Amendment No. 1 to Agreement with MGC Contractors Inc.
Extracted text (via ocr_local)
26346 characters
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
C23-1008-1
Project Name: THUNDERBIRD RESERVIOR UPGRADES - GMP1A
Project No.: 212233.1
Amendment No: 001
Date:
This Amendment to that certain Standard Form Agreement dated September 26, 2023 by and between the City of
Glendale and MGC Contractors, Inc., (CM@Risk) for services, deliverables and work related to Project No.
212233.1, Project Name: Thunderbird Reservior Upgrades - GMP 1A, (the “Agreement”) is made and entered into
effective this 9th day of April , 2024.
1. This Amendment #001 establishes a Guaranteed Maximum Price (“GMP”) and Construction Phase Fee
for Construction Services and incorporates such terms into the Agreement, making the Agreement effective
for Construction Phase Services:
a. The total fee for Construction Phase Services, which is included in the Guaranteed Maximum Price (GMP)
as defined under the Agreement, shall be fixed at Fifty-Six Thousand, Five Hundred Ninety and 94/100
Dollars ($56,590.94). This amendment for GMP1A is part of a multi-phase agreement for the Thunderbird
Reservior Upgrades Project.
b. The Guaranteed Maximum Price (“GMP”) for Construction Services, as defined under the Agreement, shall
be Seven Hundred Sixty-Nine Thousand, Thirty-Four and 14/100 Dollars ($769,034.14). This amendment
for GMPIA is part of a multi-phase agreement for the Thunderbird Reservior Upgrades Project.
c. The total compensation under the Agreement, as amended by this Amendment, shall be:
Pre-Construction Phase Construction Phase Total
Original Agreement: $75,582.00 $5,878,219.61 $5,953,801.61
Previous Amendments: $ $ $
This Amendment: $ $769,034.14 $769,034.14
Total (including this
Amendment): $75,582.00 $6,647,253.75 $6,722,835.75
2. DELETE the blank template “Exhibit C — Cost of the Work — Schedule of Values” from the Agreement,
and ADD “Exhibit C—- MGC Contractors, Inc., Cost of the Work — Schedule of Values” dated 26 January
2024 (5 Pages), attached herein.
3. ADD “Exhibit E —- Construction Documents necessary to define Scope of Work and deliverables for the
Construction Phase Services, including plans, designs, drawings, specifications and other required
Contract Documents” dated 26 January 2024 (30 Pages), attached herein.
4, ADD “Exhibit F - Statement of All Clarifications and Assumptions” dated 26 January 2024 (1 Pages),
attached herein.
5. ADD “Exhibit G— Schedule of Major Milestones” dated 26 January 2024 (1 Pages), attached herein.
6. All other provisions, terms and conditions of the Agreement shall remain unchanged and in full effect.
(Signature on following page)
City of Glendale Standard Form Agreement Between Owner and CM@Risk (May 15, 2023)
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
IN WITNESS WHEREOF, the Parties hereto have duly executed this Amendment, effective as of the date first
written above.
OWNER CM@RISK
City of Glendale MGC Contractors, Inc.
5850 W. Glendale Avenue 4110 E. Elwood St.
Glendale, AZ 85301 Phoenix, AZ 85040
By: Its Authorized Representative: YAS AUAStized Representative:
Bigan Forster
Signature Signature “
“Printed Name a “Printed Name
Title : Title .
