Fire Station 153 Project Update

Fire Station 153 Project Update
2
Staff is providing an informational update on the 
demolition of Fire Station 153 and the 
construction of a new station at the same location.

Fire Station 153 Project Update
3
Dailey Street
59th Avenue

Fire Station 153 Project Update
4
Site Plan
Dailey Street
59th Avenue
11,800 Sq.Ft.
Fuel Station

Fire Station 153 Project Update
5
Floor Plan - Zones

Fire Station 153 Project Update
6
Floor Plan

Fire Station 153 Project Update
7

Fire Station 153 Project Update
8

Fire Station 153 Project Update
9

Fire Station 153 Project Update
10
• Timeline
– Guaranteed Maximum Price (GMP) November 28, 
2023, voting meeting
– Mid-January 2024 to start installing temporary 
facilities
– Late January 2024 to start demolition
– Project completion May/June 2025

Fire Station 153 Project Update
11
 
 
 
 
 
 
 
 
Thank you!