directed by the ENGINEER. 
2.0  
PRODUCTS 
2.01 
GENERAL FILL MATERIAL 
A. 
The General Fill for ramps, haul roads, etc. shall consist of on-site soil materials 
and shall be free of debris, foreign objects, roots, organic and other materials 
considered deleterious by the ENGINEER. 
2.02 
ENGINEERED FILL MATERIAL 
A. 
The Engineered Fill material shall be on-site soil materials, or other materials, as 
approved by the OWNER or ENGINEER.  The Engineered Fill shall be free of 
rock greater than 6 inches in diameter retained on a 6-inch mechanical screen.  
The location of all screening and crushing equipment shall be approved by the 
OWNER and ENGINEER prior to the production of the Engineered Fill materials. 
The Engineered Fill Material shall be free of debris, foreign objects, roots, and 
organic and other materials considered deleterious by the ENGINEER.  The 
Engineered Fill material shall be composed of cohesive materials. 
2.03 
PIPE BEDDING MATERIAL 
A. 
The Pipe Bedding aggregate shall be washed ASTM C33 Coarse Aggregate Size 
Number 57 with the following gradation. Alternate particle sizes will be 
considered by the OWNER or ENGINEER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 3 of 10 
Sieve 
Designation 
Percent 
Passing 
1 1/2" 
100 
1" 
95-100 
1/2" 
25-60 
#4 
0-10 
#8 
0-5 
 
B. 
Native soil backfill may be used for backfill for the temporary culverts. 
2.04 
ACCESS ROAD SEGMENT SURFACING 
A. 
Access roads shall be surfaced with Asphalt Surface Millings and oil mixture 
(millings). The millings are reclaimed asphalt pavement (AP) material meeting 
the requirements of MAG Section 709.1. The millings shall be free of detrimental 
quantities of organic, non-granular soils and deleterious materials. The millings 
shall be stored in such a manner as to permit ready inspection and shall be 
protected from contamination. Any portion of the stockpile that has been 
consolidated so that the uniformity is affected will require reprocessing prior to 
use.  Reclaimed asphalt millings are available on site and are to be used along 
with the specified emulsion mixture.   
3.0  
EXECUTION 
3.01 
PREPARATION 
A. 
The CONTRACTOR shall establish and identify required lines and levels. 
B. 
The CONTRACTOR shall maintain benchmarks, monuments, and other 
reference points and re-establish if disturbed or destroyed, at no additional cost to 
the OWNER. 
C. 
Before start of the Work, the CONTRACTOR shall locate utilities in the Work 
areas. The CONTRACTOR shall notify utilities to remove and relocate lines that 
are in the way of construction and are not to be relocated as a part of the Work 
covered by these Specifications. 
D. 
The CONTRACTOR shall maintain, protect, reroute, or extend as required 
existing utilities to remain which pass through the Work area. 
E. 
The CONTRACTOR shall develop access to the construction area in accordance 
with the requirements of the Drawings and Specifications.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 4 of 10 
F. 
The CONTRACTOR shall install barriers and other devices to protect areas 
adjacent to construction. 
G. 
The CONTRACTOR shall install silt fences or other means to control surface 
erosion in accordance with the Construction AZPDES Permit. 
3.02 
STOCKPILING 
A. 
Excavated material classified as General Fill material and/or Engineered Fill 
material shall be segregated from other materials and stockpiled in the manner 
shown on the Drawings or as specified by the OWNER or ENGINEER. 
B. 
Excavated materials classified as oversize material (defined as rock materials 
larger than 6 inches in any direction), rejects from any screening or crushing 
operation, and the Crushed Rock material shall be stockpiled in designated areas 
separate from General Fill material and/or Engineered Fill material and from 
incompatible soil, clearing debris, or other objectionable materials. Stockpile 
areas will be shown on the Drawings or designated by the OWNER or 
ENGINEER. 
C. 
Stockpiles of Engineered Fill material and General Fill material shall be no 
steeper than 2:1 (horizontal: vertical) or their respective angle of repose, 
whichever is flatter, without approval of the ENGINEER, graded to drain, sealed 
by track walk with a Dozer parallel to the slope or other means approved by the 
ENGINEER, and graded uniformly daily during periods when fill is taken from 
the stockpile.  Upon completion of a stockpile the CONTRACTOR shall soak the 
surface and shall form a ¼ inch thick crust on all surfaces.  After creation of the 
crust, no further vehicle traffic will be allowed. Any screening berms will be 
sealed by tracking parallel to the slope with a Dozer or other means approved by 
the ENGINEER and graded to remove loose materials and provide a smooth even 
surface. 
D. 
The CONTRACTOR shall perform watering as necessary to control dust. 
E. 
Soil from the cell excavation shall be stockpiled within the area specified on the 
Construction Drawings. Stockpile sideslopes shall be no greater than 2:1, unless 
otherwise approved by the ENGINEER. 
3.03 
EXCAVATION – GENERAL 
A. 
Excavation shall be performed, at a minimum, to the lines and grades indicated 
on the Drawings. Additional excavation shall be performed to achieve a stable 
working base or filled to bridge over weak subgrade materials. The limits of 
additional excavation shall be determined by the ENGINEER. 
B. 
All excavation shall be open cut unless otherwise shown on Plans or approved by 
the OWNER or ENGINEER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 5 of 10 
C. 
Excavated materials shall be transported to stockpile locations, as indicated on the 
Drawings or as directed by the ENGINEER. 
D. 
The tolerances from the dimensions and elevations shown on the Drawings for 
excavation activities only shall be: 
1. 
Trenches: 
Line 
±0.1 foot 
 
 
Grade 
±0.1 foot 
2. 
Cell Floor and  
Line 
±0.5 foot 
 
Slope 
Grade 
±0.1 foot 
to be lined(1): 
 