3/25/2024
Date Date
ATTEST:
Julie K. Bower (SEAL)
City Clerk
APPROVED AS TO FORM:
Michael D. Bailey
City Attomey
DESIGN PROFESSIONAL
Wilson Engineers, LLC
1620 W. Fountainhead Pkwy
Tempe, AZ 85282
By Its Authorized Representative:
_-the Tell”
Signature (Reviewed in accordance with the “Agreement Between Owner and Design Professional” Section 4,8.1.14
of Exhibit A “Scope of Services for the Design Professional”)
Stephen Todd
Printed Name
Principal
Title
March 21, 2024 _
Date
City of Glendale Standard Form Agreement Between Owner and CM@Risk (May 15, 2023)
DocuSign Envelope ID: 6894B9AE-F 1FB-432F-8FFC-311770B6927D
EXHIBIT C
Cost of the Work
(One (1) page - template)
(5 pages - final document to be included with GMP Amendment)
See Attached
City of Glendale Standard Form Agreement Between Owner and CM@Risk (May 15, 2023)
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
GUARANTEED MAXIMUM PRICE (ADJUSTMENT TO GMP 1)
Project Number: _212233.1
(Date: 1/26/2024
Project Title: Thunderbird Reservoir Upgrades - Guaranteed Maximum Price Adjustment
ICONSTRUCTION SERVICES AMOUNT
DIRECT COSTS
1 Cost of Construction - Thunderbird Reservoir Upgrades GMP 1A $ 538,961.29
I SUBTOTAL DIRECT COSTS| $ 538,961.29
INDIRECT COSTS ae
iA. General Conditions (Excluding Bonds and Insurance) 0.00%| $ -
B. Payment and Performance Bonds 1.00%] $ 7,690.34
Ic. Insurance 2.00%| $ 15,380.68
D. SUBTOTAL GENERAL CONDITIONS COSTS| $ 23,071.02
E. SUBTOTAL DIRECT AND INDIRECT COSTS | $ 562,032.31
F. [Construction Fee (Overhead & Profit) (on Cost of Construction only) I 10.50%] $ 56,590.94
G] SUBTOTAL DIRECT AND INDIRECT COSTS (INCLUDING FEE)| $ 618,623.25
[Sales Tax $ 30,410.89
I. Direct & Indirect Cost Plus Sales Tax $ 649,034.14
J. Allowances $ 120,000.00
'L. Total GMP Amount $ 769,034.14
5 ; Bop |
| %2L'6 60) ‘et Jo aBequaoieg
301 SJELAIe) 1£304 10Ge7 3803 12201
dov'zs $ | 63'8zs‘0z $ | 6zT96‘8Es ES
$ | O'v00'2 $ | Oo'vES's $ | 22'6ee $ | .suone007 9% SINT YIM qng Suryeod yssy| LS@
$ | s"€09°S $ | 02'490'L $ | eS ppt $ | suotye007] 6b S}NN pure sjfog SurssiW eovjdoy 9'St
$ | 09°E08'T $ | OO T9Z'% $ | z9°ESZ $ eq € So}e[q JOF OOURISISSY PlOM / SUTIN jo suleIg ose
$ | 92's83'o 09°L19°E $ | O8'9TS $ ici Z OT-g ted syog ues] 5% 1984 OTL $'Sz
0000's $ - 00'000°S $ | 00°000‘S $ 1 T Salosseooy pue S}]Og/s}nN JO eseyoing €Se
= O€ EIS‘ TSI $ | ese29%> $ eg 9% soqeld [va ¢) pue suring (ea ¢7) Jo Furye0D Zsz
a 00°00T'S $ | 00°002'T $ ict € SayeTq Woddng (ee ¢) SupIOM T'Se
9000's $ | 8zZez‘LZT $lorees‘sst $l] oteéee‘est ¢ ST t SDNIGNIM NOILOGASNI OT-Ga - SZ 4
00e'T $ | Oz er9"8Tt $ [0c 6622 $ | 62'rEo'T $ | suoneooT Lz syroddng Surprem 10; juowdinbgy pue 10qe7 [euontppy eS.
