PowerPoint Presentation
Extracted text (via pymupdf)
52726 characters
FY2025-2034 Capital Improvement Plan March 5th, 2024 Agenda 2 • ARPA Update • Capital Improvement Plan (CIP) Overview • Capital Improvement Plan Projects • Council Feedback and Questions Budget Calendar 3 Item Date Workshop #1 – Budget Overview / Revenues / Five-Year Financial Forecasts December 12, 2023 Workshop #2 – FY25-34 Capital Improvement Plan March 5, 2024 Workshop #3 – (All Day) FY25 Operating Budget Department Presentations April 2, 2024 Workshop #4 – (All Day) FY25 Operating Budget Department Presentations April 4, 2024 Workshop #5 – FY25 Budget Workshop April 16, 2024 Voting Meeting – Tentative Budget Adoption May 14, 2024 Voting Meeting – Budget Adoption / Property Tax Levy June 11, 2024 Voting Meeting – Property Tax Adoption June 25, 2024 American Rescue Plan Act (ARPA) Update ARPA Update 5 ARPA Strategy Category Budget Actual Remaining Public Health $14,768,300 $1,590,071 $13,178,229 Negative Economic Impacts $27,011,666 $12,522,012 $14,489,654 Public Health - Negative Economic Impact $11,583,444 $6,201,619 $5,381,825 Infrastructure $5,778,200 $572,889 $5,205,311 Administrative $375,000 $0 $375,000 TOTAL $59,516,610 $20,886,592 $38,630,018 ARPA Update – Actual Spending 6 ARPA Strategy - Actuals Category Project Actual Public Health Vaccination Clinics and Incentives, Additional Custodial Services, Continuity of Operations $5,640,279 Negative Economic Impacts CBR and Arena (FY22), Parks Projects (Playground Equipment Replacement) $6,312,061 Public Health - Negative Economic Impact Retention Pay, COVID Leave, Temp Pay for Recreation Staff, Referral/Hiring Bonuses $8,361,363 Infrastructure Glenn Drive Drainage Project, Parks Irrigation and Recreation Center Projects $572,889 Administrative Temporary Staff for Grant Administration $0 TOTAL $20,886,592 ARPA Update – Remaining Budget 7 ARPA Strategy – Remaining Budget Category Project Actual Public Health COVID Medical Claims, Building Improvements, IT Projects, and Library Resources $9,128,021 Negative Economic Impacts Parks, Special Event and Library Programming, Community Centers, Parks Improvements, including Playground and Lighting Improvements, Splash Pads, and Heroes Regional Park Ballfields $20,699,605 Public Health - Negative Economic Impact Retention Pay, COVID Leave, Temp Pay for Recreation Staff, and Referral/Hiring Bonuses $3,222,081 Infrastructure Parks Irrigation Projects, Community Center Improvements, and Storm Water Projects $5,205,311 Administrative Senior Account, Grant Management $375,000 TOTAL $38,630,018 ARPA Update – Changes to ARPA Projects 8 • Swapped $5.8M in ARPA Funding in the Downtown Campus Reinvestment Project (DCRP) with General Fund Capital Funding from the Heroes Regional Park Ballfields project • Moved $1.5M in ARPA Funding from the Sahuaro Ranch Park Splash Pad project to the Heroes Regional Park Ballfields project • Splash Pad will be part of the Sahuaro Ranch Park Buildout Project Capital Improvement Plan Elements of a Capital Improvement Plan 10 • Assets valued over $50,000 with a useful life of 5+ years • Land, buildings, streets & improvements, plants, large equipment • Ten-Year Plan (only FY24-25 is adopted as part of the FY24-25 budget) Financial Policy: A. Improve existing assets B. Replace existing assets as needed C. Construct new assets CIP Process 11 Staff Develops 5-year Financial Forecasts Departments work with Engineering on Project Scope and Timelines Projects are Submitted to Budget and Finance Budget and Finance Evaluates Funding Sources for Projects Draft CIP Presented to Council Council Adopts 10-Year CIP (Year 1 Appropriated) CIP Funding Sources 12 • Development Impact Fees • One-time charges to developers for new development • New or expanded infrastructure • General Obligation Bonds • Debt issuance must be authorized by Voters • Streets, Public Safety, Parks, Government Facilities, Open Space/Trails, Libraries, and Flood Control • Debt service paid by Secondary Property Tax • Grants • Federal or state grant funding • Often require a match contribution to the project • Pay-As-You-Go • Cash funded projects CIP Funding Sources 13 • Special Revenue Funds • Transportation Sales Tax • Half cent sales tax • Improve service for all modes of transportation • Highway User Revenue Funds • Restricted Special Revenue Fund • Right of Way acquisition, construction, reconstruction, maintenance, and repair • Enterprise Funds • Water/Sewer o Funding can come from G. O. Bonds, revenue bonds, revenue obligations or cash financing o Debt service paid from future water/sewer fee revenue • Landfill – paid by Landfill user fees • Solid Waste – paid by Solid Waste user fees CIP Funding Sources 14 Pay-As-You-Go Funds • 1080 – General Government Capital Projects (General Fund) • 2110 – Arts Commission General Obligation Bonds • 4010 – Streets Construction • 4040 – Public Safety Construction • 4050 – Parks Construction • 4060 – Government Facilities • 4080 – Cultural Facility • 4090 – Open Space/Trail Construction • 4100 – Library Construction • 4110 – Flood Control Construction CIP Funding Sources 15 Development Impact Fees (DIF) • 4173 – 2019 DIF – Fire • 4223 – 2014 DIF – Police • 4284 – 2019 DIF – Libraries • 4325 – 2014 DIF – Parks & Rec • 4383 – 2019 DIF – Parks & Rec • 4410 – 2014 DIF – Streets Zone 1 East • 4420 – 2014 DIF – Streets Zone 2 West • 4431 – 2019 DIF – Streets East • 4434 – 2023 DIF – Streets West • 6065 – 2014 DIF – Water • 6071 – 2019 DIF – Water • 6095 – 2014 DIF – Sewer • 6101 – 2019 DIF – Sewer CIP Funding Sources 16 Special Revenue Funds • 2050 – HURF Operating (Pavement Management) • 4020 – HURF Capital • 2070 – TST Operating (Pavement Management) • 4030 – Transportation Sales Tax Capital • 2071 – Transportation Streets in Lieu Fund (SILF) • 2200 – GRPSTC Revenue CIP Funding Sources Enterprise User Fees • 6020 – Water • 6030 – Sewer • 6110 – Landfill • 6120 – Solid Waste Grants • 2060 – Transportation Grants • 2160 – Other Grants • 2190 – Airport Capital Grants • 4610 – ARPA Capital Projects FY25-34 DRAFT CIP By Project Type 18 Streets $443.4M Water $364.8M Public Safety $276.7M Wastewater $211.0M Facility Maintenance $195.8M Parks $133.7M Parking Lots $76.5M Solid Waste $53.4M Airport $46.6M Library $42.0M Drainage $41.6M Landfill $36.5M Transit $12.7M Arts $1.0M Total