Professional Services Agreement with Black & Veatch Corporation

City of Glendale — Regular Meeting (2024-05-28)

View PDF Item 9 Meeting page

Extracted text (via pymupdf) 65007 characters
1 
10/05/2023 
C      
PROFESSIONAL SERVICES AGREEMENT 
ELECTRICAL VULNERABILITY AND ARC FLASH ASSESSMENT 
PROJECT 222344 
This Professional Services Agreement ("Agreement") is entered into and effective between CITY OF GLENDALE, 
an Arizona municipal corporation ("City") and Black & Veatch Corporation, a Delaware corporation, authorized to 
do business in the State of Arizona, ("Consultant") as of the _____ day of _________________, 2024 (“Effective 
Date”). 
RECITALS 
A. 
City intends to undertake a project for the benefit of the public and with public funds that is more fully set 
forth in Exhibit A, Scope of Work (the "SOW"); 
B. 
City desires to retain the professional services of Consultant to develop, create, make, generate, supply, deliver, 
provide and/or perform the specific benefits, services, tasks, activities, expertise, etc. as set forth in the Scope 
of Work; and 
C. 
City and Consultant desire to memorialize their agreement with this document. 
AGREEMENT 
The parties hereby agree as follows: 
1. 
Key Personnel; Other Consultants and Subcontractors. 
1.1 
Professional Services.  Consultant will provide all Services necessary to assure all portions, tasks, 
activities and specifications of the SOW (the “Services”) are completed timely and efficiently 
consistent with the SOW’s requirements, including, but not limited to, working in close interaction 
and interfacing with City and its designated employees, and working closely with others, including 
other consultants or contractors, retained by City. 
1.2 
Project Team. 
a. 
Project Manager. 
(1) 
Consultant will designate an employee as Project Manager with sufficient training, 
knowledge, and experience to, in the City's opinion, complete the project and handle 
all aspects of the SOW such that the work produced by Consultant is consistent 
with applicable standards as detailed in this Agreement; and 
(2) 
The City must approve the designated Project Manager. 
b. 
Project Team. 
(1) 
The Project Manager and all other employees assigned to the perform the SOW by 
Consultant will comprise the "Project Team." 
(2) 
Project Manager will have responsibility for and will supervise all other employees 
assigned to the perform the SOW by Consultant. 
c. 
Discharge, Reassign, Replacement. 
(1) 
Consultant acknowledges the Project Team is comprised of the same persons and 
roles for each as may have been identified in Exhibit A. 
(2) 
Consultant will not discharge, reassign, replace or diminish the responsibilities of 
any of the employees assigned to perform the SOW who have been approved by 
City without City's prior written consent unless that person leaves the employment 
of Consultant, in which event the substitute must first be approved in writing by 
City.

2 
10/05/2023 
(3) 
Consultant will change any of the members of the Project Team at the City's request 
if an employee's performance does not equal or exceed the level of competence that 
the City may reasonably expect of a person performing those duties, or if the acts 
or omissions of that person are detrimental to the completion of the SOW. 
d. 
Subcontractors. 
(1) 
Consultant may engage specific technical contractors (each a "Subcontractor") to 
furnish certain Service. 
(2) 
Consultant will remain fully responsible for Subcontractor's Services. 
(3) 
Subcontractors must be approved by the City. 
(4) 
Consultant will certify by letter that all contracts with Subcontractors have been 
executed incorporating requirements and standards as set forth in this Agreement. 
2. 
Schedule.  The Services will be undertaken in a manner that ensures the SOW is completed on time and in 
a cost- efficient manner.  The Services, including any interim milestones, shall be completed in accordance 
with the schedule contained in Exhibit A. 
3. 
Consultant’s Work. 
3.1 
Standard.  Consultant must perform Services in accordance with the standards of due diligence, care, 
and quality prevailing among consultants having substantial experience with the successful furnishing 
of Services for projects that are equivalent in size, scope, quality, and other criteria under the SOW 
and identified in this Agreement. 
3.2 
Licensing.  Consultant warrants that: 
a. 
Consultant and its Subconsultants or Subcontractors will hold all appropriate and required 
licenses, registrations and other approvals necessary for the lawful furnishing of Services 
("Approvals"); and 
b. 
Neither Consultant nor any Subconsultant or Subcontractor has been debarred or otherwise 
legally excluded from contracting with any federal, state, or local governmental entity 
("Debarment"). 
(1) 
City is under no obligation to ascertain or confirm the existence or issuance of any 
Approvals or Debarments, or to examine Consultant's contracting ability. 
(2) 
Consultant must notify City immediately if any Approvals or Debarment changes 
during the Agreement's duration. The failure of the Consultant to notify City as 
required will constitute a material default under the Agreement. 
3.3 
Compliance.   
a. 
Services will be furnished in compliance with applicable federal, state, county and local 
statutes, rules, regulations, ordinances, building codes, life safety codes, and other standards 
and criteria designated by City. 
b. 
Consultant must not discriminate against any employee or applicant for employment on the 
basis of race, color, religion, sex, national origin, age, marital status, sexual orientation, gender 
identity or expression, genetic characteristics, familial status, U.S. military veteran status or 
any disability.  Consultant will require any Sub-contractor to be bound to the same 
requirements as stated within this section.  Consultant, and on behalf of any subcontractors, 
warrants compliance with this section. 
3.4 
Coordination; Interaction. 
a. 
For projects that the City believes requires the coordination of various professional services, 
Consultant will work in close consultation with City to proactively interact with any other 
professionals retained by City ("Coordinating Professionals").

3 
10/05/2023 
b. 
Consultant will meet to review the Services to be provided in the SOW, Schedule and in-
progress work with Coordinating Professionals and City as often and for durations as City 
reasonably considers necessary in order to ensure the timely work delivery and SOW 
completion. 
c. 
For projects not involving Coordinating Professionals, Consultant will proactively interact 
with any other contractors when directed by City to obtain or disseminate timely information 
for the proper execution of the SOW. 
3.5 
Work Product. 
a. 
Ownership.  Upon receipt of payment for Services furnished, Consultant grants to City, and 
will cause its Subconsultants or Subcontractors to grant to the City, the exclusive ownership 
of and all copyrights, if any, to evaluations, reports, drawings, specifications, project manuals, 
surveys, estimates, reviews, minutes, all "architectural work" as defined in the United States 
Copyright Act, 17 U.S.C § 101, et seq., and other intellectual work product as may be 
applicable ("Work Product"). 
(1) 
This grant is effective whether the Work Product is on paper (e.g., a "hard copy"), 
in electronic format, or in some other form. 
(2) 
Consultant warrants, and agrees to indemnify, hold harmless and defend City for, 
from and against any claim that any Work Product infringes on third-party 
proprietary interests. 
b. 
Delivery.  Consultant will deliver to City copies of the preliminary and completed Work 
Product promptly as they are prepared. 
c. 
City Use. 
(1) 
City may reuse the Work Product at its sole discretion. 
(2) 
In the event the Work Product is used for another project without further 
consultations with Consultant, the City agrees to indemnify and hold Consultant 
harmless from any claim arising out of the Work Product. 
(3) 
In such case, City will also remove any seal and title block from the Work Product. 
4. 
Compensation. 
4.1 
Compensation.  Consultant's compensation for the Services, including those furnished by its 
Subconsultants or Subcontractors will not exceed $209,828 as specifically detailed in Exhibit B 
("Compensation"). 
4.2 
Change in Scope of Work.  The Compensation may be equitably adjusted if the original SOW is 
significantly modified, but only as provided below. 
a. 
Adjustments to the SOW, including adding any additional Services or any change in the 
amount of Compensation available hereunder, require a written amendment to this 
Agreement and may require City Council approval. 
b. 
Additional services which are outside the scope of the original SOW contained in this 
Agreement may not be performed by the Consultant without prior written authorization 
from the City. 
c. 
Notwithstanding the incorporation of the Exhibits to this Agreement by reference, should 
any conflict arise between the provisions of this Agreement and the provisions found in the 
Exhibits and accompanying attachments, the provisions of this Agreement shall take priority 
and govern the conduct of the parties. 
4.3 
Expenses.  City will reimburse Consultant for certain out-of-pocket expenses necessarily incurred by 
Consultant in connection with this Agreement, without mark-up (the “Reimbursable Expenses”), 
including, but not limited to, document reproduction, materials for book preparation, postage,

