PowerPoint Presentation

City of Glendale — Regular Meeting (2023-08-22)

View PDF Item 4 Meeting page

Extracted text (via pymupdf) 1070 characters
Update #14: Downtown Campus 
Reinvestment Project
City Council Workshop
August 22, 2023
Presenter: Kevin Phelps

Continuity of Operations
2
Adult Center
Civic Center Campus
GRPSTC
Airport
Sine Bldg.
Media Center

3
Continuity of Operations Status
Planning
Design
Construction
*Move In
Sine Building – Mar.  ‘22 thru Dec.‘22
Jan.
Media Center – June ‘22 thru June ‘23
*July
Adult Center – May ‘22 thru April ‘23
*May-June
GRPSTC – May ‘22 thru Dec. ‘22
Dec. 22
Airport – May ‘22 thru Dec. ‘22
Dec.22
Bead Museum – Aug. ‘22 thru Aug. ‘23
*Aug.
Annex – Aug. ‘22 thru Aug. ‘23
*Aug.

Media Center
4
Budget
$415,450
Scope
Minor tenant improvements
Schedule
Complete
Level 3
Level 2

Bead Museum
5
Budget
$1,122,100
Revised  Feb. 14:  $2,360,700
Scope
Remodel / T.I.
Schedule
Complete

Bead Museum
6

Bead Museum
7

Annex
8
Budget 
$494,850
Revised Feb. 14:   $839,300
Scope 
T.I. to meeting room & furniture
Schedule
Complete

Annex
9

Next Steps
10
•Complete Moves - August 
•DCRP Exterior Update – September/October
•Demolition/Long Lead GMP2 Package -October

11
THANK YOU