 
3. 
Unlined Cell Slopes: Line 
±0.5 foot 
 
 
Grade 
± 0.2 foot 
4. 
Road Excavations: 
Line 
±0.5 foot 
 
Grade 
±0.2 foot 
(1) – These areas to be left 1 foot “fat” from depicted grades as indicated on the 
Drawings. 
3.04 
SHEETING, SHORING, AND BRACING 
A. 
When necessary, the CONTRACTOR shall furnish, put in place, and maintain 
such sheeting, bracing, etc., as may be required to support the sides of the 
excavation and to prevent movement. 
B. 
Care shall be taken to prevent voids outside the sheeting. 
C. 
If voids are formed, they shall be immediately filled and compacted. 
D. 
Unless adjacent facilities will be damaged, the CONTRACTOR shall remove all 
sheeting, shoring, and bracing after backfill has been placed to a depth of 18 
inches over the pipeline. 
E. 
Shoring shall be completely removed prior to closure of the trench.  
F. 
The CONTRACTOR shall be responsible for performance and safety on all 
sheeting, shoring, and bracing. 
3.05 
UNAUTHORIZED EXCAVATION 
A. 
All excavation outside or below the proposed lines and grades shown on the 
Drawings shall be considered unauthorized excavation.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 6 of 10 
B. 
The CONTRACTOR shall backfill areas of unauthorized excavation with 
Engineered Fill in accordance with this Section at no additional cost to the 
OWNER, to insure the stability of the structure or construction involved. 
3.06 
OBSTRUCTIONS 
A. 
Obstructions shown on the Drawings are for information only and do not 
guarantee their exact locations nor exclude the presence of other obstructions. 
B. 
The CONTRACTOR shall exercise due care in excavating adjacent to existing 
obstructions and shall not disturb them. 
C. 
In the event obstructions are disturbed, the CONTRACTOR shall repair or replace 
them as quickly as possible to the condition existing prior to their disturbance. 
This repair or replacement will be at the CONTRACTOR’s expense. 
D. 
If desired by the utility or the OWNER, the CONTRACTOR shall pay for the 
repair or replacement Work performed by the forces of the utility, the OWNER 
or other appropriate party. 
E. 
If replacement or repair of disturbed obstructions is not performed after a 
reasonable period of time, the OWNER may have the necessary Work done and 
deduct the cost of same from payments to the CONTRACTOR. 
3.07 
PUMPING AND DRAINAGE 
A. 
At all times during construction, the CONTRACTOR shall provide, maintain and 
operate equipment and facilities to remove all water entering excavations and 
keep such excavations dry so as to obtain a satisfactory subgrade to allow the 
construction of the Work. 
B. 
Drainage shall be disposed of only in an area approved by the OWNER and the 
ENGINEER. 
3.08 
SURVEY CONTROL 
A. 
The CONTRACTOR shall survey the location and elevation of the excavations. 
He or she shall also Survey the location and elevation of the top of subgrade 
shown on the Drawings. Surveying shall be performed in accordance with 
Specifications Section 01050. 
B. 
The CONTRACTOR shall provide As-built Drawings of the location and 
elevation of the excavations and the top of subgrade, in accordance with the 
requirements of Specifications Section 01050. The CONTRACTOR shall submit 
this As-built Drawing to the OWNER or ENGINEER at least 48 hours prior to 
the start of fill placement. The CONTRACTOR may submit a partial As-built

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 7 of 10 
Drawing to obtain approval for a portion of Work. The OWNER or ENGINEER 
will define the minimum requirements for a partial Submittal. 
3.09 
PIPE BEDDING PLACEMENT 
A. 
Place pipe bedding only when trench subgrade has been prepared and approved 
by the ENGINEER. 
B. 
Compact pipe bedding according to Part 2.04 of this Section. 
C. 
Place pipe in pipe bedding to lines and grades indicated on Drawings. 
D. 
Place additional pipe bedding to springline of pipe, then compact. 
E. 
Do not damage pipe. 
F. 
Place and compact additional pipe bedding to lines, grades and cross-sectional 
dimensions shown on the Drawings and Specifications, then compact. 
G. 
Install pipe bedding to the thickness and elevations shown on the Drawings to a 
tolerance of minus zero to plus 0.10 feet. 
3.10 
SUBGRADE PREPARATION AND COMPACTION 
A. 
General: The CONTRACTOR may be required to reconstruct the subgrade in 
areas where over-excavations are determined necessary by the OWNER or 
ENGINEER at the CONTRACTOR’s expense. 
B. 
Prior to placing any fill material over undisturbed subsoil or upon completion of 
excavation to subgrade, the subgrade shall be proof-rolled with loaded dump truck 
or similar pneumatic tired vehicle under the observation of the ENGINEER. 
Should subgrade soils pump, yield or fail to achieve density required, the 
CONTRACTOR shall disc, blade, scarify and allow to dry or add moisture to aid 
the compaction process. The CONTRACTOR shall then recompact the soil in 
layers as specified in this Section under the observation of the ENGINEER. This 
procedure shall be repeated as necessary as the weather permits, to facilitate the 
drying and recompaction of the soil. After recompaction, the subgrade shall be 
fine graded within tolerance specified in this Section and rolled to form a smooth 
surface using a steel-drum vibratory roller under the observation of the 
ENGINEER. 
C. 
The CONTRACTOR shall grade the subgrade. Uneven areas and low spots shall 
be eliminated. Debris, roots, branches, stones, etc., in excess of 6 inches in size 
shall be removed.  Remove subsurface soils that have been contaminated with 
petroleum products. Rocks/stones in excess of 12 inches in size shall be relocated 
to the rock stockpile.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 8 of 10 
D. 
Prior to placing the Engineered Fill materials, the existing ground surface shall be 
scarified to a minimum depth of 8 inches, moisture-conditioned to within 
±2 percent of the optimum moisture content and compacted to 90 percent of the 
maximum dry density as determined by ASTM D1557. 
 