4 
10/05/2023 
courier and overnight delivery costs incurred with Federal Express or similar carriers, travel and car 
mileage, subject to the following: 
a. 
Mileage, airfare, lodging and other travel expenses will be reimbursable only to the extent 
these would, if incurred, be reimbursed to City of Glendale personnel under its policies and 
procedures for business travel expense reimbursement made available to Consultant for 
review prior to the Agreement’s execution, and which policies and procedures will be 
furnished to Consultant; 
b. 
The Reimbursable Expenses in this section are approved in advance by City in writing; and 
c. 
The total of all Reimbursable Expenses paid to Consultant in connection with this 
Agreement will not exceed the “not to exceed” amount identified in Section 4.1 above. 
5. 
Billings and Payment. 
5.1 
Applications. 
a. 
Consultant will submit monthly invoices (each, a "Payment Application") to City's Project 
Manager and City will remit payments based upon the Payment Application as stated below. 
b. 
The period covered by each Payment Application will be one calendar month ending on the 
last day of the month. 
5.2 
Payment. 
a. 
After a full and complete Payment Application is received, City will process and remit 
payment within 30 days. 
b. 
Payment may be subject to or conditioned upon City's receipt of: 
(1) 
Completed work generated by Consultant and its Subconsultants and 
Subcontractors; and 
(2) 
Unconditional waivers and releases on final payment from all Subconsultants and 
Subcontractors as City may reasonably request to assure the City will be free of 
claims arising from required performances under this Agreement. 
5.3 
Review and Withholding.  City's Project Manager will timely review and certify Payment Applications. 
a. 
If the Payment Application is rejected, the Project Manager will issue a written listing of the 
items not approved for payment. 
b. 
City may withhold an amount sufficient to pay expenses that City reasonably expects to incur 
in correcting the deficiency or deficiencies rejected for payment. 
6. 
Termination. 
6.1 
For Convenience.  City may terminate this Agreement for convenience, without cause, by delivering 
a written termination notice stating the effective termination date, which may not be less than 15 
days following the date of delivery. 
a. 
Consultant will be equitably compensated for Services furnished prior to receipt of the 
termination notice and for reasonable costs incurred. 
b. 
Consultant will also be similarly compensated for any approved effort expended, and 
approved costs incurred, that are directly associated with Project closeout and delivery of the 
required items to the City. 
6.2 
For Cause.  City may terminate this Agreement for cause if Consultant fails to cure any breach of this 
Agreement within seven days after receipt of written notice specifying the breach. 
a. 
Consultant will not be entitled to further payment until after City has determined its damages. 
If City's damages resulting from the breach, as determined by City, are less than the equitable

5 
10/05/2023 
amount due but not paid Consultant for Services furnished, City will pay the amount due to 
Consultant, less City's damages, in accordance with the provision of Sec. 5. 
b. 
If City's direct damages exceed amounts otherwise due to Consultant, Consultant must pay 
the difference to City immediately upon demand; however, Consultant will not be subject to 
consequential damages more than $1,000,000 or the amount of this Agreement, whichever 
is greater. 
7. 
Conflict.  Consultant acknowledges this Agreement is subject to A.R.S. § 38-511, which allows for 
cancellation of this Agreement in the event any person who is significantly involved in initiating, negotiating, 
securing, drafting, or creating the Agreement on City's behalf is also an employee, agent, or consultant of any 
other party to this Agreement. 
8. 
Insurance.  For the duration of the term of this Agreement, Consultant shall procure and maintain insurance 
against claims for injuries to persons or damages to property which may arise from or in connection with the 
performance of all tasks or work necessary to complete the Project as herein defined. Such insurance shall 
cover Consultant, its agent(s), representative(s), employee(s) and any subcontractors. 
8.1 
Minimum Scope and Limit of Insurance.  Coverage must be at least as broad as: 
a. 
Commercial General Liability (CGL). Insurance Services Office Form CG 00 01, including 
products and completed operations, with limits of no less than $1,000,000 per occurrence 
for bodily injury, personal injury, and property damage. If a general aggregate limit applies, 
either the general aggregate limit shall apply separately to this project/location or the general 
aggregate limit shall be twice the required occurrence limit. 
b. 
Automobile Liability. Insurance Services Office Form Number CA 0001 covering Code 1 
(any auto), with limits no less than $1,000,000 per accident for bodily injury and property 
damage. 
c. 
Professional Liability. Consultant must maintain a Professional Liability insurance covering 
errors and omissions arising out of the work or services performed by Consultant, or anyone 
employed by Consultant, or anyone for whose acts, mistakes, errors and omissions 
Consultant is legally liability, with a liability insurance limit of $1,000.000 for each claim and 
a $2,000,000 annual aggregate limit. 
d. 
Worker’s Compensation.  Insurance as required by the State of Arizona, with Statutory 
Limits, and Employers’ Liability insurance with a limit of no less than $1,000,000 per 
accident for bodily injury or disease. 
8.2 
Indemnification. 
a. 
To the fullest extent permitted by law, Consultant must defend, indemnify, and hold 
harmless City and its elected officials, officers, employees and agents (each, an "Indemnified 
Party," collectively, the "Indemnified Parties") for, from, and against any and all claims, 
demands, actions, damages, judgments, settlements, personal injury (including sickness, 
disease, death, and bodily harm), property damage (including loss of use), infringement, 
governmental action and all other losses and expenses, including attorneys' fees and litigation 
expenses (each, a "Demand or Expense" collectively "Demands or Expenses") asserted by a 
third-party (i.e. a person or entity other than City or Consultant) and that arises out of or 
results from the breach of this Agreement by the Consultant or the Consultant’s negligent 
actions, errors or omissions (including any Subconsultant or Subcontractor or other person 
or firm employed by Consultant), whether sustained before or after completion of the SOW 
and/or Services. 
b. 
This indemnity and hold harmless provision applies even if a Demand or Expense is in part 
due to the Indemnified Party's negligence or breach of a responsibility under this Agreement, 
but in that event, Consultant will be liable only to the extent the Demand or Expense results 
from the negligence or breach of a responsibility of Consultant or of any person or entity 
for whom Consultant is responsible.

