Linking Agreement with Hazen and Sawyer, P.C.

City of Glendale — Special (2024-03-05)

View PDF Item 5 Meeting page

Extracted text (via pymupdf) 27076 characters
1 
10/05/2023 
LINKING AGREEMENT 
BETWEEN 
THE CITY OF GLENDALE, ARIZONA 
AND 
HAZEN AND SAWYER, P.C. 
This Linking Agreement (“Agreement”) is entered into as of this       day of      , 2024, between the 
City of Glendale, an Arizona municipal corporation (“City”), and Hazen and Sawyer, P.C., a New York 
Corporation, authorized to do business in Arizona (“Contractor”), collectively, the “Parties.” 
RECITALS 
A.
On March 1, 2022, City of Buckeye, a member of the S.A.V.E Cooperative Purchasing ,  entered into
a contract with Contractor to purchase the goods and services described in On-Call Consulting For
Engineering and Architectural Services, Category 2: Water/Wastewater Contract No. 2022003.18
(“Cooperative Agreement”), which is attached hereto as Exhibit A.  The Cooperative Agreement
allows its cooperative use by other governmental agencies, including the City.
B.
Section 2-149 of the City’s Procurement Code permits the Materials Manager to procure goods and
services by participating with other governmental units in cooperative purchasing agreements when
the best interests of the City would be served.
C.
Section 2-149 also provides that the Materials Manager may enter into such cooperative agreements
without meeting the formal or informal solicitation and bid requirements of Glendale City Code
Sections 2-145 and 2-146.
D.
The City wishes to contract with Contractor for supplies or services identical to those being provided
to other units of government under the Cooperative Agreement.  Contractor consents to the City’s
cooperative use of the terms and conditions of the Cooperative Agreement, and agrees to provide
the supplies and services set forth in the Statement of Work appended hereto as Exhibit B.
AGREEMENT 
NOW, THEREFORE, in consideration of the foregoing recitals, which are incorporated by reference, and 
the covenants and promises contained in this Linking Agreement, the parties agree as follows: 
1.
Term of Agreement.
A.
As provided in the Cooperative Agreement, purchases can be made by governmental entities
from the date of award, which was March 1, 2022, until the date the contract terminates on
February 28, 2027, unless the term is extended by mutual agreement of the parties to the
Cooperative Agreement.  The Cooperative Agreement, however, may not be extended
beyond February 28, 2027.  The initial period of this Agreement is the period from the
Effective Date of this Agreement until February 28, 2027.
2.
Scope of Work; Terms, Conditions, and Specifications.
A.
Contractor shall provide City the supplies and/or services identified in the Scope of Work
attached as Exhibit B.

2 
10/05/2023 
 
B. 
Contractor agrees to comply with all the terms, conditions and specifications of the 
Cooperative Purchasing Agreement. Such terms, conditions and specifications are 
specifically incorporated into and are an enforceable part of this Agreement.   
 
3. 
Compensation.  
 
A. 
City shall pay Contractor compensation at the same rate and on the same schedule as 
provided in the Cooperative Purchasing Agreement, which is attached hereto as Exhibit C. 
 
B. 
The total purchase price for the supplies and/or services purchased under this Agreement 
shall not exceed Six hundred forty-two thousand, six hundred. and sixty-five dollars 
($642,665) for the entire term of the Agreement (initial term plus any extensions). 
 
4. 
Cancellation.  This Agreement may be cancelled pursuant to A.R.S. § 38-511. 
 
5. 
Non-discrimination.  Contractor must not discriminate against any employee or applicant for 
employment on the basis of race, color, religion, sex, national origin, age, marital status, sexual 
orientation, gender identity or expression, genetic characteristics, familial status, U.S. military veteran 
status or any disability.  Contractor will require any Sub-contractor to be bound to the same 
requirements as stated within this section.  Contractor, and on behalf of any subcontractors, warrants 
compliance with this section. 
 
6. 
Insurance Certificate.  A certificate of insurance applying to this Agreement must be provided to the 
City prior to the Effective Date.  
 
7. 
E-verify.  Contractor complies with A.R.S. § 23-214 and agrees to comply with the requirements of 
A.R.S. § 41-4401. 
 
8. 
No Boycott of Israel.  To the extent A.R.S § 35-393 through § 35-393.03 are applicable, the parties 
hereby certify that they are not currently engaged in, and agree for the duration of the Agreement to 
not engage in, a boycott of goods or services from Israel, as that term is defined in A.R.S § 35-393. 
 
