PowerPoint Presentation (Added 1/24/2025)*
Extracted text (via pymupdf)
831 characters
Update #29 Downtown Campus Reinvestment Project City Council Workshop January 28, 2025 Presenter: Eddie Garcia 2 Site Activities 3 Exterior Sheathing 4 Exterior Wall Framing 5 Exterior Wall Framing 6 Exterior Wall Framing 7 Mechanical Shaft / Cores 8 Building Systems 9 Interior Framing 10 Main Electrical Room Slab 11 Roof Top Mechanical Curbs 12 Roof Top Screen Wall 13 Council Chambers 14 Amphitheater 15 Amphitheater 16 Milestones Scope Schedule Budget • City Hall Structural Steel Complete • Long Lead Items Procured (Mechanical Units, SES, Masonry) • Glenn Drive Utility Connections Complete Next Month • Commence Masonry Install • Drill Caissons for Amphitheater, Parking Stairs and Chamber Expansion • Rooftop Mechanical Screen Wall • Set Rooftop Mechanical Units • Storm Water Lift Station 17 Thank You