FY25-34 CIP $1.94B FY25-34 DRAFT CIP by Funding Source 19 Enterprise Funds $659.3M Bond Funds $406.0M Special Revenue Funds $380.0M Pay-As-You-Go $305.7M Grants $113.3M DIF $71.1M Total FY25-34 CIP $1.94B FY24-25 DRAFT Capital Improvement Plan 20 Facility Maintenance $111.1M Streets $89.1M Parking Lots $72.0M Parks $54.6M Water $54.0M Public Safety $37.0M Wastewater $31.3M Drainage $16.3M Landfill $10.0M Library $9.5M Transit $5.9M Airport $5.1M Solid Waste $4.3M Arts $1.0M Total FY24-25 CIP $501.4M FY25-34 Draft CIP Report 21 • Change document – overall financial change in project from FY24 Adopted CIP to FY25 Draft CIP • CIP Report includes Estimated FY24 Carryover • Estimates will be updated as part of the carryover process in March/April • Final carryover will be presented as part of the Budget Workshop on April 16, 2024 22 FY25-34 Airport CIP Overview • Funded by Airport Grant Funds (87%) and Transportation Sales Tax (13%) • Projects include: • South Apron Reconstruction • Southwest Apron Capacity • Runway Rehabilitation • Parallel Taxiway B • Airport Security Fencing FY25-34 Airport by Funding Source 23 FUND FUND NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 1080 GENERAL FUND CAPITAL 26,691 26,691 2190 AIRPORT CAPITAL GRANTS 3,218,272 15,967,400 7,362,860 6,270,000 3,220,000 4,617,650 40,656,182 4030 TRANSPORTATION SALES TAX 809,865 1,038,251 388,874 403,277 418,302 433,973 2,429,855 5,922,397 TOTAL 4,054,829 1,038,251 16,356,274 7,766,137 6,688,302 3,653,973 7,047,505 46,605,271 FY25-34 Airport Projects 24 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPAP19075 NEW RIVER CHANNELIZATION EA 250,000 250,000 CIPAP19076 SOUTH APRON PHASE 1 PAVEMENT RECONS 1,814,696 1,814,969 CIPAP20001 SOUTH APRON REHABILITATION PHASE 2B 146,174 6,496,040 6,642,214 CIPAP20002 RUNWAY REHABILITATION 716,475 716,475 CIPAP20018 TAXIWAY PAVEMENT REHAB & PRESERVE 255,928 255,928 CIPAP21005 SITE SURVEY STUDY FOR CONTROL TOWER 286,590 286,590 CIPAP21007 AIRPORT MASTER PLAN STUDY 525,415 525,415 CIPAP21009 AIRPORT SECURITY FENCING 1,215,000 1,215,000 CIPAP21010 SOUTHWEST APRON – CAPACITY (DESIGN) 450,000 450,000 CIPAP21012 AIRSIDE PAVEMENT MAINTENANCE 201,136 210,376 220,895 231,939 243,537 255,713 1,483,626 2,847,221 CIPAP22001 EAST SIDE DEVELOPMENT 285,000 285,000 FY25-34 Airport Projects 25 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPAP22002 AIRPORT DESIGN STANDARDS 10,000 10,000 CIPAP22003 AIRPORT AUTO PARKING LOTS 92,217 92,217 CIPAP23046 FACILITIES AESTHETIC UPGRADE STUDY 249,120 249,120 CIPAP23071 AIRPORT FIBER PROJECT 26,691 26,691 CIPAP24006 NEW RIVER PROJECT (DESIGN) 477,650 477,650 CIPAP24007 NEW RIVER PROJECT LAND ACQUISITION 900,000 900,000 CIPAP24008 NEW RIVER CHANNELIZATION PLAN STUDY 334,355 334,355 CIPAP24009 SOUTH APRON RECONSTRUCT PHASE 3 2,070,000 2,070,000 CIPAP24010 SOUTHWEST APRON CAPACITY PHASE 1 2,070,000 2,070,000 CIPAP24011 SOUTHWEST APRON CAPACITY PHASE 2 2,970,000 2,970,000 CIPAP24012 SOUTHWEST APRON CAPACITY PHASE 3 3,240,000 3,240,000 FY25-34 Airport Projects 26 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPAP25004 ENVIRO CLEARANCE PARALLEL TAXIWAY B 286,590 286,590 CIPAP25005 RUNWAY OVERLAY 1,800,000 1,800,000 CIPAP25006 SOUTH APRON REHABILITATION PHASE 1B 2,340,000 2,340,000 CIPAP25007 PARALLEL TAXIWAY B DESIGN 573,180 573,180 CIPAP25008 RUNWAY LIGHTING & SIGNAGE REHABILITATION 900,000 900,000 CIPAP25009 TAXIWAY LIGHTING & SIGNAGE REHABILITATION 990,000 990,000 CIPAP25010 PARALLEL TAXIWAY B CONSTRUCT PHASE 1 5,063,090 5,063,090 CIPAP25011 PARALLEL TAXIWAY B CONSTRUCT PHASE2 4,200,000 4,200,000 CIPAP65078 AIRPORT MATCHING FUNDS 257,393 827,875 167,979 171,378 174,765 178,260 946,229 2,723,839 TOTAL 4,054,829 1,038,251 16,356,274 7,766,137 6,688,302 3,653,973 7,047,505 46,605,271 27 FY25-34 Arts CIP Overview • Funded by Arts Fund (100%) – 1% of Construction Completed in Current Fiscal Year on Eligible Projects • Projects include: • Municipal Arts Program • Arts Master Plan FY25-34 Arts by Funding Source 28 FUND EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 2110 – ARTS FUND 991,961 991,961 TOTAL 991,961 991,961 FY25-34 Arts Projects 29 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPAT20035 MUNICIPAL ARTS PROGRAM 891,961 891,961 CIPAT23001 ARTS MASTER PLAN 100,000 100,000 TOTAL 991,961 991,961 30 FY25-34 Drainage CIP Overview • Funded by Flood Control G. O. Bonds (61%), Grants (32%) and General Fund (7%) • Focus on Designing and Constructing Flood Control Drainage Improvements – Large project broken into stand alone packages to continue progress • Work in coordination with internal and external partners – Maricopa County Flood Control District (MCFlood) – Maximizing matching funds – Arterial Reconstruction Program (Transportation) FY25-34 Drainage by Funding Source 31 FUND EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 1080 – GENERAL FUND CIP 358,516 241,000 241,000 241,000 241,000 241,000 1,200,000 2,763,516 2160 – OTHER GRANTS 4,615,957 3,742,565 3,325,000 11,683,522 4110 – FLOOD CONTROL G. O. BONDS 5,684,610 4,211,185 4,778,000 4,148,000 4,088,000 2,534,000 25,443,795 4610 – ARPA CAPITAL PROJECTS 1,674,863 1,674,863 TOTAL 12,333,946 3,983,565 7,777,185 5,019,000 4,389,000 4,329,000 3,734,000 41,565,696 FY25-34 Drainage Projects 32 Project # Project Title EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPDR19040 CAMELBACK ROAD, 51ST TO 58TH 4,148,000 4,148,000 CIPDR19078 83RD AVE, BETHANY HM TO CAMELBACK 4,088,000 4,088,000 CIPDR19079 59TH AVE & T-BIRD RD STORM DRAIN 2,534,000 2,534,000 CIPDR21019 DRAINAGE IMP. GLENN DR. 59TH-52ND 1,674,863 188,000 1,311,000 2,158,000 5,331,863 CIPDR21034 BETHANY HOME SD 43RD to 51ST AVE 10,300,567 3,554,565 6,225,185 2,620,000 22,700,317 CIPDR79004 LOCAL DRAINAGE PROBLEMS 358,516 241,000 241,000 241,000 241,000 241,000 1,200,000 2,763,516 TOTAL 12,333,946 3,983,565 7,777,185 5,019,000 4,389,000 4,329,000 3,734,000 41,565,696 33 FY25-34 Facility Maintenance CIP Overview • Primarily Funded with General Fund (72%), G. O. Bonds (17%), Enterprise Funds (6%), Special Revenue Funds (5%) • Focus on: – Improving existing assets through programmatic replacements • Follow industry standard replacement cycles – Replacing existing assets as needed – Downtown Campus Reinvestment FY25-34 Facility Maintenance by Funding Source 34 FUND EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 