$| - 00°000'9+ $ | 0z€02'T su eO07] 4 suming 07 [923g Woddng jo Suprem| fax
zo9'e $ - Ov'z09'E $ | Geel SUOT}BOO7] Le 1203g Yoddng feuon!ppy| 8%,
zo8'y $ | oz ep9‘st $ | oo'tes‘2z $ | oo'tps‘zz $ SI t SLUOddNS LNIA UNV HOLVH Ggaaav - £Z 4
$ | cr'16s $ | 80°%92 $ | 80°%9L $| a T yoddng Surprem 103 juotudinby puy 10qey TeUonIpPy| Eatd
beCSI'T OC 68E'T 02'68E'T $ eq T quauntga Woddng Jo; ywourdinby pue 10qe’] [euorppy STZ
= 09°866 09°866 $ 1 IL SUONSUTALIOL Pue 11M [TeISU] Y YsTUIN Patd
- 00'L12'Sé 00°LTZ‘SZ $l] 07 I xog-f 9 IMpuoD Lr]/vorsngy] [ey] y ysTuIMy e1s
$ $ | OO'ZIT'ST $ | L9°8TS'% $ ici 9 Sjexovig jioddng Teuorippy| TIS
$|_- $ | 8a'Zer‘e7z $ | T9°06T $ 31 Sil unoyeid pue AvmATeN MON TTeISU] 9B YsTUMY T'1@
F $ | osezz'T $ | ot :tz6‘so $ | 9T'tz6‘s9 $ SI I WAOALV 1d GNV AVMYIVM ‘AALLINSNVAL DNILVOIGNI THAGT MAN - LZ. Tz
$|]_- $ [| 0O'LzP'TZ $ | 00'22bTZ $| 307 I (AS2L) SHMPUOD TTeM {oArssoy FupsH| oeOTIy U'8T
$ : $ | oo'LzH‘TzZ $ | oo'zzr'tz $ si I (w21) SLINGNOD TIVM NIOANISAA ALVIOTHA - ST st
$ | zLzss'9 $ | ZLose'Z $ | Zb'0% $ 1 09e syed WEE SSOTE Jo VoHLTTeIsUT +91
${ - $ | oo'sse'T glaze $ 31 o9€ TEM 9391909 Jo ,09E IOJ NAD €or
S6l'S, $ = $ | OO'S6T'% $ | 00'S6T‘% $ 301 I UOHeTeISsU] aye[g Jag Joy sroyouy spo] ari
OST‘'SZ $ a $ | OO'OST'SZ $ | 98'69 $ 31 O9€ uoreoniqey eI Jeg SUIYSE[A SSOTE or
speZe $ | ZL'z8s'9 $ | zz'eso'9e $ | zzeso'9e $ S1 Ir ALV1d LNAG SS9TS TYNOLLIGGV - 9T ot
$] - $ | oo0ET‘S $ | Oo°OET'S $]y0T i suopeuluey pue Sunt [aras
$ - $ | 00'9bZ'0S $ | 00'9bZ‘0S $ 30T I suoreleysu] Xog-¢ pue soyoitMg woIsnIjy] ‘yMpuod, Ub
P $ 2 $ | oo‘9ze'ss $ | oo'9ze'ss $ SI t SWHVTV NOISNYLNI $0-da - +T $I
$ - $ | 0o'SLb's $ | OS LEL'S $] yorg z Blowre.) SUNSEXY [/e}SUIOY PUL SAOUTOY TEI
$ 2 $ | oo'sZb's $ | oo'szt‘s $ sT is VaaWVd ALRINOGS - ST €t
$ = $ | CO'000'TT $ | oo'osL'% $ | seyoveH ¢ suyjing pue sureeg yoddns jo Surplam| fara
$ - $ | OO'brS‘ES $ | OO-98E'ET $ yoeg v sayoqeH jooy jre3suy pue ysrumy’ Tal
: $ e $ | oo'bps‘b9 $ | OO'pyS‘y9 $ ST 3 SLUOddNS GNV SAHO.LVH A0OU - ZT ZI
$ | OO TZPLZT $ | 09°TZ9'8T $ | 206907 $] aed 6 90-Ca od sjaxovig yloddng sepmp TeIsay O01
$ | Os OTL‘ $ | os OTe6 $ | Tloee't $$] youd Z 90-da Jad syayoeig Woddng uring soeday SOL
$ | €6°66 $ | €6°SOT $ | €6°SOT $ | yoeg is sioyouy pue dyg wayeg ND OI
$|- $ | os 's9T‘ze $ | ve'sse'T $| fea oT 90-ag ted syioddng mon yspumy Exes
$ = $ |(06'922'9) $ |ler'269) $| youd 6 syioddng snoraerg 10F yonpeq, ZO
ZSZ‘ST $[- $ | e2°7Se'STt $ | ez'zse'st $] 07 T 90-aa tad speoyew yoddng sepip Ot