E. 
Should efforts to achieve required density be unsuccessful, the CONTRACTOR 
shall excavate the material and replace with Engineered Fill material as specified 
in this Section. Undercutting shall not be permitted except at the direction of the 
ENGINEER. 
3.11 
GENERAL FILL 
A. 
The General Fill materials shall be placed in a single uniform lift thickness of 24 
inches and/or as specified on the Drawings. 
 
3.12 
ENGINEERED FILL PLACEMENT 
A. 
Engineered Fill material shall be compacted to 90 percent of the maximum dry 
density as determined by ASTM D1557.  Moisture content shall be uniform 
throughout a compacted lift and shall be within a moisture content range of 
±2 percent of optimum moisture content. 
B. 
Engineered Fill material shall be placed in 8 inch (maximum) uniform lift 
thickness and compacted to a uniform density. 
3.13 
ACCESS ROAD SURFACING 
A. The subgrade shall be moisture-conditioned and prepared as necessary to meet the 
final surface performance specified under paragraph D of this Subsection. 
B. Placement shall be by methods that will minimize segregation. Any damage to 
underlying or surrounding material or structures during placement of the millings 
shall be repaired before proceeding with Work. 
C. Millings shall be placed to fill layer thickness in one operation in such a manner as to 
minimize segregation and avoid damage to underlying materials. 
D. Millings shall be with an emulsion/rejuvenator application rate of 0.2 GAL/SY x 2 
with SS-1H. The millings will have a total moisture content of 6% by weight and be 
compacted to 95% Standard Proctor Density. Prior to acceptance, the surface of the 
placed millings shall be proof-rolled and shall be smooth, firm, and unyielding. At 
the completion of this activity no wheel ruts or other irregularities shall exist on the 
surface. Place millings to the lines, grades, cross-sections, and dimensions shown on 
the Drawings.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 9 of 10 
E. Millings shall be compacted by a smooth drum vibratory compactor, as approved by 
the ENGINEER, which shall make a minimum of three passes in each direction over 
the millings. 
F. After asphalt millings are compacted, a final coat of emulsion/rejuvenator will be 
applied at an application rate of 0.25 GAL/SY. 
 
3.14 
FIELD QUALITY ASSURANCE 
A. 
The minimum frequency and details of quality assurance testing are provided in 
Specifications Section 01400. The CONTRACTOR shall be aware of all field 
quality assurance activities, as these may affect the schedule. 
B. 
All perforations resulting from testing the backfill material shall be filled with soil 
and compacted to the satisfaction of the ENGINEER. 
C. 
If a defective area is discovered in the earthwork, the ENGINEER shall 
immediately determine the extent and nature of the defect by additional tests, 
observations, a review of records, or other means that the ENGINEER deems 
appropriate. 
D. 
After determining the extent and nature of a defect, the CONTRACTOR shall 
correct the deficiency at the CONTRACTOR’s expense. 
E. 
Additional testing shall be performed by the ENGINEER to verify that the defects 
have been corrected before any additional Work is performed by the 
CONTRACTOR in the area of the deficiency. 
3.15 
PRODUCT PROTECTION 
A. 
The CONTRACTOR shall use all means necessary to protect all prior Work, 
including all materials and completed Work of other Sections. 
B. 
In the event of damage, the CONTRACTOR shall immediately make all repairs 
and replacements necessary, to the approval of the ENGINEER at no additional 
cost to the OWNER. 
C. 
At the end of each day, the CONTRACTOR shall verify that the entire Work area 
was left in a state that promotes surface drainage off and away from the area and 
from finished Work. If threatening weather conditions are forecast, compacted 
surfaces shall be seal-rolled to protect finished Work. 
 
4.0  
MEASUREMENT AND PAYMENT

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02200 - 10 of 10 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025. 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02211 - 1 of 3 
SECTION B02211 
GRADING 
 
 
1.0 
GENERAL 
 
1.01 
SUMMARY DESCRIPTION 
 
A. 
Work consists of general grading (filling and excavation) required to establish a 
final Site grade as designated on the Contract Drawings.  The excavation shall be 
rough graded to the tolerances indicated in Section B02200.  Grades in the area of 
the future installation of the Module 2B liner (Not in this Contract) shall be left 1 
foot “fat” of the depicted contours as indicated on the Drawings.  These slopes will 
be trimmed back by others before the landfill liner is installed. 
B. 
The CONTRACTOR shall perform rough grading of the north cell excavation (fine 
grading will be done by others). 
C. 
The CONTRACTOR shall perform rough grading of soil stockpiles. 
D. 
The CONTRACTOR shall grade, cut, fill, and contour adjacent areas or washes in 
the immediate vicinity the work zone as required to slope to drain. 
 
1.02 
RELATED WORK SPECIFIED ELSEWHERE 
 
A. 
Section B02222 – Excavation 
B. 
Section B02223 – Backfilling 
 
1.03 
PROTECTION 
 
A. 
The CONTRACTOR shall protect bench marks, any existing structures, fences and 
roads. 
B. 
The CONTRACTOR shall protect above or below grade utilities and wells which 
are to remain. 
C. 
The CONTRACTOR shall repair all damage to any appurtenances disturbed as 
directed by the OWNER. 
 
 
2.0 
PRODUCTS 
 
NOT USED

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02211 - 2 of 3 
3.0 
EXECUTION 
 
3.01 
PREPARATION 
 
A. 
The CONTRACTOR shall identify required lines, levels, contours, and datum. 
B. 
The CONTRACTOR shall identify known below-grade utilities and stake and flag 
locations. 
C. 
The CONTRACTOR shall identify and flag above grade utilities. 
D. 
The CONTRACTOR shall maintain and protect remaining existing utilities which 
pass through the Work area. 
E. 
The CONTRACTOR shall notify appropriate utility agencies to remove and 
relocate utilities. 
F. 
The CONTRACTOR shall upon discovery of unknown utilities or concealed 
conditions, discontinue affected work and notify the ENGINEER. 
 