1080-GENERAL FUND CIP 34,880,879 47,503,777 8,212,000 6,774,000 6,835,000 6,504,000 30,563,000 14 1,272,657 2200-TRAINING FACILITY REVENUE 218,560 218,560 4030-TRANSPORT CAPITAL 634,264 665,493 3,434,903 2,686,137 50,760 1,215,505 8,687,062 4060-GOV’T FACILITIES 12,026,429 3,550,696 3,327,562 2,602,196 57,380 1,483,060 23,047,323 4080-CULTURAL FACILITIES 2,108,379 6,121,638 8,230,017 4100-LIBRARY 1,533,017 1,533,017 4610-ARPA CAPITAL PROJECTS 507,445 507,445 6020-WATER 634,264 717,393 3,971,606 3,105,846 59,590 1,572,125 10,060,824 6120-SOLID WASTE 52,970 2,188,630 2,241,600 TOTAL 52,543,238 58,558,997 18,946,071 15,168,179 7,055,700 12,963,320 30,563,000 195,798,505 FY25-34 Facility Maintenance Projects 35 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPFC19016 GLENDALE OPS CAMPUS FIELD STAFF BLD 661,078 1,038,000 10,734,071 8,394,179 20,827,328 CIPFC19037 UNDERGROUND STORAGE TANK REPLACEMENT 1,016,521 1,016,521 CIPFC19038 CITY HALL BUILDING REMODEL 26,705,337 27,899,478 54,604,815 CIPFC19061 ELECTRICAL SYSTEM RENEWAL 209,455 370,000 370,000 370,000 370,000 370,000 1,850,000 3,909,455 CIPFC19062 ELEVATOR SYSTEM RENEWAL 425,000 425,000 640,000 640,000 425,000 65,000 2,620,000 CIPFC19063 FIRE PROTECTION RENEWAL 1,368 415,000 200,000 200,000 200,000 200,000 1,000,000 2,216,368 CIPFC19064 SECURITY CAMERA IMPROVEMENTS 89,640 781,296 870,936 CIPFC19065 PLUMBING SYSTEM RENEWAL 8,251 300,000 100,000 100,000 100,000 100,000 500,000 1,208,251 CIPFC19068 ROOFING SYSTEM RENEWAL 355,443 100,000 300,000 300,000 300,000 300,000 1,500,000 3,155,443 CIPFC19071 HVAC REPAIR / REPLACEMENTS 300,000 300,000 300,000 300,000 300,000 1,500,000 3,000,000 FY25-34 Facility Maintenance Projects 36 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPFC20023 ADULT CENTER WEST RENOVATION 44,214 44,214 CIPFC22082 CITY HALL FIRE SYSTEM REPLACEMENT 133,583 133,583 CIPFC22086 CITY HALL PARKING GARAGE 1,407,449 787,798 2,195,246 CIPFC23033 ADULT CENTER EAST RENOVATION 2,832 2,832 CIPFC23034 AIRPORT MATERIALS LAB RENOVATION 23,271 23,271 CIPFC23035 CIVIC CENTER ANNEX RENOVATION 32,945 32,945 CIPFC23037 GRPSTC SECOND FLOOR RENOVATION 53,183 53,183 CIPFC23038 MEDIA CENTER RENOVATION 181,832 181,832 CIPFC23039 SINE BLDG 2ND FLOOR EAST RENOVATION 56,378 56,378 CIPFC23040 SINE BLDG 2ND FLOOR WEST RENOVATION 60,549 60,549 FY25-34 Facility Maintenance Projects 37 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPFC23041 GLENDALE OPS CAMPUS RENOVATION 220,700 6,459,320 6,680,020 CIPFC23043 COUNCIL CHAMBERS 428,777 5,064,787 5,493,564 CIPFC23070 EXTERIOR BUILDING ENHANCEMENTS 400,000 1,300,000 1,700,000 CIPFC23074 PALMAIRE CAFÉ RENOVATION 36,205 36,205 CIPFC23076 ARENA LEASE AGREEMENT CIP 10,000,000 5,000,000 15,000,000 CIPFC24044 CAR WASH REPLACEMENT 1,740,363 1,740,363 CIPFC24045 SPRING CITY DEMOLITION 62,353 2,000,000 2,062,353 CIPFC24046 ADA PROGRAM 368,320 350,000 400,000 400,000 400,000 400,000 2,000,000 4,318,320 CIPFC24047 INTERIOR REFRESH PROGRAM 700,000 750,000 750,000 750,000 750,000 3,750,000 7,450,000 CIPFC24048 RETRO COMMISSIONING PROGRAM 75,000 75,000 75,000 75,000 75,000 375,000 750,000 FY25-34 Facility Maintenance Projects 38 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPFC24049 CEMETERY IMPROVEMENTS 125,869 400,000 500,000 250,000 150,000 1,425,869 CIPFC24051 PERFORMANCE BASED CONTRACTS 3,863,331 3,863,331 CIPFC24052 PD EVIDENCE/OPS CAMPUS FIBER 61,062 61,062 CIPFC24053 SAHUARO RANCH PARK FIBER 34,070 34,070 CIPFC24056 SYSTEM OF CARE CENTER TENANT IMPROVEMENTS 1,390,808 1,000,000 2,390,808 CIPFC24061 GRPSTC MISCELLANEOUS REPAIRS 218,560 218,560 CIPFC25001 GATES AND DOORS RENEWAL PROGRAM 250,000 300,000 300,000 300,000 300,000 1,500,000 2,950,000 CIPFC25022 BRIAN ANDERSON FIELD 1,048,000 1,048,000 CIPFC25023 HEROES PARK LIBRARY SHADE STRUCTURES 350,000 350,000 CIPFC70800 BUILDING MAINTENANCE RESERVE 739,354 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 9,000,000 18,739,354 FY25-34 Facility Maintenance Projects 39 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPFC70801 CAMELBACK RANCH MAINTENANCE RESERVE 322,458 1,583,500 1,392,000 1,289,000 1,450,000 1,484,000 7,523,000 15,043,458 CIPPK77516 AMPHITHEATER RENOVATIONS 2,108,379 6,121,638 8,230,017 TOTAL 52,543,238 58,558,997 18,946,071 15,168,179 7,055,700 12,963,320 30,565,000 195,798,505 40 FY25-34 Landfill CIP Overview • Funding Source: 100% Enterprise – User Fee Revenues • Focus On Programmed Vehicle Replacements • Follow industry standard replacement cycles • North Cell Landfill Project • North Cell Phased Construction • North Cell Liner Installation • Landfill Gas Extraction System • Stormwater Controls FY25-34 Landfill by Funding Source 41 FUND EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 6110 - LANDFILL 3,811,377 6,225,005 3,726,297 3,148,588 6,647,799 4,891,130 8,078,984 36,529,180 TOTAL 3,811,377 6,225,005 3,726,297 3,148,588 6,647,799 4,891,130 8,078,984 36,529,180 FY25-34 Landfill Projects 42 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPLF19019 LANDFILL COMPACTOR REPLACEMENT 150,000 160,000 850,000 900,000 1,821,000 1,900,000 5,781,000 CIPLF19024 BULLDOZER REPLACEMENTS & REBUILDS 174,737 340,000 160,000 100,000 1,500,000 2,727,000 5,001,737 CIPLF19025 NORTH CELL LINER 3,563,200 3,563,200 CIPLF19091 LANDFILL SCRAPER REPLACEMENT 1,305,060 1,305,060 CIPLF21029 LANDFILL GPS SYSTEM EQUIPMENT 40,000 40,000 CIPLF21030 CLOSED LANDFILLS 963,802 704,500 109,300 115,000 119,500 115,000 450,000 2,577,102 CIPLF22005 BUILDING IMPROVEMENTS 450,037 100,000 400,000 950,037 CIPLF22006 SITE PAVING AND MARKINGS 48,337 209,600 628,800 886,737 CIPLF78503 LANDFILL CLOSURE SOUTH 145,566 640,000 785,565 FY25-34 Landfill Projects 43 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPLF78505 LF NORTH CELL PHASED CONSTRUCTION 100,000 5,010,600 5,110,600 CIPLF78506 LANDFILL 4x4 REPLACEMENT TRUCKS 41,000 430,000 471,000 CIPLF78514 SOLID WASTE INSPECTION TRUCKS 10,042 67,115 150,070 513,184 740,411 CIPLF78522 LANDFILL WATER PULL/TRUCK 70,000 275,000 1,600,000 1,945,000 CIPLF78532 AUXILIARY EQUIPMENT 493,989 370,000 310,000 500,000 260,000 1,933,989 CIPLF78534 STORMWATER CONTROLS 706,059 392,305 472,149 556,261 327,699 2,454,473 CIPLF78535 LANDFILL GAS EXTRACTION SYSTEM 587,810 525,000 685,248 635,212 550,000 2,983,270 TOTAL 3,811,377 6,225,005 3,726,297 3,148,588 6,647,799 4,891,130 