PowerPoint Presentation
Extracted text (via pymupdf)
887 characters
Fire Station 153 Project Update Fire Station 153 Project Update 2 Staff is providing an informational update on the demolition of Fire Station 153 and the construction of a new station at the same location. Fire Station 153 Project Update 3 Dailey Street 59th Avenue Fire Station 153 Project Update 4 Site Plan Dailey Street 59th Avenue 11,800 Sq.Ft. Fuel Station Fire Station 153 Project Update 5 Floor Plan - Zones Fire Station 153 Project Update 6 Floor Plan Fire Station 153 Project Update 7 Fire Station 153 Project Update 8 Fire Station 153 Project Update 9 Fire Station 153 Project Update 10 • Timeline – Guaranteed Maximum Price (GMP) November 28, 2023, voting meeting – Mid-January 2024 to start installing temporary facilities – Late January 2024 to start demolition – Project completion May/June 2025 Fire Station 153 Project Update 11 Thank you!