3.02 
BOULDER EXCAVATION 
 
A. 
The CONTRACTOR shall excavate boulders (average diameter more than 12 
inches) from areas to be graded and stockpiled in area(s) designated by the OWNER 
in accordance with Section B02222. 
B. 
The CONTRACTOR shall pothole with backhoe equipment as necessary to remove 
boulders protruding beyond the final grade and elevation. 
 
3.03 
GRADING 
 
A. 
The CONTRACTOR shall cut and fill areas to contours or elevations as shown on 
the Contract Drawings. 
B. 
The CONTRACTOR shall place and compact materials in continuous layers in 
conformance with Section B02223. 
C. 
The CONTRACTOR shall maintain the optimum moisture content of fill materials 
to attain required compaction densities. 
D. 
The CONTRACTOR shall make grade changes gradual and blend slopes into level 
areas. 
E. 
The CONTRACTOR shall remove excess soil, unsuitable material, and boulders 
from the Work area during rough and final grading and stockpile on-site at a 
stockpile area designated by the ENGINEER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02211 - 3 of 3 
3.04 
TOLERANCES 
 
A. 
The CONTRACTOR shall rough grade the surface of excavation subgrade to plus 
or minus 0.1 feet. 
B. 
The CONTRACTOR shall fine grade screening berm surfaces to plus or minus 0.1 
feet. 
C. 
The CONTRACTOR shall perform general rough grading of all slopes such that 
they will not create a safety hazard. 
 
 
3.05 
FIELD QUALITY CONTROL 
 
A. CQA field inspection and testing will be performed under provisions of Section A01400. 
B. The CONTRACTOR’s tests and analyses of fill material shall be performed in 
accordance with ASTM D1557. 
C. The CONTRACTOR shall be responsible for quality control measures and corrective 
actions in accordance with Section A01400 and the results of CQA testing. 
D. If tests indicate Work does not meet specified requirements the CONTRACTOR shall 
Re-Work or remove Work prior to replacing and retesting Work at no cost to the 
OWNER. 
 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. Separate measurements or payment will not be made for work required under this 
Section.  All costs in connection with the work specified herein will be considered 
incidental to the Project. 
 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02222 - 1 of 3 
SECTION B02222 
EXCAVATION 
 
 
1.0 
GENERAL 
 
1.01 
LOCAL BORROW 
 
A. 
The north cell excavation is located between the active landfill and Northern 
Avenue.  The excavation was previously mined for aggregate, and the existing cut 
slopes are near vertical.  The OWNER has completed a limited geotechnical 
investigation consisting of exploratory test borings, soil sampling. This information 
is included in Appendix A. 
 
B. 
It is estimated that approximately 50% of the material to be excavated will be fine 
grained (fines sands, silts and clays) and will be acceptable for construction of 
Engineered Fill.  The ENGINEER will determine in the field during excavation 
which materials are classified as fine grained to be used as Engineered Fill.  The 
CONTRACTOR will be required to screen Engineered Fill materials containing 
rocks greater than 6-inches in diameter as part of this Contract. 
 
C. 
The CONTRACTOR shall haul coarse grained materials (gravel) to the stockpiles 
or for the Landfill’s use as daily cover. 
 
 
2.0 
PRODUCTS 
 
NOT USED 
 
3.0 
EXECUTION 
 
3.01 
OVER EXCAVATION 
 
The CONTRACTOR shall take care not to excavate below the depth indicated on the 
Contract Drawings.  Unauthorized excavation below specified grade lines shall be refilled 
at the CONTRACTOR’S expense with clean soil material per Section B02223.  The 
CONTRACTOR will not be paid for amount of material over excavated or for backfilling 
over excavated areas.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02222 - 2 of 3 
3.02 
EXCAVATION 
 
A. 
The CONTRACTOR shall, during excavation, uniformly moisture condition and 
remove materials in an orderly manner.  Material with excessive or inadequate 
moisture content shall not be considered suitable for proper compaction.  The 
CONTRACTOR, at his own expense, shall remove or add moisture to material 
being excavated to bring it within a range of ±2 percent of the optimum moisture 
content.  Where tests indicate that moisture content of the material being excavated 
is below the Project requirements, the moisture content of the material shall be 
adjusted by the CONTRACTOR and retested.  No material will be excavated and 
hauled to stockpile locations until it meets the moisture content requirements of 
these Specifications to the satisfaction of the ENGINEER. 
 
B. 
Where work is interrupted by heavy rains, fill operations shall not be resumed until 
observations and field tests by the ENGINEER indicate the moisture content of the 
materials being excavated are within the limits previously specified.  This 
requirement does not preclude the CONTRACTOR from disking or aerating 
excessively wet areas to enhance drying. 
 
C. 
Throughout construction, all excavation areas shall be graded to provide positive 
drainage to appropriate detention basins or drainage structures to prevent ponding 
of water.  Surface water shall be controlled to avoid damage to adjoining properties 
or to finished work on the Site.  The CONTRACTOR shall assume all responsibility 
for surface water damage to completed work or adjoining properties arising from 
the CONTRACTOR’S work. 
 
D. 
The CONTRACTOR shall inspect the condition of all existing slopes prior to bid 
to determine the extent of remedial work necessary to construct the slopes shown 
on the Contract Drawings.  The submission of a bid will be considered proof that 
the bidder has examined the Site and understands the conditions to be encountered 
in performing the Work.  The CONTRACTOR shall use material from the north 
area excavation to complete the required remedial slope fills.  The CONTRACTOR 
will be responsible for the stability and safety of the existing slopes during remedial 
slope filling. 
 