8,078,984 36,529,180 44 FY25-34 Library CIP Overview • Funded by Library G. O. Bonds (96%) and Library DIF (4%) • Focus on: – Improving existing facilities • Follow industry standard replacement cycles – Replacing existing assets as needed FY25-34 Library by Funding Source 45 FUND EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 4100-Library Construction 1,375,491 6,500,000 3,500,000 10,000,000 8,098,004 4,325,656 6,610,139 40,409,290 4284-DIF Libraries 1,575,734 1,575,734 TOTAL 1,375,491 8,075,734 3,500,000 10,000,000 8,098,004 4,325,656 6,610,139 41,985,024 FY25-34 Library Projects 46 Project # Project Title EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPLB19045 VELMA TEAGUE LIBRARY RENOVATION 594,684 7,180,800 7,775,484 CIPLB19046 MAIN LIBRARY RENOVATION 780,807 6,500,000 3,500,000 10,000,000 20,780,807 CIPLB19066 FOOTHILLS LIBRARY RENOVATION 917,204 4,325,656 6,610,139 11,852,999 CIPLB23029 HEROES PARK LIBRARY EXPANSION 1,575,734 1,575,734 TOTAL 1,375,491 8,075,734 3,500,000 10,000,000 8,098,004 4,325,656 6,610,139 41,985,024 47 FY25-34 Parking Lots CIP Overview • Funded by General Fund (100%) • Annual funding for existing parking lots/garage repairs • VAI Resort Parking Garage Investment • Sine Building Covered Parking Lot FY25-34 Parking Lots by Funding Source 48 FUND EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 1080 - GENERAL FUND CIP 16,835,357 55,200,000 500,000 500,000 500,000 500,000 2,500,000 76,535,357 TOTAL 16,835,357 55,200,000 500,000 500,000 500,000 500,000 2,500,000 76,535,357 FY25-34 Parking Lots Projects 49 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPL19059 RENEW PARKING GARAGES/LOTS 10,357 500,000 500,000 500,000 500,000 500,000 2,500,000 5,010,357 CIPPL24055 VAI PARKING GARAGE INVESTMENT 16,000,000 54,700,000 70,700,000 CIPPL24058 SINE BUILDING COVERED PARKING LOT 825,000 825,000 TOTAL 16,835,357 55,200,000 500,000 500,000 500,000 500,000 2,500,000 76,535,357 50 FY25-34 Parks CIP Overview • Funded by Parks G. O. Bonds (59%), Open Space/Trail G. O. Bonds (17%), ARPA (15%), General Fund (5%) DIF (4%) • Focus on Improving Infrastructure of Existing Parks, and Select New Improvements • Emphasis on Lighting and Irrigation Upgrades, and Replacement of Playground Equipment FY25-34 Parks by Funding Source 51 FUND FUND NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 1080 GENERAL FUND CIP 120,587 6,553,433 6,674,021 4050 PARKS G. O. BONDS 1,249,638 6,020,054 5,713,350 7,996,500 57,627,489 78,607,031 4080 CULTURAL FACILITIES 36,185 36,185 4090 OPEN SPACE/TRAIL G. O. BONDS 10,793,925 10,622,564 1,684,125 23,100,614 4325 DIF PARKS AND REC 101,920 101,920 4383 DIF PARKS AND REC 2,375,760 2,931,160 5,306,920 4610 ARPA CAPITAL PROJECTS 19,836,487 19,836,487 TOTAL 34,514,503 20,107,157 1,684,125 6,020,054 5,713,350 7,996,500 57,627,489 133,663,178 FY25-34 Parks Projects 52 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPK19077 THUNDERBIRD CONSV. PARK IMPS 4,838,225 6,629,200 11,467,425 CIPPK21033 HEROES PARK REC & ACQUATICS CENTER 344,969 30,000,000 30,344,969 CIPPK21038 COMMUNITY CENTER UPGRADES 53,363 53,363 CIPPK21042 PARK RESTROOM REPLACEMENT 21,266 700,000 721,266 CIPPK21054 PLAYGROUND EQUIP. AT FOOTHILLS PARK 44,064 44,064 CIPPK22008 BONSALL PARK IMPROVEMENTS 363,923 363,923 CIPPK22011 MARY SILVA PARK IMPROVEMENTS 555,300 555,300 CIPPK22013 HERITAGE PARK IMPROVEMENTS 252,300 252,300 CIPPK22016 MISSION PARK IMPROVEMENTS 270,000 270,000 CIPPK22020 DELICIAS PARK IMPROVEMENTS 30,129 30,129 FY25-34 Parks Projects 53 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPK22021 LIONS PARK IMPROVEMENTS 46,710 46,710 CIPPK22022 COUNTRY GABLES PARK IMPROVEMENTS 62,238 62,328 CIPPK22023 SUNNYSIDE PARK IMPROVEMENTS 434,720 703,720 1,138,440 CIPPK22024 TARRINGTON RANCH PARK IMPROVEMENTS 278,230 277,650 555,880 CIPPK22025 FOOTHILLS PARK IMPROVEMENTS 841,645 841,645 CIPPK22026 NORTHERN HORIZON PARK IMPROVEMENTS 766,520 766,520 CIPPK22027 MYRTLE PARK IMPROVEMENTS 47,870 47,870 CIPPK22028 CLAVELITO PARK IMPROVEMENTS 5,749 144,260 297,750 447,759 CIPPK22029 BUTLER PARK IMPROVEMENTS 342,940 342,940 CIPPK22030 CHOLLA PARK IMPROVEMENTS 344,900 344,900 FY25-34 Parks Projects 54 PROJECT PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPK22031 SIERRA VERDE PARK IMPROVEMENTS 391,860 391,860 CIPPK22032 SKUNK CREEK LINEAR TRAIL 1,000,000 1,000,000 CIPPK22033 GRAND CANAL LINEAR PARK IMPROVEMENT 4,960,131 4,960,131 CIPPK22034 THUNDERBIRD PASEO IMPROVEMENTS 995,570 2,440,875 1,684,125 5,120,570 CIPPK22035 SUNSET PALMS SPLASH PAD 16,583 153,130 169,713 CIPPK22036 NEW RIVER TRAIL IMPROVEMENTS 552,489 552,489 CIPPK22093 SAHUARO RANCH PARK DRAINAGE/GRADING 4,393 4,393 CIPPK22097 SIERRA VERDE PARK IMPROVEMENTS 1,495,750 1,495,750 CIPPK22098 GREENWAY GRANADA SPLASH PAD 500,000 500,000 FY25-34 Parks Projects 55 PROJECT PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPK22099 SUNSET PARK IMPROVEMENTS 173,330 173,330 CIPPK22100 BONSALL PARK NORTH IMPROVEMENTS 500,000 500,000 CIPPK22101 HEROES REGIONAL PARK BALLFIELDS 17,230,431 5,778,031 23,008,462 CIPPK22111 BONSALL NORTH PARK IRRIGATION 697,000 697,000 CIPPK22112 SUNSET PALMS PARK IRRIGATION 79,470 79,470 CIPPK23004 PLAZA ROSA PARK IMPROVEMENTS 143,699 237,250 380,949 CIPPK23005 KINGS PARK IMPROVEMENTS 716,900 716,900 CIPPK23006 DESERT VALLEY PARK IMPROVEMENTS 887,400 887,400 CIPPK23007 DESERT ROSE PARK IMPROVEMENTS 856,700 856,700 CIPPK23024 SANDS PARK IMPROVEMENTS 1,249 1,249 FY25-34 Parks Projects 56 PROJECT PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPK23026 PASEO SPORTS COMPLEX 1,895 1,515,000 1,516,895 CIPPK23027 CHAPPARAL PARK IMPROVEMENTS 1,121,722 1,121,722 CIPPK23044 MURPHY PARK 121,057 3,553,433 3,674,490 CIPPK23059 PASADENA PARK PLAYGROUND 2,665 2,665 CIPPK23065 DESERT MIRAGE PARK IRRIGATION 71,538 71,538 CIPPK23066 DISCOVERY PARK IRRIGATION 674,310 674,310 CIPPK23067 NEW WORK PARK IRRIGATION 828,000 828,000 CIPPK23073 SAHUARO RANCH PARK PARKING LOT 61,629 61,629 CIPPK24001 SRP HISTORICAL ROOF REPLACEMENT 360,000 760,000 1,120,000 CIPPK24002 ADA UPGRADES 356,810 356,810 FY25-34 Parks Projects 57 PROJECT PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPK24003 PARKING LOT IMPROVEMENTS 700,000 700,000 CIPPK25014 HORIZON PARK IMPROVEMENTS 277,650 277,650 CIPPK25015 ARROWHEAD LAKES PARK IMPROVEMENTS 267,550 267,550 CIPPK25016 UTOPIA PARK IMPROVEMENTS 656,300 