6 
10/05/2023 
c. 
Consultant is not required to indemnify any Indemnified Parties for, from, or against any 
Demand or Expense resulting from the Indemnified Party's sole negligence or other fault 
solely attributable to the Indemnified Party. 
8.3 
Other Insurance Provisions.  The insurance policies required by the Section above must contain, or 
be endorsed to contain the following insurance provisions: 
a. 
The City, its officers, officials, employees and volunteers are to be covered as 
additional insureds of the CGL and automobile policies for any liability arising from or in 
connection with the performance of all tasks or work necessary to complete the Services as 
herein defined. Such liability may arise, but is not limited to, liability for materials, parts or 
equipment furnished in connection with any tasks, or work performed by Consultant or on 
its behalf and for liability arising from automobiles owned, leased, hired or borrowed on 
behalf of the Consultant. General liability coverage can be provided in the form of an 
endorsement to the Consultant’s existing insurance policies, provided such endorsement is 
at least as broad as ISO Form CG 20 10, 11 85 or both CG 20 10 and CG 23 37, if later 
revisions are used. 
b. 
For any claims related to the SOW and/or Services, the Consultant’s insurance coverage 
shall be primary insurance with respect to the City, its officers, officials, employees, and 
volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, 
employees or volunteers shall be in excess of the Consultant’s insurance and shall not 
contribute with it. 
c. 
Each insurance policy required by this Section shall provide that coverage shall not be 
canceled, except after providing notice to the City. 
8.4 
Acceptability of Insurers.  Insurance is to be placed with insurers with a current A.M. Best rating of 
no less than A: VII, unless the Consultant has obtained prior approval from the City stating that a 
non-conforming insurer is acceptable to the City. 
8.5 
Waiver of Subrogation.  Consultant hereby agrees to waive its rights of subrogation which any 
insurer may acquire from Consultant by virtue of the payment of any loss. Consultant agrees to 
obtain any endorsement that may be necessary to effect this waiver of subrogation. The Workers’ 
Compensation Policy shall be endorsed with a waiver of subrogation in favor of the City for all work 
performed by the Consultant, its employees, agent(s) and subcontractor(s). 
8.6 
Verification of Coverage.  Within 15 days of the Effective Date of this Agreement, Consultant shall 
furnish the City with original certificates and amendatory endorsements, or copies of any applicable 
insurance language making the coverage required by this Agreement effective. All certificates and 
endorsements must be received and approved by the City before work commences. Failure to obtain, 
submit or secure the City’s approval of the required insurance policies, certificates or endorsements 
prior to the City’s agreement that work may commence shall not waive the Consultant’s obligations 
to obtain and verify insurance coverage as otherwise provided in this Section. The City reserves the 
right to require complete, certified copies of all required insurance policies, including any 
endorsements or amendments, required by this Agreement at any time during the Term stated herein. 
Consultant’s failure to obtain, submit or secure the City’s approval of the required insurance policies, 
certificates or endorsements shall not be considered a Force Majeure or defense for any failure by 
the Consultant to comply with the terms and conditions of the Agreement, including any schedule 
for performance or completion of the Project. 
8.7 
Subcontractors.  Consultant shall require and shall verify that all subcontractors maintain insurance 
meeting all requirements of this Agreement. 
8.8  
Special Risk or Circumstances.  The City reserves the right to modify these insurance requirements, 
including any limits of coverage, based on the nature of the risk, prior experience, insurer, coverage 
or other circumstances unique to the Consultant, the Project or the insurer.

7 
10/05/2023 
9. 
E-verify, Records and Audits. To the extent applicable under A.R.S. § 41-4401, the Consultant warrants 
their compliance and that of its subconsultants with all federal immigration laws and regulations that relate to 
their employees and compliance with the E-verify requirements under A.R.S. § 23-214(A). The Consultant or 
subconsultant’s breach of this warranty shall be deemed a material breach of the Agreement and may result 
in the termination of the Agreement by the City under the terms of this Agreement. The City retains the legal 
right to randomly inspect the papers and records of the other party to ensure that the other party is complying 
with the above-mentioned warranty. The Consultant and subconsultant warrant to keep their respective 
papers and records open for random inspection during normal business hours by the other party. The parties 
shall cooperate with the City’s random inspections, including granting the inspecting party entry rights onto 
their respective properties to perform the random inspections and waiving their respective rights to keep such 
papers and records confidential. 
10. 
No Boycott of Israel.  To the extent A.R.S § 35-393 through § 35-393.03 are applicable, the parties hereby 
certify that they are not currently engaged in, and agree for the duration of the Agreement to not engage in, a 
boycott of goods or services from Israel, as that term is defined in A.R.S § 35-393. 
11. 
Uyghur Forced Labor Prevention Act (UFLPA). Consultant certifies that it does not currently, and during 
the term of this Agreement, will not use: 
a.  
the forced labor of ethnic Uyghurs in the People’s Republic of China;  
b. 
any goods or services produced by the forced labor of ethnic Uyghurs in the People’s 
Republic of China; and  
c. 
any contractors, subcontractors or suppliers that use the forced labor or any goods or 
services produced by the forced labor of ethnic Uyghurs in the People’s Republic of China. 
12. 
Attestation of PCI Compliance.  When applicable, the Consultant will provide the City annually with a 
Payment Card Industry Data Security Standard (PCI DSS) attestation of compliance certificate signed by an 
officer of Consultant with oversight responsibility. 
13. 
Notices. 
13.1 
A notice, request or other communication that is required or permitted under this Agreement (each 
a "Notice") will be effective only if: 
a. 
The Notice is in writing; and 
b. 
Delivered in person or by overnight courier service (delivery charges prepaid), certified or 
registered mail (return receipt requested). 
c. 
Notice will be deemed to have been delivered to the person to whom it is addressed as of 
the date of receipt, if: 
(1) 
Received on a business day before 5:00 p.m. at the address for Notices identified 
for the Party in this Agreement by U.S. Mail, hand delivery, or overnight courier 
service; or 
(2) 
As of the next business day after receipt, if received after 5:00 p.m. 
d. 
The burden of proof of the place and time of delivery is upon the Party giving the Notice. 
e. 
Digitalized signatures and copies of signatures will have the same effect as original signatures. 
13.2 
Representatives. 
a. 
Consultant.  Consultant's representative (the "Consultant's Representative") authorized to 
act on Consultant's behalf with respect to the SOW and/or Services, and his or her address 
for Notice delivery is: 
 
Black & Veatch Corporation 
c/o Mike Caruso 
3133 East Camelback Road, Suite 210

8 
10/05/2023 
Phoenix, Arizona 85016 
 
b. 
City.  City's representative ("City's Representative") authorized to act on City's behalf, and 
his or her address for Notice delivery is: 
City of Glendale 
c/o  Joe Hernandez 
5850 West Glendale Avenue 
Glendale, Arizona 85301 
 