E. 
The CONTRACTOR shall not haul any material excavated from the north area 
excavation to locations other than General or Engineered Fill areas shown on the 
Drawings or the stockpile locations shown on the Contract Drawings, unless 
otherwise directed by the ENGINEER.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02222 - 3 of 3 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not specifically 
listed in Section A01025 will be considered incidental to the Project.  The 
CONTRACTOR will not be compensated for Work not specifically listed in 
Section A01025. 
 
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 1 of 8 
SECTION B02223 
BACKFILLING 
 
1.0 
GENERAL 
 
1.01 
SUMMARY DESCRIPTION 
 
A. 
This Section describes the general requirements for subgrade preparation, 
backfill placement, and structural fill. 
 
1.02 
RELATED WORK SPECIFIED ELSEWHERE 
 
A. 
Section B02211 – Grading 
B. 
Section B02222 – Excavation 
 
1.03 
REFERENCES 
 
A. 
American Society for Testing and Materials (ASTM): 
 
1. 
D 422 
Method for Particle-Size Analysis for Soils 
2. 
D 854 
Test Method for Specific Gravity of Soils 
3. 
D 1556 
Test Method for Density of Soil in Place by the Sand-Cone 
Method 
4. 
D 1557 
Test Methods for Moisture-Density Relations of Soils and 
Soil-Aggregate Mixture Using 10-lb (4.54 kg) Rammer 
and 30-in. (457 mm) Drop 
5. 
D 3034 
Standard Test Method for Permeability of Granular Soils 
(Constant Head) 
6. 
D 2850 
Test 
Methods 
for 
Unconsolidated, 
Undrained 
Compressive Strength of Cohesive Soils in Triaxial 
Compression 
7. 
D 3087 
Classifications of Soils for Engineering Purposes 
8. 
D 2922 
Test Methods for Density of Soil and Soil-Aggregate in 
Place by Nuclear Methods (Shallow Depth) 
9. 
D 2937 
Test Methods for Density of Soil in Place by the 
Drive-Cylinder Method 
10. D 3017 
Test Methods for Moisture Content of Soil and Soil-
Aggregate Mixtures.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 2 of 8 
11. D 4330 
Test Method for Liquid Limit, Plastic Limit, and Plasticity 
Index of Soils 
12. D 4643 
Test Method for Determination of Water (Moisture) 
Content of Soil by the Microwave Oven Method 
 
B. 
United States Environmental Protection Agency (USEPA): 
 
 
 
1. 
USEPA Test Method 9100 
 
1.04 
GENERAL REQUIREMENTS 
 
A. 
The CONTRACTOR shall be solely responsible for the safety of temporary 
cuts and fills. 
B. 
The CONTRACTOR shall, except as otherwise required by Engineer or 
Specifications, maintain the finished surface or subgrade adjacent to or 
forming the foundation for backfill within normal industry tolerance for the 
specific Work. 
C. 
The CONTRACTOR shall use equipment, tools, and machines to perform 
the Work in accordance with requirements covered by the Specifications.  
The CONTRACTOR shall maintain equipment, tool and machines in 
satisfactory working condition.  Compaction equipment shall be suitable for 
the soils to be compacted so as to consistently produce the required 
strengths throughout the compacted soil mass as required by the 
Specifications. 
D. 
The CONTRACTOR shall exclusively use excavated materials for 
structural fill. 
E. 
The CONTRACTOR shall grade and restore areas disturbed in any manner 
not required for completion of the Work during construction and restore 
disturbed areas to their original grade and profile. 
F. 
The CONTRACTOR shall conduct work to reduce erosion/sedimentation 
to as little as possible and shall provide temporary erosion control as 
required. 
G. 
The CONTRACTOR is responsible for quality control measures for 
conducting the Work and corrective actions required by CQA testing and 
inspection.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 3 of 8 
1.05 
PERFORMANCE REQUIREMENTS 
 
A. 
The daily and intermediate cover stockpiles shall at a nominal 85% of 
Modified Proctor in accordance with ASTM D1557. 
 
 
1.06 
QUALITY CONTROL 
 
A. 
General 
 
1. 
CQA observation, sampling and testing will be performed by the 
ENGINEER to confirm that materials and construction are in 
compliance with the requirements of the Contract Documents in 
accordance with Section 01400. 
 
2. 
The CONTRACTOR shall implement the necessary quality control 
measures for earthwork preparation, excavation, backfill, and 
compaction of the Work. 
 
B. 
Laboratory Test Methods 
 
1. 
It shall be the responsibility of the CQA Engineer to perform any 
laboratory tests on the soils being excavated by the CONTRACTOR.  
The CONTRACTOR shall perform laboratory Quality Control testing 
in accordance with the approved Quality Control Plan.  
 
C. 
Field Test Methods 
 
1. 
It shall be the responsibility of the CQA Engineer to perform 
Construction Quality Assurance field testing.  The CONTRACTOR 
shall perform field Quality Control testing in accordance with the 
approved Quality Control Plan. 
 
1.07 
SUBMITTALS 
 
A. 
The CONTRACTOR shall submit for the ENGINEER’s review, 
specifications of the equipment proposed for the excavation, hauling and 
compaction and its application at least 15 days before commencing each 
application. 
 
B. 
Verification shall also be made after the first month of operation that the 
equipment proposed is of sufficient size and quantity to accomplish the 
work within the term of the Contract.

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 4 of 8 
 
1.08 
ENGINEERED FILL AREAS 
 
A. 
Areas of Engineered Fill shall be remedial slope fills, and any other areas 
so designated by the ENGINEER. 
 
1.09 
STRUCTURES 
 
A. 
Structures shall be defined as improvements such as soil stockpiles, 
drainage ditches, piping, and culverts. 
 
2.0 
PRODUCTS 
 
2.01  RIPRAP 
 
A. Riprap shall be obtained from off-site sources selected by the CONTRACTOR 
and shall be approved by the ENGINEER. The riprap shall be hard, durable, 
angular to sub-rounded in shape; resistant to weathering and to water action; 
free from overburden, spoil, and organic material; and shall meet the gradation 
requirements for the size specified. Rounded shaped stone such as “river rock” 
shall not be acceptable for use as riprap material. Neither the width nor 
thickness of a single stone should be less than one-third its length. Not more 
than 25 percent of the stone reasonably distributed throughout the gradation 
shall have a length of more than 2.5 times the width or thickness. The minimum 
unit weight of the stone shall be 157 pounds per cubic foot. 
 