656,300 CIPPK25017 FOOTHILLS PARK SKATE RENOVATION 2,302,950 2,302,950 CIPPK25018 SUNSET VISTA PARK IMPROVEMENTS 267,550 267,550 CIPPK25019 GREENWAY GRANDA PARK IMPROVEMENTS 817,500 817,500 CIPPK25020 SUNSET RIDGE PARK IMPROVEMENTS 267,550 267,550 CIPPK25021 GLND YOUTH SPORTS COMP FLD LIGHTING 411,830 411,830 CIPPK25068 SAHUARO RANCH PARK BUILDOUT 27,627,489 27,627,489 FY25-34 Parks Projects 58 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPK70546 SAHUARO RANCH PK MASTER PLAN 31,792 31,792 CIPPK73576 FOOTHILLS PARK PICKLEBALL COURTS 9,211 403,650 412,861 TOTAL 34,514,503 20,107,157 1,684,125 6,020,054 5,713,350 7,996,500 57,627,489 133,633,178 59 FY25-34 Public Safety CIP Overview • Funded by Public Safety G. O. Bonds (54%), General Fund (23%), Special Revenue Funds (19%), Fire DIF (2%) and Police DIF (2%) • Focus on: – Improving existing facilities • Follow industry standard replacement cycles • Health, safety, and functional improvements – Replacing existing assets as needed FY25-34 Public Safety by Funding Source 60 FUND EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 1080-GENERAL FUND CIP 10,624,206 8,268,164 7,712,007 4,675,000 574,774 32,101,598 63,955,749 2200-TRAINING FACILITY REVENUE 2,325,106 2,500,000 6,050,000 3,982,000 500,000 177,341 36,426,337 51,960,784 4040-PUBLIC SAFETY CONSTRUCTION 6,133,296 6,802,280 21,653,550 27,348,060 59,901,280 7,659,160 19,940,280 149,437,906 4173-2019-DIF FIRE 6,500,000 6,500,000 4223-2019-DIF POLICE 4,417,090 4,417,090 4610-ARPA CAPITAL PROJECTS 380,000 380,000 TOTAL 19,462,608 17,570,444 41,915,557 36,005,060 60,401,280 12,828,365 88,468,215 276,651,529 FY25-34 Public Safety Projects 61 Project # Project Title EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPFC20036 GRPSTC DRIVERS TRAINING TRACK 63,900 232,000 1,200,000 1,495,900 CIPFC21053 CITY COURT RENOVATIONS 1,265,710 1,265,710 CIPPS19029 FIRE STATION #153 REPLACEMENT 1,838,097 3,000,000 4,838,097 CIPPS19030 POLICE EVIDENCE STORAGE FACILITY 2,778,490 1,500,000 4,278,490 CIPPS19041 MAIN PUBLIC SAFETY BLDG RENOVATION 82,998 2,202,280 6,314,420 4,480,010 13,079,708 CIPPS19042 FOOTHILLS POLICE STATION RENOVATION 427,433 1,606,450 2,995,840 3,112,860 8,142,583 CIPPS19043 GATEWAY POLICE STATION RENOVATION 34,133 2,825,350 10,563,840 13,423,323 CIPPS19044 FIRE STATION #154 RENOVATION 100,000 7,940,280 8,040,280 CIPPS19049 FIRE STATION WESTERN AREA 19,793,020 19,793,020 CIPPS19050 FIRE STATION #155 RENOVATION 283,130 3,714,600 3,865,600 7,863,330 FY25-34 Public Safety Projects 62 Project # Project Title EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPS19051 FIRE STATION #156 RENOVATION 312,940 3,739,980 4,052,920 CIPPS19052 FIRE STATION #157 RENOVATION 4,546,300 4,546,300 CIPPS19053 POLICE STATION WEST AREA 4,417,090 4,417,090 CIPPS23002 LP15 HEART MONITOR REPLACE 2,232,682 2,232,682 CIPPS23003 FIRE RADIO REPLACEMENT 78,163 2,422,500 2,500,663 CIPPS23030 GRPSTC PARKING LOT 86,434 86,434 CIPPS23031 POLICE CRIME LABORATORY 15,056,000 8,472,000 8,472,000 32,000,000 CIPPS23042 COURT RENOVATION PHASE 2 10,471,000 10,471,000 CIPPS23074 POLICE MOBILE COMMAND VEHICLE 596,338 596,338 CIPPS24004 FIRE CAPITAL ASSET REPLACEMENT PROG 61,600 4,292,500 4,354,100 FY25-34 Public Safety Projects 63 Project # Project Title EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPS24005 GRPSTC FIRE HYDRANT REPLACEMENT 16,206 177,341 226,337 419,884 CIPPS24050 FIRE STATION – AIRPORT AREA 6,500,000 5,936,710 12,436,710 CIPPS24054 REPLACE GRPSTC CLASS A BURN BUILDING 2,210,000 1,000,000 2,300,000 5,510,000 CIPPS24057 POLICE DEPARTMENT RADIO REPLACEMENT 3,400,000 3,100,000 1,250,000 1,500,000 9,250,000 CIPPS24063 GRPSTC MASTER PLAN 35,000 35,000 CIPPS25002 PUBLIC SAFETY DRIVING SIMULATOR 175,000 175,000 CIPPS25003 FIRE MOBILE COMPUTER TERMINALS – MCT’S 350,000 350,000 CIPPS25024 FIRE STATION – 75TH & ORANGEWOOD 12,000,000 12,000,000 CIPPS25025 MARKED CARTRIDGE /BIG BOX PROP 1,500,000 3,750,000 3,750,000 9,000,000 CIPPS25026 TRAINING ACADEMY EXPANSION NEEDS 35,000,000 35,000,000 FY25-34 Public Safety Projects 64 Project # Project Title EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPPS25027 CONNEX BOX BASIC SKILLS PROP 500,000 500,000 CIPPS70814 FIRE APPARATUS REPLACEMENT 4,255,423 5,168,164 6,112,007 3,000,000 574,774 25,386,598 44,496,996 TOTAL 19,462,608 17,570,444 41,915,557 36,005,060 60,401,280 12,828,365 88,468,215 276,651,529 65 FY25-34 Solid Waste CIP Overview • Funding Source: 100% Enterprise – User Fee Revenues • Focus On Programmed Vehicle Replacements • Follow industry standard replacement cycles FY25-34 Solid Waste by Funding Source 66 FUND FUND NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 6120 SOLID WASTE 699,861 3,638,742 5,282,383 4,932,236 4,327,059 3,813,456 30,696,201 53,389,938 TOTAL 699,861 3,638,742 5,282,383 4,932,236 4,327,059 3,813,456 30,696,201 53,389,938 FY25-34 Solid Waste Projects 67 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPSW19027 REPLACE STREET SWEEPERS 951,419 998,990 549,445 2,575,934 5,075,788 CIPSW78001 REPLACE ROLLOFF TRUCKS – COMMERCIAL 236,500 248,325 573,631 1,058,456 CIPSW78002 REPLACE FRONTLOAD TRUCKS- COMMERCIAL 86,113 431,949 907,092 952,447 500,035 4,334,637 7,212,273 CIPSW78003 REPLACE SIDELOAD TRUCKS- RESIDENTIAL 296,035 1,899,923 2,043,576 2,145,754 2,816,303 2,365,694 15,753,414 27,320,699 CIPSW78004 REP BULK TRASH EQUIP- RESIDENTIAL 217,231 1,160,870 1,059,877 639,930 671,926 705,523 7,128,749 11,584,106 CIPSW78005 REPLACE PICKUPS / SERVICE TRUCKS 62,332 126,000 63,919 175,115 70,470 192,794 329,836 1,020,466 CIPSW78009 ALLEY GATING 38,150 20,000 20,000 20,000 20,000 118,150 TOTAL 699,861 3,638,742 5,282,383 4,932,236 4,327,059 3,813,456 30,696,201 53,389,938 FY25-34 Streets CIP Overview 68 • Funded Sources: • Transportation Sales Tax (56%) • HURF (13%) • Streets G.O. Bonds (13%) • Development Impact Fees (8%) • Transportation Grants (7%) • General Fund (3%) FY25-34 Streets CIP Overview 69 • Safety Projects • Active Transportation (Bicycle/Pedestrian) • Intersection Signalization/Improvements • PMP/Pavement/Arterial Reconstruction FY25-34 Streets by Funding Source 70 FUND FUND NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 1080 GENERAL FUND CIP 7,989,748 1,128,429 1,155,994 579,744 590,848 602,286 1,452,466 13,499,514 2050 HURF – HIGHWAY USER REVENUE FUND 8,558 3,098,213 