With required copy to: 
City Manager 
City Attorney 
City of Glendale 
City of Glendale 
5850 West Glendale Avenue 
5850 West Glendale Avenue 
Glendale, Arizona  85301 
Glendale, Arizona  85301 
c. 
Concurrent Notices. 
(1) 
All notices to City's representative must be given concurrently to City Manager and 
City Attorney. 
(2) 
A notice will not be deemed to have been received by City's representative until the 
time that it has also been received by the City Manager and the City Attorney. 
(3) 
City may appoint one or more designees for the purpose of receiving notice by 
delivery of a written notice to Consultant identifying the designee(s) and their 
respective addresses for notices. 
d. 
Changes.  Consultant or City may change its representative or information on Notice, by 
giving Notice of the change in accordance with this section at least ten days prior to the 
change. 
14. 
Financing Assignment.  City may assign this Agreement to any City-affiliated entity, including a non-profit 
corporation or other entity whose primary purpose is to own or manage the SOW or Services. 
15. 
Entire Agreement; Survival; Counterparts; Signatures. 
15.1 
Integration.  This Agreement contains, except as stated below, the entire agreement between City 
and Consultant and supersedes all prior conversations and negotiations between the parties regarding 
the SOW or this Agreement. 
a. 
Neither Party has made any representations, warranties or agreements as to any matters 
concerning the Agreement's subject matter. 
b. 
Representations, statements, conditions, or warranties not contained in this Agreement will 
not be binding on the parties. 
c. 
Inconsistencies between the solicitation, any addenda attached to the solicitation, the 
response or any excerpts attached as Exhibit A, and this Agreement, will be resolved by the 
terms and conditions stated in this Agreement. 
15.2 
Interpretation. 
a. 
The parties fairly negotiated the Agreement's provisions to the extent they believed necessary 
and with the legal representation they deemed appropriate. 
b. 
The parties are of equal bargaining position and this Agreement must be construed equally 
between the parties without consideration of which of the parties may have drafted this 
Agreement. 
c. 
The Agreement will be interpreted in accordance with the laws of the State of Arizona.

9 
10/05/2023 
15.3 
Survival.  Except as specifically provided otherwise in this Agreement, each warranty, representation, 
indemnification and hold harmless provision, insurance requirement, and every other right, remedy 
and responsibility of a Party, will survive completion of the SOW, or the earlier termination of this 
Agreement. 
15.4 
Amendment.  No amendment to this Agreement will be binding unless in writing and executed by 
the parties. Electronic signature blocks do not constitute execution for purposes of this Agreement. 
Any amendment may be subject to City Council approval. 
15.5 
Remedies.   All rights and remedies provided in this Agreement are cumulative and the exercise of 
any one or more right or remedy will not affect any other rights or remedies under this Agreement 
or applicable law. 
15.6 
Severability.  If any provision of this Agreement is voided or found unenforceable, that determination 
will not affect the validity of the other provisions, and the voided or unenforceable provision will be 
reformed to conform with applicable law. 
15.7 
Counterparts.  This Agreement may be executed in counterparts, and all counterparts will together 
comprise one instrument. 
16. 
Term.   
16.1 
Extensions.  The term of this Agreement commences upon the effective date and continues for a 
one (1) year initial period.  The City may, at its option and with the approval of the Consultant, extend 
the term of this Agreement an additional one (1) years, on an annual basis.  Consultant will be notified 
in writing by the City of its intent to extend the Agreement period at least thirty (30) calendar days 
prior to the expiration of the original or any extension period.  Price adjustments will only be reviewed 
during the Agreement extension period and will be a determining factor for any extension.  There 
are no automatic extensions or renewals of this Agreement.  
16.2 
Extension for Procurement Process.  Upon the expiration of the Term of this Agreement, including 
the initial term and any extensions, at the City’s sole discretion, this Agreement may be extended on 
a month-to-month basis for a maximum of six (6) months to allow for the City to complete its 
procurement process to select a vendor to provide the services/materials similar to those provided 
under this Agreement.  The City will notify the Contractor in writing of its intent to extend the 
Agreement at least thirty (30) calendar days prior to the expiration of the Term.  Any extension 
provided under this subsection will continue under the same terms and conditions as in effect 
immediately prior to the expiration of the then-current term. 
17. 
Dispute Resolution.  Any controversy or claim arising out of or relating to this contract, or the breach 
thereof, shall be settled by arbitration administered according to the American Arbitration Association’s 
Commercial Arbitration Rules, and judgment on the award rendered by the arbitrator may be entered in any 
court having jurisdiction thereof. 
18. 
Cooperative Use of Contract.  This agreement may be extended for use by other governmental agencies 
and political subdivisions of the State. Any such usage by other entities must be in accord with the ordinances, 
charter, rules and regulations of the respective entity and the approval of the Contractor and City.  For a list 
of SAVE members, click on the following link: 
 http://www.mesaaz.gov/business/purchasing/save  
19. 
Exhibits.  The following exhibits, with reference to the term in which they are first referenced, are 
incorporated by this reference. 
 
Exhibit A 
Scope of Work 
Exhibit B 
Compensation 
 
 
The parties enter into this Agreement effective as of the date shown above.

EXHIBIT A 
Professional Services Agreement 
SCOPE OF WORK 
 
See attached.

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 1 of 12 
April 16, 2024 
 
Exhibit A Summary 
City of Glendale Water Services Department 
Electrical Vulnerability and Arc Flash Assessment 
Project No. 222344 
 
April 2024 
 
Project Description 
 
Project Description 
 
The City of Glendale (City) has five primary treatment facilities (three water and two 
wastewater), seven finished water reservoirs, multiple pump stations, lift stations, and 
groundwater wells. All of these facilities have various types of electrical equipment and systems 
that require constant maintenance and equipment replacement. With electrical equipment 
procurement continuing to be problematic based on market demands and continuing supply 
chain fallout from the pandemic, the City’s goal for this project is to create a framework for and 
perform an electrical vulnerability assessment of key, critical City water and wastewater 
facilities. The assessment will identify recommended timing for procurement and replacement of 
electrical equipment or other improvements necessary to maintain redundancy and resiliency 
through the water distribution and wastewater collections systems. 
 
The City is also interested in performing engineered Power Study analyses (Short Circuit, 
Coordination and Arc Flash studies) at select facilities and remote sites for National Electric 
Code recommended compliance and safety of their personnel. 
 
General Project Scope  
This project will be executed over the course of multiple years and parts.  Part I (THIS 
PROJECT) will be performed by the Consultant and its specialty sub-consultants to complete 
the following scope of services: 
 
Phase 100 – Project Management (Part I) 
Phase 200 – Data Collection (Parts I & II) 
Phase 300 – Electrical Vulnerability Assessment (Parts I & II) 
Phase 400 – Power Study Program Assessment (Parts I & II) 
Phase 500 – Electrical Improvements Design (Part II) 
Phase 600 – Electrical Improvements Construction Administration (Part II) 
 
Part I scope of work is as described herein. Any additional tasks not detailed in the Scope of 
Services will be performed under an Owner’s Allowance or a contract amendment (Part II) at the 
direction/discretion of the City.