zsz‘st $ | se-zez‘oz $ | tz'6zt‘6és $ | tz'6zt‘6s $ SI t SLYOddNs AACID ANV NITANd 90-da - OT or
dL spepaazeyy |[ejOL doqey] 1210, ys09 nun wy MO wopdjz9saq / awey jueunsnipy #yuoursn[py
WOHINAJSUO,) JO SOD
VI did Sopeisdy WoArosoy parqiopunyy,
CLZ69S0LL} /€-0448-4ZEr-G4 | J-AVESHESY :C] Sdojaaug uBjsno0q
$ 00°001'S = = oo00T's 00°002"T Val e 60-Ca ind Sareld PIM POPPY - 1ST
00°000°9b = = ‘00°000°Ob oz 02 PS Zz Sieg epsuy lemons Poppy - 6 eC
00°000'TT = = 00°000TT Ty 0b PS Z@ SHupuedO jemyjonyg ye SUIP[M PePPV - CCL
[oo oores i = roOrZ9 SI T DTT UID TTS SAPO |
$ $ | severe, = a Eradaaad T9061 aT Ea WHO eld @ ACMTEM LT Pea TTC,
$ $ | oopys'es = 5 O0"PbS"ES o0'9Re ET va v SaqoTeH Joo Ped TCI
F $1] 8r 9e0°9L i __- = "9E0" Si T OTT anory FUypIME wISyEoA|
$ $|__- $ = $[eseze $ $ | SSezE $ [ze $ Va ‘002 SIsyseM UOUSL = TOT
3 s1_- s In siavere —_$ _sleseze srt bith a tt
$ OO'LIZ'Se = a O0'L1e'Se OOLIZ St 7S T THIS SHITE B “SoXOG IMPUOD QUO “LIT Ped - O16
$ 00'LEb'TZ = - OO L2b TS 00°LzH'TS ST T SIMPUSD TEA SuNsH UsTeo/TeMOT - TST
00°9bz'0S = a 00°9bz'0S 00°9bz 0S. ST T_| SARS SSOTE 8 "BexOG TNpuoD OuD UBTy UOISsHAUT - ToT
00'Szb'S S s| — $s 00°S24'S Os Zee wBiouIeD SUNS TeIsU]-oa Y eaowoy - TET
Oo'S9e'ZOT <1 REE z [oo-sse"2oL sT st SUT ORTOP WES
$ Sloeeistat § = s| = 3 Os EIS tet 65°8L9°b va 9%_| _SuOTIIaTUOD pe a pue STapiiH Jo SupeoD GO-da - CSz
$ g| - = ozs! $¢ OOwITST OOTIT'ST RS T Sproddng eanvorng ITT - 6 Te
$|_- - os'sol'%e_ Jos'sor'zz EERtTa val oF Sjayoeig woddng posiaey - © OT
$ Sa = losoiz9) 106°927'9) Tev"z69) va 6 Syaxjserg TeUIaO Foy OMPAC - TOT
z §] oeeis tat i oF 000 Te —& OG ers car SI i ee
$ ${ - $ = $looosi'sz F $]ooost'se $ | 98°69 $ aT age SovBid JUST SSOTE poyweouded - TOT
2 (wee a ES Ss looostsz —¢ S [ovrostse 3 ST
= = Ov'8s9 $ | oF'aso or'or $ a1 OF TUtTETID-O [AIS PAZTUOATED .9X,9 = TEC]
= ~ OO Pee $ | 00 prE'z CL bT $ aT 002 PFU [PIS POTUCATED .bX.b - VES
o 31 [or cose $ [oF cos" ST T "6D ATTONS TIO TURIN PUT)
$ $ | 09°866 a a ¢ 09°866 09°866 $ Va T Wavy UOSAIO] Gey LTT aeUIULIL we ON - FTC
$ | oo'0eT's = i $ (00°0eT'S oszect va ¥ Say WOISKAU] GOTH Jooy STeUTUAIAL *— SM - CPL
= $1] o9szr'9 ; a Gun @ [oo eer'o ST T —_ ou Apssy SepaIsUg|
$loosset _$ = $|_- $ $loosset _$[ ze $ a1 09 Tem Hoarosay JO Ydd - POT
3 $loosse) ¢ = (ape = Sloosset #! Tr t STM BSspArsy wor ToUwUy Puy FUT WoL TuOIUIOTS|
$| - = oosel% 00'S61'% ooserz ST T Sioyouy SSpamn SSOTE - COT
i ims = SRL § 2ESTSL Zestgz _$ ST Sod pue sInN .87S - 1 OL
= tL “oro! $ ZO ST BWwig WAToD|
alee = if =23 == == -
eS See e o ao rs La!
