1
05/10/2023
C23-0278-1
AMENDMENT NO. 1
Arterial Reconstruction of 51st Avenue from Olive Avenue to Cactus Road
(Project Nos. 202112 & 202113, Contract No. C23-0278-1)
This Amendment No. 1 (“Amendment”) to the Professional Services Agreement (“Agreement”) is
made this ______ day of ________, 2023, (“Effective Date”), by and between the City of Glendale,
an Arizona municipal corporation (“City”) and Ardurra Group, Inc., a Florida Corporation, authorized
to do business in Arizona (“Contractor”).
RECITALS
A.
City and Ardurra Group, Inc. (“Contractor”) previously entered into Professional Services
Agreement, Contract No. C23-0278, dated March 14, 2023 (“Agreement”); and
B.
City and Consultant wish to modify and amend the Agreement subject to and strictly in
accordance with the terms of this Amendment.
AGREEMENT
In consideration of the mutual promises set forth herein and other good and valuable consideration,
the receipt and sufficiency of which are hereby acknowledged, the City and Contractor hereby agree
as follows:
1.
Recitals. The recitals set forth above are not merely recitals, but form an integral part of this
Amendment.
2.
Term. The term of the Agreement is unchanged and shall expire on March 14, 2024.
3.
Scope of Work. This amendment includes providing the design and pothoing for all of the
ADA improvements along the roadway for the design phase of the project.
4.
Compensation. The compensation for this Agreement will increase by $158,810.00, for a
new not to exceed amount of $253,375.
5.
Insurance Certificate. Current certificate will expire on June 30, 2024 and a new certificate
applying to the extended term must be provided prior to this date to Materials Management
and the Contract Administrator.
6.
Non-discrimination. Contractor must not discriminate against any employee or applicant
for employment on the basis of race, color, religion, sex, national origin, age, marital status,
sexual orientation, gender identity or expression, genetic characteristics, familial status, U.S.
military veteran status or any disability. Contractor will require any Sub-contractor to be bound
to the same requirements as stated within this section. Contractor, and on behalf of any
subcontractors, warrants compliance with this section.
7.
No Boycott of Israel. To the extent A.R.S § 35-393 through § 35-393.03 are applicable, the
parties hereby certify that they are not currently engaged in, and agree for the duration of the
2
05/10/2023
Agreement to not engage in, a boycott of goods or services from Israel, as that term is defined
in A.R.S § 35-393.
8.
Uyghur Forced Labor Prevention Act (UFLPA). Contractor certifies that it does not
currently, and during the term of this Agreement, will not use:
(a)
the forced labor of ethnic Uyghurs in the People’s Republic of China;
(b)
any goods or services produced by the forced labor of ethnic Uyghurs in the People’s
Republic of China; and
(c)
any contractors, subcontractors or suppliers that use the forced labor or any goods or
services produced by the forced labor of ethnic Uyghurs in the People’s Republic of
China.
9.
Attestation of PCI Compliance. When applicable, the Contractor will provide the City
annually with a Payment Card Industry Data Security Standard (PCI DSS) attestation of
compliance certificate signed by an officer of Contractor with oversight responsibility.
10.
Ratification of Agreement. City and Contractor hereby agree that except as expressly
provided herein, the provisions of the Agreement shall be, and remain in full force and effect
and that if any provision of this Amendment conflicts with the Agreement, then the provisions
of this Amendment shall prevail.
[Signatures on the following page.]
City of Glendale Arterial Concrete Reconstruction Program
Task 1A - 51st Ave. (Olive Ave. to Peoria Ave.)
Task 1B – 51st Ave. (Peoria Ave. to Cactus Rd.)
COG Project Nos: Task 1A (202112) & Task 1B (202113)
City of Glendale (City) requested Ardurra prepare sealed sheets for ADA ramp sidewalk and curb
replacements not included in existing contract scope. City provided Adobe pdf with photos and notes
for each of the replacement locations and requested Ardurra prepare/submit contract modification.
Ardurra’s scope of work for the survey and final design services is described in the following tasks:
Project Administration and Progress Meetings
1. Project Meetings: Ardurra will schedule with City Project Manager (PM), representatives and
stakeholders, conduct, and prepare and distribute agenda and minutes for:
a. Kickoff/Strategy Meeting (1): The meeting will overview Ardurra’s project schedule to
complete survey and prepare construction documents.
b. Progress Meetings (3): Meetings will overview and discuss design progress, project’s
technical aspects and action item resolution status.
c. Comment Resolution Meetings (2): Meetings will overview and discuss design progress,
project’s technical aspects and action item resolution status.