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 2 of 12 
April 16, 2024 
 
Exhibit A 
City of Glendale Water Services Department 
Electrical Vulnerability and Arc Flash Assessment 
Project No. 222344 
 
April 2024 
 
Scope for Consultant Services 
 
Project Description 
 
The City of Glendale (City) has five primary treatment facilities (three water and two 
wastewater), seven finished water reservoirs, multiple pump stations, lift stations, and 
groundwater wells. All of these facilities have various types of electrical equipment and systems 
that require constant maintenance and equipment replacement. With electrical equipment 
procurement continuing to be problematic based on market demands and continuing supply 
chain fallout from the pandemic, the City’s goal for this project is to perform an electrical 
vulnerability assessment of the City’s critical water and wastewater facilities. The assessment 
will identify recommended timing for procurement and replacement of electrical equipment or 
other improvements necessary to maintain redundancy and resiliency through the water 
distribution and wastewater collections systems. 
 
The City’s is also interested in performing engineered Power Study analyses (Short Circuit, 
Coordination and Arc Flash studies) at select facilities and remote sites for National Electric 
Code recommended compliance and safety of their personnel. 
 
Due to budget limitations through fiscal year (FY) 2024-2025, Part I initial data collection will be 
focused on creating a framework for consistent initial and future electrical equipment 
vulnerability assessments for existing electrical equipment to repair or replace critical 
components and determination if a power system study has been performed for all facilities. 
Additional evaluations and analysis may be added to this effort through owner allowance.  Part 
II of the project is anticipated to include remaining evaluations, design, construction cost 
estimating, construction administration services for the identified electrical and 
instrumentation/SCADA improvements as well as detailed power system study / arc flash 
assessments for prioritized locations. 
 
Due to budget limitations through fiscal year (FY) 2024-2025, Part I of Consultant Services for 
the Power Study Program will only include an Arc Flash Hazard Analysis update for the 
Arrowhead Ranch WRF. The Arc Flash update will be performed by the original study firm. 
Power system study efforts for other facilities, as needed, will be performed as future activities 
in Part II. In addition, this scope will include development of a Power Study specification to be 
used by the City of Glendale. 
 
Consultant Services  
Black & Veatch (Consultant) will provide consulting services for the items described in the 
Scope of Services. The Engineer will execute this project in two parts.  Part I is assumed to be 
completed from notice to proceed through the current FY 2023-2024 and through the end of FY

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 3 of 12 
April 16, 2024 
 
2024-2025; Part II is anticipated to start in FY 2025-2026 and extend as required by the City.  
Specialty sub-consultants are anticipated during Part I and may also be utilized during Part II of 
this project. The Consultant will complete the following scope of services: 
 
Phase 100 – Project Management 
Task 101 – Monitor Progress and Prepare Status Reports (Part I & II) 
 
Phase 200 – Data Collection 
Task 201 – Kickoff and Progress Meetings (Part I & II) 
Task 202 – Collect Facility & Electrical Equipment Data (Part I) 
Task 203 – Utility Coordination (Part II) 
Task 204 – Develop Site Investigation Plans (Parts I & II) 
Task 205 – Field Inspection Execution (Parts I & II) 
 
Phase 300 – Electrical Vulnerability Assessment  
Task 301 – Review Electrical System Data Collected and Report Development (Parts I & 
II) 
 
Phase 400 – Power Study Program Assessment 
Task 401 – Arrowhead Ranch WRF Arc Flash Hazard Analysis (Part I) 
Task 402 – Facility Power Study Analysis (Part II) 
 
Phase 500 – Electrical Improvements Design (Part II) 
 
Phase 600 – Electrical Improvements Construction Administration (Part II)

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 4 of 12 
April 16, 2024 
 
Scope of Services 
 
The Black & Veatch team (Consultant) will provide the consulting services described below for 
the City of Glendale for the project. 
 
Construction-related, non-professional services will be required during Part II to support this 
project. It is anticipated the City will hire a job order contractor (JOC) and/or construction 
manager-at-risk (CMAR) contractor to provide these services depending on the size of the 
identified improvement. JOC/CMAR support is not anticipated during Part I. This exhibit and 
scope may refer to future services and to the JOC under various tasks for which the JOC 
contractor will provide support. Consultant will provide direction to the JOC, if required, for the 
necessary support work for the assessments described herein. 
 
Phase 100 – Project Management 
 
Task 101 – Monitor Progress and Prepare Status Reports 
 
Provide monthly budget and progress updates to City staff. Prepare and submit monthly 
invoices to the City project manager. Status reports will be prepared and submitted along 
with each monthly invoice.  Status reports will identify what work has been performed during 
the billing period and the completion status of major tasks. 
 
Deliverables: Submit monthly invoices and status reports.  
 
Phase 200 – Data Collection 
 
Task 201 – Kickoff and Progress Meetings 
 
Coordinate with stakeholders to establish and document project goals early in the project, 
prior to inspection execution. Through progress meetings, provide monthly updates to City 
staff regarding project status. Two types of meetings in this task are listed and described 
below.  
(1) Project Kick-off Meeting. The Consultant will propose attendees, plan, coordinate, and 
summarize an in-person kickoff meeting to review project goals. Project aspects that will 
be discussed include specific facilities for which electrical vulnerability are anticipated to 
be targeted during the data collection planning and data collection processes, and 
overall schedule. 
(2) Monthly Progress Meetings. The Consultant will conduct monthly progress meetings for 
the duration of the project. The Consultant will distribute the meeting agenda prior to 
each meeting, prepare meeting materials and content, and summarize each meeting in 
meeting minutes. 
 
Deliverables: Meeting agenda and minutes with handouts for each meeting.  
 
Assumptions: One kickoff meeting with City staff. Several informal pre-meetings and other 
communications with city staff are also anticipated to plan the meeting effectively. Monthly 
progress meetings are planned. City staff will participate in the meetings. Progress meetings 
are assumed to last 1 hour and be virtual and/or in person.

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 5 of 12 
April 16, 2024 
 
Task 202 – Collect Facility & Electrical Equipment Data 
The following facilities have been identified to be associated with the electrical vulnerability 
assessment.  Only select facilities will be included in this project as noted below.  The entire 
list of facilities include: 
• 
Water Treatment Plants (WTP) / Water Reclamation Facilities (WRF) (including 
booster pump stations and reservoirs) 
o Water –  
 
Cholla WTP (by Others) 
 
Oasis (surface and groundwater) WTPs (this project) 
 
Pyramid Peak WTP (this project) 
o Wastewater – 
 
Arrowhead Ranch (ARWRF) (by Others) 
 
West Area (WAWRF) (by Others) 
• 
Groundwater Wells 
o Six current (6) City-owned wells 
 
COG43 (this project) 
 
AR22, Camelback Ranch, COG6, Manistee Ranch, and SR1 (Part II 
or by Others) 
• 
Booster Pump Stations (and reservoirs) 
o Pump Station 1 (Zone 4) (this project) 
o Pump Station 2 (Hillcrest Ranch) and Arrowhead Manor 1 (Part II or by 
Others) 
• 
Lift Stations (LS) 2 
o ARWRF service area – LS9 (this project), LS10 (Part II or by Others) 
o WAWRF service area – LS1, LS2, LS4, LS5, LS6 (Part II or by Others) 
o SROG service area – LS3 (Part II or by Others) 
 