B. The gradation requirements for 6-inch riprap are as follows: 
 
TABLE B02223-1 
RIPRAP GRADATION 
 
Stone Size 
for 6-in 
riprap 
(in inches) 
Percent Total Weight Smaller 
(than the Given Size) 
12 
100-90 
9 
85-70 
6 
50-30 
4 
15-5 
2 
5-0

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 5 of 8 
3.0 
EXECUTION 
 
3.01 
PREPARATION FOR FILL PLACEMENT 
 
A. 
Before placing fill materials, the CONTRACTOR shall prepare the Work 
area by clearing existing obstructions, vegetation, and debris.  Unsuitable 
material shall be removed where directed. 
B. 
The CONTRACTOR shall maintain proper and adequate surface drainage 
to the satisfaction of the ENGINEER in order to keep the Site dry and in 
such condition that placement and compaction of fill may proceed 
unhindered by saturation of the Work area. 
C. 
The CONTRACTOR shall proof roll existing surfaces in the presence of the 
ENGINEER prior to fill placement.  Proof rolling shall be performed with 
available heavy construction equipment of not less than 10-ton wheel load.  
Soft or unstable areas shall be removed and replaced with suitable materials 
as directed by the ENGINEER and recompacted.  Rock subgrades exposed 
during grading shall be observed by the ENGINEER and repaired for voids, 
cracks or other weaknesses as directed by the ENGINEER. 
D. 
Except as noted on the Contract Drawings or as required by the 
ENGINEER, sloped ground surfaces steeper than one vertical to 5 
horizontal, on structural fill on which structures are constructed, shall be cut 
to form benches as the Work is brought up in layers. 
 
3.02 
MATERIAL PROCESSING 
 
A. 
All soil materials to be utilized for construction of the remedial slope fills 
shall be processed in the excavation area before transporting the material to 
the fill locations except for minor adjustments to be made in moisture 
content specified in the construction method.  The processing of the soil 
materials shall involve the following tasks: 
• 
Water content adjustment; 
• 
Removal of oversized material (boulders averaging more than 6” in 
diameter); 
• 
Reduction or pulverization of clay clods; and 
• 
Mixing of soil. 
 
The ENGINEER may observe, periodically test, and document processing 
of the material.  The ENGINEER shall perform visual classification of soils 
by utilizing field tests such as dry strength, fines content, toughness tests 
(ASTM D2488) and perform fines content (ASTM D1140), moisture 
content with calcium carbide (ASTM D4944) or nuclear gauge (ASTM 
D3017) or microwave method (ASTM D4643).

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 6 of 8 
B. 
Due to the climatic conditions in Glendale, Arizona, it will be necessary for 
the CONTRACTOR to process the material before placement so that the 
moisture content remains at the target or within the specified range, the 
consistency of the soil is uniform, and the amount of clods are minimal. 
 
3.03 
GENERAL REQUIREMENTS FOR BACKFILLS 
 
A. 
The CONTRACTOR shall obtain fill materials from the required 
excavation.  Materials shall be free of objectionable material, with no stone 
dimension greater than as specified by material type.   
B. 
The CONTRACTOR shall not operate heavy equipment over pipes and 
buried structures until at least 1.5 feet of fill material has been placed and 
compacted over the top in conformance with the requirements specified 
herein, or as directed by the ENGINEER.  The CONTRACTOR shall select 
and operate compaction equipment so that structures are not damaged nor 
over stressed during compaction operations.  The CONTRACTOR shall use 
hand-operated mechanical tampers for compaction of fill material adjacent 
to structures where rolling equipment is impractical for use in compaction. 
C. 
The CONTRACTOR shall place fill materials in horizontal layers not 
exceeding the allowable lift thickness and which, after compaction, meet or 
exceed established compaction requirements.  The CONTRACTOR shall 
place material containing stones in a manner to prevent segregation of the 
material and to prevent the formation of rock nests and voids in the fill. 
D. 
The CONTRACTOR shall place and compact fill materials while at their 
required water content. 
E. 
The CONTRACTOR shall provide general fill to lines, grades, and 
elevations as shown on the Contract Drawings or as required in writing by 
the OWNER or ENGINEER. 
F. 
The CONTRACTOR shall place material in continuous layers not 
exceeding the required loose condition depth unless otherwise directed or 
approved.  The cross fall of each layer shall not exceed one foot in 20 feet. 
G. 
The CONTRACTOR shall backfill systematically, as early as possible, to 
allow maximum time for natural settlement.  The CONTRACTOR shall not 
backfill over porous, wet, or spongy subgrade surfaces. 
H. 
The CONTRACTOR shall make changes in grade gradual and blend slopes 
into level areas. 
I. 
The CONTRACTOR shall compact each layer with a sufficient number of 
passes of the soil compactor.  The number of passes shall be determined 
such that in the opinion of ENGINEER, sufficient compaction has been 
obtained. 
J. 
Soils which cannot be placed and compacted to the criteria indicated in the

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 7 of 8 
Specifications due to excessive moisture content should be air dried for a 
sufficient amount of time such that they may be placed and compacted to 
meet the criteria or removed and replaced. 
K. 
In the event of a failing test, supplemental testing shall be performed prior 
to placing additional fill in order to define the area that has been 
inadequately compacted.  The area shall be reworked and/or removed and 
replaced, then retested prior to subsequent material being placed over the 
area. 
 