9. 
Uyghur Forced Labor Prevention Act (UFLPA). Contractor certifies that it does not currently, and 
during the term of this Agreement, will not use: 
 
a.  
the forced labor of ethnic Uyghurs in the People’s Republic of China;  
b. 
any goods or services produced by the forced labor of ethnic Uyghurs in the People’s 
Republic of China; and  
c. 
any contractors, subcontractors or suppliers that use the forced labor or any goods 
or services produced by the forced labor of ethnic Uyghurs in the People’s Republic 
of China. 
10. 
Attestation of PCI Compliance.  When applicable, the Contractor will provide the City annually with 
a Payment Card Industry Data Security Standard (PCI DSS) attestation of compliance certificate 
signed by an officer of Contractor with oversight responsibility. 
 
11. 
Notices.    Any notices that must be provided under this Agreement shall be sent to the Parties’ 
respective authorized representatives at the address listed below:

3 
10/05/2023
City of Glendale 
c/o Julie Ossege
7070 W. Northern Avenue
Glendale, AZ 85303
and 
Hazen and Sawyer, P.C.
c/o Curtis D. LeCourter 
1400 E. Southern Avenue, Suite 340
Tempe, AZ 85282
IN WITNESS WHEREOF, the parties hereto have executed this Agreement as of the date and year set 
forth above. 
“City”
“Contractor” 
City of Glendale, an Arizona 
Hazen and Sawyer, P.C., 
municipal corporation 
a New York Corporation
By: 
____________________________  
By: 
____________________________ 
Kevin R. Phelps
Name: Curtis D. Courter
City Manager
Title: Associate Vice President
ATTEST:
___________________________ 
Julie K. Bower   
(SEAL)
City Clerk
APPROVED AS TO FORM: 
___________________________ 
Michael D. Bailey
City Attorney

LINKING AGREEMENT 
BETWEEN 
THE CITY OF GLENDALE, ARIZONA 
AND 
HAZEN AND SAWYER, P.C. 
 
EXHIBIT A 
ON-CALL CONSULTING FOR ENGINEERING AND ARCHITECTURAL SERVICES 
CATEGORY 2: WATER/WASTEWATER, CITY OF BUCKEY CONTRACT NO. 2022003.18

LINKING AGREEMENT 
BETWEEN 
THE CITY OF GLENDALE, ARIZONA 
AND 
HAZEN AND SAWYER, P.C.  
 
EXHIBIT B 
Scope of Work 
 
Lead and Copper Program Implementation per the attached scope of work.