For Part I of this Scope, Consultant will focus on five facilities that will be used as framework 
for completing the other sites.  The five facilities that are part of this scope will be as follows: 
• 
Pyramid Peak WTP 
• 
Oasis Water Campus WTP 
• 
PS1 - Zone 4 Booster Station and Reservoir 
• 
LS9 - 83rd Ave. and Bell Lift Station 
• 
COG Well 43 
 
For existing facilities included with this project, Consultant will make a data request that 
includes, but is not limited to: 
• 
Conformed to Construction Record drawings. 
• 
Previously completed electrical assessment, functional testing, inspection reports / 
bases of design at all facilities 
• 
Previously completed Power Study reports at all facilities, including Power Study 
model files (SKM/ETAP) (Part II activity) 
 
1 Pump Station #2 analysis will include Thunderbird Reservoir and future Pump Station 
2 Glendale Regional Public Safety Training Center (GRPSTC) and Glendale Ave West of 99th Avenue are City-owned 
but not maintained by Water Services

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 6 of 12 
April 16, 2024 
 
• 
2022 SCADA Master Plan (Part II activity) 
 
Deliverables: none. 
 
Assumptions: Only facilities listed above will be included in Part I of this Scope. Future 
facilities currently under design will not be included in the electrical vulnerability review but 
can be included as a supplemental service. Pressure Reducing Valves at the three (3) water 
distribution pressure zone boundaries are not required or included in the analysis. 
Task 203 – Utility Coordination (Part II) 
Scope to be included as a supplemental service or as part of Part II.  
 
Deliverables: none. 
 
Assumptions: Utility data collection with the electric Utility (SRP and APS) to obtain up to 
five (5) years of outage reports will be performed as part of a follow up vulnerability analysis 
performed as a supplemental service or in Part II. 
 
Task 204 – Develop Site Inspection Plans 
The Consultant will work with City staff to confirm constraints for each site in Part I and 
develop an inspection plan at each facility for collection of general electrical equipment data 
to be used for confirmation of record drawings, electrical vulnerability assessment and 
power study confirmations. Specific, detailed electrical equipment, device and installation 
information for Power Study efforts will be collected as a supplemental service or with Part II 
services.  
 
The Consultant will prepare a Draft Inspection Plan for each site in Part I for City review. 
Each Inspection Plan will include: 
• 
Project overview and introduction, site summary with relative information from Task 
202.  
• 
Each Inspection Plan will provide plans for scheduling and outlining the following: 
o Assessment methodologies and protocols 
o Roles and responsibilities 
o Site access and City support information 
o General proposed electrical equipment review sequencing. 
o Identification of Primary electrical equipment to review.  
o Site constraints and proposed schedule 
o Project personnel contact information 
 
Final Inspection Plan to incorporate the City’s comments on the Draft Inspection Plan 
document. 
 
Deliverables: Draft and Final Inspection Plans for each facility. 
 
Assumptions: Site interruptions (isolation of equipment) are not expected. Primary 
electrical equipment will be defined as the equipment that receives the utility service

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 7 of 12 
April 16, 2024 
 
connection and critical electrical distribution equipment at the facility. Ground system testing 
will be completed as a supplemental service or in Part II. 
 
Task 205 – Field Inspection Execution 
The Consultant will work with City operations staff to implement the Inspection Plans 
identified in Task 204 for each facility. 
 
Consultant will perform the following work for each site visit: 
• 
Verify the actual age (where possible), condition, size, and rating of the electrical 
distribution equipment. 
• 
Digitally photograph electrical equipment and devices 
• 
Document discrepancies between observed equipment and record drawing 
information. 
• 
Discuss equipment failure concerns with City staff and experiences for equipment 
and component replacement. 
 
Deliverables: None 
 
Assumptions: Critical equipment component information will only be collected from 
deenergized equipment, if required. De-energization of electrical equipment will be executed 
by City personal. It is expected external review of equipment will be performed.  
Phase 300 – Electrical Vulnerability Assessment 
 
Task 301 – Review Electrical System Data Collected and Report Development 
Consultant will compare the data collected in Phase 200 to facility record drawing 
information and identify discrepancies. Deviations will be noted in a report. 
Consultant will contact equipment manufacturer(s) to document the following conditions for 
the electrical distribution equipment reviewed: 
1. Equipment components that are obsolete and no longer supported. 
2. Equipment components that are near or at the end of their recommended service life 
3. Equipment components that have long lead times for replacement or repair 
Consultant will develop a report for each facility visited to document findings from site review 
and communications from electrical equipment manufacturers. General recommendations 
will be provided that describe potential solutions for equipment failure remedies. 
Consultant will conduct a meeting with City staff to discuss the initial findings and 
incorporate feedback into the report. 
Deliverables: Draft Report summarizing facility electrical equipment vulnerability 
assessments and recommendations at each site as described in the report. Final Report 
with the inclusion of agreed upon City comments.

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 8 of 12 
April 16, 2024 
 
Assumptions: City will participate in the vulnerability evaluations. Report recommendations 
are general in nature and will not include remedies on per component level. The study will 
focus on components with high likelihood of failure only. 
Phase 400 – Power Study Program Assessment 
 
Task 401 – Arrowhead Ranch WRF Arc Flash Hazard Analysis 
Consultant will coordinate with Sub-Consultant to perform a Power Study Analysis of the 
Arrowhead Ranch WRF Electrical Distribution System. This effort will utilize the existing 
electronic modeling file but may require confirmation of all parameters and settings to 
ensure a complete, accurate and verifiable product. Thoroughly reviewing existing 
conditions and information ensures the owner is provided with correct results for 
understanding the hazards associated with the electrical distribution system and the proper 
protection necessary when working with the electrical equipment. The following activities will 
be required by the Sub-Consultant. 
Site Visit, Data Gathering.  The Sub-Consultant will utilize all available electrical record 
drawings, existing arc flash studies, existing coordination studies, and existing electrical 
distribution equipment shop drawings obtained from the City. The information will be 
collected in electronic PDF or JPG format or copies of hard copies will be made. The level of 
effort is based on City assistance by providing direction on how to collect this data, what 
data is believed to be available, and provide Sub-Consultant access to City libraries to 
collect the data.  Sub-Consultant will coordinate with the electric utility provider to obtain 
short circuit current fault contribution values. 
Per the National Electric Code (NEC), a five-year review of electrical equipment is 
recommended. Using the NEC for guidance, the Sub-Consultant will perform a site 
investigation to visually observe the encompassing portions of electrical distribution system 
from normal power source or sources up to and including overcurrent protection devices in 
the service entrance metering section, main breaker in sub-distribution panels, main breaker 
in each panelboard and motor control center, medium voltage switches, transformers, 
switchgear, and switchboards. Also, existing cable or bus duct size and length. Sub-
Consultant will verify equipment ratings of the existing equipment mentioned above. Site 
investigation will not include three phase motors less than 10 horsepower, DC equipment, 
control panels, transient voltage surge suppression (TVSS), power factor correction 
capacitor (PFCC), soft starters, junction boxes, pull boxes, or terminal boxes. Where data is 
unable to be visually verified in the field best practice engineering assumption will be made. 
These assumptions will be identified in the Power Study Report. If Sub-Consultant is unable 
to access medium voltage equipment during the initial site visit, the city will provide the latest 
protective device relay phase and ground settings, current transformers (CTs), cable size, 
cable quantity, and cable type.