Ng pue 10}d¥.1j]U0NqGNS
VI dD Sopersdy moarosoy prquepungy, - aTepuaty Jo AD
CLZE9GOLL1 LE-0448-4ZEP-As | J-AVEAPER’ ‘CI edojaauz uBlgn50q
00°000°071_$ JADNVMOTTV dD TVLOL ‘ad
00°000°07 $ ST I SIappeT/siiej}s ssaooy AeMyeM JOOY [euoNIppy] Z
00°000°00T $ ST [ OUBMOI[W S8URY) 2d09g $19UMO| T
aouemory (e30L | un |Amuend uondiiasog "ON
UMOPYBIIG DUBMOTTV
VI dD sopeisdy MoaAsosoy piiqiopuny |,
QLZ6980L21 1€-0448-4ZEP-G4 | J-AVERHERY ‘CI edojaaug ub}sno0q
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
Thunderbird Reservoir Upgrades GMP 1A
Taxable and Non-Taxable Items
Description 212233.1 Unit Total Allowance
Direct & Indirect Total Job Cost 1 LS $ 538,961.29
Material List:
None.
TOTAL GMP TAXABLE ITEMS| $ 538,961.29
TOTAL GMP NON-TAXABLE ITEMS| $ :
| Sales Tax Total] $ 30,410.89 |
Page 4 of 6
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
THIS PAGE IS BLANK
City of Glendale Standard Form Agreement Between Owner and CM@Risk (May 15, 2023)
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
EXHIBIT E
Construction Documents necessary to define Scope of Work and Deliverables for the
Construction Phase Services, including plans, designs, drawings, specifications and other
required Contract Documents
(30 pages - To be Incorporated by Amendment)
See Attached
City of Glendale Standard Form Agreement Between Owner and CM@Risk (May 15, 2023)
SCOPE OF WORK
Tab 1 - Scope of Work
GG Construction Manager At Risk Contractor
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
mace
QUALITY - PERFORMANCE « VALUE,
March 13, 2024
City of Glendale
Water Services Department
Glendale, AZ 85308
Attn: Mr. James Hannasch
Re: 212233.1 — Thunderbird Reservoir Upgrades Project - GMP 1A — Rev 00
Dear James:
In accordance with the information provided, we are pleased to offer a cost proposal for the additional
scope of work listed below at the City of Glendale Thunderbird Reservoir site. The total price is
($769,034.14) Seven Hundred Sixty-Nine Thousand Thirty-Four Dollars and Fourteen cents.
A further breakdown of the proposal and quotations are attached. We have included all applicable sales
tax, bonds, and insurance.
Reservoir Location Design Engineer
Thunderbird
23098 N. 64" Avenue,
Glendale, AZ 85310 Wilson Engineers
MW RYNS
Location: 23098 N. 64" Avenue, Glendale, AZ 85310
Size: Less than 1 acre being disturbed
Type of Job: Thunderbird Reservoir Roof Replacements and Upgrades.
Usage: Potable Water Storage
Work to be completed during GMP 1A per scope of work changes:
This GMP includes multiple additional scope items that have arisen during GMP 1
construction activities by MGC Contractors and thorough reservoir inspections by
Wilson Engineers. These items have been tracked via adjustment numbers. Each
adjustment is a newly found condition that needs to be addressed while the
reservoir is offline. These unforeseen conditions have added additional scope to
the original GMP 1 and are being addressed in GMP 1A as an amendment. If an
Engineering Directive (ED) was issues for the additional work, it has been
included for reference under ‘Tab 11 — Project Plans’.
See ‘Tab 9 — Adjustment Details’ for more information on scope.
Adjustment 10 — ED-06 Girder Support Brackets.
o Per ED-06 from Wilson Engineers, we have included costs associated with
fabricating and installing (16 each) purlin and girder supports.
Adjustment 12 — Roof Hatches and Supports.
o Includes the purchase cost of the (3 Each) 4’x4’ hatches and (1 Each) 8’x8’
hatch. Also included is the welding of the support beams to the purlins.
Adjustment 13 — Security Camera
o Includes the removal and re-installation of the existing camera located on the
South-East corner of the Thunderbird Reservoir.