LCRR Phase 2 Final Scope of Services 
City of Glendale 
1 
EXHIBIT B 
 
Lead and Copper Rule Revisions 
Phase 2: Program Implementation 
 
City of Glendale 
 
Scope of Work 
FINAL 
January 16, 2024

LCRR Phase 2 Final Scope of Services 
City of Glendale 
2 
Introduction 
This approach outlines how the Hazen team will work with the City of Glendale (City) to complete Phase 
2 of the LCRR compliance program. The LCRR was promulgated by the United States Environmental 
Protection Agency (USEPA) on January 15, 2021 and became effective on December 16, 2021. The 
LCRR includes a 3-year timeframe for utilities to meet the new regulatory requirements with a 
compliance deadline of October 16, 2024. As of December 2023, less than 11 months remain for LCRR 
compliance. State primacy agencies retain the option to accelerate this timeline; however, the Arizona 
Department of Environmental Quality (ADEQ) is planning to match the EPA’s compliance deadline. The 
LCRR compliance deliverables in the state of Arizona include the following: 
• Initial Lead Service Line (LSL) Inventory (Inventory Framework completed in Phase 1) 
• Tap Sampling Plan 
In late November 2023, the USEPA also released the pre-publication Lead and Copper Rule 
Improvements (LCRI) which are intended to build upon LCRR requirements and ensure all service lines 
are confirmed as non-lead and that all LSLs and galvanized requiring replacement (GRR) are replaced 
within a 10-year period. The LCRI is anticipated to be finalized in 2024; however, the LCRI is not 
anticipated to become effective until 2027. The LCRI compliance deliverables include the following: 
• October 2027 Deliverables 
o LCRI Baseline Inventory 
o Service Line Replacement Plan (pending LCRI finalization by October 16, 2024) 
o Annual Updates: 
▪ 
Service Line Inventory 
▪ 
Revised List of Compliance Sample Sites 
• October 2034 Deliverables 
o Non-Lead Validation at 95% Confidence Level 
• October 2037 Deliverables 
o 100% Unknown Service Line Verification 
o 100% LSL and GRR Replacement 
Project Understanding and Approach 
The LSL Inventory must include the utility and customer-owned portions of each service line and indicate 
whether the service line material is lead, galvanized requiring replacement (GRR), non-lead, or lead status 
unknown. During Phase 1 efforts, it was determined there are 65,873 service lines in the service area with 
644 unknowns on the utility-side and 35,681 unknowns on the customer-side;35,779 distinct locations 
with an unknown on either side of the meter. In November 2023, ADEQ formally revised the LSL 
Inventory Quick Reference Q&A Guidance (ADEQ: LCRR Quick Reference Q &A (azdeq.gov)) which 
effectively reversed prior approvals of LSL Inventory criteria utilized during Phase 1. Initial estimates 
indicate that approximately 2,000 additional service lines will be recategorized as lead status unknown; 
however, additional updates and review of the revised criteria are needed.  
The proposed compliance program schedule for the City is shown below in Figure 1.

LCRR Phase 2 Final Scope of Services 
City of Glendale 
3 
 
Figure 1: Proposed LCRR Project Phasing 
Figure Notes: *Indicated compliance actions and deliverables are only required for water systems with 
LSLs, GRR, and/or lead status unknown service lines per the LCRR requirements. 
Phase 2 of the LCRR Compliance Program is aimed to fulfill the City’s goal to have zero lead status 
unknown service lines. In order to reach this goal, field work must be completed for a prescribed quantity 
of lead status unknown service lines based upon the selected indirect method. Additionally, site review of 
field verified service lines and an updated LSL Inventory will be needed to integrate field work findings. 
All field verified service lines will need to be categorized as non-lead, and the City will need to conduct 
additional investigation of any customer-side galvanized service lines through record review or ADEQ 
coordination, if customer-side galvanized service lines are identified downstream of a service line that 
was or is lead status unknown. Beyond the LSL Inventory, compliance sample sites and sampling 
protocol as well as will be required to fulfill two additional compliance requirements. Finally, customer 
education and outreach is a critical component of LCRR requirements in the future after the compliance 
deadline including for systems with a “No Lead Service Line Verification”.

LCRR Phase 2 Final Scope of Services 
City of Glendale 
4 
Scope of Services 
The Scope of Services includes the necessary tasks to complete Phase 2. The following tasks will be 
performed as part of this project: 
• Task 1: Project Management and Meetings  
• Task 2: Field Work Preparation 
• Task 3: Field Work Review and Inventory Updates 
• Task 4: Sampling, Monitoring, and Protocol 
• Task 5: Customer Outreach and Education 
• Task 6: Regulatory and Third Party Coordination 
• Task 7: Owner’s Allowance