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 9 of 12 
April 16, 2024 
 
The City will provide qualified personnel familiar with the site to accompany the Sub-
Consultant and open all electrical equipment doors, locks, etc. as necessary during the site 
investigation. 
Short-Circuit Study.   The Sub-Consultant will perform an American National Standards 
Institute (ANSI) short-circuit study and an equipment evaluation of the devices and 
equipment modeled. The evaluation will identify if devices and equipment are sufficiently 
rated for the available short-circuit current. Equipment with no short-circuit rating label in the 
field will be included in the evaluation but noted that no rating was found during the site 
survey. Sub-Consultant will state conclusions and provide recommendations, if necessary, 
in the Power Study Report. 
Protective Device Coordination.    The Sub-Consultant will perform an ANSI protective 
device study of relays, fuses, circuit breakers, and all other protective devices and will 
submit a coordination and protective device settings report as specified herein.  The study 
will be performed in compliance with Institute of Electrical and Electronics Engineers (IEEE) 
Standard 242 and include the entire distribution system, including existing power distribution 
components starting with the smallest – 480 volt, 3 phase, 60 Hz – circuit protective device 
on the load end to the nearest protective device on the power company's line side. 
Protective device relay phase and ground overcurrent curves are anticipated to at least have 
a 0.2 second time margin from other devices and 0.4 seconds if possible.  Protective device 
settings will be selected / recommended to provide selective coordination to the maximum 
extent possible for device coordination while also balancing the goal to reduce the 
calculated incident energy to the greatest extent possible. Sub-Consultant will state 
conclusions and provide recommendations in the Power Study Report. 
Perform Arc Flash Analyses.   The Sub-Consultant will utilize the existing arc flash model as 
provided to perform an Arc Flash Hazard Analysis for each existing three phase electrical 
equipment including service entrance sections, sub-distribution panels, panelboards and 
motor control centers, medium voltage switches, transformers, switchgear, and 
switchboards, in accordance with IEEE Standard 1584 – the IEEE Guide for Performing Arc-
Flash Calculations and will submit findings in the Power Study Report. 
The analysis will include single-phase alternating current (AC) circuits as requested by the 
City.  The analysis will not include direct current (DC) distribution systems as these types of 
circuits and systems are not covered by IEEE 1584-2018 Arc Flash calculation guidelines or 
required by the City’s specifications. 
Protective-device settings will be selected to provide the necessary coordination required 
while also balancing the goal of minimizing the calculated incident energy to the greatest 
extent possible. 
The Arc Flash Hazard Analysis will calculate the arc flash protection boundary and the arc 
flash incident energy at defined working distances for the locations specified in the analysis. 
The analysis will be performed for up to three (3) electrical system modes of operation to

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 10 of 12 
April 16, 2024 
 
calculate the worst-case incident energy.  At a minimum, the system will be analyzed for the 
minimum and maximum available fault current and X/R ratios from the electric utility 
supplying service or for the separately derived power system. 
When performing incident energy calculations, the line side of the main breaker will be used 
as the point of analysis for a given piece of equipment per IEEE 1584 guidelines. Fault 
contributions from both the line and load sides shall be used when performing the 
calculation. If appropriate, a max clearing time of 2 seconds will be used for calculations. 
Under certain circumstances, assumptions are required if needed information is unavailable.  
Sub-Consultant will provide their due diligence to obtain the needed information. Any 
assumptions used in the analysis will be documented in the Power Study Report. 
Deliverables: The Sub-Consultant will develop and submit a draft Power Study Report 
documenting the analysis and protective device settings for review and acceptance by the 
City. The Sub-Consultant will meet with the City to gather comments on the draft Power 
Study Report and answer any questions.  Final selection of recommended protective device 
settings will be subject to review and acceptance by the City. 
The Sub-Consultant will incorporate comments as needed and submit a final Power Study 
Report. 
Sub-Consultant will remove existing stickers, create and apply new updated arc flash labels. 
Assumptions: City will provide electronic application model file of the existing arc flash 
study. City will provide support staff for data collection. 
Task 402 – Facility Power Study Analysis 
Scope to be included as a supplemental service or as part of Part II. 
Phase 500 – Electrical/Instrumentation/SCADA Improvements Design 
Scope to be included as a supplemental service or as part of Part II.  
 
Phase 600 – Electrical/Instrumentation/SCADA Improvements Construction 
Administration 
Scope to be included as a supplemental service or as part of Part II. 
Schedule 
See attached schedule in Exhibit A-1. 
 
Budget 
See attached level of effort in Exhibit B-1. 
 
Owner’s Allowance – Supplemental Services 
The purpose of this allowance is to provide as-needed assistance during the contract period. 
Activities or costs will be separately scoped and authorized by the City depending on City needs

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 11 of 12 
April 16, 2024 
 
over the course of the project. Examples of activities that might be requested from this 
allowance include, but are not limited to, the following: 
• 
Detailed internal review of deenergized existing electrical equipment. 
• 
Existing Ground system testing (3-point Fall of Potential or Clamp on Test) 
• 
Detailed electrical distribution vulnerability analysis involving likelihood of failure (LOF) 
and consequence of failure (COF) with service life estimations. 
• 
Review on going facility designs by others for resiliency and vulnerabilities that align with 
City goals. 
• 
Conductor insulation testing with summarized report of results. Tests to be performed 
per NETA testing standards. 
• 
Design of identified electrical, instrumentation/SCADA (PLC) improvements, including 
creations of engineering plans and/or in-kind electrical replacement specifications. 
• 
Construction administration associated with identified electrical, instrumentation/SCADA 
(PLC) improvements, including JOC bid / GMP coordination, factory acceptance test 
witness, submittal review, RFI response / clarification, field inspections, special 
inspections. 
• 
Power Study assessment, the findings of which would be submitted in the Power Study 
Report, including: 
o Data collection. 
o Creation / Update of System Model.  Review/update of existing model or creation 
of new model which begins downstream of the utility service and continue down 
through the City’s electrical distribution system up to and including fuses in 
service entrance metering section, main breaker in sub-distribution panels, main 
breaker in each panelboard and motor control center, medium voltage switches, 
transformers, switchgear, and switchboards. 
o Short-Circuit Study.   Perform an American National Standards Institute (ANSI) 
short-circuit study and an equipment evaluation of the devices and equipment 
modeled. The evaluation will identify if devices and equipment are sufficiently 
rated for the available short-circuit current. Equipment with no short-circuit rating 
label in the field will be included in the evaluation but noted that no rating was 
found during the site survey. 
o Protective Device Coordination.  Perform an ANSI protective device study of 
relays, fuses, circuit breakers, and all other protective devices and will submit a 
coordination and protective device settings report as specified herein.  The study 
will be performed in compliance with Institute of Electrical and Electronics 
Engineers (IEEE) Standard 242 and include the entire distribution system, 
including existing power distribution components starting with the smallest – 
480 volt, 3 phase, 60 Hz – circuit protective device on the load end to the nearest 
protective device on the power company's line side. Protective device relay 
phase and ground overcurrent curves are anticipated to at least have a 0.2 
second time margin from other devices and 0.4 seconds if possible.  Protective 
device settings will be selected / recommended to provide selective coordination

City of Glendale 
Electrical Vulnerability and Arc Flash Assessment 
Water Services Department 
City Project No. 222344 
Black & Veatch Corporation 
Page 12 of 12 
April 16, 2024 
 
to the maximum extent possible for device coordination while also balancing the 
goal to reduce the calculated incident energy to the greatest extent possible. 
o Arc Flash Analyses.   Perform additional Arc Flash Hazard Analyses as 
described herein.