Adjustment 14 — ED-04 Intrusion Alarms.
o Per Wilson Engineers ED-04 we have included costs for furnishing and installing
intrusion alarms and associated conduits, j-boxes, and wiring at all (4 each)
4110 E. Elwood St. Phoenix, Arizona 85040 Telephone (602) 437-5000 Fax (602) 470-4000
License Numbers ROC069949 & ROC071441
DocuSign Envelope ID: 6894B9AE-F'1FB-432F-8FFC-311770B6927D
RASS
QUALITY - PERFORMANCE - VALUE
hatches.
o Adjustment 14 does not include the (1 each) intrusion alarm in ED-09. Those
costs are provided in Adjustment 21.
Adjustment 16 — Additional 316SS Bent Plate.
o Includes the fabrication and installation of 360 lineal feet of 316SS bent plate on
the north-east side of the reservoir.
Adjustment 18 — Relocate Reservoir Wall Conduits.
o Includes the lowering ‘relocation’ of the existing power and control conduits that
run along the outside of the Thunderbird Reservoir CMU wall. These conduits
need to be relocated because they conflict with the new reservoir roofing system.
o Due to the unknown usable existing materials involved with the relocation of the
existing reservoir conduits, Swain will perform this work on a time-and-
materials basis.
Adjustment 21 — New Level Indicating Transmitter, Walkway, and Platform.
o Includes the fabrication and installation of a new 118° walkway with platform,
new level indicating transmitter (LIT), LIT enclosure, enclosure support beams,
intrusion alarm, conduit, wiring, and terminations. MGC will need to assist
Woody’s Metal Craft welders by providing additional manlift and labor needed
to manually move manlift floor weight distribution sheathing and lifts to each
location. This will be an additional crew and manlift then accounted for in
original GMP. The additional crew and manlift will be required to meet the
project schedule.
Adjustment 23 — Additional Hatch and Vent Supports.
o Includes the fabrication and installation of required additional support brackets at
all hatch and vent locations. MGC will need to assist Woody’s Metal Craft
welders by providing additional manlift and labor needed to manually move
manlift floor weight distribution sheathing and lifts to each location. This will be
an additional crew and (3 each) additional manlifts then accounted for in original
GMP. The additional crew and manlifts are required to keep the project on
schedule.
Adjustment 25 —- ED-10 Inspection Findings.
o Per Wilson Engineers Engineering Directive 10 (ED-10), this proposal includes
the fabrication and installation of (3 each) steel plates at (3 each) purlin
connections, coating of (23 each) purlins (each side), (3 each) welded purlin
connection plates, wire wheel cleaning at (7 each) areas, replace nuts and bolts
(49 each) connection areas. MGC will need to assist both Woody’s Metal Craft
welders and Sonoran Field Services by providing additional manlift and labor
needed to manually move manilift floor weight distribution sheathing and lifts to
each location. This will be an additional crew and manlift then accounted for in
original GMP.
We have included an Owners Allowance of $100,000.00 to be used if any
additional structural repairs on unforeseen conditions arise. An additional
$20,000.00 allowance for additional roof walkway access stairs and ladders has
also been included. A total of $120,000.00 in project allowances has been
included.
4110 E. Elwood St. Phoenix, Arizona 85040 Telephone (602) 437-5000 Fax (602) 470-4000
License Numbers ROC069949 & ROC071441
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
wee G
QUALITY - PERFORMANCE * VALUE
Guaranteed Maximum Price (GMP) 1A Purpose:
This GMP 1 Cost Proposal aims to provide a fully functional roof replacement, generally in accordance
with Wilson Engineer’s 100% “Thunderbird Reservoir Upgrades” Design Plan set approved by the City
of Glendale on December 23, 2023, and “Thunderbird Reservoir Upgrades Project” Technical
Specifications approved by the City of Glendale on November 28, 2023, for the City of Glendale at the
Thunderbird Reservoir site.
Guaranteed Maximum Price (GMP) 1A Included Scope and Deliverables:
To ensure accuracy and complete transparency on all items covered by GMP 1A, please review ‘Tab 3 —
Cost of Construction/Schedule of Values’ and ‘Tab 9 — Adjustment Details’ on the attached GMP 1A Cost
Proposal. These Tabs cover in detail all project-related tasks and associated costs.
e Project Deliverables Include:
o Submittals on all materials used.
co Monthly project schedule updates and deliverables.
o Weekly 3-week look ahead schedules.