3.04 
REMEDIAL SLOPE FILLS 
 
A. 
The CONTRACTOR shall provide Engineered Fill to lines, grades and 
elevations as shown on the Contract Drawings and as approved by the 
ENGINEER. 
B. 
The CONTRACTOR shall place the processed soil materials in 
approximately ten-inch loose lifts to produce a compacted lift thickness of 
approximately eight inches.  The CONTRACTOR shall compact each lift 
to meet the requirements specified herein. 
C. 
Compaction shall be performed with appropriate equipment capable of 
providing compactive forces commensurate with the densities required. 
D. 
Engineered fill materials are to be compacted to at least 90 percent 
compaction as specified by ASTM D 1557 unless otherwise specified or 
approved by the ENGINEER. 
E. 
Moisture content shall be maintained uniform throughout and within the 
limits of ±2 percent of optimum moisture content. 
F. 
The maximum compacted lift thickness shall be 8”. 
G. 
The CONTRACTOR shall separate/segregate fine grained and course 
grained materials as directed by the ENGINEER.  Fine grained materials 
will be used for remedial slope fills. 
H. 
Where work is interrupted by rains, fill operations shall not be resumed until 
observations and field tests by the ENGINEER indicate that the moisture 
content and density of the in-place fills are within specified limits. 
I. 
Unless otherwise specified by the ENGINEER, no permanent cut slopes 
shall be excavated steeper than allowed by the ENGINEER, the OWNER 
or the Regulator. 
 
3.05 
UNSUITABLE MATERIALS 
 
A. 
Unsuitable material encountered below the natural ground surface in fill 
areas or below the grading plane in excavation areas shall be excavated and

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
SECTION B02223 - 8 of 8 
disposed of as directed by the ENGINEER.  Unsuitable material is defined 
as material the ENGINEER determines to be one of the following: 
 
1. 
Of such unstable nature as to be incapable of being compacted to 
specified density using ordinary methods at optimum moisture 
content; 
2. 
Too wet to be properly compacted and circumstances prevent 
suitable in-place drying prior to incorporation into the Work; or 
3. 
Otherwise unsuitable for the planned use. 
 
The presence of excessive moisture in a material is not, by itself, sufficient 
cause for determining that the material is unsuitable. 
B. 
When unsuitable material is removed and disposed of, the resulting space 
shall be filled with material suitable for the planned use.  Such suitable 
material shall be placed and compacted in layers as herein specified 
C. 
The CONTRACTOR shall dispose of foreign materials, rubble, abandoned 
construction waste, and material that is unacceptable to the ENGINEER for 
fill in accordance with local regulations. 
D. 
The CONTRACTOR shall grade temporary waste holding areas to maintain 
a natural appearing variable percentage slope and to prevent slope failures. 
 
3.06 
TEMPORARY DRAINAGE 
 
A. 
The CONTRACTOR shall be responsible for constructing, operating and 
maintaining temporary drainage systems while construction occurs prior to 
the permanent drainage system being constructed and operational.  
Temporary drainage systems shall be required to handle existing drainage 
and the revised drainage patterns as they occur during construction.  
Temporary drainage systems shall not impact the ability to construct 
permanent drainage systems.  The CONTRACTOR shall be solely 
responsible for repairing/replacing appurtenances and/or Work damaged 
due to inadequate stormwater management during construction at no cost to 
the OWNER. 
 
4.0 
MEASUREMENT AND PAYMENT 
 
A. 
All costs in connection with the Work specified herein that are not 
specifically listed in Section A01025 will be considered incidental to the 
Project.  The CONTRACTOR will not be compensated for Work not 
specifically listed in Section A01025.  
END OF SECTION

CITY OF GLENDALE – GLENDALE LANDFILL 
NORTH CELL PHASE 2B EXCAVATION, HAUL, AND STOCKPILE PROJECT 
 
 
 
 
APPENDIX A 
 
NORTH CELL GEOTECHNICAL INFORMATION

OF
SHT.
602.263.1100
Blue Stakes Center
CALL COLLECT
CALL FOR THE BLUE STAKES
Two Working Days Before You Dig
REVISION DATE:
FILE NAME:
AUTOCAD VER.:
PLOTTING DATE:
04-18-2023
2018
Glendale Landfill North Cell
Phase 2B Excavation
COG CIP #212261.1
623.930.2940
c.o.g. traffic control
72 Hours Before start of constuction
5
CITY OF GLENDALE
MCL
RTL
MCL
SHT. #
SHEET INDEX
CITY OF GLENDALE
GLENDALE, ARIZONA
COG CIP #212261.1
Glendale Landfill North Cell
Phase 2B Excavation
11480 W. Glendale Ave
MAYOR
CITY COUNCIL
JERRY P. WEIERS
RAY MALNAR
JOYCE V. CLARK
LAUREN TOLMACHOFF
BART TURNER
IAN HUGH
JAMIE ALDAMA
CITY CLERK
CITY ATTORNEY
JULIE K. BOWER
MICHAEL D. BAILEY
CITY MANAGER
KEVIN R. PHELPS
PINNACLE PEAK RD.
DEER VALLEY RD.
BEARDSLEY RD.
UNION HILLS DR.
BELL RD.
GREENWAY RD.
THUNDERBIRD RD.
CACTUS RD
PEORIA AVE.
OLIVE AVE.
NORTHERN AVE.
GLENDALE AVE.
BETHANY HOME RD.
CAMELBACK RD.
GRAND AVE.
115TH AVE
107TH AVE.
99TH AVE.
91ST AVE.
83RD AVE.
75TH AVE.
67TH AVE.
59TH AVE.
51ST AVE.
43RD AVE.
VICINITY      MAP
KEY      MAP
EL MIRAGE RD.
SARIVAL AVE.
REEMS RD.
BULLARD AVE.
LITCHFIELD RD.
DYSART RD.
SITE
1
COVER SHEET
CONTRACT COPY ONLY 
SIGNED APPROVAL PRIOR TO CONSTRUCTION