LCRR Phase 2 Final Scope of Services 
City of Glendale 
5 
Task 1: Project Management and Meetings 
Hazen will provide project management services throughout the project, including preparation of billing 
statements, document control, record keeping, and project budget and schedule tracking.  Hazen will also 
track project performance including budget and schedule, identify any outstanding issues, and hold 
progress meetings/conference calls with City staff as necessary. 
Our management approach includes well-defined roles and responsibilities of each resource and the lines 
of communication among team members and the City, as well as plans for maintaining QA/QC. Hazen 
will provide an initial schedule with milestones using MS Project to guide the project. 
Project Kick-Off Meeting and Review: Hazen will conduct a 1-hour virtual kickoff meeting with the 
City to introduce our project team, establish lines of communication, review LCRR and LCRI 
requirements, and review the scope of services and project schedule. 
During the kickoff meeting, Hazen will verify the City’s team participants, needs, and schedule. 
Project Progress Meetings: Hazen will coordinate with City throughout the duration of the project. 
Coordination meetings will be held between the Hazen and the City, as needed (up to 7 meetings). 
Progress Reports: Project progress will be summarized each month in invoice progress reports. 
Deliverables: 
• Kickoff Meeting – agenda, slides, action items, and key takeaways 
• Project schedule 
• Meeting minutes for monthly project progress meetings, which will be billed monthly  
• Monthly progress reports, which will be billed monthly for those that occurred in that month. 
Assumption: 
• Conduct a kickoff meeting and virtual monthly progress calls, as needed, during a project 
duration (estimated at 7 months). 
• The work effort included within this proposal utilizes regulatory guidance as of 12/15/2023. 
Task 2: Field Work Preparation 
Revised Inventory Framework and Service Line Identification Plan: Following the November 2023 
ADEQ guidance, the City has approved the revision of the inventory framework to utilize non-lead 
designations based on a January 1, 1990 service line installation date and >2” service line diameter. These 
revisions will be completed with the current inventory framework prepared during Phase 1. Additionally, 
ADEQ’s revised field verification requirements requires further regulatory coordination, analysis, and 
documentation within the Service Line Identification Plan 2.0. Hazen will conduct a revised subdivision 
analysis with ADEQ’s 2023 subdivision criteria to determine the revised quantity of sites for field 
verification.

LCRR Phase 2 Final Scope of Services 
City of Glendale 
6 
Mobile App and Dashboards: Hazen will develop a Field Maps app to directly integrate field 
verification findings into the Lead Service Line Inventory Database. The Field Maps app will cover the 
required service line verification points as required by ADEQ. Service line sites may be assigned to 
separate Contractor(s) or City personnel, as desired, within the app platform. Instructions for utilization of 
the Field Maps app will be included in Task 3’s Training Materials. Additionally, a Field Verification QC 
Dashboard will be developed for the review of service line field verification submissions from the Field 
Maps app. 
Training: Hazen will host one three-hour training session for Contractor(s) and/or City staff to meet the 
ADEQ field work training requirements. Hazen will coordinate with ADEQ on training materials to 
ensure they meet ADEQ requirements. 
Workshop with Council: Hazen will attend and prepare for one workshop with Council in support of the 
City. Hazen will answer questions, as needed, and if directed to. 
Deliverables: 
• Contractor and/or City Staff Training. 
• Field Verification Mobile App. 
• Field Verification QC Dashboard. 
• Workshop Talking Points and Presentation Material, if needed. 
Assumptions: 
• The Field Verification Mobile App will be developed through ArcGIS Field Maps app 
available in the Apple and Google Play app stores. 
• The cost of data acquisition for the revised subdivision analysis will be covered by the City. 
Task 3: Field Work Review and Inventory Updates 
Identification Review: Hazen will coordinate with Contractor(s) and/or City staff to review Field Maps 
mobile app field verification submissions in the Glendale ArcGIS Online Field Maps QC platform. Each 
submission will be designated as one of the following: 
• Not Inspected (Orange Circle): Awaiting field verification by staff 
• Inspected – Completed (Green Circle): Field verified by contractor, approved by Quality 
Control staff. 
• Inspected – Submitted (Blue Circle): Field verified by contractor, awaiting review by Quality 
Control staff. 
• Inspected – Rejected (Red Circle): Field verified by contractor, rejected by Quality Control 
staff. 
• Inspected – In Progress (Yellow Circle): Field verified by contractor with unusual result, 
marked for advanced Quality Control or site/entry repair. 
• Obstacle (Yellow Diamond with Exclamation Point): Obstacle encountered by contractor. 
Contractor may need to revisit site to complete field verification if alternates are unavailable.