2. Project Schedule: Ardurra will prepare, submit, and revise design schedule reflecting NTP,
major design activities, submittal milestones, and anticipated completion dates. Updated
schedule showing completed and in-progress tasks with each monthly invoice.
3. Project Administration: Ardurra will:
a. Perform accounting functions to establish project tasks, subtasks, and billing rates to match
executed contracts.
b. Submit monthly invoice, progress report, and cash flow schedule.
Topographic Survey & Base Mapping
1. Horizontal and vertical control: Ardurra will re-establish and verify project control using NAD 83
Arizona State Plane Central Zone Coordinates and City of Glendale NAVD88 benchmarks.
2. Data Collection: Ardurra will collect supplemental survey of roadway and sidewalk features
including curb, gutter, sidewalk ramps at (53) locations attached to City’s 8/17/23 email.
3. Base Mapping: Ardurra will incorporate supplemental survey and topographic data into existing
AutoCad file of existing surface features.
Design & Plan Production
1. Scoping/Predesign: Ardurra will prepare an Initial and Final Scoping Document. The Scoping
Document will confirm project limits, provide 60% design plans that identify concrete
reconstruction areas.
2. Final Design: Ardurra will:
a. Prepare construction documents in accordance with most current City of Glendale Project
Development Guidelines, MAG Standard Specifications and Details as amended by the City
of Glendale, and other standards such as AASHTO, MUTCD and ASTM.
b. Perform horizontal and vertical calculations to establish concrete replacement locations and
elevations.
c. Prepare ADA compliant details for sidewalk ramps at twenty-one (21) locations
3. Drainage Evaluation: No additional scope resulting from this contract modification.
4. Construction Plans: Ardurra will update current 90% road plans to reflect the concrete sidewalk,
curb/gutter and sidewalk ramp replacement locations and prepare ADA compliant ramp
replacement details. Revised/updated plan sets will be with 60%, 100%, and sealed construction
plans (24” X 36") using AutoCAD Civil 3D (2020) at a scale of 1”=40’ Horizontal and 1”=4’
Vertical. Current set of plans will be added/supplemented as follows:
a. Cover (1 sheet)
b. General Notes and Legend (1 sheet)
c. Geometric Control (2 sheet)
d. Plan/profile sheets (sheet quantity depends on sidewalk and curb replacement locations)
e. ADA ramp details (6 sheets)
Opinion of Probable Cost (OPC) and Special Provisions
1. Prepare and include OPC to update existing OPC with the 60%,100% and sealed submittals.
2. Prepare and include Special Provisions to update existing with the 60%, 100% and sealed
submittals.
a. It is anticipated Special Provisions will be “performance” based description of contractor’s
requirements. Special Provision will describe material, installation and product acceptance
requirements for asphalt pavement, sidewalk, curb/gutter/aprons, ADA ramps, associated
allowances, and pedestrian push button poles.
Allowance: Potholing
1. Ardurra will, after receiving City approval, pothole per a mutually agreed upon plan.
FEE SCHEDULE
FEE SUMMARY
TASK
Description
Fee
1.0
Meetings & Project Management
$10,415.00
2.0
Survey
$27,490.00
3.0
Specifications
$5,400.00
4.0
Pre-design
$20,810.00
5.0
Construction Plans
$56,085.00
6.0
Deliverables
$6,820.00
7.0
Opinion of Probable Cost
$11,790.00
8.0
Sub-total:
$138,810.00
Pothole Allowance
$20,000.00
Total: $158,810.00
Assumptions
1. Supplemental survey, design and preparation of construction documents concrete reconstruction
is for following fifty-three (53) locations identified in pdf attachment to City’s 8/17/23 email:
a. 51st Ave and Olive Ramp on SE corner.
b. 51st Ave and Olive Ramp on NE corner.
c. North of 51st Ave and Olive replace 15 LF of curb and gutter.
d. North of 51st Ave and Olive replace 75 LF of sidewalk.
e. North of 51st Ave and Olive replace 21.5 LF of curb and gutter.
f. North of 51st Ave and Olive replace 247.25 SF of concrete panel.
g. North of 51st Ave and Olive replace 172.5 SF of concrete and curb.
h. North of 51st Ave and Olive replace 70.5 LF of curb and gutter.
i.