3,253,124 3,415,780 3,586,568 3,765,897 21,849,408 38,977,548 2060 TRANSPORTATION GRANTS 7,130,024 1,993,267 20,626,747 1,220,085 339,505 1,117,716 32,427,344 2070 TST – TRANSPORTATION SALES TAX 553,955 14,828,904 15,555,370 16,318,111 17,032,581 16,998,533 93,885,593 175,173,047 2071 STREETS IN LIEU 2,500,000 2,500,000 5,000,000 4010 STREETS BONDS 856,912 5,953,292 2,692,898 4,833,436 6,524,407 6,927,805 28,394,237 56,182,987 4020 HURF CAPITAL FUND 5,097,364 1,080,110 1,107,319 1,135,293 1,164,061 1,193,645 6,442,504 17,220,296 4030 TST – CAPITAL PROJECT 15,399,246 10,751,467 15,023,510 9,858,714 2,103,220 3,367,747 13,830,368 70,334,272 FY25-34 Streets by Funding Source 71 FUND FUND NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 4410 2014 – DIF STREET EAST 559,359 559,359 4420 2014 – DIF STREETS WEST 937,975 937,975 4431 2019 – DIF STREETS 2,122,136 5,207,641 4,321,973 8,776,190 20,427,940 4434 2023 – DIF STREETS 967,896 1,902,054 8,825,416 12,663,261 TOTAL 41,623,173 47,509,220 66,236,935 46,137,353 31,001,685 35,097,471 175,797,708 443,403,544 FY25-34 Streets Projects 72 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST19006 PAVEMENT MANAGEMENT 562,514 17,927,117 18,808,494 19,733,891 20,619,149 20,674,430 115,735,001 214,150,596 CIPST19048 CAPITAL BRIDGE REPAIR PROGRAM 71,447 1,238,329 772,054 371,598 390,177 409,685 2,376,964 5,630,255 CIPST20012 FLASHING YELLOW ARROWS 513,245 513,245 CIPST20013 VEHICLE REPLACEMENT 1,488,872 560,432 583,890 607,246 631,535 656,796 3,699,718 8,228,489 CIPST20022 BIKE PROJECTS (LOCAL MATCH) 143,208 146,072 148,994 151,973 155,013 822,827 1,568,087 CIPST21001 TELECOM CONDUITS 419,200 209,600 209,600 209,600 209,600 209,600 1,048,000 2,515,200 CIPST21015 CENTRAL CORE SIDEWALK GAPS 358,801 358,801 CIPST21016 67TH AVENUE BIKE LANES 966,003 966,003 CIPST21018 ST RECON GLENDALE – 101 TO 91ST 853,435 853,435 CIPST21047 ST RECON 51ST AVE – OLIVE TO PEORIA 3,477 3,477 FY25-34 Streets Projects 73 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST21052 ST RECON 83RD – GLENDALE TO NORTHERN 1,502,334 1,502,334 CIPST22062 PAVEMENT CUT REPAIR 114,224 111,122 113,346 115,612 117,924 120,283 638,475 1,330,986 CIPST22063 TRANSPORTATION NETWORK IMPROVEMENT 2,000,000 2,000,000 CIPST22064 TRANSPORTATION SAFETY PROGRAM 684,467 440,912 449,730 458,725 467,901 477,258 2,533,342 5,512,334 CIPST22065 SCALLOP STREET PROGRAM 7,570,548 7,570,548 CIPST22067 57TH AND GREENWAY INTERSECTION IMPROV. 200,000 200,000 CIPST22068 59TH AND NORTHERN INTERSECT IMPROV. 1,040,521 1,040,521 CIPST22120 95TH AVE/MONTEBELLO INTERSECTION 184,164 184,164 CIPST23014 OLIVE AVE, 59TH – 67TH STREET LIGHTS 321,737 321,737 CIPST23015 61ST / OLIVE TRAFFIC SIGNAL UPGRADE 179,518 179,518 FY25-34 Streets Projects 74 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST23016 53RD / CAMELBACK NEW HAWK 484,847 484,847 CIPST23017 NORTHERN PARKWAY CABLE BARRIER 2 1,173,236 1,173,236 CIPST23018 TMC UPGRADE 228,692 2,013,998 2,242,690 CIPST23019 MARYLAND ACTIVE TRANSPORTATION IMPR 140,127 95,155 235,282 CIPST23020 MISSOURI ACTIVE TRANSPORTATION IMPR 311,782 311,782 CIPST23047 SARIVAL AVE/BETHANY HOME RD SIGNAL 1,041,882 1,041,882 CIPST23048 SARIVAL AVE/GLENDALE AVE SIGNAL 73,841 967,896 1,041,737 CIPST23049 INFILL STREETLIGHTS PHASE II 168,156 493,627 503,499 513,569 1,678,851 CIPST23050 58TH AVENUE/BETHANY HOME ROAD 76,786 679,643 756,429 CIPST23051 TRAFFIC SIGNAL INTERCONNECT 736,019 671,332 671,332 2,078,683 FY25-34 Streets Projects 75 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST23052 SPEED FEEDBACK SIGNS SCHOOL ZONES 57,132 57,132 CIPST23053 INFILL SIDEWALK 331,830 165,241 168,544 171,916 175,354 178,862 949,418 2,141,165 CIPST23054 GUARDRAIL UPDATE 2,353 110,160 112,363 114,611 116,903 119,241 710,893 1,286,525 CIPST23056 ARTERIAL STREET RECONSTRUCTION 8,668,451 8,668,451 CIPST23057 FLASHING YELLOW ARROWS PHASE 5 105,981 882,086 988,067 CIPST23071 83RD AVE CARDINALS WAY INTERSECTION 144,306 130,050 274,356 CIPST23075 59TH AVE CAPACITY ENHANCE LOOP 101 48,145 48,145 CIPST24013 43RD AVE-PEORIA INTERSECTION IMPROV. 31,212 180,405 211,617 CIPST24014 51ST AVE-CAMELBACK INTERSECTION IMPR 191,250 585,225 776,475 CIPST24015 51ST AVE – OLIVE INTERSECTION IMPR 500,000 500,000 FY25-34 Streets Projects 76 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST24016 59TH AVE- THUNDERBIRD INTERSECTION 61,200 353,736 414,936 CIPST24017 67TH AVE-GREENWAY INTERSECTION 382,500 1,170,450 1,552,950 CIPST24018 67TH AVE-PEORIA INTERSECTION IMPRV 50,000 200,000 250,000 CIPST24019 67TH AVE: ARROWHEAD LP TO DVALLEY 2,733,407 2,733,407 CIPST24020 67TH AVE: LP 101 TO ARROWHEAD LP 1,056,006 1,056,006 CIPST24021 67TH AVE: PINNACLE PK TO DEER VAL 650,250 1,989,765 2,640,015 CIPST24022 67TH AVE- THUNDERBIRD INTERSECTION 332,928 489,600 2,546,899 3,369,427 CIPST24024 99TH AVE: GLENDALE AVE TO NORTHERN 229,500 1,353,040 1,582,540 CIPST24025 BALLPARK BLVD: BHR TO MARYLAND AVE 468,180 2,706,080 3,174,260 FY25-34 Streets Projects 77 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST24026 CAMELBACK RD: 99TH AVE TO LOOP 101 40,800 373,320 414,120 CIPST24027 LITCHFIELD-BHR TRAFFIC SIGNAL 115,928 670,067 785,995 CIPST24029 NORTHERN: REEMS- LITCHFIELD WIDENING 690,050 2,111,555 2,801,605 CIPST24030 NORTHERN: SARIVAL- ALSUP WIDENING 2,718,800 2,718,800 CIPST24031 REEMS-HATCHER TRAFFIC SIGNAL 165,612 506,773 672,385 CIPST24032 SARIVAL: GLENDALE TO NORTHERN ROADW 828,060 2,584,543 3,412,603 CIPST24033 SARIVAL-OLIVE TRAFFIC SIGNAL 248,418 760,160 1,008,578 CIPST24034 SARIVAL-PEORIA INTERSECTION IMPRV 193,490 591,235 784,725 CIPST24035 RIGHT OF WAY LANDSCAPE PLAN 918,829 946,394 370,144 381,248 392,686 404,466 3,413,766 CIPST24036 STREET DESIGN PROJECT 1,000,000 1,000,000 FY25-34 Streets Projects 78 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST24037 TRANSPORTATION PLAN 500,000 510,000 552,040 1,172,578 2,734,618 CIPST24039 FEDERAL GRANT FUND MATCH 2,500,000 2,500,000 5,000,000 CIPST24040 51ST AVE CORRIDOR PROJECT 2,034,180 6,056,836 8,091,016 CIPST24041 BELL RD CORRIDOR PROJECT 1,581,360 5,665,272 7,246,632 CIPST24042 CENTRAL GLENDALE INFRA IMPRV 7,162,963 7,666,640 CIPST24043 GLENDALE SS4A ACTION PLAN 999,834 999,834 CIPST24062 WATER CONSERVATION – TURF CONVERSION 810,000 810,000 CIPST25012 GLENDALE AVE RADAR DET & ADAPT CONT 397,192 397,192 CIPST25013 ADVANCE DETECTION & STOP BAR