Allowances Breakdown (Tab 7 - GMP 1A):
Thunderbird Reservoir Upgrades GMP 1A
Allowance Breakdown
No. Description Quantity] Unit Total Allowance
1 |Owner's Scope Change Allowance 1 LS $ 100,000.00
Additional Roof Walkway Access Stairs/Ladders | LS $ 20,000.00
B. TOTAL GMP ALLOWANCE] $ 120,000.00
e An allowance use proposal (adjustment) will be sent for each item utilized and approved by the Owner
before conducting the adjustments outlined in the Scope of Work.
Anticipated Contract Duration:
e GMP 1A City Council approval — 4/09/2024
Notice to proceed (NTP) — 4/10/2024
Substantial Completion — 05/24/2024
44 calendar days from NTP to GMP IA final completion.
Project Start Date: 10 April 2024 — Project End Date: 24 May 2024
Total Project Working Days: 33
eee?
Thank you for the opportunity to be of service; if you have any questions, please do not hesitate to call.
Sincerely,
Scott Whitley
Project Manager
MGC Contractors, Inc.
309-397-2151
4110 E. Elwood St. Phoenix, Arizona 85040 Telephone (602) 437-5000 Fax (602) 470-4000
License Numbers ROC069949 & ROC071441
=
- |
Tab 11- Project Plans |
WILSON ENGINEERS
HUNDERBIRD RESERVOIR UPGRADES
- 100% DESIGN PLANS
COVER PAGE
-ED-04
-ED-06
-ED-09
-ED-10
ve
Tab 11 - Project Plans
’ ac Construction Manager At Risk Contractor - J - :
|
ea pees SEA SSPEDESEEAN POY
SCV
SS
SB
| .OV
QLZ69S0LL1 Le-0448-4ZEP-G4 |} t-AVESPEE :Cl edojeauy uBigno0q ~
{I
———————— "XV 2/b 0% — XVI n2/b 0% | “XV u2/b 0 ————+}
|
4
i]
i
|
| LYOddNs HOVA
LV YANALSVS (1) ONINALSV4
TWOILNAG! AVM NOILVTIVLSNI OL 3YyO439 YNV1d STANVd S0€ OW34
|_4py dO adIs aLlsoddo _/1) HORid HSH1S9O1 THNG-Sud “TENNVHO (5) |_/@s OL BVINOIGNaduad <> (xv)
| NU STAINNVHO HOV LY \+? syinvid N3LSV4 LuYOddNs HOWa LY \2/ \8? Sond «8/2 bL Xz (p) | ‘0° 07 LV
HLONAT TANNVHO |
8
ALINGNOS 9YD
an TIVLSNI
LINGNOD OND
HONIL SYNLAS
“~~ 9NO1 SSHONI-¥Z
‘INMLSINN SS OLE
ALZ69S0LL} /£-0-448-4ZEP-G4 1 4-AVEAPER :C Adojanuy UBIgnoog ~
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
WAG
QUALITY - PERFORMANCE * VALUE
August 11, 2023
City of Glendale
Water Services Department
Glendale, AZ 85308
Attn: Mr. Martin Soma
Re: —212233.1 — Thunderbird Reservoir Upgrades Project -GMP 1 — Rev 00
Dear Martin:
In accordance with the information provided, we are pleased to offer a cost proposal for the Scope of
Work listed below at the City of Glendale Thunderbird Reservoir site. The total price is ($5,953,801.61)
Five Million Nine Hundred Fifty-Three Thousand Eight Hundred One Dollars and Sixty-One cents.
A further breakdown of the proposal-and quotations are attached. We have included all applicable sales
tax, bonds, and insurance.
Reservoir Location Design Engineer
Thunderbird
23098 N. 64° Avenue,
Glendale, AZ 85310 Wilson Engineers
1.
2.
3.
4.
5.
Location: 23098 N. 64" Avenue, Glendale, AZ 85310
Size: Less than | acre being disturbed
Type of Job: Thunderbird Reservoir Roof Replacements and Upgrades.
Usage: Potable Water Storage
Work to be completed during this Project per Scope of Work:
Removal of existing Roof System.
Replacement of the Centerline Purlins and up to 5% additional Purlins as noted by
Wilson Engineers.
Surface Preparation and Recoating the Tops of all Purlins.