North of 51st Ave driveway into Goodwill replace 52.5 LF of curb and gutter.
j.
North on 51st past Goodwill driveway replace 98 LF of curb and gutter.
k. North 51st Ave and Hatcher replace 96 SF of valley gutter.
l.
North 51st Ave and Hatcher replace 291.5 SF of apron.
m. North 51st Ave and Hatcher replace 162.5 SF of ramp.
n. North on 51st Ave past Hatcher replace 28 LF of curb and gutter.
o. North on 51st Ave between Hatcher and Vogel replace 20 LF of curb and gutter.
p. North 51st Ave and Vogel replace 96 SF of valley gutter.
q. North 51st Ave and Vogel replace 292.5 SF of apron.
r. North 51st Ave and Vogel replace 162.5 SF of ramp.
s. North 51st Ave and Mountain View replace 210 SF of ramp.
t. North 51st Ave and Mountain View replace 159 SF valley gutter.
u. North 51st Ave and Mountain View replace 537 SF of apron.
v. North 51st Ave and Onyx replace 96 SF of valley gutter.
w. North 51st Ave and Onyx replace 247 SF of apron.
x. North 51st Ave and Brown replace 163 SF of ramp.
y. North 51st Ave and Brown replace 250 SF of apron.
z. North 51st Ave and Brown replace 78 SF of valley gutter.
aa. North 51st Ave and Christy replace 96 SF of valley gutter.
bb. North 51st Ave and Christy replace 292 SF of apron.
cc. North 51st Ave and Shangri La replace 96 SF of valley gutter.
dd. North 51st Ave and Yucca replace 66 SF of gutter.
ee. South 51st Ave and Rivera replace 210 SF of ramp.
ff. South 51st Ave and Rivera replace 210 Sf of ramp.
gg. South 51st Ave and Sierra replace 8.5 LF of curb and gutter.
hh. South 51st Ave across from Petra Job replace 45 LF of curb and gutter.
ii. South 51st Ave and Beryl replace 130 SF of ramp.
jj. South 51st Ave and Beryl replace 130 SF of ramp.
kk. South 51st Ave and Brown replace 140 SF of ramp.
ll. South 51st Ave and Brown replace 140 SF of ramp.
mm.
South 51st Ave and Brown replace 96 SF of valley gutter.
nn. South 51st Ave and Cinnabar replace 140 SF of ramp.
oo. South 51st Ave and Cinnabar replace 140 SF of ramp.
pp. South 51st Ave and Mountain View replace 210 SF of ramp.
qq. South 51st Ave and Mountain View replace 210 SF of ramp.
rr. South 51st Ave and Perdue replace 135 SF of ramp.
ss. South 51st Ave and Perdue replace 135 SF of ramp.
tt. South 51st Ave and Perdue replace 237 SF of apron.
uu. South 51st Ave and Palo Verde replace 210 SF of ramp.
vv. South 51st Ave and Palo Verde replace 210 SF of ramp.
ww.
South 51st Ave and Palo Verde replace 512 SF of apron
xx. South 51st and Sanna replace 163 SF of ramp
yy. South 51st and Sanna replace 163 SF of ramp
zz. South 51st and Sanna replace 292 SF of apron
aaa.
51st and Olive NW corner replace 160 SF of ramp
2. Scope of work is for a single set of construction documents.
3. Cactus Road and 51st Avenue intersection will not be part of this project.
4. City staff will procure a TCE for the Goodwill commercial driveway work behind the sidewalk.
5. Concrete replacement will not extend beyond limits designated in City’s 8/17/23 email.
6. Design schedule is estimated to be approximately nine months (11/1/23 through 7/1/24).
Exclusions
1. Drainage analysis
2. Signing and marking plans
3. Maintenance of Traffic plans
4. Traffic signal modifications
5. SRP prior rights research, relocation coordination, easement legal descriptions
6. Public Outreach
7. SWPPP
8. Maricopa County Environmental Services (MCESD) permit application or basis of design report
9. Landscape or restoration design
10. Utility Coordination & Conflict Resolution (scope not included with existing contract)