INSTALL 513,746 513,746 CIPST25028 107TH AVE, ORANGEWOOD TO NORTHERN 417,404 417,404 FY25-34 Streets Projects 79 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST25029 UNION HILLS, 67TH AVE TO 75TH AVE 332,258 332,258 CIPST25030 69TH AVE, BELL RD TO CAMPO BELLO DR 137,176 137,176 CIPST25031 DESERT COVE AVE, 59TH DR TO 60TH DR 93,331 93,331 CIPST25032 72ND AVE, LUKE AVE TO SAN JUAN AVE 256,816 256,816 CIPST25033 76TH LN, CAMELBACK RD TO CUL-DE-SAC 63,827 63,827 CIPST25034 ST RECON, 43RD AVE- GLENDALE AREA 2,291,884 2,291,884 CIPST25035 ST RECON 59TH AVE - GLENDALE AREA 760,476 760,476 CIPST25036 ST RECON STREETS 75TH, 73RD, READE AVE 1,278,565 1,278,565 CIPST25037 ST RECON 59TH AVE & BEARDSLEY AREA 2,141,305 2,141,305 CIPST25038 63RD AVE, THUNDERBIRD TO CUL-DE-SAC 321,856 321,856 FY25-34 Streets Projects 80 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST25039 ST RECON 59TH AVE & CACTUS AREA 622,650 622,650 CIPST25040 RECON ST, 51ST AVE & PEORIA AV AREA 2,121,830 2,121,830 CIPST25041 ST RECON 67TH & BETHANY HM AREA 4,146,772 4,146,772 CIPST25042 ST RECON 71ST AVE & BEARDSLEY AREA 4,833,436 4,833,436 CIPST25043 ST RECON 63RD AVE & BEARDSLEY AREA 2,381,920 2,381,920 CIPST25044 RECON 55TH AVE, CACTUS TO CHOLLA ST 423,079 423,079 CIPST25045 ST RECON, 51ST AVE & NORTHERN AREA 1,110,458 1,110,458 CIPST25046 ST RECON, 51ST AVE & GLENDALE AREA 2,026,759 2,026,759 CIPST25047 ST RECON, 83RD AVE & MARYLAND AREA 533,351 533,351 CIPST25048 RECON GLENN DR, 88TH LN TO 87TH DR 193,158 193,158 FY25-34 Streets Projects 81 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST25049 MOUNTAIN VIEW RD, 43RD TO 59TH 1,690,217 1,690,217 CIPST25050 ST RECON, 75TH AVE & NORTHERN AREA 4,834,190 4,834,190 CIPST25051 RECON ROSE LN, GRAND CANAL TO 99TH 226,563 226,563 CIPST25052 ST RECON, 75TH AVE & DENARO DR AREA 152,880 152,880 CIPST25053 46TH AVE, McLENNAN TO OCOTILLO 78,203 78,203 CIPST25054 ST RECON, 59TH AVE & BETHANY AREA 4,919,302 4,919,302 CIPST25055 ST RECON, 69TH AVE & GREENWAY AREA 2,969,724 2,969,724 CIPST25056 ST RECON, 47TH AVE & NORTHERN AREA 2,508,177 2,508,177 CIPST25057 ROSE LN, CUL-DE-SAC TO 49TH AVE 93,111 93,111 CIPST25058 ST RECON, 71ST AVE & NORHTERN AREA 1,802,836 1,802,836 FY25-34 Streets Projects 82 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST25059 ST RECON, 79TH AVE & BETHANY AREA 894,504 894,504 CIPST25060 ST RECON, 75TH AVE & GLENDALE AREA 639,440 639,440 CIPST25061 UNION HILLS, 51ST AVE TO 59TH AVE 1,875,919 1,875,919 CIPST25062 59TH, DEER VALLEY TO PINNACLE PEAK 1,135,439 1,135,439 CIPST25063 RECON BELL RD, 67TH AVE TO 75TH AVE 3,901,163 3,901,163 CIPST25064 ST RECON, 55TH AVE & BELL RD AREA 1,941,887 1,941,887 CIPST25065 ST RECON, 79TH AVE & GLENDALE AREA 3,114,618 3,114,618 CIPST25066 NEW RIVER, GLENDALE TO CUL-DE-SAC 767,812 767,812 CIPST25067 ST RECON, OLIVE AVE & 51ST AVE AREA 3,250,430 3,250,430 CIPST25069 ACTIVE TRANSPORTATION PLAN 900,000 900,000 FY25-34 Streets Projects 83 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST25070 ST RECON BETHANY – 43RD AVE TO 51ST AVE 3,396,161 3,396,161 CIPST25071 ST RECON CAMELBACK - 51ST TO 59TH 3,323,265 3,323,265 CIPST25072 ST RECON GREENWAY – 59TH AVE TO 51ST AVE 2,591,410 2,591,410 CIPST25073 ST RECON CAMELBACK - 59TH TO 79TH 5,953,292 5,953,292 CIPST25074 ST RECON CAMELBACK - 75TH TO 83RD 1,330,305 1,330,305 CIPST25075 ST RECON 75TH-DEER VLLY TO BEARDSLEY 1,362,593 1,362,593 CIPST65005 ITS UPGRADES (LOCAL MATCH) 560,747 209,304 213,491 217,760 222,115 226,557 1,202,594 2,852,568 CIPST65006 BUS PULLOUTS 611,523 330,683 337,297 344,044 350,924 357,942 1,900,004 4,232,417 CIPST65016 NORTHERN PARKWAY 120,281 670,000 670,000 670,000 2,130,281 CIPST68918 INFILL LIGHTING PROGRAM PHASE I 1,414,252 165,240 168,545 171,916 175,354 178,861 949,416 3,223,584 FY25-34 Streets Projects 84 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPST68922 STREETLIGHT POLE PROGRAM 45,400 82,620 84,273 85,958 87,677 89,430 474,708 950,066 TOTAL 41,623,173 47,509,220 66,236,935 46,137,353 31,001,685 35,097,471 175,797,708 443,403,544 85 FY25-34 Transit CIP Overview • Funded by Transportation Sales Tax (52%) and Transportation Grants (48%) • Projects include North Glendale Park and Ride, Bus Stop Enhancements, Bus Fleet Replacement, and Transportation Program Planning FY24-33 Transit by Funding Source 86 FUND EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 2060 - TRANSPORTATION GRANTS 2,870,407 1,240,688 2,010,000 6,121,095 4030 - TRANSPORTATION CAPITAL PROJ 1,288,122 495,456 504,864 509,362 518,949 523,628 2,736,665 6,577,046 TOTAL 4,158,529 1,736,144 2,514,864 509,362 518,949 523,628 2,736,665 12,698,141 FY24-33 Transit Projects 87 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPTR21013 NORTH GLENDALE PARK & RIDE PROJECT 3,480,953 3,480,953 CIPTR22069 BUS STOP ENHANCEMENTS 16,145 220,456 224,864 229,362 233,949 238,628 1,266,665 2,430,069 CIPTR22095 TRANSIT BUS FLEET REPLACEMENT 370,407 1,240,688 2,010,000 3,621,095 CIPTR65022 TRANSP. PROG. ENGR. CONSULTANT 291,024 275,000 280,000 280,000 285,000 285,000 1,470,000 3,166,024 TOTAL 4,158,529 1,736,144 2,514,864 509,362 518,949 523,628 2,736,665 12,698,141 Funded by Sewer Enterprise Fees (97%) and Sewer DIF (3%) Capital Improvement Plan Priorities: • Maintain a resilient and secure infrastructure • Meet all Federal and State regulations Major Projects for first five years: • Rehab sewer lines, manholes and lift stations • 91st Avenue Wastewater Treatment Plant • Rehabilitate West Area Water Reclamation Facility 88 FY25-34 Wastewater CIP Overview FY25-34 Wastewater by Funding Source 89 FUND FUND NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 6030 SEWER FUND 9,113,880 22,234,000 17,931,600 16,451,000 19,531,000 17,151,000 102,245,000 204,657,480 6095 2014 SEWER DIF 700,000 700,000 500,914 1,900,914 6101 2019 SEWER DIF 199,086 700,000 3,500,000 4,399,086 TOTAL 9,113,880 22,234,000 18,631,600 17,651,000 20,231,000 17,851,000 105,745,000 210,957,480 FY25-34 Wastewater Projects 90 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPWW19086 SEWER LINE - GLENDALE AT 91ST AVE 50,000 50,000 CIPWW19087 ARROWHEAD SEWER LINE REHAB 685,529 685,529 CIPWW19088 ARROWHEAD SEWER LINES 3,000,000 2,500,000 3,500,000 9,000,000 CIPWW21026 WEST AREA WRF IMPROV PH 2 2,305,000 1,100,000 1,600,000 3,800,000 5,800,000 12,050,000 26,655,000 CIPWW21027 ARROWHEAD