Surface Preparation and Recoating of the Sides of up to 20 Girders.
Surface Preparation and Recoating of the Reservoir C-Channel.
Furnish and Installation of all new BEMO Roof System.
Furnish and Installation of three new 4-foot x 4-foot Roof Hatches, one new 8-foot
x 8-foot Hatch, and 23 Roof Vents.
Conduct up to 20 Column Repairs as noted by Wilson Engineers.
Repair Connection Points and Damaged Nuts/Bolts as noted by Wilson Engineers.
Conduct an Initial and Final Reservoir Leak Test. ;
Conduct Disinfection of the Reservoir before putting the Reservoir back online.
Conduct a Survey of the Reservoir's Benchmarks and Provide Permanent Markers.
Mounting of Girder Support Brackets w/GPR as noted by Wilson Engineers.
Liner Protection and Repairs (if needed.)
Removal of an existing 8” PVC pipe that runs around the inside of the Reservoir. The pipe
clamps will remain in place so no damage to the liner will occur.
Any additional work requested by Wilson Engineering and approved by the City
via an allowance adjustment.
4110 E. Elwood St. Phoenix, Arizona 85040 Telephone (602) 437-5000 Fax (602) 470-4000
License Numbers ROC069949 & ROC071441
DocuSign Envelope ID: 6894B9AE-F1FB-432F-8FFC-311770B6927D
Employee Owned
WAG
QUALITY - PERFORMANCE - VALUE
Guaranteed Maximum Price (GMP) I Purpose:
This GMP 1 Cost Proposal aims to provide a fully functional roof replacement, generally in accordance
with Wilson Engineer’s 90% “Thunderbird Reservoir Upgrades” Design Plan set dated July 12, 2023,
and “Thunderbird Reservoir Upgrades Project” Technical Specifications dated July 2023 for the City of
Glendale at the Thunderbird Reservoir site.
Guaranteed Maximum Price (GMP) 1 Included Scope and Deliverables:
To ensure accuracy and complete transparency on all items covered by GMP 1, please review Tab 3 —
Cost of Construction/Schedule of Values and Tab 9 — Estimate Summary on the attached GMP 1 Cost
Proposal. These Tabs cover in detail all project-related tasks and associated costs.
e Project Deliverables Include:
o Submittals on all materials used.
o Reservoir leak testing and disinfection documentation.
o Monthly project schedule updates and deliverables.
o Weekly 3-week look ahead schedules.
Allowances Breakdown (Tab 7- GMP 1):
No. Description Quantity} Unit Total Allowance
1 |Re-Pave Access Way from Upper Lot to Reservoir 1 LS $ 15,000.00
2 |Crane Pick Engineering - 2 [1 Ls [$_ 5,000.00
3 |Material Escalation (15% Material Cost) 1 LS $ 14,000.00
4 |GPR Wall Scanning 1 LS $ 5,000.00
5 | Ultrasonic Level Enclosure Removal and Re-Installation 1 LS $ 10,000.00
6 |Weekly Street Sweeping per Spec 01550-1 1 LS $ 15,000.00
7 |Liner Patch Repair Allowance 1 LS $ 30,000.00
8 |Column Repair Allowance 1 LS $ 100,000.00
9 |Roof Hatch Allowance 1 LS $ 53,544.00
10 |Remove/Re-Install Security Camera Pole for Crane Access 1 LS $ 10,000.00
11 |NACE Inspector Allowance ] LS $ 10,000.00
12 [Replace Purlins As Needed Basis Allowance 1 LS $ 20,000.00
13 |Procure and Install Nuts/Bolts/Washers As Needed Basis Allowance 1 LS $ 20,000.00
14 |Survey Point Benchmark Allowance 1 LS $ 10,000.00
B. TOTAL GMP ALLOWANCE] $ 317,544.00
o An allowance use proposal (adjustment) will be sent for each item utilized and approved by the
Owner before conducting the adjustments outlined Scope of Work.
Anticipated Contract Duration:
e GMP | City Council approval — 9/26/2023
Notice to proceed (NTP) — 9/27/2023
Substantial Completion — 03/01/2024
156 calendar days from NTP to GMP 1 final completion.
Project Start Date: 16 October 2023 — Project End Date: 08 March 2024
Total Project Working Days: 98