ID
Task Name
Duration
Start
Finish
Predecessors
0
City of Glendale Electrical Vulnerability & Arc Flash Assessment  
Project No. 222344
404 days
Tue 7/18/23
Fri 1/31/25
1
NTP 
4 days
Tue 6/11/24
Fri 6/14/24
2
Phase 100 - PROJECT MANAGEMENT
165 days
Mon 6/17/24
Fri 1/31/25
3
101 - Monitor Progress & Prepare Status Reports (Part I & II)165 days
Mon 6/17/24
Fri 1/31/25
1
4
Phase 200 - PROGRAM DEVELOPMENT
133 days
Fri 6/14/24
Thu 12/19/24
1
5
201 - Kickoff & Progress Meetings
130 days
Thu 6/20/24
Thu 12/19/24
13
202 - Collect Facility & Electrical Equipment Data (Part I)
30 days
Mon 6/17/24
Fri 7/26/24
1
14
203 - Utility Coordination (Part II)
0 days
Fri 6/14/24
Fri 6/14/24
15
204 - Site Visits for Data Collection (Part I)
15 days
Mon 7/29/24
Fri 8/16/24
16
Develop Site Inspection Plans (Part I)
15 days
Mon 7/29/24
Fri 8/16/24
13
17
205 - Field Inspection Preparation and Execution (Part I)
41 days
Tue 7/23/24
Tue 9/17/24
18
Water Treatment Plants
21 days
Tue 8/20/24
Tue 9/17/24
19
Oasis WTP
1 day
Tue 8/20/24
Tue 8/20/24
16FS+1 day
20
Pyramid Peak WTP
1 day
Tue 9/17/24
Tue 9/17/24
23FS+2 days
21
Water Reclamation Facilities (by Others)
0 days
Tue 7/23/24
Tue 7/23/24
22
Groundwater Wells
1 day
Thu 9/12/24
Thu 9/12/24
23
COG43
1 day
Thu 9/12/24
Thu 9/12/24
27
24
Booster Stations
1 day
Tue 8/13/24
Tue 8/13/24
25
#1 - Zone 4
1 day
Tue 9/10/24
Tue 9/10/24
35FS+1 day
26
Lift Stations
1 day
Wed 9/11/24
Wed 9/11/24
27
LS9 - 83rd & Bell
1 day
Wed 9/11/24
Wed 9/11/24
25
28
Phase 300 - ELECTRICAL VULNERABILITY ASSESSMENT 
PRIORITIZATION (Part I)
401 days
Tue 7/18/23
Tue 1/28/25
29
301 - Review Electrical Vulnerability Data Collected (Part I)
95 days
Wed 9/18/24
Tue 1/28/25
30
Develop Draft Report
60 days
Wed 9/18/24
Tue 12/10/24
17
31
City Review
20 days
Wed 12/11/24
Tue 1/7/25
30
32
Final Report
15 days
Wed 1/8/25
Tue 1/28/25
31
33
302 - Electrical System Review Guidance Document 
Development (Part I)
45 days
Mon 7/29/24
Fri 9/27/24
34
Develop Draft Report
15 days
Mon 7/29/24
Fri 8/16/24
16FF
35
City Review
15 days
Mon 8/19/24
Fri 9/6/24
34
36
Final Report
15 days
Mon 9/9/24
Fri 9/27/24
35
37
303 - Develop Electrical Vulnerability Assessment Priortization 
Plan (Part I)
45 days
Tue 7/18/23
Mon 9/18/23
38
Phase 400 - POWER STUDY PROGRAM ASSESSMENT (Part 
I & II)
60 days
Fri 7/26/24
Fri 10/18/24
39
401 - Arrowhead Ranch WRF Arc Flash Hazard Initial Analysis 
(Part I)
60 days
Mon 7/29/24
Fri 10/18/24
13
40
402 - Power Study Analyses (Part II)
0 days
Fri 7/26/24
Fri 7/26/24
13
41
Phase 500 - ELECTRICAL IMPROVEMENTS DESIGN (Part II)
0 days
Fri 6/14/24
Fri 6/14/24
1
42
Phase 600 - ELECTRICAL IMPROVEMENTS CONSTRUCTION 
ADMINSTRATION (Part II)
0 days
Fri 6/14/24
Fri 6/14/24
1
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Qtr 2, 2024
Qtr 3, 2024
Qtr 4, 2024
Qtr 1, 2025
Task
Summary
Project Summary
Exhibit A-1
 City Project Number 222344 - City of Glendale Electrical Vulnerability & Arc Flash Assessment - Part I
Page 1
City of Glendale Electrical Vulnerability & Arc Flash Assessment  P
Date: Part I Baseline - 4/17/24

EXHIBIT B 
Professional Services Agreement 
COMPENSATION 
 
METHOD AND AMOUNT OF COMPENSATION 
Compensation shall be hourly rates plus allowable reimbursable expenses. 
NOT-TO-EXCEED AMOUNT 
The total amount of compensation paid to Consultant for Services as defined herein during the entire term of the 
Project must not exceed $209,828.  
DETAILED PROJECT COMPENSATION 
See attached.

100
Phase 100 – Project Management
56
              
$9,476
200
Pre-Award Services
327
            
$62,194
-
               
300
Phase 300 – Electrical Vulnerability Assessment
298
            
$54,858
400
Phase 400 – Power Study Program Assessment
32
              
$6,114
500
Phase 500 – Electrical Improvements Design (Part II)
-
            
$0
600
Phase 600 – Electrical Improvements Construction Administration (Part II)
-
            
$0
EXPENSES
$2,139
SUBCONSULTANTS
$25,047
BLACK & VEATCH SUBTOTAL w/ SUBS; w/o ALLOWANCES
713
             
$159,828
Owner's Allowance
Supplemental Services Allowance
$50,000
BLACK & VEATCH TOTAL w/ ALLOWANCES             713 
$209,828
Exhibit B-1 Compensation Summary
City of Glendale
City PN 222344 - Electrical Vulnerability and Arc Flash Assessment (PART I)
Phase
Description
 Total 
Hours
Total Fee
Black & Veatch Corporation
17 April 2024