15%
OF
SHT.
602.263.1100
Blue Stakes Center
CALL COLLECT
CALL FOR THE BLUE STAKES
Two Working Days Before You Dig
REVISION DATE:
FILE NAME:
AUTOCAD VER.:
PLOTTING DATE:
04-18-2023
2018
Glendale Landfill North Cell
Phase 2B Excavation
COG CIP #212261.1
623.930.2940
c.o.g. traffic control
72 Hours Before start of constuction
5
CITY OF GLENDALE
MCL
RTL
MCL
0
GRAPHIC SCALE:1''=
100'
300'
300'
600'
Plan View
2
 TEL 602.267.0336 FAX 602.267.0446
22601 N. 19th Avenue, Suite 225
Phoenix, AZ 85027
BAS

15%
970
980
950
960
970
980
990
1000
940
2:1
950
990
1000
1010
930
940
950
2:1
PHASE 1 (EXISTING)
PHASE 2
960
950
1010
2%
2%
1020
RIP RAP DOWNDRAIN
(NIC)
STORMWATER DIVERSION
BERM (NIC)
EDGE OF FUTURE PHASE 2 LINER
EDGE OF PHASE 1 LINER
1030
MRF STOCKPILE (SHEET 4)
15%
OF
SHT.
602.263.1100
Blue Stakes Center
CALL COLLECT
CALL FOR THE BLUE STAKES
Two Working Days Before You Dig
REVISION DATE:
FILE NAME:
AUTOCAD VER.:
PLOTTING DATE:
04-18-2023
2018
Glendale Landfill North Cell
Phase 2B Excavation
COG CIP #212261.1
623.930.2940
c.o.g. traffic control
72 Hours Before start of constuction
5
CITY OF GLENDALE
MCL
RTL
MCL
0
GRAPHIC SCALE:1''=
50'
100'
100'
200'
North Cell Excavation Plan
3
 TEL 602.267.0336 FAX 602.267.0446
22601 N. 19th Avenue, Suite 225
Phoenix, AZ 85027
BAS

15%
RIPRAP CHANNEL
(NIC)
0.5%
2:1
2:1
1050
1060
1070
1040
1078
D50 = 6" RIPRAP DOWNDRAIN
(NIC)
PERIMETER CHANNEL
(NIC)
0.5%
CULVERT INLET
N: 927154.87
E: 580888.55
ELEV. 1024'
(NIC)
CULVERT OUTLET
N: 927059.27
E: 580888.37
ELEV. 1023.5'
(NIC)
2x30" CSP PIPE, 14 GA.
(NIC)
2x12" CSP PIPE, 14 GA.
AND HEADWALL
(NIC)
1079
1079
1076
2:1
1078
1080
.3%
.3%
.3%
.3%
.3%
6%
RIPRAP CHANNEL
(NIC)
CLOSE OFF CULVERT ENTRANCE AND EXIT
AND ABANDON CULVERT IN PLACE
(NIC)
2 FT STORMWATER DIVERSION BERM
(NIC)
OF
SHT.
602.263.1100
Blue Stakes Center
CALL COLLECT
CALL FOR THE BLUE STAKES
Two Working Days Before You Dig
REVISION DATE:
FILE NAME:
AUTOCAD VER.:
PLOTTING DATE:
04-18-2023
2018
Glendale Landfill North Cell
Phase 2B Excavation
COG CIP #212261.1
623.930.2940
c.o.g. traffic control
72 Hours Before start of constuction
5
CITY OF GLENDALE
MCL
RTL
MCL
0
GRAPHIC SCALE:1''=
30'
60'
60'
120'
MRF Stockpile Plan
4
 TEL 602.267.0336 FAX 602.267.0446
22601 N. 19th Avenue, Suite 225
Phoenix, AZ 85027
BAS

EXISTING PERIMETER ROAD -
TOP OF EXISTING
STORMWATER LEVEE
DISTANCE VARIES TO MEET EXISTING GRADE
2' OFFSET
20'
16' CHANNEL
2
1
1
2
8' ACCESS ROAD
S=2%
8'
3
1
1
2
SOIL STOCKPILE
2'
OF
SHT.
602.263.1100
Blue Stakes Center
CALL COLLECT
CALL FOR THE BLUE STAKES
Two Working Days Before You Dig
REVISION DATE:
FILE NAME:
AUTOCAD VER.:
PLOTTING DATE:
04-18-2023
2018
Glendale Landfill North Cell
Phase 2B Excavation
COG CIP #212261.1
623.930.2940
c.o.g. traffic control
72 Hours Before start of constuction
5
CITY OF GLENDALE
MCL
RTL
MCL
NTS
1
TYPICAL MRF STOCKPILE PERIMETER CROSS SECTION (NIC)
REFERENCE SHEET 4
Details
5
 TEL 602.267.0336 FAX 602.267.0446
22601 N. 19th Avenue, Suite 225
Phoenix, AZ 85027
BAS
NTS
3
NTS
MAG STANDARD 501-4 HEADWALL IRRIGATION (NIC)
REFERENCE SHEET 4
4
NTS
RIP-RAP DOWNDRAIN (NIC)
REFERENCE SHEETS 3 & 4
5
NTS
STORMWATER BERM (NIC)
REFERENCE SHEET 3
1
1
1
1
VARIES
2'
10'
2' MIN.
1'
*NOTE:
ARMOR BERM AT DOWNDRAIN OUTLET
1
2
1
2
2
1
2'
4'
4'
1
VARIES
16' CHANNEL
2
1
1
2
8'
2'
NTS
2
MRF STOCKPILE RIP RAP CHANNEL (NIC)
REFERENCE SHEET 4
1
2