PowerPoint Presentation (updated 09/06/2024)*
Extracted text (via pymupdf)
698 characters
BONSALL PARK NORTH MASTER PLAN September 10, 2024 Bonsall Park – North Timeline 2 October 24, 2023: Master Plan presented at Council Workshop Consensus received to move forward with Design 3 Bonsall Park – North Timeline 4 October 24, 2023: Probable Cost Estimate: $2,944,925 Available Budget: $2,451,418 Budget Gap: $493,507 Bonsall Park – North Design Development 5 Updated Cost Estimate: $3.8M Available Budget: $2.4M Budget Gap: $1.4M Factors in cost increase: Rebuild sport courts (pickleball, tennis, basketball) Increase in materials and labor costs Bonsall Park – Budget 6 Additional $1.4M in ARPA Funds identified to complete the project 7 Consensus to move forward? Questions?