LCRR Phase 2 Final Scope of Services 
City of Glendale 
7 
Hazen will track Field Maps fields and high-level Contractor progress in the Field Maps Dashboard. 
Inventory Updates: Throughout the field identification effort, Hazen will update the LSL Inventory to 
provide an estimated quantity of remaining unknowns. At the completion of field identification, the LSL 
Inventory Template will be populated with the final LSL Inventory results for future detailed inventory 
submission requirements by ADEQ. 
Deliverables: 
• Updated LSL Inventory 
• LSL Inventory Template 
Assumptions: 
• The City will be responsible for conducting field survey efforts using City staff or a contractor. 
• During Phase 1, Hazen estimated approximately 13,000 sites for field verification within the 
City using preliminary subdivision estimates at 20%, as required by ADEQ in November 2023. 
Additionally, approximately 2,000 service lines are now considered lead status unknown under 
revised criteria. For planning purposes, 15,000 sites are estimated for field verification and 
field work review. 
• Based on efforts for other communities in Maricopa County, contractors are completing 
approximately 1,500 sites per month using the methods that the City will likely apply for field 
verification. At this rate with three (3) teams working in parallel, it is estimated to take 
approximately 6 months to complete field verification of approximately 15,000 required sites. 
An additional 14% of sites is added to consider obstacles and site reassignments for a total of 
17,000 sites. 
• Field verification contractor submissions will not exceed 17,000 sites. The estimated time to 
review each site, coordinate with contractors, and provide alternates, as needed, is 8 mins, 
which equates to 1,968 hours. 
• The City will backup all collected data weekly with snapshot data backup. The City will 
provide the Contractor access to the Glendale AGO, as needed. 
• The field verification crews will maintain a viable mobile device and upload all service line 
data into the Field Maps mobile app without need for manual entry by Hazen staff. 
• Leaded solder testing is not currently included in this effort. 
• Identification of disadvantaged communities is not included in this effort. 
Task 4: Sampling, Monitoring, and Protocol 
Hazen will develop an LCRR Compliant Sampling Site Selection including recommendations for revising 
the standard monitoring sample site pool based upon LSL Inventory results and existing sample sites to 
reflect the new tiered structure. Additionally, Hazen will update sampling protocols to account for 1st and 
5th Liter sample requirements in the LCRR, as applicable. The LCRR Compliant Sampling Plan will 
include the following components: 
• Detailed list of selected sites

LCRR Phase 2 Final Scope of Services 
City of Glendale 
8 
• Revised sampling protocol 
• 1st and 5th liter sampling SOPs, as applicable 
• List and map of schools and childcare facilities which includes both public and private schools 
and childcare facilities and year of construction for the facilities, as available 
To further assist the City in ongoing compliance with the LCRR, Hazen will prepare a Sampling 
Dashboard that tracks historical sample sites, sample values, and provides new sample sites, as needed. 
Sites requiring shorter notice times due to sample results will be included. 
Deliverables: 
• 
Updated list and map of compliance samples sites with year of construction for the facilities, 
as available. 
• 
Sampling SOPs for 1st and 5th liter sampling. 
• 
Sampling Dashboard 
Assumptions: 
• 
Compliance Tap Sample Site Selection may require updating based upon future service line 
material verification results.  
• 
The LCRR initial inventory requirements and sample site selection notably vary from the 
LCRI. Thus, additional review and revisions of the selected sample sites after the October 16, 
2024 deadline is recommended. 
Task 5: Customer Outreach and Education 
Hazen will prepare Customer Outreach materials including topics for educational material, sampling 
instructions, sampling results, and additional customer notifications. Many of these deliverables are 
required for all water systems to provide to customers under certain compliance scenarios. Additionally, 
distribution system and site assessment (DSSA) materials are only required if an individual compliance 
sample exceeds 10 µg/L. Hazen will coordinate with ADEQ, as needed, during the project timeline to 
ensure materials meet ADEQ requirements. 
Deliverables: 
• Educational Material: 
• POU Installation and Use Instructions (1 Page – Front & Back) 
• Lead in Drinking Water Educational Material (1 Page – Front & Back) 
• Find-and-Fix with POU Instructions (1 Page – Front & Back) 
• Annual Educational Information for Schools and Childcare Facilities (1 Page – Front  
and Back) 
• Sampling Instructions: 
• Routine Compliance Sampling Instructions – 1st Liter Only (1 Page – Front & Back)