WRF IMPROVEMENTS 352,459 510,000 2,000,000 2,950,000 2,950,000 1,500,000 15,000,000 25,262,459 CIPWW21028 UNDERGROUND STORAGE FACILITY PERMIT 63,176 63,176 CIPWW22076 SEWER LINE REHAB PROGRAM 2,497,694 5,413,000 3,570,000 2,750,000 2,550,000 2,550,000 27,490,000 46,820,694 CIPWW22077 LIFT STATION & FORCE MAIN REHAB 310,000 400,000 3,200,000 2,750,000 500,000 500,000 2,500,000 10,130,000 CIPWW23010 ROOF REPLACEMENT – SEWER 194,775 101,000 261,600 101,000 101,000 101,000 505,000 1,365,375 CIPWW23012 SEWER DEVELOPMENT INFRASTRUCTURE 700,000 700,000 700,000 700,000 3,500,000 6,300,000 FY25-34 Wastewater Projects 91 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPWW60016 WEST AREA WRF IMPROV PH 1 1,632,793 3,000,000 4,632,793 CIPWW63003 99TH AVE INTERCEPTOR LINE 738,306 1,600,000 3,000,000 2,000,000 2,000,000 1,300,000 2,000,000 12,638,306 CIPWW63006 ARROWHEAD SEWER LINE REHAB 50,000 50,000 CIPWW63010 91ST AVENUE WWTP IMPROVEMENTS 1,236,467 4,501,000 3,500,000 3,000,000 3,800,000 4,000,000 25,000,000 45,037,467 CIPWW63016 SEWER LINE PHASE V 1,221 1,221 CIPWW63024 SEWER MANHOLE REHAB PROGRAM 502,075 604,000 500,000 530,000 530,000 600,000 4,200,000 7,466,075 CIPWW63030 LIFT STATION REHAB – 67TH AVE & ACDC 517,380 517,380 CIPWW63031 WASTEWATER CAPITAL EQUIPMENT 225,374 500,000 500,000 500,000 500,000 500,000 5,000,000 7,725,374 CIPWW63032 WASTEWATER COLLECTION IMPROVE 56,633 300,000 300,000 300,000 300,000 300,000 5,000,000 6,556,633 TOTAL 9,113,880 22,234,000 18,631,600 17,151,000 20,231,000 17,851,000 105,745,000 210,957,480 Funded by Water Enterprise Fees (97%) and Water DIF (3%) Capital Improvement Plan Priorities: • Provide water supply from multiple sources • Maintain a resilient and secure infrastructure • Meet all Federal and State regulations Major Projects for first five years: • Rehab water lines, booster stations and reservoirs • Rehab water treatment plants • Add new groundwater wells and rehab existing • Add water rights and supply infrastructure 92 FY25-34 Water CIP Overview FY25-34 Water by Funding Source 93 FUND FUND NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL 6020 WATER FUND 18,998,330 30,238,000 41,627,000 41,252,000 31,067,000 31,122,000 158,150,000 352,454,330 6065 2014 WATER DIF 2,686,259 54,657 2,740,916 6071 2019 WATER DIF 1,995,343 1,575,000 3,650,000 1,025,000 1,325,000 9,570,343 TOTAL 21,684,589 32,288,000 43,202,000 44,902,000 32,092,000 32,447,000 158,150,000 364,765,589 FY25-34 Water Projects 94 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPWA19018 WATER RIGHTS & OTHER SUPPLY SOURCES 660,000 660,000 3,500,000 875,000 875,000 20,000,000 26,570,000 CIPWA19020 SCADA IMPROVEMENTS 247,123 725,000 825,000 900,000 1,000,000 900,000 5,000,000 9,597,123 CIPWA19021 STORAGE & RECOVERY WELLS REHAB 11,538 460,000 420,000 2,200,000 3,091,538 CIPWA19022 GROUNDWATER WELLS & INTERCONNECTS 5,450,664 7,700,000 7,000,000 6,000,000 8,500,000 14,500,000 10,250,000 59,400,664 CIPWA21022 OASIS WTP IMPROVEMENTS 147,929 1,228,000 500,000 500,000 1,000,000 3,000,000 16,500,000 22,875,929 CIPWA21023 PYRAMID PEAK WTP IMPROVEMENTS 1,797,000 700,000 1,200,000 1,540,000 1,300,000 23,000,000 29,537,000 CIPWA21024 CHOLLA WTP IMPROVEMENTS 33,087 5,000,000 6,000,000 6,000,000 7,000,000 3,000,000 20,000,000 47,033,087 CIPWA21025 WATER LINE – PACK 2 REHAB 447,203 447,203 CIPWA21032 67TH AVE TRANS LINE IMPROVEMENTS 163,218 163,218 CIPWA22071 WATER LINE 59TH - GLENN TO NORTHERN 100,000 400,000 500,000 CIPWA22079 WATERLINE-BETHANY, 43RD TO 51ST 200,000 200,000 FY25-34 Water Projects 95 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPWA23008 WATER METER DATA COLLECTION SYSTEM 2,662,096 4,500,000 12,000,000 12,000,000 2,000,000 33,162,096 CIPWA23009 ROOF REPLACEMENT – WATER 255,992 202,000 202,000 202,000 202,000 202,000 1,000,000 2,265,992 CIPWA23011 WATER DEVELOPMENT INFRASTRUCTURE 1,148,224 150,000 150,000 150,000 450,000 750,000 2,798,224 CIPWA60015 ASSET MANAGEMENT PROGRAM 175,000 175,000 CIPWA60017 WATER & WASTEWATER SYSTEMS MODELING 452,174 250,000 150,000 150,000 150,000 150,000 1,302,174 CIPWA60018 LABORATORY EQUIPMENT REPLACEMENT 174,443 150,000 150,000 150,000 150,000 150,000 924,443 CIPWA60019 VEHICLE REPLACEMENT PROGRAM 1,356,727 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 5,000,000 11,356,727 CIPWA61001 WATER VALVE REPLACEMENT PRGM 156,466 1,050,000 1,050,000 850,000 1,250,000 1,250,000 9,400,000 15,006,466 CIPWA61013 WATER LINE REHABILITATION PROGRAM 2,055,377 3,555,000 3,750,000 3,700,000 3,500,000 3,500,000 17,150,000 37,210,377 CIPWA61023 WATER SYSTEM SECURITY 180,000 150,000 150,000 150,000 150,000 150,000 350,000 1,280,000 CIPWA61024 CHOLLA WTP – 2014 IMPROVEMENTS 241,252 241,252 FY25-34 Water Projects 96 PROJECT # PROJECT NAME EST CARRYOVER FY25 FY26 FY27 FY28 FY29 FY30-34 TOTAL CIPWA61043 PYRAMID PEAK – 2017 IMPROVEMENTS 36,400 36,400 CIPWA61045 THUNDERBIRD RESERV & DIST SYS IMPROV 500,326 1,500,000 5,250,000 6,000,000 13,250,326 CIPWA61047 METER VAULT REPLACEMENT PROGRAM 253,017 515,000 300,000 515,000 1,583,017 CIPWA61048 GROUNDWATER WELL REHAB PROGRAM 1,238,206 1,487,000 1,150,000 650,000 850,000 100,000 21,150,000 26,625,206 CIPWA61049 BOOSTER STATION – 69 & DEER VALLEY 1,671,064 1,671,064 CIPWA61051 ACCRUE LONG-TERM WATER CREDITS 100,000 100,000 CIPWA61054 DISTRIBUTION SYSTEM IMPROV PROGRAM 51,693 225,000 500,000 200,000 500,000 200,000 2,500,000 4,176,693 CIPWA61058 PYRAMID PEAK WTP EXTPANSION 888,000 888,000 CIPWA61061 WATER CAPITAL EQUIPMENT REPLACEMENT 1,211,046 500,000 700,000 700,000 700,000 700,000 3,500,000 8,011,046 CIPWA61062 TRANSMISSION LINE & VALVE ASSESSMENT 76,324 209,000 800,000 600,000 600,000 600,000 400,000 3,285,324 TOTAL 21,684,589 32,288,000 43,202,000 44,902,000 32,092,000 32,447,000158,150,000364,765,589 97 Questions? Budget Calendar 98 Item Date Workshop #1 – Budget Overview / Revenues / Five-Year Financial Forecasts December 12, 2023 Workshop #2 – FY25-34 Capital Improvement Plan March 5, 2024 Workshop #3 – (All Day) FY25 Operating Budget Department Presentations April 2, 2024 Workshop #4 – (All Day) FY25 Operating Budget Department Presentations April 4, 2024 Workshop #5 – FY25 Budget Workshop April 16, 2024 Voting Meeting – Tentative Budget Adoption May 14, 2024 Voting Meeting – Budget Adoption / Property Tax Levy June 11, 2024 Voting Meeting – Property Tax Adoption June 25, 2024