LCRR Phase 2 Final Scope of Services 
City of Glendale 
9 
• Customer Requested Sampling Instructions (1 Page – Front & Back) 
• DSSA Sampling Instructions– 1st Liter (1 Page – Front & Back) 
• DSSA Sampling Instructions– 1st and 5th Liter (1 Page – Front & Back) 
Front & Back) 
• Sampling Results: 
• Routine Notification of Results (Letter) 
• Action Level Exceedance Notification (Letter) 
• School & Childcare Notification of Results (Letter) 
Assumptions: 
• Two revisions to the draft customer communication materials will be included. The first round 
of revisions will be completed in Microsoft Word, and the second round of revisions will be 
completed on a PDF version with graphics. 
Task 6: Regulatory and Third Party Coordination 
ADEQ Coordination: While ADEQ is requiring utilities to complete their LSL Inventory and Tap 
Sampling Plan by October 16, 2024 under the LCRR, they are still developing the standard/approved 
methods and will likely delay the preparation of a primacy package until after the compliance deadline. 
Additionally, ADEQ is providing case-by-case approval to inventory narratives and methods for service 
line material verification. Thus, coordination between ADEQ and the City to ensure regulatory 
compliance is a top priority for this project. Hazen will attend up to four calls with ADEQ to 
communicate the approach and findings. Hazen will also provide guidance to the City to further support 
coordination and approval of Phase 2 deliverables. 
Following the release of the LCRI, ADEQ is working to coordinate all LCRR compliance requirements 
for the planned implementation of one primacy package. Hazen will coordinate with ADEQ on this effort 
and provide recommendations on the inventory effort for the initial 2024 deadline. 
AMWUA Coordination: Hazen will attend up to 4 Arizona Municipal Water Users Association 
(AMWUA) LCRR Meetings, and coordinate with other AMWUA agencies in support of the City. 
Application for “No LSL Verification”: Once all required field verification sites are completed and 
confirmed as non-lead service line material coordination with ADEQ will begin to assist the City in 
reaching a non-lead designation, if the field verification work and inventory results align with ADEQ’s 
requirements. If acquired, the non-lead designation will allow the City to opt out of the public-facing 
website and annual customer communication service line material notification requirements under the 
LCRR. 
Deliverables: 
• Material verification findings summary 
• Request for a “No Lead Service Lines Verification” designation

LCRR Phase 2 Final Scope of Services 
City of Glendale 
10 
Assumptions: 
• Hazen will conduct regulatory coordination meetings with ADEQ on the material verification 
methods and development of the inventory throughout the duration of the project. 
• Written verification from ADEQ on service lince material identification methods will be 
received prior to commencing field work in Task 3. 
• No more than five (5) AMWUA meetings on the LCRR will take place in 2024. 
Task 7: Owner’s Allowance 
The Owner may elect to utilize this allowance in writing to Hazen. Example of the Owner’s allowance 
usage may include the customer survey revisions, QC, and additional field verification. 
Project Schedule 
Our proposed project schedule is provided below. The anticipated Notice to Proceed (NTP) date is 
tentatively prior to January 2024. It shows the planned progression of the project starting with the Kick-
off Meeting and ending with the final customer outreach and education deliverables. The schedule 
identifies the major tasks and subtasks that need to be undertaken, as well as activities that will need to 
occur concurrently. We are proposing a timeline of completing the project within 7 months.

LINKING AGREEMENT 
BETWEEN 
THE CITY OF GLENDALE, ARIZONA 
AND 
HAZEN AND SAWYER, P.C. 
 
EXHIBIT C 
 
METHOD AND AMOUNT OF COMPENSATION 
 
Consultant will be compensated for completed work per the attached Fee Proposal. 
 
NOT TO EXCEED AMOUNT 
 
The total amount of compensation paid to Contractor for full completion of all work required by the 
Statement of Work must not exceed $642,665 for the entire term of the Agreement. 
 
DETAILED PROJECT COMPENSATION 
 
Consultant will be compensated for completed work. per the attached Fee Proposal.

LCRR Phase 2 Final Scope of Services 
City of Glendale 
11 
EXHIBIT C 
The total fee associated with this project is shown on the below table using contract rates. The work 
would be billed time and materials up to the not-to-exceed amount shown in the table. 
  
Task No. 
Task Name 
Fee 
Task 1 
Project Management and Meetings 
$         32,295 
Task 2 
Field Work Preparation 
$         80,500 
Task 3 
Field Work Review and Inventory Updates $      369,790 
Task 4 
Sampling, Monitoring, and Protocol 
$         33,500 
Task 5 
Customer Outreach and Education 
$         47,120 
Task 6 
Regulatory Coordination 
$         29,460 
Task 7 
Owner's Allowance 
$         50,000 
Base Fee 
$      642,665